Docket: T-1347-13
Citation:
2015 FC 492
Ottawa, Ontario, April 17, 2015
PRESENT: The
Honourable Madam Justice Strickland
BETWEEN:
|
NUNATSIAVUT
GOVERNMENT
|
Applicant
|
and
|
ATTORNEY GENERAL OF CANADA
(DEPARTMENT OF FISHERIES
AND OCEANS)
|
Respondent
|
and
|
HER MAJESTY IN RIGHT OF
NEWFOUNDLAND AND LABRADOR AS
REPRESENTED BY THE MINISTER OF THE
DEPARTMENT OF ENVIRONMENT
AND CONSERVATION
|
Second Respondent
|
and
|
NALCOR
ENERGY
|
Third Respondent
|
I. The Project 4
II. Factual Background. 5
Phase 1: Initial Engagement and
Consultation on the Draft JRP Agreement, the Appointment of the JRP Members and
the EIS Guidelines. 12
Phase 2: JRP Process Leading to Hearings. 15
Phase 3: Hearings and Preparation of the
JRP Report 18
Phase 4: Consultation on the JRP Report 20
Phase 5: Regulatory Permitting. 29
III. Issues. 42
Issue 1: What is the Standard of Review?. 43
Applicant’s Position. 43
Canada’s Position. 44
Nalcor’s Position. 44
Analysis.. 45
Issue 2: What was the Content of the Duty to Consult
and Accommodate, More Specifically: 57
A.......... Does the Agreement Exhaustively Define
the Crown’s Duty to Consult? 57
Applicant’s
Submissions. 57
Canada’s Submissions. 58
Nalcor’s Submissions. 58
Analysis. 59
B........... What was the Scope and Extent of the
Duty to Consult and Accommodate in this Case? 66
Applicant’s
Position. 66
Canada’s
Position. 68
Nalcor’s Position. 69
Analysis. 71
(i) The Agreement 71
(ii) Scope of Duty to Consult at Common Law.. 76
Issue 3: Was the Applicant Adequately Consulted and
Accommodated?. 90
A.......... Preliminary Issues. 90
(i) Collateral
Attack. 90
(ii) Delegation
of Authority. 96
B........... Was the Applicant Adequately Consulted
and Accommodated?. 99
Applicant’s
Position. 99
Canada’s
Position. 101
Nalcor’s
Position. 105
Analysis. 109
(a) Discrete Consultation Issues. 109
i. Adequacy of Consultation in Phases 1-3. 109
ii. Aboriginal Consultation Report 111
iii. Section 11.6.2 Procedure. 115
iv. May 1, 2008 Letter 117
v. Failure to Identify the Applicant in
Canada’s Response. 118
(b) Adequacy of Consultation prior to Issuance of
Authorization. 118
(c) Accommodation. 124
vi. High Level Management Structure. 127
vii. Comprehensive Downstream Assessment 128
viii. Framework Language for Compensation. 143
ix. Full Clearing. 143
IV. Conclusion. 149
JUDGMENT AND REASONS
[1]
This is an application for judicial review
pursuant to ss 18 and 18.1 of the Federal Courts Act, RSC 1985, c-7 (“Federal
Courts Act”), by which the Applicant challenges the decision of the
Minister of Fisheries and Oceans to issue Authorization No. 13-01-005
(“Authorization”) to Nalcor Energy (“Nalcor”). The Authorization was issued on
July 9, 2013 and, pursuant to ss 32(2)(c) and 35(2)(b) of the Fisheries Act,
RSC 1985, c F-14 (“Fisheries Act”), it permits impacts to fish and fish
habitat arising from the construction of the Muskrat Falls hydroelectric
generation facility proposed by Nalcor for the lower Churchill River as part of
the Lower Churchill Hydroelectric Generation Project in Labrador.
[2]
The Applicant claims that it was not properly
consulted and that concerns of Labrador Inuit were not fully and fairly
considered or adequately accommodated by Canada, as represented by the
Department of Fisheries and Oceans (“DFO”), in the decision to issue the
Authorization.
[3]
Nalcor proposed to develop two hydroelectric
generation facilities on the lower Churchill River in central Labrador with a
combined capacity of 3,047 megawatts (“MW”). The project would consist of two
dams located at Muskrat Falls (824 MW) and at Gull Island (2,250 MW), two
reservoirs, and transmission lines connecting Muskrat Falls, Gull Island and
the existing Churchill Falls hydroelectric facility. Additional facilities
would include access roads, temporary bridges, construction camps, borrow pits
and quarry sites, diversion facilities and spoil areas (“Project”) (as
described in the Report of the Joint Review Panel: Lower Churchill
Hydroelectric Generation Project dated August 2011(“JRP Report”)).
[4]
Given the nature of the Applicant’s claim, it is
necessary to set out, in some detail, the factual background of this matter,
its legislative backdrop and the relevant provisions of the Labrador Inuit
Land Claims Agreement, between The Inuit of Labrador, Her Majesty The Queen
in Right of Newfoundland and Labrador, and Her Majesty The Queen in Right of
Canada, 22 January 2005 (“Agreement”), which was given force of law pursuant to
the Labrador Inuit Land Claims Agreement Act, SNL 2004, c L-3.1 and the Labrador
Inuit Land Claims Agreement Act, SC 2005, c 27.
[5]
On November 30, 2006 Nalcor submitted a project
registration and description document for the Project with the Newfoundland and
Labrador Department of Environment and Conservation (“NL DEC”) and the Canadian
Environmental Assessment Agency (“Agency”), to initiate the provincial and
federal environmental assessment processes pursuant to the Newfoundland and
Labrador Environmental Protection Act, SNL 2002, c E-14.2 (“NL EPA”)
and the Canadian Environmental Assessment Act, SC 1992, c 37 (“CEAA”).
The Agency was responsible for coordinating federal Aboriginal consultation
during the environmental assessment of the Project, and for acting as the Crown
Consultation Coordinator as described in the Consultation Framework
described below.
[6]
Transport Canada (“TC”) and DFO determined that
an environmental assessment was required because, to proceed, the Project would
require approval pursuant to s 5(1) of the Navigable Waters Protection Act,
RSC 1985, c N-22 (“NWPA”) as it involved dam construction, and an
authorization pursuant to s 35(2) of the Fisheries Act as it would
likely result in the harmful alteration, disruption or destruction of fish
habitat, thereby triggering s 5(1)(d) of the CEAA. TC and DFO each
identified themselves as a “responsible authority”
(“RA”) as defined in the CEAA, being a federal authority that is
required to ensure that an environmental assessment (“EA”) is conducted (CEAA,
ss 2(1), 11(1)). Health Canada identified itself as being in possession of
specialist or expert information or knowledge necessary to conduct the EA, as
did Environment Canada (“EC”), Natural Resources Canada (“NRC”), and Aboriginal
Affairs and Northern Development Canada (then Indian and Northern Affairs
Canada).
[7]
In response to a December 4, 2006 opinion
request from NL DEC, DFO advised Newfoundland and Labrador (the “Province”) on
January 12, 2007 that, amongst other things: an Environmental Impact Statement
(“EIS”) was recommended in order to address the potential impacts on fish and
fish habitat; the potential for bioaccumulation of mercury should be assessed
in all fish species; a discussion of potential downstream effects should be
provided; Nalcor should consider and discuss methods to reduce the release of
mercury into the reservoir, thereby reducing mercury uptake and accumulation;
and, the effects of changes to fish and fish habitat downstream of Muskrat
Falls and/or Lake Melville should be discussed.
[8]
On February 9, 2007 a Notice of Commencement of
an Environmental Assessment for the Project was posted on the Agency Registry,
which initiated an EA of the Project under the CEAA. Because DFO was of
the opinion that the Project was likely to cause significant adverse
environmental impacts, the federal Minister of Environment ultimately
determined that a joint Canada-Newfoundland and Labrador EA, to be conducted by
an independent review panel pursuant to ss 25(a) and 29 of the CEAA,
being the most stringent of the EA review options under that legislative
regime, was appropriate.
[9]
Prior to making that determination, the Minister
of Environment, as represented by the Minister of Lands and Natural Resources,
wrote to the Applicant on May 30, 2007, advising of his intent to refer the
proposed Project to a joint Canada-Newfoundland and Labrador review panel,
referred to as the Joint Review Panel (“JRP” or “Panel”) for the EA and
advising that the Agency had been asked to contact the Applicant to discuss the
next steps in the process.
[10]
On August 8, 2007 DFO and TC wrote to the
Applicant concerning the Project and, as required by s 11.2.8 of the Agreement,
provided the Project registration document. The letter explained that DFO had
determined that the proposed damming and formation of the reservoirs would
likely cause a harmful alteration, disruption or destruction of fish habitat
and, therefore, that authorizations under the Fisheries Act would be
required. Further, that TC had determined that the NWPA approvals would
likely be required because a dam was a named work under Part I of the NWPA,
those regulatory requirements being triggers for an EA pursuant to s 5(1)(d) of
the CEAA. The letter also advised that DFO and TC were arranging
consultations with Aboriginal groups to hear and understand their views about
how they might be affected by the granting of the authorizations and approvals
to construct and operate the Project, and invited participation.
[11]
Prior to this, DFO had met with representatives
of the Applicant and other Aboriginal groups in Goose Bay, Labrador on October
19 and 20, 2006 to discuss DFO’s role with respect to the EA and to identify their
early positions and perspectives about the Project. At that time the Applicant
had noted, amongst other things, that it should be consulted as, while the
Project was not on Labrador Inuit Lands (“LIL”) or in the Labrador Inuit
Settlement Area (“LISA”), which terms are defined in the Agreement, it could
affect the zone where the Applicant has harvesting rights pursuant to ss
12.13.10 and 12.13.13 and Schedule 12-E of the Agreement. The Applicant
further noted that consultation should be in accordance with the Agreement.
[12]
In March 2007 the Province provided DFO with
draft Environmental Impact Statement Guidelines (“EIS Guidelines”) for
comment. The preface of the draft EIS Guidelines stated that they were
intended to assist the proponent with the preparation of the EIS, the purpose
of which was to identify the important environmental impacts associated with
the undertaking, to identify appropriate mitigation and produce a statement of
residual effects for evaluation by the Minister of Environment and Conservation.
With respect to the EIS to be prepared by Nalcor, the EIS Guidelines stated
that, “The contents of the EIS will be used by the
Minister of Environment and Conservation, in consultation with Cabinet, to
determine the acceptability of the proposed project based on anticipated
impacts, proposed mitigation, and severity of unmitigable residual impacts from
the proposed undertaking”. DFO reviewed the draft and made comments
including that the study area boundary should include areas downstream of Muskrat
Falls (Upper Lake Melville) where biological effects may be expected to occur.
[13]
DFO and the Agency met with the Applicant in
Goose Bay on September 18, 2007 at which time the need for input by the
Applicant into the EIS was noted and a copy of the draft EIS Guidelines was provided.
The draft EIS Guidelines were made available to the public for review on
December 19, 2007. More than fifty interested parties responded. The
Applicant provided comments on February 22, 2008, referencing the potential application
of consultation provisions as found in the Agreement and seeking, amongst other
things, an expanded study area for the EIS.
[14]
On June 6, 2008 the Assistant Deputy Minister
for the NL DEC responded to the Applicant’s comments on the draft EIS Guidelines,
noting that they had been reviewed by both governments and that the Province
was responding with the consent of the Agency. It noted that the draft EIS
Guidelines had been significantly modified to include consideration of the
interests and knowledge of Aboriginal groups and communities, the Applicant in
particular. Further, that s 7.0, Consultation with Aboriginal Groups and
Communities, had been completely revised and that a list of the Aboriginal
groups and communities to be consulted by Nalcor when preparing the EIS,
including the Applicant, was now included. A table responding to the
Applicant’s comments, on a point by point basis, was attached to the letter,
which also stated that should further explanation be required, the Applicant,
upon request, would be provided with a meeting with both governments in an
effort to resolve any outstanding concerns with the draft EIS Guidelines.
Absent such a request, the Province and Canada would proceed to finalize the
EIS Guidelines.
[15]
The finalized EIS Guidelines were issued by
Canada and the Province in July 2008. Ultimately, the EIS Guidelines did not stipulate
specific geographic boundaries for the EIS, but required Nalcor to provide
rationale for delineating the study area boundaries as it did (EIS Guidelines,
s 4.4.2). They also required that in its EIS, Nalcor assess whether the
Project may reasonably be expected to have adverse environmental effects on the
LISA (EIS Guidelines, s 4.2.5).
[16]
The EIS Guidelines described the EA as a process
for identifying a Project’s potential interactions with the environment,
predicting environmental effects, identifying mitigation measures and
evaluating the significance of residual environmental effects. The document
also stated that if the Project proceeded, the EA process would provide the
basis for setting out the requirements for monitoring and reporting to verify
compliance with the terms and conditions of approval and the accuracy and
effectiveness of predictions and mitigation measures (EIS Guidelines, s 2.1). Aboriginal
and public participation, aboriginal traditional and community knowledge, the
precautionary principle (EIS, Guidelines, ss 2.2, 2.3 and 2.5) and other
matters were identified as basic principles of an EA. Regarding consultation
with Aboriginal groups, the EIS Guidelines stated:
4.8 Consultation with Aboriginal
Groups and Communities
The EIS shall demonstrate the Proponent’s
understanding of the interests, values, concerns, contemporary and historic
activities, Aboriginal traditional knowledge and important issues facing
Aboriginal groups, and indicate how these will be considered in planning and
carrying out the Project.
To assist in ensuring that the EIS provides
the necessary information to address issues of potential concern to these groups,
the Proponent shall consult with each group for the purpose of:
(a) Familiarizing the group with the
Project and its potential environmental effects;
(b) Identifying any issues of concern
regarding potential environmental effects of the Project; and
(c) Identifying what actions the
Proponent is proposing to take to address each issue identified, as
appropriate.
[17]
Prior to this, in February 2008 the Government
of Canada had released the Aboriginal Consultation and Accommodation:
Interim Guidelines for Federal Officials to Fulfill the Legal Duty to Consult
(“Interim Consultation Guidelines”). The evidence of DFO was that these
Interim Consultation Guidelines established that consultation by Canada
with Aboriginal groups was to be conducted by way of a “whole
of government approach” and should be integrated with the EA process to
the extent possible. Further, that to the best of DFO’s ability, the Project
consultations were conducted with reference to the Interim Consultation
Guidelines throughout the Project until the issuance of the Aboriginal
Consultation and Accommodation: Updated Guidelines for Federal Officials to
Fulfill the Duty to Consult in March 2011 (Affidavit of Ray Finn, Regional
Director of Ecosystems Management, Newfoundland and Labrador Region, DFO dated
22 October 2013 (“Finn Affidavit”), paras 35-36).
[18]
On May 1, 2008 the Province wrote to the
Applicant, with the consent of the Agency, advising that both levels of
government wished to work with the Applicant to ensure that their respective obligations
under the Agreement were met. In that regard, they had reviewed the Agreement
with respect to obligations concerning “undertakings”, as defined in the
Agreement, and identified ss 11.2.2, 11.2.8, 11.2.9 and 11.5.11 as key items
for consideration. The Province and the Agency proposed and attached a draft
process (“Draft Consultation Process”) as a means to achieve those
obligations. This proposal divided the EA process into its constituent parts
and indicated how the Applicant would be consulted at each stage of the
process.
[19]
On August 13, 2010 Canada issued the Federal
Aboriginal Consultation Framework for the Lower Churchill Hydroelectric
Generation Project (“Consultation Framework”). The Agency sent the Consultation
Framework to the Applicant on August 20, 2010. It states that it sets out
additional detail as to how the federal government would rely on the JRP
process, to the extent possible, to assist in fulfilling its legal duty to
consult Aboriginal groups with respect to the proposed Project. It identifies
the Agency as being responsible for coordinating federal Aboriginal
consultation during the EA and that the Agency would also fulfill the role of
Crown Consultation Coordinator. As such, the Agency would ensure that the
activities described in the Consultation Framework were carried out and
that Aboriginal groups were well informed. On September 7, 2010 the Agency met
with representatives of the Applicant. The minutes of the meeting indicate
that they were asked if they had any comments on the Consultation Framework.
The response was that it was fine as it was fairly generic and contained
nothing unexpected, however, that 45 days to prepare for the hearings was too
short and it should be 90 days. At this meeting, the Applicant also expressed
its view that the Project area as described by Nalcor was inadequate as it did
not include Lake Melville.
[20]
The Consultation Framework appears to
follow the same general process as the May 2008 Draft Consultation Process, but
with further detail. It divides the consultation into the following five
phases, which are adopted below for convenience:
•
Phase 1: Initial
engagement and consultation on the draft JRP Agreement, the appointment of the
JRP members and the EIS Guidelines;
•
Phase 2: JRP
process leading to hearings;
•
Phase 3: Hearings
and preparation of the JRP Environmental Assessment Report (JRP Report);
•
Phase 4:
Consultation on the JRP Report; and
•
Phase 5:
Regulatory permitting.
The evidence of DFO is that the Agency led
the consultation in Phases 1-4, whereas DFO did so in Phase 5 (Affidavit of
Stephen Chapman, Associate Director, Regional Operations, with the Agency,
dated 22 October 2013 (“Chapman Affidavit”), paras 130, 132).
[21]
Phase 1 included initial engagement and the
preparation of the EIS Guidelines, the related consultation for which is
described above. It also included consultation on the draft JRP agreement (“JRP
Agreement”), draft JRP terms of reference (“TOR”), and Panel selection.
[22]
On May 7, 2008 the Province, with the consent of
the Agency and in accordance with Draft Consultation Process, provided the
Applicant with the draft JRP Agreement and the draft TOR in advance of making
these publicly available for comment on June 6, 2008. The Applicant was
invited to provide comments and was advised that these would be given full and
fair consideration and that a written response would be provided prior to the
execution of the JRP Agreement and TOR. The Applicant could also request a
meeting with the Province and the Agency in an effort to resolve any concerns
with the draft JRP Agreement and TOR. The Applicant did not provide any
comments on these documents.
[23]
The JRP Agreement and TOR were finalized and
released in January 2009. Subsequently, these were amended to extend the
comment period for the EIS by 30 days for three Aboriginal groups, including
the Applicant, and to provide for translation of certain JRP documents into
Aboriginal languages, including Inuktitut.
[24]
The JRP Agreement required the Panel to conduct
the EA in a manner that discharged the requirements of the CEAA, NL
EPA and TOR. All JRP hearings were to be public and to provide for the
participation of Aboriginal groups, the public, governments, Nalcor and other
interested parties. Upon completion of the EA, the JRP was to prepare a report
which would address the factors to be considered under s 16 of the CEAA
and s 65 of the NL EPA, set out the rationale, conclusions and
recommendations of the JRP relating to the EA, including any mitigation
measures and follow-up program, and include a summary of issues raised by
Aboriginal groups, the public, governments and other interested parties (JRP
Agreement, ss 4.2, 4.3 and 6.3).
[25]
The TOR set out the scope of the EA and the
steps in the EA process. With respect to the scope, it specifically addressed
Aboriginal rights as follows:
Aboriginal Rights Considerations
The Panel will have the mandate to invite information
from Aboriginal persons or groups related to the nature and scope of potential
or established Aboriginal rights or title in the area of the Project, as well
as information on the potential adverse impacts or potential infringement that
the Project/Undertaking will have on asserted or established Aboriginal rights
or title.
The Panel shall include in its Report:
1. information provided by Aboriginal persons or groups
related to traditional uses and strength of claim as it relates to the
potential environmental effects of the project on recognized and asserted
Aboriginal rights and title.
2. any concerns raised by Aboriginal persons or groups
related to potential impacts on asserted or established Aboriginal rights or
title.
The Panel will not have a mandate to make
any determinations or interpretations of:
• the validity or the strength of any Aboriginal group’s
claim to aboriginal rights and title or treaty rights;
• the scope or nature of the Crown’s duty to consult
Aboriginal persons or groups;
• whether Canada or Newfoundland and Labrador has met its
respective duty to consult and accommodate in respect of potential rights
recognized and affirmed by s. 35 of the Constitution Act, 1982; and
• the scope, nature or meaning of the Labrador Inuit Land
Claims Agreement.
[26]
By letter of May 13, 2008 the Province invited
the Applicant to propose three nominees for consideration for appointment to
the JRP. The Applicant proposed one nominee, Dr. Keith Chaulk, who was
subsequently appointed as one of the five JRP members.
[27]
Phase 2 concerned the JRP process leading up to
the public hearings, including consultation on the EIS and additional
information requests (“IR”). The Applicant was one of eleven groups who
received participant funding pursuant to s 58(1.1) of the CEAA. It
received $23,471 for participation in Phase 2.
[28]
On February 17, 2009 Nalcor submitted its EIS to
the JRP. The EIS, together with its component studies, comprised over 10,000
pages and incorporated a number of baseline studies and other information. The
JRP then initiated a 75-day public consultation process on the EIS. The public
consultation process was subsequently extended by 30 days as some Aboriginal
groups had not received notification of their participant funding until after
the public review period had commenced.
[29]
On June 19, 2009 the Applicant provided a
detailed response to the JRP in respect of the EIS. This included its view
that the study area of the EIS should be expanded, that the EIS contained no
support for the statement that there was no reasonable possibility the Project
would have an adverse environmental effect in the LISA, and, that the follow up
program should include Lake Melville with focus on water temperature, salinity,
primary production and methylmercury levels in fish and marine mammals.
[30]
Based on the comments received and the JRP’s own
questions, 166 IRs regarding the EIS were sent to Nalcor in five rounds by the
JRP. Nalcor responded to each IR, submitting approximately 5000 pages of
additional documentation. The JRP invited the public, Aboriginal groups and
governments to review the additional information received from Nalcor and to
provide comments.
[31]
On December 18, 2009 the Applicant submitted its
comments to the JRP with respect to the additional information submitted by
Nalcor. Nalcor responded to the submissions on February 16, 2010.
[32]
On February 15, 2010 the JRP wrote to the
Applicant advising that the information provided to date by Nalcor was
insufficient and that additional information was required before it could
conclude on the sufficiency of the EIS for the purpose of proceeding to public
hearings. It advised that it had sent additional IRs to Nalcor, and encouraged
the Applicant to participate and to provide information regarding traditional
land and resource use to Nalcor. It also invited the Applicant to provide to
the JRP information related to the nature and scope of Aboriginal rights or
title in the Project area and any potential adverse impacts or potential
infringement of the Project on those rights or title, all as set out in the
TOR. The JRP repeated this request on December 3, 2010.
[33]
During this time there were also various
communications between the Applicant, the Agency and the JRP. On January 14,
2011, the JRP determined that the EIS along with the information submitted in
response to the IRs contained sufficient information to allow it to proceed to
the public hearings phase of the EA.
[34]
On February 16, 2011 the Agency and DFO met with
the Applicant to provide information on the hearings process and the process
for consultation on the JRP Report. At this time the Applicant also discussed
issues of concern to it, including downstream impacts. DFO advised of its
position that there was not enough evidence in the EIS to back up Nalcor’s
conclusion that there would be no downstream effects in Lake Melville and that
DFO, Health Canada and other federal departments would make a joint
presentation on mercury concerns during the relevant public hearing.
[35]
On February 21, 2011 DFO provided to the JRP a
summary of its views on the EIS and related recommendations. DFO supported
removal of all vegetation in the reservoir footprints and three meters above
the full supply level prior to impoundment to lessen the extent of mercury
release, but did not make a recommendation to that effect. Further, because it
was possible that mercury bioaccumulation as a result of the Project may be
observed at a greater magnitude, for longer periods and further downstream than
predicted by Nalcor, DFO recommended that Nalcor be required to develop a
comprehensive program to monitor spatial and temporal changes in mercury in
fish within the reservoirs and downstream following reservoir creation. The
frequency and timing of sampling supporting a clear assessment of the magnitude
and timing of changes and informed determinations as to risks to human health
and implementation of fisheries management measures. Further, DFO recommended
that more baseline data be collected on mercury levels in estuarine fish
downstream of Muskrat Falls and in Goose Bay in advance of inundation.
[36]
Phase 3 included the public hearings and the
preparation of the JRP Report. The JRP held 30 days of hearings in nine
locations in Newfoundland and Labrador and in Quebec between March 3 and April
15, 2011. The Applicant made written submissions and participated in the
public hearings, raising concerns about environmental, social, cultural and
health effects of the Project, emphasizing the downstream effects, including
methylmercury. In its written submissions the Applicant proposed
recommendations and mitigation measures, including an accord between the
Applicant and Nalcor concerning baseline establishment and monitoring of
effects and compliance as a condition of approval, as well as clearing of all
wood and brush within reservoir boundaries. DFO participated in the hearings,
as did other parties.
[37]
The JRP Report was issued on August 25, 2011. It
is a comprehensive, 355 page document which describes the process leading to
its issuance and, for each topic addressed in the report, sets out Nalcor’s
views, the views of the participants and the JRP’s conclusions and
recommendation(s) concerning that topic. In total, the JRP made 83
recommendations, should the Project be approved. In Chapter 17, the Panel’s
Concluding Comments, and as summarized in the executive summary, the JRP
reported that it had determined that the Project would be likely to have
significant adverse effects in the areas of: fish habitat and fish assemblage;
terrestrial, wetland and riparian habitat; the Red Wine Mountain caribou herd;
fishing and seal hunting in Lake Melville should consumption advisories be
required; and, culture and heritage. It also identified a range of potential
Project benefits, as well as crucial additional information required before the
Project should proceed in the areas of long-term financial returns, energy
alternatives to serve island needs, and reducing uncertainty about downstream
effects. The JRP noted that it did not make the final decision about whether
the Project should proceed but that government decision-makers would have to
weigh all effects, risks and uncertainties in order to decide whether the Project
was justified in the circumstances and should proceed in light of the
significant adverse environmental effects identified by the JRP.
[38]
Chapter 6, Aquatic Environment, is particularly
relevant to the issues raised by the Applicant in this application. There the
JRP described the views of Nalcor and the participants on a number of issues
including the fate of mercury and downstream effects. It identified the key
issues that emerged from the review process which included: the effects of
reservoir preparation; the fate of methylmercury in reservoirs; downstream
effects below Muskrat Falls and the likelihood that Project effects, including
bioaccumulation of mercury, would be seen in Goose Bay or Lake Melville; and
follow-up monitoring. Related to this are findings in Chapters 4, 8, 9, 10 and
13.
[39]
The JRP was not convinced that all effects
beyond the mouth of the river would be “non-measurable”
as defined by Nalcor. It stated that while effects in Lake Melville were more
difficult to predict on the basis of existing information, this emphasized the
need for a precautionary approach, particularly because no feasible adaptive
management measures had been identified to reverse either long-term adverse
ecological changes or mercury contamination of renewable resources.
[40]
The JRP concluded that, based on the information
before it, it was unable to make a significance determination with respect to
the risk of long term alteration of ecological characteristics in the estuarine
environment. There was a risk that mercury could bioaccumulate in fish and
seals in Goose Bay, and possibly in Lake Melville populations as well, but this
would probably not represent a risk to the health of these species. While the
implications on health and land use were addressed elsewhere in the JRP Report,
Recommendation 6.7 addressed the need to take a precautionary approach to
reduce uncertainty regarding both the potential ecological and mercury effects
downstream. As described in more detail later in these reasons, Recommendation
6.7 suggested that prior to impoundment, Nalcor be required to carry out a
comprehensive assessment of downstream effects, including baseline mercury data
collection and revised modelling to predict the fate of mercury in the
downstream environment.
[41]
The significance of the potential for downstream
mercury effects on Aboriginal and non-Aboriginal land and resource use, and on
human health and communities was discussed by the JRP in Chapters 8, 9, and 13.
[42]
Phase 4 concerned consultation on the JRP Report
and recommendations. The Applicant was provided with funding in the amount of
$21,000 by the Agency’s participant funding program to support its engagement
at this stage.
[43]
On August 31, 2011 the Applicant wrote to the Premier
of the Province generally endorsing the JRP Report and highlighting key issues,
including potential bioaccumulation of mercury downstream and the importance of
fishing and seal hunting to Inuit, and requesting a meeting. A second request
followed which was responded to on November 8, 2011. In its response, the
Province referenced the September 16, 2011 meeting that the Applicant had with
the Agency, DFO, EC, and NL DEC, described below.
