Docket: A-196-13
Citation:
2014 FCA 189
CORAM:
|
GAUTHIER J.A.
MAINVILLE J.A.
BOIVIN J.A.
|
BETWEEN:
|
|
COUNCIL OF THE INNU OF EKUANITSHIT
|
|
Appellant
|
|
and
|
|
THE ATTORNEY GENERAL OF CANADA, in his capacity of legal member of
the Queen’s Privy Counsel for Canada
and
The Honourable Keith ASHFIELD, in his capacity of MINISTER OF
FISHERIES AND OCEANS CANADA
and
The Honourable Denis LEBEL, in his capacity of MINISTER OF
TRANSPORT CANADA
and
The Honourable Joe OLIVER, in his capacity of MINISTER OF NATURAL
RESOURCES CANADA
and
NALCOR ENERGY
|
|
Respondents
|
|
|
|
|
REASONS
FOR JUDGMENT
I. Background. 4
A. The
Project 4
B. The
decision to subject the Project to a joint environmental assessment 4
C. The
guidelines for the environmental impact assessment 6
II. The
judge’s decision. 10
III. Issues. 11
IV. Analysis. 11
A. Did
the judge err in finding that the decisions of the Governor in Council and the
responsible authorities complied with the CEAA?. 11
(1) Standard
of review.. 12
(2) Reasonableness
of the decisions of the Governor in Council and responsible authorities 15
(3) Conclusion. 28
B. Did
the judge err in finding that the Crown had not breached its duty to consult
the Innu of Ekuanitshit on aspects of the Project likely to have a prejudicial
effect on their Aboriginal rights and to seek accommodation measures?. 29
(1) Standard
of review.. 29
(2) The
Crown’s duty to consult 29
V. Conclusion. 45
BOIVIN J.A.
[1]
This is an appeal from a decision of Justice
Scott (the judge) of the Federal Court dated April 23, 2013. In his
decision, the judge dismissed the application for judicial review of the
Council of the Innu of Ekuanitshit (the appellant or Innu of Ekuanitshit)
against an order of the Governor in Council adopted on March 12, 2012, and
a decision made on March 15, 2012, by Fisheries and Oceans Canada,
Transport Canada and Natural Resources Canada. The order and the decision
authorize, following an environmental assessment process, a project for the
construction of two hydroelectric plants on the Churchill River in Newfoundland and Labrador. In dismissing the application for judicial review, the judge
also found that the federal government had met its constitutional duty to
adequately consult the appellant before adopting the order, but that consultations
should continue.
[2]
In the order of March 12, 2012, the
Governor in Council approved the federal government’s response to the Report
of the Joint Review Panel, Lower Churchill Hydroelectric Generation Project, Nalcor Energy, Newfoundland and Labrador. In its response, the federal government
essentially found that the energy, socioeconomic and environmental benefits of
the hydroelectric plant project outweighed its adverse environmental effects.
The Governor in Council also allowed, under subsection 37(1.1) of the Canadian
Environmental Assessment Act, S.C. 1992, c. 37 (Repealed, 2012, c. 19, s.
66) (the CEAA ), Fisheries and Oceans Canada, Transport Canada and
Natural Resources Canada (the responsible authorities) to follow up on the
Report of the Joint Review Panel.
[3]
In their decision of March 15, 2012, made
in conformity with the approval of the Governor in Council and under
subsection 37(1) of the CEAA, the responsible authorities followed
up with the Report and decided that they would allow the implementation of the project
if certain environmental mitigation measures were applied.
[4]
The appellant essentially argued that the judge erred in law and fact in his
interpretation of the CEAA and in his conclusion that the federal
Crown had fulfilled its duty to consult.
[5]
For the following reasons,
the appeal should be dismissed.
[6]
The sequence of events that led to this dispute
is as follows.
[7]
On November 30,
2006, Newfoundland and Labrador Hydro, now Nalcor Energy (Nalcor), submitted a
registration and description document for the “Lower
Churchill Hydroelectric Generation Project” (Project).
