Docket: T-1339-13
Citation:
2015 FC 981
Ottawa, Ontario, August 18, 2015
PRESENT: The
Honourable Madam Justice Strickland
|
BETWEEN:
|
|
NUNATUKAVUT
COMMUNITY COUNCIL INC AND TODD RUSSELL, ON THEIR OWN BEHALVES AND ON BEHALF
OF THE MEMBERS OF NUNATUKAVUT COMMUNITY COUNCIL INC
|
|
Applicants
|
|
and
|
|
THE ATTORNEY
GENERAL OF CANADA AND NALCOR ENERGY
|
|
Respondents
|
JUDGMENT AND REASONS
Background. 3
Consultation Framework. 5
Phase 1 – Initial Engagement and
consultation on the draft JRP Agreement, the appointment of the JRP Panel
members and the development of EIS Guidelines. 6
Phase 2 – JRP Process leading to Hearings. 10
Phase 3 – Hearings and Preparation of the
JRP Report 12
Phase 4 – Consultation of the JRP Report 15
Phase 5 – Regulatory Permitting. 18
Issues. 28
Issue 1: What is the standard of review?. 29
The NCC’s Position. 29
Canada’s Position. 29
Nalcor’s Position. 30
Analysis. 31
Issue 2: What was the content of the duty to consult and
accommodate?. 38
The NCC’s Position. 38
Canada’s Position. 39
Nalcor’s Position. 41
Analysis. 42
(a) UNDRIP. 42
(b) Content of the Duty to
Consult 44
Issue 3: Did Canada satisfy its duty to consult and
accommodate?. 52
The NCC’s Position. 52
Canada’s Position. 54
Nalcor’s Position. 57
Analysis. 58
(a) Funding – Aboriginal
Traditional Knowledge and Land and Resource Use. 62
(b) Funding – Phase 5. 71
(c) Funding – Phase 5,
Legitimate Expectations. 82
(d) Funding – Phase 5, Review
of FHC and EEM Plans. 84
(e) Lack of Meaningful
Consultation and Bad Faith. 91
Issue 4: Was the decision to issue the Authorization
reasonable?. 97
The NCC’s Position. 97
Canada’s Position. 98
Nalcor’s Position. 99
Analysis. 101
(a) Recommendations 6.7 and
4.5. 101
(b) Reservoir Clearing –
Recommendation 4.5. 113
(c) Effectiveness of the FHC
Plan. 119
(d) Miscellaneous Issue. 127
(i) Impoundment 127
(ii) Treatment of Innu. 128
Conclusion. 129
[1]
This is an application for judicial review
brought pursuant to ss 18 and 18.1 of the Federal Courts Act, RSC, 1985,
c F-7, by which the Applicants challenge the decision of the Minister
(“Minister”) of the Department of Fisheries and Oceans (“DFO”) to issue
Authorization No. 13-01-005 (“Authorization”) to Nalcor Energy (“Nalcor”). The
Authorization was issued on July 9, 2013 and, pursuant to ss 32(2)(c) and
35(2)(b) of the Fisheries Act, RSC 1985, c F-14 (“Fisheries Act”),
permits impacts to fish and fish habitat arising from the construction of the
Muskrat Falls hydro-electric generating station proposed by Nalcor for the
lower Churchill River as part of the Lower Churchill Hydroelectric Generation
Project in Labrador.
[2]
The Applicants claim that they were not
adequately consulted or accommodated, that the Minister breached her duty of
procedural fairness; and, that her decision to issue the Authorization was
incorrect or unreasonable and an improper use or an abuse of her discretion.
[3]
The NunatuKavut Community Council Inc. describes
itself as the self-governing organization representing the interests of the
Inuit descendants (sometimes referred to as Inuit-Metis) of central and
southern Labrador. The NCC was formed in 2010 and at all relevant times Mr.
Todd Russell (“Russell”) was its President. The Applicants will be referred
to, collectively, as “NCC” in this decision.
[4]
In 1991, the NCC’s predecessor, the Labrador
Metis Association (later known as the Labrador Metis Nation), filed a land
claim document with the government of Canada (“Canada”). It filed additional
research in 1996 and did so again in 2010 in the form of a document entitled “Unveiling
NunatuKavut, Describing the Lands and People of South/Central Labrador,
document in Pursuit of Reclaiming a Homeland, NunatuKavut, 2010” (“Unveiling
NunatuKavut”). Although the NCC has asserted a land claim in the region it
describes as overlapping the project area, this has not currently been accepted
for negotiation by either Canada or the government of the Province of
Newfoundland and Labrador (“Province”).
[5]
Nalcor was incorporated pursuant to the Energy
Corporation Act, SNL 2007, c E-11.01, its predecessor being Newfoundland and Labrador Hydro. Nalcor was created to engage in and carry out activities
pertaining to the energy resources of the Province, which is its sole
shareholder.
[6]
Nalcor proposed to develop two hydro-electric
generation facilities on the lower Churchill River in central Labrador with a
combined capacity of 3,047 megawatts (“MW”). The project (“Project”) would
consist of dams located at Muskrat Falls (824 MW) and at Gull Island (2,250
MW), and would include reservoirs, transmission lines, access roads, temporary
bridges, construction camps, borrow pits and quarry sites, diversion facilities
and spoil areas as described in the Report of the Joint Review Panel Lower
Churchill Hydroelectric Generation Project, dated August 2011 (“JRP
Report”).
[7]
Given the nature of the NCC’s claim, it is
necessary to set out, in some detail, the factual background of this matter.
[8]
On November 30, 2006, Nalcor registered the
Project with the Newfoundland and Labrador Department of Environment and
Conservation (“NL DEC”) and the Canadian Environmental Agency (“Agency”) to
initiate the provincial and federal environmental assessment processes pursuant
to the Newfoundland and Labrador Environmental Protection Act, SNL 2002,
c E-14.2 (“NL EPA”) and the Canadian Environmental Assessment Act,
SC 1992, c 37 (“CEAA”).
[9]
In January 2007, Nalcor was advised by NL DEC
that, pursuant to the NL EPA, an Environmental Impact Study (“EIS”) was
required for the Project. In February 2007, the Minister advised the Minister
of the Environment that DFO had determined that an environmental assessment
(“EA”) was required because, to proceed, the Project would require approval of
Transport Canada (“TC”) pursuant to s 5(1) of the Navigable Waters
Protection Act, RSC 1985, c N 22 (“NWPA”) as it involved dam
construction, and, an authorization by DFO pursuant to s 35(2) of the Fisheries
Act, as it would likely result in the harmful alteration, disruption or
destruction of fish habitat, thereby triggering s 5(1)(d) of the CEAA.
The Minister requested that the Project be referred to a review panel in
accordance with s 25(a) of the CEAA.
[10]
TC and DFO each identified themselves as a “responsible authority” (“RA”) as defined in the CEAA,
that is, a federal authority that is required to ensure that an environmental
assessment is conducted (CEAA, ss 2(1) and 11).
[11]
Canada, in its written submissions, divides the
consultation process into five phases, based on the Federal Aboriginal Consultation
Framework for the Lower Churchill Hydroelectric Generation Project, dated
August 13, 2010 (“Consultation Framework”).
[12]
The Consultation Framework sets out
additional details as to how the federal government would rely on the joint
review panel (“JRP” or “Panel”) process, to the extent possible, to assist it
in fulfilling its legal duty to consult Aboriginal groups with respect to the
proposed Project. The JRP process was identified as the primary mechanism for
Aboriginal groups to learn about the Project and present their views, including
with respect to their traditional knowledge, the environmental effects of the
Project, effects on their land use, the nature and scope of their potential or
established treaty rights, the impact the Project would have on them, and
appropriate measures to mitigate. It identified the Agency as being
responsible for coordinating federal Aboriginal consultation during the EA. As
such, the Agency would ensure that the activities described in the Consultation
Framework were carried out and that the Aboriginal groups were kept well
informed. It divided the consultation process into five phases, which are
adopted below for convenience:
•
Phase 1 – Initial engagement and consultation on
the draft Joint Review Panel Agreement (“JRP Agreement”), the appointment of
the JRP panel members and the development of EIS Guidelines;
•
Phase 2 – JRP process leading to hearings;
•
Phase 3 – Hearings and preparation of the JRP
Report;
•
Phase 4 - Consultation on the JRP Report; and
•
Phase 5 - Regulatory permitting.
[13]
On October 19, 2006, DFO representatives met
with representatives of the NCC, and other Aboriginal groups, in Goose Bay to
discuss DFO’s role with respect to the EA for the Project and to ascertain
their early positions and perspectives. The NCC, amongst other things, stated
that it looked forward to formal consultation and noted its land claim. On
August 8, 2007, DFO and TC wrote to the NCC advising that the Project would
require an EA pursuant to the CEAA and that DFO and TC would be
arranging consultation with Aboriginal groups concerning how they may be
affected by the granting of authorizations and approvals permitting harmful
alteration, disruption or destruction of fish habitat.
[14]
In October 2007, the Agency and NL DEC jointly
issued draft Environmental Impact Statement Guidelines (“EIS Guidelines”) to
Aboriginal groups, including the NCC, for comment. The draft EIS Guidelines
were made available to the public for review on December 19, 2007. More than
fifty interested parties responded, including the NCC, which provided comments
on February 27, 2008.
[15]
The NCC’s Comments on the Lower Churchill EIS
Guidelines, addressed various issues including reservoir preparation (tree
stump removal to reduce methylmercury accumulation), cumulative effects,
downstream effects on the entire downstream environment, timing and adequacy of
fish habitat compensation programs, and, Aboriginal rights or title. It also
addressed the gathering and funding of this information, the consultation or
accommodation process, the use of Aboriginal Traditional Knowledge and a
comprehensive environmental agreement. The NCC noted its limited time and
funding in preparation of its comments.
[16]
The final EIS Guidelines were issued by Canada
and the Province in July 2008. The purpose of the EIS Guidelines was described
as a process for identifying the Project’s potential interactions with the
environment, predicting environmental effects, identifying mitigation measures
and evaluating the significance of residual environmental effects. The document
also stated that if the Project proceeded, the EA process would provide the
basis for setting out the requirements for monitoring and reporting to verify
compliance with the terms and conditions of approval and the accuracy and
effectiveness of predictions and mitigation measure (EIS Guidelines, s 2.1).
[17]
Further, Aboriginal and public participation,
Aboriginal traditional and community knowledge, the precautionary principle
(EIS Guidelines, ss 2.2, 2.3 and 2.5) and other matters were identified as
basic principles of an EA. Regarding consultation with Aboriginal Groups, the
EIS Guidelines stated:
4.8 Consultation with Aboriginal
Groups and Communities
The EIS shall demonstrate the Proponent’s
understanding of the interest, values, concerns, contemporary and historic
activities, Aboriginal traditional knowledge and important issues facing
Aboriginal groups, and indicate how these will be considered in planning and
carrying out the Project. The Aboriginal groups and communities to be
considered include, in Newfoundland and Labrador, the Innu Nation, the Labrador
Metis Nation and the Nunatsiavut Government and, in Quebec, the Innu
communities of Uashat Mak Mani-Utenam, Ekuanitshit, Nutaskuan, Unamen Shipu,
Pakua Shipi and Matimekush-Lake John.
[18]
On May 7, 2008, the Province, with the consent
of the Agency, provided the NCC with the draft JRP Agreement and its Terms of
Reference (“TOR”) in advance of making these publicly available for comment.
The NCC was invited to provide comments and advised that these would be given
full and fair consideration and that a written response would be provided prior
to the execution of the JRP Agreement and TOR. The NCC could also request a
meeting in an effort to resolve any related issues. The NCC did not provide
comments on the draft JRP Agreement and TOR.
[19]
The JRP Agreement and TOR were finalized and
released in January 2009. The JRP Agreement was subsequently amended to extend
the consultation period for Aboriginal groups and to provide for translation of
certain JRP documents into Aboriginal languages.
[20]
The JRP Agreement and TOR required the Panel to
conduct the EA in a manner that discharged the requirements of the CEAA
and the NL EPA. All JRP hearings were to be public and to provide for
the participation of Aboriginal groups, the public, governments, Nalcor and
other interested parties. Upon completion of the EA, the JRP was required to
prepare a report which would address the factors to be considered under s 16 of
the CEAA and s 65 of the NL EPA, set out the rationale, conclusions
and recommendation of the JRP relating to the EA, including any mitigation
measures and follow up programs, and include a summary of issues raised by the
Aboriginal groups, the public, governments and other interested parties (JRP
Agreement, ss 4.2, 4.3 and 6.3).
[21]
The TOR specifically addressed Aboriginal rights
as follows:
Aboriginal Rights Considerations
The Panel will have the mandate to invite
information from Aboriginal persons or groups related to the nature and scope
of potential or established Aboriginal rights or title in the area of the
Project, as well as information on the potential adverse impacts or potential
infringement that the Project/Undertaking will have on asserted or established
Aboriginal rights or title.
The Panel shall include in its Report:
1. information provided by Aboriginal persons or groups related
to traditional uses and strength of claim as it relates to the potential
environmental effects of the project on recognized and asserted Aboriginal
rights and title.
2. any concerns raised by Aboriginal persons or groups related
to potential impacts on asserted or established Aboriginal rights or title.
The Panel will not have a mandate to make
any determinations or interpretation of:
• the validity or the strength of any Aboriginal group’s
claim to aboriginal rights and title or treaty rights;
• the scope or nature of the Crown’s duty to consult
Aboriginal persons or groups;
• whether Canada or Newfoundland and Labrador has met its
respective duty to consult and accommodate in respect of potential rights
recognized and affirmed by s. 35 of the Constitution Act, 1982; and
• the scope, nature or meaning of the Labrador Inuit Land
Claims Agreement.
[22]
On February 17, 2009, Nalcor submitted its EIS
to the JRP. The EIS comprised over 10,000 pages, including over sixty
supporting component studies. On March 9, 2009, the JRP initiated a 75 day
public consultation process on the EIS.
[23]
In April 2009, the Science Branch of DFO
reviewed sections of the EIS and component studies related to the aquatic
environment for the purpose of offering advice with respect to the scientific
reliability of the EIS, including an opinion on the accuracy of Nalcor’s
predictions regarding environmental impacts. The NCC was invited to attend the
review, conducted by way of a Regional Advisory Process, but did not
participate. In June 2009, the Science Advisory report (entitled Science
Evaluation of the Environmental Impact Statement for the Lower Churchill
Hydroelectric Project to identify Deficiencies with respect to Fish and Fish
Habitat) identified deficiencies in the EIS, including the exclusion of the
environment below Muskrat Falls, including Lake Melville, from the study area;
a lack of detail in the monitoring programs; and, that additional effort was
required to document local knowledge of fish habitat, especially in the area
below Muskrat Falls.
[24]
The JRP invited the public, Aboriginal groups
and governments to review the EIS received from Nalcor and to provide comments
as to the adequacy of the additional information, as measured against the EIS
Guidelines, and the technical merit of the information presented. Based on the
comments received and the JRP’s own questions, between May 1, 2009 and January
7, 2011, the JRP issued one hundred and sixty-six information requests (“IR”)
to Nalcor regarding the EIS. The IRs required Nalcor to provide additional
information or analysis in respect of the questions raised. In response,
Nalcor submitted approximately 5000 pages of additional documentation by way of
information request replies (“IRR”).
[25]
On January 14, 2011, the JRP announced that it
had sufficient information to proceed to public hearings.
[26]
The hearings commenced on March 3, 2011.
Between then and April 15, 2011, the JRP held thirty days of hearings in nine
locations in Newfoundland and Labrador and in Quebec. DFO participated in the
various sessions of the hearings.
[27]
On March 4, 2011, the NCC advised the JRP that
it would be seeking an injunction to enjoin the public hearings based on its
belief that there were unanswered questions that must be resolved before the
JRP Panel hearings could continue.
[28]
By letter of March 10, 2011, the JRP expressed
its disappointment that the NCC would not participate in the hearings but
stated, if an injunction were not granted, that there would be time and
opportunity in the remaining portion of the hearings for the JRP to hear from
the NCC regarding its asserted claim to Aboriginal rights and title and how the
Project may impact these. This information could supplement the information
already provided by the NCC, including the “Unveiling NunatuKavut”
report.
[29]
The injunction was brought in the Supreme Court
of Newfoundland and Labrador. In addressing the NCC’s claims “that despite the frequent contacts it has had with the two
levels of government, with Nalcor, with the CEA and with the JRP, it has never
been meaningfully consulted or accommodated about the Lower Churchill Project”,
the Court stated that it did “not accept that
Nunatukavut was not consulted appropriately” (NunatuKavut Community
Council Inc v Newfoundland and Labrador Hydro-Electric Corporation (Nalcor
Energy), 2011 NLTD(G) 44 at paras 21 and 41 [NCC I]). The Court
further found that the NCC would not suffer irreparable harm if the hearings
proceeded, and that the NCC could face harm if it did not engage in the
remaining phases of the EA process (NCC I at paras 50 and 52-53). The
injunction was denied on March 24, 2011.
[30]
In October 2012, the NCC conducted a protest
which blocked access to a preliminary work site for the Project. The NCC
asserted that Nalcor and the Province had failed to comply with their
obligations to consult with it in respect of the Project. An interim
injunction sought by Nalcor was initially granted, followed, in November 2012,
by a permanent injunction (Nalcor Energy v Nuntukavut Community Council Inc,
2012 NLTD(G) 175). However, this was subsequently vacated on appeal (NunatuKavut
Community Council Inc v Nalcor Energy, 2014 NLCA 46).
[31]
On April 5, 2011, the NCC made a presentation to
the JRP. This addressed consultation with Nalcor, a lack of funding to gather
and present Aboriginal Traditional Knowledge, land use data gaps and issues
with IR# JRP-151 (Aboriginal Consultation and Traditional Land and Resource
Use), concerns about the status of Nalcor’s work on downstream effects,
cumulative effects, and methylmercury contamination. Two PowerPoint
presentations were made, one including reference to “Unveiling NunatuKavut”.
On April 13, 2011, the NCC submitted a paper entitled “A brief paper to the
Joint Review Panel on the Lower Churchill Hydroelectric Generation Project”
which also addressed its concerns.
[32]
The JRP Report was issued on August 25, 2011.
It is a comprehensive, 392 page document (including the appendices) which
describes the process leading to its issuance, and, for each topic addressed in
the report, sets out Nalcor’s views, the views of the participants and the
JRP’s conclusions and recommendation(s) concerning that topic. In total, the
JRP made 83 recommendations, should the Project be approved. Of
particular note to this matter is Chapter 6, Aquatic Environment. There,
the JRP identified the key issues that emerged from the review process which
included: the effects of reservoir preparation; the fate of methylmercury in
reservoirs; downstream effects below Muskrat Falls and the likelihood that
Project effects, including the bioaccumulation of mercury, would be seen in
Goose Bay or Lake Melville; and, follow-up monitoring.
[33]
In the concluding comments of Chapter 17, and as
summarized in the executive summary, the JRP reported that it had determined
that the Project would be likely to have significant adverse effects on: fish
habitat and fish assemblage in reservoirs; terrestrial, wetland and riparian
habitat; the Red Wine Mountain caribou herd; fishing and seal hunting in Lake
Melville, should consumption advisories be required; and, culture and
heritage. It also identified a range of potential benefits including economic,
social and cultural benefits to future generations, and, identified crucial
additional information required before the Project should proceed in the areas
of long-term financial return, energy alternatives to serve island needs, and, to
reduce the uncertainty about downstream effects. The JRP noted that it did not
make the final decision about whether the Project should proceed but that
government decision-makers would have to weigh all effects, risks and uncertainties
in order to decide whether the Project was justified in the circumstances and
should proceed in light of the significant adverse environmental effects
identified by the JRP.
[34]
Phase 4 concerned consultation on the JRP
Report.
[35]
On September 16, 2011, the Agency met with the
NCC to discuss the JRP Report and Aboriginal consultation. On November 9, 2011,
the NCC submitted its comments on the JRP Report. Among these comments, the NCC
submitted that the JRP had discriminated against NCC communities, that it did
not exercise its TOR as it had failed to insist that Nalcor or government(s)
provide funding for studies so that the proper information from the NCC was
forthcoming and that proper work be carried out with respect to Aboriginal
Traditional Knowledge. Further, that more consultation was needed to address
land and resource work in the footprint area, that Nalcor had not been candid
with the NCC throughout the process, and that the JRP had failed to address the
cumulative effects of the Project.
[36]
On January 24, 2012, the Agency prepared an
internal report entitled Lower Churchill Hydro Electric Generation Project:
Report on Aboriginal Consultation Associated with the Environmental Assessment
(“Aboriginal Consultation Report”) which states that it describes how
the federal government consulted with Aboriginal groups in the context of the
EA, in particular, how it had relied on the JRP process, to the extent
possible, to assist in discharging its legal duty to consult. The report
states that it describes the positions of the Aboriginal groups with respect to
how the potential adverse environmental effects of the proposed Project may
impact their potential or established Aboriginal or treaty rights, which was derived
from presentations the Aboriginal groups made to the JRP and from comments made
by the groups directly to federal government department officials.
[37]
By Order-in-Council dated March 12, 2012, the
Governor-in-Council, on the recommendation of the Minister, pursuant to s
37(1.1)(a) of the CEAA, approved Canada’s response to the JRP Report.
[38]
The “Government of Canada Response to the
Report of the Joint Federal-Provincial Review Panel for Nalcor’s Lower
Churchill Generation Project in Newfoundland and Labrador” (“Canada’s
Response”) describes the Project, the federal regulatory approvals and
involvement, the EA process, the JRP Report and Canada’s conclusions. Canada’s
Response states that DFO and TC, as the RAs under the CEAA, as well as
other interested parties, such as Natural Resources Canada (“NRC”), reviewed
the JRP Report, a subsequent independent supply report commissioned by Nalcor,
an economic analysis of the Project that was conducted by Canada, and comments
submitted by Aboriginal groups and other stakeholders during and following the
JRP process.
[39]
In considering whether the significant adverse
environmental effects of the Project could be justified in the circumstances,
Canada’s Response stated that it accounted for the potential adverse effects of
the Project and the commitments that had been made by the federal government
related to the recommendations provided in the JRP Report, and those made by
Nalcor in its EIS and during the panel hearings. Canada would require certain
mitigation measures, environmental effects monitoring and adaptive management
be undertaken by Nalcor, as well as additional studies on downstream effects.
This would be done through inclusion of requirements in federal authorizations
and approvals. Canada’s Response stated that ensuring that those commitments
were carried out would minimize the negative effects of the Project and reduce
the risks associated with the uncertainty about the success of mitigation
measures.
[40]
Further, that the potential social, economic and
environmental benefits for the Province, communities and Aboriginal groups, as
well as benefits beyond the Province that are associated with the Project, were
also considered, as was an economic analysis of the Project by Canada.
[41]
Canada determined that the expected significant
energy, economic, socio-economic and environmental benefits outweighed the “significant adverse environmental effects” of the
Project that were identified in the JRP Report:
Therefore the Government of Canada concludes
that the significant adverse environmental effects of the Lower Churchill
Hydroelectric Generation Project are justified by the benefits of the Lower
Churchill Hydroelectric Generation Project.
(Canada’s Response, p 8)
[42]
On March 16, 2012, in conformity with the
Governor-in-Council’s approval of Canada’s Response, TC and DFO issued their
course of action decision pursuant to ss 37(1) and 37(1.1) of the CEAA
(“Course of Action Decision”). The Course of Action Decision noted that a
follow-up program to verify the accuracy of the EA and/or determine the
effectiveness of any mitigation measures was required for the Project, and that
the estimated dates of the follow-up program were October 1, 2012 to October 1,
2037.
[43]
Phase 5 of the consultation process concerned
regulatory permitting leading to the issuance of the Authorization.
