Date:
20130423
Docket:
T-778-12
Citation: 2013
FC 418
Ottawa, Ontario,
April 23, 2013
PRESENT: The
Honourable Mr. Justice Scott
BETWEEN:
|
CONSEIL DES INNUS DE
EKUANITSHIT
|
|
|
Applicant
|
and
|
|
LE PROCUREUR GÉNÉRAL
DU CANADA,
EN SA QUALITÉ DE
JURISCONSULTE DU
CONSEIL PRIVÉ DE SA
MAJESTÉ
POUR LE CANADA
ET
L’HONORABLE KEITH
ASHFIELD, EN SA CAPACITÉ DE MINISTRE DES PÊCHES ET DES OCÉANS CANADA
ET
L’HONORABLE DENIS
LEBEL,
EN SA CAPACITÉ DE
MINISTRE
DES TRANSPORTS
CANADA
ET
L’HONORABLE JOE
OLIVER,
EN SA CAPACITÉ DE
MINISTRE DES
RESSOURCES
NATURELLES CANADA
ET
NALCOR ENERGY
ET
NEWFOUNDLAND AND LABRADOR HYDRO-ELECTRIC
CORPORATION
|
|
|
Respondents
|
REASONS FOR
JUDGMENT AND JUDGMENT
I. Introduction
[1]
This
is an application for judicial review filed on April 16, 2012 pursuant to
sections 18 and 18.1 of the Federal Courts Act, RSC 1985, c-7 [FCA], by
which the Applicant challenges the lawfulness of the Order in Council (C.P.
2012-285) taken by the Governor in Council (“the Order”) approving the federal
government’s Response (“the Response”) to the Report of the Joint Review
Panel, Lower Churchill Hydroelectric Generation Project, Nalcor Energy,
Newfoundland and Labrador (“the Report”) and the related cause of action
Decision dated March 16, 2012 (“the Decision”) by the responsible authorities,
Fisheries and Oceans Canada [DFO], Natural Resources Canada [NRCan] and
Transport Canada [TC] (collectively “the RAs”) pursuant to subsection 37(1) of
the Canadian Environmental Assessment Act, SC 1992, c 37 [CEAA]. The
Report was issued by a Joint Review Panel [JRP] as the culmination of its
environmental assessment (“the EA”) of the Lower Churchill Hydroelectric
Generation Project (“the Project”). The Order was made by the Governor in
Council on March 12, 2012 pursuant to subsection 37(1.1) of the CEAA.
[2]
The
Applicant is seeking, amongst other remedies:
1. a
declaration that
a) the
Governor in Council and RAs did not fulfill their duty to consult the Innus
d’Ekuanitshit (the Ekuanitshit) on the elements of the Project liable to have a
prejudicial effect on their traditional rights;
b) the
Governor in Council and RAs did not seek to accommodate the Ekuanitshit in a
spirit of reconciliation consistent with the honour of the Crown;
c) despite
the requirements of paragraph 4(1)(a) of the CEAA, the Governor in Council
and RAs did not possess sufficient information to assess the potential negative
impact that the Project is liable to have on the current use of the land and
resources for traditional purposes by the Ekuanitshit;
d) the
Project proposed by Nalcor Energy (“Nalcor”) is no longer the project proposed
for evaluation under the CEAA due to subsequent changes in the
implementation process;
e) the
Project and the Labrador-Island Transmission Link Project (Transmission Link)
constitute a single project under the CEAA; and
f) the
Governor in Council and RAs did not have sufficient information in order to
judge the economic benefits of the Project or whether there are other
economically and technically feasible means of meeting energy requirements that
are less environmentally harmful;
2. an
order quashing the Order and the Decision;
3. an
order returning the Report to the Governor in Council and RAs so that they may:
a) fulfill
their duty to consult and accommodate the Ekuanitshit pursuant to section 35 of
The Constitution Act, 1982 regarding the potential negative impacts of
the Project on their traditional rights in a manner consistent with the honour
of the Crown;
b) ask
that further information be supplied regarding the necessity and negative
impacts of the Project;
c) determine
whether, in light of the supplementary information mentioned above, the
Project’s negative impacts are still justifiable in the circumstances;
4. a
writ of prohibition preventing the ministers of the DFO and TC from:
a) issuing
permits under the Fisheries Act, RSC 1985, c F-14 and the Navigable
Waters Protection Act, RSC 1985, c N-22; and
b) taking
any other irrevocable decision in their roles as RAs with regards to the
Project 5) Costs, regardless of the result of the application.
[3]
For
the reasons that follow, the Court is dismissing this application.
II. Background
A. The
parties
(i)
The
Applicant
[4]
Le
Conseil des Innus d’Ekuanitshit (“the Applicant”) is a registered Indian band
within the meaning of section 2 of the Indian Act, RSC 1985, c I-5.
[5]
The
Applicant participated throughout the EA process for the Project, and was
awarded funding through the Canadian Environmental Assessment Agency’s (“the
Agency”) Participant Funding Program to facilitate its participation in
different phases of the EA.
(ii) The
Respondents
[6]
The
Respondents are: (1) the Attorney general of Canada [AGC] named in lieu of the
Governor in Council, whose approval of the Response is required pursuant to
subsection 37(1.1) of the CEAA; (2) the Minister of Fisheries and
Oceans, who, together with (3) the Minister of Transport and (4) the Minister
of Natural Resources, constitute the Responsible Authorities [RAs] related to
the Project; (the Government Respondents); (5) Nalcor; and (6) Newfoundland and
Labrador Hydro-Electric Corporation.
[7]
Fisheries
and Oceans Canada [DFO] and Transport Canada [TC] identified themselves from
the beginning as RAs with respect to the Project. DFO found that certain
components of the Project would result in the harmful alteration, disruption or
destruction of fish habitat and would consequently require authorizations under
subsection 35(2) of the Fisheries Act, RSC 1985, c F-14. Transport Canada determined that the Project would require formal approval under subsection 5(1) of
the Navigable Waters Protection Act, RSC 1985, c N-22 [NWPA] because the
Project’s dams constitute works under that Act.
[8]
Natural
Resources Canada became a responsible authority on August 19, 2011, when a
decision was taken by the Government of Canada to provide financial assistance
to Nalcor in the form of a loan guarantee for a part of the Project.
[9]
Nalcor
is a Crown Corporation incorporated pursuant to the Energy Corporation Act,
SNL 2007, c E-11.01. It is wholly owned by the Government of Newfoundland and Labrador (“the Province”), and was constituted to “engage in and carry out activities
pertaining to the Province’s energy resources, including hydro-electric
generation”. Nalcor is responsible for the implementation of the
Province’s energy policy, and is governed in that respect by: the Energy
Corporation Act, above; the Province’s long term energy policy, Focusing
Our Energy (“the Energy Plan”); and the Electrical Power Control Act,
1994 , SNL 1994, c E-5.1.
B. The
Project
[10]
Nalcor’s
proposed Project consists of:
“hydroelectric generating facilities at Gull Island and Muskrat Falls, and interconnecting transmission lines to the existing Labrador grid. The Project will be the subject of engineering design and marketing studies
that will be conducted concurrently with the environmental assessment. As part
of the environmental assessment, alternative means of carrying out the Project
will be evaluated including its capacity, design, layout, and technology. The
Project as currently planned is presented and, as with any project, will
require optimization to reflect current market and business opportunities.
Nevertheless, the Project will be very similar to previous concepts.
Optimization will determine details such as the size and number of turbines
within each powerhouse, and construction sequencing pending access to the south
side of the river. Such changes and refinements will be relatively slight, and
consistent with the normal process leading to final Project sanction. The Gull Island facility will consist of a generating station with a capacity of approximately
2,000 MW and include:
- a dam 99 m high and 1,315m long; and
- a reservoir 200 km2 in area at an
assumed full supply level of 125 m asl.
The dam will be a central till-cored, rock-fill,
zone embankment. The reservoir will be 225 km long, and the area of inundated
land will 85 km2 at full supply level. The powerhouse will contain
four to six Francis turbines.
The Muskrat Falls facility will consist of a generating
station that will be approximately 800 MW in capacity and will include:
- a concrete dam with two sections on the north and
south abutments of the river;
-
a 107 km2 reservoir at an assumed full supply level of 39 m asl.
The
north section of the dam will 32 m high and 180 m long, while the south section
will be 29 m high and 370 m long. The north section will serve as a spillway in
extreme precipitation events. The reservoir will be 60 km long and the area of
inundated land will be 36 km2 at full supply. The powerhouse will
contain four to five propeller or Kaplan turbines, or a combination of both.
The
interconnecting transmission lines will consist of:
-
a 735 kV transmission line between Gull Island and Churchill Falls; and
-
two 230 kV transmission lines between Muskrat Falls and Gull Island.
The
735 kV transmission line will be 203 km long and the 230 kV transmission lines
will be 60kn long. Both lines will likely be lattice-type steel structures. The
location of the transmission lines will be north of the Churchill River; the
final route is the subject of a route selection study that will be included in
the environmental assessment. The lines between Muskrat Falls and Gull Island may be on separate towers, or combined on double-circuit structures”. (See
Affidavit of Stephen Chapman, Exhibit SC-4, Federal Respondents
Representations, Vol. 1, pages 270-271)
[11]
The
Project has a long history. Since 1978, three different versions of the Project
have been contemplated. Two versions involved diversions of rivers and an
agreement with Hydro Québec. As the negotiations failed with Hydro-Québec and
it was determined that the diversion of rivers upstream of Churchill Falls was
unfeasible, Nalcor focused on a project that did not entail the diversion of
rivers. The version of the Project that was defined and registered by Nalcor
for environmental assessment in November of 2006 is as described above; it does
not rely on the diversion of rivers and is predicated on meeting identified
needs within the Province and generating surplus energy to access export
markets.
C. The
CEAA Environmental Assessment Process
[12]
It
is important to describe the framework that applied to this EA under the CEAA.
There are five stages involved. This application for judicial review was filed
at the conclusion of the fourth stage.
[13]
The
Applicant submitted that correspondence related to phase V should be allowed in
the record despite the fact that it was exchanged after the application. The
Court decided that it should not be accepted in the record because phase V is
still ongoing and, more importantly, the record should be confined to what was
before the decision maker at the time the application was filed.
[14]
The
Project was registered in November 2006 and the RAs determined that the CEAA
applied to the Project in February 2007.
[15]
In
June 2007, the Minister of the Environment referred the assessment to a review
panel. Since the Province of Newfoundland and Labrador had also concluded that
public hearings would be required under provincial legislation, the two
Governments agreed to set up a JRP in January 2009.
[16]
It
is important to note that the CEAA provides for three types of environmental
assessments: screening, comprehensive study and panel review. A panel review
calls for a more comprehensive assessment and extended involvement by
participants. The assessment was conducted by the JRP after the “Agreement for
the Establishment of a Panel for the Environmental Assessment of the Lower
Churchill Hydroelectric Generation Project” was concluded in January 2009. The
federal Minister of the Environment, together with the provincial Ministers of
Environment and Conservation and the Minister of Intergovernmental Affairs,
appointed the five member panel responsible for the panel review.