[44]
On September 9, 2011 the Agency wrote to the
Applicant advising that consultation on the JRP Report and its conclusions and
recommendations would be conducted to fulfill any applicable duty to consult
that each government may owe to any Aboriginal government or group. The letter
requested that, prior to the governments taking any decision or course of
action which would enable the Project to proceed, the Applicant prepare and
submit its views on the JRP Report to the two governments within 45 days of the
public release of the oral translation in Inuktitut of the JRP Report’s
Executive Summary. The letter stated that this consultation would seek to
establish the Applicant’s views on whether all concerns about potential impacts
of the Project on Labrador Inuit’s rights under the Agreement had been
characterized accurately and on the manner and extent to which any recommended
mitigation measures might serve to accommodate those concerns. Further, to
determine whether there remained any outstanding issues. Full and fair
consideration would be given to such views and, where requested, the
governments would meet with the Applicant to discuss its views on the JRP
Report. The Agency advised that this consultation would inform reports to the
federal and provincial Cabinets concerning the consultation process with the
Aboriginal groups.
[45]
On September 16, 2011 representatives of the
Agency, DFO, EC and NL DEC met with representatives of the Applicant in Goose
Bay to discuss consultation on the JRP Report. With respect to the process of
consultation, the Agency’s meeting notes indicate that in response to the
Applicant’s question of which government would respond to the JRP Report and to
the responses of the Aboriginal groups, the Agency advised that the responses
from Cabinets would very likely be general and a rationale may not always be
given. However, that the departments would provide a rationale to the
Aboriginal groups to the best of their ability as soon as possible after the Cabinets’
responses. If the Applicant advised which recommendations were most important
to it, the Agency and departments could focus on those in developing
rationale. With respect to monitoring of downstream effects, the Applicant put
forward its views, including that a comprehensive holistic approach to arctic
science in Lake Melville should be funded, Inuit led and carried out utilizing
ArcticNet, and, that specific wording for consumption advisories should be
developed. The August 30, 2013 Affidavit of Tom Sheldon, the Applicant’s
Director of Environment (“Sheldon Affidavit”), indicates that he also
emphasized the need for implementation of Recommendation 6.7 and agreed with
the JRP’s recommendation for full clearing of the Muskrat Falls reservoir as
well as the need for an agreement between Nalcor and the Labrador Inuit
regarding further mitigation given the JRP’s conclusions and report (Sheldon
Affidavit, para 32).
[46]
On November 11, 2011 the Applicant submitted the
Nunatsiavut Government Response to Panel Report. This acknowledged that
the Applicant had spent considerable time participating in the EA process in
order to assert its views that the Project would have potential negative
effects on Labrador Inuit and their rights and title, environment, culture and
way of life. This participation had included approximately 30 separate
submissions to the JRP and the Applicant stated that it was pleased that the
JRP had found many of its concerns to be valid and that it agreed with many of
the JRP’s recommendations.
[47]
The submissions recited the JRP’s findings with
respect to downstream effects; referenced a recent study on the human health
effects of prenatal and childhood exposure to environmental contaminants, such
as methylmercury, on the health and development of Inuit children in northern
Quebec that was released subsequent to the Panel hearings; included a table
setting out its response to each JRP Recommendation; and, set out three major
recommendations that the Applicant submitted would help to mitigate impacts on
Inuit and Inuit rights and to allow Inuit to constructively contribute to the
Project process going forward. These are summarized as follows:
- Inuit representation on management structure
This asserted a fundamental right to
participate as a part of a high level management mechanism for the proposed
Project which would consist of the Nunatsiavut Government, the Innu Nation, the
Province and Canada;
- Inuit rights, Inuit research – baseline studies and monitoring
This asserted a right of Inuit to conduct
and lead baseline research and monitoring into a broad suite of potential
impacts that the Project would have on Inuit and Inuit rights. It also
asserted a moral and legal obligation on Nalcor, Canada and the Province to
fund this, and requested a minimum of $200,000 per year for a program
specifically designed to establish baseline conditions directly related to
Inuit rights. The Applicant asserted a need for a large scale, comprehensive
understanding of the downstream environment and how changes would impact Inuit
(biophysical, cultural, socioeconomic and health impacts). It asserted that research
should be led by Inuit, who would collaborate with Nalcor and governments, and
who would utilize ArcticNet for this purpose; and
- Compensation related to impacts on Inuit and Inuit rights as a
result of the Project
This asserted that framework language should
be included as a condition of permits associated with the development of the
Project to ensure that Inuit have a mechanism for compensation if any listed
impact, including losses related to harvesting and cultural practices and
unplanned events, should arise.
[48]
On December 21, 2011 the Applicant wrote to the
Premier of the Province (Canada was copied on the letter) requesting a meeting
between senior political levels of the Province, Nalcor and the Nunatsiavut
Government prior to the announcement of the Province’s response to the JRP
Report. The Premier responded the following day, and a meeting was held on
January 9, 2012. The meeting was attended by representatives of the Applicant
and the Province.
[49]
By letter of January 16, 2012 to the Minister of
Natural Resources for the Province (cc’d to the Ministers for DFO, EC and
others), the Applicant set out four core mitigative measures proposed during
that meeting. These included the three major recommendations in the
Applicant’s response to the JRP Report (summarized above), as well as Inuit
priority for jobs, training and business opportunities associated with the
Project, second only to Innu.
[50]
On January 24, 2012 the Agency prepared an
internal report entitled Lower Churchill Hydroelectric Generation Project:
Report on Aboriginal Consultation Associated with the Environmental Assessment
(“Aboriginal Consultation Report”) which states that it describes how
the federal government consulted with Aboriginal groups in the context of the
EA, in particular, how it had relied on the JRP process, to the extent
possible, to assist in discharging its legal duty to consult. The report
states that it describes the positions of the Aboriginal groups with respect to
how the potential adverse environmental effects of the proposed Project may
impact their potential or established Aboriginal or treaty rights, which
information was derived from presentations the Aboriginal groups made to the
JRP and from comments made by the groups directly to federal government department
officials.
[51]
On January 30, 2012 Ray Finn, DFO’s Regional
Director of Ecosystems Management, Newfoundland and Labrador Region, prepared a
memorandum for DFO’s Regional Director General for Newfoundland and Labrador
(“DFO Regional Director General”) which provided an update on the EA for the
Project and on consultations to that point with Aboriginal groups. Amongst
other things, the background section of the memorandum noted that DFO had
participated in Aboriginal consultation on the JRP Report, led by the Agency,
during the review and development of Canada’s response. Further, that the Innu
Nation and Nunatsiavut Government “are generally
supportive of the project”, while the Nunatsiavut and Innu groups of
Quebec believed they were not adequately considered during the JRP process.
Under the “Analysis / DFO Comment” section, it is noted that Canada’s response
was currently being completed for submission to Cabinet on February 8, 2012 and
that DFO would participate in the review and finalization of the Aboriginal
Consultation Report to ensure Aboriginal concerns had been addressed, where
appropriate, prior to Canada making its decision.
[52]
The Government of Canada Response to the
Report of the Joint Federal-Provincial Review Panel for Nalcor’s Lower Churchill
Generation Project in Newfoundland and Labrador (“Canada’s Response”),
which responded to the JRP Report and its recommendations, was approved by the
Governor General, on the recommendation of the Minister of Fisheries and
Oceans, pursuant to s 37(1.1)(a) of the CEAA, by Order-in-Council dated
March 12, 2012. It was published on the Agency Registry on March 15, 2012. The
Province’s response was issued on the same day.
[53]
Canada’s Response states that it was prepared by
the RAs (DFO, TC and NRC) pursuant to s 37(1.1) of the CEAA, in
consultation with other federal agencies. It states that in preparing the
response, the RAs reviewed the JRP Report, as well as a subsequent independent
supply report commissioned by Nalcor, an economic analysis of the Project that
was conducted by Canada, and comments submitted by Aboriginal groups and other
stakeholders during and following the JRP process.
[54]
In considering whether the significant adverse
environmental effects of the Project could
be justified in
the circumstances, Canada’s Response stated that it accounted for the potential
adverse effects of the Project, the commitments that had been made by the
federal government in relation to the recommendations provided in the JRP
Report, and the commitments made by Nalcor in its EIS and during the JRP
hearings. Canada would require certain mitigation measures, environmental
effects monitoring and adaptive management be undertaken by Nalcor, as well as
require additional studies on downstream effects. This would be done through
inclusion of the requirements in federal authorizations and approvals.
Canada’s Response stated that ensuring that those commitments were carried out
would minimize the negative effects of the Project and reduce the risks
associated with the uncertainty about the success of mitigation measures.
[55]
Further, Canada’s Response stated that the
potential social, economic and environmental benefits for the Province,
communities and Aboriginal groups, as well as benefits beyond the Province,
were also considered, as was an economic analysis of the Project that was
conducted by Canada.
[56]
Canada determined that the expected significant
energy, economic, socio-economic and environmental benefits outweighed the significant
adverse environmental effects of the Project identified in the JRP Report:
Therefore the Government of Canada concludes
that the significant adverse environmental effects of the Lower Churchill
Hydroelectric Generation Project are justified by the benefits of the Lower
Churchill Hydroelectric Generation Project.
(Canada’s Response, p 8)
[57]
As to the Course of Action Decision, Canada’s
Response noted that s 37(1.1)(c) of the CEAA indicates that the RAs’
course of action shall be in conformity with the approval of the
Governor-in-Council, and that, pursuant to s 37(1), if the Project is likely to
cause significant adverse environmental effects that can be justified in the
circumstances, the RAs may exercise any power or duty that would permit the
Project to be carried out, in whole or in part. As such:
[…] Fisheries and Oceans Canada and
Transport Canada may issue any subsection 35(2) and s. 32 Fisheries Act
authorizations and any Part 1, Section 5 of the Navigable Waters Protection
Act approvals associated with the Project, respectively…
Under, [sic] subsection 37(2.2) of the Canadian
Environmental Assessment Act, a Responsible Authority is required to ensure
the implementation of mitigation measures for an approved Project. Similarly,
under subsection 38(2) of the Canadian Environmental Assessment Act, the
Responsible Authorities will ensure the implementation of follow-up programs
that determine the accuracy of the conclusions of the environmental assessment
and the effectiveness of the mitigation measures.
(Canada’s Response, pp 8-9)
[58]
Canada’s Response then addressed each of the JRP
Recommendations that were directed to the federal government.
[59]
As to Recommendation 6.7, Canada’s Response
stated that the Government of Canada agreed with the intent of that
recommendation and noted that it was directed to Fisheries and Oceans Canada.
It went on to say that, as a condition of a s 35(2) authorization under the Fisheries
Act, and prior to impoundment, DFO would require Nalcor to collect
additional baseline data on bioaccumulation of methylmercury in fish and on
fish habitat downstream of Muskrat Falls. DFO would also require Nalcor to
conduct a comprehensive multi-year program to monitor and report on
bioaccumulation of methylmercury in fish (including seals) within the
reservoirs and downstream, including the Goose Bay/Lake Melville area, and to
carry out multi-year post-project monitoring and reporting downstream into Lake
Melville on a variety of parameters including nutrients, primary production,
fish habitat utilization and sediment transport in order to assess changes to
downstream fish habitat.
[60]
On March 16, 2012, in conformity with the
Governor-in-Council’s approval of Canada’s Response, the three RAs issued their
course of action decision pursuant to s 37(1) of the CEAA (“Course of
Action Decision”). The Course of Action Decision stated that the RAs may
exercise any power or perform any duty or function with respect to the Project
because, after taking into consideration the JRP Report and the implementation
of appropriate mitigation measures, the RAs were of the opinion that the
Project is likely to cause significant adverse environmental effects that can
be justified in the circumstances. The Course of Action Decision noted that a
follow-up program to verify the accuracy of the EA and/or determine the
effectiveness of any mitigation measures was required for the Project, and that
the estimated dates of the follow-up program were October 1, 2012 to October 1,
2037.
[61]
Phase 5 of the consultation process concerned
regulatory permitting leading to the issuance of the Authorization.
[62]
By letter of April 23, 2012 the Agency advised
the Applicant that responsibility for leading and coordinating Crown
consultation for the federal government was being transferred from the Agency
to DFO for the Phase 5 consultations.
[63]
On July 9, 2012 DFO wrote to the Applicant
stating that, pursuant to the Consultation Framework, the federal
government was entering the regulatory permitting phase (Phase 5) for the
Project and wished to continue consultations respecting specific regulatory
decisions, approvals or actions that may have potential adverse impacts on
their asserted Aboriginal rights or title. DFO advised that the federal
government anticipated issuing three kinds of approvals: the ss 32 and 35(2) Fisheries
Act authorizations from DFO and the s 5 approval under the NWPA from
TC. DFO proposed to conduct consultations during the regulatory phase in
accordance with an attached Proposed Protocol for Regulatory Phase
Aboriginal Consultation Lower Churchill Generation Project (“Regulatory
Phase Protocol”), and sought comments on the proposed process within 14
days.
[64]
The proposed Regulatory Phase Protocol
stated that it followed the Consultation Framework, and involved a five
step process within Phase 5. First, upon receipt of the Fish Habitat
Compensation Plan (“FHC Plan”) or the Environmental Effects Monitoring Program
(“EEM Plan”), both conditions of the Fisheries Act Authorization, or a
Request for Work Approval per the NWPA, the departments would provide
those documents and relevant supporting information to the Applicant, who would
then have 30 days to review it. Regulatory approvals would not be issued prior
to the end of that timeframe and consideration of any comments received.
Second, 10 days prior to the end of the timeframe to submit comments, a
reminder would be sent to the Applicant. Third, if no comments had been
received when the timeframe ended, the Applicant would be notified that the
approval or authorization would be considered and, if appropriate, approved.
If comments were received, then within 30 days of receipt, the departments
would give them full and fair consideration and would respond to them in
writing. Fourth, the departments would incorporate changes as appropriate. And
fifth, within 14 days of issuance of the Fisheries Act authorization and
the NWPA approval they would be sent to the Applicant.
[65]
On July 24, 2012 the Applicant provided comments
on the draft Regulatory Phase Protocol. The Applicant took the position
that, in order to align the Regulatory Phase Protocol with the Agreement
and the meaning of “Consult” therein: the Fisheries Act authorization
and the NWPA approval should not be issued prior to Project sanction by
both levels of government; the timeframe for the Applicant to prepare its
comments should be increased to 90 days and, upon request, the Applicant should
be permitted the opportunity and funding to present its views in person to DFO;
where the Applicant provided comments, DFO should not provide a response to
those comments in less than 15 days, in order to ensure adequate time for full
and fair consideration; and, the Fisheries Act authorization and the NWPA
approval should be sent to the Applicant on the date of issuance.
[66]
A revised and final Regulatory Phase Protocol
adopted a 45 day time frame for the Applicant to submit comments and confirmed
that regulatory approvals would not be issued prior to the end of that
timeframe and consideration of comments received. The revised protocol added
that within 10 days of receipt, the Applicant could request a meeting with the
RA to discuss the application/document, to be held within the 45 day review
period. Finally, the amended protocol stated that copies of the Fisheries
Act authorization and the NWPA approval would be provided to the
Applicant within 5 days of issuance. DFO sent the finalized Regulatory
Phase Protocol to the Applicant on February 21, 2013.
[67]
Nalcor provided a draft FHC Plan to the
Applicant on December 21, 2012 and invited the Applicant to a public
information session, which would provide a technical briefing on the FHC Plan
and EEM Plan, held on January 16, 2013. Nalcor also met with the Applicant on
January 23, 2013 to present details of the FHC Plan and EEM Plan, at which time
the Applicant raised a number of concerns.
[68]
A February 5, 2013 DFO memorandum for the DFO
Regional Director General addressed the status of aboriginal consultations for
Phase 5. Amongst other things, it noted that comments received on the proposed
protocol indicated that some Aboriginal groups still had concerns about the EA
that they felt had not been addressed. The majority of these related to
impacts on Aboriginal rights and title, caribou, cumulative impacts, and the
lack of land and resource use studies. “Close the loop” letters addressing the
outstanding EA issues were to be sent to Aboriginal groups prior to sending the
finalized Regulatory Phase Protocol.
[69]
On February 12, 2013, the Applicant met with the
Minister of Fisheries and Oceans to discuss its concerns about the Project. The
Applicant provided a power point that restated its concerns about downstream
effects, the JRP’s findings and that Nalcor was not conducting a comprehensive
assessment of downstream effects as recommended by the JRP which, in its view,
put Inuit health and well-being at risk because Nalcor’s approach was reactive
rather than proactive.
[70]
It also stated that preliminary data gathered by
research being conducted on behalf of the Applicant suggested that total
mercury from the Churchill River extends into Lake Melville and the LISA and
sought, as a condition of the s 35(2) Fisheries Act authorization, that
Nalcor be required to provide the Applicant with annual funding of $200,000-
$500,000 for its research and monitoring of the overall effects on the
downstream environment. Further, that meaningful engagement of the Applicant
as a government, not a stakeholder, was required.
[71]
A February 21, 2013 memorandum for the Deputy
Minister of DFO summarized the status of Aboriginal consultations for Phase 5.
It anticipated that DFO would complete the consultations by mid-May and should
be in a position to issue a Fisheries Act authorization by June 2013.
[72]
On February 28, 2013, DFO wrote to the Applicant
advising that it was preparing to issue a Fisheries Act authorization
and provided the draft FHC Plan and EEM Plan, as received from Nalcor, and
sought comments on the two plans within 45 days as per the Regulatory Phase
Protocol. The Applicant did not provide comments on the FHC Plan, but on
several occasions expressed concerns regarding inadequacies in the EEM Plan
with respect to baseline data, as described below.
[73]
On March 22, 2013 the Applicant met with DFO to
discuss the EEM Plan. Amongst other things, the Applicant suggested that the current
draft EEM Plan was too basic, and that a much more comprehensive scientific
investigation of the Lake Melville ecosystem as a whole was necessary to
understand current baseline conditions and to answer future questions as to
Project effects. The Applicant gave examples of additional parameters to be
studied. DFO responded that it would require Nalcor to implement an EEM Plan
to satisfy the CEAA monitoring requirements and to verify specific
predictions, but not to undertake foundational environmental research (Finn
Affidavit, para 83). The Applicant also sought accommodation by way of a
requirement by DFO that Nalcor, as a condition of the Authorization, provide
funding to the Applicant to complete a comprehensive mercury study to inform
the Human Health Risk Assessment, as well as a thorough Lake Melville ecosystem
study, so that the Applicant could ensure appropriate baseline study was
conducted.
[74]
On April 15, 2013 the Applicant wrote to DFO
providing comments on the draft EEM Plan. The Applicant stated that the EEM
Plan was not of sufficient form and detail to allow it to prepare its views or
to determine if it would be an effective monitoring tool both adjacent to and
within the LISA, and that it had not been provided with any additional documentation
or detail since expressing this view to Nalcor on January 25, 2013 and to DFO
on March 22, 2013. The Applicant stated that the Phase 5 consultation did not
meet the definition of “Consult” as found in the Agreement. The Applicant
referred to Recommendation 6.7 and stated that a comprehensive assessment of
downstream effects into Lake Melville had still not been completed nor was one
planned.
[75]
The Applicant stated that the EEM Plan was
premised on the assumption by Nalcor that a monitoring program can be in place
for a system, Lake Melville, that is not well understood. The Applicant
asserted that the basic science of monitoring required that the system being
monitored be well understood prior to a monitoring program being established.
After a baseline understanding of the Lake Melville system was acquired, an EEM
Plan of sufficient form and detail could then be developed. Nalcor’s refusal
to conduct a holistic downstream effects analysis, as recommended by the JRP,
resulted in an EEM Plan that did not have sufficient baseline understanding,
form and detail to allow the Applicant to prepare its views. By not requiring
Nalcor to carry out a comprehensive downstream effects assessment, DFO was not
respecting the constitutionally protected rights of the Applicant, including
that of consultation. The Applicant stated that it was leading the only
comprehensive downstream effects assessment, as per Recommendation 6.7, and
that this assessment included mercury, oceanography, climate, sea ice, human health
risk assessment and socioeconomic components. Based on results to date, it was
known that the Churchill River is a substantial source of total mercury to Lake
Melville and that the mercury influence from the river can be detected at least
150 km from the river mouth. The Applicant also again requested that DFO
require Nalcor, as a condition of the Authorization, to provide funding to the
Applicant for the completion of its comprehensive downstream effects
assessment.
[76]
On May 30, 2013 DFO responded to the Applicant’s
comments on the EEM Plan. DFO stated that it was of the view that the plan
contained sufficient detail to allow the Applicant to prepare its views and
comment on it. And, based on comments that it had received, DFO would require
Nalcor to add to the EEM Plan some additional details on the protocols for
sampling and analysis of fish and seals for methylmercury currently set out in
baseline monitoring reports. As to Recommendation 6.7, Canada’s Response
stated that Nalcor would be required to collect additional baseline data on
methylmercury bioaccumulation in fish and on fish habitat downstream of Muskrat
Falls prior to impoundment. This information was collected by Nalcor in 2011
and 2012, including in Lake Melville, and would continue to be collected prior
to impoundment. DFO stated that it wished to clarify that the primary
objective of an EEM or follow-up program is to verify specific predictions made
by a proponent during an EA, especially where there may be uncertainty about
the severity or extent of a possible impact. EEM programs are not designed or
implemented to study environments or changes in them overall. The Nalcor EEM
Plan with respect to fish and fish habitat addressed those predictions for
which DFO considered monitoring to be required for verification, including in
relation to methylmercury bioaccumulation in fish. As to the Applicant’s view
that DFO was not respecting the Applicant’s consultation rights, DFO stated
that it was consulting with the Applicant in accordance with the Regulatory
Phase Protocol which was developed in consideration of and consistent with
the Agreement. Finally, as to the Applicant’s funding request, DFO stated that
it typically sets out monitoring and reporting requirements that a proponent
must meet in a s 35 Fisheries Act authorization, but does not specify
who a proponent is to engage to carry this out. DFO would require Nalcor to
make raw data and results of the EEM Plan available to interested parties, and
encouraged the Applicant to discuss the sharing of monitoring results and
possible collaboration in monitoring directly with Nalcor.
[77]
Following various communications between Nalcor
and DFO, Nalcor submitted its revised, final EEM Plan and FHC Plan on June 26,
2013 and DFO advised Nalcor the next day that these were acceptable to DFO and
would be attached as conditions to the Authorization.
[78]
On June 28, 2013 DFO, on behalf of Canada,
responded to the Applicant’s November 11, 2011 and July 24, 2012 letters,
addressing the concerns raised therein on a point by point basis. It stated
that these concerns were taken into account when the federal government
responded to the JRP Report, as indicated in Canada’s Response. With respect
to the Applicant’s concerns regarding significant adverse effects should
consumption advisories or other impacts arise, and the Applicant’s requests for
participation on a high level management structure and for framework language
for compensation as a condition of any permits, DFO stated that a high level
management structure was not contemplated for the Project, but that DFO and TC
would be consulting with the Applicant in the context of their regulatory
functions and that DFO had consulted with the Applicant on the EEM Plan and FHC
Plan it was requiring as conditions of Fisheries Act Authorization.
Further, that it was requiring Nalcor to collect data on methylmercury in fish
and seals as part of the EEM Plan which would be forwarded to Health Canada for
subsequent advice on consumption levels, and that Nalcor was responsible for
relaying that information to the Applicant and posting any consumption
advisories. Finally, that the requested framework language would not be
included as a condition of the authorizations or approval as it would not be
enforceable as a condition under the Fisheries Act or the NWPA.
[79]
As to the Applicant’s concerns regarding
monitoring and assessment of environmental effects and the Applicant’s
suggestion that it be funded to develop and implement a program specifically
designed to establish baseline conditions directly related to Inuit rights, DFO
advised that as a condition of any s 35(2) authorization under the Fisheries
Act, and prior to impoundment, DFO was requiring Nalcor to collect
additional baseline data both in the Muskrat Falls reservoir and downstream of
Muskrat Falls into Goose Bay/Lake Melville, including data on fish and fish
habitat utilization as well as mercury levels in both fish and seals. DFO
would require Nalcor to conduct a comprehensive multi-year program to monitor
and report on bioaccumulation of methylmercury in fish (including seals) in
those areas after creation of the Muskrat Falls reservoir. Additionally, DFO
would require Nalcor to carry out multi-year post-project monitoring and
reporting downstream into Lake Melville on a variety of parameters including
nutrients, primary production, fish habitat utilization and sediment transport
in order to assess changes to downstream fish habitat. The monitoring
requirements of any Fisheries Act authorization are the responsibility
of Nalcor, and those associated with the bioaccumulation of mercury would be
outlined in the EEM Plan which was sent to the Applicant for review and input
prior to finalizing. The letter also apologized for the late response but
noted that consultation on the regulatory approvals had occurred since the
Applicant’s letters.
[80]
The Applicant’s concerns were reiterated in a
letter to the Minister of Fisheries and Oceans on July 2, 2013. The Applicant
stated that throughout the EA and post-EA process, Nalcor had not provided
meaningful baseline measurements or conducted sufficient research to
characterize the downstream environment that would be impacted by the Project,
particularly in Lake Melville.
[81]
Further, that Canada’s Response to
Recommendation 6.7 was an extreme simplification of its intent. The response
eliminated the need to understand the downstream environment at a holistic
level and the ability to model or predict downstream impacts prior to
flooding. This simplification was reflected in the EEM Plan, which required
the collection of baseline methylmercury data only in fish and seals, such that
downstream impacts related to mercury would only be detected once
concentrations have increased in country foods that Inuit consume and depend on
for their health. The Applicant asserted that accurate prediction is critical
to permit preventative mitigation measures. Absent an accurate understanding
of the pathways and fate of mercury, the only mitigation measure available
would be consumption advisories, which would constitute a threat to Inuit food
security and health and would violate Inuit rights. The Applicant stated that
it considered any increase in mercury concentrations downstream to be a
significant impact, irrespective of harvesting advisories which should be a
mitigation measure of last resort only, and one for which compensation must be
available.
[82]
The Applicant further stated that although the
JRP found that the uncertainty as to whether consumption advisories would be
required beyond the mouth of the Churchill River needed to be resolved before
reservoir filling proceeds, DFO was not requiring Nalcor to conduct any
meaningful work related to this. The Applicant stated that more certainty in
predictions regarding downstream impacts was needed, and that this required an
understanding of the entire Lake Melville system and mercury behaviour within
that system related to Muskrat Falls. Further, that the preliminary data of
research being conducted by the Applicant validated the Applicant’s concerns.
The Applicant took the position that DFO should change the conditions of its Authorization
and the EEM Plan to account for this preliminary research and to accommodate
the Applicant’s concerns.
[83]
The Applicant stated that DFO’s complete
disregard of Inuit concerns throughout the entire EA process, including the May
30, 2013 response, indicated that neither good faith consultation nor
accommodation had taken place. The letter listed three items of concern and
requested Ministerial intervention in the decisions being made by DFO. These
are summarized as follows:
•
the need for a comprehensive baseline report on
mercury in water, sediments and biota that also identifies all possible
pathways for mercury throughout the food web downstream from the Project,
including throughout Lake Melville to provide basic foundational knowledge of
the environment which is essential for the prediction of downstream impacts as
a result of flooding, as well as for the formulation of a meaningful EEM Plan
and consultation respecting that plan;
•
while the total elimination of increased mercury
and methylmercury concentrations downstream may be impossible, the primary and
only mitigation measure that could reduce the risk or concentrations of
mercury prior to flooding is full clearing of the reservoir area, including
trees and the top layer of organic matter. A first step towards accommodation
would be to require this; and
•
consumption advisories are not an acceptable
approach to mitigation, as Inuit rights and well-being cannot be put at
potential risk for economic benefits. Any potential increase in mercury or
methylmercury concentrations downstream would be a direct violation of Inuit
human, treaty, and individual rights.
[84]
On July 9, 2013 the Authorization for the
Project was issued to Nalcor, pursuant to ss 32(2)(c) and 35(2)(b) of the Fisheries
Act, for the harmful alteration, disruption or destruction of fish habitat
and the killing of fish. It is this Authorization that the Applicant has
sought to have judicially reviewed.
[85]
The Authorization is eleven pages in length and
lists a number of Conditions of Authorization. A few of the particularly
relevant conditions are summarized as follows:
•
Condition 1.1 states that if, in DFO’s opinion,
the authorized impacts to fish and fish habitat are greater than previously
assessed, DFO may suspend any works, undertakings, activities and/or operations
associated with the proposed development to avoid or mitigate adverse impacts
to fish and fish habitat. DFO can also direct Nalcor to carry out any
modifications, works or activities necessary to avoid or mitigate such further
adverse impacts. If DFO is of the view that greater impacts may occur than
were contemplated by the parties, then it may also modify or rescind the
Authorization.