[44]
By letter of April 23, 2012, the Agency advised
the NCC that the consultation process was moving into Phase 5, regulatory
permitting, as set out in the Consultation Framework. Accordingly,
responsibility for leading and coordinating the consultation for the federal
government was being transferred from the Agency to DFO. DFO sent a similar
letter on July 9, 2012.
[45]
Around this time, the NCC, Grand Riverkeeper,
Labrador Inc. and the Sierra Club of Canada, sought judicial review of the JRP
Report and Canada’s Response and “to prohibit the
various federal Respondents from issuing permits, authorizations or financial
assistance relating to the Project, and to quash the Governor in Council’s
Response to the Report” (Grand Riverkeeper, Labrador Inc v Canada
(Attorney General), 2012 FC 1520 at para 1 [Grand Riverkeeper]).
Justice Near (then of this Court) found that Canada’s Response was not properly
before the Court, as it had been released after the notice of application had
been filed. As such, the judicial review in Grand Riverkeeper was
limited to the JRP Report (Grand Riverkeeper at para 17). Ultimately,
Justice Near dismissed the application for judicial review on December 20, 2012,
concluding that the JRP reasonably considered the need for and alternatives to
the Project (Grand Riverkeeper at para 54), reasonably recommended that
the Province and an independent study panel augment the information gathered (Grand
Riverkeeper at paras 59 and 62), and turned its mind to questions regarding
the cumulative effects of the Project (Grand Riverkeeper at paras 59 and
64).
[46]
By letter of May 4, 2012, the NCC wrote to the
Minister stating that because of the ongoing judicial review, any participation
by it in Phase 5 would be under protest. Further, that it had not been
provided with sufficient information regarding the regulatory permits that were
to be granted and, therefore, it could not identify which of its Aboriginal
rights and title may be impacted by the permitting process. The NCC also
stated that it had a number of outstanding concerns not dealt with during the
EA process and that it had not been provided with information regarding the
process that DFO intended to follow in fulfilling its constitutional duty to
consult. The NCC described what it considered that duty to entail, which
included funding for participation in the consultation process, for research on
cultural and environmental impacts of the Project and for relevant scientific,
technical and, if necessary, legal advice.
[47]
On May 9, 2012, at the NCC’s request, its
representatives met with DFO representatives to discuss the regulatory permits.
[48]
On May 12, 2012, the NCC wrote to DFO describing
the May 9, 2012 meeting. The NCC stated that DFO had advised that permitting
would be by way of authorizations under ss 32 and 35 of the Fisheries Act;
that a Letter of Advice had been issued on a portion of the Project; and, that
DFO could provide the NCC with no funding for the Phase 5 consultations. The
NCC stated that it had previously been advised that a Consultation Framework
was being developed; that it had no resources to review or respond to
permitting and that DFO had advised that it could not provide such resources;
that the NCC wanted to be consulted in a meaningful way regarding mitigation,
compensation and accommodation; that the permitting process had begun without
consultation; that the NCC should be provided with a copy of the Letter of
Advice, which should be rescinded; and, that all further authorizations should
be held in abeyance until an adequate consultation process was effected. The
NCC formally requested a copy of the Letter of Advice on May 28, 2012.
[49]
On June 1, 2012, DFO provided copies of two
Letters of Advice issued to Nalcor concerning stream fording and explained that
these were not regulatory permits. Further, that prior to the issuance of a Fisheries
Act authorization, DFO would consult with Aboriginal groups, including the
NCC, and that an Aboriginal consultation protocol governing that process was
under development and would be provided to the NCC for comment.
[50]
By letter of June 4, 2012, the NCC stated that
the EA did not account for Aboriginal Traditional Knowledge of the NCC and that
its members might hold very site-specific knowledge that would inform better
decisions as to the placement of the culverts and stream fording which were addressed
by the Letters of Advice. Further, that the NCC had sought resources to
present that knowledge, but had been refused by Nalcor.
[51]
DFO responded on June 14, 2012, noting that
Letters of Advice are not regulatory instruments, encouraging the NCC to share
information they may have on any site-specific stream and review crossings in
the area at issue, and, stating that DFO would be formally consulting with the
NCC, and other Aboriginal groups, with respect to Fisheries Act
authorizations for the Project.
[52]
On July 9, 2012, DFO wrote to the NCC stating
that, pursuant to the Consultation Framework, the federal government was
entering the regulatory permitting phase (Phase 5) for the Project and wished
to continue consultations respecting specific regulatory decisions, approvals
or actions that may have potential adverse impacts on their asserted Aboriginal
rights or title. DFO advised that the federal government anticipated issuing
three kinds of approvals: the s 35(2) and s 32(2) Fisheries Act
authorizations from DFO and, the s 5 approval under the NWPA from TC.
DFO proposed to conduct consultations during the regulatory phase in accordance
with an attached proposed Protocol for Regulatory Phase Aboriginal
Consultation Lower Churchill Generation Project (“Regulatory Phase
Protocol”) and sought comments on that process within 14 days.
[53]
The NCC responded by way of email of August 8,
2012. This requested that a protocol be put in place to share the NCC’s
Aboriginal Traditional Knowledge, that more emphasis be placed on Aboriginal
Traditional Knowledge and that a clear definition of the Project footprint area
be provided. By letter of February 21, 2013 DFO stated that comments not
directly related to the draft protocol would be addressed by follow-up letter
and that the comments on the protocol had been fully and fairly considered and
were reflected in the final version of the protocol, which was attached.
[54]
The final Regulatory Phase Protocol
stated that in Step 1, upon receipt of the Fish Habitat Compensation Plan (“FHC
Plan”) or the Environmental Effects Monitoring Program (“EEM Program” or “EEM
Plan”), both conditions of the Fisheries Act authorization, a condensed
Fish Habitat Compensation Report or condensed Environmental Effects Monitoring
Program Report with a link to the full plan/program would be provided to the
NCC. The NCC would then have 45 days for review and comment.
[55]
In Step 2, within 10 days of receiving the
application, the NCC could request a meeting with the RA, to be held within the
45 day period, to discuss the application/document. If no comments were
received, then the RA would notify the NCC that the 45 day timeframe had ended
and that the approval or authorization would be considered and, if appropriate,
granted. If comments were received, then the RA would give them full and fair
consideration and provide a written response. In Step 4, the RA would incorporate
changes as appropriate and, in Step 5, within 5 days of issuance to Nalcor,
copies of the Fisheries Act Authorization and the NWPA Approval
would be provided to the NCC.
[56]
Nalcor provided the FHC Plan to the NCC on
December 21, 2012, and invited it to a public information session, which would
provide a technical briefing on the FHC and EEM Plans, to be held in Goose Bay
on January 16, 2013. Representatives of the NCC attended that session. The
letter also extended an offer to meet with representatives of the NCC to brief
them on the FHC and the EEM Plans. The NCC did not respond to Nalcor’s offer
of a meeting.
[57]
A February 5, 2013 DFO memorandum for the DFO
Regional Director General addressed the status of Aboriginal consultations for
Phase 5. Amongst other things, it noted that comments received on the proposed
protocol indicated that some Aboriginal groups still had concerns about the EA
that they felt had not been addressed. The majority of these related to
impacts on Aboriginal rights and title, caribou, cumulative impacts, and the
lack of land and resource use studies. “Close the loop” letters to the groups
were being drafted addressing the outstanding issues prior to finalizing the Regulatory
Phase Protocol.
[58]
A February 21, 2013 memorandum for the Deputy
Minister for DFO again summarized the status of Aboriginal consultations for
Phase 5. It anticipated the DFO would complete the consultations by mid-May
and should be in a position to issue a Fisheries Act authorization by
June 2013.
[59]
On February 28, 2013, DFO wrote to the NCC
advising that it was preparing to issue a Fisheries Act authorization
and provided the draft FHC and EEM Plans, as received from Nalcor, and sought
comments on the two plans within 45 days as per the Regulatory Phase Protocol.
The letter also noted that the NCC could, within the first 10 days of receiving
the plans, request a meeting with DFO to discuss the documents. DFO stated
that it would give full and fair consideration to the comments and respond in
writing. A follow-up reminder letter was sent to the NCC on April 5, 2013.
[60]
The NCC responded on April 15, 2013. Its letter
did not provide comments on the FHC Plan or the EEM Plan. It stated that there
had been an absence of procedural engagement with the NCC in preparing the
plans; that the Regulatory Phase Protocol was unacceptable; that a
meeting was sought with the official most directly involved in advising the
Minister, or the Minister’s delegate, regarding the Authorization to discuss
non-compliance by Nalcor and the inadequacies of consultation and accommodation
to date; that the 45 day review period of the Regulatory Phase Protocol
was not acceptable; that the NCC’s concerns on impoundment remained
unaddressed; that no resources had been provided for the Phase 5 consultation
and accommodation efforts; that there had been no direct consultation with the NCC
in relation to the proposed authorizations; and, that a 60 day extension was
required. The letter attached a table listing JRP Recommendations 6.6, 6.7, 6.9,
7.1, 7.2, 7.3, 8.4 and 9.3, the governments’ responses, and the steps taken by
Nalcor and the regulator which the NCC deemed deficient.
[61]
On May 31, 2013, DFO responded to the NCC’s
letter of April 15, 2013 addressing twelve issues. These included that Nalcor
had advised DFO that the NCC was provided with an opportunity to meet with
Nalcor to discuss the FHC Plan, but that such a meeting did not take place.
DFO stated that this fulfilled Canada’s commitment in this regard. As to the
advisory letters, because DFO had determined that the proposed activities would
not cause harmful impacts and did not require the issuance of a Fisheries
Act authorization, it was not required to consult with the NCC. As to
Recommendation 6.7, Canada’s Response stated that Nalcor would be required to
collect additional baseline data on methylmercury accumulation in fish and on
fish habitat downstream of Muskrat Falls in advance of reservoir impoundment.
The EEM Plan provided for review of the detailed information that Nalcor would
collect. Finalization and implementation of the EEM Plan as a condition of the
Authorization would fulfil commitments of Canada in this regard. As to
Recommendation 6.9, DFO referred to Canada’s Response agreeing with the intent
of the Recommendation and stated that Nalcor had carried out public information
sessions in Goose Bay on January 16, 2013 and had advised DFO that the NCC had
been provided with an opportunity to meet with Nalcor to discuss the FHC Plan
and EEM Plan, which meeting had not taken place. Canada had accordingly
fulfilled its commitments in this regard.
[62]
By email of May 31, 2013, DFO provided Nalcor
with a draft of the Authorization and advised that it had completed its
Aboriginal consultation related to the conditions of the Authorization,
specifically the FHC and EEM Plans, and would be sending a letter outlining
minor changes/clarifications needed prior to plan approval. On June 7, 2013,
DFO sent Nalcor an email advising that there would be a requirement for some
additions to the plans, in particular to EEM Plan, based on DFO’s consultation.
[63]
On June 17, 2013, AMEC Environmental and
Infrastructure (“AMEC”), as consultants for and on behalf of Nalcor, provided
DFO with a revised EEM Plan. The accompanying email stated that the method
sections of the 2011 and 2012 baseline studies had been incorporated, where
applicable, into the EEM document. Sample sizes had also been added,
particularly pertaining to mercury. An addendum on sampling locations within Lake Melville was also added.
[64]
Following further discussions, the EEM Plan was
revised by AMEC and resubmitted to DFO on June 21, 2013. DFO responded on June
25th stating that the additional details added went a long way to clarifying
specifics of the EEM Plan to address concerns raised during consultations. Two
further clarifications were requested along with some edits.
[65]
Nalcor submitted its revised, final EEM and FHC
Plans on June 26, 2013 and DFO advised Nalcor the next day that these were
acceptable to DFO and would be attached as conditions to the Authorization.
[66]
On June 28, 2013, DFO responded to the NCC’s
submissions of November 9, 2011 and email of August 8, 2012 addressing the
concerns raised therein on a point by point basis. These included the NCC’s
concern that more emphasis should be put on Aboriginal Traditional Knowledge
and that a protocol should be put in place to share such knowledge. In
response, DFO noted that the Regulatory Phase Protocol had been
developed in collaboration with Aboriginal groups and provided the opportunity
for meetings at which Aboriginal groups could share Aboriginal Traditional
Knowledge for review and consideration in the issuance of permits or
approvals. DFO had offered such meetings to the NCC on February 28, 2013 for
the authorizations being prepared for Muskrat Falls. Further, prior to
submitting a FHC Plan and EEM Plan, Nalcor may offer to meet with Aboriginal
groups, at which time such knowledge could be shared for incorporation into the
plans.
[67]
As to the concern that a clear definition of the
Project and the footprint area had not been provided, DFO stated that this was
done during the EA. As to the NCC’s concern that the federal and provincial
governments had a duty to engage separately with the NCC before the JRP process
which had not been done, nor had there been adequate consultation or
accommodation of the NCC’s interests, DFO stated that the JRP provided various
opportunities for participation during the JRP process. The public hearings
provided Aboriginal persons and groups with the opportunity to be heard and for
the JRP to gather such information. Further, DFO and TC had been and would
continue to consult with the NCC in accordance with the Regulatory Phase
Protocol, which would give the NCC the opportunity to provide input and
have discussions with those departments on related conditions.
[68]
On July 9, 2013, the Authorization for the
Project was issued to Nalcor pursuant to ss 32(2)(c) and 35(2)(b) of the Fisheries
Act, for the harmful alteration disruption or destruction of fish habitat,
and the killing of fish. The Authorization was provided to the NCC on the same
date. It is this Authorization that the NCC has sought to have judicially
reviewed.
[69]
The Authorization is ten pages in length and
lists six detailed Conditions of Authorization. These include Condition 1.1,
which states that if, in DFO’s opinion, the authorized impacts to fish and fish
habitat are greater than previously assessed, then DFO may suspend any works,
undertakings, activities and/or operations associated with the proposed
development to avoid or mitigate adverse impacts to fish and fish habitat. DFO
can also direct Nalcor to carry out any modifications, works or activities
necessary to avoid or mitigate further such adverse impacts. If DFO is of the
view that greater impacts may occur than were contemplated by the parties, then
it may also modify or rescind the Authorization.
[70]
Nalcor is also required to undertake the Project
in accordance with the EIS, the Project Wide Environmental Protection Plan and
the FHC Plan (1.4), and, to implement mitigation techniques set out in such
plans (2.1). It also requires that Nalcor monitor mitigation measures (3.0)
and lists conditions concerning compensation for the authorized impacts to fish
and fish habitat (4) and relating to monitoring and reporting of compensation
habitat. Condition 6 requires Nalcor to undertake an EEM Program, as outlined
in the EEM Plan, to monitor and verify the predicted impacts of the Project
from a fish and fish habitat perspective, including Project-related downstream
effects, methylmercury bioaccumulations in fish, and fish entrainment at the Muskrat Falls facility, in accordance with Conditions 6.1-6.5. This includes annual
monitoring of methylmercury bioaccumulation to determine levels in resident
fish species, including seals, both within the reservoir and downstream as per
the established monitoring schedule, to record and report peak levels and
subsequent decline to background levels (6.3).
[71]
In my view the issues can be framed as follows:
1. What is the standard of review?
2. What is the content of the duty to consult and accommodate?
3. Did Canada satisfy its duty to consult and accommodate?
4. Was the decision to issue the Authorization reasonable?
[72]
As to consultation and accommodation, the NCC
argues that both the standards of correctness and reasonableness may apply.
The NCC relies on Ahousaht First Nation v Canada (Fisheries and Oceans),
2012 FCA 212 at paras 33-34, referring to Haida Nation v British Columbia
(Minister of Forests), 2004 SCC 73 at paras 61-62 [Haida], for the
proposition that the determination of the existence and extent of the duty to
consult or accommodate is a question of law and reviewable on a standard of
correctness. Once the extent of the duty to consult or accommodate has been
satisfactorily determined by the Crown, its decision will only be set aside if
the ensuing process of consultation and accommodation is unreasonable.
[73]
For the grounds of review relating to the abuse
of the Minister’s discretion, the NCC submits that the standard of review is
reasonableness (Baker v Canada (Minister of Citizenship and Immigration),
[1999] 2 S.C.R. 817 at para 62 [Baker]).
Canada’s
Position
[74]
Canada agrees with the Applicant that the
standard of review for the content of the duty to consult is correctness (Conseil
des innus de Ekuanitshit c Canada (Procureur général), 2013 FC 418 at para
97 [Ekuanitshit FC]; Beckman v Little Salmon/Carmacks First Nation,
2010 SCC 53 at para 48 [Little Salmon]). The question of whether
Canada’s efforts satisfied its duty to consult is reviewable on the
reasonableness standard (Ekuanitshit FC at para 97; Katlodeeche
First Nation v Canada (Attorney General), 2013 FC 458 at paras 126-127 [Katlodeeche];
Cold Lake First Nations v Alberta (Tourism, Parks and Recreation), 2013
ABCA 443 at paras 37-38 [Cold Lake]).
[75]
As to the Minister’s decision to issue the
Authorization, Canada submits that the Court is to determine whether the
Authorization rests on a reasonable basis, and not whether its measures will be
effective. The standard of review on this question is, therefore,
reasonableness (Ekuanitshit FC at para 94; Grand Riverkeeper at
paras 27-39).
[76]
Nalcor’s view is that questions regarding the
extent of the duty are reviewable on the correctness standard only if they are
questions of pure law. Where the extent of the duty depends on findings of
fact within the expertise of a decision-maker, the reasonableness standard
applies (Haida at para 61). The Crown has discretion as to the
structure of the consultation process and whether the consultation process was
adequately discharged involves determinations of mixed fact and law. These
determinations are entitled to deference and are reviewed on a standard of
reasonableness (Cold Lake at para 39; Taku Tlingit First Nation v
British Columbia (Project Assessment Director), 2004 SCC 74 at para 40 [Taku
River]; Ka’a’Gee Tu First Nation v Canada (Attorney General), 2007
FC 763 at paras 91 and 92 [Ka’a’Gee Tu #1]). Further, the applicable
standard of review for the adequacy of accommodation is also reasonableness (Haida
at paras 47-50, 62 and 63; Mikisew Cree First Nation v Canada (Minister of
Canadian Heritage), 2005 SCC 69 at para 66 [Mikisew Cree]; Native
Council of Nova Scotia v Canada (Attorney General), 2007 FC 45 at para 60,
aff’d 2008 FCA 113).
[77]
As to the Minister’s decision to issue the
Authorization, Nalcor submits that considerations involving the destruction of
fish habitat and relevant mitigative measures fall within DFO’s expertise and
that discretionary decisions under s 35 are to be reviewed on a reasonableness
standard. This is consistent with the general principle that discretionary
decision-making powers of the Minister under the Fisheries Act are
reviewable on that standard (Prairie Acid Rain Coalition v Canada (Fisheries and Oceans), 2006 FCA 31 at para 11; Malcolm v Canada (Fisheries and
Oceans), 2013 FC 363 at para 57 [Malcolm]).
[78]
To further this point, Nalcor contends that the
NCC attacks the reasonableness of the decision by questioning the quality of
the evidence relied upon by the Minister, therefore, no question of law arises
and the decision demands deference. Otherwise the Court would usurp the role
of the Minister and become an “academy of science”.
Similarly, qualitative decisions should not be disturbed unless they are made
in bad faith or on the basis of irrelevant considerations (Vancouver Island
Peace Society v Canada (TD), [1992] 3 FC 42 at paras 7 and 12; Alberta
Wilderness Assn v Express Pipelines Ltd, 137 DLR (4th) 177 at para 10; Alberta
Wilderness Assn v Cardinal River Coals Ltd, [1999] 3 FC 425 at paras
24-26).
[79]
A standard of review analysis need not be
conducted in every instance. Instead, where the standard of review applicable
to a particular question before the Court is well-settled by past
jurisprudence, the reviewing court may adopt that standard (Dunsmuir v New
Brunswick, 2008 SCC 9, [2008] 1 S.C.R. 190 [Dunsmuir] at para 57; Kisana
v Canada (Minister of Citizenship and Immigration), 2009 FCA 189 at para
18; Council of the Innu of Ekuanitshit v Canada (Attorney General), 2014
FCA 189 at para 38 [Ekuanitshit FCA]).
[80]
The standard of review applicable to the duty to
consult was addressed by the Supreme Court of Canada in Haida which
stated that:
[61] On questions of law, a
decision-maker must generally be correct: for example, Paul v. British Columbia (Forest Appeals Commission), [2003] 2 S.C.R. 585, 2003 SCC 55. On
questions of fact or mixed fact and law, on the other hand, a reviewing body
may owe a degree of deference to the decision-maker. The existence or extent
of the duty to consult or accommodate is a legal question in the sense that it
defines a legal duty. However, it is typically premised on an assessment of
the facts. It follows that a degree of deference to the findings of fact of
the initial adjudicator may be appropriate. The need for deference and its
degree will depend on the nature of the question the tribunal was addressing
and the extent to which the facts were within the expertise of the tribunal:
Law Society of New Brunswick v. Ryan, [2003] 1 S.C.R. 247, 2003 SCC 20; Paul,
supra. Absent error on legal issues, the tribunal may be in a better
position to evaluate the issue than the reviewing court, and some degree of
deference may be required. In such a case, the standard of review is likely to
be reasonableness. To the extent that the issue is one of pure law, and can be
isolated from the issues of fact, the standard is correctness. However, where
the two are inextricably entwined, the standard will likely be reasonableness: Canada (Director of Investigation and Research) v. Southam Inc., [1997] 1
S.C.R. 748.
[62] The process itself would likely
fall to be examined on a standard of reasonableness. Perfect satisfaction is
not required; the question is whether the regulatory scheme or government
action “viewed as a whole, accommodates the collective aboriginal right in
question”: Gladstone, supra, at para. 170. What is required is
not perfection, but reasonableness. As stated in Nikal, supra, at para.
110, “in . . . information and consultation the concept of reasonableness must
come into play. . . . So long as every reasonable effort is made to inform and
to consult, such efforts would suffice.” The government is required to make
reasonable efforts to inform and consult. This suffices to discharge the duty.
[63] Should the government misconceive
the seriousness of the claim or impact of the infringement, this question of
law would likely be judged by correctness. Where the government is correct on
these matters and acts on the appropriate standard, the decision will be set
aside only if the government’s process is unreasonable. The focus, as
discussed above, is not on the outcome, but on the process of consultation and
accommodation.
[81]
Until the Supreme Court’s subsequent decision in
Little Salmon, the above reference in Haida was consistently
interpreted as meaning that the scope or extent of the duty to consult (its content)
should be reviewed on the standard of correctness whereas the adequacy of the
process of consultation requires an analysis of the factual context and should
be reviewed on a standard of reasonableness (Katlodeeche at paras
126-127; Ka’a’Gee Tu #1 at paras 92-93; Ka’A’Gee Tu First Nation v
Canada (Attorney General), 2012 FC 297 at para 89 [Ka’a’Gee Tu #2]).
[82]
In Little Salmon the Supreme Court
addressed the standard of review in one paragraph:
[48] In exercising his discretion under
the Yukon Lands Act and the Territorial Lands (Yukon) Act, the
Director was required to respect legal and constitutional limits. In
establishing those limits no deference is owed to the Director. The
standard of review in that respect, including the adequacy of the consultation,
is correctness. A decision maker who proceeds on the basis of inadequate
consultation errs in law. Within the limits established by the law and the
Constitution, however, the Director’s decision should be reviewed on a standard
of reasonableness: Dunsmuir v. New Brunswick, 2008 SCC 9
(CanLII), [2008] 1 S.C.R. 190, and Canada (Citizenship and
Immigration) v. Khosa, 2009 SCC 12 (CanLII), [2009] 1 S.C.R. 339. In other
words, if there was adequate consultation, did the Director’s decision to
approve the Paulsen grant, having regard to all the relevant considerations,
fall within the range of reasonable outcomes?
[Emphasis added]
[83]
In discussing the content of the duty to
consult, the Supreme Court stated in part:
[72] The
adequacy of the consultation was the subject of the First Nation’s
cross-appeal. The adequacy of what passed (or failed to pass) between the
parties must be assessed in light of the role and function to be served by
consultation on the facts of the case and whether that purpose was, on the
facts, satisfied.