[17]
In
order to better comprehend the scope and degree of involvement required under
the EA, the Court believes that reproducing substantive extracts from the JRP
Agreement that defined the Terms of Reference for the Panel’s EA will
facilitate the comprehension of the issues raised by this application. The JRP
Agreement specified that:
“2.0 Establishment of the Panel
2.1 A process is
hereby established for the creation of a Panel, pursuant to sections 40, 41 and
42 of the CEAA and section 73 of the EPA and, for the purposes of the review of
the Project/Undertaking.
3.0 Constitution of the Panel
3.1 The Minister
of the Environment and the Lieutenant-Governor in Council of the Province of Newfoundland and Labrador shall jointly establish the Panel.
3.2 The Panel shall consist of five members.
4.0 Conduct of
the Environmental Assessment by the Panel
4.1 The Panel
shall have all the powers and duties of a panel set out in section 35 of the
CEAA and sections 64 and 65 of the EPA and applicable regulations.
4.2 The Panel
shall conduct the EA in a manner that discharges the requirements set out in
the CEAA, the EPA and in the Terms of Reference for the Panel set out in
Schedule 1.
6.0 Record of
environmental Assessment and Panel Report
6.1 A Project
File containing all records produced, collected or submitted with respect to
the EA of the Project/Undertaking shall be maintained by the Agency from the
appointment of the Panel until the report of the Panel is submitted to the
Ministers. The Public Registry shall be operated in a manner to ensure
convenient public access to the records for the purposes of compliance with
section 55 of the CEAA and the practices of the Department.
6.2 On
completion of the EA of the Project/Undertaking, the Panel shall prepare a
report and submit it to the Ministers who will make it public.
6.3 The
report will address the factors required to be considered under section 16 of
the CEAA and section 65 of the EPA, will set out the rationale, conclusions and
recommendations of the Panel relating to the EA of the Project/Undertaking,
including any mitigation measures and follow-up program, and include a summary
of issues raised by Aboriginal groups, governments and other interested
parties. [Emphasis added]
6.4 The Parties
agree to coordinate, to the extent possible, the timing and announcements of
decisions on the Project/Undertaking.
6.5 Once the
report is submitted to the Minister of the Environment, responsibility for the
maintenance of the Public Registry in accordance with section 55 of the CEAA
will be transferred to Fisheries and Oceans Canada as responsible authority.
8.0 Participant Funding
8.1 The
Agency will administer a participant funding program to facilitate the
participation of Aboriginal groups and the public in the EA of the
Project/Undertaking. [Emphasis added]
Part I – Scope of the Project/Undertaking
The Proponent proposes a project/undertaking
consisting of hydroelectric generating facilities at Gull Island and Muskrat Falls, and interconnecting transmission lines to the existing Labrador grid.
The Project/Undertaking includes the following
components as described by the Proponent. The specific
dimensions/characteristics of the proposal are subject to change as a result of
the findings of the environmental assessment.
The Gull Island facility consisting of a generating
station with a capacity of approximately 2,000 MW that includes:
•
A
dam 99 m high and 1,315 m long; and
•
A
215 km2 reservoir in area at an assumed full supply level of 125 m
above sea level (asl).
The dam is to be a concrete faced, rock fill dam.
The reservoir is to be 230 km long, and the area of inundated land is to be in
the order of 85 km2 at full supply level. The powerhouse is to
contain five Francis turbines.
The Muskrat Falls facility consisting of a
generating station with a capacity of approximately 800 MW that includes:
•
A
concrete dam with two sections on the north and south banks of the river; and
•
A
100 km2 reservoir in area at an assumed full supply level of 39 m
asl.
•
The north and south dams will be constructed or
roller compacted concrete. The north section dam is to be in the order of 32 m
high and 432 m long, while the south section is to be in the order of 29 m high
and 125 m long. The reservoir is to be 60 km long and the area of inundated
land is to be in the order of 41 km2 at full supply level.
The powerhouse is to contain four propeller or
Kaplan turbines, or a combination of both.
Interconnecting transmission lines consisting of:
•
A
735 kV transmission line between Gull Island and Churchill Falls; and
•
Two
230 kV transmission lines between Muskrat Falls and Gull Island.
The 735 kV transmission line is to be 203 km long
and the 230 kV transmission lines are to be 60 km long. Both lines will be
lattice-type steel structures. The location of the transmission lines is to be
north of the Churchill River; the final route is the subject of a route
selection study that will be combined on double-circuit structures.
Part II – Scope of the Environmental Assessment
The panel shall consider the following factors in
the EA of the Project/Undertaking as outlined in Sections 16(1) and 16(2) of
the CEAA and Sections 57 and 69 of the EPA:
1.
Purpose
of the Project/Undertaking;
2.
Need
for the Project/Undertaking;
3.
Rationale
for the Project/Undertaking;
4.
Alternative
means of carrying out the Project/Undertaking that are technically and
economically feasible and the environmental effects of any such alternative
means;
5.
Alternatives
to the Project/Undertaking;
6.
Extent
to which biological diversity is affected by the Project/Undertaking;
7.
Description
of the present environment which may reasonably be expected to be affected,
directly or indirectly, by the Project/Undertaking, including adequate baseline
characterisation;
8.
Description
of the likely future condition of the environment within the expected life span
of the Project/Undertaking if the Project/Undertaking was not approved;
9.
Environmental
Effects of the Project/Undertaking, including the Environmental Effects of
Malfunctions, accidents or unplanned events that may occur in connection with
the Project/Undertaking;
10.
Any
cumulative Environmental Effects that are likely to result from the
Project/Undertaking in combination with other projects or activities that have
been or will be carried out;
11.
The
significance of the Environmental Effects as described in items 9 and 10;
12.
Mitigation
measures that are technically and economically feasible and that would mitigate
any significant adverse Environmental Effects of the Project/Undertaking,
including the interaction of these measures with existing management plans;
13.
Proposals
for environmental compliance monitoring;
14.
Measures
to enhance any beneficial Environmental Effects;
15.
Need
for and requirements of any follow-up program in respect of the
Project/Undertaking;
16.
Capacity
of renewable resources that are likely to be significantly affected by the
Project/Undertaking to meet the needs of the present and those of the future;
17.
Extent
of application of the precautionary principle to the Project/Undertaking;
18.
Comments
received from Aboriginal persons or groups, the public and interested parties
by the Panel during the EA;
19.
Factors
related to climate change including greenhouse gas emissions;
20.
Proposed
public information program.
To assist in the analysis and consideration of these
issues, in addition to the Secretariat established by Canada and Newfoundland and Labrador to support the Panel, the Panel may retain, within its approved
budget, independent expertise to provide information on and help interpret
technical and scientific issues and matters related to traditional knowledge
and community knowledge.
Aboriginal Rights Considerations
The Panel will have the mandate to invite
information from Aboriginal persons or groups related to the nature and scope
of potential or established Aboriginal rights or title in the area of the
Project, as well as information on the potential adverse impacts or potential
infringement that the Project/Undertaking will have on asserted or established
Aboriginal rights or title.
The Panel shall include in its Report:
1.
information
provided by Aboriginal persons or groups related to traditional uses and
strength of claim as it relates to the potential environmental effects of the
project on recognized and asserted Aboriginal rights and title.
2.
any
concerns raised by Aboriginal persons or groups related to potential impacts on
asserted or established Aboriginal rights or title.
The Panel will not have a mandate to make any
determinations or interpretations of:
•
the
validity or the strength of any Aboriginal group’s claim to Aboriginal rights
and title or treaty rights;
•
the
scope or nature of the Crown’s duty to consult Aboriginal persons or groups;
•
whether
Canada or Newfoundland and Labrador has met its respective duty to consult and
accommodate in respect of potential rights recognized and affirmed by section
35 of the Constitution Act, 1982;
•
the
scope, nature or meaning of the Labrador Inuit Land Claims Agreement. [Emphasis added]
Part III – Steps in the Environmental Assessment
Process
The main steps in the EA by the Panel will be as
follows:
1.
Site
Visit;
2.
Public
Information Centres;
3.
Submission
of the EIS;
4.
Review
of the EIS;
5.
Comments
provided to the Proponent;
6.
EIS
Sufficiency;
7.
Scheduling
of Public Hearings;
8.
Location
of Public Hearings;
9.
Conduct
of Public Hearings;
10.
Length
of Public Hearings;
11.
Delivery
of Panel Report.”
[18]
The
final Environment Impact Statement [EIS Guidelines] were released by the
Governments on July 15, 2008 after considering input provided by Aboriginal
groups, including the Applicant, and other stakeholders between December 19,
2007 and February 27, 2008 on the scope of the Project and other issues (see
Exhibit A-98 to Bennett Affidavit, Nalcor Representations [NR], Vol. 1 and
Chapman Affidavit at paras 71 and 99, Federal Respondents Representations, Vol.1).
[19]
The
EIS Guidelines is a 10,800 page document that addresses the need, alternatives
and cumulative effects of the Project.
[20]
The
EIS issues of concern were determined through: (a) the EIS Guidelines; (b)
stakeholder and public consultation; (c) local and existing knowledge of
potential environmental effects of projects (including hydro-electric
projects); (d) Nalcor’s submissions describing the existing environment; and
(e) analysis of the Nalcor study team, comprised of 15 environmental consulting
firms.
(See
Exhibits H, I, JJ, NN to Bennett Affidavit (NR, Vol 1, pages 421, 453 and 1737)
[21]
The
Applicant received plain language summaries of the EIS, translated into French
and the Québec dialect of Innu-aimun (“Innu-aimun”).
(See Exhibit A-398 to
Bennett Affidavit (NR, Vol. 1)
[22]
Between
March 9, 2009 and April 15, 2011, the JRP conducted its information gathering
process. They began by inviting the public and government agencies to comment
on the adequacy of the EIS. The Applicant was among the 52 parties who
presented detailed submissions (see document entitled Legal Comments on the
Adequacy of the Environmental Impact Statement of the Lower Churchill
Hydroelectric Project dated June 22, 2009 (Applicant’s Record, Exhibit 12, page
996, NR, Vol. 3, page 490).
(See Exhibit J to
Bennett Affidavit (NR, Vol. 1, page 462)
[23]
These
submissions led the JRP to issue Information Requests [“IRs”] to Nalcor.
Between May 1, 2009 and March 21, 2010, the JRP sent 166 IRs in five separate
rounds. The process was meant to enable the JRP and the public to: (a)
scrutinize the EIS; (b) make additional requests for information; and (c)
comment on Nalcor’s IR responses.
(See
Exhibits A-251- A-432, K, L, pages 498 and 513 to Bennett Affidavit (NR, Vol. 1
and 3)
[24]
Nalcor
implemented a planning framework for the Project called the “Gateway Process”.