[8]
In its Project, Nalcor
planned the construction and operation of two hydroelectric plants in Lower Churchill River, Labrador. The Project specifically includes two
hydroelectric plants, at Gull Island and Muskrat Falls, as well as transmission
lines to the Labrador grid. The two plants will generate a total of more than
3,000 megawatts (MW). The Gull Island plant will have a capacity of
2,250 MW and will include a dam 99 m high and 1,315 m long, with
a 232 km long reservoir inundating 85 km2 of land. The
Muskrat Falls plant has a capacity of 824 MW, will include a dam 32 m
high and 432 m long and a second one 29 m high and 325 m long,
with a 59 km long reservoir, inundating an area of 41 km2.
[9]
In January 2007,
the Minister of Environment and Conservation of Newfoundland and Labrador (provincial minister) decided that the Project would be subject to the Environmental
Protection Act, SNL 2002, c. E-14.2 and an environmental impact study. He
also recommended that a public hearing on the Project be held.
[10]
One month later, Fisheries
and Oceans Canada found that, to carry out the Project, it would have to take
measures under subsection 35(2) of the Fisheries Act,
R.S.C. 1985, c. F-14. Transport Canada found that it had to take measures
under paragraph 5(1)(a) of the Navigable Waters Protection
Act, R.S.C. 1985, c. N‑22. Since the Project required that
Fisheries and Oceans Canada and Transport Canada issue permits and provide pre‑approval,
they determined that the Project had to be subject to a federal environmental
assessment. Fisheries and Oceans Canada and Transport Canada also decided that they would be the responsible authorities for the environmental
assessment. Natural Resources Canada was added to the group of responsible
authorities on August 19, 2011, after granting Nalcor a loan guarantee.
[11]
Considering that the Project
risks creating adverse environmental effects, the responsible authorities
recommended submitting the Project to a federal review panel. In June 2007, the federal Minister of the
Environment adopted this recommendation and decided to refer the assessment to
a review panel.
[12]
Following this process, the Newfoundland and Labrador government and the federal government agreed to submit the
Project to an environmental assessment process, which would be conducted by a
Joint Review Panel.
[13]
In December
2007 the provincial minister and the Canadian Environmental Assessment Agency
jointly published a draft of the guidelines for the environmental impact
assessment.
[14]
From December 19, 2007,
to February 27, 2008, the guidelines for the environmental impact
assessment were subject to a public consultation.
[15]
Following the comments
received, the provincial Minister of the Environment and his federal
counterpart published a final version of the guidelines for the environmental
impact assessment on July 15, 2008. They told Nalcor that it would have to
refer to these guidelines in completing its environmental impact study so as to
meet the statutory requirements of both governments.
[16]
On January 8, 2009, the
provincial minister and the Canadian Environmental Assessment Agency, in
accordance with section 40 of the CEAA, entered into an agreement to
establish a Joint Review Panel (“Agreement for the Establishment of a Joint Review Panel for the
Environmental Assessment of the Lower Churchill Hydroelectric Generation
Project”). This agreement describes the mandate of the Joint Review Panel, which is essentially responsible for
determining whether the completion of the Project is likely to have significant
adverse effects on the environment, considering the implementation of
mitigation measures by the proponent Nalcor. Under the agreement, the Joint
Review Panel must also invite Aboriginal groups to make submissions on their
Aboriginal rights in the region of the Project and the negative impact that the
Project may have on them. Under section 15 of the CEAA, the federal
Minister of the Environment defined the scope of the Project to be assessed as
including the Muskrat Falls and Gull Island plants.
[17]
Generally, under
section 34 of the CEAA, the Joint Review Panel must first gather
the information required for the environmental assessment of the Project under
review. Second, it must hold hearings so as to give the public the opportunity
to participate in the environmental assessment of the Project. Third, it must
prepare a report containing its conclusions and recommendations relating to the
environmental assessment of the Project and summarizing the comments received
from the public. Fourth, it must submit its report to the federal Minister of
the Environment and to the responsible authorities.
[18]
On February 17, 2009,
Nalcor submitted its environmental impact study, developed in accordance with
the guidelines established by the Newfoundland and Labrador government and the
federal government. In its environmental impact study, Nalcor identified the
adverse environmental effects of the Project, proposed measures likely to
mitigate them and assessed their significance considering these mitigation
measures.