[84]
At the hearing of this matter, I asked the
parties to address the standard of review with respect to the adequacy of the
process in light of Little Salmon and the Federal Court of Appeal’s
finding in Ekuanitshit FCA, as described below. The NCC submitted that
the Courts appear to be struggling with the question. While the bulk of the
jurisprudence contemplates a reasonableness standard, the Federal Court of
Appeal in Ekuanitshit FCA appeared to accept the correctness standard. Canada submitted that while the Federal Court of Appeal’s reasons appear confusing, they
must be read in context. Further, that Little Salmon did not change the
Haida test. Haida held that if constitutional or legal matters
were at issue then the correctness standard applied. However, within the
limits of the law, the adequacy of consultation is reviewable on the
reasonableness standard. This has not changed (Cold Lake at para 39). And, approached on a principled basis, as the Minister’s decision is
discretionary, the standard must be reasonableness. Nalcor submitted that the
Minister’s decision is a discretionary one, accordingly, the standard is
reasonableness (Malcolm at para 35).
[85]
In my view, although it has been suggested that
the effect of these paragraphs from Little Salmon is to alter the
standard of review with respect to the adequacy of the consultation process
from reasonableness to one of correctness, for the reasons I have set out in
detail in Nunatsiavut Government v Attorney General of Canada (DFO),
2015 FC 492 at paras 105-120 [Nunatsiavut], I do not understand this to
be the case.
[86]
There, I noted that in Ekuanitshit FC at
para 126, and with respect to this Project, this Court has previously dealt
with a challenge to the lawfulness of the March 12, 2012 Order-in-Council
approving Canada’s Response to the JRP Report and the related March 15, 2012
Course of Action Decision. In addressing the question of whether the Innu of
Ekuanitshit had been properly consulted and accommodated, Justice Scott, relying
on Haida, found that the consensus in the case law was that a question
regarding the existence and content of the duty to consult is a legal question
that attracts the standard of correctness. A decision as to whether the
efforts of the Crown satisfied its duty to consult in a particular situation
involves assessing the facts of the case as against the content of the duty
which is a mixed question of fact and law to be reviewed on the standard of
reasonableness (Ka’a’Gee Tu #1 at para 91). The standard of
reasonableness was not stated to be in error by the Federal Court of Appeal in Ekuanitshit
FCA.
[87]
Further, in White River First Nation v Yukon
(Minister of Energy, Mines and Resources), 2013 YKSC 66 [White River],
the Yukon Supreme Court referenced paragraphs 61 to 63 of Haida, as well
as paragraph 48 of Little Salmon, and concluded:
[92] The standard of review may be
correctness if the issue relates to the legal and constitutional obligations of
the Director, i.e., the existence and extent of the duty to consult and
accommodate. On the other hand, the process of consultation, because it depends
on the government’s reasonable efforts to inform and consult, is reviewed on a
reasonableness standard.
[88]
And, the Alberta Court of Appeal in Cold Lake,
leave to appeal to the Supreme Court of Canada refused, 35733 (May 15, 2014),
considered the above provisions of Little Salmon but concluded that the
standard of review applicable to the issue of adequacy of the consultation
process was to be reviewed on a reasonableness standard (at paras 36-40). The
British Columbia Court of Appeal came to a similar conclusion in West
Moberly First Nations v British Columbia (Minister of Energy, Miners and
Petroleum Resources), 2011 BCCA 247 [West Moberly], leave to appeal
to the Supreme Court of Canada refused, 34403 (February 23, 2012), although the
three separate judgments reached this conclusion in different manners (at paras
141, 174, 196-198) (see also Dene Tha First Nation v British Columbia
(Minister of Energy and Mines), 2013 BCSC 977 at paras 104-108; and Adam
v Canada (Minister of Citizenship and Immigration), 2014 FC 1185 at paras
65-66, 87 [Adam]).
[89]
It is clear from the above jurisprudence that
the existence and extent of the duty to consult or accommodate is to be assessed
on the correctness standard. However, even there, where the extent of the duty
is premised on an assessment of the facts, deference may be owed and the
standard of review is likely to be reasonableness (Haida at para 61).
[90]
As to the adequacy of the process, based on Haida,
Ekuanitshit FCA, White River and Cold Lake, I am not convinced that Little Salmon was intended to alter, in every case,
the standard of review with respect to the question of whether the Crown
adequately consulted and accommodated to one of correctness.
[91]
In determining the extent of the duty to
consult, the Crown is obliged to identify the applicable legal and
constitutional limits, such as the specific treaty rights, legislative rights,
common law rights and the administrative and constitutional law applicable to
that case. That is, the Crown must correctly identify the legal parameters of
the content of the duty to consult in order to also properly identify what will
comprise adequate consultation. To proceed without having done so would be an
error of law. However, if those parameters are correctly identified, then the
adequacy of the subsequent process of consultation employed would remain a
question of reasonableness. This view can be seen as consistent with both Haida
and Little Salmon.
[92]
Where the standard of review is correctness, as
is the case with respect to the extent of the duty, no deference is owed to the
Crown (Dunsmuir at para 34; Little Salmon at para 48).
[93]
Where the standard of review is reasonableness,
as is the case with respect to the adequacy of the consultation and
accommodation, this Court’s review is concerned with the existence of
justification, transparency and intelligibility within the decision making
process. It is also concerned with whether the decision falls within a range
of possible, acceptable outcomes which are defensible in respect of the facts
and the law (Dunsmuir at paras 47-48; Canada (Minister of Citizenship
and Immigration) v Khosa, 2009 SCC 12, at para 59). As stated by Justice
de Montigny in Ka’a’Gee Tu #2, perfection is not required when assessing
the conduct of Crown officials. If reasonable efforts have been made to
consult and accommodate and the result is within the range of possible,
acceptable outcomes which are defensible in respect of the facts and the law,
there will be no justification to intervene. Further, the focus should not be
on the outcome but rather on the process of consultation and accommodation (Ka’a’Gee
Tu #2 at paras 90- 92; Haida at para 42).
[94]
As to the Minister’s decision to issue the
Authorization, in Ekuanitshit FCA, the Federal Court of Appeal held that
while reviewing courts must ensure that the exercise of power delegated by
Parliament remains within the bounds established by the statutory scheme, “a reviewing court must show deference when reviewing the
exercise of power delegated by the Act to the Governor in Council or to a
Minister” (Ekuanitshit FCA at paras 41 and 44) (see also Malcolm
at paras 30-34; Agraira v Canada (Public Safety and Emergency Preparedness),
2013 SCC 36 at para 50 [Agraira]; Canada (Citizenship and
Immigration) v Kandola, 2014 FCA 85 at paras 40-42 [Kandola]).
While the reasonableness review in Ekuanitshit FCA related to a
challenge to the lawfulness of the Order-in-Council approving Canada’s Response
and the related Course of Action Decision, made pursuant to s 37(1.1) and s
37(1) of the CEAA respectively, I see no reason why a different standard
should apply to the decision to issue the Authorization under s 35(2)(b) of the
Fisheries Act. Further, there is a presumption that decisions of
Ministers and their delegates are to be reviewed deferentially (Agraira
at para 50; Kandola at para 42). And, the reasonableness standard has
previously been applied to the decisions of the Minister of Fisheries (Malcolm
v Canada (Fisheries and Oceans), 2014 FCA 130 at para 30). Accordingly,
in my view, the decision to issue the Authorization is a matter to be reviewed
on the standard of reasonableness.
[95]
In its written submission, the NCC referred to Haida,
stating that the Supreme Court of Canada held that the duty to consult is
proportionate to a preliminary assessment of the strength of the case
supporting the existence of the right or title and to the seriousness of the
potentially adverse effects on the right or title claimed (at para 39). The
NCC did not put forward a view as to where the content of the duty to consult
fell in this case in terms of a spectrum analysis. However, when appearing
before me, counsel for the NCC stated that their position was that this matter
falls from the middle to the high end of the spectrum.
[96]
The NCC also submitted that the Minister’s duty
to consult and accommodate should be read in light of the United Nations
Declaration on the Rights of Indigenous Peoples, GA Res 61/295, UN GAOR,
61st Sess., Supp. No. 49 Vol. III, UN Doc. A/61/49 (2007) (“UNDRIP”), which Canada endorsed on November 12, 2010. Values reflected in international human rights law
may help inform the contextual approach to statutory interpretation and
judicial review (Baker at para 70) and, although not binding,
international law informs the interpretation of domestic law pursuant to the
presumption of conformity (R v Hape, 2007 SCC 26 at paras 53-55). The
Supreme Court has relied on UNDRIP to interpret Aboriginal rights (Mitchell
v Minister of National Revenue, 2001 SCC 33 at paras 80-83 [Mitchell])
and, since its endorsement, this Court has accepted that UNDRIP applies to the
interpretation of domestic human rights legislation and the interpretation of
administrative manuals directed at Aboriginal peoples (Canada (Human Rights
Commission) v Canada (Attorney General), 2012 FC 445 at paras 350-354;
aff’d 2013 FCA 75; Simon v Canada (Attorney General), 2013 FC 1117 at
para 121 [Simon]).
[97]
Canada refers to the Haida spectrum
analysis which it submits depends, in part, on the strength of the potential
claim and the seriousness of the potential adverse impact of the proposed
activity on the claimed Aboriginal right. In this case, the NCC’s claim falls
at the low end of the consultation spectrum as their claim to the Project area
is not strong and the adverse impact on them was found by the JRP to be adverse
but not significant. Thus, the only duty on the Crown was to give notice,
disclose information and discuss any issues raised in response to the notice (Haida
at para 43).
[98]
Alternatively, if the Court should find the
NCC’s claim to be more compelling but accepts the JRP’s impacts finding, then a
mid-range consultation standard would be appropriate. This would require notice
of the matter to be decided, an opportunity to discuss with decision-makers the
potential adverse impacts of the decision and how they might be mitigated, and,
that the decision-maker take the expressed concerns into account when making
the decision (Katlodeeche at para 95; Yellowknives Dene First Nation
v Canada et al, 2013 FC 1118 at para 59; Cold Lake at para
33). In any event, the NCC was consulted in a manner that far exceeded either
the low or mid-range consultation requirements.
[99]
As to UNDRIP, Canada submits that it was adopted
by a non-binding resolution of the United Nations General Assembly and has no
legal effect in Canada; it does not override or alter Canada’s existing
constitutional and domestic legal framework; and, questions of whether an
alleged duty to consult is owed are to be determined solely in relation to the
test enunciated by the Supreme Court of Canada in Rio Tinto Alcan Inc v
Carrier Sekani Tribal Council, 2010 SCC 43 at para 31 [Rio Tinto]
(see also Hupacasath First Nation v Canada (Foreign Affairs), 2013 FC
900 at para 51 [Hupacasath]). UNDRIP does not, therefore, assist the NCC
in defining the duty to consult.
[100]
Nalcor submits that three factors trigger the
Crown’s duty to consult and accommodate – i) the existence of an Aboriginal
claim or potential right; ii) the Crown’s knowledge of the claim or right, and
iii) the proposed Crown action that may adversely affect the claim or right (Haida
at para 35; Taku River at para 25; Rio Tinto at para 31).
Consultation can be fulfilled through an appropriately executed statutory or
regulatory review process and failure on the part of an Aboriginal group to
participate in such a process does not justify a claim of inadequate
consultation (Taku River at para 40; Ka’a’Gee Tu #2 at paras 91,
121; Brokenhead Ojibway First Nation v Canada (Attorney General), 2009
FC 484 at para 42). The Aboriginal group to whom the duty is owed has a
reciprocal duty to co-operate with the Crown’s efforts (Mikisew Cree at
para 65; Halfway River First Nation v British Columbia (Ministry of Forests),
1999 BCCA 470 at para 161 [Halfway River First Nation]; Nalcor Energy
v NunatuKavut Community Council Inc, 2012 NLTD 175 at para 97), to make
their concerns known, respond to attempts to meet those concerns and to try to come
to a mutually satisfactory solution (Cheslatta Carrier Nation v British
Columbia (Environmental Assessment Act, Project Assessment Director), 53
BCLR (3d) 1 (SC) at paras 71 and 73; Upper Nicola Indian Band v British
Columbia (Environment), 2011 BCSC 388 at para 128). Further, the duty to
consult does not imply a duty to agree and is not an outcome dependent obligation
(Haida at para 42; Ekuanitshit FC at para 126). Nalcor does not
dispute that the duty to consult exists in this case, but argues that it has
been met.
[101] The Authorization is not an approval of the Project, which Nalcor
had already obtained. Rather, it establishes conditions that address the
anticipated harm to fish and fish habitat. The consultation process must focus
on the terms of the Authorization, not on broader issues related to the Project
or prior approvals.
[102] Nalcor submits that UNDRIP was not ratified by Parliament and does
not create substantive rights. The question of whether a duty to consult has
been discharged must be determined solely by application of the test set out in
Haida and Rio Tinto. This Court has rejected the application of
UNDRIP in the context of the duty to consult (Hupacasath at para 51).
And, although UNDRIP may inform the contextual approach to statutory
interpretation, there is no issue of statutory interpretation in this case.
[103] I agree with the NCC’s general premise that UNDRIP may be used to
inform the interpretation of domestic law. As Justice L’Heureux Dubé stated in
Baker, values reflected in international instruments, while not having
the force of law, may be used to inform the contextual approach to statutory
interpretation and judicial review (at paras 70-71). In Simon, Justice
Scott, then of this Court, similarly concluded that while the Court will favour
interpretations of the law embodying UNDRIP’s values, the instrument does not
create substantive rights. When interpreting Canadian law there is a
rebuttable presumption that Canadian legislation is enacted in conformity to Canada’s international obligations. Consequently, when a provision of domestic law can be
ascribed more than one meaning, the interpretation that conforms to
international agreements that Canada has signed should be favoured.
[104] That said, in Hupacasath, Chief Justice Crampton of this
Court stated that the question of whether the alleged duty to consult is owed
must be determined solely by application of the test set out in Haida
and Rio Tinto. I understand this to mean that UNDRIP cannot be used to
displace Canadian jurisprudence or laws regarding the duty to consult, which
would include both whether the duty to consult is owed, and, the content of
that duty.
[105] While the NCC refers to Mitchell, it is of little relevance.
There Justice Binnie, in concurring reasons, at para 81 referred to Article 35
of a draft of UNDRIP to illustrate the difficulties Aboriginal peoples had in
freedom of movement across borders, however, the declaration did not play a
significant part of the interpretational analysis in that case.
[106] Most significantly, in this matter the NCC does not identify an
issue of statutory interpretation. Rather, it submits that UNDRIP applies not
only to statutory interpretation but to interpreting Canada’s constitutional
obligations to Aboriginal peoples. No authority for that proposition is
provided. Nor does the NCC provide any analysis or application of its position
in the context of its submissions. In my view, in these circumstances, the NCC
has not established that UNDRIP has application to the issues before me, or,
even if it has, how it applies and how it impacts the duty to consult in this
case.
[107]
In this matter there is no dispute as to whether
the Crown owed a duty to consult to the NCC with respect to the Project, this
is acknowledged by Canada and Nalcor.
[108] The seminal decision concerning the scope of the duty to consult
remains Haida. There the Supreme Court of Canada held that the content
of the duty to consult and accommodate varies with the circumstances.
Generally speaking, the scope of the duty is proportional to a preliminary
assessment of the strength of the case supporting the existence of the right or
title claimed, and the seriousness of the potential adverse effects on that
right or title (Haida at para 39). At all stages, good faith is
required by both sides. The Crown must have the intention of substantially
addressing Aboriginal concerns as they are raised through a meaningful process
of consultation, however, there is no duty to agree. Further:
[43] … the concept of a spectrum may be
helpful, not to suggest watertight legal compartments but rather to indicate
what the honour of the Crown may require in particular circumstances. At one
end of the spectrum lie cases where the claim to title is weak, the Aboriginal
right limited, or the potential for infringement minor. In such cases, the
only duty on the Crown may be to give notice, disclose information, and discuss
any issues raised in response to the notice. “‘[C]onsultation’ in its least
technical definition is talking together for mutual understanding”: T. Isaac
and A. Knox, “The Crown’s Duty to Consult Aboriginal People” (2003), 41 Alta.
L. Rev. 49, at p. 61.
[44] At the other end of the spectrum
lie cases where a strong prima facie case for the claim is established,
the right and potential infringement is of high significance to the Aboriginal
peoples, and the risk of non-compensable damage is high. In such cases deep
consultation, aimed at finding a satisfactory interim solution, may be
required. While precise requirements will vary with the circumstances, the
consultation required at this stage may entail the opportunity to make
submissions for consideration, formal participation in the decision-making
process, and provision of written reasons to show that Aboriginal concerns were
considered and to reveal the impact they had on the decision. This list is neither
exhaustive, nor mandatory for every case. The government may wish to adopt
dispute resolution procedures like mediation or administrative regimes with
impartial decision-makers in complex or difficult cases.
[45] Between these two extremes of the
spectrum just described, will lie other situations. Every case must be
approached individually. Each must also be approached flexibly, since the
level of consultation required may change as the process goes on and new
information comes to light. The controlling question in all situations is what
is required to maintain the honour of the Crown and to effect reconciliation
between the Crown and the Aboriginal peoples with respect to the interests at
stake. Pending settlement, the Crown is bound by its honour to balance
societal and Aboriginal interests in making decisions that may affect
Aboriginal claims. The Crown may be required to make decisions in the face of
disagreement as to the adequacy of its response to Aboriginal concerns.
Balance and compromise will then be necessary.
[46] Meaningful consultation may oblige
the Crown to make changes to its proposed action based on information obtained
through consultations…
[47] When the consultation process
suggests amendment of Crown policy, we arrive at the stage of accommodation.
Thus the effect of good faith consultation may be to reveal a duty to
accommodate. Where a strong prima facie case exists for the claim, and
the consequences of the government’s proposed decision may adversely affect it
in a significant way, addressing the Aboriginal concerns may require taking
steps to avoid irreparable harm or to minimize the effects of infringement,
pending final resolution of the underlying claim. Accommodation is achieved
through consultation, as this Court recognized in R. v. Marshall, [1999]
3 S.C.R. 533, at para. 22: “. . . the process of accommodation of the treaty
right may best be resolved by consultation and negotiation”.
[48] This process does not give
Aboriginal groups a veto over what can be done with land pending final proof of
the claim. The Aboriginal “consent” spoken of in Delgamuukw is
appropriate only in cases of established rights, and then by no means in every
case. Rather, what is required is a process of balancing interests, of give
and take.
[49] This flows from the meaning of
“accommodate”. The terms “accommodate” and “accommodation” have been defined
as to “adapt, harmonize, reconcile” . . . “an adjustment or adaptation to suit
a special or different purpose . . . a convenient arrangement; a settlement or
compromise”: Concise Oxford Dictionary of Current English (9th ed.
1995), at p. 9. The accommodation that may result from pre-proof consultation
is just this — seeking compromise in an attempt to harmonize conflicting
interests and move further down the path of reconciliation. A commitment to
the process does not require a duty to agree. But it does require good faith
efforts to understand each other’s concerns and move to address them.
(See also Taku River at para 29).
[109] Thus, the first step in this case is to consider the strength of the
NCC’s claim.
[110] The Affidavit of Todd Russell sworn on December 6, 2013 in support
of the NCC’s application for judicial review (“Russell Affidavit”) states that
in 1991 the NCC filed a comprehensive land claim document with Canada. Additional research information was filed in 1996 and in 2010 additional
substantive research on its claims was submitted by way of “Unveiling NunatuKavut”.
Further, that in The Labrador Metis Nation v Her Majesty in Right of
Newfoundland and Labrador, (2006) 258 Nfld & PEIR 257; aff’d 272 Nfld
& PEIR 178; leave to appeal to the Supreme Court of Canada refused, 32468
(May 29, 2008) [Labrador Metis Nation], the Newfoundland and Labrador
Court of Appeal found that NunatuKavut had a credible rights claim in the area
of the Trans-Labrador Highway and that the Government of Newfoundland and
Labrador had a duty to consult with NunatuKavut in respect of the construction
of the highway.
[111] In Labrador Metis Nation the Newfoundland and Labrador Court
of Appeal stated:
[51] A “preliminary evidence-based
assessment” of the strength of the respondents’ claim, such as discussed in Haida,
at paras. 37 and 39, supports the view in the present case that the claim is
more than a “dubious” or “peripheral” or “tenuous” one, which would attract
merely a duty of notice. The respondents have established a prima facie
connection with precontact Inuit culture and a continuing involvement with the
traditional Inuit lifestyle. They have presented sufficient evidence to
establish that any aboriginal rights upheld will include subsistence hunting
and fishing.
[52] The scope of consultation
requested by the respondents was set out in a letter to the Minister of
Environment and Conservation on October 26, 2004:
We now request that your office
forward to us any and all applications for water crossings and other relevant
permit requirements under your legislated mandate during the construction phase
of the Trans Labrador Highway – Phase III. We also request adequate time to
review and comment on the various permit applications.
An obligation to consult at this relatively
low level would be triggered by a claim of less prima facie strength than that
of the respondents. While it would be helpful to provide more guidance to the
parties as to the scope of future duties to consult, this is not possible
without knowing the future evidence which may be presented regarding the
strength of the respondents’ claim and regarding the types of adverse effects
on the potential aboriginal claim from future Crown activity. Any
unsatisfactory consequences for the parties, from the Court’s inability to
provide greater guidance, may be alleviated by their implementing a process for
reasonable ongoing dialogue.
[112] It concluded that the claim was at least strong enough to trigger a
duty to consult at the low level requested.
[113] The status of the NCC’s claim is also addressed in the record of
this matter. The Aboriginal Consultation Report prepared by the Agency,
addressed the status of NCC’s claim:
The Labrador Metis Nation submitted
its comprehensive claim to Canada in 1991-92. In 1998, the Department of
Justice advised that the Labrador Metis Nation did not meet the legal
tests for proof of Aboriginal rights, as an Inuit group. The evidence failed
to establish that the claimants were an Inuit Aboriginal group with rights
protected under s. 35(1) of the Constitution Act (1982). Rather, it was
primarily a political organization which represented, not distinctive
Aboriginal communities, but individuals of various Aboriginal descents.
The NunatuKavut asserted that Justice
Canada’s review was not impartial. In 2002, the claimants submitted further
material to Canada. Upon review, the Department of Justice confirmed its
earlier advice on the claimants’ inability to demonstrate the continuing
existence of Aboriginal rights in the south and central Labrador.
On an exceptional basis, Canada committed, in 2003, to contract a legal agent to conduct a further legal review of the claim
on the same basis as it was submitted to and reviewed by Canada. This outside review would only take place if Canada rejected the claim based on
the new material the claimants intended to submit. Furthermore, the outside
review would be based on the same material reviewed by Justice and would be
non-binding on Canada. In the interim, the Minister of Indian Affairs wrote to
the claimants on March 16, 2004, providing a detailed rationale for the claims
rejection. The Assessment and Historical Research Directorate is now in the
process of reviewing this material against the comprehensive claim policy and
have informed NunatuKavut that their claim will be assessed in a timely manner.
[114] Thus, the circumstances are that the NCC’s claim, although
originally rejected, is still being re-assessed. The NCC has not made
substantive submissions supporting the strength of its claim in the context of
a spectrum analysis. And, while “Unveiling NunatuKavut” is in the
record, the Court has not been asked to and is not in a position to assess that
document so as to determine the strength of the NCC’s claim. Accordingly, it
is my view that the best the Court can do in these circumstances is adopt the
finding of the Newfoundland and Labrador Court of Appeal, being that the claim
is at least strong enough to trigger a duty to consult at the lower level.