The process entails six sequential phases between opportunity evaluation and
decommissioning. In essence, at each of the six phases, there is a decision
gate with respect to the development or not of the asset. Either the activity
is stopped pending additional information or it can move to the next sequential
phase or it is abandoned.
[25]
Further
to an announcement by Premier Williams on October 25, 2010, regarding a
possible change in the sequencing of the Project, Nalcor was asked to provide
additional information with respect to the change in the sequencing and the
corresponding potential impact and environmental effects. Responses IR#JRP.165
and IR#JRP.166 filed in January 2011 contain a total of 160 pages. The main
conclusion was to the effect that there are no material changes to the
predicted environmental effects resulting from re-sequencing the Project phases
(see Exhibit A-549 to Bennett Affidavit (NR, Vol 11, page 2756). These
responses make no reference to the Applicant or to any other Quebec based
innus.
[26]
The
application for the Transmission Link was filed on January 29, 2009 and revised
on September 15, 2009. It called for the construction and operation of an
approximately 1,100 km long transmission line and associated infrastructure
within Labrador and the Island of Newfoundland and finally favoured the Gros
Morne and the selection of the Long Range Mountains crossing as the proposed
transmission corridor (see Applicant’s Record, V. Duro Affidavit, Exhibit 10, Vol.
3, Page 804).
[27]
The
record reveals that Nalcor filed over 5,000 pages of additional documentation
for consideration by the JRP and stakeholders by way of IR responses. Thirteen
of the IRs touched upon the Applicant’s specific concerns with respect to: (a)
Aboriginal consultation; (b) caribou, including the Red Wine Mountain and Lac Joseph herds; (c) monitoring and follow-up; and (d) waterfowl survey
methodology.
(See
Exhibits A-251, A-432, A-588, K, L, KK, LL to Bennett Affidavit (NR, Vol 1, 3
and 8)
[28]
On
two occasions, the JRP invited the public to comment on Nalcor’s IR responses.
The Applicant filed detailed submissions on both occasions.
(See
Exhibits K, M, N to Bennett Affidavit (NR, Vol. 3, pages 498 and 544 and Exhibits
13, 17 to Duro Affidavit (Applicant’s Record, Vol. 4 and 5)
[29]
On
January 14, 2011, the JRP determined that the EIS (including the additional
information submitted by Nalcor) was sufficient to proceed to the Hearing.
(See Exhibit A-544 to Bennett
Affidavit (NR, Vol. 1)
[30]
On
January 14, 2011, participants were informed that the Hearing would begin on
March 3, 2011. The Final Public Hearing Procedures were released on February
16, 2011, after consideration of extensive input from the public, including the
Applicant.
[31]
The
Hearing was conducted over 30 days between March 3 and April 15, 2011, in six
different communities and in the Province of Quebec. There were general,
community and topic-specific hearing sessions.
(See Exhibit A-1385 to
Bennett Affidavit (NR, Vol. 12)
[32]
The
Applicant, through its representatives, made oral submissions during the
community Hearing session in Sept-Îles, Quebec, on April 7, 2011, during which
a video and materials were presented to the JRP. Simultaneous translation was
provided (French and Innu-aimun).
(See
Exhibits A-1220, A-1244, A-1280, A-1284 to Bennett Affidavit (NR, Vol. 1 and Exhibits
20-25, 28, 43 to Duro Affidavit (Applicants Record, Vol. 5, 6 and 9)
[33]
After
the conclusion of 30 days of hearings, the JRP declared the record closed.
The Report
[34]
The
355 page JRP Report was released to the Governments and the public on August 23
and 25, 2011, respectively.
(See Applicant’s
Record, Affidavit V. Duro, Exhibit 3, Vol. 1, page 221)
[35]
As
required by CEAA and the TOR, the Report contains: (a) a description of the EA
process, including public hearings; (b) the rationale, conclusions and
recommendations regarding the nature and significance of the potential
environmental effects ; (c) recommendations concerning, amongst others, the
mitigation measures relating to the environmental management of the Project,
caribou, monitoring and follow-up programs; (d) a summary of issues identified
and comments and recommendations received from Aboriginal persons/groups; and
(e) a summary of the issues raised and comments and recommendations received
from the public, Governments and interested parties.
The Decision and
Response of the Federal Government
[36]
Pursuant
to the CEAA and the EPA, the Governments jointly issued their responses and the
decisions on March 15, 2012.
(See
Exhibits
R, S and T to Bennett Affidavit, NR, Vol. 3 and V. Duro Affidavit, Applicant’s
Record, Exhibits 1 and 3, Vol. I, pages 170 and 218)
[37]
The
Response describes the Federal involvement in the Generation Project, the EA
process, and the key considerations contained in the JRP Report. It also sets
out the conclusions of the Federal Government and the reasons for its
conclusion that the significant adverse environmental effects of the Generation
Project are justified by its benefits; it also describes the decisions required
of TC and DFO under their respective Acts and the CEAA and responds to
each recommendation of the JRP.
(See
Exhibit R to Bennett Affidavit (NR, Vol. 1 and 3, Applicant’s Record, V. Duro Affidavit,
Exhibit 1, Vol.1, page 170)
[38]
The
Decision determined that the implementation of mitigation measures is required
for the Project to address, inter alia: (a) birds, fish and mammals
and/or their habitat (the caribou); (b) current Aboriginal use of land and
resources for traditional purposes; (c) socio-economic impacts; and (d)
physical and/or cultural heritage. The Decision also required the
implementation of a follow-up program to verify the accuracy of the EA and to
determine the effectiveness of any measures taken to mitigate adverse
environmental effects of the Project for the period extending from October 1,
2012 to October 1, 2037.
(See
Exhibit S to Bennett Affidavit, NR. Vol. 3, and V. Duro Affidavit, Exhibit 2, Vol.
1, page 218)
III. Relevant
legislation
[39]
The
applicable sections of the Canadian Environmental Assessment Act, SC
1992, c 37 and of The Constitution Act, 1982, Schedule B to the Canada Act 1982 (UK), 1982, c 11,
are appended to this decision.
IV. The
issues
[40]
The
Court has framed the issues raised by this application as follows:
1. Is
the Applicant’s challenge of the Project scoping decision statute barred? If
not was it scoped in accordance with section 15 of the CEAA?
2. Did
the Government Respondents properly consider section 16 factors of the CEAA
prior to issuing their Decision and Response pursuant to s 37 of the CEAA?
3. Was
the Applicant properly consulted and accommodated in relation to the Project?
V. Standard
of review and analysis of the first issue:
1. Is
the Applicant’s challenge of the Project scoping decision statute barred? If
not was it scoped in accordance with section 15 of the CEAA?
A. Standard of review
[41]
Determining
the scope of a project under section 15 of the CEAA is a discretionary
exercise to be reviewed on the standard of reasonableness (see Prairie Acid
Rain Coalition v Canada (Minister of Fisheries and Oceans) [Prairie Acid
Rain Coalition], 2004 FC 1265 at para 42; Inverhuron & District
Ratepayers Ass. v Canada (Minister of The Environment) [Inverhuron],
2001 FCA 203; Bow Valley Naturalists Society v Canada (Minister of Canadian
Heritage) [Bow Valley], 2001 CanLII 22029 (FCA), [2001] 2 FC 461) at
para 55; Pembina Institute for Appropriate Development v Canada (Minister of
Fisheries and Oceans), 2005 FC 1123).
B. Analysis
[42]
The
Applicant challenges, albeit indirectly, the Minister of the Environment’s [the
Minister] scoping decision, made pursuant to paragraph 15 (1)(b), to
conduct separate EAs for the Project and the Transmission Link. The Applicant argues
that this amounted to “project splitting”. Citing subsections 15(1) and 15(3)
of the CEAA, the Applicant argues that the Minister unreasonably refused
to exercise his discretion to enlarge the scope of the Project’s EA by not
including the Transmission Link. The Applicant submits that the Transmission
Link is a related construction that was likely to be carried out in relation to
the Project and is now an essential element.
[43]
According
to the Applicant, an inevitable result of this failure to “scope in” the
Transmission Link is that the true negative effects of the actual Project
remain unknown. This, in turn, renders the responsible authorities’
determination (pursuant to paragraph 37(1)(a) of the CEAA) that
the significant adverse environmental effects of the Project could be justified
in the circumstances, unreasonable.
[44]
The
Respondents counter that the judicial review of the Minister’s scoping decision
is statute barred by subsection 18.1(2) of the FCA and that the
Applicant is attempting to indirectly challenge the decision via its arguments
based on paragraph 37(1)(a) of the CEAA and that in any case, the
decision to maintain the scope of the Project as proposed by Nalcor was
reasonable.
[45]
A
scoping decision made under section 15 of the CEAA is unquestionably a
decision made by a “federal board, commission or other tribunal” within the
meaning of subsection 18.1 (2) of the FCA (see Prairie Acid Rain Coalition,
Inverhuron and Bow Valley, above). As such, the Applicant had to
commence its application for judicial review within 30 days after the time the
decision was first communicated. The Court may, however, in its discretion,
grant an extension of time to commence an application (see subsection 18.1 (2) FCA).
[46]
As
a preliminary issue, the Court finds it is necessary to address the pertinence
of the decision in Tzeachten First Nation v Canada (Attorney General),
2007 FC 1131 [Tzeachten 1], to the case at hand. Applying the reasoning
found in Krause v Canada, [1999] FCJ No 179, Justice Lemieux found that
“no extension of time is required […] when the object of the litigation is to
obtain relief in a case where the duty to consult and accommodate reserve and
aboriginal interests is engaged” (Tzeachten 1, above, at para 27). The
limit to file in subsection 18.1(2) FCA does not apply in such cases.
[47]
However,
the decision in Tzeachten 1 is distinguishable from the present case because
it dealt with the aboriginal group’s right to have the Crown’s consultation
process judicially reviewed despite failure to file within the prescribed
delay. Such is not the case in the present instance because if the Court declaring
judicial review of the scoping decisions statute barred will not impact the
judicial review of the consultation process provided to the Applicant. Subsection
18.1 (2) continues to apply.
[48]
The
Project scoping decision was made by the Minister and communicated to the
Applicant on January 8, 2009. It is important to note that the Applicant had
been aware of the Project’s scope since December 2007 when the EIS Guidelines
were released. As for the decision to conduct separate EAs for the Generation
Project and the Transmission Link, Nalcor advised the Applicant of the scope in
February 2009 and the decision was taken in November 2009. Furthermore, the decision
was re-confirmed and communicated to the Applicant on multiple occasions
afterwards, with the last relevant communication occurring on January 31, 2011.
This last confirmation was made in response to a letter sent by the Applicant
on December 16, 2010, conveying its concerns about the scoping decisions to the
Agency, the Province and the JRP. Despite its concern, the Applicant only
commenced its application for judicial review on April 16, 2012.