•
Condition 1.4 requires Nalcor to undertake the
Project in accordance with the EIS, the Project Wide Environmental Protection
Plan and the FHC Plan.
•
Condition 6 requires Nalcor to undertake an EEM
program, as outlined in the EEM Plan, to monitor and verify the predicted
impacts of the Project from a fish and fish habitat perspective including
Project-related downstream effects, methylmercury bioaccumulation in fish, and,
fish entrainment at the Muskrat Falls facility, in accordance with conditions
6.1-6.5. This includes annual monitoring of methylmercury bioaccumulation to
determine levels in resident fish species, including seals, both within the
reservoir and downstream as per the established monitoring schedule, as well as
a requirement to record and report peak levels and subsequent decline to
background levels (Condition 6.3). There are also a number of reporting
mechanisms as well, including annual reports and comprehensive EEM Plan reports
every 5th year starting in 2023.
[86]
By letter of July 9, 2013 DFO advised the
Applicant that the Authorization had been issued, and provided it with a copy.
[87]
Subsequently, by letter of July 12, 2013 to the
Applicant, the Minister of Fisheries and Oceans addressed several issues,
including that at the February 12, 2013 meeting the Applicant had presented
information concerning its interest in a downstream research and monitoring
program. The Minister stated that, as set out in Canada’s Response, DFO would
require Nalcor to carry out a comprehensive multi-year program to monitor and
report on mercury levels downstream of the Project both before and after
reservoir creation. Although the Authorization had already been issued, the
Minister stated that Nalcor had developed an EEM Plan which was being reviewed
by DFO and, once approved, would become a condition of the s 35 Fisheries
Act Authorization. The Minister also referenced the February 28, 2013
letter from his officials encouraging the Applicant’s participation in the
review of the EEM Plan, and again encouraged the Applicant to engage with DFO
on the finalization of the requirements that DFO would impose on Nalcor by way
of the Authorization. The Minister also noted that DFO had no role in Nalcor’s
decision as to who it engaged to carry out the monitoring required by the
Authorization.
[88]
On August 27, 2013 the Minister wrote to the
Applicant responding to its July 2, 2013 letter. The letter noted that the JRP
had considered predictions concerning methylmercury bioaccumulation that may arise
as a result of the Project and the need for consumption advisories. Further,
that Canada agreed with the intent of the JRP’s Recommendations in relation to
downstream effects. And, pursuant to Canada’s Response, DFO was requiring
Nalcor to collect additional baseline data on methylmercury bioaccumulation in
fish and on fish habitat downstream of Muskrat Falls prior to impoundment and
to conduct a comprehensive long term program to monitor bioaccumulation of
methylmercury in fish (including seals) downstream of Muskrat Falls and into
Lake Melville. That EEM monitoring would follow up on predictions that the
bioaccumulation of methylmercury at distances downstream of the reservoir, and
particularly in Lake Melville, would not have significant adverse effects.
Follow-up monitoring of this type was required and implemented to verify
specific predictions, rather than to provide basic foundational knowledge of
the environment.
[89]
The Minister also noted that DFO had consulted
with the Applicant in the process of reviewing the EEM Plan and preparing
conditions of the Authorization, and had considered comments and advice
received from the Applicant, which led to some additions to the monitoring
plans. DFO also carried out rigorous reviews of the monitoring plans. As to
the suggestion that the removal of trees and organic matter from the reservoir
would be an appropriate mitigation measure, Canada’s Response agreed with the
intent of the JRP Recommendations on that issue, but did not commit to
undertaking a pilot study or to other recommended actions in that regard. The
Minister noted that requirements related to clear cutting of vegetation falls
under provincial legislation. The Minister stated that she was confident that
the monitoring was adequate to verify predictions about downstream aquatic
effects and that it would allow Canada to continue to make decisions that
consider and protect the interests of the Applicant.
[90]
The Applicant submits that the issue is:
1. Whether its rights under s 35(1) of the Constitution Act, 1982,
being Schedule B to the Canada Act 1982 (UK), 1982, c 11 [Constitution
Act, 1982] and under the Agreement have been respected and, in particular,
whether its rights to consultation and accommodation were met. Resolving this
issue involves assessing:
a. whether the consultation process was correctly carried out and met
the standards dictated by the Agreement and by the Constitution Act, 1982;
and
b. whether its views were given full and fair consideration and
accommodation in good faith prior to DFO issuing the Authorization.
[91]
Canada submits the issues in the form of
statements, being that:
1. The content of the duty to consult is defined by the Agreement; and
2. Canada’s consultation efforts were reasonable.
[92]
Nalcor submits that the issues are:
1. What is the standard of review of the Authorization?
2. Did DFO fulfill the Crown’s duty to consult with and, if necessary,
accommodate the Applicant in respect of the Authorization?
[93]
In my view, the issues can be restated as
follows:
1. What is the standard of review?
2. What is the content of the duty to consult and accommodate, more
specifically:
a. Does the Agreement exhaustively define the Crown’s duty to consult?
b. What was the scope and extent of the duty to consult and of any duty
to accommodate in this case?
3. Did Canada satisfy its duty to consult and accommodate?
[94]
The Applicant submits that Canada’s decision to
issue the Authorization is subject to review on the standard of correctness.
The duty to consult in this matter arises under the common law and in the
specific context of the Agreement, which is a modern treaty for the purposes of
s 35(1) of the Constitution Act, 1982. The Supreme Court of Canada has
identified the appropriate standard of review for assessing whether consultation
has occurred in the context of a modern treaty (Beckman v Little Salmon/Carmacks
First Nation, 2010 SCC 53 at para 48 [Little Salmon]; Haida
Nation v British Columbia (Minister of Forests), 2004 SCC 73 [Haida]).
[95]
The requirements of the duty to consult are
determined on the standard of correctness. Only if there was adequate
consultation does the question of whether the decision to issue the
Authorization was reasonable arise.
[96]
Canada agrees that the question of the content
of the duty to consult is reviewable on the correctness standard (Innu of
Ekuanitshit v Canada (Attorney General), 2013 FC 418 at para 97 [Ekuanitshit
FC]; Little Salmon at para 48) but submits that the question of
whether Canada’s efforts satisfied its duty to consult is reviewable on the
reasonableness standard (Ekuanitshit FC at para 97; Katlodeeche First
Nation v Canada (Attorney General), 2013 FC 458 at paras 126-127 [Katlodeeche];
Cold Lake First Nations v Alberta (Tourism, Parks and Recreation), 2013
ABCA 443 at paras 37-39, leave to appeal to SCC refused, [2014] SCCA No 62 [Cold
Lake]).
[97]
Nalcor submits that insofar as the Applicant is
attacking the decision-making of the Minister under the Fisheries Act,
the standard of review is reasonableness, and deference is owed absent a
decision made in bad faith or on the basis of irrelevant considerations (Malcolm
v Canada (Minister of Fisheries and Oceans), 2013 FC 363 at para 57; Vancouver
Island Peace Society v Canada, [1992] 3 FC 42 (TD) at paras 7, 12; Alberta
Wilderness Assn v Express Pipelines Ltd, 137 DLR (4th) 177 (FCA) at para
10; Alberta Wilderness Assn v Cardinal River Coals Ltd, [1999] 3 FC 425
(TD) at paras 24-26).
[98]
As to the adequacy of consultation and
accommodation, Nalcor submits that the extent of the duty is reviewable on a
standard of correctness since the legal requirements are expressly set out in
the Agreement (Haida at para 61; Agreement, s 11.6.2). However, where
the extent of these requirements depends on findings of fact, the standard is
one of reasonableness (Haida at paras 61, 63; Ka’a’Gee Tu First
Nation v Canada (Attorney General), 2012 FC 297 [Ka’a’Gee Tu #2] at
paras 91, 121; Agreement, s 1.1.1). Finally, whether the consultation process
was adequately carried out requires deference since it involves determinations
of fact and applications of the law to the facts (Cold Lake at para 39; Taku
River Tlingit First Nation v British Columbia (Project Assessment Director),
2004 SCC 74 at para 40 [Taku River]; Ka’a’Gee Tu #2 at paras 91,
121).
[99]
A standard of review analysis need not be
conducted in every instance. Instead, where the standard of review applicable
to a particular question before the Court is well-settled by past
jurisprudence, the reviewing court may adopt that standard (Dunsmuir v New
Brunswick, 2008 SCC 9 at para 62 [Dunsmuir]; Innu of Ekuanitshit
v Canada (Attorney General), 2014 FCA 189 at para 38, leave to appeal to
SCC refused [2014] SCCA No 466 [Ekuanitshit FCA]).
[100] The standard of review applicable to the duty to consult was
addressed by the Supreme Court of Canada in Haida, which stated that:
[61] On questions of law, a
decision-maker must generally be correct: for example, Paul v. British
Columbia (Forest Appeals Commission), [2003] 2 S.C.R. 585, 2003 SCC 55. On
questions of fact or mixed fact and law, on the other hand, a reviewing body
may owe a degree of deference to the decision-maker. The existence or extent
of the duty to consult or accommodate is a legal question in the sense that it
defines a legal duty. However, it is typically premised on an assessment of
the facts. It follows that a degree of deference to the findings of fact of
the initial adjudicator may be appropriate. The need for deference and its
degree will depend on the nature of the question the tribunal was addressing
and the extent to which the facts were within the expertise of the tribunal: Law
Society of New Brunswick v. Ryan, [2003] 1 S.C.R. 247, 2003 SCC 20; Paul,
supra. Absent error on legal issues, the tribunal may be in a better
position to evaluate the issue than the reviewing court, and some degree of
deference may be required. In such a case, the standard of review is likely to
be reasonableness. To the extent that the issue is one of pure law, and can be
isolated from the issues of fact, the standard is correctness. However, where
the two are inextricably entwined, the standard will likely be reasonableness: Canada
(Director of Investigation and Research) v. Southam Inc., [1997] 1 S.C.R.
748.
[62] The process itself would likely
fall to be examined on a standard of reasonableness. Perfect satisfaction is
not required; the question is whether the regulatory scheme or government
action “viewed as a whole, accommodates the collective aboriginal right in
question”: Gladstone, supra, at para. 170. What is required is not
perfection, but reasonableness. As stated in Nikal, supra, at para.
110, “in . . . information and consultation the concept of reasonableness must
come into play. . . . So long as every reasonable effort is made to inform and
to consult, such efforts would suffice.” The government is required to make
reasonable efforts to inform and consult. This suffices to discharge the duty.
[63] Should the government misconceive
the seriousness of the claim or impact of the infringement, this question of
law would likely be judged by correctness. Where the government is correct on
these matters and acts on the appropriate standard, the decision will be set
aside only if the government’s process is unreasonable. The focus, as
discussed above, is not on the outcome, but on the process of consultation and
accommodation.
[101] Until the Supreme Court’s subsequent decision in Little Salmon,
the above reference in Haida was consistently interpreted as meaning
that the scope or extent of the duty to consult (its content) should be
reviewed on the standard of correctness, whereas the adequacy of the process of
consultation requires an analysis of the factual context and should be reviewed
on a standard of reasonableness (Katlodeeche at paras 126-127; Ka’a’Gee
Tu First Nation v Canada (Attorney General), 2007 FC 763 at paras 92-93 [Ka’a’Gee
Tu #1]).
[102] As stated by Justice de Montigny in Ka’a’Gee Tu #2:
[89] …A reviewing court owes very
little deference to the decision-maker when determining whether the duty to
consult is triggered or delineating the scope and extent of the duty in regard
to legal and constitutional limits. On the other hand, the question as to
whether the Crown discharged its duty to consult and accommodate will be reviewable
on the standard of reasonableness.
(Also see Katlodeeche at paras
126-127).
[103] In Little Salmon the Supreme Court addressed the standard of
review as follows:
[48] In exercising his discretion under
the Yukon Lands Act and the Territorial Lands (Yukon) Act, the
Director was required to respect legal and constitutional limits. In
establishing those limits no deference is owed to the Director. The
standard of review in that respect, including the adequacy of the consultation,
is correctness. A decision maker who proceeds on the basis of inadequate
consultation errs in law. Within the limits established by the law and the
Constitution, however, the Director’s decision should be reviewed on a standard
of reasonableness: Dunsmuir v. New Brunswick, 2008 SCC 9, [2008]
1 S.C.R. 190, and Canada (Citizenship and Immigration) v. Khosa, 2009
SCC 12, [2009] 1 S.C.R. 339. In other words, if there was adequate
consultation, did the Director’s decision to approve the Paulsen grant, having
regard to all the relevant considerations, fall within the range of reasonable
outcomes?
[Emphasis added]
[104] In discussing the analysis of the adequacy of consultation, the
Supreme Court stated, in part:
[72] The adequacy of the consultation
was the subject of the First Nation’s cross-appeal. The adequacy of what
passed (or failed to pass) between the parties must be assessed in light of the
role and function to be served by consultation on the facts of the case and
whether that purpose was, on the facts, satisfied.
[105] In Ekuanitshit FC, affirmed 2014 FCA 189, leave to appeal to
SCC refused [2014] SCCA No 466, which also concerned the subject Project, this
Court dealt with a challenge to the lawfulness of the March 12, 2012 Order in
Council approving Canada’s Response to the JRP Report and the related Course of
Action Decision. In addressing the question of whether the Innu of Ekuanitshit
had been properly consulted and accommodated, Justice Scott, relying on Haida,
found that the consensus in the case law was that a question regarding the
existence and content of the duty to consult is a legal question that attracts
the standard of correctness. On the other hand, a decision as to whether the
efforts of the Crown satisfied its duty to consult in a particular situation
involves assessing the facts of the case as against the content of the duty
which is a mixed question of fact and law to be reviewed on the standard of
reasonableness (Ekuanitshit FC at para 98).
[106] The Federal Court of Appeal upheld Justice Scott’s decision. It
noted that its role in an appeal from a judicial review decision is to first
determine whether the applications judge identified the appropriate standard of
review, and then to determine whether it was applied correctly. As to the
issue of the duty to consult, the Federal Court of Appeal stated:
[82] The judge noted in his reasons
that issues relating to the existence and content of the duty to consult
attract a standard of correctness. He further asserted that a decision as to
whether the Crown met its duty to consult is reviewable on a reasonableness
standard, as it is a mixed question of fact and law. In the present instance,
the parties acknowledge that the Crown recognized its duty to consult from the
outset. The issue is therefore not whether the Crown has a duty to consult but
rather whether the efforts of the Crown met the requirements of its duty to
consult. As Justice Binnie writes in Beckman v. Little Salmon/Carmacks First
Nation, 2010 SCC 53, [2010] 3 S.C.R. 103 at paragraphs 48 and 77 [Little
Salmon]: “the standard of review in that respect, including the adequacy of
the consultation, is correctness”, but nonetheless it “must be assessed in
light of the role and function to be served by consultation on the facts of the
case and whether that purpose was, on the facts, satisfied”.
[83] It is through that lens that the
following issues will be examined.
[note: the above reference by the Federal
Court of Appeal to paragraph 77 of Little Salmon was likely intended to
be to paragraph 72]
[107] Although the Federal Court of Appeal refers to paragraph 48 of Little
Salmon, which could be understood to suggest that the correctness standard
applies when assessing whether the Crown’s efforts were adequate to meet its
duty to consult, it did not state that Justice Scott erred in identifying the
standard of review in that regard as one of reasonableness. Its following
analysis was primarily concerned with whether, on the facts of the case, the
consultation process carried out to that point by Canada was adequate and
proportionate both to the strength of the Innu claim and to the seriousness of
the adverse impacts the contemplated government action would have on the
claimed right. The Court of Appeal found that Justice Scott did not err in
finding that the Innu had been adequately consulted prior to the Order of the
Governor-in-Council being issued.
[108] In White River First Nation v Yukon (Minister of Energy, Mines
and Resources), 2013 YKSC 66 [White River], the Yukon Supreme Court
referenced paragraphs 61 to 63 of Haida as well as paragraph 48 of Little
Salmon and concluded:
[92] The standard of review may be
correctness if the issue relates to the legal and constitutional obligations of
the Director, i.e., the existence and extent of the duty to consult and
accommodate. On the other hand, the process of consultation, because it depends
on the government’s reasonable efforts to inform and consult, is reviewed on a
reasonableness standard.
[109] The Alberta Court of Appeal in Cold Lake, leave to the SCC
denied, also referred to Little Salmon and interpreted it as follows:
[36] Parks submits that the reviewing
judge erred in applying the correctness standard to the question of the
adequacy of the consultation process and that both the consultation process and
decision should be reviewed for reasonableness.
[37] We agree. In Haida, the
court held that the existence and extent of the duty to consult or accommodate
(including the assessment of the seriousness of the claim and the extent of
adverse impact) are questions of law, subject to review on a standard of
correctness: at para 61. However, where these questions are infused with
questions of fact or mixed fact and law, some deference to the initial
adjudicator may be appropriate. With respect to the consultation process
itself, “[w]hat is required is not perfection, but reasonableness”: at para 62.
Chief Justice McLachlin said:
Should the government misconceive the
seriousness of the claim or impact of the infringement, this question of law
would likely be judged by correctness. Where the government is correct on these
matters and acts on the appropriate standard, the decision will be set aside
only if the government’s process is unreasonable. The focus, as discussed
above, is not on the outcome, but on the process of consultation and accommodation
(at para 63).
[38] This court followed this approach
in Tsuu T’ina, stating that the questions of whether there is a duty to
consult and the assessment of the scope of the duty are reviewed on a standard
of correctness, with deference owed to any underlying findings of fact, while
the consultation process is reviewed on a standard of reasonableness: paras
27-29. There has been the suggestion in recent case law that the Supreme Court
in Beckman may have altered the standard of review for assessing the
consultation process to correctness. The British Columbia Court of Appeal
applied the correctness standard in reviewing the consultation process in Halalt
First Nation v British Columbia (Minister of Environment), 2012 BCCA 472,
[2013] 1 WWR 791. It agreed with the trial judge’s analysis that deference may
be appropriate on findings of fact where there is a neutral tribunal assessing
the consultation process. However, where the initial decision maker is a
representative of the Crown and a party to the dispute, less deference is
warranted. We note that this distinction has not been articulated by the
Supreme Court and many other courts have concluded that the adequacy of the
consultation process involves issues of mixed fact and law reviewable on a
reasonableness standard: see Neskonlith Indian Band v Salmon Arm (City),
2012 BCCA 379, 354 DLR (4th) 696, Long Plain First Nation v Canada (Attorney
General), 2012 FC 1474 at para 65, [2013] 1 CNLR 184; Dene Tha’ First
Nation v British Columbia (Minister of Energy and Mines), 2013 BCSC 977 at
paras 103-08, West Moberly First Nations v British Columbia (Ministry of
Energy, Mines and Petroleum Resources), 2011 BCCA 247, 333 DLR (4th) 31.
[39] In our view, the duty to consult
is described in very general terms and there is significant flexibility in how
the duty is met. The Crown has discretion as to how it structures the
consultation process. As noted by Garson JA (dissenting in the result) in West
Moberly First Nations, the consultation process requires compromise, and
compromise is a “difficult, if not impossible, thing to assess on a correctness
standard”: at para 197. The assessment of the adequacy of consultation process
will necessarily involve factual determinations and applications of the law to
facts. This necessarily attracts some appellate deference.
[40] Accordingly, we conclude that the
standard of review applicable to both the issue of the adequacy of the
consultation process and the final decision to end consultation and proceed
with the project are to be reviewed on a standard of reasonableness.
[110] In West Moberly First Nations v British Columbia (Minister of
Energy, Mines and Petroleum Resources), 2011 BCCA 247, leave to appeal to
SCC refused, [2011] SCCA No 399 [West Moberly], as referenced above in Cold
Lake, the judgment of Chief Justice Finch, as he then was (separate reasons
for judgment by Justices Hinkson and Garson) did not directly address the
standard of review in relation to the scope of the duty to consult but did note
that the question was whether the consultation process was reasonable (para
141). He also stated that “A consultation that
proceeds on a misunderstanding of the Treaty, or a mischaracterization of the
rights that the Treaty protects, is a consultation based on an error of law,
and cannot therefore be considered reasonable” (para 151). Justice
Hinkson, in concurring reasons, accepted that the appropriate standard of
review in consultation cases for the Crown’s assessment of the extent of its
duty to consult is correctness, and that the appropriate standard of review for
assessing the process adopted for a particular consultation and the results of
that process is that of reasonableness (para 174). In dissenting reasons,
Justice Garson addressed the standard of review and, in particular, paragraphs
48 of Little Salmon and 61–63 of Haida. She was of the view that
Little Salmon’s adoption of a higher standard was attributable to the
fact that the case concerned the construction of a modern, comprehensive treaty
and distinguished it on that basis. She then stated:
[196] Thus, I would apply a
reasonableness standard to the question of the adequacy of the consultation
where the historical treaty does not provide the degree of specificity
necessary to ascertain the “correct” process.
[197] As was held in Rio Tinto Alcan
Inc. v. Carrier Sekani Tribal Council, 2010 SCC 43, [2010] 2 S.C.R. 650, at
para. 74, “[c]onsultation itself is not a question of law, but a distinct
constitutional process requiring powers to effect compromise and do whatever is
necessary to achieve reconciliation of divergent Crown and Aboriginal
interests”. Compromise is a difficult, if not impossible, thing to assess on a
correctness standard.
[198] In summary, the Crown’s
determination of the scope and extent of its duty to consult must be assessed
on a correctness standard. But the third Taku question, as to the
adequacy of the consultation and the outcome of the process, must be assessed
on a reasonableness standard as those questions are either questions of fact or
mixed fact and law. The consultation process must also meet the administrative
law standards of procedural fairness.
[111] Whether Little Salmon altered the standard of review was also
addressed in Dene Tha’ First Nation v British Columbia (Minister of Energy
and Mines), 2013 BCSC 977. There Justice Grauer of the British Columbia
Supreme Court recited paragraphs 61-63 of Haida, noting that therein the
Supreme Court had explained that the standard to be applied to consultation
decisions is bifurcated. He then noted that this approach was followed by
Justice Neilson of the British Columbia Supreme Court (as she then was) in Wii’litswx
v British Columbia (Minister of Forests), 2008 BCSC 1139 at paras 15-16.
[112] He next referred to West Moberly, noting that it too involved
Treaty 8 rights, and the three separate judgments of the members of the British
Columbia Court of Appeal concerning the standard of review. At this stage Justice
Grauer stated the following:
[104] I pause, respectfully, to add my
own comments to those of Garson J.A. concerning the conundrum posed by Justice
Binnie's choice of words in the Beckman decision when he stated that
"a decision maker who proceeds on the basis of inadequate consultation
errs in law". At first glance, this seems inconsistent with previous
statements by the Supreme Court in cases such as Haida Nation and
Taku River.
[105] I have already reviewed how, as
discussed in Haida Nation, the standard of review of the question
of scope and extent of duty can move from correctness towards reasonableness
depending on the extent to which the decision inextricably combined questions
of fact and law. In Beckman, it seems to me, as in the judgment of Finch
C.J.B.C. in West Moberly First Nations, we have a hint that the
real question comes down to the adequacy of the consultation process which will
itself, to an extent, determine the correctness of the scope. In other words,
if the process did not accomplish a reasonable result, then it was probably
carried out pursuant to an incorrect assessment of its proper scope.
[106] One of the distinguishing features
of this case is that, from at least the Crown's perspective, the consultation
process is fluid and ongoing. From the perspective of the DTFN, however, that
cannot cure the fact that it started out on the wrong foot because of a scope
assessment that was wrong in law, judged on the correctness standard.
[107] It is, however, clear to me from
the evidence that the Crown's determination of the extent and scope of its duty
to consult was inextricably bound up with its assessment of the underlying
question of the direct and potential impact of the 21 tenure sales on the
DTFN’s treaty rights in the Key Response Area. This question turns on factual
analyses, as indicated in the competing impact/disturbance reports. Thus, as
suggested above, the issue of the scope and extent of the duty to consult in
this case is intertwined with the issue of the adequacy of the consultation.
[108] Whether a duty to consult and, if
indicated, to accommodate existed is clearly a question of law, and was never
in doubt in this case. Not only did the Crown acknowledge the existence of
such a duty throughout, but the Crown had also entered into a Consultation
Agreement with the DTFN aimed at covering the very sort of situation that
arose. But when it comes to the Crown's assessment of the scope and extent of
that duty, I conclude that in the circumstances of this case, the
"correctness" of the Crown's assessment depends upon the
"reasonableness" of that assessment's underpinning. We have a
question of mixed law and fact so the standard, in effect, becomes one of
reasonableness as noted in the passage from Haida Nation quoted
above.
[113] It is clear from the above jurisprudence that the existence and
extent of the duty to consult or accommodate is to be assessed on the
correctness standard. However, even there, where the extent of the duty is
premised on an assessment of the facts, deference may be owed and the standard
of review is likely to be reasonableness (Haida at para 61).
[114] As to the adequacy of the process, based on Haida, Ekuanitshit
FCA, White River and Cold Lake, I am not convinced that Little
Salmon was intended to alter, in every case, the standard of review with
respect to the question of whether the Crown adequately consulted and
accommodated to one of correctness.
[115] In determining the extent of the duty to consult, the Crown is
obliged to identify the applicable legal and constitutional limits, such as the
specific treaty rights, legislative rights, common law rights and the
administrative and constitutional law applicable to that case. That is, the
Crown must correctly identify the legal parameters of the content of the duty
to consult in order to also properly identify what will comprise adequate
consultation. To proceed without having done so would be an error of law.
However, if those parameters are correctly identified, then the adequacy of the
subsequent process of consultation employed would remain a question of
reasonableness. This view can be seen as consistent with both Haida and
Little Salmon.
[116] For example, a modern treaty by its terms may specify all, or
certain aspects of, the consultation required, including participation in an
identified environmental assessment process. Should the Crown fail to comply
with those consultation requirements by not participating then it would have
breached its duty to consult and, necessarily, would also have failed to
identify and implement an adequate process of consultation in that regard. To
proceed on that basis would be an error of law. However, if the Crown
correctly identified the prevailing legal parameters, then the adequacy of the
consultation process would be reviewed on the reasonableness standard.
[117] As noted in Cold Lake, quoting Justice Garson in West Moberly,
“the consultation process requires compromise, and
compromise is a “difficult, if not impossible, thing to assess on a correctness
standard”” (para 39).
[118] I would also note that subsequent decisions of this Court and of the
British Columbia Court of Appeal have held that the standard of review for the
adequacy of consultation and accommodation is reasonableness (Adam v Canada
(Minister of Citizenship and Immigration), 2014 FC 1185 at paras 65-66, 87
[Adam]; Da’naxda’xw/Awaetlala First Nation v British Columbia Hydro
and Power Authority, 2015 BCSC 16 at para 229).
[119] Where the standard of review is correctness, as is the case with
respect to the extent of the duty, no deference is owed to the Crown (Dunsmuir
at para 34; Little Salmon at para 48).
[120] Where the standard of review is reasonableness, as is the case with
respect to the adequacy of the consultation and accommodation, this Court’s
review is concerned with the existence of justification, transparency and
intelligibility within the decision making process. It is also concerned with
whether the decision falls within a range of possible, acceptable outcomes
which are defensible in respect of the facts and the law (Dunsmuir at
paras 47-48; Canada (Minister of Citizenship and Immigration) v Khosa,
2009 SCC 12 at para 59). As stated by Justice de Montigny in Ka’a’Gee Tu #2,
perfection is not required when assessing the conduct of Crown officials. If
reasonable efforts have been made to consult and accommodate and the result is
within the range of possible, acceptable outcomes which are defensible in
respect of the facts and the law, there will be no justification to intervene.
Further, the focus should not be on the outcome but rather on the process of
consultation and accommodation (paras 90-92).
A. Does the Agreement Exhaustively Define the Crown’s Duty to Consult?
B.
What was the Scope and Extent of the Duty
to Consult and of any Duty to Accommodate in this Case?