[115] As to the seriousness of the potential harmful effects of the
Project, the NCC asserts that its Aboriginal rights and title, treaty rights
and other interests over land and waters would be affected by the Project. Its
members are concerned about a number of potential impacts on those rights
including: adverse effects on aquatic and terrestrial wildlife and plants;
methylmercury contamination; downstream effects; flooding of traditional lands and
waters; water crossings which may disturb fish and aquatic life; access roads;
the possible use of herbicides and defoliants; and, cumulative environmental
effects. The NCC submits that these concerns are exacerbated by some of the
problems it has identified pertaining to the Authorization.
[116] All of these concerns are related to land and resource use which was
addressed by the JRP. In its report the JRP addressed current Aboriginal land
and resource use of individual Aboriginal groups, including the NCC. In the
executive summary it stated (p xxiii):
The Panel was required to specifically
consider Project effects on current use of lands and resources for traditional
purposes by Aboriginal persons. Information available to Nalcor, submissions by
Aboriginal groups and testimony during the public hearing suggested that
current use of the Project area (deemed by the Panel to be within the last 20
years) for traditional purposes is generally intermittent and sporadic relative
to use of other areas that would not be affected by the Project.
Some Aboriginal persons suggested that there
has been some decline in the intensity and extent of traditional land and
resource use activities in recent time due to societal and economic changes.
Nevertheless, the Panel recognized the importance, common to all Aboriginal
persons, of practicing traditional activities within the entire extent of their
traditional territory and the fact that for many groups, any effect from the
Project on their practice of traditional activities would act cumulatively with
impacts caused by the development of the earlier Churchill Falls project.
…
Inuit-Metis
The NunatuKavut Community Council indicated
that it was only able to provide limited information about current land and
resource use activities for traditional purposes by Inuit-Metis because of its
injunction application and the lack of time and financial resources to provide
detailed hearing submissions. Most information was received from individual
Inuit-Metis participants, rather than from the organization, and affiliation of
participants could not always be confirmed.
The Panel concluded that, based on
information identified through the environmental assessment process, there were
uncertainties regarding the extent and locations of current land and resource
use by the Inuit-Metis in the Project area. The Panel recognized that
additional information could be forthcoming during government consultations. To
the extent that there are current uses in the Project area, the Panel concluded
that the Project’s impact on Inuit-Metis land and resource uses, after
implementation of the mitigation measures proposed by Nalcor and those
recommended by the Panel, would be adverse but not significant.
The Panel also observed that many land and
resource use locations reported to be frequented by Inuit-Metis are outside of
the Project area and would remain unaffected and accessible. Measures
considered to mitigate the effects of the Project on trapping activities and to
compensate for losses of trapping income, property or equipment attributed to
the Project may also be particularly relevant for Inuit-Metis.
…
[Emphasis added]
[117] The JRP found that its significant finding in Chapter 8, with
respect to the Project’s effect on fishing and seal hunting in Goose Bay and
Lake Melville, would apply to traditional harvesting activities by Labrador
Inuit, including the harvesting of country food in this area should
Project-related consumption advisories be required. The JRP did not make a
similar finding with respect to the Inuit-Metis or any other Aboriginal group.
[118] Because the JRP concluded that the Project impacts on the NCC would
be adverse but not significant, I would be inclined to also place the
seriousness of the potential harm to the NCC on the lower end of the spectrum.
However, I recognize that the JRP also stated that it had received limited
information about current land and resource use activities for traditional
purposes in the Project area by the NCC and other Aboriginal groups.
[119] Given this, and currently unresolved status of the NCC’s land claim,
when considering both the strength of the NCC claim and the seriousness of the
potentially adverse effects on the right or title claimed, I would place the
duty to consult between the low and middle range of the spectrum.
[120] As to what is required in that range, the Supreme Court of Canada in
Haida stated that every case must be approached individually and
flexibly with the controlling question in all cases being what is required to
maintain the honour of the Crown and to effect reconciliation between the Crown
and the Aboriginal peoples with respect to the interest at stake (Haida
at para 45). The scope of consultation owed in the mid-range is something more
than the giving notice, disclosing information and discussing any issues raised
in response to the notice (Haida at para 43) and has been held to
include:
•
adequate notice of the matter to be decided, the
opportunity to discuss the potential impacts of the decision and how these
might be mitigated, and, that the concerns be taken into account in making the
decision (Katlodeeche at para 145);
•
that the Crown must inform itself of the impact
of the project on the rights of the Aboriginal group, communicate its findings
and engage directly and in good faith to hear concerns and attempt to minimise
adverse effects, and, some mitigation of the adverse effects (Cold Lake
at paras 32-33);
•
providing notice, disclosing of information,
responding to concerns raised; meeting, hearing and discussing the concerns;
taking them into meaningful consideration; and advising as to the course of
action taken and why (Long Plain First Nations, 2012 FC 1474 at
para 74); and
•
consultation in good faith, with an open mind
and the intention of substantially addressing the concerns of the party being
consulted as they are raised (Haida at paras 10 and 42).
[121] I note that when appearing before me the NCC asserted that Canada’s consultation process was flawed because there was no evidence that Canada had conducted a spectrum analysis. In my view, that submission cannot succeed.
Here Canada implemented a five phase Consultation Framework and the
issue in this judicial review is whether there was adequate consultation in
Phase 5 of that consultation process. In such circumstances, Canada was not required to undertake an explicit spectrum analysis, an analysis usually
adopted by the Courts, in Phase 5 or otherwise.
Issue 3: Did Canada satisfy its duty to consult and
accommodate?
[122] The NCC submits that it was not meaningfully consulted during Phase
5 because the Minister failed to address outstanding issues from the JRP,
including uncertainties regarding the extent and location of current land use
by the NCC members. Because of this, and, in the absence of Phase 5 funding,
the ability of all parties to assess the Project’s impact on the NCC’s
Aboriginal rights and title was limited.
[123] Further, a lack of funding or other resources at Phase 5 of the
consultation process made it impossible for the NCC to adequately review,
understand and comment on the highly technical FHC and EEM Plans which formed a
critical part of the Authorization. Accordingly, there was no meaningful
consultation at that stage (Platinex Inc v Kitchenuhmaykoosib Inninuwag
First Nation, 2007 CanLii 20790 [Platinex]).
[124] A complete denial of funding at Phase 5 was also not reasonable or
in good faith and that the NCC held a legitimate expectation that they would be
provided with such resources.
[125] The NCC also submits that the lack of funding precluded its ability
to present necessary Aboriginal Traditional Knowledge. The NCC submits that
despite the requirement of s 2.3 of the EIS Guidelines that Aboriginal,
traditional and community knowledge of the existing environment be an integral
part of the EIS, to the extent that it was available to Nalcor, there was no
commitment or effort on Nalcor’s part to gather this knowledge from the NCC.
The evidence suggests that while Nalcor funded some community consultation,
communications broke down over funding for a traditional knowledge study and
the gap was never addressed. The Minister also failed to consider the NCC’s
Aboriginal Traditional Knowledge and thereby failed to meaningfully consult and
accommodate it.
[126] The NCC asserts that the JRP identified uncertainties regarding the
extent and locations of current land and resource use by the NCC and that
additional time and resources would have been necessary for the NCC to
investigate this more fully. Further, that additional information could be
forthcoming during government consultations. However, that additional time and
resources were not provided at Phase 5 to address this deficiency in
information or data gap. This lack of information limited the ability of all
parties to assess, and determine the Project’s impact on the NCC’s Aboriginal rights
and title.
[127] The NCC also submits that the Regulatory Phase Protocol was
imposed on it, midway through the consultation process. Further, the delay in
responding to its comments on the proposed protocol and in responding to the
NCC’s response to the JRP Report until immediately prior to the issuance of the
Authorization also demonstrates a lack of meaningful consultation as well as a
lack of good faith (Mikisew Cree at paras 53-54) as demonstrated by the
response itself, which did not address concerns raised during the consultation
process, and DFO’s “close the loop” approach to consultation.
Canada’s
Position
[128] Canada submits that the consultation process far
exceeded the requirements of either a low or mid-range consultation. The majority
of the consultations took place within the EA and Canada is entitled to rely on
such consultations to discharge its duty to consult (Taku River at paras 2, 40-41; Ekuanitshit FCA at para 113). The JRP Report demonstrates
that the NCC’s concerns were heard and addressed and, in Grand Riverkeeper,
this Court found that the NCC was treated fairly within that process.
[129] The consultation history demonstrates that the process leading to
the issuance of the Authorization was comprehensive and fair. The NCC was
consulted on all draft protocols and, once finalized, the protocols were
followed. The NCC made no significant objection to the protocols when asked
for comments but, in some cases, criticized them later. The fact the NCC
limited its engagement for strategic purposes does not invalidate the process
or make it unfair.
[130] As to the timeliness of DFO’s June 28, 2013 letter responding to the
NCC’s November 9, 2011 letter, Canada points out that its June 28, 2013 reply
was just one letter among many communications over the five phase consultation
process. On May 31, 2013, DFO provided a detailed response to the NCC’s
concerns raised on April 15, 2013 and DFO also met with the NCC within Phase 5
and sought its comments on the EEM and FHC Plans. The NCC’s letter of November
9, 2011 focused primarily on what it felt was wrong with the JRP Report and,
the Province’s and Nalcor’s activities, but it makes little reference to
Canada. Further, between November 9, 2011 and June 28, 2013, the NCC’s
position on the JRP Report was rejected by this Court in Grand Riverkeeper.
[131] Canada submits that there is no requirement that
the Crown must provide funding to facilitate consultation. Where some funding
is necessary in order to allow for meaningful consultation, there is no right
to a particular level of funding. The appropriateness of funding depends on
the degree of consultation required and the circumstances of the case (Adams Lake Indian Band v British Columbia (Ministry of Forests, Lands and Natural
Resource Operations), 2013 BCSC 877 at paras 85 and 87 [Adams Lake]).
[132] In this instance, Canada provided the NCC with $154,000 in funding
specifically in relation to the Project consultations; $1.8 million in relation
to its land claims; and, Nalcor provided $248,000 for land use research. This
was more than sufficient to enable the NCC to participate meaningfully, and the
NCC had been advised in October 2006 and again in May 2012 that DFO would not
be providing funding at Phase 5. Although no funds were specifically designated
for Phase 5, the NCC did not make a proposal for funds at that stage, it has
not said what resources would have been sufficient, and, it did not allocate
any of its own funds for this purpose, although it did fund two unsuccessful
applications challenging the consultation process.
[133] Further, additional funding was not essential to enable the NCC to
communicate its traditional knowledge to Canada, given that traditional
knowledge regarding land use in the Project area is solely within the NCC’s
collective knowledge (Adams Lake at para 85). The NCC was aware that
traditional knowledge and land use information would be needed by the JRP and
it was responsible for filling any perceived gaps in that information (Grand
Riverkeeper at paras 69-70). The NCC elected to boycott much of the JRP
process even though that was the primary venue for presenting such
information. The NCC now seeks to avoid the consequences of its strategic
decision not to fully engage and attempts to challenge the validity of the
Authorization on the same basis.
[134] In any event, individual members of the NCC did participate and the
NCC made a series of presentations near the end of the JRP hearings, after the
injunction sought by them was refused. Thus, the NCC was provided with
meaningful opportunities to present its traditional knowledge at that stage.
[135] Canada submits that the NCC has failed to show
that a lack of funding hindered its participation in the Phase 5 consultations
or that additional funding was necessary for meaningful consultation.
[136] Nalcor submits that the scope and process set out in the Phase 5, Regulatory
Phase Protocol, and followed by DFO was reasonable given the circumstances
which led up to it. The NCC was provided with detailed information about the
Authorization, which supplemented the extensive information previously provided
about the environmental effects of the Project. It was given an opportunity to
provide input into the consultation process and the Authorization including the
FHC Plan and the EEM Plan. The NCC participated in the consultation process,
by providing its views on both the process and the Authorization itself. These
submissions were considered by DFO, as summarized in its letter to the NCC
dated May 31, 2013.
[137] As to funding, Nalcor submits that in total the NCC received at
least $438,200 in funding specifically intended to allow it to present its
views on the Project. Further, a significant amount of information was
presented, in particular during the EA process, included the “Unveiling
NunatuKavut” report which documents all of the NCC land claims data and
research, for which the NCC received $2.0 million in federal government
funding.
[138] It was reasonable for the Minister to rely on the extensive
Aboriginal and technical information which arose from the EA and to refuse to
provide further funding, particularly as the NCC did not indicate how much
funding it required or for what purpose (Ktunaxa Nation v British Columbia
(Forests, Lands and Natural Resource Operations), 2014 BCSC 568 at
para 205 and 232 [Ktunaxa]; Adams Lake at para 85-88; Ekuanitshit
FC at para 129). Further, the information is within the knowledge of the
NCC and its members, and is not highly technical or complex nor is there any
evidence that additional technical studies are required.
[139] It must first be noted that the NCC in this application for judicial
review challenges the decision of the Minister to issue the Authorization.
Accordingly, it is not open to the NCC to collaterally attack the validity of Canada’s Response or the Course of Action Decision by way of this application. However, as
I found in Nunatsiavut, the five phase consultation process that
underlies the JRP Report, and all of the decisions made subsequent to it by Canada, was an ongoing one.
[140] The phases of the consultation process, and the consultation
undertaken in each phase, are connected. The prior consultation therefore
serves, to a degree, to inform the consultation and accommodation undertaken in
Phase 5. The consultation process cannot be considered to be complete until
the end of Phase 5. Thus, the totality of the consultation between Canada and the NCC in each phase of the EA must be considered in order to understand and
assess the extent of the consultation and accommodation in respect of the
Authorization. To the extent that the NCC questions the content or adequacy of
the consultation with respect to the issuance of the Authorization, it is
entitled to look at the prior consultation for that purpose, but not as an
attempt to impugn the validity of those prior decisions.
[141] In that regard, this Court in Ekuanitshit FC was faced with
an argument by Canada that the Innu of Ekuanitshit had filed their application
for judicial review challenging the Order-in-Council approving Canada’s Response and the Course of Action Decision before the consultation period had come
to an end. The application for judicial review was filed at the conclusion of
Phase 4; at the time of the hearing the process was in Phase 5 (at para 13) of
the Consultation Framework. This Court found that the judicial review
at that stage of the federal government’s consultation and accommodation
process was premature:
[112] The Court finds that judicial
review of the federal government’s consultation and accommodation process is
premature at this stage. One of the goals of consultation and accommodation is
to “preserve [an] Aboriginal interest pending claims resolution” (Haida,
cited above, at para 38). This requires that Aboriginal groups be consulted and
accommodated before the rights they lay claim to are irrevocably harmed. While
it is true that preparatory work for the Project has begun, the acts that truly
put the Applicant’s rights and interests at risk are those which require
permits issued by TC and DFO. It is premature to evaluate the federal
government’s consultation process before those decisions are made.
Notwithstanding this finding, the Court considers it should nonetheless review
and assess the adequacy of the consultation that has taken place up to the moment
when this application for judicial review was filed.
[142] The Court went on to assess the adequacy of the consultation up to
the time that the application was filed and found that the Crown had
satisfactorily fulfilled its duty to consult (Ekuanitshit FC at para
137).
[143] On appeal of that decision, the Federal Court of Appeal in Ekuanitshit
FCA agreed with this approach, stating that:
[108] With respect, I find it difficult
to conclude that the judge erred in finding that the appellant had been
adequately consulted prior to the government’s order being issued. Phase V of
the Consultation Framework confirms that the consultation process
between the Crown and the Aboriginal people continues up to the issuance of
licences by Transport Canada and Fisheries and Oceans. These licences will
authorize Nalcor to undertake certain activities, including the construction of
dams that could have consequences on the navigable waters under the Navigable
Waters Protection Act or on fish habitat under the Fisheries Act.
But we are not at that point yet. As confirmed and acknowledged by the lawyers
of the Attorney General of Canada, the federal government’s consultation has
not been completed and will remain ongoing until the final phase, namely, the
issuance of licences.
[144] The Federal Court of Appeal also stated that the Crown must continue
to honourably fulfil its duty to consult until the end of the process (Ekuanitshit
FCA at para 110).
[145] Further, in NCC I, the NCC sought an interlocutory injunction
to stop the JRP hearings until the Court had dealt with its claim. In February
2011, the NCC had sued Nalcor, the federal and provincial governments, the
Agency, and the five JRP panel members. It sought, amongst other things, a
declaration that the defendants had breached their duty to consult with the NCC
and directions on how consultations should be conducted. Justice Handrigan of
the Newfoundland and Labrador Supreme Court rejected the NCC’s claim that it
would suffer irreparable harm if the public hearings were not enjoined, as he
disagreed that the consultation and accommodation to that stage had been
deficient, and noted that there were still two phases following the hearings
during which the NCC could continue to be involved before the process would be
finished (NCC I at paras 50-53).
[146] In Grand Riverkeeper the NCC and the other applicants
challenged the lawfulness of the JRP Report. There the issues were whether the
JRP had fulfilled its mandate with respect to the need for and alternatives to
the Project and its cumulative effects. The NCC also claimed that the JRP had
breached principles of procedural fairness or violated its right to be heard.
[147] Justice Near, then of this Court, dismissed the application. With
respect to the NCC’s argument that the JRP had a duty to consult it on all
matters and to compel evidence from the NCC on the issues in dispute, Justice
Near held that the JRP’s mandate was determined by its TOR which required it to
invite information from Aboriginal groups or persons. Further:
[69] Moreover, the Panel fulfilled its
mandate by inviting, and accepting, on several occasions written submissions
from NunatuKavut. In addition, the Panel heard from the group in the General
Hearing Sessions it held in Happy Valley-Goose Bay and in St. John’s. Indeed,
the group received over $130,000 through the Participant Funding Program to
participate in the EA process. NunatuKavut’s choice not to participate in a
portion of the hearings by virtue of its injunction proceedings, regardless of
how good the group’s intentions, cannot impose a duty on the Panel to compel
evidence from it.
[148] Justice Near concluded that there was no infringement of
NunatuKavut’s right to be heard or of any other principle of procedural
fairness with respect to the group’s participation in the EA process.
[149] I would also note that the Nunatsiavut Government challenged a July
10, 2013 permit to alter a body of water issued by the Province with respect to
the Project on the basis that the Province breached its duty to consult and
accommodate the applicant. The Supreme Court of Newfoundland and Labrador, in Nunatsiavut
v Newfoundland and Labrador (Department of Environment and Conservation),
2015 NLTD(G) 1, found that the conclusions of the EA provided an informed basis
for subsequent regulatory decision-making as various permits are sought.
Further, that the objection to the permit and to construction of the dam
related to issues of mercury contamination were fully considered by the JRP and
by the Province, although not to the applicant’s satisfaction, before the
Province issued its Order-in-Council formally releasing the Project from the EA
on March 15, 2012. Justice Orsborn was of the view that it was the decision to
issue the Order-in-Council that should have been challenged, rather than a
subsequent regulatory decision relating to the specifics of the Project
construction. He stated that “… in the circumstances
of this case, allowing issues relating directly to the response to the Joint
Review Panel and the 2012 release Order to support a challenge to a later and
separate issuance of a regulatory permit would be unfair” (at para
114). For that reason he expressed no opinion on whether the Province’s
response to the JRP Report or the release Order itself suffered from any legal
defect relating to consultation, accommodation or reasonableness.
[150] Given the foregoing, it is my view that the totality of the
consultation between DFO, Nalcor and the NCC from initiation and including
Phases 1 to 4 must also be considered when considering the adequacy of
consultation and accommodation pertaining to the Phase 5 decision to issue the
Authorization, including any concerns arising from an alleged lack of funding
and resources (see Adam at para 77; Ktunaxa at paras 203-206).
[151] Section 8.1 of the JRP Agreement states that the Agency will
administer a participant funding program to facilitate the participation of
Aboriginal groups and the public in the EA of the Project. Section 58(1.1) of
the CEAA states that the Minister shall establish a participant funding
program to facilitate the participation of the public in assessments conducted
by review panels.
[152] Documentation from the Agency contained in the record of this matter
indicates that the Participant Funding Program (“PFP”) was designed to promote
public participation in the evaluation and review process of projects that are
subject to federal EAs pursuant to s 58(1.1) of the CEAA. A Funding
Review Committee (“FRC”), independent from the JRP, was established to review
funding applications and allocate up to $50,000 to applicants during the Phase
1 consultations. Five eligible applications were received, including that of
the NCC. A total of $119,500 was requested to participate in the review of and
to comment on the draft EIS Guidelines and to facilitate public participation
for the EIS. The NCC requested $50,000, and, on August 23, 2007 was awarded
$13,000 of the available $50,000. In connection with this, the NCC submitted a
draft budget which sought a total of $420,911.50 to cover expenses in
connection with the JRP, the EIS Guidelines, EIS review, JRP hearings and
government responses. This would, in effect, encompass Phases 1-4.
[153] On March 9, 2009, the FRC reviewed three applications received by
the PFP - Aboriginal Funding Envelope which requested a total of $1,183,393.
The FRC recommended awarding a total of $664,439 to the three applicants to
assist with their participation in the JRP hearings, including the review of
the EIS and to engage in associated consultation activities. The NCC was
awarded $120,000 of the available $664,439 on July 7, 2008. The related
Contribution Agreement between the Agency and the NCC required the NCC to
participate in the assessment by the JRP in compliance with the approved work
plan, and to ensure that the information gathered was submitted to the JRP.
The approved work plan was attached as Appendix B and states, in part, that the
NCC will: engage in consultation activities with the federal government that
are linked to the EA; “have meetings to collect and
distribute information pertaining to the project and to collect local
traditional knowledge”; hold workshops to ensure an understanding of the
process, science and technical issues involved with the Project; prepare for
and participate in consultation meetings associated with the EA; and, to
prepare for and participate in public hearings and to prepare their submission
to the JRP.
[154] On May 19, 2011, the Agency advised the NCC that Phase 4 funding was
being provided under the PFP – Aboriginal Funding Envelope. A total of
$120,000 was available and was intended to support Aboriginal groups who had
participated in the JRP review and now wished to engage in consultation
activities with Canada concerning the JRP Report. The funds could be used to
assist Aboriginal groups with reviewing the report, holding community meetings
to review the report and expenses related to meeting with Crown
representatives. In its application, the NCC described the proposed activities
for which it was seeking funding, which included holding meetings to collect
traditional knowledge. It sought $149,740.81 in funding. On August 12,
2011, it was granted $21,000 of the available $120,000 which related to the
stated eligible activities. These were consultations on the JRP Report and its
Recommendations, as well as seeking to establish whether potential impacts of
the Project on potential or established Aboriginal or treaty rights had been
addressed and consultations on the manner and extent to which any recommended
mitigation measures may serve to accommodate those concerns and whether there
remained any outstanding items.
[155] The Affidavit of Stephen Chapman, Associate Director, Regional
Operations with the Agency (“Chapman Affidavit”), filed in support of Canada’s position in this application, states that according to documentation from Indian
and Northern Affairs Canada (“INAC”), the NCC also received funding outside the
EA process for consultation on its comprehensive land claims. Attached as Exhibit
16 of the Chapman Affidavit is a document described as a spreadsheet from INAC
that, after subtracting amounts that are core funding, indicates funding of
$479,589 for 2006-7; $301,173.68 for 2007-8; $506,127 for 2008-9 and $581,665
for 2009-10.
[156] The referenced document is entitled Budget Allocation Per Year
Report and the referenced entries pertain to POWLEY or POWLEY – Metis
Aboriginal Rights. No explanation of this term is given in the Chapman
Affidavit or in the document itself. Counsel for Nalcor referred the Court to
page 41 of “Unveiling NunatuKavut” which refers to research for a
comprehensive lands claims submission to the federal government and to four
years of work funded by the federal government from two different programs,
footnoted to be “Powley funding (Office of the
Interlocutor) and Comprehensive Claims finding (INAC)”. In my view,
this adds little clarity to the matter. However, this issue was previously
addressed by Justice Handrigan in NCC I who stated at paragraph 41 that:
…I am not sure how much funding was actually
allotted to either Nunatukavut or the Innu Nation specifically for the Lower
Churchill EA process, but I do know that Nunatukavut received more than
$2,000,000 to research and write “Unveiling NunatuKavut”, its land claim
document, which it did present to the JRP ...