[49]
In
Harold Leighton et al v Her Majesty in Right of Canada, 2007 FC 553 at
paras 33 and 34, Justice Lemieux summarized the principles that should guide a
decision to grant an extension of time to commence a judicial review:
[33]
To grant or refuse a request for an extension of time to launch a judicial review
application is a matter of discretion which must be exercised on proper
principles. Those principles are well known with the Federal Court of Appeal’s
decision in Grewal v. Canada (Minister of Employment and Immigration),
[1985] 2 F.C. 263, being the seminal case.
[34]
From Grewal, above, and other decisions of the Federal Court of Appeal,
the task at hand is as follows:
•
A number of considerations or factors must be taken into account in the
exercise of the discretion;
•
These factors include: (1) a continuing intention to bring the application, (2)
any prejudice to the parties opposite, (3) a reasonable explanation for the
delay, (4) whether the application has merit i.e., discloses an arguable case
(hereinafter the four-prong test) and (5) all other relevant factors particular
to the case [emphasis mine], see James Richardson International Ltd. v.
Canada [2006] FCA 180 at paragraphs 33 to 35;
•
As explained in Jakutavicius v. Canada (Attorney General) [2004] FCA
289, these factors or consideration are not rules that fetter the discretionary
power of the Court. Once the relevant consideration or factors are selected,
sufficient weight must be given to each of those factors or considerations;
•
The weight to be given to each of the factors or considerations will vary with
the circumstance of each case (Stanfield v. Canada, 2005 FCA 107
(CanLII), 2005 FCA 107);
•
The underlying consideration in an application to extend time is to ensure that
justice is done between the parties. The usual consideration in the standard
four-prong test of continuing intention, an arguable case, a reasonable
explanation for the delay and prejudice to another party is a means of ensuring
the fulfillment of the underlying consideration of ensuring that justice is
done between the parties. An extension of time can be granted even if one of
the standard criteria is not satisfied (Minister of Human Resources
Development v. Hogervrost, 2007 FCA 41; and
•
The factors in the test are not conjunctive (Grewal, above, at pages 11
and 13).
[50]
While
the Court acknowledges that the Applicant has an arguable case, it will not
grant an extension in the present case for the following reasons. Firstly, the
indirect challenge comes two years after the Transmission Link scoping decision
was communicated to the Applicant and the Applicant has failed to request such
an extension. Secondly, the Court is convinced that any delay attributable to a
review of the scoping decision will result in a serious financial prejudice to
the opposing parties (Nalcor and the Government Respondents) and to the public
in general.
[51]
The
Applicant has not petitioned this Court for an extension of time to challenge
the scoping decisions, nor has it offered any reasonable explanation for the two
years that have passed before bringing its application forward on this issue.
This is not surprising given that the Applicant is challenging the decisions
indirectly through subsection 37(1) of the CEAA. The Court underlines
the fact that the Applicant was represented by able counsel throughout the
relevant time frame and should have challenged the scoping decisions at the
first opportunity before even participating in the two EA processes that were
based on them.
[52]
Because
the Applicant neglected to challenge the Minister’s scoping decisions, the EA
processes moved forward. Studies were conducted, meetings were held and serious
investments were made by the proponents to move the Project along. As the
Respondents explain: “To change the scope of the two projects at this time
would require at least one new EA process, the preparation of a new EIS,
reconvening a JRP, scheduling new public hearings, and re-engaging hundreds of
stakeholders, all at great cost, inconvenience and delay”.
•
Was
the Minister’s decision not to expand the scope of the Project proposed by
Nalcor reasonable?
[53]
Regardless
of whether the Applicant’s scoping challenge is statute barred or not, this
Court finds that the Minister’s decision to maintain the scope of the Project
as proposed by Nalcor to be reasonable.
[54]
Under
section 15 of the CEAA, the RAs ((under 15(1) (a)) or Minister
(under 15(1) (b)) have the discretion to determine what elements of a
proposed undertaking will make up a project for the purpose of an EA. In MiningWatch
Canada v Canada (Fisheries and Oceans), 2010 SCC 2, [2010] 1 S.C.R. 6 at para
39 [MiningWatch], the Supreme Court of Canada set limits to this
discretion by deciding that “[…] the minimum scope is the project as proposed
by the proponent, and the RA or Minister has the discretion to enlarge the
scope when required by the facts and circumstances of the project”. Subsections
15(2) and (3) are examples of situations where the RA or Minister may increase
the scope of the project beyond the description proposed by the proponent. “In
sum, while the presumed scope of the project to be assessed is the project as
proposed by the proponent, under s. 15(2) or (3), the RA or Minister may
enlarge the scope in the appropriate circumstances” (MiningWatch, above,
at para 39). The Minister may also enlarge the scope of projects pursuant to
15(1) where the conditions of 15(2) and (3) are not met.
[55]
One
of the harms that subsections 15(2) and 15(3) seek to prevent is referred to as
“project splitting”. The Supreme Court explained that “project splitting”
occurs when a proponent “[…] represent[s] part of a project as the whole, or
propos[es] several parts of a project as independent projects in order to
circumvent additional assessment obligations […]”. The Court then provided an
example of how project splitting could be used to “circumvent additional
assessment obligations”:
Where
the RA or Minister decides to combine projects or to enlarge the scope under s.
15(2) or (3), it is conceivable that the project as proposed by the proponent
might have only required a screening. However, when the RA or Minister
considers all matters in relation to the project as proposed, the resulting
scope places the project in the [Comprehensive Study List]. Where this occurs,
the project would be subject to a comprehensive study (MiningWatch at
para 40).
[56]
In
other words, project splitting can be used as a means to avoid a more rigorous
EA. In the case at bar, the Applicant argues that Nalcor is engaging in a form
of project splitting. By having the Project and Transmission Link undergo
separate EAs, Nalcor, according to the Applicant, is hiding the Project’s true
environmental footprint and can therefore justify more readily its adverse
environmental effects. The Applicant also underlines that the negative impacts
of the Project and the Transmission Link are considered separately, yet the
government’s response considered their positive impacts cumulatively.
[57]
In
order to guide the RAs or Minister in determining whether to expand the scope
of a project beyond that advanced by a proponent, the Agency released an
Operational Policy Statement [OPS] in February 2010, entitled Establishing
the Project Scope and Assessment Type under the Canadian Environmental
Assessment Act. The OPS suggests that when two projects can be considered
“connected actions”, they should generally be scoped together. Two projects are
connected actions when (1) one project is automatically triggered by another;
(2) one project cannot proceed without the other; or (3) both are part of a
larger whole and have no independent utility if considered separately.
[58]
The
Applicant argues that paragraph 15(3) (b) required the Minister “tout au
long de l’évaluation de se pencher sur la question de savoir s’il y a d’autres
opérations susceptibles “d’être réalisées en liaison avec l’ouvrage” […] dont
le promoteur propose la construction” (Applicant’s Record, Vol. 2, page 3663, at
para 158). This interpretation of subsection 15(3) is at odds with the
jurisprudence on the issue of scoping. In Friends of the West Country Assn.
v Canada (Minister of Fisheries and Oceans), 1999 CanLII 9379 (FCA), [2000]
2 FC 263 at para 14 [Sunpine], the Court of Appeal explained that “the
words in subsection 15(3) do not have the effect of rescoping a project to
something wider than what was determined under subsection 15(1)”. That is to
say, subsection 15(3) is only relevant when the RA or Minister initially scopes
the project under subsection 15(1). Once the project is scoped, subsection 15(3)
no longer imposes any obligation on the Minister to expand it. In the Court’s
opinion, the real question to ask in this instance is whether subsection 15(3)
required the Minister to include the Transmission Link when he initially scoped
the Project. The Court finds that he did not have such an obligation for the
following reasons.
[59]
The
Transmission Link was not a “construction, operation, modification,
decommissioning, abandonment or other undertaking in relation to” the Project
(subsection 15(3) of the CEAA). The jurisprudence has interpreted these
undertakings as works “that pertain to the life cycle of the physical work
itself or that are subsidiary or ancillary to the physical work that is the
focus of the project as scoped” (Sunpine, above, at para 20). The Court
of Appeal in Sunpine offered some examples of the type of undertakings
contemplated in subsection 15(3):
[F]or
example, something as major as a coffer dam required to hold back water where
the construction of a bridge required work on a river bed, or of a lesser
order, such as the construction of temporary living quarters for construction
workers (Sunpine, at para 20).
[60]
The
Court agrees with the Respondents that the Transmission Link was not initially
a subsidiary or ancillary undertaking that is part of the life cycle of the
Project. The Transmission Link will not be erected in order to fix, maintain or
decommission the Muskrat Falls dam.
[61]
The
two pertinent subsections are therefore 15(1) and (2).
[62]
Subsection
15 (2) clearly states that the RA or Minister can expand the scope of a project
to include one or more other projects when they are “so closely related that
they can be considered to form a single project”. Subsection 15(2) clearly
contemplates a situation where a proponent attempts to register closely related
projects for separate EAs at or around the same time. As the Respondents
pointed out to this Court, at the time when the Project was registered for its
EA:
“Nalcor
was working to determine transmission options […] [and] had not yet determined:
(a) which market it would pursue (an overland route through Québec to export
markets, routes from Labrador to the Island and through to export markets in
the Maritimes and/or United States, or industrial development in Labrador); or
(the preferred option for meeting domestic Island needs” (NR, page 3355, para
95).
[63]
While
the Transmission Link project existed as one of several options that was
included in the Energy Plan, no decision had been taken when the Project was
registered.
[64]
The
Applicant suggests that the Transmission Link was really a “fait accompli”
and that Nalcor was engaging in project splitting. The evidence in the record,
more specifically the sequence of events, does not support the allegation that
Nalcor was attempting to split the Project in two. Hence, when the decision was
taken by the Minister he properly applied section 15(1) of the CEAA by
scoping the Project as proposed by Nalcor. The Transmission Link was not
automatically triggered by the Project. As the Respondents submit, “[t]he
Generation project was technically and economically feasible on its own for the
purpose of delivering electricity and interconnecting to the existing Labrador
grid” (NR, page 3357, para 100). The initial option contemplated developing Gull Island first for export using the Quebec corridor. Furthermore, the harm that the
Applicant is concerned with (i.e. that the full environmental effects of the
Project not being considered cumulatively with the Transmission Link) is
addressed by paragraph 16(1)(a) of the CEAA which requires an EA
to include “the environmental effects of the project […] and any cumulative
effects that are likely to result from the project in combination with other
projects […] that have or will be carried out”.
[65]
It
is important to note that Nalcor registered the Transmission Link for a
separate EA in January 2009 (two years after the Project was registered). The
Transmission Link was initially tracked as a screening but was later upgraded
to a comprehensive review after the release of the MiningWatch decision.
The two projects were maintained as separate EAs, however. Those decisions were
communicated to the public on April 14th, 2010. Was the decision to
maintain separate EAs for the Project and the Transmission Link reasonable?