[121] The Applicant submits that the consultation obligations under the
Agreement do not exhaustively define Canada’s duty to consult. Rather, Canada
has an additional duty to consult based on the honour of the Crown, pursuant to
s 35 of the Constitution Act, 1982. Thus, Canada’s treaty obligations
are to be interpreted consistently with the honour of the Crown (Little
Salmon at paras 61-62). Both the honour of the Crown and Chapter 11 of the
Agreement require the Crown to act in a manner that accomplishes the intended
purposes of the Agreement (Manitoba Metis Federation Inc v Canada (Attorney
General), 2013 SCC 14 at para 73 [Manitoba Metis]). When the
effects and impacts on rights are significant, deeper consultation is required
and accommodation may be required (Haida at para 47).
[122]
Canada submits that the source and content of
the duty in this case is delineated by the Agreement, as negotiated and agreed
between the parties (Little Salmon at para 67). By its terms, the
Agreement requires the Respondent to consult prior to issuing the Authorization
(s 11.6.2), and “consult” is defined in s 1.1.1. Canada submits that a similar
definition applied in Little Salmon and that there the Supreme Court of
Canada found that the duty to consult was at the low end of the spectrum (Little
Salmon at paras 57, 74, 79).
[123] Nalcor submits that since a process of consultation has been
incorporated into the Agreement, the Crown’s consultation obligations with
respect to the Project are governed by Chapters 1 and 11 of the Agreement and
that there is no additional duty to consult based on the honour of the Crown or
otherwise. Contrary to the Applicant’s reading of Little Salmon, the
Supreme Court of Canada did not find an “additional
duty” there; it merely identified the source of the duty. Further,
unlike in Little Salmon, there is no need to identify the source of the
duty here as the Agreement expressly states this (Little Salmon at paras
54, 58-67, 72-75). Finally, there is no need to invoke the honour of the Crown
as an interpretive tool, as the parties expressly agreed that consultation was
required prior to a federal decision to issue an authorization, and the
definition of “consult” in the Agreement contains sufficient flexibility to
allow for consultation in various circumstances (Agreement, s 11.6.2; Little
Salmon at para 67).
[124]
In this matter, there is no dispute that the
Crown had a duty to consult the Applicant with respect to the Project. There
is also no dispute that the Agreement is a modern comprehensive land claims
agreement which is a treaty as contemplated by s 35(3) of the Constitution
Act, 1982 (Little Salmon at para 62).
[125] In terms of general principles, the jurisprudence has established
that the Crown’s duty to consult with Aboriginal peoples and accommodate their
interests is grounded in the honour of the Crown which is always at stake when
dealing with Aboriginal peoples (Haida at para 16). The honour of the
Crown also infuses treaty making and treaty interpretation (Haida at
para 19; Ka’a’Gee Tu #2 at para 94) and requires the Crown to act in a
way that accomplishes the intended purposes of treaty and statutory grants to
Aboriginal peoples (Manitoba Metis at para 73). Even though
consultation may be shaped by agreement of the parties, the Crown cannot
contract out of its duty of honourable dealings with Aboriginal peoples (Little
Salmon at para 61). However, the duty that flows from the honour of the
Crown varies with the situation in which it is engaged, and what constitutes
honourable conduct will vary with the circumstances (Manitoba Metis at
paras 73-74). And, although the concept of the duty to consult is a valuable
adjunct to the honour of the Crown, it plays a supporting role and should not
be viewed independently from its purpose (Little Salmon at para 44).
[126] The duty to consult in the context of a modern land claim treaty was
addressed by the Supreme Court of Canada in Little Salmon. There the
Yukon territorial government approved a grant of 65 hectares of surrendered
land to a resident. The plot formed part of the applicant’s traditional
territory, to which the applicant’s members had an express treaty right to hunt
and fish for subsistence. The treaty contemplated that the government could
take up surrendered land from time to time for other purposes, including
agriculture.
[127] The applicants contended that in considering the grant, the
government had proceeded without proper consultation and without proper regard
to their concerns. Conversely, the territorial government took the position
that no consultation was required as the treaty was a complete code. While the
treaty referred to consultation in over 60 different places, a land grant
application was not one of them. The territorial government therefore
contended that, where not specifically included in the treaty, the duty to
consult was excluded.
[128] The Supreme Court of Canada was unanimous in the result that the
Crown had met its duty to consult, but was split on the source of that duty. Justice
Binnie, writing for the majority, did not accept the territorial government’s
argument that the treaty was a “complete code”
and that the absence of a treaty obligation to consult before granting land
meant that such an obligation was excluded by negative inference (paras 52, 55,
59-62). Rather, he was of the view that the duty to consult is derived from
the honour of the Crown, which applies independently of the treaty (para 52).
Further, he held that, given the procedural gap in the treaty, the First Nation
was correct “in calling in aid the duty of consultation
in putting together an appropriate procedural framework” (para 38).
[129] As to the territorial government’s position that the procedural gap
in the case of land grants precluded consultation as an implied term of the
treaty, Justice Binnie stated:
[61] I think this argument is
unpersuasive. The duty to consult is treated in the jurisprudence as a means
(in appropriate circumstances) of upholding the honour of the Crown.
Consultation can be shaped by agreement of the parties, but the Crown cannot
contract out of its duty of honourable dealing with Aboriginal people. As held
in Haida Nation and affirmed in Mikisew Cree, it is a
doctrine that applies independently of the expressed or implied intention of
the parties.
[130] Thus, Justice Binnie found that, because there was a procedural gap
in the treaty as its provisions did not govern the process for agricultural
grants at that time, consultation was necessary to uphold the honour of the
Crown. The duty to consult was, therefore, imposed as a matter of law (para
62). However, he also found that the First Nation went too far in seeking to
impose on the territorial government the substantive right of accommodation in
addition to the procedural protection of consultation, as nothing in the treaty
or surrounding circumstances gave rise to a requirement of accommodation in
that case (paras 14-15, 82).
[131] Also of note in Little Salmon is the approach taken by the
majority to modern treaties. Justice Binnie noted that, unlike their
historical counterparts, the modern comprehensive treaty is the product of
lengthy negotiations between well resourced and sophisticated parties (para
9). Further:
[12] The increased detail and
sophistication of modern treaties represents a quantum leap beyond the
pre-Confederation historical treaties such as the 1760-61 Treaty at issue in R.
v. Marshall, [1999] 3 S.C.R. 456, and post-Confederation treaties such as
Treaty No. 8 (1899) at issue in R. v. Badger, [1996] 1 S.C.R. 771, and Mikisew
Cree First Nation v. Canada (Minister of Canadian Heritage), 2005 SCC 69,
[2005] 3 S.C.R. 388. The historical treaties were typically expressed in lofty
terms of high generality and were often ambiguous. The courts were obliged to
resort to general principles (such as the honour of the Crown) to fill the gaps
and achieve a fair outcome. Modern comprehensive land claim agreements, on the
other hand, starting perhaps with the James Bay and Northern Québec
Agreement (1975), while still to be interpreted and applied in a manner
that upholds the honour of the Crown, were nevertheless intended to create some
precision around property and governance rights and obligations. Instead of ad
hoc remedies to smooth the way to reconciliation, the modern treaties are
designed to place Aboriginal and non-Aboriginal relations in the mainstream
legal system with its advantages of continuity, transparency, and
predictability. It is up to the parties, when treaty issues arise, to act
diligently to advance their respective interests. Good government requires
that decisions be taken in a timely way. To the extent the Yukon territorial
government argues that the Yukon treaties represent a new departure and not
just an elaboration of the status quo, I think it is correct. However,
as the trial judge Veale J. aptly remarked, the new departure represents but a
step — albeit a very important step — in the long journey of reconciliation
(para. 69).
[132] In addition to finding that modern treaties are intended to create
some precision around property and governance rights and obligations, while
still to be interpreted and applied in a manner that upholds the honour of the
Crown, Justice Binnie restated at several junctures that the consultation can
be shaped by the agreement of the parties, as set out in paragraph 61 of that
decision, and the significance of this:
[46] …And the content of meaningful
consultation “appropriate to the circumstances” will be shaped, and in some
cases determined, by the terms of the modern land claims agreement. Indeed,
the parties themselves may decide therein to exclude consultation altogether in
defined situations and the decision to do so would be upheld by the courts
where this outcome would be consistent with the maintenance of the honour of
the Crown.
[…]
[54] The difference between the LSCFN
Treaty and Treaty No. 8 is not simply that the former is a “modern
comprehensive treaty” and the latter is more than a century old. Today’s
modern treaty will become tomorrow’s historic treaty. The distinction lies in
the relative precision and sophistication of the modern document. Where
adequately resourced and professionally represented parties have sought to order
their own affairs, and have given shape to the duty to consult by incorporating
consultation procedures into a treaty, their efforts should be encouraged and,
subject to such constitutional limitations as the honour of the Crown, the
Court should strive to respect their handiwork: Quebec (Attorney General) v.
Moses, 2010 SCC 17, [2010] 1 S.C.R. 557.
[…]
[67] When a modern treaty has been
concluded, the first step is to look at its provisions and try to determine the
parties’ respective obligations, and whether there is some form of consultation
provided for in the treaty itself. If a process of consultation has been
established in the treaty, the scope of the duty to consult will be shaped by
its provisions.
[…]
[69] However, as stated, the duty to
consult is not a “collateral agreement or condition”. The LSCFN Treaty is the
“entire agreement”, but it does not exist in isolation. The duty to consult is
imposed as a matter of law, irrespective of the parties’ “agreement”. It does
not “affect” the agreement itself. It is simply part of the essential legal
framework within which the treaty is to be interpreted and performed.
[133] In concurring reasons, Justice Deschamps (writing for herself and
Justice Lebel) agreed that the appeal and cross appeal should be dismissed but
for different reasons than those of the majority. She found that there was no
gap in the treaty and that, because of this, there was no need to resort to a
duty outside the treaty. She also disagreed with the majority that the common
law constitutional duty to consult applies in every case, even where there is
no gap. Instead, it was her view that the common law constitutional duty to
consult applies to the parties to a treaty only if they have said nothing about
consultation in respect of the right the Crown seeks to exercise under the
treaty (para 94, also see paras 118, 203-204).
[134] In my view, Little Salmon stands for the proposition that
when a modern day land claim treaty is in place, the starting point for any
analysis of the duty to consult will always be the text of the agreement.
Where its terms address the duty to consult in a given situation, then the
scope of that duty will primarily, if not exclusively, be shaped by those
terms. If the agreement is silent on the duty to consult in that situation, or
there is a procedural gap, then pursuant to the honour of the Crown, a duty to
consult will still arise at law. Further, even if the terms of the agreement
speak to the duty to consult, because it is also imposed as a matter of law in
every case, it is part of the essential legal framework within which the treaty
is to be interpreted and performed.
[135] I also take this to mean that, if necessary, the honour of the Crown
and adjunct duty to consult may be used as interpretive tools when considering
consultation provisions found in a modern treaty. As such, I do not understand
that there is an additional or parallel duty owed in such circumstances.
[136] My understanding is also consistent with that of Dwight G. Newman,
who has stated that both the majority and the concurring judgments in Little
Salmon appear “attentive to text as a dominant
feature in modern treaty interpretation”. Further, that:
Although for the majority the duty to
consult can continue to operate as a parameter outside the treaty if there are
areas in which the treaty leaves differences of interpretation, [paras 62, 69]
the text of a detailed treaty will nonetheless take priority in defining when
the duty to consult applies.
[…]
[A]ll the judges have come to agreement that
modern treaties are to be approached in a manner suited to their detailed
negotiated text, that approaching them with deep attention to text is the
primary means of interpreting them to achieve their purposes, and that failing
to approach them in this way undermines processes of reconciliation underway in
various ongoing negotiations. Modern treaty interpretation is fundamentally
different from the approaches the Court has taken to historical treaty
interpretation.
(Dwight Newman, “Contractual and Covenantal
Conceptions of Modern Treaty Interpretation” (2011), 54 SCLR (2d) 475 at
481-483).
[137] In my view this interpretation is also in keeping with and is
supported by the Quebec Court of Appeal’s decision in Makivik v Quebec,
2014 QCCA 1455 [Makivik], in which the Court of Appeal respected the
terms of the treaty as the primary source of the duty to consult, but
interpreted the treaty in accordance with constitutional duties and the honour
of the Crown. Specifically, it found that the Minister’s constitutional duty
to consult with an open mind applied to any consultation prescribed by the
treaty, such that his failure to comply with an outlined process, based on his
belief that it would not change the ultimate result, was not purely a
procedural irregularity but was a breach of the honour of the Crown through a
failure to consult with an open mind, and therefore a breach of the provisions
of the treaty. In effect, the Court of Appeal focused on the contractual
certainty principles from Little Salmon while recognizing that the
general common law constitutional principles concerning the duty to consult are
the underlying and, therefore, can be the interpretive framework of the duty
prescribed by the treaty.
[138] In summary, as stated in Little Salmon, where adequately
resourced and professionally represented parties have given shape to the duty
to consult by incorporating consultation procedures into a treaty, their
efforts should be encouraged and, subject to such constitutional limits as the
honour of the Crown, the Courts should strive to respect those efforts (Little
Salmon at para 54). This may even include circumstances where the parties
themselves decide to exclude consultation entirely which could be an acceptable
outcome so long as, in the prevailing circumstances, it was also consistent
with the maintenance of the honour of the Crown (Little Salmon at para
46).
[139] In my view, this means that the existence of consultation provisions
within a modern day treaty, as in this case, will require that the Court first
and foremost look to the text of those provisions to assess where a duty is
owed, and the scope of that duty, i.e. the content of meaningful consultation
appropriate to the circumstances. If necessary to interpret the text, or if
the text is silent in some area, the Court can apply the common law principles
concerning the duty to consult as they will, in either event, be underlying by
way of the honour of the Crown. Thus, in that context, a treaty may perhaps
never “exhaustively” define the Crown’s duty to
consult. However, in each case the extent, if any, to which reference must be
made to the underlying principles concerning the duty to consult, will be fact
driven. In this case, while s 2.11.1(b) of the Agreement states that it
exhaustively sets out the rights in Canada of Inuit that are recognized and
affirmed by s 35 of the Constitution Act, 1982, I do not understand this
to preclude reference to the common law constitutional duty to consult if
necessary to interpret the text or where there is a gap therein.
[140] The Applicant submits that the Agreement’s provisions for federal
EAs treat both “projects” and “undertakings”, as those terms are defined in the
Agreement, in the same way. Canada was required to consult with the Applicant
about environmental effects in both cases as well as about the best way to
achieve meaningful participation by the Applicant in the EA process, to supply
the Applicant with the results of the EA and to consult with it before taking
any action that would allow the Project to proceed or making a decision to
issue a permit or other authorization (Agreement, ss 11.6.1, 11.6.2, 11.6.3 and
11.7).
[141] With respect to the duty to provide full and fair consideration to
views presented by the party being consulted, the Applicant submits that the
content of the duty will depend on the context, including the nature of the
project or undertaking and the rights and interests affected. In this case,
the obligation to accommodate inherent in “deep” consultation, as referred to
in Haida, was engaged. This is because the Project was reasonably
expected to have impacts in the LISA or on Inuit rights under the Agreement. Labrador
Inuit rights and territory will likely be adversely impacted by increased
mercury levels, Inuit are largely powerless to prevent or mitigate this, the
consequences could be severe and incapable of remediation, and the fear of
mercury contamination is well-founded. Specifically, Inuit subsistence rights
are recognized by the Agreement, yet the sole mitigation measure in the event
of methylmercury contamination, consumption advisories, is not truly mitigation
as it does not protect the right. Accommodation was required.
[142] The Applicant submits that in the specific circumstances of this
case, as part of the duty to consult, Canada had an ongoing requirement to
inform and discuss plans with the Applicant prior to acting. Further, that the
Agreement sets out specific consultation requirements which cannot be
delegated. The fact that the Applicant participated in the JRP hearings did
not relieve Canada of the duty to consult and to provide meaningful
consultation and accommodation. Further, Canada incorrectly assumed that if it
acted in accordance with the federal and provincial protocols it would fulfill
its duties under s 11.6 of the Agreement.
[143] Canada submits that the source and content of the duty to consult
the Applicant in the context of the Project is delineated by the Agreement as
negotiated and agreed to by the parties. The content of the duty to consult
falls in the mid-range of the consultation spectrum, more than low end
consultation but significantly less than the deep consultation asserted by the
Applicant (White River at para 98). The provisions of the Agreement
shape the duty to consult in this case (Little Salmon at para 67;
Agreement, ss 1.1.1, 11.6.2). Canada submits that a similar definition of
“consult” applied in Little Salmon and that there the Supreme Court of
Canada found that the duty to consult was at the low end of the spectrum (Little
Salmon at paras 57, 74, 79).
[144] Canada acknowledges that the potential for an impact on the
Applicant in this case would be more significant than that in Little Salmon,
but submits that this factor does not lead to a requirement of deep
consultation because the impacts on the Applicant are uncertain, indirect and
contingent. As found by the JRP, there is a chance that fish and seal
consumption advisories may be required if methylmercury levels rise beyond safe
levels in Lake Melville. Should such advisories be issued, it would adversely
affect seal hunting and fishing in Lake Melville. Further, as the Muskrat
Falls dam and reservoir will not be constructed or operated within the LISA
(i.e. it is an “undertaking” according to the Agreement), it has less exacting
procedural requirements than if it were constructed or operated therein (i.e.
if it were a “project” under the Agreement), also pointing to a lower level of
consultation.
[145] Canada also submits that the mid-range consultation requirement of
the Agreement is consistent with other situations where a mid-range duty to
consult has been found, such as in Yellowknives Dene First Nation v Canada
(Minister of Aboriginal Affairs and Northern Development), 2013 FC 1118 (at
para 59), Cold Lake (at para 33) and Katlodeeche (at para 95).
The scope of consultation in the mid-range includes adequate notice of the
matter to be decided, an opportunity to discuss with decision-makers the
potential adverse impacts of the decision and how those impacts might be
mitigated, and a requirement that the decision-maker take the expressed
concerns into account in making its decision (Katlodeeche at para 95).
[146] Canada submits that the Applicant’s current position on the scope of
consultation respecting the Project is not supported by the Agreement and is
also contradicted by past positions taken by the Applicant within the process.
[147] Nalcor submits that modern day comprehensive treaties are to be
interpreted generously and within the context of the written terms of the
treaty text ((Quebec (Attorney General) v Moses, 2010 SCC 17 at para 12;
Little Salmon at para 10).
[148] Like Canada, Nalcor submits that the Project is an “undertaking” as
defined by the Agreement. As such, the EA obligations differ and the Applicant
is entitled to less jurisdiction, control and engagement than if it were a
“project” (s 11.6.2). Therefore, consultation at the low end of the spectrum
is required.
[149] To the extent that Nalcor is required to respond to a challenge to
Canada’s Response, the Course of Action Decision and the Authorization, Nalcor
submits that ss 11.2.8, 11.2.9, and 11.6.1 to 11.6.6 of the Agreement apply.
[150] Further, there is no authority for the Applicant’s assertion that
the proper procedure pursuant to s 11.6.2 required Canada to provide the
Applicant with a draft preliminary decision on Canada’s Response and the Course
of Action Decision for review and comment.
[151] Nalcor submits that a duty to accommodate may be triggered where the
proposed Crown action is likely to infringe Aboriginal rights. This does not
mean that the Aboriginal groups have a veto over the proposed Crown action, nor
that the Crown has a duty to reach an accommodation agreement. This also does
not guarantee the Aboriginal group the outcome it desires. It simply requires
the Crown to balance the Aboriginal concerns and interests reasonably with
competing interests. Additionally, Aboriginal groups must be flexible and reasonable
when discussing accommodation options (Haida at paras 47-50, 62-63; Mikisew
Cree First Nation v Canada (Minister of Canadian Heritage), 2005 SCC 69 at
para 66 [Mikisew Cree]; Taku River at para 2; Native Council
of Nova Scotia v Canada v Canada (Attorney General), 2007 FC 45 at para 60,
aff’d 2008 FCA 113 [Native Council of Nova Scotia]; Kwicksutaineuk
Ah-Kwa-Mish First Nation v Canada (Attorney General), 2012 FC 517 at para
124 [Kwicksutaineuk]).
[152]
As set out above, the starting point for an
analysis of the content of the duty to consult in this case is the text of the
Agreement. Accordingly, the relevant provisions are set out below:
1.1.1 In the
Agreement, unless otherwise provided:
“Consult” means to provide:
(a) to the Person being consulted, notice of a matter to be
decided in sufficient form and detail to allow that Person to prepare its views
on the matter;
(b) a reasonable period of time in which the Person being
consulted may prepare its views on the matter, and an opportunity to present
its views to the Person obliged to consult; and
(c) full and fair consideration by the Person obliged to
consult of any views presented;
…
“Environmental Assessment” means:
(a) an assessment of the Environmental Effects of a proposed
undertaking, project, work or activity in Labrador Inuit Lands that is
conducted in accordance with Inuit Laws made under part 11.3;
(b) an assessment of the Environmental Effects of a Project or
Undertaking that is conducted under the Canadian Environmental Assessment
Act;
(c) an assessment of the Environmental Effects of a Project or
Undertaking that is conducted under the Environmental Protection Act; or
(d) an assessment that is conducted under two or more Laws
referred to in clauses (a), (b) and (c);
“Environmental Effect” means, in
respect of a proposed undertaking, project, work or activity:
(a) any change that the proposed undertaking, project, work or
activity may cause in the Environment, including any change to health and
socio-economic conditions, to physical and cultural heritage, to the current
use of lands and resources for traditional purposes by aboriginal individuals,
or to any structure, site or thing that is of historical, archaeological,
palaeontological or architectural significance; and
(b) any change to the proposed undertaking, project, work or
activity that may be caused by the Environment,
whether the changes occur within or outside
Canada;
…
"Project" means any
undertaking, project, work or activity proposed to be located or carried out in
the Labrador Inuit Settlement Area that requires an Environmental Assessment;
…
“Undertaking” means any undertaking,
project, work or activity proposed to be located or carried out outside the
Labrador Inuit Settlement Area that requires an Environmental Assessment under
the Canadian Environmental Assessment Act or the Environmental
Protection Act;
…
2.11.1 The
Agreement:
(a) constitutes the full and final settlement of the
aboriginal rights of Inuit in Canada; and
(c) exhaustively sets out the rights in Canada of Inuit that
are recognized and affirmed by section 35 of the Constitution Act, 1982.
…
CHAPTER 11: ENVIRONMENTAL ASSESSMENT
11.1.1 In
this chapter:
“Authority” means a federal or
Provincial authority, or both, as the case may be, including a Minister,
responsible for taking an action or making a decision pursuant to the Canadian
Environmental Assessment Act or the Environmental Protections Act;
…
Part 11.2 General
11.2.7 When
an Authority receives a registration document or an application for a Project
or an application for a permit, licence or authorization in relation to a
Project and the Project, in the opinion of the Authority, may reasonably be
expected to have adverse Environmental Effects, the Authority shall give:
(a) timely written notice of the Project and shall provide
relevant available information on the Project and the potential adverse
Environmental Effects to the Nunatsiavut Government; and
(b) written notice of the Project to
the other Authority.
11.2.8 When
an Authority receives a registration document or an application for an
Undertaking or an application for a permit, licence or authorization in
relation to an Undertaking and the Undertaking, in the opinion of the
Authority, may reasonably be expected to have adverse Environmental Effects in
the Labrador Inuit Settlement Area, the Authority shall give timely written
notice of the Undertaking and shall provide relevant available information on
the Undertaking and the potential adverse Environmental Effects to the
Nunatsiavut Government.
...
Part 11.6 Federal Environmental
Assessment Process
11.6.1 If, in
the opinion of a federal Authority, a Project or an Undertaking that is subject
to the Canadian Environmental Assessment Act may reasonably be expected
to have adverse Environmental Effects in the Labrador Inuit Settlement Area or
adverse effects on Inuit rights under the Agreement, the Authority shall, in
addition to providing the notice and information required under sections 11.2.7
and 11.2.8, ensure that the Nunatsiavut Government:
(a) is Consulted about the Environmental Effects of the
Project or Undertaking;
(b) is Consulted about the best way to achieve meaningful
participation of Inuit in the Environmental Assessment; and
(c) receives the report generated as a result of the
Environmental Assessment including, where applicable, the rationale,
conclusions, and recommendations of the official, mediator or review panel that
carried out the Environmental Assessment.
11.6.2 A
federal Authority shall Consult the Nunatsiavut Government before taking any
action that would allow a Project or Undertaking referred to in section 11.6.1
to proceed or making a decision to issue a permit, licence, funding, or other
authorization in relation to the Project or Undertaking.
11.6.3 If
Canada refers a Project or Undertaking referred to in section 11.6.1 to a
review panel under the Canadian Environmental Assessment Act:
(a) in the case of a Project, at least one member of the
review panel shall be a nominee of the Nunatsiavut Government; and
(b) in the case of an Undertaking, the members of the review
panel shall be selected from a list that includes candidates nominated by the
Nunatsiavut Government.
…
11.6.5 The
Nunatsiavut Government shall, in addition to its functions and duties in
relation to the matters referred to in part 11.2 and sections 11.6.1 and 11.6.2
with respect to public reviews, be entitled to make representations to the
mediator or review panel.
11.6.6 Upon
completion of the mediation or of the hearings of the review panel, the
mediator or review panel shall prepare and submit a report to the relevant
Authorities and the Nunatsiavut Government which shall include, but shall not
be limited to:
(a) a description of the Environmental Assessment process,
including provisions for public participation;
(b) a summary of any comments and recommendations from the
public; and
(c) the rationale, conclusions, recommendations and where
applicable, Mitigation measures and Follow-up Program requirements recommended
by the mediator or review panel.
Part 11.7
Monitoring
11.7.1 If a
Project or an Undertaking that may reasonably be expected to have adverse
Environmental Effects in the Labrador Inuit Settlement Area is allowed to
proceed subject to a permit, licence or other authorization containing conditions
that require Mitigation measures, the Nunatsiavut Government and the relevant
Authorities, within their respective jurisdictions, shall:
(a) coordinate their responsibilities for Follow-up Programs
to the extent possible; and
(b) in
the exercise of their powers or the performance of their duties and functions,
ensure that any Mitigation measures that they consider to be appropriate are
implemented.
[153] Chapter 4 of the Agreement defines the LISA and the LIL, the latter
being a number of specified areas located within the LISA, as well as Inuit
rights attached to both.
[154] The Project is an “undertaking” as defined by the Agreement because
it is an undertaking, project, work or activity proposed to be located or
carried out outside the LISA that requires an EA under the CEAA. It
is not a “project”, as that term is defined by the Agreement, as it is not
located or carried out in the LISA.
[155] Part 11.6 deals with the federal EA process for a “project” or an
“undertaking” that is subject to the CEAA and may reasonably be expected
to have adverse Environmental Effects in the LISA or adverse effects on Inuit
rights under the Agreement. Pursuant to Chapter 12 of the Agreement, that
would include areas outside the LISA where Inuit rights include the harvesting
of wildlife and plants (s 12.13.10) and time limited harvesting of migratory
birds (s 12.13.13) (see Schedule 12-E of the Agreement).
[156] It is this text that determines, or at the very least shapes, the
content of the duty to consult in this case.
[157] As noted above, the text of the Agreement is the primary source of
the content of the duty to consult in this case. To the extent that the
content of the duty to consult is not fully addressed by the terms of the
Agreement, or there is some doubt as to what that duty is comprised of, the
common law can be utilized to fill a gap or aid with interpretation.
[158] In that event, the starting place for an analysis of the scope of
the common law duty to consult remains Haida.
[159] In Haida, which did not concern a treaty duty to consult, the
Supreme Court of Canada held that the content of the duty to consult and
accommodate varies with the circumstances. The scope of the duty is
proportionate to a preliminary assessment of the strength of the case
supporting the existence of the right or title claimed and the seriousness of
the potential adverse effects on that right or title (para 39). At all stages
good faith is required by both sides. The Crown must have the intention of
substantially addressing Aboriginal concerns as they are raised through a
meaningful process of consultation, however, there is no duty to agree (para
42). Further:
[43] … the concept of a spectrum may be
helpful, not to suggest watertight legal compartments but rather to indicate
what the honour of the Crown may require in particular circumstances. At one
end of the spectrum lie cases where the claim to title is weak, the Aboriginal
right limited, or the potential for infringement minor. In such cases, the only
duty on the Crown may be to give notice, disclose information, and discuss any
issues raised in response to the notice. “‘[C]onsultation’ in its least
technical definition is talking together for mutual understanding”: T. Isaac
and A. Knox, “The Crown’s Duty to Consult Aboriginal People” (2003), 41 Alta.