[157] The Affidavit of Mr. Gilbert Bennett, Vice President of the Project
for Nalcor (“Bennett Affidavit”) filed in support of Nalcor’s position in the
application, states that Nalcor and NCC entered into two community consultation
agreements (“CCA”) whereby the NCC was provided with an additional $248,000.
Amongst other things, the CCAs were intended to allow the NCC to gather
information related to its members’ contemporary land and resource use surrounding
the Project and Nalcor’s proposed Labrador Transmission Link (Bennett Affidavit
at para 39).
[158] The CCAs are found at Exhibit K of the Bennett Affidavit. The first
is dated December 11, 2009. Its preamble states that the EIS Guidelines
for the Project require Nalcor to consult with Aboriginal groups, including the
NCC, to familiarize the groups with the Project and its potential environmental
effects, to identify any related issues or concerns and identify what actions
Nalcor proposed to take to address them.
[159] Further, that Nalcor wished to provide information respecting both
the Project and the Transmission Project and to consult with the NCC in respect
of the impacts of each project to fulfil the requirements of the EIS Guidelines
and to obtain information with respect to the potential environmental effects
of each project upon the interests and rights of the NCC and its members and
communities. The community consultation process it described includes: the
determination of what the NCC thinks about the projects and how each project
may affect it, its members and communities; the communication of findings of
the community consultation process to the NCC and Nalcor; and, “to identify traditional knowledge and current use of
resources” (s 1.1). Should the CCA remain in effect for its full term
(to March 31, 2010 with an option to extend by 12 months), it was agreed that
compliance by Nalcor with its provisions would completely fulfil the
requirements of the EIS Guidelines and discharge the obligations of Nalcor with
respect to the consultation with the NCC in that regard (s 8.8). The total
amount of funding for the period of December 11, 2009 to March 31, 2010 was
$103,800.
[160] The second CCA is dated January 19, 2011. In its preamble, it
refers to the CCA that expired on March 31, 2010 and notes that the NCC
requested that the parties continue the process of consultation, with a focus
on the transmission project, and to collect information in relation to the
contemporary land and resource use in the area depicted on the map attached as
Schedule I (the Study Area) and relevant traditional ecological knowledge held
by members of the NCC. A total maximum amount of funding for eligible
expenditures was $108,400. It was also agreed that the report to be generated would
contain sufficient information respecting NunatuKavut traditional knowledge,
land and resource use and identification of NunatuKavut issues of concern to
enable Nalcor to use the information as a source of material in the EA process.
[161] The Appendix A – Work scope states:
1. Objective
Information on NunatuKavut’s issues and
concerns relating to, and land use and harvesting activities in the area of,
the Lower Churchill Hydroelectric Generation Project (the “Generation Project”)
was provided by NunatuKavut under the Community Consultation Agreement which
expired on March 31, 2010. NunatuKavut has also provided Nalcor with its
supplemental land claims documentation (“Unveiling NunatuKavut”). This
information, together with other publicly available information, has been
provided in the Consultation Assessment Report (Supplemental Information to IR
JRP. 151) which Nalcor submitted to the Joint Review Panel on September 27,
2010.
Nalcor now proposes to conclude the Phase II
Community Consultation Agreement with NunatuKavut to supplement existing and
available information respecting NunatuKavut traditional ecological knowledge,
contemporary land use and resource use in the Study Area (shown on the map
attached as Appendix “A”) and issues of concern in relation to the
Labrador-Island Transmission Link (the “Transmission Project”). The proposed
Agreement will provide funding for the following activities to be carried out
over a four month period from December 15, 2010 to April 15, 2011:
• A community consultation process
• The collection of relevant traditional ecological knowledge,
and
• A survey of NunatuKavut land use and harvesting activities in
the Study Area.
[162] The purpose of the CCA is stated to include collection of
information on harvesting activities, intensity, seasonality, locations, and
species and sites of socio-cultural importance to the NunatuKavut in the Study
Area; to complement existing NunatuKavut land and resource use held by Nalcor;
and, to collect information on NunatuKavut traditional ecological knowledge.
Land and resource use data collection is described and includes the hiring of
researchers and the conducting of interviews with key members of NunatuKavut
determined to have contemporary land and resource use knowledge in the Study
Area. The results of the land and resource use data collection and analysis
was to be contained in the final report.
[163] The JRP Report also speaks to participant funding received by the
NCC:
1.4.2 Participant Funding Program
Pursuant to subsection 58(1.1) of the Canadian
Environmental Assessment Act, participant funding was made available to help
the public and Aboriginal groups participate in the environmental assessment of
the Project. The Participant Funding Program consisted of two funding
envelopes: the regular funding envelope and the Aboriginal funding envelope.
Funding was available to help participants review the draft EIS Guidelines and
the EIS and to participate in the public hearing.
The Canadian Environmental Assessment Agency
established Funding Review Committees, independent from the Panel, to review
funding applications and to recommend funding allocations. In total, the
Canadian Environmental Assessment Agency allocated funding to the following
applicants:
• Council of the Innu of Unamen Shipu and Council of the Innu of
Pakua Shipu: $106,875;
• Corporation Nishipiminan (Council of the Innu of Ekuanitshit):
$55,850.25;
• Fiducie Takuaikan (Nutashkuan First Nation): $46,000;
• Grand Riverkeeper Labrador Inc.: $77,600;
• Innu Nation: $533,968;
• Labrador Métis Nation (now the NunatuKavut Community Council):
$133,000;
• Naskapi Nation of Kawawachikamach: $9,165;
• Natural History Society of Newfoundland and Labrador: $16,400;
• Nunatsiavut Government $23,471;
• Sierra Club Canada - Atlantic Chapter: $50,000; and
• Women in Resource Development: $5,000.
The Canadian Environmental Assessment Agency
will make additional funding available under the Aboriginal funding envelope
for the participation of Aboriginal groups in consultation activities related
to the Panel report.
[164] Based on the foregoing, it is apparent that the NCC did receive
funding that was, at least in part, intended to assist it in gathering
Aboriginal Traditional Knowledge and assessing current land and resource use.
The NCC asserts that this was inadequate for that purpose and, therefore, that
there was no meaningful consultation. However, the funds that it received from
Nalcor and the Agency were in fact in excess of the NCC draft budget which
sought a total of $420,911.50 to cover expenses in connection with the JRP, the
EIS Guidelines, EIS review, JRP hearings and government responses.
Additionally, it was funded so as to produce “Unveiling NunatuKavut”
which documented its land claim. A stated purpose of that document was to act
as a foundational treatise to be provided to the federal government in an
effort to illustrate present day rights and title held by the Inuit descent
people of South Central Labrador. That document also points the reader to the
work of Dr. Hanrahan, entitled “Salmon at the Centre”, which examined the
Indigenous Knowledge, including local knowledge of animals, plants and
landscape, of Inuit elders and experts.
[165] The NCC refers to Platinex in regard to the role of funding.
That was a motion arising out of a decision directing the parties to continue
the process of consultation and negotiation in the hope of implementing a
consultation protocol and other steps. The Court reserved its right to make
further orders in that regard if the parties could not reach agreement. As to
funding, the consultation agreement appended a schedule of eligible costs.
Ontario had offered to fund the first nation’s reasonable costs for consulting
in phase 1 and set a $150,000 target, with the quantum and other matters to be
captured in a contribution agreement. This was rejected by the first nation as
being inadequate, it sought $600,000 up front and an assurance that all of its
consultation and litigation costs would be covered, and asserted that the
imbalance between the financial positions of the parties rendered the
consultation process unfair. The Court stated that the issue of appropriate
funding is essential to a fair and balanced consultation process to ensure a
level playing field, however, that there was insufficient material before the
court for it to make an informed decision as to what level of funding would be
available (Platinex at paras 23-27).
[166] In this matter, the NCC has not provided any evidence as to what
level of funding, in addition to that which it did receive, would have been
adequate for purposes of gathering Aboriginal Traditional Knowledge and
assessing its current land and resource use. I would note that the FRC
recommended the allocation of funding amounts that it deemed reasonable in
light of the information provided in the funding applications, follow-up
responses and funds received by applicants from other sources. Further, that
the level of funding that was provided by the Agency to the NCC does not appear
to be out of line with the funding provided to other Aboriginal groups, as
reflected in the JRP Report listing above.
[167] Ultimately, this Court is simply not in a position to make an
assessment as to the adequacy of funding and, in the absence of evidence to the
contrary, must assume that the Agency had not only the authority to allocate
funding, but also appropriately exercised its discretion to determine
appropriate funding levels in the prevailing circumstances.
[168] The NCC also submits that a complete denial of funding in Phase 5
precluded fair and meaningful consultation because the Minister failed to
address the uncertainties regarding the extent and location of current land and
resource use by the NCC and, without additional funding at Phase 5, the
Project’s impact on NCC’s Aboriginal rights and title were not properly
addressed.
[169] In my view, in this regard, it must be recalled that Phase 5 was not
the only opportunity afforded to the NCC to make representation on Aboriginal
Traditional Knowledge and current land and resource use. During the consultation
process the NCC not only received funding to collect Aboriginal Traditional
Knowledge and to address land and resource use but also to participate in the
JRP process. The NCC did participate as described in the JRP Report. For
example, in considering the sufficiency of the EIS, the JRP issued 166 IRs in
total. A table of concordance issued by the JRP indicates that 56 IRs were
generated by the JRP taking into consideration submissions made by the NCC,
including concerning Aboriginal Traditional Knowledge. The JRP also invited
comments on Nalcor’s responses. In that regard the NCC submitted its “Response
to Lower Churchill Hydroelectric Generation Project Environmental Impact
Statement” on June 19, 2009. On December 18, 2009, the NCC submitted a
further response of the same name, taking issue with the level or lack of
consultation by Nalcor in relation to the EIS.
[170] The JRP sought additional information concerning Aboriginal
Consultation and Traditional Land and Resource Use by way of IR JRP.151.
Nalcor submitted its response to JRP.151 in May, 2010. In it, Nalcor stated
that consultation efforts with the NCC regarding the Project had been ongoing
since April 2007, and included a record of consultation. Nalcor submitted a
supplemental response in September 2010 which was comprised of its Aboriginal
Consultation Assessment Report. This described consultation efforts and
additional data collected pertaining to the NCC, and other Aboriginal Groups,
including historic and contemporary activities including fishing, hunting,
trappings and marine mammal and plant harvesting. It also set out a table
listing issues of concern to the NCC and proposed and complete actions and
responses. The NCC filed a submission in response.
[171] The JRP hearings commenced on March 3, 2011. On March 4, 2011, the
NCC advised the JRP that it would not participate and had filed an injunction
seeking to halt the hearing. The JRP responded with regret and stating that as
it had said in the past, it viewed the public hearings as an opportunity for
Aboriginal groups to provide it with valuable information on asserted or
established Aboriginal rights and title and how the Project may impact them,
such information could then be included in the JRP Report.
[172] On March 24, 2011, the injunction application in NCC I was
dismissed by Justice Handrigan of the Newfoundland Supreme Court. He set out a
detailed review of the communications and consultations to that point in time and
also addressed the role of the JRP stating:
[49] But Nunatukavut’s criticism of the
JRP casts the Panel in a poor light and unfairly so. In fact, the Panel quite
vigorously, if not aggressively, insisted that Nalcor take its duty to consult
and accommodate Nunatukavut and the other Aboriginal groups seriously. I note,
for example, the four series of comprehensive information requests which it
directed to Nalcor between May 1, 2009 and November 2, 2010, one of which
related specifically to Nalcor’s consultation with Aboriginal groups. I also
note here the letter the JRP sent to Nalcor on February 5, 2010 instructing
Nalcor to provide monthly updates to the Panel on its consultation activities
with Aboriginal groups and the JRP’s decision in January, 2010 that the
information it had received from Nalcor by then was not sufficient to go to
public hearings.
[50] The JRP has been an important
advocate for Aboriginal consultation and accommodation throughout the EA
process. And it has, to the extent that its mandate will permit, sought and
received information about the potential adverse impacts that the Project will
have on asserted or established Aboriginal rights or title, including those of
Nunatukavut. Nunatukavut has not and will suffer no harm, irreparable or
otherwise, because of the Panel’s actions. It does risk harm, though it will
not likely be irreparable, if it declines the JRP’s outstanding invitation to
participate in public hearings and otherwise engage in the remaining phases of
the EA process.
[173] Subsequent to the denial of the injunction, the NCC did participate
and made oral submissions to the JRP, accompanied by presentation materials.
The first presentation concerns perceived data gaps, the need for a literature
review, archival records and the time and resources to address this. The
second recommended that Aboriginal Traditional Knowledge be incorporated in the
EIS, that there be more meaningful consultation and that outstanding
environmental issues be resolved.
[174] The JRP acknowledged the significance of its report in the context
of Canada’s overall consultation process:
In August 2010, the Canadian Environmental
Assessment Agency released the Federal Aboriginal Consultation Framework for
the Lower Churchill Hydroelectric Generation Project (the Framework) to clarify
how the federal government would rely on the Panel review process in fulfilling
its legal duty to consult Aboriginal groups. The Framework clarified the role
of the Canadian Environmental Assessment Agency and federal departments in
consultation activities during the Panel review process as well as consultation
activities outside the Panel process.
The Framework identified the importance of
the Panel review process within overall federal government consultation
activities and the importance of Aboriginal participation in that process. The
Framework also pointed out that the Panel report and records established
through the Panel review would be the primary source of information to support
the federal government assessment of potential impacts of the Project on
potential and established Aboriginal and treaty rights.
[Emphasis added]
[175] The JRP Report, in Chapter 8, Land and Resource Use, addressed
effects of the Project on harvesting activities (hunting, trapping, fishing,
and berry picking), cabins, winter travel, navigation and other resource-based
activities (mining, agriculture and ecotourism) applicable to Aboriginal and
non-Aboriginal land and resource users alike. The JRP noted that the available
information suggested that the area affected is used for a variety of purposes,
but is currently not a prime area for land and resource use activities. It
concluded that the Project would have an adverse but not significant effect on
fishing in the main stem of the Churchill River because this is not currently
an important fishing destination.
[176] However, should new consumption advisories be required in Goose Bay
and Lake Melville, the Project would have a significant adverse effect on
fishing and seal hunting in this area because of the reliance by many
Aboriginal and non-Aboriginal people on fish and seals caught there. It was
uncertain whether consumption advisories would be required beyond the mouth of
the Churchill River, and the JRP referenced its Recommendation 6.7 concerning
the assessment of downstream effects in that regard. Thus, the Project would
not have a significant adverse effect on land and resources use, with the
exception of the potential effects on fishing and seal hunting in the Lake
Melville area the JRP identified.
[177] In Chapter 9, Current Aboriginal Land and Resource Use of
Traditional Purposes, the JRP set out Nalcor’s and the participants’ views,
including that the NCC did not agree with Nalcor’s conclusion that the NCC’s
members do not currently practice land and resource use activities within the
Project area and its submission that this conclusion was based on deficient
information. In particular, the NCC disagreed with Nalcor’s use of information
contained in “Unveiling NunatuKavut” as it was primarily concerned with
a limited study area.
[178] The JRP noted that in reaching its conclusions on current Aboriginal
land and resource use for traditional purposes, it had considered certain
factors to be particularly relevant. These included information related to
experiences on the land shared with the Panel by some Aboriginal persons which suggested
that there has been some decline in the practice of traditional land and
resource use practices in recent time; that the intensity of traditional
activities practiced within the Project area varies across the various
Aboriginal groups, but the area does not appear to be a prime area for land and
resource use activities, with mostly intermittent and sporadic use relative to
other areas outside of the assessment area; and, that the absence of negotiated
consultation agreements with certain Aboriginal groups led to the JRP receiving
limited and imprecise information with respect to current Aboriginal land and
resource use within the Project area.
[179] The JRP then listed its findings and recommendation in connection
with each Aboriginal group. For the NCC this was:
Inuit-Metis
The Panel recognizes that it received only
limited information during the review process about current land and resource
use activities for traditional purposes in the Project area by Inuit-Metis.
While some efforts were achieved initially when the first phase of a
consultation agreement to facilitate information gathering was agreed upon by
the NunatuKavut Community Council and Nalcor, late participation of the
NunatuKavut leadership in the public hearing due to their interlocutory injunction
application limited their input into the review process. The Panel also
recognizes that the NunatuKavut Community Council’s lack of resources prevented
it from submitting substantial information after it started participating in
the public hearing. During the public hearing, most information was received
from individual Inuit-Metis participants, rather than from the organization,
and the Panel notes that affiliation of participants could not always be
confirmed.
The Panel notes that the main land and
resource use activity practiced by NunatuKavut members, which has persisted for
two centuries, is trapping and measures considered to mitigate the effects of
the Project on trapping activities and to compensate for losses of trapping
income, property or equipments attributed to the Project (Recommendation 8.1)
might be particularly relevant to Inuit-Metis trappers. The Panel also observes
that many land and resource use locations reported to be frequented by
Inuit-Metis are outside of the Project area and would remain unaffected and
accessible.
Based on the information on current land
and resource use identified through the environmental assessment process, there
are uncertainties regarding the extent and locations of current land and
resource use by the Inuit-Metis in the Project area. The Panel recognizes that
additional information could be forthcoming during government consultations. To
the extent that there are current uses in the Project area, the Panel concludes
that the Project’s impact on Inuit-Metis land and resource uses, after
implementation of the mitigation measures proposed by Nalcor and those
recommended by the Panel, would be adverse but not significant.
[Emphasis added]
[180] Importantly, the JRP found that its significant finding in Chapter 8,
with respect to the Project’s effect on fishing and seal hunting in Goose Bay
and Lake Melville, would apply to traditional harvesting activities by Labrador
Inuit, including the harvesting of country food in this area should
Project-related consumption advisories be required. The JRP did not make a
similar finding with respect to the Inuit-Metis or any other Aboriginal group.
[181] It is also of note that in its findings concerning Quebec Aboriginal
groups, the JRP recognized, as it did with respect to the Inuit-Metis, that it
received only limited information during the review process regarding current
land and resource use activities for traditional purposes in the Project area.
In that case this was due to the fact that Nalcor and the Aboriginal groups were
unable to conclude consultation agreements, with the exception of the Council
of the Innu of Pakua Shipu. In addition, time constraints during the hearing
period did not allow the Panel to travel to each community in Quebec.
[182] However, like its treatment of the NCC, the JRP concluded that
although there were uncertainties regarding the extent and locations of current
land and resource use by Quebec Aboriginal groups in the Project area, and that
additional information could be forthcoming during government consultations, to
the extent that there are current uses in the Project area, the Project’s
impact on Quebec Aboriginal land and resource uses, would be adverse but not
significant. In other words, the NCC was not singular in the JRP’s findings
that available information regarding current land use activities for
traditional purposes in the Project area was limited. Regardless, and
recognizing that further information might be forthcoming during consultation
subsequent to the issuance of its report, it concluded that the Project impact
on land and resource use would be adverse but not significant.
[183] In Chapter 10, Aboriginal Rights and Title, the JRP noted that in
accordance with its mandate, it invited Aboriginal persons or groups to submit
information related to the nature and scope of potential or established
Aboriginal rights or titles in the area of the Project, as well as information
on the potential adverse impacts or potential infringement that the Project
would have on asserted or established Aboriginal rights or titles. Information
on Aboriginal rights and titles was received by the JRP through testimony
during the public hearings and written submissions. A summary of that
information was provided. Further, Appendix 7 contains a list of documents
received from each Aboriginal group with information relative to their
respective Aboriginal rights and title. In accordance with its mandate, the
JRP did not come to any conclusions or make any recommendations with respect to
this information. However, it is significant that while acknowledging that
further information might be forthcoming, the JRP was able to make a
determination that the impact on the NCC’s land and resource use would be
adverse but not significant.
[184] From the foregoing it is clear that the JRP process was the primary
mechanism by which Aboriginal groups could identify their concerns about
potential adverse Project impacts on their Aboriginal rights or title. The NCC
was aware of this. It received funding to address these issues in the JRP
process. While it may not be satisfied with the level of funding, I am unable
to conclude that this precluded the NCC from meaningfully participating in the
JRP process. And, to the extent that it elected not to do so but to instead
pursue its injunction, it was aware of the risk that it took by not taking full
advantage of that process and, ultimately, it did make limited submissions.
[185] It is true that the JRP acknowledged that there were uncertainties
regarding the extent and locations of current land use in the Project area.
However, the NCC also received funding in Phase 4 which concerned consultation
on the JRP Report. In its funding application for Phase 4 the NCC described
the proposed activities for which it was seeking funding which included holding
meetings to collect traditional knowledge. The funding received, $21,000,
served to permit consultation on the JRP Report and its recommendations – which
acknowledged the land use uncertainties – as well as to establish whether
potential Project impacts on Aboriginal or treaty rights had been addressed,
recommended mitigation measures and any remaining outstanding items. Being
aware of the JRP’s findings regarding current land and resource use, the NCC
was in a position to substantively address that alleged knowledge gap at Phase
4 by providing further information, but did not choose to do so.
[186] The NCC’s comments on the JRP Report were set out in its November 9,
2011 submission. It alleged that:
−
The JRP process was impaired by Canada and the Province’s failure to engage separately with the NCC prior to the JRP
process;
−
Aboriginal and treaty rights were not adequately
considered, and the obligation to consult and accommodate had not been met;
−
The Province and Nalcor were indistinguishable
and the Province was biased and intent on obstructing consultation;
−
The JRP discriminated against the NCC and gave
preferential treatment to other Aboriginal groups;
−
The JRP recognised that the NCC required
additional time and financial resources to investigate more fully current land
and resource use but failed to make a recommendation in that regard. Further,
resources were still unavailable to conduct proper studies;
−
The JRP applied a Eurocentric world view to its
consideration of what constitutes traditional land use which was prejudicial
and an error of law;
−
The JRP did not exercise its TOR as it failed to
insist that the NCC be provided with funding and that proper work on Aboriginal
Traditional Knowledge be carried out;
−
As to accommodation, the JRP should have
required that licenses and permits issued to Nalcor be conditional on adequate
consultations, financial accommodations and impact- benefit arrangements and
royalty sharing;
−
The JRP abdicated its jurisdiction and
responsibility to consider Project alternatives and to assess cumulative
effects;
−
Nalcor was not candid and kept information from
the JRP that was contrary to its interests and misrepresented information
received from the NCC or its members:
NCC completed its contractual expectations
by delivering information to Nalcor and then, when Nalcor did not present that
information fairly and completely, lacked the resources to re-present the
material directly to the JRP. As a result, the data before the JRP with
respect to the NCC communities was seriously flawed.
−
Further, that Nalcor had failed to engage the
NCC at any level during the assessment.
[187] Many of these concerns had already been addressed by Justice
Handrigan in his decision denying the NCC’s injunction and were later addressed
by Justice Near in Grand Riverkeeper. But what is significant for the
purpose of this judicial review is the absence of a substantive response to the
alleged lack of information concerning Aboriginal Traditional Knowledge and current
land and resource use information when Phase 4 funding was provided and could
have been directed to that issue. Even if the funding was not at a level that
the NCC might have wished, given the importance that it places on this issue,
it would have permitted at least some form of substantive response to factually
ground its concerns. And, if the NCC felt that the data it gathered with the funding
received from Nalcor was inaccurately presented by Nalcor to the JRP, it could
have presented the information at Phase 4 and explained the basis of its
concerns. As that research had previously been funded, there would have been
little or no cost restriction in that regard.