[66]
Although
it is clear that, in April 2010, the two projects were so closely related (to
the point where the Transmission Link could not proceed without the Project)
that the RAs might have considered joining them, the Court finds that the
decision to keep two separate EAs was reasonable for the following reasons.
First, given that the Transmission Link project had been upgraded to a
comprehensive study, the harm that subsection 15(2) seeks to prevent (i.e. a
less rigorous EA for one of the projects) was no longer an issue. In addition,
paragraph 16(1)(a) ensured that there was no risk that the two projects’
environmental impacts would be considered independently. In fact, the combined
negative effects of the projects will be considered twice (once in the Project
EA and a second time in the Transmission Link EA).
[67]
Second,
it should be noted that, the Project’s EA was already well underway when the
Transmission Link was registered as indicated by Nalcor:
“the
JRP Agreement was signed; the EIS Guidelines had been issued; Nalcor had filed
its 11,000 page EIS and responded to 165 IRs. […] Restarting the Generation
Project EA to include both projects would have been highly prejudicial to all
parties: (a) causing considerable delay and confusion among stakeholders; (b)
requiring Nalcor to restart the EIS and component studies (which had taken
years to prepare), including, re-review by all stakeholders; and (c)_requiring
Nalcor to adjust the construction schedules for both of the projects (NR, page
3358, para 106).
[68]
In
short, the Court accepts the Respondents’ argument that there was no harm in
maintaining separate EAs, whereas joining them would have wasted a substantial
amount of work and cost a significant amount of money. The main consideration
under the CEAA is that the environmental impact of the Project and the
Transmission Link are considered in a careful and precautionary manner and that
there is meaningful public participation throughout the environmental
assessment process. The Applicant has not convinced this Court that it was
unreasonable not to proceed to a single EA for the Project and Transmission
Link. It is not clear that starting anew with a single EA in April 2010 (i.e.
when the Transmission Link was upgraded to a comprehensive study) would have
significantly increased the quality of the assessment of the environmental
impacts of these projects. Hence, our conclusion that the decision to maintain
the Project and the Transmission Link EAs separate is reasonable given the
circumstances.
VI. Standard
of review and analysis of the second issue:
2) Did
the Government Respondents properly consider section 16 factors of the CEAA
prior to issuing their Decision and Response pursuant to s 37 of the CEAA?
A. Standard
of review
1. Section
16 of the CEAA
[69]
In
Pembina Institute for Appropriate Development v Canada (Attorney General),
2008 FC 302 at para 37 [Pembina], Justice Tremblay-Lamer summarized the
jurisprudence regarding the standard of review to be applied to decisions taken
under section 16 of the CEAA:
All parties agree that to the extent that the issues
posed involve the interpretation of the CEAA, as questions of law, they are
reviewable on a standard of correctness (Friends of West Country Assn. v.
Canada (Minister of Fisheries and Oceans), [2000] F.C. 263, [1999] F.C.J.
No. 1515 (QL), at para. 10; Bow Valley Naturalists Society v. Canada
(Minister of Canadian Heritage), 2001 CanLII 22029 (FCA), [2001] 2 F.C.
461, [2001] F.C.J. No. 18 (QL), at para. 55). However, issues relating to
weighing the significance of the evidence and conclusions drawn from that
evidence including the significance of an environmental effect are reviewed on
the standard of reasonableness simpliciter (Bow Valley, cited
above, at para. 55; Inverhuron, cited above, at paras. 39-40).
[70]
The
issue in the present case is whether the JRP could, despite a lack of certain
information, validly conclude that the Project’s impact on the Applicant’s use
of the land for traditional purposes would be negative but not significant
after mitigating matters are implemented. This is clearly a question dealing
with “weighing the significance of the evidence and conclusions drawn from that
evidence including the significance of an environmental effect”. The standard
of review on such a question is reasonableness (see Pembina, cited
above, at para 37).
[71]
It
is also worth noting that much more recently, in Grand Riverkeeper, Labrador
Inc v Canada (Attorney General), 2012 FC 1520 [Grand Riverkeeper],
Justice Near re-assessed the standard of review applicable to the same question
in light of the four factors described in Dunsmuir v New Brunswick, 2008
SCC 9, [2008 ] SCJ No 9 [Dunsmuir], namely (1) the existence of a
privative clause; (2) the purpose of the tribunal as determined by interpreting
the enabling legislation; (3) the expertise of the tribunal; and (4) the nature
of the question at issue (Dunsmuir, above, at para 64). He also
concluded that the standard of review on such questions is reasonableness (see Grand
Riverkeeper, above, at para 40).
2. Subsections
37(1) and 37(1.1)
[72]
Decisions
taken by responsible authorities upon receipt of an EA report are reviewable on
a standard of reasonableness (see Inverhuron above, at para 32). In Bow
Valley, above, at para 78, Justice Linden described the level of deference
owed to these decisions as follows:
The Court must ensure that the steps in the Act are
followed, but it must defer to the responsible authorities in their substantive
determinations as to scope of the project, the extent of the screening and the
assessment of the cumulative effects in the light of the mitigating factors
proposed. It is not for the judges to decide what projects are to be
authorized, but, as long as they follow the statutory process, it is for the
responsible authorities.
[73]
A
high level of deference for decisions under section 37 was also suggested in Pembina,
above:
The assessment of the environmental effects of a
project and of the proposed mitigation measures occur outside the realm of
government policy debate, which by its very nature must take into account a
wide array of viewpoints and additional factors that are necessarily excluded
by the Panel’s focus on project related environmental impacts. In contrast,
the responsible authority is authorized, pursuant to s. 37(1)(a)(ii), to permit
the project to be carried out in whole or in part even where the project is
likely to cause significant adverse environmental effects if those effects “can
be justified in the circumstances”. Therefore, it is the final decision-maker
that is mandated to take into account the wider public policy factors in
granting project approval (Pembina, above, at para 74).
[74]
The
Government Respondents agree with the findings in Bow Valley
that decisions made by the Governor in Council [GIC] pursuant to subsection
37(1.1) are only reviewable in cases where the statutory process for the EA was
not followed or otherwise acted outside the boundaries of the statute. They
submit that such an understanding of the scope of review is consistent with the
Supreme Court of Canada’s decision in Thorne’s Hardware Ltd et al. v The
Queen et al., [1983] 1 S.C.R. 106, and argue that the motives behind the GIC’s
approval of the federal government’s Response are beyond the Court’s reach.
[75]
In
Canada (Wheat Board) v Canada (Attorney General), 2009 FCA 214 at para
37, Justice Noël described the limits imposed on the Courts’ ability to review
decisions made by the GIC pursuant to a legislative power given to it by
statute as follows:
It
is well-settled law that when exercising a legislative power given to it by
statute, the Governor in Council must stay within the boundary of the enabling
statute, both as to empowerment and purpose. The Governor in Council is
otherwise free to exercise its statutory power without interference by the
Court, except in an egregious case or where there is proof of an absence of
good faith (Thorne’s Hardware Ltd. et al. v. The Queen et al., 1983
CanLII 20 (SCC), [1983] 1 S.C.R. 106, page 111; Attorney General of Canada
v. Inuit Tapirisat of Canada et al., 1980 CanLII 21 (SCC), [1980] 2 S.C.R.
735, page 752).
[76]
This
Court agrees with the above formulation of Justice Noël. As a result, the Court
will only intervene with the GIC and Responsible Ministers’ decisions under subsections
37(1.1) and 37(1) if it finds that: 1) the CEAA statutory process was not
properly followed before the section 37 decisions were made; 2) the GIC or
Responsible Ministers’ decisions were taken without regard for the purpose of
the CEAA or 3) the GIC or Responsible Ministers’ decisions had no
reasonable basis in fact ;which is tantamount to an absence of good faith.
B. Analysis
•
Section
16 challenge to the sufficiency of information before the Government
Respondents in drafting the JRP and making the decisions under subsections
37(1) and 37(1.1).
[77]
The
Applicant argues that the Government Respondents violated section 16 of the CEAA
by failing to properly consider the negative impacts of the Project on the
Applicant’s current use of the land for traditional purposes. It also claims
that the JRP was unable to properly consider the negative impacts on the
Applicant because it lacked certain information on the extent and location of
their current land use of the land. As noted above, the Applicant blames Nalcor
and the Government Respondents for the paucity of information before the JRP.
[78]
Given
the lack of information as to the negative impacts of the Project on the
Applicant and other Quebec aboriginal groups, the Applicant submits that the
decisions taken pursuant to subsections 37(1.1) and 37(1) of the CEAA
were unreasonable. The Governor in Council and Responsible Ministers could not
reasonably conclude that the negative environmental effects of the Project were
justifiable in the circumstances without a complete and thorough understanding
of the severity of those environmental effects.
[79]
While
counsel for the Government Respondents acknowledge that the JRP did not have a
full picture of the current land use by Quebec Aboriginal groups (including the
Applicant) in the Project area, they submit that it possessed sufficient information
to fulfill its mandate under section 16 of the CEAA. Based on the
information before it, the JRP noted that current use in the Project area
appeared to be “seasonal, sporadic and of short duration.” It also noted that
many of the areas reported to be used by Quebec Aboriginal groups were outside
the Project area and would not be affected. The JRP’s conclusion on the issue
went as follows:
Based
on the information on current land and resource use identified through the
environmental assessment process, there are uncertainties regarding the extent
and locations of current land and resource use by Quebec Aboriginal groups in
the Project area. The Panel recognizes that additional information could be
forthcoming during government consultations. To the extent that there are
current uses in the Project area, the Panel concludes that the Project’s impact
on Quebec Aboriginal land and resource uses, after implementation of the
mitigation measures proposed by Nalcor and those recommended by the Panel,
would be adverse but not significant (see page 3148, NR, Vol. 12).
[80]
Counsel
for the Government Respondents concludes that the JRP properly considered the
impact that the Project would have on the current use of the land by Quebec
Aboriginal Groups and more importantly by the Applicant, as required by section
16 of CEAA. They submit that the Governor in Council and Responsible
Ministers had sufficient information on this aspect of environmental effects to
take a reasonable decision pursuant to subsections 37(1.1) and 37(1) of CEAA.
[81]
Nalcor,
for its part, denies that the information available to the JRP was insufficient
and argues that “[t]he reasonableness of the information considered during the
EA pursuant to section 16 must be evaluated in light of the reasonableness of
the EA process, which provided the Applicant with ample opportunities to
provide relevant information” (NR, page 3364). They submit that this argument
must also fail if the federal government is found to have met its duty to
consult. Finally, they remind the Court that the JRP in question was found to
have met its obligations under section 16 in a recent judgment rendered by
Justice Near (see Grand Riverkeeper, above, at para 71).