L. Rev. 49, at p. 61.
[44] At the other end of the spectrum
lie cases where a strong prima facie case for the claim is established,
the right and potential infringement is of high significance to the Aboriginal
peoples, and the risk of non-compensable damage is high. In such cases deep
consultation, aimed at finding a satisfactory interim solution, may be
required. While precise requirements will vary with the circumstances, the
consultation required at this stage may entail the opportunity to make
submissions for consideration, formal participation in the decision-making
process, and provision of written reasons to show that Aboriginal concerns were
considered and to reveal the impact they had on the decision. This list is
neither exhaustive, nor mandatory for every case. The government may wish to
adopt dispute resolution procedures like mediation or administrative regimes
with impartial decision-makers in complex or difficult cases.
[45] Between these two extremes of the
spectrum just described, will lie other situations. Every case must be
approached individually. Each must also be approached flexibly, since the
level of consultation required may change as the process goes on and new
information comes to light. The controlling question in all situations is what
is required to maintain the honour of the Crown and to effect reconciliation
between the Crown and the Aboriginal peoples with respect to the interests at
stake. Pending settlement, the Crown is bound by its honour to balance
societal and Aboriginal interests in making decisions that may affect
Aboriginal claims. The Crown may be required to make decisions in the face of
disagreement as to the adequacy of its response to Aboriginal concerns. Balance
and compromise will then be necessary.
[46] Meaningful consultation may oblige
the Crown to make changes to its proposed action based on information obtained
through consultations…
[47] When the consultation process
suggests amendment of Crown policy, we arrive at the stage of accommodation.
Thus the effect of good faith consultation may be to reveal a duty to
accommodate. Where a strong prima facie case exists for the claim, and
the consequences of the government’s proposed decision may adversely affect it
in a significant way, addressing the Aboriginal concerns may require taking
steps to avoid irreparable harm or to minimize the effects of infringement,
pending final resolution of the underlying claim. Accommodation is achieved
through consultation, as this Court recognized in R. v. Marshall, [1999]
3 S.C.R. 533, at para. 22: “. . . the process of accommodation of the treaty
right may best be resolved by consultation and negotiation”.
[48] This process does not give
Aboriginal groups a veto over what can be done with land pending final proof of
the claim. The Aboriginal “consent” spoken of in Delgamuukw is
appropriate only in cases of established rights, and then by no means in every
case. Rather, what is required is a process of balancing interests, of give
and take.
[49] This flows from the meaning of
“accommodate”. The terms “accommodate” and “accommodation” have been defined
as to “adapt, harmonize, reconcile” . . . “an adjustment or adaptation to suit
a special or different purpose . . . a convenient arrangement; a settlement or
compromise”: Concise Oxford Dictionary of Current English (9th ed.
1995), at p. 9. The accommodation that may result from pre-proof consultation
is just this — seeking compromise in an attempt to harmonize conflicting
interests and move further down the path of reconciliation. A commitment to
the process does not require a duty to agree. But it does require good faith
efforts to understand each other’s concerns and move to address them.
(Also see Taku River at para 29).
[160] In Little Salmon, the Supreme Court found that the adequacy
of consultation must be assessed in light of the role and function to be served
by consultation on the facts of the case and whether that purpose was, on the
facts, satisfied (para 72).
[161] In this matter Canada concedes, and I agree, that the duty to
consult is higher than the duty at the lower end of the spectrum as was found
to apply in Little Salmon.
[162] Although the Supreme Court in Mikisew Cree also ultimately
concluded that the consultation required in that case was at the lower end of
the spectrum, its description of the content of that duty is useful. There,
the Supreme Court found that the determination of the content of the duty to
consult will be governed by the context. One such contextual factor is the
seriousness of the impact on the Aboriginal people of the Crown’s proposed
course of action. The more serious the impact, the more important will be the
role of consultation. In that case the most important contextual factor was
that Treaty 8 provided a framework within which to manage the continuing
changes in land use. In that context, consultation was held to be key to
achievement of the overall objective of the modern law of treaty and aboriginal
rights, being reconciliation (para 63). The content of the duty in that
context was as follows:
[64] The duty here has both
informational and response components. In this case, given that the Crown is
proposing to build a fairly minor winter road on surrendered lands where
the Mikisew hunting, fishing and trapping rights are expressly subject to the
“taking up” limitation, I believe the Crown’s duty lies at the lower end of the
spectrum. The Crown was required to provide notice to the Mikisew and to
engage directly with them (and not, as seems to have been the case here, as an
afterthought to a general public consultation with Park users). This
engagement ought to have included the provision of information about the
project addressing what the Crown knew to be Mikisew interests and what the
Crown anticipated might be the potential adverse impact on those interests.
The Crown was required to solicit and to listen carefully to the Mikisew
concerns, and to attempt to minimize adverse impacts on the Mikisew hunting,
fishing and trapping rights. The Crown did not discharge this obligation when
it unilaterally declared the road realignment would be shifted from the reserve
itself to a track along its boundary. I agree on this point with what Finch
J.A. (now C.J.B.C.) said in Halfway River First Nation at paras. 159-60.
The fact that adequate notice of an
intended decision may have been given does not mean that the requirement for
adequate consultation has also been met.
The Crown’s duty to consult imposes
on it a positive obligation to reasonably ensure that aboriginal peoples are
provided with all necessary information in a timely way so that they have an
opportunity to express their interests and concerns, and to ensure that
their representations are seriously considered and, wherever possible,
demonstrably integrated into the proposed plan of action.
[Emphasis added by Binnie J]
[163] A decision perhaps closer to the mid-range of the spectrum is Taku
River. There the first nation objected to a company’s plan to build a road
through a portion of its traditional territory. The first nation participated
in the EA process engaged by the province of British Columbia but took issue
with the process’ final outcome and challenged the Minister’s decision to issue
a project approval certificate. No treaty was in place. The Supreme Court
found that the first nation’s claim to rights and title was relatively strong,
and that the potential adverse effects of the Minister’s decision on the first
nation’s claims appeared to be relatively serious. Expert reports recognized
the first nation’s reliance on its system of land use to support its domestic
economy and its social and cultural life. Although the proposed access road
was only 160 km long, a geographically small intrusion on the 32,000 square kilometre
area claimed, it would pass through an area critical to the first nation’s
domestic economy and could attract further development. Therefore, it could
have an impact on the first nation’s continued ability to exercise its
Aboriginal rights and alter the landscape to which it laid claim. The Supreme
Court stated:
[32] In summary, the TRTFN’s claim is
relatively strong, supported by a prima facie case, as attested to by
its acceptance into the treaty negotiation process. The proposed road is to
occupy only a small portion of the territory over which the TRTFN asserts
title; however, the potential for negative derivative impacts on the TRTFN’s
claims is high. On the spectrum of consultation required by the honour of the
Crown, the TRTFN was entitled to more than the minimum receipt of notice,
disclosure of information, and ensuing discussion. While it is impossible to
provide a prospective checklist of the level of consultation required, it is
apparent that the TRTFN was entitled to something significantly deeper than
minimum consultation under the circumstances, and to a level of responsiveness
to its concerns that can be characterized as accommodation.
[164] In Katlodeeche, a First Nations band applied for judicial
review of the decision of the Minister of Indian and Northern Affairs to
approve a decision of the MacKenzie Valley Land and Water Board that granted
the proponent’s application for a water licence that would allow it to use
water for oil and gas exploration. This Court found that the first nation had
nothing more than reasonably arguable treaty and Aboriginal rights in the
project area, and that the seriousness of any potential adverse effects of the
water licence on the asserted treaty rights could be no higher than moderate.
The only convincing evidence of potential adverse impacts came from a report
indicating that, with the implementation of the recommended measures and the
proponent’s commitments, the proposed development would likely not have a
significant environmental impact or be cause for public concern. For that
reason, the duty to consult was found to be no higher than the mid-range of the
spectrum. More than mere notice and information sharing was required, but it
was not a case where deep consultation and serious accommodation were required
(paras 142-144).
[165] In Squamish Nation v British Columbia (Minister of Community
Sport and Cultural Development), 2014 BCSC 991, the British Columbia
Supreme Court found a mid-range duty as the first nation had a strong prima
facie claim to Aboriginal title and the potential for adverse impacts on
the Aboriginal title claim was moderate. The Court discussed the content of a
mid-range duty:
[197] Although every situation is unique
and should be approached flexibly and individually, I note some general
parameters from the case law on what a mid-range consultation may consist of.
It is more than a duty "to give notice, disclose information, and discuss
any issues raised in response to the notice" (Haida Nation
at para. 43). It is less than "the opportunity to make submissions for
consideration, formal participation in the decision-making process, and
provision of written reasons to show that Aboriginal concerns were considered
and to reveal the impact they had on the decision" (Haida Nation
at para. 44).
[198] In Dene Tha' First Nation v.
British Columbia (Minister of Energy and Mines) Grauer J. found that the
government engaged in a reasonable mid-range consultation by giving the First
Nation the opportunity to make "extensive and wide-ranging submissions",
exchanging reports and a "great deal of information, economic,
environmental, scientific and speculative", and setting up processes to
involve the First Nation "in ongoing development decisions that could give
rise to potential adverse impacts on its treaty rights" (at para. 117).
[199] In Long Plain First Nation
Hughes J. held that a mid-range consultation required more than the minimum of
giving notice, disclosing information and responding to concerns raised. He
said the consultation ought to include "at least some of the higher duties
including a duty to meet with the Applicants, to hear and discuss their
concerns, to take those concerns into meaningful consideration and to advise as
to the course of action taken and why" (para. 74).
[200] In Da'naxda'xw at para. 197
Fisher J. found that a mid-range duty to consult
required the Minister to consider the
Da'naxda'xw's request in the context of the terms of the Collaborative
Agreement and the on-going negotiations about a government-to-government
process for managing the conservancy and considering boundary amendments, and
to provide the Da'naxda'xw with an opportunity to respond to any substantive
concerns the Minister may have had. While the Minister was entitled to consider
the public interest as described in the government's policy, this required
something more than the opportunity for the Da'naxda'xw to make an application
within the scope of that policy. It required an opportunity for some dialogue
on a government-to-government basis with a view to considering a reasonable
accommodation of the Da'naxda'xw's interests in allowing the Project to be
assessed in the [environmental review] process.
[166] Recently, in Adam, where the applicant challenged two
decisions of the federal government made pursuant to the CEAA, Justice
Tremblay-Lamer found that deep consultation was required. The proposed
expansion of an open pit oil-sands mine would be carried out on the traditional
lands of a first nation, which held Treaty 8 rights. The expansion would
destroy a 21 kilometre stretch of the Muskeg River, much being the first
nation’s traditional land, including more than 10,000 hectares of wetlands, 85
percent of which were peatlands that could not be reclaimed. In addition, it
would adversely affect the first nation’s rights, notably its Treaty 8 rights
to hunting, fishing and the harvesting of animals and plants, and would
interfere with the maintenance of the first nation’s culture and way of life.
Justice Tremblay-Lamer concluded that a deep duty to consult was owed by the
Crown as:
The Project would destroy a large part of
the ACFN’s traditional lands and might also impinge upon the maintenance of
their culture and way of life. Some of the harm to the ACFN is potentially
irreversible or has not been mitigated through means of proven efficacy.
[167] Finally, I would note that although the duty to consult may require
accommodation where appropriate, the test is not a duty to accommodate to the
point of hardship for the non-Aboriginal population. Adequate consultation having
occurred, the Court’s task is to review the exercise of discretion taking into
account all the relevant interests and circumstances, including the strength of
the claim and seriousness of the impact on that claim (Little Salmon at
para 81). Said another way:
[2] ...Where consultation is
meaningful, there is no ultimate duty to reach agreement. Rather, accommodation
requires that Aboriginal concerns be balanced reasonably with the potential
impact of the particular decision on those concerns and with competing societal
concerns. Compromise is inherent to the reconciliation process...
(Taku River)
[168] Given these principles and decisions, the question is where does the
duty to consult lie on the spectrum in this case? The rights at issue are
established by the Agreement. Therefore, for the purposes of this spectrum
analysis, the strength of the claim need not be assessed and this factor can be
assumed to generally point to a higher level of consultation. However, the
potential impact of the Project on those rights is a factor that requires
assessment in the context of this application. In that regard, the Applicant
is primarily concerned with the downstream effects of methylmercury
bioaccumulation on its established subsistence rights.
[169] On that issue the JRP stated that it could not confidently conclude
what the ecological effects would be downstream from Muskrat Falls, that
Nalcor’s assertion that there would be no measurable effect on mercury levels
in Goose Bay and Lake Melville had not been substantiated, and, that there is a
risk of mercury bioaccumulation in fish and seals in Goose Bay and possibly
Lake Melville. Therefore, it made Recommendation 6.7, that DFO require Nalcor
to carry out a comprehensive assessment of downstream effects (JRP Report, Chapter
6, Aquatic Environment, pp 88-89).
[170] The JRP also determined that although there is still uncertainty
about whether consumption advisories would be required, this would have a “significant adverse effect” on fishing and seal
hunting in those areas because of the reliance by many Aboriginal and
non-Aboriginal people on fish and seals caught there (JRP Report, Chapter 8,
Land and Resource Use, p 146). As to Aboriginal land and resource use for
traditional purposes (Chapter 9), the JRP stated that if consumption
advisories are required in Lake Melville, this would likely have a marked
effect on the acceptability and attraction of Goose Bay and Lake Melville as
harvesting locations for fish and seals. Even if no advisories are required,
the JRP noted that reduced confidence in the safety of fish and seal meat would
have a negative effect on traditional harvesting activities, especially as the
recent decline of the George River caribou herd may cause residents to rely
more heavily on seal meat as a source of protein. Fishing and seal harvesting
activities could be displaced or reduced (JRP Report, p 167).
[171] The JRP further recognized that methylmercury production is an
inevitable result of reservoir impoundment and that the consumption of fish or
country food contaminated with methylmercury can pose risks to human health,
particularly in young children, and that consumption of these foods remains an
important part of many Labrador and Quebec Aboriginal and non-Aboriginal
peoples’ diets for both health and economic reasons. Further, that there is no
biophysical mitigation possible for this effect. It concluded that if
consumption advisories are required in Goose Bay and Lake Melville as a result
of elevated methylmercury in fish or seals from the Project, this would
constitute a “significant adverse effect” on the
residents of the Upper Lake Melville communities and Rigolet (JRP Report,
Chapter 13).
[172] Given these findings and considering the jurisprudence, it is my
view that this matter, absent a specification of the content of the duty to
consult in the Agreement, would fall between the medium and high end of the
spectrum. The potentially significant adverse environmental impact moves it
above the medium range but I am not convinced that it is a circumstance that
falls at the highest end of the spectrum. As noted by the JRP Report, if
mercury levels rise beyond the predicted levels thereby resulting in the use of
consumption advisories, this would be a significant adverse impact. However,
the risk is uncertain (JRP Report, pp 88-89, 238). Further, the JRP Report
also indicated that it is anticipated that the levels will peak 5 to 16 years
after flooding and then gradually decrease to background levels over 30 or more
years (JRP Report, pp 71-72). While this will take decades and may impact
harvesting rights and the Applicant’s traditional way of life, it is not
permanent or irreversible. Thus, these circumstances are unlike those in Adam
where an open pit oil-sands mine would be located on traditional lands, would
destroy a 21 kilometre stretch of river within those lands, including more than
10,000 hectares of wetlands that could not be reclaimed, and would negatively
impact harvesting rights.
[173] Further, while I reach this conclusion that the duty owed is between
the medium and high end of the spectrum based on the jurisprudence, and to the
extent that the common law duty may have application to this matter as an
interpretive tool or in the absence of a specific consultation provision, it
cannot be viewed in isolation of the text of the Agreement. In Little
Salmon, even though the Supreme Court found that because of a gap in the
relevant treaty the source of the duty to consult was the common law, it still
found that the treaty set out the elements that the parties regarded as an
appropriate level of consultation, including: notice of a matter to be decided
in sufficient form and detail to allow that party to prepare its view on the
matter; a reasonable period of time in which the party to be consulted may
prepare its views on the matter and an opportunity to present such views; and,
full and fair consideration by the party obliged to consult of any views
presented:
[75] In my view, the negotiated
definition is a reasonable statement of the content of consultation “at the
lower end of the spectrum”. The treaty does not apply directly to the land
grant approval process, which is not a treaty process, but it is a useful
indication of what the parties themselves considered fair, and is consistent
with the jurisprudence from Haida Nation to Mikisew Cree.
[174] In this case, the Agreement sets out the requirements of the duty to
consult in the same terms as described in Little Salmon. “Consult” is
defined as including notice; time for the person being consulted to prepare its
views and an opportunity to present them; and, full and fair consideration of
those views (s 1.1.1). Further, where an “undertaking” is subject to the CEAA
and may reasonably be expected to have adverse effects on Inuit rights under
the Agreement, the additional consultation requirements as set out in ss 11.6.1
to 11.6.6 apply. While in Little Salmon the same definition of consult
was at issue and the Supreme Court found consultation at the low end of the
spectrum, here the additional requirements of the Agreement, in my view,
require consultation at least at the mid-range of the spectrum.
[175] In that regard, it is also to be recalled that the Project is not
taking place in the LISA which, pursuant to the terms of the Agreement, would
in some circumstances have required a much higher level of engagement of the
Applicant in the EA process. Chapter 11, Environmental Assessment,
demonstrates that a higher level of direct involvement by the Applicant is
required when “projects” occur in the LIL. For example, no “project” in the
LIL shall commence until an EA has been completed and all necessary permits,
licences or other authorizations required for the project to commence have been
issued by the appropriate Authority and by the Applicant under an Inuit Law (s 11.2.1).
No similar bar applies to “undertakings”. Further, Part 11.3, which concerns
the jurisdiction of the Applicant with respect to undertakings, projects, works
or activities in LIL, states that the Applicant may decide whether a proposed
matter in LIL should be allowed to proceed and, if so, on what terms (s
11.3.1(b)). There is no similar provision with respect to “projects” or
“undertakings” taking place outside LIL, even where a project or undertaking
which is subject to the CEAA may reasonably be expected to have adverse
environmental effects in the LISA or on Inuit rights under the Agreement,
thereby giving rise to specified consultation requirements.
[176] As the Agreement sets out circumstances in which the Applicant’s
consent to an undertaking, project, work or activity would be required, and the
Project does not fall within that category, this is a factor that also supports
my view that the Project would not fall at the highest end of the consultation
spectrum. In short, the Agreement too supports a view that the appropriate
range is above the mid-range but below the highest level of the spectrum.
[177] In conclusion, I am of the view that the scope of the duty to
consult in this case is, in the first instance, determined by the text of the
Agreement. To the extent that it may have application, the content of the
common law duty to consult owed in the mid-range of the spectrum includes
adequate notice of the matter to be decided; a reasonable period of time to
permit the party being consulted to prepare its views on the issues and an
opportunity to present those views to the decision-makers; consultation in good
faith, with an open mind and with the intention of substantially addressing the
concerns of the party being consulted as they are raised through a meaningful
process of consultation (Haida at para 42; Makivik at paras
76-78); direct engagement with the party being consulted, including the
provision of information, soliciting, listening carefully to and seriously
considering their concerns; taking the expressed concerns into account when
making the decision; and attempting to minimize the adverse impacts (Katlodeeche
at para 95; Mikisew Cree at para 64). As this matter falls above the
mid-range, in my view the duty would also include a requirement of
responsiveness on the part of the Crown (Taku River at para 25).
[178] Put otherwise, the duty includes a requirement to demonstrate that
the views of the party being consulted were taken into consideration (Mikisew
Cree at para 64) and to provide a response to those concerns (Haida
at para 44; Ka’a’Gee Tu #2 at para 131; West Moberly at para 144)
with a view to reasonable accommodation (Da’naxda’xw/Awaetlala First Nation
v British Columbia (Minister of Environment), 2011 BCSC 620 at para 197).
[179] There may also be a requirement to accommodate, to the extent
possible, by taking steps to avoid or mitigate significant adverse effects or
irreparable harm.
[180]
The Applicant submits that the Authorization was
predicated on Canada’s Response and the Course of Action Decision which
permitted the Project to proceed such that any failure to adequately consult in
respect of those decisions tainted or compromised the ability to issue the
Authorization.
[181] Nalcor submits that this is an impermissible collateral attack on
Canada’s Response and the Course of Action Decision. First, the time period to
challenge those decisions pursuant to s 18.1(2) of the Federal Courts Act
has now expired (Behn v Moulton Contracting Ltd, 2013 SCC 26 at paras
37, 40-42; Cheslatta Carrier Nation v British Columbia (Environmental
Assessment Act, Project Assessment Director) (1998), 53 BCLR (3d) 1 (SC) at
paras 71-73; Aba-Alkhail v University of Ottawa, 2013 ONCA 633 at para
12; Papaschase Indian Band No 136 v Canada (Attorney General), 2004 ABQB
655 at para 114; Athabasca Chipewyan First Nation v Alberta (Minister of
Energy), 2009 ABQB 576 at paras 19, 23; Teletech Canada Inc v Canada
(Minister of National Revenue), 2013 FC 572 at paras 43-51). Second, the
Authorization was not predicated on Canada’s Response and the Course of Action
Decision. Rather, the Authorization is a separate decision made by a separate
body, namely DFO. And while Canada’s Response and the Course of Action
Decision decided whether the Project should be permitted to proceed, the
Authorization is a decision authorizing specific activities and the conditions
to which they are subject. Finally, the challenge to Canada’s Response and the
Course of Action Decision was improperly framed and pleaded as no relief is
sought in relation to those decisions, the Applicant did not name the other
ministries responsible for consultation in respect thereof, and, seeking
judicial review of three separate decisions would be in contravention of Rule
302 as they did not form a continuous course of action (Mahmood v Canada
(1998), 154 FTR 102 (FCTD) at para 10; Truehope Nutritional Support Ltd v
Canada (Attorney General), 2004 FC 658 at para 6; Servier Canada Inc v
Canada (Minister of Health), 2007 FC 196 at paras 17-18).
[182] Nalcor also submits, however, that the Crown consultations that
occurred before, during and after the EA relate to and inform the consultation
and accommodation in respect of the Authorization. In this regard, the
totality of the consultation between DFO and the Applicant in each phase of the
EA must be considered in order to understand the extent of the consultation in
respect of the Authorization.
[183] In my view, it is significant that while the EA process concluded
with the issuance of the JRP Report, the consultation process did not. Canada’s
Response was largely informed by Phases 1 to 3 of the Consultation Framework,
which culminated in the JRP report, and the Phase 4 consultation in response to
that report. The Consultation Framework also required consultation on
regulatory permitting in Phase 5, the process for which was determined by the Regulatory
Phase Protocol, and which informed the issuance of the Authorization.
[184] It is also significant that other court decisions concerning the
Project, described below, have held that challenges to the consultative process
commenced prior to the conclusion of the Phase 4 and 5 consultations were
premature or failed to recognize that the consultation process had not
concluded. This too suggests that the consultation process, as a whole, must
be considered when viewing the adequacy of consultation and accommodation
pertaining to the decision to issue the Authorization.
[185] This Court in Ekuanitshit FC, affirmed by the Federal Court
of Appeal, leave to appeal to SCC refused, was faced with an argument by Canada
that the Innu of Ekuanitshit had filed their application for judicial review
challenging the Order-in-Council approving Canada’s Response and the Course of
Action Decision before the federal government’s consultation period had come to
an end. At that time, the process was in Phase 5 of the Consultation
Framework. This Court found that the judicial review at that stage of the
federal government’s consultation and accommodation process was premature
because the acts that truly put the applicant’s rights and interests at risk
were those that required authorizations and approvals issued by DFO and TC. It
was premature to evaluate the federal government’s consultation process before
those decisions were made (Ekuanitshit FC at paras 108-112). Regardless
of that finding, the Court went on to assess the adequacy of the consultation
up to the time that the application was filed and found that the Crown had
satisfactorily fulfilled its duty to consult. The Federal Court of Appeal
agreed with this, stating that:
[108] With respect, I find it difficult
to conclude that the judge erred in finding that the appellant had been
adequately consulted prior to the government’s order being issued. Phase V of
the Consultation Framework confirms that the consultation process
between the Crown and the Aboriginal people continues up to the issuance of
licences by Transport Canada and Fisheries and Oceans. These licences will
authorize Nalcor to undertake certain activities, including the construction of
dams that could have consequences on the navigable waters under the Navigable
Waters Protection Act or on fish habitat under the Fisheries Act.
But we are not at that point yet. As confirmed and acknowledged by the lawyers
of the Attorney General of Canada, the federal government’s consultation has
not been completed and will remain ongoing until the final phase, namely, the
issuance of licences.
(Ekuanitshit FCA at para 108)
[186] The Federal Court of Appeal also stated that the Crown must continue
to honourably fulfill its duty to consult until the end of the process (para
110).
[187] Further, in Nunatukavut Community Council Inc v Newfoundland and
Labrador Hydro-Electric Corp (Nalcor Energy), 2011 NLTD(G) 44, the
Nunatukavut Community Council, representing the Inuit Aboriginal people of
central and southern Labrador, sought an interlocutory injunction to stop the
JRP hearings until the court had dealt with its claim. In February 2011,
Nunatukavut had sued Nalcor, Canada, the Province, the Agency and the five
Panel members. It sought, amongst other things, a declaration that the
defendants had breached their duty to consult with Nunatukavut and directions
on how consultations should be conducted. Justice Handrigan of the
Newfoundland and Labrador Supreme Court rejected the applicant’s claim that it
would suffer irreparable harm if the public hearings were not enjoined, as he
disagreed that the consultation and accommodation to that stage had been
deficient, and noted that there were still two phases following the hearings
during which Nunatukavut could continue to be involved before the process would
be finished.
[188] I would also note that the Applicant challenged a July 10, 2013
permit to alter a body of water issued by the Province with respect to the
Project on the basis that the Province breached its duty to consult and
accommodate the Applicant. The Supreme Court of Newfoundland and Labrador, in Nunatsiavut
v Newfoundland and Labrador (Department of Environment and Conservation),
2015 NLTD(G) 1 [Nunatsiavut, 2015 NLTD], decided that matter subsequent
to the hearing of the Applicant’s judicial review application before me. That
Court found that the conclusions of the EA provided an informed basis for
subsequent regulatory decision-making as various permits are sought. Further,
that the objection to the permit and to construction of the dam related to
issues of mercury contamination were fully considered by the JRP and by the
Province, although not to the Applicant’s satisfaction, before the Province
issued its Order-in-Council formally releasing the Project from the EA on March
15, 2012. Justice Orsborn was of the view that it was the decision to issue
the Order-in-Council that should have been challenged, rather than a subsequent
regulatory decision relating to the specifics of the Project construction. He stated
that “… in the circumstances of this case, allowing
issues relating directly to the response to the Joint Review Panel and the 2012
release Order to support a challenge to a later and separate issuance of a
regulatory permit would be unfair” (para 114). For that reason he
expressed no opinion on whether the Province’s response to the JRP Report, the
release Order itself suffered from any legal defect relating to consultation,
accommodation or reasonableness.
[189] Justice Orsborn also concluded that the Agreement, as regards to the
Province, excluded any duty to consult with respect to the decisions involving
specific regulatory permits in the context of an already approved undertaking,
noting that it contained no equivalent to the federal duty to consult set out
in s 11.6.2, although consultation obligations did arise from the Province’s
Aboriginal Consultation Guidelines.
[190] In contrast, in the matter before me, the Agreement specifically
contemplates further consultation at the regulatory permitting phase. In
accordance with that obligation, the Consultation Framework states that
decisions on regulatory permitting may require federal departments to further
consult Aboriginal groups on specific regulatory issues, and the decision to
undertake additional consultation will be made taking into consideration:
•
the consultation record;
•
mitigation, compensation, accommodation measures
to address outstanding concerns not addressed through the EA;
•
the government response to the JRP Report; and
•
any direction that may be provided by the
federal Cabinet.
[191] Thus, the phases of the consultation process, and the consultation
undertaken in each phase, are connected and, to some extent, cumulative.