[188] In summary, the NCC has not identified how much additional funding
it would have required at Phase 5 to address Aboriginal Traditional Knowledge
and current land and resource use. However, it had been provided with funding
that was or could have been used for that purpose in Phases 1-4. Further, the
JRP process was the primary mechanism by which Canada was to effect
consultation with Aboriginal groups. Therefore, it was incumbent upon the NCC
to fully utilize that process. If, at Phase 4, it remained unsatisfied as to
the lack of information concerning Aboriginal Traditional Knowledge and current
land and resource use it could, at that phase, made some effort to further
factually address its concerns; specifically, to address, at least at a
preliminary level, the uncertainty identified by the JRP. However, no
substantive submission was made in that regard. The NCC also does not explain
how the alleged gaps in such knowledge and information affected the Phase 5
consultation, which is concerned, in particular, with the FHC and EEM Plans.
For all of these reasons, I am unable to conclude that the NCC has established
that a lack of funding at Phase 5 precluded it from presenting necessary
Aboriginal Traditional Knowledge and current land and resource use information
which resulted in a lack of meaningful consultation during that Phase.
[189] As to the doctrine of legitimate expectations, in my view the NCC’s argument
on this point cannot succeed. The Supreme Court laid out the test for
legitimate expectations in CUPE v Ontario (Minister of Labour), 2003 SCC
29 at para 131:
The doctrine of legitimate expectation is
“an extension of the rules of natural justice and procedural fairness”: Reference
re Canada Assistance Plan (B.C.), [1991] 2 S.C.R. 525, at p. 557. It looks
to the conduct of a Minister or other public authority in the exercise of a discretionary
power including established practices, conduct or representations that can be
characterized as clear, unambiguous and unqualified, that has induced in the
complainants (here the unions) a reasonable expectation that they will retain a
benefit or be consulted before a contrary decision is taken. To be
“legitimate”, such expectations must not conflict with a statutory duty. See:
Old St. Boniface Residents Assn. Inc. v. Winnipeg (City), [1990] 3 S.C.R.
1170; Baker, supra; Mount Sinai, supra, at para. 29; Brown and
Evans,supra, at para. 7:2431. Where the conditions for its application
are satisfied, the Court may grant appropriate procedural remedies to respond
to the “legitimate” expectation.
[190] As stated in Agraira at para 94, if a public authority has
made representations about the procedure it will follow in making a particular
decision, or if it has consistently adhered to certain procedural practices in
the past in making such a decision, the scope of the duty of procedural
fairness owed to the affected person will be broader than it otherwise would
have been.
[191] In its written submissions, the NCC states that its legitimate
expectations regarding funding, and other matters, are informed largely by the
JRP process. However, the NCC does not point to anything within that process
that can be characterized as clear, unambiguous and unqualified and that
induced in the NCC a reasonable expectation that they would receive Phase 5
funding. Rather, the NCC simply states that as it received funding for Phases
1 to 4, its expectation as to Phase 5 is legitimate. In my view this does not
meet the test for legitimate expectations. As the EA process concluded at
Phase 4, it is unsurprising that funding for Phase 5, the regulatory
permitting phase, would not have been addressed by the JRP or the PFP.
[192] Further, the Participant Funding Program Review Report for Phase 2
of the EA process contains no mention of further or future funding to be
provided and the Funding Report for Phase 4 is virtually identical. Nor
has the NCC provided any evidence that a similar funding application process
for Phase 5 funding was contemplated.
[193] In short, the record contains no evidence that the Minister
represented in a clear, unambiguous and unqualified manner, or in fact in any
manner, that funding for Phase 5 would be provided. Nor did the NCC provide
evidence that there is a practice of providing Phase 5 funding that would give
rise to such an expectation. Accordingly, the NCC’s submission as to
legitimate expectations cannot succeed.
[194] The NCC also submits that the lack of Phase 5 funding prevented it
from adequately reviewing and commenting on what it describes as the highly
technical FHC and EEM Plans. As a result, the NCC could not meaningfully
participate at this stage of the consultation. As noted above, the NCC has at
no time indicated what level of funding it would have required in this regard.
[195] The FHC Plan describes itself as outlining Nalcor’s plan to offset
fish habitat loss and harmful alteration caused by the Project through a series
of physical habitat creations and enhancements that will be added to the
predicted use of the reservoir by resident fish, together with a detailed
adaptive monitoring program to measure function, effectiveness and to direct any
required mitigations.
[196] It is also of note that the roots of the FHC Plan existed prior to
Phase 5. The Chapman Affidavit indicates that Nalcor recognized that a FHC
Plan would be required in order to obtain the Authorization and that its
development started in 2006. The first step was the development by AMEC,
engaged by Nalcor, of a Fish Habitat Compensation Framework for submission to
DFO. This was also submitted to the JRP by way of response to IR# JRP.107. In
May 2010, the Fish Habitat Compensation Strategy was completed. This was
provided to the JRP by Nalcor in respect to IR# JRP.153. The Nalcor submission
on its Fish Habitat Compensation Strategy states that it provides habitat
requirements for fish species present and demonstrates how these will be met
through habitat creation and enhancement, the intent being to sustain, to the
extent possible, the existing and natural patterns of fish habitat
utilization. Values attributed to fish and fish habitat by the public,
Aboriginal groups and other stakeholders were identified as part of its
development and would continue to be incorporated in the future work on the FHC
Plan.
[197] Fish habitat compensation workshops were held by Nalcor in April
2009. A representative of the NCC attended each of the two Fish Habitat
Compensation workshops held in Happy Valley – Goose Bay on April 7, 2009.
Exhibit KKK of the Chapman Affidavit contains notes from the workshops, the
objective of which is stated to be to gain input from people that use and are
knowledgeable about the river or are familiar with fish habitat compensation
measures. A PowerPoint presentation provided an overview of the process,
existing information and the approach of the strategy and raised questions for
discussion, such as the importance of preferred species, angler access,
preferred rivers for downriver enhancements, etc.
[198] Additional workshops were held in St. John’s, Newfoundland on March
12, 2010 and in Happy Valley – Goose Bay on March 23, 2010. Nalcor prepared a
summary of questions, comments and concerns arising from these, based on the
minutes of those meetings. The NCC does not appear to have attended, although
various other stakeholders did, such as Grand Riverkeeper, the Innu Nation and
others.
[199] On December 21, 2012, Nalcor wrote to the NCC advising that it
intended to consult with stakeholders concerning the draft FHC Plan and EEM
Plan. This letter extended an offer to meet with representatives of the NCC to
offer a briefing on the FHC Plan. It also extended an invitation to the NCC to
attend a public information session in Happy Valley - Goose Bay on January 16, 2013 when the plan would be discussed. Nalcor enclosed a copy of the FHC
Plan for the NCC’s review. The letter stated that the FHC Plan was an important
mitigation strategy for the Project effects and that Nalcor looked forward to
engagement with the NCC. It also stated that if the NCC had any questions or
required further information, it could contact Nalcor to discuss the matter
further. The Bennett Affidavit states that the NCC did not respond to this
offer to meet.
[200] On January 16, 2013, Nalcor hosted a public information session to
present the draft FHC and EEM Plans. Representatives of the NCC attended the
information session and the Summary Report of that session indicates that the
draft FHC Plan was posted on Nalcor’s website at that time.
[201] As to the EEM Plan, the Bennett Affidavit states that AMEC was
engaged to prepare the plan which focuses on predictions made in the EA, and is
designed to verify the environmental effect predictions and determine the
effectiveness of mitigation measures.
[202] With regard to DFO’s consultation in Phase 5, as set out above in
the background facts, on May 9, 2012 at the NCC’s request, its representatives
met with those of DFO’s to discuss the regulatory permits. At that time a
number of issues were raised, including that the NCC had no resources to review
or respond to the permitting, and DFO advised that it could not provide such
resources.
[203] By letter of June 1, 2012, DFO advised that prior to the issuance of
the Authorization it would consult with Aboriginal groups, including the NCC,
and that an Aboriginal consultation protocol governing that process was being
developed and would be provided to the NCC for comment.
[204] On July 9, 2012, DFO wrote to the NCC advising that, pursuant to the
Consultation Framework, the Project was now entering the regulatory
permitting phase and proposed to conduct the Phase 5 consultations in
accordance with the attached draft Regulatory Phase Protocol. DFO
sought comments on the process within 14 days.
[205] Although the NCC did respond, more than 30 days later, its August 8,
2012 email reply did not substantially address the proposed Regulatory Phase
Protocol. Instead, it made the following comments, and stated these were
all of its comments at that time:
– We would like to have a protocol put in place to share/review
NCC’s aboriginal traditional knowledge;
– We would like more emphasis placed on aboriginal traditional
knowledge;
– As well as, a clear definition of the project in the footprint
area.
[206] The draft FHC Plan was provided to the NCC by Nalcor on December 21,
2012. Both the draft FHC and EEM Plans were provided to the NCC on February 28,
2013 by DFO which also stated that detailed biological and engineering designs
associated with the plans “are provided in the Fish
Habitat Compensation Plan and Environmental Effects Monitoring Plan which can
be accessed on the Nalcor’s website at
http://nalcorenergy.com/news-and-publications.asp”. Pursuant to the Regulatory
Phase Protocol, DFO sought comments, within 45 days, and noted that the NCC
could request a meeting within 10 days if necessary to discuss the plans with
DFO. DFO also stated that it would provide a written response to such comments.
[207] The NCC responded on April 15, 2013, but did not provide comments on
the FHC Plan or EEM Plan. It stated, amongst other things, that the NCC did
not accept the Regulatory Phase Protocol, that the 45 day review period
was unreasonable, that there had been an absence of procedural engagement with
the NCC in preparing the plans, that no resources had been provided for Phase
5, and that there had been no direct consultation with the NCC in relation to
the proposed Authorizations.
[208] The letter also stated that none of the agencies or companies
holding a direct or delegated duty to consult in relation to the Authorization
had met with the NCC directly on its concerns. The NCC sought a meeting to
discuss its concerns as to non-compliance by the proponent and inadequacies in
consultation and accommodation. It attached a table listing certain of the JRP
recommendations, and deficiencies in response to them, as identified by the
NCC.
[209] The FHC Plan is, undoubtedly, a technical document. The question
is, did a lack of funding for Phase 5 preclude meaningful consultation. While
it certainly would have been preferable if further funding had been provided at
this stage, I am not convinced that without it there could be no meaningful
consultation. The NCC was aware that Phase 5 funding would not be provided.
It was provided with opportunities to meet with Nalcor to discuss the FHC and
EEM Plans. While Nalcor, as the Project proponent, may not have been viewed by
the NCC as an independent source of information, it could at least have sought
to have Nalcor explain the technical aspects of the FHC Plan to ascertain
whether or not it adequately addressed and mitigated the NCC’s interests, in
particular, being any adverse impact on its current land and resource use.
[210] Similarly, although DFO was not able to provide Phase 5 funding, it
effected and followed the Regulatory Phase Protocol and offered the NCC
the opportunity to comment on that process. That encompassed the opportunity
for the NCC to request a meeting within 10 days of receipt of the draft plans.
The NCC did not make such a request, although it did subsequently challenge the
protocol process and sought a meeting. DFO had no self interest in the Plans
and it was in a position to provide the NCC with technical expertise in
interpreting them. With such information, the NCC could have determined whether
or not the FHC Plan was deficient in mitigating any adverse Project effects on
its interests in the affected fish resources. It is also of note that the Affidavit
of Ray Finn, Regional Director of Ecosystems Management, Newfoundland and
Labrador Region, DFO, sworn February 5, 2014 in support of DFO’s position in
this application, states that he was advised that at the May 9, 2012 meeting
requested by the NCC to discuss regulatory permitting, the NCC was told that,
although DFO could not provide Phase 5 funding, it could meet as required to
discuss the documents.
[211] The Todd Affidavit states that the NCC does not have the technical
expertise or the resources to interpret the Plans. However, as Canada and Nalcor point out, the NCC was able to find resources to bring an injunction and
later an application for judicial review of the JRP decision as well as this
current application. In my view, it would not seem unreasonable, therefore,
for it to have engaged a consultant, if necessary, to provide technical advice,
and, at least at a preliminary level, to determine if the FHC and EEM Plans
sufficiently mitigated any adverse impact, or were deficient, in the context of
the NCC’s claimed land and resource use.
[212] As stated in Halfway River First Nation:
[161] There is a reciprocal duty on
aboriginal peoples to express their interests and concerns once they have had
an opportunity to consider the information provided by the Crown, and to
consult in good faith by whatever means are available to them. They cannot
frustrate the consultation process by refusing to meet or participate, or by
imposing unreasonable conditions: see Ryan v. Fort St. James Forest District
(District Manager) (January 25, 1994), Doc. Smithers 7855, 7856 (B.C.
S.C.); affirmed (1994), 40 B.C.A.C. 91 (B.C. C.A.).
[213] By not making at least some effort to assess the FHC and EEM Plans,
either by way of the offered meetings with Nalcor or DFO or by utilizing its own
resources to instruct and retain a consultant to provide preliminary advice,
the NCC has failed to provide any evidence both that there was a failure to
adequately consult and a resultant adverse impact on its rights and title.
[214] For these reasons, I am not satisfied that a lack of funding at
Phase 5 precluded meaningful consultation.
[215]
The NCC also submits that there was an absence
of good faith and meaningful consultation at Phase 5 as demonstrated by an
internal DFO memorandum and the delayed response of DFO to the NCC’s comments
on the JRP Report and the Regulatory Phase Protocol.
[216] The referenced memorandum is dated February 5, 2013. It was
prepared for the DFO Regional Director General, NL Region, addresses the status
of Aboriginal consultations for Phase 5, and was updated on February 21, 2013.
The updated memorandum states that comments received in response to the
proposed Regulatory Phase Protocol “predictably” indicated that some
Aboriginal groups still had concerns about the EA that they felt had not been
addressed and that “close the loop” letters were being prepared in response:
“Close the loop” letters will be sent prior
to sending the finalized regulatory phase consultation protocol. DFO expects to
send the letters and protocol to Aboriginal groups by the end of February 2013
and commence consultation immediately afterwards.
[217] During the hearing before me, the NCC advised that it no longer
asserted that these memorandums were indicative of bad faith. They did,
however, indicate a lack of meaningful consultation.
[218] When seen in the context of the document in whole, this reference is
not, in my view, indicative of bad faith or condoning perfunctory responses to
Aboriginal concerns. Rather, the phrase is used in the context of the
preparation of future communications to Aboriginal groups to address their
outstanding concerns.
[219] More troublesome is Canada’s delay in responding to the NCC. The
NCC received Canada’s reply to their November 9, 2011 comments on the JRP
Report and their August 8, 2012 comments on the draft Regulatory Phase
Protocol on June 28, 2013. The NCC submits that this appears to be the
“close the loop” letter and came a year and a half after its comments on the
JRP Report were submitted, almost a year after its comments on the draft Regulatory
Phase Protocol were submitted and only days before the Authorization was
issued. The NCC submits that waiting until the last moment, days before
issuing the Authorization, to send a letter which responds to, but does not
address, concerns raised in the consultation process is not meaningful and good
faith consultation.
[220] However, in my view, Canada’s June 28, 2013 letter cannot be viewed
in isolation. As noted above, the NCC’s comments on the JRP Report were wide
ranging. They alleged that the JRP discriminated against the NCC, that it did
not live up to its TOR, that it failed to consider alternatives to the Project,
that there was a lack of candor on the part of Nalcor and other matters. The
letter made few comments that concerned specific issues raised and
Recommendations made by the JRP. Thus, while Canada certainly did not respond
to it in a timely manner, given that the comments were made in Phase 4 while a
response was not provided up until Phase 5, viewed in context, I am not
convinced that the delay amounted to a lack of good faith or meaningful
consultation.
[221] As to the NCC’s August 9, 2012 email responding to the draft Regulatory
Phase Protocol, as noted above, this did not provide substantive comments
on the proposed protocol. Further, by letter of February 21, 2013, Canada
advised that comments not directly relating to the protocol would be addressed
in a follow-up letter to follow shortly and that comments on the protocol had
been fully and fairly considered and were reflected in the final version of the
protocol, which was provided with that letter.
[222] In that regard, in its June 28, 2013 letter, DFO specifically
addressed the NCC’s view that a clear definition of the Project and the footprint
had not been provided, advising that both were defined during the EA. As to
the NCC’s concern that more emphasis should be placed on Aboriginal Traditional
Knowledge and that a protocol be put in place to share/review the NCC’s
Aboriginal Traditional Knowledge, DFO responded as follows:
DFO and other federal authorities developed,
in collaboration with aboriginal groups, a protocol for consulting with
aboriginal groups during the regulatory phase of the Project. This protocol
provides the opportunity for meetings, at which Aboriginal groups could share
Aboriginal traditional knowledge with regulatory authorities for review and
consideration in the issuance of permits or approvals. DFO offered such
meetings to the NCC on February 28, 2013 for the authorizations being prepared
for the Muskrat Falls site, and will offer meetings similarly for any future
authorizations for the Project.
Prior to submitting a Fish Habitat
Compensation Plan, as well as an Environmental Effects Monitoring Plan, to DFO,
Nalcor Energy (Nalcor) as a proponent may also offer to meet with Aboriginal
groups. At that time, groups can share traditional knowledge with Nalcor so
that it can be incorporated into the plans prior to submission.
[223] Given the delay in receiving this letter and its proximity to the
issuance of the Authorization on July 9, 2013, the NCC’s submission that this
was not meaningful consultation is not without merit. However, when the letter
is viewed together with other correspondence between Canada and the NCC, and well
as the opportunities in Phase 5 to relay their Aboriginal Traditional
Knowledge, I cannot conclude that this constitutes a breach of the duty to
consult or a lack of meaningful consultation.
[224] For example, on April 15, 2013, the NCC sent DFO a letter citing its
concerns with, among other things, the protocol for Phase 5, its lack of
resources for consultation during this Phase and its need to have more time for
review.
[225] DFO responded soon after, on May 31, 2013. It noted that it gave
full and fair consideration to the comments provided on the draft Regulatory
Phase Protocol, including those of the NCC; that by Canada’s letter of
February 28, 2013, the NCC had been offered an opportunity to request a meeting
with DFO to discuss the FHC and EEM Plans prior to the submission of comments,
but that such a request had not been made; and its view that Nalcor had
provided the NCC an opportunity to meet with Nalcor to discuss the FHC Plan,
but such a meeting did not take place, and Canada’s obligations had, therefore,
been fulfilled in that regard. The letter also responded to the NCC’s view that
JRP Recommendations 6.7 and 6.9 had not been addressed.
[226] And, as described above, on January 16, 2013, Nalcor hosted a public
information session in Happy Valley - Goose Bay to present its draft FHC and
EEM Plans and gather input from interested stakeholders. A letter was sent,
prior to the event, notifying the NCC of the session and offering to meet with
the NCC. However, the NCC did not respond to that opportunity.
[227] And, on February 28, 2013, DFO sent a letter to the NCC, asking for
input on Nalcor’s FHC and EEM Plans. In accordance with the Regulatory
Phase Protocol, it notified the NCC that it could request a meeting with
DFO to discuss the documents within the first 10 days of receiving the Plans
and that such a meeting must be held within the 45 day review period. The NCC
did not request such a meeting until the period had passed at which time, by
way of its April 15, 2013 letter, it also challenged the consultation process
as set out in the Regulatory Phase Protocol.
[228] Thus, while Canada could certainly have acted with greater
expediency in addressing some of the NCC’s concerns, considering the above, I
am not convinced the delay in response indicates a lack of good faith or that Canada did not adequately or meaningfully consult with the NCC during Phase 5. The
consultation process must be reasonable, not perfect (Ekuanitshit FC at
para 131).
[229] In my view, the Regulatory Phase Protocol clearly identified
how the consultation process for Phase 5 would proceed. DFO provided the NCC
with a draft of the proposed protocol for its comment. Although the NCC did respond,
its comments were not responsive to the proposed process. DFO proceeded in
accordance with the finalized Regulatory Phase Protocol, which had been revised
in response to other comments received with respect to the draft document.
And, as set out above, DFO addressed three issues raised by the NCC, albeit not
to its satisfaction.
[230] The NCC also submits that a lack of good faith and meaningful
consultation is demonstrated by Canada’s imposition of the Regulatory Phase
Protocol on it, without incorporating the NCC’s feedback, and that it
received the final form of the protocol midway through the process, after much
of Nalcor’s work on the FHC and EEM Plans was complete.
[231] In my view, this submission lacks merit. As set out above, Canada provided the draft Regulatory Phase Protocol to the NCC for comment in July
9, 2012 and sought comments within 14 days. On August 8, 2012, the NCC
responded but did not provide substantive comments on the protocol. Canada provided the final form of the Regulatory Phase Protocol on February 21,
2013. Canada then proceeded in accordance with the process set out in the Regulatory
Phase Protocol. It is true that by its letter of April 15, 2013, after it
had been provided with the draft FHC and EEM Plans for review, the NCC then
asserted that the Regulatory Phase Protocol was unacceptable to it.
However, this does not support a view that the protocol was forced upon it.
Further, it is clear from the record that the Plans required much background
work and were being developed long before the commencement of Phase 5, the
purpose of which was to review and comment on the completed draft Plans.
Accordingly, the fact that work on these Plans had been done prior to the
drafts being provided to the NCC pursuant to the Regulatory Phase Protocol
is not indicative of a lack of good faith or failure of Canada’s duty to consult.
[232] In my view, viewed in context, the Phase 5 consultation process was
adequate, if not perfect, and Canada satisfied its duty to consult.
[233] The NCC submits that the JRP process was relied upon heavily by Canada in fulfilling its consultation obligations. The JRP Recommendations were one of the
main measures for mitigating the impacts of the Project and, therefore, an
important accommodation measure. As such, a failure to follow the JRP Recommendations
is a failure of accommodation.
[234] In particular, Nalcor was not required to follow Recommendation 6.7
and to carry out a comprehensive review of downstream effects prior to
impoundment, with third party expert review, and a discussion workshop involving
Aboriginal groups. As a result, the downstream effects of the Project have
never been properly studied, and there remains a substantial risk of serious
downstream effects, including methylmercury contamination of fish, seals, birds
and humans.
[235] Although Canada accepted the intent of Recommendation 6.7, the
required actions of baseline sampling and monitoring, which are directed at
identifying problems in the future as they arise, is different than carrying
out a comprehensive review prior to impoundment, which is directed toward
identifying problems before they start. As a consequence, the NCC argues that
baseline sampling and monitoring fulfils Recommendation 6.9, the development of
an aquatic monitoring program, but not Recommendation 6.7.
[236] This is compounded by the fact that the JRP recommended full
clearing of the reservoir, yet Nalcor has only been required to conduct partial
clearing. This necessarily results in higher levels of methylmercury
contamination, the impact of which has not been appreciated by the Minister.
[237] The NCC submits that while the Minister was not bound by the JRP
Recommendations, given the importance that Canada placed on the JRP process in
fulfilling its duty to consult obligations, they should not be taken lightly.
Here the Minister is departing from the Recommendations without explicitly
acknowledging that she is doing so, without providing reasons for doing so and
in a manner that creates an elevated risk of methylmercury contamination. The
decision to issue the Authorization is, for these reasons, unreasonable.
[238] The NCC also submits that, with respect to the FHC Plan, the Minster
ignored the science available to her, including that of DFO scientists,
regarding the lack of effectiveness of DFO’s fish habitat compensation programs
in actually reaching “no net loss” of fish habitat, as recognized by the JRP.
Because DFO provided no information on the measures being taken to improve the
effectiveness of the program it was, in effect, knowingly adopting an
ineffective mitigation measure. Accordingly, the decision to issue the
Authorization was not reasonable.
Canada’s
Position
[239] Canada takes the view that the NCC’s primary
allegation is that the Authorization is unreasonable because the monitoring and
mitigation measures required by the Authorization are unlikely to be
effective. Canada submits that this is an impermissible attack on the science
underpinning the Authorization and is contrary to the principle that the Court
is not to be turned into an “academy of science”. The Court’s role is to
determine whether the Authorization rests on a reasonable basis, and not
whether its measures will be effective (Ekuanitshit FC at para 94). The
standard of review is reasonableness and considerable deference is owed
regarding the effectiveness of the plans (Grand Riverkeeper at paras
27-39). Canada also asserts that the NCC’s argument is an unacceptable
collateral attack on the Order-in-Council.