[82]
The
Court concludes that there is no reason to intervene in the present instance
for the following reasons. Firstly, there is no evidence before this Court that
the statutory process called for by the CEAA was breached. On the
contrary, the CEAA was closely followed and adhered to at every stage of
the process.
[83]
Secondly,
as the Applicant points out, the primary purpose of the CEAA is to
ensure that projects are considered carefully before they are sanctioned by federal
authorities so that they do not cause significant adverse effects (para 4(1)(a)
of the CEAA). The preamble to the CEAA also clearly states that :
“[….] the Government of Canada seeks to achieve sustainable development by
conserving and enhancing environmental quality and by encouraging and promoting
economic development that conserves and enhances environmental quality.” This
goal is subject to the caveat that projects creating significant adverse
environmental effects may still be approved if they are deemed to be
justifiable in light of other considerations (subsection 37(1) of the CEAA).
Consideration of the factors listed in section 16 ensures that the responsible
authorities will have a good appreciation for the potential/likely adverse
environmental effects of a project.
[84]
The
Court finds that on this subject, the JRP possessed sufficient information to
properly assess the likelihood of significant adverse impacts of the Project on
the Applicant’s (and other Quebec Aboriginal groups’) current use of the land
for traditional purposes. While some details on the extent and location of
usage could have been supplemented, the JRP had sufficient documentation and
information before it, namely, testimony from members of Quebec aboriginal
groups and historical documents, to validly conclude that usage in the Project
area is “seasonal, sporadic and of a short duration”. A close review of the
documentation filed by Nalcor with the JRP reveals that the studies conducted
by Hydro-Québec as part of the La Romaine Project together with the Comtois
study and the presentation made by the Applicant in Sept Îles adequately describes
the Applicant’s ties to the caribou that roam on part of the Project’s
footprint. The Court is also satisfied that reasonable efforts were made by the
JRP to acquire a more complete picture of the Project’s impact on the
Applicant. The Court fails to see how further details would have significantly
modified the JRP’s ultimate conclusion in this instance.
[85]
The
JRP carefully considered the issues, noted that certain information was lacking
but still felt confident that the Project’s negative impacts on Quebec
Aboriginal land use in the Project area would be small after the proposed
mitigating measures were put into place, particularly as they pertain to the
caribou. Its conclusion “falls within a range of possible, acceptable outcomes
which are defensible in respect of the facts and law” (Dunsmuir, cited
above, at para 47). This finding also means that the GIC and RAs possessed
sufficient information on the topic to make their decisions pursuant to
subsections 37(1.1.) and 37(1) of the CEAA.
•
Benefits
of the Transmission Link
[86]
The
Applicant contends that the federal government’s response to the JRP report
unreasonably considered the benefits of the Transmission Link in concluding
that the Project’s negative consequences could be justified in the circumstances.
In its Response, the federal government lists the “replacement of non-renewable
generation plants that produce significant green house, and air pollutants”
among the benefits of the Project. The Applicant submits that the only
generation plant the Government could be referring to is the Holyrood
generation plant located on the Island of Newfoundland. They further argue that
Holyrood could not be replaced without the Transmission Link. The Applicant
therefore argues that it is unreasonable to consider the benefits of the
Transmission Link while ignoring its negative impacts. Since the two projects
were scoped separately, the Applicant contends that they should not be
considered together because the Transmission Link is still undergoing its EA and
has yet to be approved. They posit that including the benefits of the
Transmission Link was, therefore, premature.
[87]
According
to the Applicant, the fact that the Response considers the benefits of the
Transmission Link is also evidence that the Project has been substantially
modified. The Applicant argues that the “true project” that is being approved
and intended on being built is not the one described in the Report but rather
that of the Muskrat Falls dam with the Transmission Link. The Gull Island dam has, according to the Applicant, either been abandoned or indefinitely
postponed. This situation creates a significant problem according to the
Applicant because it entails an indefinite approval for Gull Island. The dam would hang over the land like “the sword of Damocles”. It is further submitted
that the George River caribou herd is currently experiencing an alarming
decline in numbers and that the construction of Gull Island at a later date,
without further assessment, could be potentially disastrous for the herd.
[88]
Nalcor
and the Government Respondents both reply that there is nothing in the CEAA
which prevents the government from considering the benefits of related or
unrelated projects. On the contrary, both argue that it would be unreasonable
to consider a project in isolation and ignore any benefits accruing from other
projects. In addition, Nalcor argues that “while the Response considers the
Transmission Link, it does not focus on it exclusively” (NR, page 3366). The
economic analysis conducted by NRCan (a study the federal government relied on)
“considers the economic viability of the Generation Project as a whole, as well
as an assumption that only one or the other component might proceed […] [and
concluded that] any of these scenarios could be economically viable” (NR, page
3366).
[89]
Nalcor
equally insists that it still intends to move forward with Gull Island but that it must clear its gateway process before moving any further. The fact that
there is currently no determined start date for the Gull Island dam does not
mean that it will not be built. Nalcor considers that the only significant
change that has occurred relates to the sequencing of the construction of the
two dams. What is more, according to Nalcor the impact of switching the order
of construction was already considered in detail during the EA. It referred the
Court to IR JRP 165. Nalcor also points to section 24 of the CEAA to
substantiate its position that there is no indefinite approval of Gull Island. That section, according to Nalcor, is designed to prevent the precise harm
that the Applicant is concerned about. If the construction of Gull Island does not proceed within a reasonable timeframe, section 24 of the CEAA will
apply and require that a new EA be conducted.
[90]
The
Court accepts the Respondents’ argument on this issue. In addition to the
points they raised above, the Court adds the following. Under paragraph 16(1)(a)
of the CEAA, a JRP must take into account the cumulative environmental
effects of prior and future projects. Given that the negative impacts of a
future project must be taken into account in an EA, the Court considers that
the positive impacts can also be weighed in just as well. Section 16 does not
preclude such an exercise.
[91]
The
Applicant’s concerns regarding the approval of Gull Island is fundamentally a
scoping argument which the Court has already concluded to be statute barred in
this instance. The Applicant submits that Gull Island should have been removed
or “scoped out” of the Project. The Supreme Court of Canada already decided
that the minimum scope of a project “is the project as proposed by the
proponent” (see MiningWatch, above, at para 39). The scope of the
Project can then be increased but not decreased. The rationale is easy to
understand. Why would a proponent propose a project larger than they intended
to build? They would only be rendering the EA process more onerous for no valid
reason. Furthermore, section 24 of the CEAA will prevent the indefinite
approval of any component of a project which is not built within a reasonable
timeframe.
•
Economic
Feasibility and Alternatives
[92]
The
Applicant argues that the GIC and Responsible Ministers unreasonably ignored
the JRP’s conclusions and recommendations regarding the adequacy of the
economic studies produced by Nalcor and the need to examine alternatives. The
JRP concluded in section 4.2 as follows:
The
Panel concludes that Nalcor’s analysis that showed Muskrat Falls to be the best and least cost way to meet domestic demand requirements is inadequate and
an independent of economic, energy and broad-based environmental considerations
of alternatives is required.
[93]
In
its Response, the federal government noted that it had two economic analyses
(one by NRCan and another by Manitoba Hydro International [MHI]), which
“concluded by supporting Nalcor’s assertions that the Project represents the
least cost option for meeting anticipated electricity demand” (NR, Vol. 3, page
0601). The Applicant contends that these studies could not corroborate each
other because the analysis conducted by NRCan evaluated the Project as
originally proposed (Gull Island followed by Muskrat) whereas MHI and Nalcor’s
looked at Muskrat Falls together with the Transmission Link.
[94]
The
Court cannot find a reviewable error on this issue. The JRP fulfilled its
purpose under para 4(1)(a) of the CEAA by alerting the
responsible authorities to its conclusion that Nalcor’s economic analysis was
inadequate. The federal government disagreed with the JRP on the basis that
another analysis corroborated Nalcor’s. The federal government’s decision on
this issue had, therefore, a reasonable factual basis. It is important to
reiterate that it is not this Court’s role to decide whether or not the Nalcor
and MHI’s analyses are correct and to reassess the weight to be assigned to one
study over another, but rather to determine whether the federal government’s
decision rests on a reasonable basis. As Justice Sexton reasoned in Inverhuron,
above:
The
environmental assessment process is already a long and arduous one, both for
proponents and opponents of a project. To turn the reviewing Court into an
"academy of science" - to use a phrase coined by my colleague Strayer
J. (as he then was) in Vancouver Island Peace Society v. Canada[12] -
would be both inefficient and contrary to the scheme of the Act (Inverhuron,
above, at para 36).
[95]
The
evidence before the Court indicates that the federal government was properly
informed on the potential negative environmental impacts of the Project.
Furthermore it reasonably justified its decision to proceed in this instance
after having weighed the benefits against the negative environmental impacts
from its national perspective. As the Court reviewed the Response and Decision,
it is clear that both are carefully considered decisions that balance competing
objectives.
VII. Standard of review and
analysis of the third issue:
3) Was
the Applicant properly consulted and accommodated in relation to the Project?
A. Standard
of Review
[96]
In
Dunsmuir, above, at para 62, the Supreme Court of Canada
indicated that the first step in determining the appropriate standard of review
is to “ascertain whether the jurisprudence has already determined in a
satisfactory manner the degree of deference to be accorded with regard to a
particular category of question”. If the case law has, then the inquiry ends
there and the established standard of review should be followed.
[97]
The
standard of review to be applied in cases where the “government’s conduct is
challenged on the basis of allegations that it failed to discharge its duty to
consult and accommodate pending claims resolution” was first discussed in Nation
v British Columbia (Minister of Forests), 2004 SCC 73 at para 60 [Haida].
Applying the principles established by Haida, the consensus in the case
law is that a question regarding the existence and content of the duty to
consult is a legal question that attracts the standard of correctness. A
decision as to whether the efforts of the Crown satisfied its duty to consult
in a particular situation involves “assessing the facts of the case against the
content of the duty” (Ka’a’Gee Tu First Nation v Canada (Attorney General),
2007 FC 763 at para 91 [Ka’a’Gee]). This is a mixed question of fact and
law to be reviewed on the standard of reasonableness.
[98]
It
is clear from the facts of this case that the federal government understood its
duty to consult the Applicant on the Project. Ultimately, the question to be
answered on this issue is whether the federal government satisfied the Crown’s
duty to consult and accommodate the Applicant in the present case. The standard
of review is reasonableness. The question is then: Did the Crown make
reasonable efforts to satisfy the duty to inform and consult incumbent upon
them? (See Haida, above, at para 62).
B. Analysis
•
What
was the scope of the Crown’s duty to consult and accommodate?
[99]
In
order to decide whether the Crown fulfilled its duty to consult, the Court
needs to determine the scope or content of that duty. The Supreme Court, in Haida,
above, found that the scope of the duty to consult it “is proportionate to
a preliminary assessment of the strength of the case supporting the existence
of the right or title, and to the seriousness of the potentially adverse effect
upon the right or title claimed” (Haida, above, at para 39).