[192] It is correct that the Applicant in its application for judicial
review challenges only the decision to issue the Authorization. It is also
correct that it is not open to the Applicant to collaterally attack the
validity of Canada’s Response or the Course of Action Decision by way of this
application. However, while Canada’s Response, the Course of Action Decision
and the Authorization were separate decisions, the consultation process that underlies
the JRP Report and all of the decisions made subsequent to it was an ongoing
one. As described above, two Courts have found that the consultation process
would not properly conclude until the Phase 5 consultation was complete, namely
the issuance of regulatory permits, authorizations or approvals. And, as
Nalcor submits, the consultation that occurred before, during and after the EA
relates to and informs the consultation and accommodation required in respect
of the Authorization. Accordingly, I agree with Nalcor that, in that regard,
the totality of the consultation between Canada and the Applicant in each phase
of the EA must be considered to understand the extent of the consultation and
accommodation in respect of the Authorization. To the extent that the
Applicant questions the content or adequacy of the consultation with respect to
the issuance of the Authorization, it is entitled to look to the prior
consultation record for that purpose, but not as an attempt to impugn the
validity of those prior decisions.
[193]
I do not accept the Applicant’s argument that
the consultation obligations in the Agreement could not be met, at least in
part, by the JRP process.
[194] The Agreement explicitly incorporated the JRP process into the
consultation process where Canada refers a project or undertaking to a review
panel under the CEAA (Agreement, ss 11.6.3-11.6.6).
[195] Further, jurisprudence confirms that the duty to consult can be
satisfied through the consultation that takes place within the regulatory
process. In Taku River, where the Aboriginal rights and title claims
were unproven and no treaty was in place, the Supreme Court of Canada held that
the process engaged by the Province of British Columbia under its
Environmental Assessment Act, in which the first nation had participated
for three years, fulfilled the procedural requirements of its duty to consult:
[40] The chambers judge was satisfied
that any duty to consult was satisfied until December 1997, because the members
of the TRTFN were full participants in the assessment process (para. 132). I
would agree. The Province was not required to develop special consultation
measures to address TRTFN's concerns, outside of the process provided for by
the Environmental Assessment Act, which specifically set out a scheme
that required consultation with affected Aboriginal peoples.
[196] In Little Salmon the Supreme Court referred to its decision
in Taku River and stated that there it had held “that
participation in a forum created for other purposes may nevertheless satisfy
the duty to consult if in substance an appropriate level of consultation is
provided” (para 39, emphasis in original).
[197] This issue has also previously been addressed in the context of this
Project in Ekuanitshit FCA, described above. There the Federal Court of
Appeal disagreed with the appellant that the Crown could not partially meet its
constitutional duties by including the Aboriginal group in the EA process
provided for under the CEAA. The Court ultimately concluded that the
findings of the JRP regarding the Innu of Ekuanitshit and the territory covered
by the Project were determinative in that case, and stated:
[99] In Taku River, the Supreme
Court held that participation in a forum created for other purposes, such as a
social and environmental impact assessment process, may nevertheless satisfy
the duty to consult if, in substance, an appropriate level of
consultation is provided. This principle was recently explicitly reiterated in Little
Salmon at paragraph 39 and in Carrier Sekani at paragraphs 55 to 58.
The Supreme Court of Canada, per Justice Binnie, further teaches that, under
the appropriate circumstances, the environmental assessment process provided
under the CEAA may be applied by the federal government to carry out
consultations and fulfill its duty to consult Aboriginal peoples (Quebec
(Attorney General) v. Moses, 2010 SCC 17, [2010] 1 S.C.R. 557 at
para. 45).
[Emphasis in original]
(Also see Katlodeeche, which held at
paragraph 97 that the Crown is entitled to rely on regulatory processes in
determining whether the duty to consult has been discharged).
[198] In my view, given that the use of the CEAA EA process in
these circumstances was explicitly contemplated by the Agreement, there can be
no question that the parties to the Agreement intended that it would comprise a
part of the required duty to consult with respect to the Project.
[199] Similarly, I see no error in the use of the five-phase Consultation
Framework or the Regulatory Phase Protocol. The Applicant was
advised in May 2007 that Canada and the Province proposed a JRP process for the
EA. In August 2010 the Consultation Framework was provided to the
Applicant which noted one concern regarding response time but otherwise took no
issue with process. As to the Regulatory Phase Protocol, this was
provided to the Applicant by the Agency in draft form in July 2012, following
which the Applicant commented on the draft and DFO revised the document in
consideration of those comments.
[200] So long as the process established by those protocols satisfies the
duty to consult required by the Agreement, and full and fair consideration was
given to any response provided to the proposed process contained in the
protocols, the requirement to consult as defined in the Agreement and set out
in ss 1.1.1, 11.2.8, 11.6.1 and 11.6.2 could be met by utilization of such
process. The Crown has discretion as to how it structures the consultation
process, and there is significant flexibility in how the duty is met (Cold
Lake at para 39).
[201] In that regard, the Regulatory Phase Protocol reflects the s
11.6.2 requirement to conduct ongoing consultation after the consultation
specific to the CEAA EA process set out in s 11.6.1 has been concluded.
[202] Thus, I conclude that the Crown’s consultation obligations could be
met, at least in part, through the JRP process.
[203]
The Applicant submits that it has been
consistent in making its concerns known and has attempted to establish an appropriate
research program to understand how methylmercury enters the food chain and to
ensure its early detection. Once levels begin to rise in fish and seals the
only step that can be taken is the issuance of consumption advisories, which
the Applicant submits is not a mitigation measure and will not protect the
Labrador Inuit’s right to engage in subsistence harvesting.
[204] The Applicant submits that Canada failed to carry out its
consultation duties under the Agreement in three material respects: (i) it
avoided and did not follow the requirements of ss 11.6.1 and 11.6.2 and failed
to properly consult the Applicant; (ii) it did not adequately consult the
Applicant with respect to its key decisions under s 11.6.2; and (iii) it failed
to provide full and fair consideration of and to adequately accommodate the
concerns of the Applicant.
[205] The joint letter of the Agency and the Province, dated May 1, 2008,
contains no reference to s 11.6. The Applicant submits that Canada’s approach
to this obligation was to avoid the issue instead of fulfilling its
obligations. This approach was applied consistently throughout the process, so
that when key decisions and steps were taken in relation to the Authorization,
Canada was not guided by s 11.6.2 but by reference to protocols and guidelines
developed by the federal and provincial governments.
[206] Section 11.6.2 required Canada to provide a draft of the EEM Plan
and Authorization once a preliminary decision on these matters was made, in
order to provide the Applicant with an opportunity to provide its views
thereon.
[207] Further, the Applicant submits that Canada did not adequately
consult it with respect to Canada’s Response and Course of Action Decision, as
required by s 11.6.2, which compromised its ability to issue the Authorization.
Specifically, the Applicant submits that its views were not given the required
consideration in Canada’s Response and Course of Action Decision, as Canada’s
Response does not refer to Inuit specifically or to the Agreement, and does not
address whether the Project may reasonably be expected to have adverse
environmental effects in the LISA or on Inuit rights under the Agreement. As
such, Canada has failed to establish that it fully and fairly considered the
Applicant’s views.
[208] In addition, Ray Finn’s final briefing note to the DFO Regional
Director General prior to Canada’s Response stated that the Applicant was “generally supportive” of the Project. A similar
statement is found in the summary of Aboriginal positions contained in the Aboriginal
Consultation Report. These statements unfairly misrepresent the
Applicant’s position, and are not in keeping with the honour of the Crown or
the requirement for meaningful consultation.
[209] The Applicant further submits that the Respondent did not give full
and fair consideration to the Applicant’s views on downstream mercury
contamination, as required by the Agreement, either in Canada’s Response, the
Course of Action decision or in the decision to issue the Authorization. The
Applicant had continually maintained the position that downstream effects
needed to be addressed and understood, which was also the position expressed by
the JRP in Recommendation 6.7. The decision to issue the Authorization shows
that the fundamental concerns and views of the Applicant were not addressed.
[210] With one exception, Canada’s Response to the views presented by the
Applicant in relation to the Authorization was to reject them. The change in
monitoring requirements in the EEM Plan was minor, did not address the
Applicant’s fundamental concerns or submissions, and was confined to what
Canada’s Response to Recommendation 6.7 directed. In short, Canada’s Response
served to predetermine what was considered and decided with respect to the
Authorization and the EEM Plan which was not fair or reasonable.
[211] Canada submits that the extensive consultations that took place in
this case were genuine, comprehensive and sufficient to discharge its duty to
consult pursuant to the Agreement, s 35 of the Constitution Act, 1982, and
in the context of the honour of the Crown, even if “deep consultation” was
required.
[212] The duty to consult does not constitute a veto over the proposed
course of action (Little Salmon at para 14; Mikisew Cree at para
65) and there is no duty to agree (Haida at paras 42, 49).
[213] Canada submits that it met its duty to consult as defined by the
Agreement, and that much of the consultation took place within the EA. The
Applicant should be taken to have accepted the procedural and substantive
consultation within the EA up to and including the issuance of the JRP Report
and the consultation in response to that report as: the Applicant participated
extensively in the JRP process; it directly provided input that resulted in
Canada making procedural and substantive changes; the JRP examined and
addressed its concerns; and, the Applicant acknowledged the adequacy and
substance of the JRP Report in its press release and its own response to the
JRP Report.
[214] Canada submits that the Applicant’s assertion that it was not consulted
on Canada’s Response to the JRP Report attempts to isolate artificially one
element of a complex and ongoing consultation process. In any event, Canada’s
Response and the process leading up to it have been reviewed by this Court and
deemed reasonable (Ekuanitshit FC at para 95). The consultation in this
case went further than that in Little Salmon, where a minimal process
satisfied the similar definition of “consult” in the treaty at issue in that
case.
[215] Similarly, Canada submits that the Applicant’s assertion that it was
not consulted in respect of the Authorization inappropriately isolates Phase 5
of the process. The process leading up to the issuance of the Authorization
was comprehensive and fair. The Applicant did not ask to review a draft of the
Authorization and provides no authority to support its assertion that there was
an obligation on Canada to provide such a draft. Further, the Applicant agreed
to the consultation protocols that were followed.
[216] The Applicant was advised on many occasions that DFO was
contemplating a Fisheries Act authorization and was consulted on the
process to be followed, including input into draft consultation protocols.
Although the Applicant now challenges the fact that DFO followed these
protocols, it largely endorsed them at the time. Further, in addition to the
steps set out in the Regulatory Phase Protocol, the Applicant met
personally with the Minister of Fisheries and Oceans on February 12, 2013 to
discuss particular issues. The Applicant was made aware that the FHC and EEM
Plans would be key conditions of the Authorization, and the Applicant made
known its concerns with respect to the EEM Plan. DFO responded to these
concerns and required Nalcor to make changes to the EEM Plan based on them. There
were no surprises in the text of the Authorization and the Applicant did not
ask to see a preliminary draft or raise the issue as a problem prior to filing
its Memorandum on judicial review. Aboriginal groups are required to make
their concerns known in order to provide the Crown an opportunity to address
them, and raising them for the first time in Court is not acceptable (Mikisew
Cree at para 65; Katlodeeche at paras 119, 164-165).
[217] As to accommodation, Canada submits that although it did not accede
to the Applicant’s request to be put in charge of baseline data collection and
monitoring of Lake Melville, and instead assigned the monitoring
responsibilities to Nalcor, it still reasonably and fully accommodated the
Applicant’s concerns by adapting the EA process and the Authorization
conditions. Compromise rather than perfection is required (Haida at
paras 62-63) and when consultation is meaningful, there is no ultimate duty to
reach an agreement (Taku River at para 2). If consultation has been
sufficient, it is acceptable for a decision-maker to make the contemplated
decision, even where the Aboriginal group maintains that their concerns have
not been addressed satisfactorily (Little Salmon at para 84; Katlodeeche
at para 101; Taku River at para 42).
[218] Canada submits that each of the Applicant’s concerns were responded
to within the consultation process, summarized as follows:
- “Full clearing” of the reservoir:
The Applicant agreed with the JRP’s recommendation until very late in the
process, but wrote to the Minister of Fisheries and Oceans on July 2,
2013, changing its position such that full clearing would now include
removal of all trees and the top layer of organic matter in the reservoir.
The JRP had already addressed such a suggestion, however, noting that
full clearing did not mean removal of all trees, and that soil removal was
not a proven mitigation measure. Further, the Minister responded to this
letter, advising that clear cutting of vegetation was a matter of
Provincial jurisdiction. In any case, the Applicant’s concerns have been
substantially addressed, as Nalcor is engaged in extensive clearing of
merchantable timber within the Muskrat Falls reservoir.
- Baseline data and monitoring program of potential downstream
impacts: Recommendation 6.7 was the
Applicant’s highest priority. Canada’s Response accepted the intent of
this recommendation and made it clear that it would require Nalcor to
collect further baseline data prior to impoundment, and to conduct a
multi-year monitoring program on mercury and other potential downstream
effects. The Applicant supported Recommendation 6.7 and took the position
that Nalcor should be required to provide funding to the Applicant so it
could lead a research group to gather baseline data and monitor Lake
Melville.
DFO advised the Applicant that it would
ensure that Nalcor gathered appropriate baseline data and conducted ongoing
significant monitoring of Lake Melville. Further, that it would not direct
Nalcor to retain or fund the Applicant to carry out this work. Canada required
Nalcor to make enhancements to its draft EEM Plan in respect of baseline data
and monitoring, and the Authorization satisfies the Applicant’s main concerns
in these respects. Furthermore, the Applicant is conducting its own baseline
assessment and monitoring of downstream effects relating to the Project, so it
will have the benefit of Nalcor’s research as well as its own. Finally, DFO
has the power to rescind the Authorization or take other measures in the future
if it is determined that the impacts are more serious than those authorized.
- Inuit representation on Project management, and framework
agreement: In its November 2011 letter, the
Applicant took the position that the Authorization should stipulate: (a)
that the Applicant would participate in a high-level Project management
structure; and (b) that Nalcor and the Applicant would have to conclude a
framework agreement to address compensation if adverse impacts were to
materialize. DFO responded to this letter, and there was no subsequent
communication on the issue of participation in management.
[219] Canada submits that the conditions of the Authorization address the
Applicant’s underlying concerns and represent an appropriate and significant
compromise although not precisely as proposed by the Applicant. As appropriate
consultation took place, and the Applicant’s concerns were heard, understood
and taken into account, the discretion to authorize the Project was exercised
reasonably and the terms of the Agreement and the honour of the Crown were
upheld.
[220] Nalcor submits that the Applicant was consulted on the high end of
the spectrum, beyond what was required under the Agreement, and that its
concerns were adequately accommodated.
[221] Pursuant to s 11.2.8, the Applicant was notified by DFO of the
Project registration, the EA and the Authorization. The Applicant was also
provided with substantial information before, during and after the EA including
the EIS, the IRs (many of which responded directly to the Applicant’s comments),
the draft FHC Plan and EEM Plan, as well as information provided directly by
DFO and Nalcor. Pursuant to s 11.2.9, the Applicant was consulted extensively
about the EA process.
[222] With respect to s 11.6.1(a), consultation about the Environmental
Effects of the Project, the Applicant received early notice of the Project,
received thousands of pages of information, and had time to prepare studies,
presentations and submissions on its views, as well as federal funding to do
so. The Applicant attended the JRP hearings and had direct meetings with
representatives of DFO and other government representatives for the purpose of
presenting its views, including a meeting with the Minister.
[223] Nalcor submits that the very views that the Applicant now claims
were not fully and fairly considered were expressly and demonstrably considered
by the JRP, the RAs and the Governor-in-Council, and mitigation measures were
imposed to directly accommodate the Applicant’s views and concerns. In
particular, IR # JRP.166 required Nalcor to increase the study area for
downstream effects beyond those set out in the EIS. Further, the Applicant was
directly consulted on the JRP Report, and Canada’s Response and the Course of
Action Decision accepted the majority of the JRP’s recommendations with which
the Applicant is concerned and mandated key mitigation measures to protect
Aboriginal interests.
[224] In respect of the Authorization, once notice was given under ss
11.2.8 and 11.2.9, the only relevant provision was s 11.6.2, which required DFO
to consult before making a decision to issue the Authorization. The Applicant
received notice of the Authorization application and, prior to that, had been
advised of the impending regulatory consultation. DFO consulted with the
Applicant on the protocol for such consultation. The Applicant was also
provided with advance copies of the FHC Plan and EEM Plan, summaries of these,
and additional detail about these plans.
[225] The Applicant was provided with a reasonable period of time to
prepare its views on the FCH Plan and EEM Plan and opportunities to present
them.
[226] As to full and fair consideration, the body of the EA consultation
record was before DFO. DFO had also consulted directly with the Applicant
since 2006 and, therefore, had an advanced understanding of the Applicant’s
concerns. DFO also provided oral and written responses to the Applicant as to
how its concerns were considered.
[227] In addition, the Applicant was reasonably accommodated. To the
extent that DFO did not follow the Applicant’s precise requests, this was
because it was not within DFO’s jurisdiction to do so or a reasonable
alternative measure had already been adopted in the Authorization. The Crown
is not required to agree to all of the Applicant’s requests. Rather, its
decision must fall within a range of reasonable outcomes.
[228] Aboriginal groups must also be flexible and reasonable when
discussing accommodation options (Haida at paras 47-50, 62-63; Mikisew
Cree at para 66; Taku River at para 2; Native Council of Nova
Scotia at para 60; Kwicksutaineuk at para 124).
[229] As to full clearing of the Muskrat Falls reservoir, such a direction
is ultra vires the Minister, and Canada’s Response noted that this lay
within provincial jurisdiction. Further, Nalcor concluded that there was no
scientific evidence to support the assertion that full clearing would result in
a meaningful reduction of methylmercury impacts downstream. In any event, this
issue was extensively considered, and such a direction would have been
unreasonable in the circumstances.
[230] As to the aquatic effects prediction and assessment program, this
issue was the subject of extensive consultation and was a requirement of
Canada’s Response and the Course of Action Decision. DFO also required
enhancements to the draft EEM Plan as a result of the Applicant’s comments.
Nalcor submits that the Applicant simply prefers its own program to that
required by the Minister and is asking the Court to usurp the role of the
Minister and become an “academy of science”. It
has provided no evidence to support the probability of adverse effects within
the LISA, and Nalcor’s research does not support the Applicant’s theory that it
will be affected by increased mercury levels. During the EA, the Applicant was
dissatisfied with Nalcor’s research and, in order to accommodate the
Applicant’s concerns, Nalcor was required to do additional research and
modelling which supported the same conclusion. Nalcor has also undertaken to
implement an extensive monitoring program to monitor mercury levels in fish and
has committed to posting consumption advisories if mercury levels reach or
exceed Health Canada’s guidelines.
[231] DFO concluded that the plans contemplated by the Authorization are
reasonable in the circumstances. This was the very decision that the Minister
was empowered to make.
[232] Finally, as to a framework agreement between Nalcor and the
Applicant, Nalcor submits that the scientific evidence before the Minister was
that significant downstream impacts in the LISA are unlikely. Further, the
plans already require engagement in respect of mitigation, including
compensation, if monitoring suggests downstream impacts are occurring in the
LISA. As no downstream impacts are anticipated, it is unreasonable to require
a framework agreement. The Authorization reasonably requires Nalcor to carry
out the necessary monitoring and to act promptly if the predicted environmental
effects are exceeded.
[233]
In making the decision to issue the
Authorization, I find that Canada adequately consulted and accommodated the
Applicant in accordance with the terms of the Agreement. Before I give my
reasons for this conclusion, I will briefly deal with some of the related
concerns that the Applicant has raised which can be disposed of separately from
the main analysis.
i. Adequacy of Consultation
in Phases 1-3
[234] As discussed above, the Agreement specifically defines an EA as
including an assessment of the environmental effects of an undertaking that is
conducted under the CEAA. The Project is an undertaking as defined in
the Agreement. Consult is defined in the Agreement as requiring notice, a
reasonable period of time for the party being consulted to prepare and an
opportunity to present its views on the matter, and, full, and fair
consideration of those views. Further, because the Project was identified as
one that would reasonably be expected to have adverse environmental effects in
the LISA or on Inuit rights under the Agreement, there was a further obligation
pursuant to s 11.6.1 of the Agreement to ensure that the Applicant was
consulted about the environmental effects, the best way to achieve meaningful
participation of the Inuit in the EA, and that it received a report generated
as a result of the EA, including the rationale, conclusions and recommendations
of the JRP.
[235] It is my view that the summary of the facts set out at the beginning
of these reasons demonstrate that the Applicant was adequately consulted in
Phases 1-3 by way of the EA process conducted by the JRP as contemplated by the
Agreement. That is, that the consultation requirements of s 11.6.1 were met.
[236] The Applicant was fully engaged in the JRP process and the JRP was
mandated to and did set out in the JRP Report information provided by
Aboriginal groups, including the Applicant, concerning traditional uses as
related to the potential environmental effects of the Project on recognized
Aboriginal rights, as well as their concerns in that regard. The issue of
potential methylmercury bioaccumulation, including downstream of Muskrat Falls
and in Goose Bay and Lake Melville, was at the forefront of the JRP’s
considerations and was the basis of many of its Recommendations. When the JRP
Report was issued, the Applicant publicly expressed its general satisfaction
with its conclusions (Nunatsiavut, News Release, “Nunatsiavut
Government pleased with panel recommendations on proposed Lower Churchill
project” (29 August 2011)) and, significantly, the focal point of the
Applicant’s concerns with the consultation and accommodation process that
followed the issuance of the JRP Report is the extent to which Nalcor was
required to comply with JRP Recommendation 6.7, the assessment of downstream
effects.
[237] Further, although at various points in its written and verbal
submissions the Applicant suggested that its concerns, in particular
methylmercury bioaccumulation downstream of the Project, were not given
adequate consideration throughout the EA process as well as prior to the
issuance of the Authorization, the Applicant ultimately conceded at the hearing
before me that it did not take issue with the adequacy of the consultation
afforded to it by way of the JRP. Accordingly, the underlying consultation in
those phases is not at issue with respect to the decision to issue the
Authorization, as per s 11.6.2 of the Agreement, when taking into consideration
the totality of the consultation in all five Phases.
ii. Aboriginal
Consultation Report
[238] The Applicant also takes issue with the internal Aboriginal
Consultation Report concerning the Project which was prepared by the Agency
in January 2012. The Applicant submits that the report misrepresents its
position, thereby acting contrary to the honour of the Crown, or that it
indicates a lack of meaningful consultation.
[239] The Applicant was unaware of this document until the disclosure
process connected with its application for judicial review. Importantly,
however, the report describes the positions of each of the Aboriginal groups
identified therein with respect to their views as to how the potential adverse
effects of the proposed Project may impact their potential or established
Aboriginal or treaty rights. This was based on the presentations the
Aboriginal groups made to the JRP and on comments made by them directly to
federal government department officials.
[240] Section 6.2 of the Aboriginal Consultation Report concerns
the Applicant, the Nunatsiavut Government, as the representative of the Inuit
of Labrador. It describes the community profile, the Agreement, including that
Inuit living outside the LISA have rights to harvest wildlife, plants and
migrating birds pursuant to the provisions of Chapter 12 (Schedule 12-E), and
that s 11.6.1 of the Agreement requires consultation. The report notes that in
its March 31, 2011 submission to the JRP the Applicant stated that it could not
support the Project as currently proposed. In the Applicant’s final submission
to the Panel in April 2011, it expressed its concerns, as described, and
provided a list of recommendations to address those issues. The report also
describes the JRP conclusions as to the Applicant’s concerns and the
Applicant’s response to the JRP Report of November 11, 2011, including the
Applicant’s three main mitigation recommendations. The report summarized the
Applicant’s position as follows:
7.1.1 Nunatsiavut
Nunatsiavut is primarily concerned with the
potential effects of mercury downstream of the Project. The proponent did not
consider that Inuit would be affected by its project and essentially excluded
Labrador Inuit from their analysis of project impacts. Nunatsiavut emphasized
that the Panel made a significant adverse effect pronouncement for Inuit,
without making the same determination for any other Aboriginal group involved
in the environmental assessment process.
Nunatsiavut maintain that Inuit rights and
title, and traditional territory as established under the Labrador Inuit Land
Claims Agreement and agreed upon in the overlap agreement with Innu Nation will
be significantly adversely affected if the proposed development proceeds. They
stated that this must be accommodated for and mitigated by the proponent and
the provincial and federal governments and clarified that further consultation
does not constitute, and is not equal to, mitigation. Nunatsiavut also directed
the provincial and federal governments to review a recent study on the human
health effects of prenatal and childhood exposure to environmental
contaminants, such as methylmercury, on the health and development of Inuit
children in Nunavik (northern Quebec) that was released subsequent to Panel
hearings.
[241] Section 7.2 of the report also noted that the Applicant had provided
recommendations for addressing their concerns regarding mitigation while moving
forward with Project development, being participation in a high level
management mechanism for the Project and a minimum of $200,000 funding annually
for baseline research and monitoring. An outstanding issue was identified,
that being the Applicant’s desire to have a mechanism to compensate Inuit for
any Project effects: in its response to the JRP Report, the Applicant had
proposed text that it wished to be included with the permit(s) associated with
the Project.
[242] The Applicant takes issue with this report, in that it states that
Nunatsiavut “are generally supportive of the Project”
(Aboriginal Consultation Report, s 7). When asked about this by way of
his Responses to Written Examination, Chapman stated that it was his
understanding that this statement was based on the fact that the Applicant had
provided recommendations to the JRP on how issues of concern to the Applicant
could be remedied and had not refused outright to consider the Project
proceeding in any form.
[243] Similarly, the Applicant takes issue with the January 30, 2012
internal DFO memo to the DFO Regional Director General, as it also states that
the Innu Nation and Nunatsiavut Government “are
generally supportive of the Project”. The Applicant submits that this
is a misrepresentation of its position. When questioned on this point by way
of his Responses to Written Examination, Finn, the author of the memo, stated
that his statement that the Applicant was generally supportive of the Project
was based on the fact that the Applicant had provided recommendations to the
JRP during and after the Panel hearings on how issues of concern to the
Applicant could be remedied. By way of example, he referred to the
recommendations made by the Applicant in its April 13, 2011 submissions to the
JRP and its recommendations made in its response to the JRP Report.
[244] In this regard it is of note that in its response to the JRP Report,
the Applicant set out three major recommendations that would “help to mitigate impacts on Inuit and Inuit Rights and allow
Inuit to constructively contribute to the Lower Churchill process going
forward”. Further, in its January 16, 2012 letter to the Province and
DFO, the Applicant set out four core mitigative measures it had raised at a
January 9, 2012 meeting with the Premier of the Province. Both of these
documents predate both the internal DFO memo and the Aboriginal Consultation
Report that the Applicant takes issue with.
[245] In my view, little turns on this issue. The Aboriginal
Consultation Report as well as the JRP Report clearly communicated the
Applicant’s concerns, including its ongoing concern with the downstream effects
of methylmercury bioaccumulation and the mitigation steps that it had
proposed. More importantly, the comments reasonably reflect the Applicant’s
position at the time that they were made. Accordingly, I do not agree that DFO
misrepresented the Applicant’s position and thereby acted contrary to the
honour of the Crown or that the comments indicate a lack of meaningful
consultation.
[246] The Applicant also points out that while the internal DFO memo at
issue is dated six days after the Agency’s Aboriginal Consultation Report,
it states that DFO would participate in the Aboriginal Consultation Report
to ensure Aboriginal concerns were addressed, where appropriate, prior to
Canada making its decision. Again, in my view, while DFO’s internal update
memo was inaccurate, little turns on the point.
iii. Section 11.6.2
Procedure
[247] The Applicant also submits that the Agreement is to be interpreted
as requiring a procedure whereby Canada was to provide the Applicant with
copies of the reports generated as a result of the EA process as required by s
11.6.1(c), and then, under s 11.6.2, to make a preliminary decision on the
Project. If that preliminary decision was to allow the Project to proceed,
then the Applicant should have been notified, provided with sufficient
information about the proposed decision to allow it to formulate its views and
allowed a reasonable amount of time to prepare a response, which would then be
fully and fairly considered.
[248] In my view, this is in effect an attempt to collaterally attack
Canada’s Response, as that was the decision that permitted the Project to
proceed, subject to the requirements of the Course of Action Decision. I would
note, however, that the Applicant was provided with the report required by s
11.6.1(c), which was the JRP Report. As to s 11.6.2, it requires consultation
prior to any action that would allow the Project to proceed or the making of a
decision to issue an authorization in relation to the Project. As described
above, the Applicant was consulted on the JRP Report in Phase 4.