[240] Further, that all of the JRP Recommendations noted by the NCC were
implemented, although Recommendations 4.5 and 6.7 were not implemented
precisely as recommended by the JRP. Regardless, the Authorization conditions
concerning baseline sampling, monitoring and habitat compensation are
reasonable.
[241] Nalcor conducted its analysis in this regard in the context of
considering whether the Minister’s decision to issue the Authorization
constituted an abuse of discretion as a failure to consider a relevant ground.
Nalcor submits that where legislation is silent as to the factors that an administrative
decision-maker must take into consideration, as is the situation here, the
decision-maker has the discretion to determine the appropriate factors (Guy
Regimbald, Canadian Administrative Law, 1st ed (Markham: LexisNexis
Canada, 2008 at pp 190); Electric Power & Telephone Act (PEI), Re
(1994), 109 DLR (4th) 300 at para 15).
[242] Nalcor submits that the RAs and the Governor-in-Council were
required to consider the JRP Report and carry out their ss 37 and 37.1 duties.
Canada’s Response accepted, accepted with modifications or rejected the
Recommendations. This was approved by the Governor-in-Council, which mandated
what Recommendations and mitigation measures were required. The NCC did not
seek judicial review of Canada’s Response. In the exercise of her discretion
the Minister is guided by the Fisheries Act, Canada’s Response and the CEAA.
This means that she was required to follow the direction contained in the JRP
Report. In the event of conflict, the Order-in-Council and the CEAA
prevail.
[243] There was no obligation on the Minister to implement Recommendation
4.5. The factors for consideration were within her discretion and she
reasonably excluded reservoir clearing as a requirement. A direction to fully
clear the Muskrat Falls reservoir is also ultra vires the Minister, as
it would encroach on the jurisdiction over forestry of the Province. Further,
Nalcor considered the question of reservoir clearing and is proceeding with
“partial clearing”. In Nalcor’s view, there is a negligible difference in predicted
methylmercury levels between full and partial clearing. It also took into
consideration other factors such as safety, logistics, fish habitat, greenhouse
gas emissions and economics.
[244] As to Recommendation 6.7, the requirements of Canada’s Response have been incorporated into the FHC and EEM Plans and, therefore, the
Authorization. There is also no evidence to support the NCC’s argument that
the Minister is adopting a fish habitat compensation program that she knows
will not be effective. Canada’s Response to Recommendation 6.6 required Nalcor
to develop and implement a compensation plan that will include a multi-year
habitat monitoring strategy with thresholds identified for further action and,
if required, reporting processes and adaptive management measures. Nalcor
asserts that it must adjust the FHC Plan, if necessary, to ensure
effectiveness.
[245]
The NCC asserts that by declining to implement
Recommendation 6.7, the downstream effects on the Project have not been
properly studied. This creates a risk with regard to downstream methylmercury
contamination. The EEM and FHC Plans, as conditions of the Authorization, do
not remedy this defect and, therefore, the NCC’s concerns were not
accommodated. This is compounded by the failure to implement full clearing as
per Recommendation 6.5. In Nunatsiavut, I described in detail
Recommendation 6.7, primarily in the context of methylmercury bioaccumulation.
The NCC’s position results in a similar analysis.
[246] Chapter 6 of the JRP Report, Aquatic Environment, addressed a number
of issues including methylmercury in the reservoirs and downstream. As to the
fate of mercury in the reservoirs, the JRP set out the views of Nalcor and the
participants. Nalcor included a description of how reservoir formation leads
to the release of methylmercury into the aquatic environment. Specifically,
that when soils in reservoir areas are flooded, bacterial breakdown of the
vegetation causes methylation, a chemical process that converts inorganic
mercury in the soils to methylmercury, a more toxic form. Methylmercury then
enters the aquatic ecosystem accumulating in aquatic animals mostly when they
feed on organisms with elevated mercury. The concentration of methylmercury
increases upward through the food chain (referred to as bioaccumulation)
resulting in higher concentrations in predatory fish, in animals such as otters
or seals that eat fish, and potentially in humans. Typically, as shown in
experience from other reservoirs in boreal regions, mercury levels in fish peak
5 to 16 years after flooding and then gradually decrease to background levels
over 30 or more years. Nalcor’s modeling predicted that mercury concentrations
would peak within 5 years after flooding, declining to baseline levels within
35 years.
[247] The JRP noted that Nalcor’s proposed mitigation and monitoring
related to methylmercury included monitoring fish mercury concentrations
annually for the first 10 years following inundation to verify predictions.
Monitoring frequency could then be adjusted depending on results.
[248] As to the participants, the JRP noted that both EC and NRC concluded
that Nalcor had modelled mercury increases in the lower Churchill River
appropriately. DFO also stated that Nalcor’s predictions about mercury levels
were consistent with the current state of knowledge but questioned the accuracy
of Nalcor’s predictions regarding the magnitude and duration of methylmercury
in the lower Churchill River. DFO therefore recommended that Nalcor develop a
comprehensive program to monitor spatial and temporal changes in mercury in
fish within the reservoirs and downstream, including at Goose Bay, following reservoir creation. The frequency and timing of sampling should be sufficient
to support a clear assessment of the magnitude and timing of these changes, and
inform determinations of risks to human health and implementation of related
fisheries management measures. Further, that more baseline data should be
collected on mercury levels in estuarine fish downstream of Muskrat Falls and in Goose Bay in advance of inundation.
[249] Recommendation 6.7 addressed downstream effects including flow
dynamics, water quality, productivity and mercury. The JRP again set out
Nalcor’s position as well as those of the participants.
[250] Nalcor predicted that mercury levels would increase after
impoundment in water and plankton downstream to the mouth of the river and into
the Goose Bay narrows. Methylmercury levels would increase in fish downstream
to and including Goose Bay, but levels would be lower compared to fish in the
reservoirs with the exception of piscivorous fish feeding below the tailrace of
Muskrat Falls. Mercury would not be detectable beyond Goose Bay because concentrations in the water would be gradually diluted, sediments would settle, and
plankton and zooplankton die-off before or at the saltwater interface. Effects
of elevated mercury levels associated with piscivores feeding on entrained fish
would only be seen fairly close to the tailrace area below Muskrat Falls. In any
case, Nalcor predicted that at no time would fish methylmercury reach a level
to affect fish health or behaviour at a population level. Peak methylmercury
levels were expected to return to baseline levels within 35 years.
[251] Nalcor stated that a more extensive assessment of the cumulative
effects of mercury levels associated with the Churchill Falls hydro-electric
project was not necessary. Nalcor acknowledged some uncertainties associated
with its modelling and the state of knowledge about bioaccumulation and the
fate of mercury in the ecosystem that limited its ability to make accurate
predictions of potential increases in methylmercury in Lake Melville. However, Nalcor said its methylmercury modelling in the downstream environment was
sufficient for planning and assessment purposes. Further, that its modeling
approach provided the necessary level of predictive capacity required to
determine downstream methylmercury concentrations. This would be backed up by
Nalcor’s commitment to monitor the follow-up to verify protection, address
uncertainty and incorporate adaptive management. Nalcor’s proposed mitigation
measures included working with Aboriginal stakeholders to monitor mercury in
fish and seals downstream of Muskrat Falls and collecting more baseline data on
mercury levels in estuarine fish and seals downstream of Muskrat Falls and in Goose Bay.
[252] As to other participants, the JRP noted that they had raised
concerns about the exclusion of Goose Bay and Lake Melville from the assessment
area, changes to erosion and deposition downstream, mercury accumulation,
including entrainment effects, in fish and seals, and changes to ice
formation. DFO said that Nalcor had provided insufficient rationale for its
decision to exclude Goose Bay and Lake Melville.
[253] The JRP noted that DFO had released a research paper showing that
mercury effects from the Churchill Falls project could be seen in several
estuarine species (rainbow smelt, tomcod, sea trout) in the waters of Lake Melville over 300 kilometres away from the Smallwood Reservoir. DFO expressed concern
about the absence of downstream sampling of primary producers and macrobenthos
because of their potential to bioaccumulate mercury. DFO therefore recommended
that Nalcor develop a comprehensive program to monitor spatial and temporal
changes in mercury in fish within the reservoirs and downstream including at Goose Bay following reservoir creation. The frequency and timing of sampling should
support a clear assessment of the magnitude and timing of these changes, and
inform determinations of risks to human health and implementation of related
fisheries management measures. More baseline data should be collected on
mercury levels in estuarine fish downstream of Muskrat Falls and in Goose Bay in advance of inundation.
[254] In its conclusions and recommendations the JRP acknowledged that
there was limited information on downstream, estuarine effects on hydro
projects in a boreal region, and limited application of reports that were cited
by participants, which lack of information it said was likely compounded by
Nalcor’s decision to place the study boundary at the mouth of the river and,
therefore, not carry baseline sampling in Lake Melville. As a result, the JRP
stated that it could not confidently conclude what the ecological effects would
be downstream of Muskrat Falls, particularly in the estuarine environment of Goose Bay and Lake Melville:
The Panel concludes that Nalcor’s assertion
that there would be no measurable effect on levels of mercury in Goose Bay and Lake Melville has not been substantiated. Evidence of a long distance effect from
the Churchill Falls project in estuarine species clearly indicate that mercury
effects can cross from freshwater to saline environments, in spite of Nalcor’s
assertions to the contrary. The Panel also concludes that Nalcor did not carry
out a full assessment of the fate of mercury in the downstream environment,
including the potential pathways that could lead to mercury bioaccumulation in
seals and the potential for cumulative effects of the Project together with
other sources of mercury in the environment. Because Nalcor did not acknowledge
the risk that seals could be exposed to mercury from the Project, it did not
address whether elevated mercury would represent any threat to seal health or
reproduction.
The significance of the potential for
downstream mercury effects on Aboriginal and non-Aboriginal land and resource
use, and on human health and communities is discussed in Chapters 8, 9, and 13.
The Panel is not convinced that all effects
beyond the mouth of the river will be “nonmeasurable” as defined by Nalcor
(within natural variability). The Panel concludes that downstream effects would
likely be observed in Goose Bay over the long term caused by changes in
sediment and nutrient supply and in water temperature. Effects in Lake Melville are more difficult to predict on the basis of existing information. The Panel
acknowledges that there is difficulty in accurately predicting the scale of
effects given the absence of long-term ecological studies of the effects of
hydroelectric projects in northern environments on receiving waters. However,
the Panel believes that this emphasizes the need for a precautionary approach,
particularly because no feasible adaptive management measures have been
identified to reverse either long-term adverse ecological changes or mercury
contamination of renewable resources.
With the information before it, the Panel is
unable to make a significance determination with respect to the risk of
long-term alteration of ecological characteristics in the estuarine
environment. The Panel concludes that there is a risk that mercury could
bioaccumulate in fish and seals in Goose Bay and possibly in Lake Melville populations as well but would probably not represent a risk to the health of
these species. The implications on health and land use are addressed elsewhere,
but the following recommendation addresses the need to take a precautionary
approach to reduce the uncertainty regarding both the potential ecological and
mercury effects downstream.
RECOMMENDATION 6.7 Assessment of
downstream effects
The Panel recommends that, if the Project is
approved and before Nalcor is permitted to begin impoundment, Fisheries and
Oceans Canada require Nalcor to carry out a comprehensive assessment of
downstream effects including:
• identifying all possible pathways for mercury throughout the
food web, and incorporating lessons learned from the Churchill Falls project;
• baseline mercury data collection in water, sediments and
biota, (revised modelling taking into account additional pathways, and
particularly mercury accumulation in the benthos) to predict the fate of
mercury in the downstream environment;
• quantification of the likely changes to the estuarine
environment associated with reduction of sediment and nutrient inputs and
temperature changes; and
• identification of any additional mitigation or adaptive
management measures.
The results of this assessment should be
reviewed by Fisheries and Oceans Canada and by an independent third-party
expert or experts, and the revised predictions and review comments discussed at
a forum to include participation by Aboriginal groups and stakeholders, in
order to provide advice to Fisheries and Oceans Canada on next steps.
[255] It is important to consider the context of this Recommendation. The
JRP, based on the information before it, was not able to make a significance
determination with respect to the risk of long-term alteration of ecological
characteristics in the estuarine environment. However, it concluded that there
was a risk of mercury bioaccumulation in fish and seals in Goose Bay and possibly Lake Melville. It made its Recommendation to reduce uncertainty
regarding both the potential ecological and mercury effects downstream.
[256] Thus, the intent of Recommendation 6.7 was to obtain a greater level
of certainty about mercury effects downstream prior to impoundment.
[257] Canada’s Response stated that it considered
whether the significant adverse environmental effects of the Project could be
justified in the circumstances, taking into consideration Canada’s commitments made in response to the JRP Recommendations, as well as those of
Nalcor in the EIS and at the JRP hearings. Further, that Canada would require
certain mitigation measures, environmental effects monitoring and adaptive
management be undertaken by Nalcor, as well as additional studies on downstream
effects by way of requirements in federal authorizations and approvals. Canada determined that ensuring that those commitments were carried out minimized the
negative effects of the Project and reduced the risks associated with the
uncertainty about the success of the mitigation measures. Further, that the
anticipated significant energy, economic, socio-economic and environmental benefits
outweighed the significant adverse environmental effects as identified in the
JRP Report.
[258] Canada’s Response in relation to Recommendation
6.7 stated that:
6.7 Response:
The Government of Canada agrees with the
intent of this recommendation and notes it is directed to Fisheries and Oceans
Canada.
As a condition of a subsection 35(2)
authorization under the Fisheries Act, and prior to impoundment,
Fisheries and Oceans Canada will require Nalcor to collect additional baseline
data on bioaccumulation of methyl mercury in fish and on fish habitat
downstream of Muskrat Falls.
Fisheries and Oceans Canada will require
Nalcor to conduct a comprehensive multi-year program to monitor and report on
bioaccumulation of methyl mercury in fish (including seals) within the
reservoirs and downstream, including the Goose Bay/Lake Melville area.
Fisheries and Oceans Canada will also require that Nalcor carry out multi-year
post-project monitoring and reporting downstream into Lake Melville on a
variety of parameters including nutrients, primary production, fish habitat
utilization and sediment transport in order to assess changes to downstream
fish habitat.
[259] There is no question that the Response does not fully adopt
Recommendation 6.7. While the Recommendation suggests that there be further
pre-impoundment assessment to better predict the levels of mercury in the
downstream environment, that this assessment be reviewed by DFO and an
independent third party expert(s), and that the revised predictions be
discussed at a forum, including Aboriginal groups, to advise DFO on “next
steps”, Canada’s Response requires the pre-impoundment collection of additional
baseline data and a comprehensive multi-year program to monitor and report on
bioaccumulation of methylmercury in fish and seals within the reservoir and downstream
into Lake Melville.
[260]
The Authorization addressed these requirements
in Condition 6:
6. The
Proponent shall undertake an Environmental Effects Monitoring Program as
outlined in the “Lower Churchill Hydroelectric Generation Project - Aquatic
Environmental Effects Monitoring Program - Muskrat Falls” (EEM Plan), dated
February 2013, to monitor and verify the predicted impact of the proposed
development from a fish and fish habitat perspective including project related
downstream effects, methylmercury bioaccumulation in fish and fish entrainment
as the Muskrat Falls facility by:
…
6.3 Methylmercury bioaccumulation
shall be monitored annually to determine levels in resident fish species,
including seals, both within the reservoir and downstream as per established
monitoring schedule, to record and report peak level and subsequent decline to
background levels.
6.4 Information collected from the
baseline and post-project surveys to compare and verify predictions if project
impact to fish and fish habitat is to be reported by:
6.4.1 Providing a comprehensive
annual report summarizing all aspects associated with the EEM Program
(including baseline data collection) to DFO by March 31. This will include
on-going baseline monitoring up to an including 2016, as well as post-project
monitoring for a period of no less than twenty (20) years from 2018 through and
including 2037
6.4.2 Providing a comprehensive
EEM Program review report summarizing all aspects associated with the
post-Project EEM Program to DFO by March 31 of every fifth (5th) year,
commencing in 2023. This will facilitate adjustments as needed, and as
approved by DFO.
…
[261] The EEM Plan notes that transport of mercury into Goose Bay and Lake Melville was modelled with the results showing minimal increases within Goose Bay. The report includes a table setting out the predicted total mercury
concentrations in water, five months following impoundment. However, it also
states that bioaccumulation of mercury in river reaches downstream of
hydro-electric development is a known phenomenon. Therefore, relying solely on
a before and after comparison of mercury concentration is not considered an
appropriate means of monitoring environmental effects. Post-project mercury concentration
would, therefore, be compared to modeled results as well as baseline data in
conjunction with literature from similar hydro-electric developments. And,
while baseline data had been collected since 2001, it was for the purpose of
developing the model used to predict post-project concentrations.
[262] The EEM Plan study area for mercury sampling includes the Muskrat Falls reservoir and downstream out to Goose Bay/Lake Melville. Sampling is to
occur on an annual basis until the visible peak and decline in concentration is
observed. Further analysis will be conducted at that point, and additional
monitoring will occur “with an efficient schedule”.
[263] The EEM Plan states that baseline total mercury concentrations in
fish have been collected over a 13 year period (since 1999) and that actual
concentration at the time of inundation may be different. Therefore, additional
fish samples would be collected and analysed for mercury body burden during
pre-inundation in order to continue collection of mercury concentrations and as
much data as possible from each fish. A graph shows the mean mercury
concentrations that have been measured in the mainstream below Muskrat Falls
for nine types of fish to date, while another shows mean mercury concentrations
measured in Goose Bay and Lake Melville for eleven types of fish. Similar
information concerning seals is provided.
[264] As noted above, Canada’s Response does not fully adopt
Recommendation 6.7. The NCC does not suggest that Canada is bound to accept
recommendations made by the JRP as part of the EA process. However, in my
view, as the purpose of the EA process and the JRP Report is to identify
environmental impacts and to inform Canada’s Response, the JRP’s
Recommendations cannot simply be ignored or rejected without reasons. To do so
would be to entirely undermine the EA process and its use by Canada to fulfil its consultation obligations.
[265] Here, however, Recommendation 6.7 was not ignored or rejected in
whole. Rather, the intent of the Recommendation was accepted to the extent
that the uncertainty identified by the JRP was acknowledged and addressed,
although not in the manner recommended by the JRP. Canada’s Response explained
that ensuring commitments made by Nalcor and the provincial government were
carried out would minimize the negative effects of the Project and reduce
the risks associated with the uncertainty about the success of the mitigation
measures. Further, that the anticipated significant energy, economic,
socio-economic and environmental benefits outweighed the significant adverse
environmental effects as identified in the JRP Report.
[266] In this regard, the JRP did not identify the NCC as being at risk of
a significant adverse effect if consumption advisories were required. But,
even if it had, Canada’s Response acknowledged the concerns and balanced the
competing interests explaining why it arrived at its conclusion (Haida
at para 45; Taku River at para 2). While Canada’s Response could,
undoubtedly, have provided a more in-depth explanation as to why it accepted
the intent of Recommendation 6.7, but not its adoption in whole, its rationale
is apparent from the record. In the context of this judicial review of the
issuance of the Authorization, this is relevant as it pertains to the
underlying consultation and rationale supporting Canada’s Response and the
Course of Action Decision, which, in turn, led to the issuance of the
Authorization and its conditions.
[267] And, although the further assessment recommended by the JRP may have
permitted a higher level of predictive certainty as to mercury levels, it is
also apparent from DFO’s submissions to the JRP, which were essentially adopted
by Canada’s Response, that DFO was satisfied that the modeling and data
gathered by Nalcor also served to provide a sufficient predictive basis against
which future monitoring could be compared when combined with the further
baseline sampling and monitoring required by the EEM Plan. That is, Canada was satisfied that the uncertainty and risk pertaining to methylmercury bioaccumulation
could be managed by way of the monitoring programs.
[268] The consultation process demonstrates that Canada was fully informed of the views of Aboriginal groups to the extent of the downstream
assessment that was required. However, it is apparent that it did not agree
with those views. The May 31, 2013 letter from DFO to the NCC responded to
this issue in the context of Phase 5. DFO explained that with respect to
Recommendation 6.7, per Canada’s Response, Nalcor would be required to collect
additional baseline data on methylmercury accumulation in fish and on fish
habitat downstream of Muskrat Falls in advance of impoundment. The EEM Plan
provided for review of the detailed information that Nalcor will collect.
[269] In essence, Recommendation 6.7 sought further assessment prior to
impoundment to obtain a greater predictive level of certainty about mercury
effects downstream. Canada’s Response, in effect, accepted that this
uncertainty presented a risk. However, balanced against the Project benefits,
the significant adverse environmental effects were outweighed and could be
managed by way of the Authorization conditions. The NCC disagrees with this
conclusion, however, its objections are not concerned with any perceived flaws
in the EEM Plan. It does not suggest, for example, that annual sampling is
insufficient, that the number of fish species tested is not representative or
that there are specific steps that could be taken that would improve the
baseline sampling or monitoring efforts described. Rather, it again raises its
disagreement, in principle, with Canada’s Response.
[270] Again, while Canada undoubtedly could have done a far better job
explaining why a more in-depth assessment was not required and why the EEM Plan
sufficed, its explanation was sufficient to provide an understanding of its
rationale (Haida at para 44; Ka’a’Gee Tu #2 at para 131; West
Moberly at para 144).
[271] The JRP addressed reservoir preparation both in Chapter 4, Project
Need and Alternatives, and Chapter 6, Aquatic Environment of its report.
[272] In Chapter 4, the JRP described Nalcor’s submissions on the
environmental, technical and economic reasoning for three clearing scenarios:
no clearing, full clearing or partial clearing. It also described the
participants’ views. This included NRC’s view that the methods Nalcor had used
to model the fate of mercury in the environment after reservoir clearing were
appropriate; however, that the EIS did not indicate whether Nalcor had
considered the effectiveness of partial clearing. Nor had Nalcor assessed
removing the organic layer of soil or selective clearing of brush or other
organics to reduce methylmercury production. Based on new information from
experimental lakes, NRC recommended the removal of trees, brush and possibly
soils in the drawdown zone river between high and low water levels, as research
indicated that this area would be the greatest contributor of methylmercury,
thus supporting Nalcor’s scenario of partial clearing. The NCC does not appear
to have made any submissions on this issue.
[273] The JRP noted that Nalcor’s “partial clearing” alternative involved
clearing trees only in the ice and stick up zones around the perimeter of the
reservoirs and only in areas in these zones that are within Nalcor’s
pre-defined safety, environmental and economic pending constraints, otherwise
the trees are left standing. The “full clearing” alternative involved, in
addition to partial clearing, clearing wood in the flood zone in areas that
meet the same operating criteria as for “partial clearing”. In other words,
“full clearing” did not mean the removal of all trees.
[274] The JRP listed the factors it considered to be particularly relevant
in reaching its conclusions on alternate means of reservoir preparation. It
stated that:
The Panel also notes, as further discussed
in Chapter 5, the more trees cleared, the more benefits accrue in terms of
reducing methylmercury accumulation and greenhouse gas emissions, though gains
may be small. The Panel also notes that National Resources Canada recommended
that Nalcor study the removal of soils in the drawdown area to reduce the
production of methylmercury in flooded terrain. This is discussed in Chapter 6.
[275] The JRP concluded that it was both technically and economically
feasible to carry out “full clearing” for the Muskrat Falls reservoir. Its
Recommendation 4.5 was that, if the Project was approved, Nalcor be required to
apply its full clearing reservoir preparation option to that reservoir.