[100]
At
the low end of the spectrum, that is to say, where there is little evidence
supporting the existence of a right, the importance of the right to the
Aboriginal peoples small, and the potential impact of the proposed action on
that right limited, the duty may only be “to give notice, disclose information
and discuss any issues raised in response to the notice” (Haida at para
43). When the opposite is true, that is when “a strong prima facie case
for the claim is established, the right and potential infringement is of high
significance to the Aboriginal peoples, and the risk of non-compensable damage
is high” (Haida at para 44) then deep consultation may be required. Deep
consultation may involve “the opportunity to make submissions for
consideration, formal participation in the decision-making process, and
provision of written reasons to show that Aboriginal concerns were considered
and to reveal the impact they had on the decision.” (Haida at para 44).
Even in cases where the duty to consult is at the lower end of the spectrum, the
duty requires that aboriginal peoples’ concerns be taken seriously and, where
possible, mitigation measures implemented (Mikisew Cree First Nation v
Canada (Minister of Canadian Heritage), 2005 SCC 69, [2005] 3 S.C.R. 388 at
para 64 [Mikisew]).
[101]
Regardless
of where the Crown’s duty to consult lies on this spectrum, “the controlling
question in all situations is what is required to maintain the honour of the
Crown and to effect reconciliation between the Crown and the Aboriginal peoples
with respect to the interests at stake. Pending settlement, the Crown is bound
by its honour to balance societal and Aboriginal interests in making decisions
that may affect Aboriginal claims” (Haida at para 45). A key requirement
in honourable consultation is responsiveness (Taku River Tlingit First Nation v British Columbia (Project Assessment Director), 2004 SCC 74 at
para 25 [Taku River]).
[102]
The
case law has also clearly established that consultation is not a “one way
street” and there exists an obligation for both parties to actively engage in
the process. As Justice Finch explained in Halfway River First Nation v
British Columbia (Ministry of Forests), 1999 BCCA 470 at para 161 [Halfway
River]:
There
is a reciprocal duty on aboriginal peoples to express their interests and
concerns once they have had an opportunity to consider the information provided
by the Crown, and to consult in good faith by whatever means are available to
them. They cannot frustrate the consultation process by refusing to meet or
participate, or by imposing unreasonable conditions: see Ryan et al v. Fort
St. James Forest District (District Manager) (25 January, 1994) Smithers
No. 7855, affirmed (1994), 40 B.C.A.C. 91.
Preliminary assessment of the strength
of the claim
[103]
The
Applicant has filed a number of documents testifying to the Ekuanitshit’s
traditional use of the land in and around the Project
area for hunting small and large game, particularly caribou. Such
documents include: 1) A 1983 study by Robert Comtois, Occupations et
utilisation du territoire par les Montagnais de Mingan conducted in support
of the Ekuanitshit’s claims in the federal government’s comprehensive land
claims process (the “Conseil Attikamek Montagnais [CAM] negotiations); 2) an
archeological study by Hydro-Québec (Applicant’s Record, Vol. X, page 3181); 3)
historical and archeological reports produced by Nalcor (Applicant’s Record,
Vol. X, pages 3113, 3121 and 3122).
[104]
The
federal government has never questioned the strength of the Ekuanitshit’s claim
and, as the Applicant points out, already accepted it for the purpose of
negotiating a treaty in 1979 (the CAM negotiations). While Nalcor initially
claimed that the information they possessed did not provide any evidence of the
Applicant’s historical or contemporary use of the land in the Project area,
they later submitted a number of documents testifying to it. Those documents
include: 1) the CAM; (2) 11 Aboriginal consultation updates filed by Nalcor
with the JRP; and (3) Nalcor’s responses to information requests number JRP.2
and 1S/2S. In light of the uncontradicted evidence
adduced, the Court concludes that the Applicant has a strong prima facie
case for land use rights in the Project area.
The seriousness of the potentially
harmful effect
[105]
The
Court recognizes that caribou are at the very heart of Ekuanitshit culture. The
Applicant is particularly concerned about the future of the caribou living in
and around the Project area. During the JRP hearings, Chief Piétacho explained
the respect that members of the Innu nation have for the caribou and how
important they were to the nation’s survival. For historical reasons, including
the creation of the Mingan reserve and the imposition of the Indian Residential School system, there was a break with the Applicant’s caribou hunting
tradition in Labrador. During the JRP hearings, Chief Piétacho explained that
the Ekuanitshit are now returning to Labrador to hunt caribou and perpetuating
their traditional ties to the caribou.
[106]
Regarding
the potential adverse effects of the Project on the caribou, the JRP report
paints a nuanced picture. Due to a number of factors, the Red Wine Mountains herd is already a species at risk and it is unclear whether the herd, with or
without the Project, can be saved. Nevertheless, the JRP concluded that “in
light of the current state of the herd and the cumulative effects on its
recovery, the Project would cause a significant adverse environmental effect on
the Red Wine Mountain caribou herd” (NR, Vol. 12, page 3096).
[107]
While
the Ekuanitshit no longer depend on the caribou for their survival and have
only recently resumed hunting them in the Project area the animal’s cultural
significance should not be underestimated. Furthermore, the Court considers
that in this case, reconciliation demanded that the federal government consult
and take measures within its legislative powers to ensure that this traditional
activity be maintained. This duty becomes even more evident as the Court
acknowledges the fact that the federal government is partially to blame for the
Applicant’s break with tradition (cf. the residential schooling system). Given
that the Applicant presents a strong prima facie case for its claim and
that the potential for adverse effects on a culturally significant right is
high, this Court finds that the Applicant was entitled to more than minimum
consultation. The Applicant’s concerns needed to have been seriously addressed and
mitigating measures needed to have been included in the Project.
•
Preliminary
issues
Is judicial review premature?
[108]
The
Government Respondents argue that the Applicant filed its application for
judicial review before the federal government’s consultation period came to an
end. Consultation did not come to end with the GIC’s Order in Council.
According to the Federal Consultation Framework, the process is now in Phase V:
Regulatory permitting. Consultation is to continue up until TC and DFO issue
permits allowing Nalcor to pose acts that will obstruct navigable waterways or
destroy fish habitat.
[109]
The
Government Respondents rely on Justice Barnes’ decision in Gitxaala v Canada
(Transport, Infrastructure and Communities ) 2012 FC 1336 at para
54 [Gitxaala] where he found that an application for judicial
review based on a claim that Crown consultation was inadequate is premature if
“the effective end-point in the process of consultation has not been reached”
.In that same paragraph he also noted that the Supreme Court of Canada in Haida
,above, explained that “there are a variety of remedies available for a
failure to consult not the least of which is the opportunity at later stages in
the process to engage in meaningful dialogue and, where necessary, to
accommodate First Nations concerns”. Justice Barnes’ conclusion was that the First
Nations groups could be heard again if “the process proves to be deficient or
perfunctory” (Gitxaala, above, at para 54).
[110]
The
Applicant argues that consultation and accommodation must not only be evaluated
when final permits are issued but also when ““strategic, higher level
decisions” that may have an impact on Aboriginal claims and rights” are taken (Rio
Tinto Alcan Inc v Carrier Sekani Tribal Council, 2010 SCC 43 [2010] 2 SCR
650 at para 44 [Carrier Sekani]). The decisions taken pursuant to subsections
37(1) and 37(1.1) are not only “higher level decisions” but their effect is to
release the Project from the EA process and will, in turn, have a substantial
influence on the permit granting decisions.
[111]
The
Government Respondents reply that Carrier Sekani, above, refers to
decisions that trigger or engage the duty to consult, not the duty to evaluate
the consultation process (Carrier Sekani, above, at para 43). In this
case, the consultation process began long before the decisions under review
were made. The consultation process is still ongoing and should not be judged
until it is over.
[112]
The
Court finds that judicial review of the federal government’s consultation and
accommodation process is premature at this stage. One of the goals of
consultation and accommodation is to “preserve [an] Aboriginal interest pending
claims resolution” (Haida, cited above, at para 38). This requires that
Aboriginal groups be consulted and accommodated before the rights they lay
claim to are irrevocably harmed. While it is true that preparatory work for the
Project has begun, the acts that truly put the Applicant’s rights and interests
at risk are those which require permits issued by TC and DFO. It is premature
to evaluate the federal government’s consultation process before those
decisions are made. Notwithstanding this finding, the Court considers it should
nonetheless review and assess the adequacy of the consultation that has taken
place up to the moment when this application for judicial review was filed.
Constitutive elements of the
Crown’s consultation
[113]
The
Applicant claims that the federal government’s consultation consisted of one
letter sent to the Applicant on September 9th, 2009, requesting
comments on the JRP report. The Government Respondents allege that this is an
inaccurate caricaturization of the federal government’s consultation in this
case. The federal government emphasized in their Consultation Framework that
the second and third phases of Crown consultation would take place within the
context of the JRP’s EA process. The Government Respondents remind the Court
that it is now a well accepted practice that Crown consultation can take place
through the CEAA’s EA process (see Quebec (Attorney General) v Moses,
2010 SCC 17, [2010] 1 S.C.R. 557 at para 45; Taku River, above, at paras 2
and 22; and Gitxaala, above, at para 50). The Court is satisfied
that the consultations conducted by the JRP during the EA constituted federal
government consultation.
Consultation
[114]
The
Applicant’s participation in the Project EA began early on in the process, at
the planning stage. The Canadian Environmental Assessment Agency (the “Agency”)
and the Provincial Department of Environment and Conservation (the “NLDEC”)
invited the Applicant to comment on their draft Environmental Impact Statement
Guidelines (“Draft Guidelines”). The Applicant responded by submitting comments
on what information it felt Nalcor should include in its EIS in order to assist
the Joint Review Panel [JRP] in carrying out the EA. The Applicant was also invited
to comment on the draft JRP Agreement and to nominate JRP members.
[115]
The
Applicant acknowledged that it was actively involved in the EA process. To fund
that participation, the Agency granted the Applicant the full amount it
initially requested through its participant funding program (an initial $55,
850.25 and an additional $11, 105.00 upon further request later on in the
process). Through this funding, the Applicant was able to present written
submissions regarding Nalcor’s EIS which subsequently informed the JRP’s IR
process. The IRs elicited a number of responses from Nalcor on issues that
concerned the Applicant, including: (a) the Red Wine Mountain and Lac Joseph
caribou herds; (b) monitoring and follow-up; (c) waterfowl survey methodology
and; (d) Aboriginal consultation.. The Applicant made further comments on the
adequacy of Nalcor’s responses which, in turn, led the JRP to make additional
IRs. Altogether the IRs resulted in 250 pages of further information.