[249] As to the procedure envisaged by the Applicant, that would require
Canada to make a preliminary determination as to whether the Project would
proceed and then to consult on that preliminary determination, this is one of
its own interpretation. Neither s 11.6.2 or any other of the Agreement’s
consultation provisions specify that approach. Nor did the Consultation
Framework, to which process the Applicant had largely agreed. In my view,
it is not open to the Applicant to challenge, after the fact, a process to
which it agreed.
[250] Similarly, Canada did not breach its duty to consult by virtue of
the fact that DFO did not circulate a draft of the Authorization or the revised
EEM Plan prior to its issuance.
[251] Section 11.6.2 does not specify that drafts must be circulated prior
to approval or issuance, and the Regulatory Phase Protocol, upon which
the Applicant had been consulted, did not contemplate that after comments were
received, a revised draft EEM Plan would be circulated to the Applicant prior
to approval by DFO. Rather, the Regulatory Phase Protocol specified
that, if comments were received, they would be given full and fair
consideration by the RA, in writing, and that the RA would incorporate changes
as appropriate. This is what occurred.
[252] The Applicant did not seek such a requirement when commenting on the
draft Regulatory Phase Protocol, or at any time, and it is not now open
to the Applicant to subsequently challenge the sufficiency of the consultation
process on a point with which it did not take issue at the relevant time.
[253] Similarly, when the Applicant commented on the draft Regulatory
Phase Protocol, it did not request that it be provided with a draft of the
Authorization prior to issuance. Rather, it requested that it be provided with
the Authorization within 5 days of issuance. In fact, it was provided with it
on the same day that it was provided to Nalcor. This did not constitute a
breach of DFO’s duty to consult.
iv. May
1, 2008 Letter
[254] The Applicant also submits that because the joint letter of May 1,
2008 from the Province and the Agency refers only to ss 11.2.2, 11.2.8, 11.2.9
and 11.5.11, with no reference to Part 11.6 of the Agreement, this demonstrates
that Canada avoided its ss 11.6.1 and 11.6.2 obligations, including determining
whether the Project would reasonably be expected to have adverse environmental
effects in the LISA or on Inuit rights under the Agreement, so that when key
decisions and steps were being taken in relation to the Authorization, Canada
was not guided by the terms of s 11.6.2, but by the protocols and guidelines
developed by the federal and provincial governments.
[255] In my view, this submission is of no merit. The letter was written
by the Province, with the consent of the Agency, which may explain why it
referenced those provisions of the Agreement which pertained to the Province’s
obligations. Further, DFO and TC wrote to the Applicant on August 8, 2007
providing the registration document pursuant to s 11.2.8 of the Agreement and
explaining that the Project would require Fisheries Act authorizations,
triggering an EA. The EA process as contemplated by s 11.6 then commenced.
[256] Thus, in my view, the omission in the May 1, 2008 joint letter is
not important when viewed in the context of the whole of the consultation
process. The real issue is not whether Part 11.6 of the Agreement was
explicitly referenced in that letter, but whether the substantive content of
the duty to consult pursuant to the Agreement was met.
v. Failure to Identify
the Applicant in Canada’s Response
[257] The Applicant also submits that Canada’s Response fails to mention
the Labrador Inuit by name, instead referring only to Aboriginal groups, and
that this brings into question whether its concerns were considered at all, let
alone fully and fairly. Again, this is an improper collateral attack on
Canada’s Response. In any event, there is also no merit to the position.
Canada’s Response cannot be viewed in isolation from the JRP Report which,
pursuant to the Agreement, properly formed a part of the underlying
consultation process. The JRP Report explicitly identified the Applicant as
one of the Aboriginal groups which participated in the EA process and
identified and discussed in detail the Applicant’s concerns as to methylmercury
bioaccumulation, downstream effects and otherwise. Canada’s Response was not
required to restate the content of the JRP Report, and its failure to name the
Applicant and the other Aboriginal groups identified in the JRP Report and in Aboriginal
Consultation Report is not fatal.
[258] The real issue in this judicial review is whether the Applicant was
adequately consulted and accommodated in respect of the decision to issue the
Authorization. In that regard, in July 2010 DFO advised the Applicant that,
pursuant to the Consultation Framework, the federal government was
entering the regulatory permitting phase of the Project and wished to continue
consultations with respect to specific regulatory decisions, approvals or
actions that may have potential adverse impacts on Aboriginal rights or title.
Further, that the federal government anticipated the issuance of a s 35(2) Fisheries
Act authorization from DFO for the harmful alteration, disruption or
destruction of fish habitat and a s 32 Fisheries Act authorization from
DFO for the destruction of fish. DFO provided the draft Regulatory Phase
Protocol for the Phase 5 consultations. The Applicant provided comments on
the draft protocol, and it was subsequently revised by DFO in consideration of
the comments received.
[259] On February 12, 2013 the Applicant met with the Minister of
Fisheries and Oceans to discuss its concerns about the Project including
downstream effects and, for the first time, stated that its preliminary data
suggested that total mercury from the Churchill River extends into Lake
Melville and the LISA, although a copy of that data does not appear to have
been provided by the Applicant. The Applicant also continued to seek annual funding
for its research and monitoring of the overall effects on the downstream
environment.
[260] On February 28, 2013 DFO advised the Applicant that it was preparing
to issue a Fisheries Act authorization, provided it with the draft FHC
and EEM Plans and sought comments within 45 days as per the Regulatory Phase
Protocol. The Applicant did not provide comments on the FHC Plan but on
several occasions expressed concerns regarding inadequacies in the EEM Plan
with respect to baseline data. This included a meeting with DFO on March 22,
2013 and formal written comments regarding the EEM Plan on April 15, 2013
which, in essence, took the position that by way of Recommendation 6.7, the JRP
had required a holistic and comprehensive downstream effects assessment, but that
Nalcor was not being required to undertake this. The Applicant was of the view
that without a comprehensive baseline understanding of the whole of the Lake
Melville system, an appropriate monitoring program could not be established.
And, accordingly, that the EEM Plan was not of sufficient form and detail to
allow the Applicant to prepare its views. The Applicant again sought, as a
condition of the Authorization, that Nalcor fund the Applicant’s comprehensive
downstream effects assessment.
[261] DFO responded to these comments on May 30, 2013. It stated that it
was of the view that the EEM Plan contained sufficient detail to allow the
Applicant to prepare its views and comment on the plan. And, based on the
comments received, DFO would require Nalcor to add to the EEM Plan additional
details on the protocols for sampling and analysis of fish and seals for
methylmercury currently set out in baseline monitoring reports. As to
Recommendation 6.7, Canada’s Response stated that Nalcor would be required to
collect additional baseline data on methylmercury bioaccumulation in fish and
on fish habitat downstream of Muskrat Falls prior to impoundment. Such
information had been collected by Nalcor in 2011 and 2012, including Lake
Melville, and would continue to be collected prior to impoundment. DFO also
explained that the primary objective of an environmental effects monitoring or
follow-up program was to verify specific predictions made by a proponent during
an environmental assessment, especially where there may be uncertainty about
the severity or extent of a possible impact. EEM programs are not designed or
implemented to study environments or changes in them overall. The EEM Plan
addressed those predictions for which DFO considered monitoring to be required
for verification, including in relation to methylmercury bioaccumulation in
fish. Finally, as to the Applicant’s funding request, DFO stated that it
typically sets out monitoring and reporting requirements that a proponent must
meet, but does not specify who a proponent is to engage to carry this out. On
June 28, 2013 DFO also responded to the Applicant’s letters of November 11,
2011 and July 24, 2012 addressing the concerns raised on a point by point
basis.
[262] The Applicant wrote to the Minister of Fisheries and Oceans on July
2, 2013 reiterating its concerns with DFO’s position as to downstream impacts
of the Project and the related EEM Plan. It stated that throughout the EA and
post-EA process, Nalcor had not provided meaningful baseline measurements or conducted
sufficient research to characterize the downstream environment that would be
impacted by the Project, particularly in Lake Melville. Further, that Canada’s
Response to Recommendation 6.7 was an extreme simplification of its intent.
Canada’s Response eliminated the need to understand the downstream environment
at a holistic level and the ability to model or predict downstream impacts
prior to flooding. The Applicant sought a comprehensive baseline study to
provide foundational knowledge which it deemed essential for the prediction of
downstream impacts and for the formulation of a meaningful EEM Plan and
consultation respecting that plan. While acknowledging that the total
elimination of increased mercury and methylmercury concentrations downstream
may be impossible, the Applicant submitted that the primary and only mitigation
measure that could reduce the risk or concentration of mercury prior to
flooding was full clearing of the reservoir area, and took the position, for
the first time, that removal of all the trees and the top layer of organic
matter was also required as an aspect of this.
[263] The Authorization with conditions was issued on July 9, 2013 and was
provided to the Applicant on the same day. On July 12, 2013 the Minister
responded to the Applicant’s February 12, 2013 concerns and on August 27, 2013
the Minister responded to the Applicant’s letter of July 2, 2013.
[264] In my view, the communications between DFO and the Applicant
together with the Regulatory Phase Protocol process served to satisfy
the consultation requirements of s 11.6.2 of the Agreement. I would have
reached the same conclusion applying the content of the common law duty to
consult above the mid-range but lower than the high end of the spectrum as
described earlier in these reasons.
[265] This is because the Applicant was given notice by DFO that it was
preparing to issue a Fisheries Act authorization and was provided with
the draft EEM Plan for comment. DFO met with the Applicant to discuss its
concerns regarding the EEM Plan. The Applicant then put its concerns in
writing and DFO responded to them in writing. As will be discussed further
below in the context of accommodation, DFO required Nalcor to add to the EEM
Plan additional details on the protocols for sampling and analysis of fish and
seals as a result of the Applicant’s comments on the draft EEM Plan, indicating
that the Applicant’s concerns were considered. While the Applicant does not
agree with DFO’s responses and feels that they did not address its view that
there was a need for a holistic and predictive downstream assessment, in my
view DFO’s response does reflect full and fair consideration of the issues that
the Applicant raised.
[266] While the Applicant argues that the EEM Plan was not of sufficient
form or detail to permit it to prepare its views, and that therefore there was
no consultation as defined by the Agreement, what the Applicant is really
saying was that it refused to address the EEM Plan because its demands to lead
a broad based, funded, comprehensive study of Lake Melville, from an Inuit
perspective, had not been accommodated.
[267] Phase 5 was concerned with the regulatory process surrounding the
issuance of the Authorization and, more particularly, with the preparation of
the FHC and EEM Plans which were to be conditions of the Authorization. As
noted by DFO in its communications to the Applicant, the EEM Plan deals with
monitoring and follow up for the purpose of verifying the EA predictions. It
is not designed or implemented to study environments or overall changes to
them. The Applicant would also have been aware of this from an early stage in
the EA process, as the summary of the EIS states that monitoring and follow up
programs are designed to verify environmental effects predictions made during
the EA as well as the effectiveness of the implemented mitigation measures.
[268] The Applicant, in challenging the Phase 5 consultation that led to
the issuance of the Authorization, takes the position that Canada’s Response
eliminated the need to understand the downstream environment on a holistic
basis and to conduct a comprehensive baseline study to provide foundational
knowledge for the prediction of downstream impacts upon which the EEM Plan
could then be based. In this regard, the Applicant is not challenging the
adequacy of the Phase 5 consultation, but is attacking Canada’s Response.
[269] For the reasons above, it is my view that the Applicant was
adequately consulted and that Canada’s duty to consult as per the Agreement was
satisfied. That said, the Minister’s response to the Applicant’s July 2, 2013
letter was not timely, as it did not come until August 27, 2013, long after the
issuance of the Authorization. However, the issues that the Minister addressed
therein had previously been raised by the Applicant and addressed by DFO, with
the exception of the new suggestion that full clearing of the reservoir should
include all trees and the top layer of organic matter, which issue is addressed
below with respect to accommodation.
[270] Adequate consultation having taken place, the remaining question is
whether, taking into account all of the relevant interests and circumstances, a
duty to accommodate arose, and if so, whether it was satisfied.
[271] The nub of this matter is that the Applicant does not agree that the
assessment of downstream effects required of Nalcor was adequate, that the
conditions of the Authorization, specifically the EEM Plan, do not remedy this
and, therefore, that its concerns in this regard were not accommodated. On one
level this is a technical, scientific issue comparing the baseline data
collection, modelling, assessment, research and monitoring that Canada deems
necessary to that which the Applicant deems necessary. It is not the role of
this Court to make such a determination (Ekuanitshit FC at para 94,
appeal dismissed by FCA, leave to appeal to SCC refused).
[272] However, the questions that are before this Court are whether any
duty to accommodate arose, whether any such duty was it met in these
circumstances, and, whether Canada, as represented by the Minister, had a
reasonable basis upon which to decide to issue the Authorization in the form
that he did.
[273] In Little Salmon, where the definition of consult was similar
to that found in the Agreement, Justice Binnie stated:
[14] The delegated statutory decision
maker was the appellant David Beckman, the Director of the Agriculture Branch
of the territorial Department of Energy, Mines and Resources. He was
authorized, subject to the treaty provisions, to issue land grants to non-settlement
lands under the Lands Act, R.S.Y. 2002, c. 132, and the Territorial
Lands (Yukon) Act, S.Y. 2003, c. 17. The First Nation argues that in
exercising his discretion to approve the grant the Director was required to
have regard to First Nation’s concerns and to engage in consultation. This is
true. The First Nation goes too far, however, in seeking to impose on the
territorial government not only the procedural protection of consultation but
also a substantive right of accommodation. The First Nation protests that its
concerns were not taken seriously — if they had been, it contends, the Paulsen
application would have been denied. This overstates the scope of the duty to
consult in this case. The First Nation does not have a veto over the approval
process. No such substantive right is found in the treaty or in the general
law, constitutional or otherwise. The Paulsen application had been pending
almost three years before it was eventually approved. It was a relatively
minor parcel of 65 hectares whose agricultural use, according to the advice
received by the Director (and which he was entitled to accept), would not have
any significant adverse effect on First Nation’s interests.
[274] And, in respect of the duty to accommodate:
[81] The First Nation’s argument is
that in this case the legal requirement was not only procedural consultation
but substantive accommodation. Haida Nation and Mikisew Cree
affirm that the duty to consult may require, in an appropriate case,
accommodation. The test is not, as sometimes seemed to be suggested in
argument, a duty to accommodate to the point of undue hardship for the
non-Aboriginal population. Adequate consultation having occurred, the task of
the Court is to review the exercise of the Director’s discretion taking into
account all of the relevant interests and circumstances, including the First
Nation entitlement and the nature and seriousness of the impact on that
entitlement of the proposed measure which the First Nation opposes. [Emphasis
in original]
[275] In this case, as in Little Salmon, the Agreement is silent as
to accommodation. Here the circumstances differ somewhat from those which
prevailed in Little Salmon as the potential consequences are more
serious and the Agreement itself contemplates the JRP process and further
consultation with respect to permitting. And, in my view, although there is no
requirement for substantive accommodation, the common law principles discussed
can be utilized to interpret what, if any accommodation is required in these
circumstances.
[276] In this regard, it is my view that Canada was obliged to consider,
take into account and respond to the issue, accommodating the Applicant, where
and to the extent possible, by taking appropriate steps to avoid or mitigate
significant adverse effects or irreparable harm. To an extent, accommodation
and reasonableness are related. The consultation process must serve to
properly inform the Minister’s decision i.e., his decision must be reasonable.
This would include accommodation to the extent possible, which is also a
question of what is reasonable in the circumstances based on properly informed
considerations and competing interests.
[277] It is also of note that the parties do not suggest that there was no
duty to accommodate in this case.
[278] The Applicant in its Phase 4 and 5 submissions identified four
recommendations that it stated would help to mitigate impacts on Inuit and
Inuit rights: i) its representation on a high-level management structure; ii)
funding for it to conduct and lead baseline research and monitoring of the Lake
Melville system, including a large scale, comprehensive understanding of the
downstream environments (biophysical, cultural, socioeconomic and health
impacts); iii) framework language as a condition of permitting to effect a mechanism
for compensation should impacts arise, including harvesting losses and loss of
cultural practices resulting from events with significant environmental effects
on Inuit or Inuit rights that result from the Project, such as an increase in
mercury levels; and, iv) full clearing of the reservoir area including trees
and the top layer of organic matter.
[279] As these are the mitigation or accommodation measures proposed by
the Applicant itself, I will address them each below.
vi. High
Level Management Structure
[280] As to the Applicant’s request for Inuit representation on a high
level management structure for the Project, which would be comprised of the
Applicant, the Innu Nation, the Province and Canada, this was first raised by
the Applicant in Phase 4 by way of its November 11, 2011 document, Nunatsiavut
Government Response to Panel Report, as a way to mitigate impacts on Inuit
and Inuit rights and to allow Inuit to constructively contribute to the
Project. As indicated above, this was very belatedly responded to by DFO’s
letter of June 28, 2013. There DFO advised that a high level management
structure was not contemplated for the Project but that the Applicant would be
consulted by DFO and TC in the context of their regulatory functions and that
DFO had consulted with the Applicant on the EEM and FHC Plans it was requiring
as conditions of the Fisheries Act authorizations.
[281] There is, in my view, a requirement of responsiveness on the part of
Canada as part of its duty to consult and accommodate (Taku River at paras
25, 32). Canada’s response to the Applicant’s request for participation on a
high level management structure was certainly not timely, coming some 19 months
after the Applicant raised the issue in response to the JRP Report. However,
it ultimately did respond and provided an explanation as to why the proposal
was not adopted. Further, the Applicant has not challenged Canada’s position
nor indicated why not implementing a high level management structure was not
reasonable in these circumstances. Thus, while the consultation process was
not perfect, I see no basis for a finding that the Applicant was not adequately
accommodated in this regard (Ekuanitshit FC at para 31).
vii. Comprehensive
Downstream Assessment
[282] Upon review of the record, it is apparent that there is a
fundamental difference of opinion between the Applicant and Canada as to what
is scientifically necessary to address, and therefore to accommodate, the
Applicant’s concerns regarding potential downstream effects, including
methylmercury bioaccumulation.
[283] In this regard, it is essential to recall that the JRP dealt
extensively with methylmercury bioaccumulation in its report.
[284] In Chapter 6, Aquatic Environment, the JRP addressed a number of
issues including methylmercury in the reservoirs and downstream. As to the
fate of mercury in the reservoirs, the JRP set out the views of Nalcor and the
participants. Nalcor included a description of how reservoir formation leads
to the release of methylmercury into the aquatic environment. Specifically,
that when soils in reservoir areas are flooded, bacterial breakdown of the
vegetation causes methylation, a chemical process that converts inorganic
mercury in the soils to methylmercury, a more toxic form. Methylmercury then
enters the aquatic ecosystem accumulating in aquatic animals mostly when they
feed on organisms with elevated mercury. The concentration of methylmercury
increases upward through the food chain (referred to as bioaccumulation)
resulting in higher concentrations in predatory fish, in animals such as otters
or seals that eat fish, and potentially in humans. Typically, as shown in
experience from other reservoirs in boreal regions, mercury levels in fish peak
5 to 16 years after flooding and then gradually decrease to background levels
over 30 or more years. Nalcor’s modelling predicted that mercury
concentrations in the reservoir would peak within 5 years after flooding,
declining to baseline levels within 35 years.
[285] The JRP noted that Nalcor's proposed mitigation and monitoring related
to methylmercury included monitoring fish mercury concentrations annually for
the first 10 years following inundation to verify predictions. Monitoring
frequency could then be adjusted, depending on results.
[286] As to the participants, the JRP noted that both EC and NRC concluded
that Nalcor had modelled mercury increases in the lower Churchill River
appropriately. DFO also stated that Nalcor’s predictions about mercury levels
were consistent with the current state of knowledge but questioned the accuracy
of Nalcor’s predictions regarding the magnitude and duration of methylmercury
in the lower Churchill River. DFO therefore recommended that Nalcor develop a
comprehensive program to monitor spatial and temporal changes in mercury in
fish within the reservoirs and downstream including at Goose Bay following
reservoir creation. The frequency and timing of sampling should be sufficient
to support a clear assessment of the magnitude and timing of these changes and
to inform determinations of risks to human health and implementation of related
fisheries management measures. Further, that more baseline data should be
collected on mercury levels in estuarine fish downstream of Muskrat Falls and
in Goose Bay in advance of inundation.
[287] Section 6.7 addressed downstream effects including flow dynamics,
water quality, productivity and mercury. The JRP again set out Nalcor’s
position as well as those of the participants.
[288] Nalcor predicted that mercury levels would increase after
impoundment in water and plankton downstream to the mouth of the river and into
the Goose Bay narrows. Methylmercury levels would increase in fish downstream
to and including Goose Bay, but levels would be lower compared to fish in the
reservoirs with the exception of piscivorous fish feeding below the tailrace of
Muskrat Falls. Mercury would not be detectable beyond Goose Bay because
concentrations in the water would be gradually diluted, sediments would settle,
and plankton and zooplankton would die-off before or at the saltwater interface.
Effects of elevated mercury levels associated with piscivores feeding on
entrained fish would only be seen fairly close to the tailrace area below
Muskrat Falls. In any case, Nalcor predicted that at no time would fish
methylmercury reach a level to affect fish health or behaviour at a population
level. Peak methylmercury levels were expected to return to baseline levels
within 35 years.
[289] Nalcor stated that a more extensive assessment of cumulative effects
of mercury levels associated with the Churchill Falls hydroelectric project was
not necessary. Nalcor acknowledged some uncertainties associated with its
modelling and the state of knowledge about bioaccumulation and the fate of
mercury in the ecosystem that limited its ability to make accurate predictions
of potential increases in methylmercury in Lake Melville. However, Nalcor said
its methylmercury modelling in the downstream environment was sufficient for
planning and assessment purposes. Further, that its modelling approach
provided the necessary level of predictive capacity required to determine
downstream methylmercury concentrations. This would be backed up by Nalcor’s
commitment to monitoring and follow up to verify predictions, address
uncertainty and incorporate adaptive management. Nalcor’s proposed mitigation
measures included working with Aboriginal stakeholders to monitor mercury in
fish and seals downstream of Muskrat Falls and collecting more baseline data on
mercury levels in estuarine fish and seals downstream of Muskrat Falls and in
Goose Bay.
[290] As to other participants, the JRP noted that they had raised
concerns about the exclusion of Goose Bay and Lake Melville from the assessment
area, changes to erosion and deposition downstream, mercury accumulation,
including entrainment effects, in fish and seals, and changes to ice formation.
DFO said that Nalcor had provided insufficient rationale for its decision to
exclude Goose Bay and Lake Melville from the assessment area. The Applicant
submitted that before any definitive conclusions could be reached on any trends
in downstream methylmercury levels or their measurable effects, Nalcor should
collect more data on suspended solids and fish and seal movements and conduct a
better analysis of mercury.
[291] The JRP noted that DFO had released a research paper showing that
mercury effects from the Churchill Falls project could be seen in several
estuarine species (rainbow smelt, tomcod, sea trout) in the waters of Lake
Melville over 300 kilometres away from the Smallwood Reservoir. DFO expressed
concern about the absence of downstream sampling of primary producers and
macrobenthos because of their potential to bioaccumulate mercury. DFO
therefore recommended that Nalcor develop a comprehensive program to monitor
spatial and temporal changes in mercury in fish within the reservoirs and
downstream including at Goose Bay following reservoir creation. The frequency
and timing of sampling should support a clear assessment of the magnitude and
timing of these changes, and inform determinations of risks to human health and
implementation of related fisheries management measures. More baseline data
should be collected on mercury levels in estuarine fish downstream of Muskrat
Falls and in Goose Bay in advance of inundation.
[292] In its conclusions and recommendations the JRP acknowledged that
there was limited literature on downstream, estuarine effects on hydro projects
in a boreal region, and limited applicability of reports that were cited by
participants, which lack of information it said was likely compounded by Nalcor’s
decision to place the study boundary at the mouth of the river and, therefore,
not carry out baseline sampling in Lake Melville. As a result, the JRP stated
that it could not confidently conclude what the ecological effects would be downstream
of Muskrat Falls, particularly in the estuarine environment of Goose Bay and
Lake Melville:
The Panel concludes that Nalcor's assertion
that there would be no measurable effect on levels of mercury in Goose Bay and
Lake Melville has not been substantiated. Evidence of a long distance effect
from the Churchill Falls project in estuarine species clearly indicate that
mercury effects can cross from freshwater to saline environments, in spite of
Nalcor's assertions to the contrary. The Panel also concludes that Nalcor did
not carry out a full assessment of the fate of mercury in the downstream
environment, including the potential pathways that could lead to mercury
bioaccumulation in seals and the potential for cumulative effects of the
Project together with other sources of mercury in the environment. Because
Nalcor did not acknowledge the risk that seals could be exposed to mercury from
the Project, it did not address whether elevated mercury would represent any
threat to seal health or reproduction.
The significance of the potential for
downstream mercury effects on Aboriginal and non-Aboriginal land and resource
use, and on human health and communities is discussed in Chapters 8, 9, and 13.
The Panel is not convinced that all effects
beyond the mouth of the river will be "nonmeasurable" as defined by
Nalcor (within natural variability). The Panel concludes that downstream
effects would likely be observed in Goose Bay over the long term caused by
changes in sediment and nutrient supply and in water temperature. Effects in
Lake Melville are more difficult to predict on the basis of existing
information. The Panel acknowledges that there is difficulty in accurately
predicting the scale of effects given the absence of long-term ecological
studies of the effects of hydroelectric projects in northern environments on
receiving waters. However, the Panel believes that this emphasizes the need for
a precautionary approach, particularly because no feasible adaptive management
measures have been identified to reverse either long-term adverse ecological
changes or mercury contamination of renewable resources.
With the information before it, the Panel is
unable to make a significance determination with respect to the risk of
long-term alteration of ecological characteristics in the estuarine
environment. The Panel concludes that there is a risk that mercury could
bioaccumulate in fish and seals in Goose Bay and possibly in Lake Melville
populations as well but would probably not represent a risk to the health of these
species. The implications on health and land use are addressed elsewhere, but
the following recommendation addresses the need to take a precautionary
approach to reduce the uncertainty regarding both the potential ecological and
mercury effects downstream.
RECOMMENDATION 6.7 Assessment of
downstream effects
The Panel recommends that, if the Project is
approved and before Nalcor is permitted to begin impoundment, Fisheries and
Oceans Canada require Nalcor to carry out a comprehensive assessment of downstream
effects including:
• identifying all possible pathways for mercury throughout
the food web, and incorporating lessons learned from the Churchill Falls
project;
• baseline mercury data collection in water, sediments and
biota, (revised modelling taking into account additional pathways, and
particularly mercury accumulation in the benthos) to predict the fate of
mercury in the downstream environment;
• quantification of the likely changes to the estuarine
environment associated with reduction of sediment and nutrient inputs and
temperature changes; and
• identification of any additional mitigation or adaptive
management measures.
The results of this assessment should be
reviewed by Fisheries and Oceans Canada and by an independent third-party
expert or experts, and the revised predictions and review comments discussed at
a forum to include participation by Aboriginal groups and stakeholders, in
order to provide advice to Fisheries and Oceans Canada on next steps.
(JRP Report, pp 88-89)
[293] It is important to consider the context of this Recommendation. The
JRP, based on the information before it, was not able to make a significance
determination with respect to the risk of long term alteration of ecological
characteristics in the estuarine environment. However, it concluded that there
was a risk of mercury bioaccumulation in fish and seals in Goose Bay and
possibly Lake Melville. It made its Recommendation in order to reduce
uncertainty regarding both the potential ecological and mercury effects
downstream.
[294] Thus, the intent of Recommendation 6.7 was to obtain a greater level
of certainty about mercury effects downstream prior to impoundment.
[295] Canada’s Response stated that it considered whether the significant
adverse environmental effects of the Project could be justified in the
circumstances, taking into account Canada’s commitments made in response to the
JRP Recommendations, as well as those of Nalcor in the EIS and at the JRP
hearings. Further, that Canada would require that certain mitigation measures,
environmental effects monitoring and adaptive management be undertaken by
Nalcor, as well as additional studies on downstream effects by way of
requirements in federal authorizations and approvals. Canada determined
that ensuring those commitments were carried out minimized the negative effects
of the Project and reduced the risks associated with the uncertainty about the
success of the mitigation measures. Further, that the anticipated significant
energy, economic, socio-economic and environmental benefits outweighed the
significant adverse environmental effects as identified in the JRP Report.