[276] In Chapter 6 the JRP also addressed reservoir clearing and described
the participants’ views. Nalcor stated that mobilization of methylmercury in
the reservoirs was an unavoidable impact of hydro-electric projects and that
the “full clearing” would only reduce mercury levels in fish by about ten
percent, which would not justify the extra expense. It also indicated that
other types of mitigation, such as intensive fishing of certain species, were
unproven and likely not feasible. Nalcor also noted that NRC recommendation, the
large scale removal of vegetation and soils before inundation, had only been
tried at an experimental level, would not be technically or economically
feasible, and would have considerable environmental effects.
[277] NRC pointed out that development of knowledge about the methylmercury
problems associated with reservoir creation was still at an early stage and
that mitigation to date had been largely confined to consumption advisories
(which the Panel addressed in Chapter 13). Recent research had shown that the
most effective mitigation may be removal of vegetation and the upper soil layer
in what would become the drawdown area of the new reservoir. NRC therefore
recommended that Nalcor consider large scale removal of mercury and carbon-rich
soils within this area, the so-called “bathtub ring”,
to mitigate methylmercury production, acknowledging that this form of
mitigation had so far only been conducted at a smaller experimental scale.
[278] The JRP concluded that:
The Panel notes that Natural Resources
Canada challenged the notion that mercury mobilization is an inevitable
consequence of hydro power development and consumption advisories are adequate
as the only response. The benefits of carrying out pre-inundation mitigation
such as more extensive clearing of vegetation or soils would need to be
evaluated in the context of effects of the predicted mercury levels on
fish-eating wildlife (Chapter 7), the use of renewable resources (Chapter 8)
and human health (Chapter 13). Similarly, the significance of the cumulative
effect of another period of methylmercury contamination on the lower Churchill
system, following the effects of the Churchill Falls project, should be
evaluated in the context of human health and the use of renewable resources.
…
The Panel accepts that selective soil
removal around the reservoir rim is not yet proven as mitigation but observes
that this approach appears to have merit, especially if the clearing can be
confined to the reservoir rim. The Panel also notes that the type of
preparation required for this mitigation might be complementary with the
riparian and fish habitat measures that Nalcor would already be undertaking.
The Panel concludes that consumption
advisories transfer part of the cost of generating hydroelectricity to local
populations and it is therefore important to find better approaches to reducing
methylmercury in reservoirs. Therefore the Panel believes that Natural
Resources Canada should move ahead with testing the mitigative approach of
removing soil in the drawdown zone, including determining how to avoid or
minimize environmental impacts, and ways to make beneficial use of the
materials removed.
[279] With respect to Recommendation 4.5, the JRP concluded that it was
both technically and economically feasible to carry out “full clearing” for the
Muskrat Falls reservoir and made the following recommendation:
RECOMMENDATION
4.5 Full clearing of the Muskrat Falls reservoir
The Panel
recommends that, if the Project is approved, Nalcor be required to apply its
‘full clearing’ reservoir preparation option to the Muskrat Falls reservoir.
[280] Canada’s Response stated the following:
Recommendation 4.5: Full clearing of the Muskrat Falls reservoir
The Panel recommends that, if the Project is
approved, Nalcor be required to apply its ‘full clearing’ reservoir preparation
option to the Muskrat Falls reservoir.
Response: The Government of Canada notes
that this recommendation is directed to the operations of Nalcor as regulated
by the Province of Newfoundland and Labrador. The Government of Canada will
work with the appropriate parties as required.
[281] The NCC submits, in essence, that when issuing the Authorization the
Minister ignored the impact that the approach taken by Canada’s Response to
Recommendation 4.5 would have on methylmercury levels and resultant impacts.
[282] The Bennett Affidavit attaches a copy of the Province’s response
which was filed on the same date as Canada’s Response. It states:
Recommendation
4.5 – Full clearing of the Muskrat Falls reservoir
The Panel
recommends that, if the Project is approved, Nalcor is required to apply its
‘full clearing’ reservoir preparation option to the Muskrat Falls Reservoir.
Response:
The Government of Newfoundland and Labrador agrees with the principle of maximizing the utilization of the forest resource.
With limited opportunities to use the resource, and the likely insignificant
reductions in mercury levels associated with full versus partial clearing, the
Government supports partial harvesting of the flood zone. If an economic
opportunity to use the resource materializes, consideration will be given to
harvesting additional fibre.
[283] The Finn Affidavit states that it is Mr. Finn’s “understanding that Nalcor is in the process of removing a
significant portion of the trees in the Muskrat Falls reservoir area”.
However, the basis of his understanding is not stated, nor is any explanation
offered as to what a “significant portion of the trees”
might mean in the context of full or partial clearing.
[284] Tree removal as a mitigation measure is directly related to the
issue of methylmercury bioaccumulation and related potential need for
consumption advisories downstream of Muskrat Falls and in Lake Melville. Thus, while Canada’s Response was based on jurisdiction, Canada would have known
that the Province was intending to require partial rather than full clearing as
recommended by the JRP. Yet Canada did not account for the resultant increase
in methylmercury in its response to Recommendation 4.5 or explain how this was
elsewhere considered. Given that methylmercury levels were a concern of
Aboriginal groups and a central issue for the JRP, and that the JRP process
fulfilled part of Canada’s duty to consult and its report informed Canada’s
Response, the NCC could well have expected that the issue would be explicitly
addressed, rather than simply disposed of on the basis that clear cutting was
within Provincial jurisdiction.
[285] However, as discussed above, Canada was satisfied that Nalcor’s
modeling, baseline data collection, sampling and monitoring, as enhanced by the
EEM Plan that formed a part of the Authorization, were sufficient to identify
any unpredicted increase of methylmercury levels in fish and seals. Therefore,
its decision to issue the Authorization without requiring full, as opposed to
partial clearing, was informed and reasonable. This is particularly so as the
JRP had acknowledged that the gains of requiring full rather than partial
clearing may be small.
[286] The NCC submits that the Minister ignored science that was available
to her, including two research papers published by DFO scientists, regarding
the lack of effectiveness of DFO’s fish compensation programs in actually
reaching no net loss of fish (Todd Affidavit, at para 69). Therefore, she
knowingly adopted a program that is unlikely to be effective rendering her
decision unreasonable.
[287] The JRP dealt with fish habitat loss, alteration and compensation in
Chapter 6 of its report. The JRP outlined Nalcor’s view, being that the key
policy guiding its assessment of effects on fish and fish habitat was DFO’s “no
net loss” principle for the management of fish habitat. Nalcor, in
collaboration with DFO, had developed a methodology specific to the lower Churchill River to calculate current and future habitat losses for all of the fish species present
in the assessment area. Nalcor referenced the EIS, which showed the amount of
fish habitat that would potentially be destroyed or altered by the Project as
determined by DFO, and the direct footprint of the Gull Island and Muskrat Falls generating facilities which would destroy 26.03 and 7.30 hectares,
respectively. Nalcor stated that this loss would be offset by creation of new
habitat both by incidental means (reservoir creation) and through the
construction of physical compensation works. Nalcor concluded that its
compensation and mitigation strategies would go a long way towards achieving
DFO’s no net loss objective and would provide sufficient habitat for each life
cycle of every fish species found in the Project area. Therefore, no significant
adverse effects for fish and fish habitat were expected. Nalcor set out its
proposed mitigation and monitoring measures which included preparing fish
habitat compensation plans, considering habitat enhancement sites outside the
flood zone to compensate for potentially ineffective physical compensative
works after impoundment, the carrying out of long-term monitoring and adaptive
management of compensation works to ensure no net loss and collection of additional
data.
[288] DFO generally concurred with Nalcor’s description of long-term
effects the Project would have on fish habitat and indicated that Nalcor’s
compensation strategy was acceptable in principle, with details to be provided
in its forthcoming compensation plan. DFO noted that Nalcor had made significant
long-term commitments to comprehensive habitat monitoring in the reservoirs and
that it expected this monitoring to adequately confirm predictions of fish
habitat utilization. DFO did, however, identify uncertainties about how long
it would take water quality in the reservoirs to stabilize and how fish
populations would adapt to those changes. DFO therefore recommended the
collection of more pre-inundation baseline data on fish and fish habitat in
advance of construction.
[289] Various participants expressed concerns about fish and fish habitat
compensation. However, as will be discussed further below, the NCC was not one
of these. Referring to several reports, Grand Riverkeeper Labrador criticized
the success of compensation works in mitigating habitat loss caused by large
projects and suggested that neither DFO nor EC had adequately fulfilled their
obligations regarding monitoring and enforcement with respect to large scale
compensation initiatives under the Fisheries Act.
[290] Amongst other findings, the JRP acknowledged that if Nalcor’s
proposed compensation strategy was successful, it would eventually likely
address most of the habitat needs of resident species. Further, that DFO had
tentatively endorsed the strategy and had reported success with smaller
compensation works, however, that detailed evidence was not provided in support
of this. Nor did Nalcor provide evidence of success or lessons learned from
similar large scale hydro-electric projects.
[291] More specifically:
The Panel heard evidence that Fisheries and
Oceans Canada has not been able to demonstrate substantive progress in
achieving its mandate of no net habitat loss and that fish habitat compensation
projects across the country, when examined closely, often do not reproduce
successful or equivalent habitat to that which was lost. Regional staff from
Fisheries and Oceans Canada stated that their experience in Newfoundland and Labrador was different and that compensation projects in the province have been effective
but did not present detailed information to support these statements.
RECOMMENDATION 6.6 Fish habitat
compensation
The Panel recommends that, if the Project is
approved, Fisheries and Oceans Canada require Nalcor to:
• prepared a detailed fish habitat compensation plan in
consultation with stakeholders and Aboriginal groups that addresses to the
extent possible the likely interactions between species and life stages,
including predator-prey relationships and also the potential to replace
tributary-type habitats;
• prepare a habitat monitoring plan including thresholds for
further action and identified adaptive management measures;
• implement the proposed plan, documenting the process;
• evaluate the extent to which new, stable habitat has been
created, its use and productivity; and
• apply any lessons learned from implementing the Muskrat Falls compensation plan to the proposed Gull Island compensation works.
If, after all feasible adaptive management
measures have been applied, Fisheries and Oceans Canada determines that there
has been a significant shortfall in the amount of habitat successfully created
and maintained, compared to the original proposal, Nalcor should be required to
compensate by carrying out habitat compensation works in other watersheds in Labrador. Preference should be given to remediation and enhancement on areas adversely
affected by the Churchill Falls project.
[292] The JRP went on to state that while it recognized the comprehensive
nature of Nalcor’s compensation plan, it concluded that there was considerable
risk that compensation measures would not be as effective as needed for the
reasons it set out, including that the Project would create a heavy dependency
on the success of an ambitious habitat compensation plan.
[293] The JRP made a significance determination in the next section of its
report dealing with effects on fish assemblage. Specifically, that because of
uncertainty about the effects on fish and fish populations caused by the number
and scale of changes in the aquatic environment as a result of reservoir creation,
the uncertainty about the effectiveness of habitat compensation, and the risk
that at least some of the fish habitat lost would not be effectively
re-created, the Project would result in a potentially irreversible, significant
adverse environmental effect to fish habitat and the final fish assemblage in
both reservoirs.
[294] Several things arise from this. First, the JRP clearly considered
the issue of the effectiveness of habitat compensation. It recognized the
uncertainty and addressed this in its report. In other words, this issue was
addressed in the course of the JRP process.
[295] Secondly, the NCC, by way of the Todd Affidavit, in making its
assertion that the Minister ignored the science that was available to her,
references two research papers published by DFO scientists regarding the lack
of effectiveness of DFO fish habitat compensation programs in actually
achieving no net loss of habitat, which reports are Exhibits to that affidavit.
[296] However, the Finn Affidavit points out that the second of the two
papers was actually discussed, along with another study by the same authors on
the topic of fish habitat compensation programs, with DFO participation, during
the JRP aquatic environmental session hearings held on March 15-16, 2011. The
Finn Affidavit also notes that the NCC did not make submissions at that session.
Further, that the two papers were known to DFO and were part of a large body of
knowledge, along with the JRP’s findings and recommendations, which were
considered and formed the scientific foundations for the FHC Plan, which was
attached as a condition of the Authorization. Mr. Finn also deposes that he
was satisfied that the FHC Plan was sound and addressed concerns like those
raised in the two papers and, therefore, recommended that the Regional Director
General issue the Authorization.
[297] The NCC acknowledges that it made no representations on this issue
during the JRP process but states that this was because it was not
participating at that time “due to ongoing litigation”.
[298] In my view, the time to raise these concerns was during the JRP
process (Katlodeeche at paras 119, 164-165). The NCC was well aware
that the JRP was the primary mechanism by which it could raise concerns of this
nature. It elected not to participate, as it was entitled to do, but that
election came with a risk. Further, there is no evidence that after its
injunction was denied, that the NCC then tried to raise this concern with the
JRP or DFO. Nor was this issue raised as a concern when the NCC sought
judicial review of the JRP Report, which was denied by this Court on December
20, 2012 (Grand Riverkeeper). The Finn Affidavit states that the
subject two reports were, in fact, never raised by the NCC as matters that DFO
or the Agency should consider prior to the filing of the Todd Affidavit. As
stated in Katlodeeche:
[164] The “fracking” concern has never
been raised by KFN in the past and has been raised for the first time before me
as a part of this application. It can hardly be said that the Crown has failed
to consult with KFN on an issue that KFN has not indicated as a concern until
now. As Paramount points out, fracking was expressly contemplated as a
completion technique within the scope of EA03-005, and was addressed in the
context of the environmental assessment. Chief Fabian conceded in
cross-examination that he was aware that the cumulative effects of the Project
were considered under EA03-005. Yet he is raising fracking before the Court for
the first time. KFN has also been repeatedly asked to state its concerns about
the Project, but has not mentioned fracking.
[165] As regards the Aquatic Effects
Monitoring, I believe KFN is well aware of the weakness of its case in this
regard, and has attempted to bolster its position by raising additional
concerns for the first time in this application. The proper venue for raising
new concerns is not this application. There is no evidence before me that KFN
will not be able to raise and have considered any new concerns with the Crown
as the Project evolves, or indeed that concerns such as “fracking” have not
already been addressed as part of the EA process. This approach by KFN of
raising new concerns before me that were not brought forward during the many
opportunities KFN has had to raise them, and when they could have been properly
considered and addressed by qualified personnel prior to the issuance of the
Type A Water Licence, cannot undermine the reasonableness of the Minister's
decision to approve the Type A Water Licence on the basis of the whole record
before him.
[299] By failing to raise this issue until this application for judicial
review, the NCC is, in effect, attempting to frustrate the consultation process
(Halfway River First Nation at paras 160-161).
[300] As stated in Katlodeeche:
[104] While consultation is a duty of the
Crown, there is also a corresponding duty on the part of Aboriginal groups to
participate in good faith in reasonable consultation opportunities. There is a
reciprocal obligation on Aboriginal groups to “carry their end of the
consultation, to make their concerns known, to respond to the government’s
attempt to meet their concerns and suggestions, and to try to reach some
mutually satisfactory solution” (Mikisew Cree, above, paragraph 65).
[301] Further, by way of the Authorization, DFO required compliance with
the FHC Plan and included conditions pertaining to it. Significantly, these
conditions include that if, at any time, Nalcor becomes aware that compensatory
habitat is not completed and/or functioning according to the criteria set out
in the Authorization and the FHC Plan, it must carry out any works which are
necessary to ensure the compensatory habitat is completed and/or functioning as
required by the Authorization (Condition 4.5), and, relating to the monitoring
and reporting of compensatory habitat (Condition 5), including implementation
of an adaptive management process to monitor post-project predictions and to
undertake adaptive measures should unanticipated changes occur (Condition 5.4).
[302] Accordingly, even if the fish habitat compensatory measures are not
as effective as predicted, Nalcor is still required by the Authorization to
take any necessary further actions to ensure full compliance.
[303] And, finally, as stated in Ekuanitshit FC, in the context of
a challenge to Canada’s Response to the Project:
… It is important to reiterate that it is
not this Court’s role to decide whether or not the Nalcor and MHI’s analyses
are correct and to reassess the weight to be assigned to one study over
another, but rather to determine whether the federal government’s decision
rests on a reasonable basis. As Justice Sexton reasoned in Inverhuron &
District Ratepayers’ Assn., above:
The environmental assessment process
is already a long and arduous one, both for proponents and opponents of a
project. To turn the reviewing Court into an “academy of science” - to use a
phrase coined by my colleague Strayer J. (as he then was) in Vancouver
Island Peace Society v. Canada [12] - would be both inefficient and
contrary to the scheme of the Act (Inverhuron, above, at para 36).
[304] This was restated in Grand Riverkeeper at para 41:
[41] The Federal Court of Appeal noted
in Inverhuron & District Ratepayers’ Assn. v. Canada (Minister of the
Environment), 2001 FCA 203, [2001] F.C.J. No. 1008 (Fed. C.A.) at para 40 that a reasonableness review requires merely that the Court be able to
perceive a rational basis for the Panel’s conclusions. This Court elaborated on
the point in Pembina Institute for Appropriate Development v. Canada
(Attorney General), 2008 FC 302, [2008] F.C.J. No. 324 (F.C.) (Pembina),
stating that “deference to expertise is based on the cogent articulation of the
rationale [sic] basis for conclusions reached” (para 75). This view is
consistent with Dunsmuir, above, in which the Supreme Court held that
reasonableness is concerned “mostly with the existence of justification,
transparency and intelligibility within the decision-making process. But it is
also concerned with whether the decision falls within a range of possible,
acceptable outcomes which are defensible in respect of the facts and law” (at
para 47).
[305] In this case, the JRP process canvassed the issue of the
effectiveness of fish habitat compensation programs, identified the
uncertainties arising and made recommendations which were implemented by the
FHC Plan and the conditions of the Authorization. There is no doubt that the
duty to consult can be satisfied through consultation that takes place within
the regulatory process (Taku River at para 40; Little Salmon at
para 39; Ekuanitshit FCA at para 99; Katlodeeche at para 97) and
I am satisfied that the duty to consult was met, that the Authorization
reflects a reasonable accommodation and that the Minister’s decision to issue it
was informed and reasonable.
[306] And, as stated in Malcolm, the role of the Court in the context
of decisions of this nature is not to reweigh the factors and come to its own
conclusion. Provided the decision is one that a Minister could reasonably make,
deference requires that it be respected (at para 73).
[307] The Russell Affidavit also asserts that DFO did not require Nalcor
to carry out reservoir impoundment according to the schedule recommended by the
JRP, which could result in damage to fish during the spawning cycle. However,
the Finn Affidavit states that the Authorization is consistent with
Recommendation 6.1 as it includes a condition specifically requiring reservoir
impoundment to be carried out between mid-July and the end of September. I
note that Canada’s Response accepted Recommendation 6.1 and that the
Authorization to be issued would require Nalcor to carry out impoundment within
the time frame recommended by the JRP, being mid-July to the end of September.
In that regard, the Authorization as issued is valid from June 15, 2013 to
December 31, 2017 and full reservoir impoundment is limited to July 15 to
September 30 within that period, this would appear to be in compliance
with Recommendation 6.1.
[308] Finally, the NCC also submits that it was not treated in the same
manner as the Innu by Nalcor and DFO and that DFO’s treatment of the Innu, as
the Aboriginal group most directly affected by the Project, is an error of law
that undermines the validity of the consultations. I see little merit in that
submission. The issue in this matter is concerned with the adequacy of
consultation by Canada with the NCC in Phase 5 in the context of the NCC’s
affected title and interests. That question is fact based, specific to the NCC,
and is concerned with the Authorization and its conditions, in particular, the
FHC and EEM Plans, and the Minister’s decision to issue the Authorization.
And, in any event, the Regulatory Phase Protocol, the consultation
process, applied to all Aboriginal groups.
[309]
The duty to consult and accommodate does not
mean that Aboriginal groups possess a veto over government decision-making. The
Crown may proceed to make decisions even if an Aboriginal group opposes them,
as long as the consultation process and accommodations are fair, reasonable and
consistent with the honour of the Crown (Adams Lake at para 100).
[310] In this case, the duty to consult fell between the low and mid-range
of the spectrum. Canada, consistent with the Consultation Framework,
proposed the Regulatory Phase Protocol for Phase 5 of the Project. DFO
met with the NCC to discuss the regulatory permitting to follow by way of the Fisheries
Act Authorization. DFO also provided the NCC with the draft Regulatory
Phase Protocol and sought the NCC’s comments on that consultation process.
The NCC did respond, outside the requested 14 day period, but did not provide
substantive comments, instead seeking a definition of the Project footprint, a
matter that had been addressed at the beginning of the five phase consultation
process, and a separate protocol to share the NCC’s Aboriginal Traditional
Knowledge, which the NCC stated should be emphasized.
[311] DFO provided the draft FHC and EEM Plans to the NCC in accordance
with the Regulatory Phase Protocol. However, rather than comment on the
Plans, the NCC challenged the protocol process, took issue with alleged
non-compliance with the JRP Recommendations, a lack of funding for Phase 5 and
other matters. DFO responded to each of those concerns.
[312] In my view, the process set out in the Regulatory Phase Protocol
was adequate to meet Canada’s duty to consult, was reasonable and was followed
by DFO. While DFO’s response may have been less than perfect, perfection is
not required so long as reasonable efforts have been made to consult and
accommodate and if the result is within the range of possible, acceptable
outcomes which are defensible in respect of the facts and the law, there will
be no basis to intervene (Ka’a’Gee Tu #2 at para 90-92; Haida at
para 42). While the NCC is not satisfied with many of Canada’s responses, as discussed above, the Minister’s decision to issue the Authorization was,
ultimately, reasonable.
[313] As to the adequacy of consultation governing the NCC’s Aboriginal
Traditional Knowledge and current land and resource use, I am not convinced
that insufficient funding or consultation opportunities in Phases 1-4 of the
consultation process precluded the NCC from gathering and presenting this
information. The JRP process was the primary mechanism addressing these
issues. Additionally, further, albeit limited, funding was provided in Phase 4
to address issues arising from the JRP Report, which would have included the
NCC’s position that its Aboriginal Traditional Knowledge and land and resource
use had not been adequately addressed. Because the consultation process was an
ongoing one, the Minister was entitled to consider the prior consultation when
deciding to issue the Authorization.
[314] Funding was not provided in Phase 5. This was unfortunate as it may
have limited the ability of Aboriginal groups, including the NCC, to retain
third party consultants, if necessary, to assist them in determining if the
Authorization, in particular, the FHC and EEM Plans, adequately mitigated any
adverse impacts to their effected title and interest. However, the NCC was
aware of the consultation process effected by the Regulatory Phase Protocol
and was also afforded the opportunity to meet with both Nalcor and DFO to
discuss the Plans but declined to do so. The NCC also did not utilize any of
its own resources in this regard. As a result, it has not established either a
failure of the duty to consult or an adverse impact resulting from it.
[315] As to the compliance with Recommendations 6.7 and 4.5 of the JRP
Report, Canada was satisfied that Nalcor’s modeling and data gathering served
to provide a sufficient predictive basis against which future monitoring could
be compared when combined with the further baseline sampling and monitoring
required by the EEM Plan. That is, Canada was satisfied that the uncertainty
and risk pertaining to methylmercury bioaccumulation could be managed by way of
the monitoring programs. Accordingly, the Minister’s decision to issue the
Authorization on that basis, and without requiring full clearing, was informed
and reasonable and does not demonstrate a failure of accommodation.
[316] Finally, the NCC’s allegation that the Minister ignored available
science and knowingly adopted a fish habitat compensation plan that was
unlikely to be effective, rendering her decision unreasonable, is not
sustainable. First, because the JRP dealt with the issue, recognized the
uncertainty and made recommendations in that regard which are reflected in the
Authorization. Secondly, because the NCC failed to raise this as a concern at
any point in the consultation process. Raising such an issue for the first
time at judicial review of the final phase of a lengthy consultation process
and asking that the Court reweigh the scientific evidence is not the role of
the Court nor an appropriate manner in which to deal with the issue.
[317] For the above reasons, it is my view that the duty to consult was
met and that the Minister’s decision to issue the Authorization was reasonable.
[318] Accordingly, this application for judicial review is denied.