[19]
From March 9, 2009, to
April 15, 2011, 52 stakeholders, including the Innu of Ekuanitshit, made
submissions regarding Nalcor’s environmental impact study to the Joint Review
Panel for its information gathering process. Following these submissions, the
Joint Review Panel submitted 166 information requests to Nalcor, who provided
responses to all these information requests. Members of the public were then
invited, on two occasions, to make submissions regarding Nalcor’s responses to
the information requests.
[20]
On January 14, 2011,
after compiling the stakeholders’ submissions and considering Nalcor’s
responses to the information requests, the Joint Review Panel found that the
assessment could proceed to public hearings.
[21]
From March 3, 2011, to
April 15, 2011, the Joint Review Panel held public hearings in six
municipalities of Newfoundland and Labrador and Quebec. The appellant made
submissions, filed documents and showed a video during a hearing held in
Sept-Îles, Quebec, on April 7, 2011.
[22]
On August 23, 2011, the
Joint Review Panel published its Report of the Joint Review Panel, Lower Churchill Hydroelectric
Generation Project and
presented it to the federal Minister of the Environment and the responsible
authorities. The key finding of this Report was that the Project is likely to
cause significant adverse environmental and socioeconomic effects, but that the
potentially significant economic benefits that it would generate, although
uncertain, would compensate for these risks. The Report also made more than 80
recommendations about the mitigation measures and the additional information
that would be required on some aspects so that the Project could move forward.
[23]
Following the publication of
the Report of the Joint Review Panel, the appellant contacted the Canadian
Environmental Assessment Agency and made some requests. In particular, the
appellant requested that no decision be made regarding the Project before
serious studies on the historic use of the land covered by the Project and on
the caribou herds that live on it were carried out.
[24]
On March 12, 2012, in
order C.P. 2012-285, the Governor in Council endorsed both the response of the
federal government to the Report (response) and the decision that the
responsible authorities had to make under their respective laws (decision).
Under subsections 37(1) and 37(1.1) of the CEAA, the federal
government and the responsible authorities had to read the Report and determine
whether the Project was justified despite its adverse environmental effects,
but it was ultimately up to the Governor in Council to approve this response.
[25]
The response, after
summarizing the environmental assessment process and the issues contained in
the Report, presented the federal government’s findings and the reasons for
which the significant adverse environmental effects of the Project are
justified by its benefits. It also responded to each of the Joint Review
Panel’s recommendations. It described, among other things, the federal
government’s participation in the Project.
[26]
The decision contains the
list of mitigation measures that must be implemented to carry out the Project,
concerning inter alia: birds, fish, mammals and their habitat;
Aboriginal use of land and resources for traditional purposes; socioeconomic
effects; and physical and cultural heritage. The decision also provides for the
implementation of a follow-up program that aims to monitor the accuracy of the
environmental assessment and the effectiveness of the mitigation measures to be
carried out from October 1, 2012, to October 1, 2037.
[27]
On March 16, 2012, the
responsible authorities officially filed their decision, previously endorsed by
the Governor in Council, with the Canadian Environmental Assessment Agency
(reference number 07-05-26178).
[28]
One month later, the
appellant filed an application for judicial review of the order of the Governor
in Council endorsing the federal government’s response to the Report and the
subsequent decision of the responsible authorities, approved by the order.
[29]
After establishing the facts of this matter and conducting an
analysis of the evidence, the judge dismissed the application for judicial
review for three main reasons.
[30]
First, the judge determined
that the appellant had not respected the deadline for the judicial review of
the order that set the scope of the Project under section 15 of the CEAA.
Despite this, whether or not the application for review was out of time, the
judge found that the decision to maintain the current scope of the Project as
presented by Nalcor - i.e. without the transportation line (between Labrador
and the Island of Newfoundland) - was reasonable and that no breach of the
process under the CEAA had been established.
[31]
Second, the judge found that
the decision of the federal government and the responsible authorities under
section 16 of the CEAA was reasonable. The government was aware of
the adverse environmental effects of the Project and carefully weighed them
against the benefits from a national perspective. The judge decided that the
appellant’s fear relating to the switched order of construction of the two dams
and to the approval of the Gull Island Project was unsubstantiated at this
stage.