[296] Canada’s Response in relation to Recommendation 6.7 stated that:
The Government of Canada agrees with the
intent of this recommendation and notes it is directed to Fisheries and Oceans
Canada.
As a condition of a subsection 35(2)
authorization under the Fisheries Act, and prior to impoundment,
Fisheries and Oceans Canada will require Nalcor to collect additional baseline
data on bioaccumulation of methyl mercury in fish and on fish habitat
downstream of Muskrat Falls.
Fisheries and Oceans Canada will require
Nalcor to conduct a comprehensive multi-year program to monitor and report on
bioaccumulation of methyl mercury in fish (including seals) within the reservoirs
and downstream, including the Goose Bay/Lake Melville area. Fisheries and
Oceans Canada will also require that Nalcor carry out multi-year post-project
monitoring and reporting downstream into Lake Melville on a variety of
parameters including nutrients, primary production, fish habitat utilization
and sediment transport in order to asses changes to downstream fish habitat.
(Applicant’s Record, Vol II, p 749)
[297] There is no question that Canada’s Response does not fully adopt
Recommendation 6.7. While the Recommendation suggests that there be further pre-impoundment
assessment to better predict the levels of mercury in the downstream
environment, that this assessment be reviewed by DFO and an independent third
party expert(s), and, that the revised predictions be discussed at a forum,
including Aboriginal groups, to advise DFO on “next
steps”, Canada’s Response requires the pre-impoundment collection of
additional baseline data and a comprehensive multi-year program to monitor and
report on bioaccumulation of methylmercury in fish and seals within the
reservoir and downstream into Lake Melville.
[298] The Authorization addressed these requirements in Condition 6:
6. The Proponent shall undertake an
Environmental Effects Monitoring Program as outlined in the "Lower
Churchill Hydroelectric Generation Project - Aquatic Environmental Effects
Monitoring Program - Muskrat Falls" (EEM Plan), dated February 2013, to
monitor and verify the predicted impact of the proposed development from a fish
and fish habitat perspective including project related downstream effects,
methymercury bioaccumulation in fish and fish entrainment as the Muskrat Falls
facility by:
[…] 6.3 Methylmercury
bioaccumulation shall be monitored annually to determine levels in resident
fish species, including seals, both within the reservoir and downstream as per
established monitoring schedule, to record and report peak level and subsequent
decline to background levels.
6.4 Information collected from the
baseline and post-project surveys to compare and verify predictions of project
impacts to fish and fish habitat is to be reported by:
6.4.1 Providing a comprehensive
annual report summarizing all aspects associated with the EEM Program
(including baseline data collection) to DFO by March 31. This will include
on-going baseline monitoring up to and including 2016, as well as post-project
monitoring for a period of no less than twenty (20) years from 2018 through to
and including 2037.
6.4.2 Providing a comprehensive
EEM Program review report summarizing all aspects associated with the
post-Project EEM Program to DFO by March 31 of every fifth (5th) year,
commencing in 2023. This will facilitate adjustments as needed, and as
approved by DFO.
…
[299] The EEM Plan notes that transport of mercury into Goose Bay and Lake
Melville was modelled with the results showing minimal increases within Goose
Bay. The report includes a table setting out the predicted total mercury
concentrations in water, five months following impoundment. However, it also
states that bioaccumulation of mercury in river reaches downstream of
hydroelectric developments is a known phenomenon. Therefore, relying solely on
a before and after comparison of mercury concentration is not considered an
appropriate means of monitoring environmental effects. Post-project mercury
concentration would, therefore, be compared to modeled results as well as
baseline data in conjunction with literature from similar hydroelectric
developments. And while baseline data had been collected since 2001, it had been
for the purpose of developing the model used to predict post-project
concentrations.
[300] The EEM Plan study area for mercury sampling includes the Muskrat
Falls reservoir and downstream out to Goose Bay/Lake Melville area. Sampling
is to occur on an annual basis until the visible peak and decline in
concentration is observed. Further analysis will be conducted at that point,
and additional monitoring will occur “with an efficient
schedule”.
[301] The EEM Plan states that baseline total mercury concentrations in
fish had been collected over a 13 year period (since 1999) and that actual
concentration at the time of inundation may be different. Therefore,
additional fish samples would be collected and analysed for mercury body burden
during pre-inundation in order to continue collection of mercury concentrations
and to collect as much data as possible from each fish captured. A graph shows
the mean mercury concentrations that have been measured in the mainstem below
Muskrat Falls for nine types of fish to date, while another shows mean mercury
concentrations measured in Goose Bay and Lake Melville for 11 types of fish. Similar
information concerning seals is provided.
[302] As noted above, Canada’s Response does not fully adopt
Recommendation 6.7. The Applicant puts forward no authority that suggests that
Canada is bound to accept recommendations made by the JRP as part of the EA
process. However, as the purpose of the EA process and the JRP Report is to
identify environmental impacts and to inform Canada’s Response, the JRP’s
Recommendations cannot, in my view, simply be ignored or rejected without
reasons. To do so would be to entirely undermine the EA process and its use by
Canada to fulfill its consultation obligations.
[303] Here, however, Recommendation 6.7 was not ignored or rejected in
whole. Rather, the intent of the Recommendation was accepted to the extent
that the uncertainty identified by the JRP was acknowledged and addressed,
although not in the manner recommended by the JRP. Canada’s Response explained
that ensuring commitments made by Nalcor and the provincial government were
carried out would minimize the negative effects of the Project and reduce
the risks associated with the uncertainty about the success of the mitigation
measures. Further, that the anticipated significant energy, economic,
socio-economic and environmental benefits outweighed the significant adverse
environmental effects as identified in the JRP Report. One of these adverse
effects was, of course, the impacts on the Applicant if consumption advisories
are required.
[304] In short, Canada’s Response acknowledged the concerns and balanced
the competing interests, explaining why it arrived at its conclusion (Haida
at para 45; Taku River at para 2). While Canada’s Response could,
undoubtedly, have provided a more in-depth explanation as to why it accepted
the intent of Recommendation 6.7, but not its adoption in whole, its rationale
is apparent from the record. In the context of this judicial review of the
issuance of the Authorization, this is relevant as it pertains to the
underlying consultation and rationale supporting Canada’s Response and the Course
of Action Decision which, in turn, led to the issuance of the Authorization and
its conditions.
[305] And, while the further assessment recommended by the JRP may have
permitted a higher level of predictive certainty as to mercury levels, it is
also apparent from DFO’s submissions to the JRP, which were essentially adopted
by Canada’s Response, that DFO was satisfied that the modelling and data gathered
by Nalcor served to provide a sufficient predictive basis against which future
monitoring could be compared when combined with the further baseline sampling
and monitoring required by the EEM Plan. That is, Canada was satisfied that
the uncertainty and risk pertaining to methylmercury bioaccumulation could be
managed by way of the monitoring programs.
[306] The consultation process demonstrates that Canada was fully informed
of the Applicant’s view as to the extent of the downstream assessment that was
required. However, it is apparent that it did not agree with this view. The
May 30, 2013 letter from DFO, which responded to the Applicant’s comments on
the EEM Plan, addressed this issue in the context of Phase 5. DFO explained
that with respect to Recommendation 6.7, per Canada’s Response, Nalcor would be
required to collect additional baseline data, which was collected in 2011 and
2012 and would continue to be collected prior to impoundment.
[307] Importantly, it also explained that the EEM Plan was to verify specific
predictions made by a proponent during an EA, especially where there may be
uncertainty about the severity or extent of a possible impact. And
significantly, that Nalcor’s EEM Plan addressed those predictions for which DFO
considered monitoring to be required for verification, including in relation to
methylmercury bioaccumulation.
[308] In written examination, Finn was asked if proper prediction of
downstream impacts required an understanding of how the specific downstream
ecological system in question works. And, if not, why not. He responded that
scientifically defensible predictions about downstream impacts on fish and fish
habitat can be made using a combination of baseline sampling and studies in the
area to be affected, scientific literature, modelling, and comparison with
other projects, local knowledge, and other information. He added that as of
the date of his response, baseline information downstream into Lake Melville
had been compiled for three years, and would continue to be compiled for the
next three years until impoundment of the Muskrat Falls reservoir. He stated
that Lake Melville is understood sufficiently for the purpose of assessing
predictions about potential impacts by the project on the downstream aquatic
environment.
[309] In essence, Recommendation 6.7 sought further assessment prior to
impoundment to obtain a greater predictive level of certainty about mercury
effects downstream. Canada’s Response, in effect, accepted that this
uncertainty presented a risk. However, balanced against the Project benefits,
the significant adverse environmental effects were outweighed and could be
managed by way of the Authorization conditions. The Applicant disagrees with
this conclusion, however, its objections are not concerned with any perceived flaws
in the EEM Plan. It does not suggest, for example, that annual sampling is
insufficient, that the number of fish species tested is not representative or
that there are specific steps that could be taken that would improve the
baseline sampling or monitoring efforts described. Rather, it again raises its
disagreement, in principle, with Canada’s Response.
[310] Again, while Canada undoubtedly could have done a far better job
explaining why a more in depth assessment was not required and why the EEM Plan
sufficed, its explanation was sufficient to provide an understanding of its
rationale (Haida at para 44; Ka’a’Gee Tu #2 at para 131; West
Moberly at para 144).
[311] In the context of accommodation, the Authorization effected the EEM
Plan. The Applicant did not provide substantial comments on the EEM Plan and
does not identify how it was not accommodated in this regard other than as
described above. Nor does it take issue with any other aspect of the
Authorization.
[312] Canada submits that based on the comments that were received with
respect to the EEM Plan, DFO required Nalcor to add additional details on the
protocols for sampling and analysis of fish and seals for methylmercury
currently set out in baseline monitoring reports and that this was
accommodation of the Applicant’s concerns. A review of a black line version of
the EEM Plan (Bennett Affidavit sworn November 25, 2013, Nalcor’s Record, Vol
10, Tab 2) indicates that these changes really were little more than “additional details”. The changes to s 2.5, Mercury
Bioaccumulation, provide clarification of descriptions and made only a couple
of substantive changes, being that additional fish samples will be collected
and analysed for mercury body burden during pre-inundation, and seals will be
analyzed for trophic feeding pattern.
[313] I agree with the Applicant’s view that these changes were modest.
However, in the circumstances described above, this does not amount to a
failure of the duty to accommodate.
[314] As to the Applicant’s funding request for the study that it was
carrying out by way of ArcticNet, in its letter of May 30, 2013 DFO stated that
it typically sets out monitoring and reporting requirements that a proponent
must meet but does not specify who a proponent is to engage to carry this out.
As stated above, accommodation does not require agreement, nor do I see any
basis on which to find that Canada was obliged to direct Nalcor as to who it
was to engage to carry out the required monitoring as an accommodation measure.
viii. Framework
Language for Compensation
[315]
As to the Applicant’s recommendation that
framework language be incorporated as a condition of permitting to effect a
mechanism for compensation should impacts arise, DFO advised the Applicant by
its letter of June 28, 2013 that the requested framework language would not be
included as a condition of the authorizations or approvals as it would not be
enforceable as a condition under the Fisheries Act or the NWPA.
The Applicant has not challenged that position.
ix. Full
Clearing
[316] As to the proposed mitigation measure of full clearing of the
reservoir, including the removal of all trees and the top layer of organic
matter, it should first be noted that the JRP addressed reservoir preparation
both in Chapter 4, Project Need and Alternatives, and Chapter 6, Aquatic
Environment.
[317] In Chapter 4 the JRP described Nalcor’s submissions on the
environmental, technical and economic reasoning for three alternative clearing
scenarios: no clearing, full clearing and partial clearing. It also described
the participants’ views. This included NRC’s view that the methods Nalcor had
used to model the fate of mercury in the environment after reservoir clearing
were appropriate. However, that the EIS did not indicate whether Nalcor had
considered the effectiveness of partial clearing. Nor had Nalcor assessed
removing the organic layer of soil or selective clearing of brush and other
organics to reduce methylmercury production. Based on new information from
experimental lakes, NRC recommended the removal of trees, brush and possibly
soils in the drawdown zone between high and low water levels, as research
indicated that this area would be the greatest contributor of methylmercury,
thus supporting Nalcor’s scenario of partial clearing. The Applicant submitted
that Nalcor must clear wood and brush within the reservoir boundaries to
decrease methylmercury contamination within and downstream of the Project area.
[318] The JRP noted that Nalcor’s “partial clearing” alternative involved
clearing trees only in the ice and stick-up zones around the perimeter of the
reservoirs and only in areas in these zones that are within Nalcor’s
pre-defined safety, environmental and economic operating constraints. Otherwise,
the trees are left standing. The “full clearing” alternative involved, in addition
to partial clearing, clearing wood in the flood zone in areas that meet the
same operating criteria as for “partial clearing”. In other words, “full
clearing” did not mean the removal of all trees.
[319] The JRP listed the factors it considered to be particularly relevant
in reaching its conclusions on alternate means of reservoir preparation. It
also stated that:
The Panel also notes, as further discussed
in Chapter 5, the more trees cleared, the more benefits accrue in terms of
reducing methylmercury accumulation and greenhouse gas emissions, though gains
may be small. The Panel also notes that Natural Resources Canada recommended
that Nalcor study the removal of soils in the drawdown area to reduce the
production of methylmercury in flooded terrain. This is discussed in Chapter 6.
[320] The JRP concluded that it was both technically and economically
feasible to carry out “full clearing” for the Muskrat Falls reservoir. Its
Recommendation 4.5 was that, if the Project was approved, that Nalcor be
required to apply its full clearing reservoir preparation option to that
reservoir.
[321] In Chapter 6, the JRP also addressed reservoir clearing and
described the participants’ views. Nalcor stated that mobilization of
methylmercury in the reservoirs is an unavoidable impact of hydroelectric
projects and that the “full clearing” option would only reduce mercury levels
in fish by about ten percent, which would not justify the extra expense. It
also indicated that other types of mitigation, such as intensive fishing of certain
species, were unproven and likely not feasible. Nalcor also noted that NRC’s
recommended large scale removal of vegetation and soils before inundation had
only been tried at an experimental level, would not be technically or
economically feasible, and would have considerable environmental effects.
[322] NRC pointed out that development of knowledge about the
methylmercury problem associated with reservoir creation was still at an early
stage and that mitigation to date had been largely confined to consumption
advisories (which the Panel addressed in Chapter 13). Recent research had
shown that the most effective mitigation may be removal of vegetation and the
upper soil layer in what would become the drawdown area of the new reservoir. NRC
therefore recommended that Nalcor consider large-scale removal of mercury and
carbon-rich soils within this area, the so-called “bathtub
ring”, to mitigate methylmercury production, acknowledging that this
form of mitigation had so far only been conducted at a smaller experimental
scale.
[323] The JRP concluded that:
The Panel notes that Natural Resources
Canada challenged the notion that mercury mobilization is an inevitable
consequence of hydro power development and consumption advisories are adequate
as the only response. The benefits of carrying out pre-inundation mitigation
such as more extensive clearing of vegetation or soils would need to be
evaluated in the context of effects of the predicted mercury levels on
fish-eating wildlife (Chapter 7), the use of renewable resources (Chapter 8)
and human health (Chapter 13). Similarly, the significance of the cumulative
effect of another period of methylmercury contamination on the lower Churchill
system, following the effects of the Churchill Falls project, should be evaluated
in the context of human health and the use of renewable resources.
[…]
The Panel accepts that selective soil
removal around the reservoir rim is not yet proven as mitigation but observes
that this approach appears to have merit, especially if the clearing can be
confined to the reservoir rim. The Panel also notes that the type of
preparation required for this mitigation might be complementary with the
riparian and fish habitat measures that Nalcor would already be undertaking.
The Panel concludes that consumption
advisories transfer part of the cost of generating hydroelectricity to local
populations and it is therefore important to find better approaches to reducing
methylmercury in reservoirs. Therefore the Panel believes that Natural
Resources Canada should move ahead with testing the mitigative approach of
removing soil in the drawdown zone, including determining how to avoid or
minimize environmental impacts, and ways to make beneficial use of the
materials removed.
RECOMMENDATION 6.5 Pilot study for
methylmercury mitigation through soil removal
The Panel recommends that Natural Resources
Canada, in consultation with Nalcor and, if possible, other hydroelectricity
developers in Canada, carry out a pilot study to determine (a) the technical,
economic and environmental feasibility of mitigating the production of
methylmercury in reservoirs by removing vegetation and soils in the drawdown
zone, and (b) the effectiveness of this mitigation measure. The pilot study
should take place in a location where the relevant parameters can be
effectively controlled (i.e. not in the Lower Churchill watershed) and every
effort should be made to complete the pilot before sanction decisions are made
for Gull Island. If the results of the pilot study are positive, Nalcor should
undertake to employ this mitigation measure in Gull Island to the extent
possible and monitor the results.
(JRP Report, p 74)
[324] Recommendation 6.5 did not pertain to the Muskrat Falls reservoir.
[325] Canada’s Response to Recommendation 4.5 was to note that it was
directed to Nalcor’s operations as regulated by the Province but that Canada
would work with the parties as required. The Applicant has not challenged that
jurisdictional finding in this application for judicial review. If Canada did
not have jurisdiction over clear cutting then its ability to accommodate the
Applicant in that regard would be similarly constrained. On this basis it was
reasonable for Canada not to have done so.
[326] It is also of note that, despite the fact that the Province elected
the partial clearing option in March 2012, the Applicant did not subsequently
raise the issue of reservoir clearing as a mitigation measure until July 2,
2013, seven days before the issuance of the Authorization. This was also when
the issue of soil removal was raised by the Applicant for the first time. In
its letter to the Minister, the Applicant stated that while the total
elimination of increased mercury and methylmercury concentrations downstream
may be impossible, the primary mitigation measure that could be taken was full
clearing of the reservoir area, including trees and the top layer of organic
matter, and that a first step towards accommodation of Inuit concerns would be
to require this. The Minister responded to this submission in his August 27,
2013 letter, noting that Canada’s Response agreed with the intent of the JRP
recommendations on the issue but did not commit to undertaking a pilot study on
the removal of organic matter or other recommended actions in this regard, and
restated that requirements relating to clear cutting of vegetation fall under
provincial legislation.
[327] While it would assuredly have been preferable for the Minister to
have responded to the Applicant’s submission on full clearing and the removal
of the top layer of organic matter prior to the issuance of the Authorization,
the late response is not fatal in this case given the six year consultation
process and the late stage at which the Applicant raised the issue as a
required mitigation step, as well as the Applicant’s prior support of full
clearing without stipulating that in its view this should include the removal
of all trees and the top layer of organic matter.
[328] Ultimately, in the Province’s Response to the JRP Report, also
issued on March 15, 2012, the Province supported only “partial clearing” (Nunatsiavut,
2015 NLTD at para 55).
[329] As I stated above, Canada’s decision not to accommodate the
Applicant’s request in this regard was reasonable given the jurisdictional
limitation. It would also be defensible based on the fact that soil removal as
a mitigation measure was acknowledged to be experimental and that the JRP did
not recommend either removal of all trees or the removal of soil.
[330] However, tree removal as a mitigation measure is directly related to
the issue of methylmercury bioaccumulation and related potential need for
consumption advisories downstream of Muskrat Falls and in Lake Melville. Thus,
while Canada’s Response was based on jurisdiction, Canada would have known that
the Province was intending to require partial rather than full clearing as
recommended by the JRP. Yet Canada did not account for the resultant increase
in methylmercury in its response to Recommendation 4.5 or explain how this was
elsewhere considered. Given that methylmercury levels were a major concern of
the Applicant and a central issue for the JRP, and that the JRP process
fulfilled part of Canada’s duty to consult and its report informed Canada’s
Response, the Applicant could well have expected that the issue would be
explicitly addressed, rather than simply disposed of on the basis that clear
cutting was within Provincial jurisdiction.
[331] However, as discussed above, Canada was satisfied that Nalcor’s
modelling, baseline data collection, sampling and monitoring, as enhanced by
the EEM Plan that formed a part of the Authorization, were sufficient to
address the uncertainty and risk and to identify any unpredicted increase of
methylmercury levels in fish and seals. Therefore, its decision to issue the
Authorization without accommodating the Applicant with respect to full, as
opposed to partial clearing, was informed and reasonable. This is particularly
so as the JRP had acknowledged that the gains of requiring full rather than
partial clearing may be small.
[332] As a general conclusion on the issue of accommodation, I note that
in Little Salmon, the Supreme Court of Canada stated the test of
accommodation is not a duty to accommodate to the point of undue hardship for
the non-Aboriginal population. Adequate consultation having occurred, the task
of the Court is to review the Minister’s exercise of discretion, taking into
account all of the relevant interests and circumstances (also see Haida
at paras 47-50).
[333] And as stated in Katlodeeche:
[101] Sometimes a decision must be made
even when an Aboriginal group asserts that consultation is not adequate, and to
make a decision in these circumstances is not unreasonable (Ahousaht Indian
Band v Canada (Minister of Fisheries and Oceans), 2007 FC 567 (CanLII) [Ahousaht]).
There is no duty to reach agreement, and no reason that a rapid conclusion to a
consultation process will necessarily deprive an Aboriginal group of meaningful
consultation when the preceding process itself has been lengthy and adequate (Taku
River, above).
[334] Further, the Supreme Court of Canada in Taku River stated:
[2] I conclude that the Province was
required to consult meaningfully with the TRTFN in the decision-making process
surrounding Redfern’s project approval application. The TRTFN’s role in the
environmental assessment was, however, sufficient to uphold the Province’s
honour and meet the requirements of its duty. Where consultation is meaningful,
there is no ultimate duty to reach agreement. Rather, accommodation requires
that Aboriginal concerns be balanced reasonably with the potential impact of
the particular decision on those concerns and with competing societal
concerns. Compromise is inherent to the reconciliation process. In this case,
the Province accommodated TRTFN concerns by adapting the environmental assessment
process and the requirements made of Redfern in order to gain project approval.
I find, therefore, that the Province met the requirements of its duty toward
the TRTFN.
[335] In this case, methylmercury bioaccumulation had been at the
forefront of Project issues since 2006. At the JRP stage, the EIS Guidelines
were amended to require Nalcor to determine whether the Project may be
reasonably expected to have adverse environmental effects on the LISA for the
purpose of determining the applicability of the Agreement and to require Nalcor
to provide the rationale used to delineate study areas (Exhibit 21 to Chapman
Affidavit, pp 2560 2570). That rationale was rejected by the Applicant, DFO
and the JRP with the result that Nalcor was required to consider impacts
downstream of Muskrat Falls including Goose Bay and Lake Melville.
[336] With respect to the effects downstream of Muskrat Falls, the JRP
concluded that should consumption advisories be required in Goose Bay and Lake
Melville, the Project would have significant adverse effects on the pursuit of
traditional harvesting activities by Labrador Inuit, including the harvesting
of country food. It extensively addressed consumption advisories, and their
impact, in other parts of its report, including Chapters 8, 9, 10 and 13.
[337] The JRP fully considered the downstream impacts of methylmercury,
including with respect to reservoir clearing as well as consumption advisories.
Therefore, Canada fully understood both the risk that existed and the
seriousness of that risk. It was informed that the Project’s effect on fishing
and seal hunting in Goose Bay and Lake Melville would apply to traditional
harvesting activities of Labrador Inuit if consumption advisories were
required.
[338] Canada’s Response specifically acknowledges that the JRP recommended
further analysis to reduce uncertainty about downstream environmental effects.
And, when considering whether the significant adverse environmental effects of
the Project could be justified, it accounted for the potential adverse effects
of the Project and the commitments that had already been made by the federal
government and Nalcor. That is, Canada acknowledged and weighed the adverse
impacts with the benefits and decided to proceed, requiring certain mitigation
measures, environmental effects monitoring and adaptive management to be
undertaken by Nalcor, as well as additional studies on downstream effects. It
found that these measures would reduce the risks associated with the
uncertainty about the success of mitigation measures.
[339] Thus, by way of Canada’s Response, the potential risk of consumption
advisories and related impact on the Applicant’s rights, was, in effect,
accepted when balanced against the Project benefits. By way of the
Authorization and Condition 6 of the Authorization, Canada did impose some
additional requirements on Nalcor as to sampling and monitoring for mercury
levels in fish and seals. The Applicant feels that this was inadequate
accommodation. However, this is based on its view that a holistic study of
Lake Melville is required before an adequate EEM Plan can be effected. Canada
does not share that view. While Canada could have done a far better job of
explaining, at Phase 4 and 5 of the consultation, why it was satisfied with a
monitoring program rather than requiring more predictive modelling before
flooding, I cannot find that it has failed to meet its duty to accommodate.
[340] My view in this regard is somewhat shaped by the fact that
throughout the JRP process, the only pro-active mitigation measure identified
as potentially feasible was reservoir site preparation. The pre-impoundment
assessment proposed by Recommendation 6.7 was not accompanied by the
identification by the JRP of further pro-active mitigation measures that could
be implemented if necessary. Re-active mitigation options were limited to monitoring
followed by consumption advisories if required.
[341] Because the available mitigation measures pertaining to
methylmercury bioaccumulation are limited, so too are the methods of
accommodation. The JRP did not reject the concept and use of consumption
advisories, which have previously been used in the Churchill River, albeit
acknowledging that their use would have a significant adverse effect on fish
and seal hunting in the area. The Applicant acknowledges in its May 30, 2013
letter that methylmercury levels rising may be an inevitable consequence of
inundation and that the only mitigation measure that could reduce the risk or
concentration of mercury prior to flooding was reservoir clearing and soil removal.
Even though the Applicant submits, in accordance with Recommendation 6.7, that
further pre-impoundment predictive assessment should be carried out, it has not
suggested that there are other mitigation measures that could be effected
should that assessment indicate levels of methylmercury will be higher than
those predicted by Nalcor. In the EEM Plan, DFO imposed the sampling and
monitoring measures it deemed necessary to verify Nalcor’s predictions,
recognizing the uncertainties, as to downstream methylmercury in fish and
seals. While the changes made to the EEM Plan as a result of the Phase 5
consultation did not greatly vary from what had been originally proposed, in
all the circumstances, the accommodation and decision to issue the Authorization
was reasonable.
[342] When appearing before me, Canada submitted that the Authorization
also permits DFO to take other measures should Nalcor’s monitoring and follow
up indicate that its predictions are not verified. Specifically, Condition 1.1
of the Authorization stipulates that should the authorized impacts to fish and
fish habitat be greater than previously assessed, DFO may suspend any works,
undertakings, activities or operations associated with the Project and direct
Nalcor to carry out any modifications, works or activities deemed necessary.
Further, if DFO is of the view that greater impacts may occur than were
contemplated, it may also modify or rescind the Authorization.
[343] Nalcor, of course, predicts that mercury bioaccumulation in fish and
seals will not rise to levels that require consumption advisories. If they are
wrong in this prediction and monitoring indicates that levels are rising and
that advisories will likely be required, it is not disputed that at that stage
there is little that can be done to reduce the levels. When appearing before
me, counsel for Canada suggested that if that were to occur, the Project could
be halted. I do not think, at that stage of such a significant, multi-billion
dollar construction project, there is even a remote possibility that the
Project would be scrapped or mothballed because downstream mercury levels
exceeded Nalcor’s predictions. Counsel for Canada also suggests that if that
were to occur, the Applicant could sue Nalcor for damages. That may be so.
[344] However, from my perspective, such an outcome would pertain to
accommodation. If, down the road, monitoring establishes that mercury
bioaccumulation in fish and seals is exceeding Nalcor’s predictions and that
consumption advisories will be required, then pursuant to the honour of the
Crown, further consultation and accommodation will be required. At that time, Canada
may well be required to accommodate the Applicant by providing financial
redress, or causing it to be provided, or taking such other measures as may be
appropriate.
[345] In summary, the Applicant was consulted and its concerns were
reasonably identified and considered. They also were balanced reasonably with
the potential impact of the Authorization on those concerns and with the
competing societal concerns. While the Applicant did not obtain its desired
outcome, the duty to consult was satisfied, the Applicant was adequately
accommodated, and the decision to issue the Authorization was reasonable.
[346] Accordingly, the Applicant’s motion for judicial review and the
relief sought is dismissed. However, given the nature of the subject matter
and that the question raised by the Applicant concerning mercury
bioaccumulation was an important one, there will be no order for costs against
the Applicant regardless of its lack of success.