(See Exhibits
A-251, U,V,W to Bennett Affidavit, pages 113, 681, 693 and 1061, NR, Vol. 1, 3,
4 and 5)
[116]
The
Applicant also presented his oral submissions at the JRP community Hearing
session which took place, at its request, in Sept-Îles on April 7, 2011. Chief
Piétacho and 4 other community elders testified on the Ekuanitshit’s use of the
land to be affected by the Project. The Applicants also played a video of other
elders describing the Ekuanitshit’s traditional
voyages from Mingan to as far as “Tshishe-shastshit” in Labrador. Simultaneous
translation of the proceedings was provided. The Court had the benefit of
viewing part of the video that was presented and finds it admissible in the
record as evidence of the representations made by the Applicant.
[117]
In
response to the Applicant’s concerns regarding the nefarious effects of the
Project on their use of the land, Nalcor introduced a number of mitigating
measures. For example, with regards to the caribou, Nalcor proposed to:
“-consider
the timing of construction and other activities and restricting access when
caribou are in the area;
-reduce
wildlife mortality by posting speed limits and implementing a no harassment/no
harvesting policy;
-arrange
work schedules to minimize travel in designated areas during calving and
post-calving periods;
-remove
trees from the riparian zone surrounding the reservoirs;
-
monitor both the Red Wine Mountain and George River herds to ensure that
predictions of Project effects are accurate including evaluating effects of
habitat loss and alteration, increased access and changes in predator-prey
dynamics;
-
design monitoring and follow-up programs to allow for the identification of
cumulative effects by referencing applicable management plans and consulting
with regulators;
-
monitor daily and seasonal road and river crossings by caribou and traffic
access;
-
provide support for telemetry work to monitor caribou population numbers, calf
survival, and movement and distribution patters;
-
monitor the Red Wine Mountain caribou herd through ongoing participation with the
Labrador Woodland Caribou Recovery Team, including support of satellite GPS
monitoring and other work directly related to the effects of the Project; and
-monitor
the George River caribou herd through the participation with the George River
Caribou Herd Co-Management Team” (NR, Vol. 12, page 3093).
[118]
The
Court notes the conclusion reached by the JRP with respect to the Applicant’s
claims. Pages 185-186 of the JRP Report read:
Based
on the information on current land and resource use identified through the
environmental assessment process, there are uncertainties regarding the extent
and locations of current land and resource use by Quebec Aboriginal groups in
the Project area. The Panel recognizes that additional information could be
forthcoming during government consultations. To the extent that there are
current uses in the Project area, the panel concludes that the Project’s impact
on Quebec Aboriginal land and resource uses, after implementation of the
mitigation measures proposed by Nalcor and those recommended by the Panel,
would be adverse but not significant (NR, page3148).
[119]
Based
on the foregoing, it is clear that the Applicant’s concerns were taken
seriously and that several mitigating measures were introduced into the Project
in response.
[120]
The
Applicant, however, maintains that the Crown failed to meet its duty to consult
in two major respects. First, the Crown did not adequately inform the
Ekuanitshit on both their contemporary use of the land in the Project zone and
on the negative impact that the Project would have on their rights. Second, the
Crown failed to sufficiently accommodate the Applicant on the predicted
negative impacts of the Project on their rights.
Failure to
inform
[121]
The
JRP concluded that while the Project’s negative impact on the Applicant’s land
use would not be significant, uncertainties remained as to the location and
extent of the Applicant’s current use of the land in the Project area. The JRP
noted that such information might become available during the course of further
consultation with the federal government. The Applicant stresses that this
never happened.
[122]
While
the Respondents maintain that the information provided during the EA process
was sufficient to satisfy the federal government’s duty to consult, they note that
Nalcor and the Applicant made numerous attempts to negotiate a Community
Consultation Agreement [CCA]. The CCA was intended to provide the Applicant the
capacity to present information on their current land use in the Project area.
The parties were unable to come to an agreement for several reasons including:
Methodology
[123]
The
Applicant believed that a similar approach to that taken by Hydro-Québec in the
La Romaine project should have been adopted. This method would have involved
the hiring of an “expert to carry out a study on the Innus of Ekuanitshit [and]
his or her work would be supported by community liaison officers paid by the
proponent and would be supervised by a Nalcor-Ekuanitshit joint committee” (NR,
page 1402). Nalcor considered the approach the Applicant put forward but
ultimately opted for an approach where the community would hire a Nalcor funded
consultation officer who would work “in close cooperation with Nalcor personnel
to collect data, disseminate information and prepare reports” (NR, page 1408).
Duration
[124]
Nalcor
believed “that the activities described in the draft agreement [could] be
implemented over a four month period” whereas the Applicant found this estimate
to be “unrealistic and impractical” (NR, page 1408).
Cost and scope
[125]
Nalcor
estimated a budget of approximately $87,500 for the activities described in
their draft consultation agreement. Again, the Applicant believed this estimate
to be unrealistic. The Applicant maintained its position throughout
negotiations that the type of study required was one similar to that performed
for the La Romaine project. The Hydro-Québec environmental impact study
included multiple studies for which the estimated cost was $600,000. Nalcor
considers that given the data available from the Comtois study and those
conducted by Hydro-Québec for La Romaine, a study of similar magnitude was not
required to uncover the scope and location of the Applicant’s current use of
the land in the Project area for traditional purposes.
[126]
It
is clear in the jurisprudence that the duty to consult does not imply a duty to
agree (Haida, above, at para 42). What is required is a “commitment […]
to a meaningful process of consultation” (Haida, above, at para 42).
When the Court applies these principles to the CCA negotiations, it finds that
Nalcor was committed to provide the Applicant with a meaningful opportunity to
update existing information regarding their current use of the land in the
Project area.
[127]
For
one, the Court does not agree with the Applicant that a study similar in scope
and kind to that performed for the La Romaine project was required in this
case. A fair amount of information already existed on the Applicant’s use of
the land in the Project area (i.e. Comtois study and those of Hydro-Québec for La
Romaine). Indeed, that information, in addition to the testimonies made during
the JRP hearing in Sept-Îles on April 7th, was sufficient enough for
the JRP to conclude that the Project would not have a significant impact on the
Applicant’s current land use. The Court agrees that the methodology proposed by
Nalcor was reasonable in this instance. The Applicant referred the Court to the
results of a study conducted by another Quebec based Innu group, the Pakua
Shipi, who accepted the $87,500 Nalcor offer and terms of reference. The
Applicant argued that it rightly rejected Nalcor’s proposal since the result of
the study were inconclusive and lacked scientific rigor.
[128]
The
Applicant also claims that the consultation process was deficient in that Innu
Nation received preferential treatment which is contrary to the principle established
in Hlalt First Nation v British Columbia (Environment), 2011 BCSC 945
[129]
The
Court finds that it was incumbent on the Applicant, having decided that the
funding and amount of time offered were insufficient, to present a counter
offer that demonstrated that it was truly engaged in the process. As the Court
reviewed the correspondence exchanged in the negotiations, it indicates that
the Applicant denounced the successive offers made by Nalcor but remained on
its position that an in-depth study similar to La Romaine was required. Given
the difference in terms of impact on the rights of the Applicant between the
Project (two dams in Labrador) and La Romaine (4 dams in close proximity to their
reserve), the Court is of the opinion that the Applicant’s position
“frustrate[d] the consultation process […] by imposing unreasonable conditions”
(Halfway River, above, at para 161).
[130]
Phase
IV of the federal government’s Consultation Framework covers the period after
the release of the JRP report up until the Decision and Response. In conformity
with the Framework, the Agency sent the Applicant a letter on September 9th,
2011 soliciting comments on the JRP report within a delay of 45 days. The Applicant
responded within the delay with a 22 page submission requesting that the
federal government refrain from authorizing the Project before:
“1) avant qu’une étude sérieuse ne soit complétée
sur l’utilisation historique et contemporaine par les Innus de Ekuanitshit du
territoire visé par le projet, y compris les effets négatifs potentiels du
projet;
2) plus, précisément, sans qu’une étude complète
sur les effets potentiels sur la harde de caribous du Lac Joseph ne soit
produite et avant qu’un programme de suivi exhaustif de la harde de caribous
des monts Red Wine ne soit mis sur pied, au sujet desquels les Innus de
Ekuanitshit devraient être consultés (Applicant’s Record, Vol. VII, pages 2088-2089, 2101-2102)”.
[131]
The
Crown did not reply to the Applicant’s request and four months later the
Project was released from the EA process. The Court agrees with the Applicant
that the federal government should have responded to that letter. As noted
above, responsiveness is a key requirement of honourable consultation (Taku
River, above, at para 25).This misstep, however, does not mean that the
consultation process, as a whole, should be deemed inadequate. As Justice
Barnes noted in Gitxaala, above, the consultation process must be
reasonable, not perfect.
[132]
Furthermore,
while the federal government did not respond to the Applicant’s letter
regarding the Lac Joseph herd, its concern was addressed by the mitigating
measures proposed in the JRP report and confirmed in the Decision (see NR: vol.
3, p. 638). Nalcor chose to focus on the Red Wine herd in its EIS (i.e. to use
it as its “key indicator”) because it was the species most at risk. The
mitigating measures introduced to prevent serious harm to the Red Wine caribous
can also be applied to the Lac Joseph herd (see NR, Vol. 8, page 1914).
[133]
The
Court believes it should underline that subsection 37(2) of the CEAA
requires a responsible authority to adopt a course of action under paragraph
37(1)(a) to “ensure that any mitigation measures referred to in that
paragraph in respect of the project are implemented”. Should the federal
government fail to do so, the Applicant may have that decision not to implement
the mitigation measures recommended judicially reviewed.
Insufficient accommodation
[134]
The
Applicant submits that the Crown has failed to establish why the Applicant
should not be accommodated to the same extent as, for example, the Innu nation.
The Applicant points to the Impact and benefits agreements [IBA] that Nalcor
signed with Innu Nation in 2008 called “Tshash Petapen” which not only includes
employment opportunities but commercial participation and even royalties.
[135]
The
Court finds that the mitigating measures proposed by Nalcor and the JRP to
minimize the negative impact on the Ekuanitshit’s rights substantially
satisfy the federal government’s duty to consult and accommodate within its
jurisdiction. The federal government’s Response confirmed that these
measures will be made an integral part of the project. [Emphasis added]
[136]
While
the traditional rights of the Applicant in question are culturally significant,
the impact the Project will have on them cannot be compared to the impact it
will have on Innu Nation. One obvious difference is that the Project will be
located on or in closer proximity to the land where the Innu Nation lives and
to which it claimed title. The Project will inevitably affect more than one
significant aspect of their lives.
[137]
In
conclusion, this application is dismissed because the Applicant was adequately
consulted, mitigation measures addressed its concerns with respect to its usage
of the territory in the Project area and, in any case, the scoping issue is
statute barred. Finally, the Court also finds that judicial review of the
consultation process is premature.
JUDGMENT
THIS
COURT’S JUDGMENT is that the application is dismissed. In view
of the general importance of some of the issues raised by this application the
Court orders that the Respondents jointly pay 25% of Applicant’s costs.
“André F.J. Scott”