[32]
Third, the judge determined
at paragraph 112 of his reasons that the government admitted that it had a
duty to consult the Innu of Ekuanitshit and that, rather, the issue was whether
the Crown had sufficiently consulted. He first stated that it was premature to
conduct the judicial review of the federal government’s consultation process
and accommodation at this stage, but he nonetheless proceeded to review the
issue.
After analyzing the evidence on the record and the case law regarding the
Crown’s duty to consult, the judge found that the consultation process was not
complete and that the consultation performed to date, i.e. up to the Governor
in Council issuing the order, was sufficient.
[33]
This appeal raises two issues:
1. Did the judge err in finding that the decisions of the
Governor in Council and the responsible authorities complied with the CEAA?
2.
Did the judge err in finding that the Crown had
not breached its duty to consult the Innu of Ekuanitshit on aspects of the
Project likely to have a prejudicial effect on their Aboriginal rights and to
seek accommodation measures?
[34]
The appellant submits
that the judge committed a number of errors in finding that the impugned
decisions of the Governor in Council and the responsible authorities complied
with the provisions of the CEAA. The errors involve, in particular, (i)
the authorization of the Project under section 37 of the CEAA despite
the lack of a construction date for the Gull Island plant, (ii) the uncertain
application of section 24 of the CEAA, and (iii) the interplay between
the powers of the Governor in Council and of the federal Minister of the
Environment.
[35]
In an appeal from a judicial
review judgment, the role of this Court is to determine, first, whether the
judge identified the appropriate standard of review and, second, whether he
applied it correctly (Agraira v.
Canada (Public Safety and Emergency Preparedness), 2013 SCC 36, [2013] 2 S.C.R. 559 at paras. 45-47; Canada
Revenue Agency v. Telfer, 2009 FCA 23 at para. 18).
[36]
In this case, the appellant
maintains that the judge erred by applying a standard of review that was far
too deferential toward the decisions of the Governor in Council and the
responsible authorities under section 37 of the CEAA. The appellant
further criticizes the judge for having applied the principles in Thorne’s
Hardware Ltd. v. The Queen, [1983] 1 S.C.R. 106 [Thorne’s Hardware] ,
when the Supreme Court recently rejected those principles in Catalyst Paper
Corp. v. North Cowichan (District), 2012 SCC 2, [2012] 1 S.C.R. 5 [Catalyst
Paper]. According to the appellant, the judge should have instead used the
standard of review analysis developed in Dunsmuir v. New Brunswick, 2008
SCC 9, [2008] 1 S.C.R. 190 [Dunsmuir] and found that a correctness
standard should be applied to questions relating to jurisdiction and to the
applicability of the CEAA (MiningWatch Canada v. Canada (Fisheries
and Oceans), 2007 FC 955, [2008] 3 F.C.R. 84, aff’d. by 2010 SCC
2, [2010] 1 S.C.R. 6 [MiningWatch]) as well as to questions regarding
the interpretation of the CEAA (Georgia Strait Alliance v. Canada
(Minister of Fisheries and Oceans), 2010 FC 1233, [2012] 3 F.C.R. 136 at
para. 60, conf. 2012 FCA 40, [2013] 4 F.C.R. 155 [Georgia Strait]).
[37]
I cannot accept the
appellant’s arguments with regard to the applicable standard of review in this
case.
[38]
The Supreme Court of Canada
teaches us that an exhaustive analysis is not always necessary for determining
the appropriate standard of review. A reviewing court must begin by determining
whether the case law has already established in a satisfactory manner the
degree of deference to be accorded with regard to a particular category of
question (Dunsmuir at para. 62).
[39]
In this case, the crucial
issue for the judge to decide with regard to the CEAA was whether the
Governor in Council and the responsible authorities had respected the
requirements of the Act prior to making their decisions under subsections 37(1)
and 37(1.1) of the CEAA.
[40]
The judge determined, at
paragraphs 72 to 76 of his reasons, that the decisions made under subsections
37(1) and 37(1.1) of the CEAA should be reviewed on a reasonableness
standard. In reaching his conclusion, the judge relied on Thorne’s Hardware,
but also Inverhuron & District Ratepayers’ Assn. v. Canada (Minister
of the Environment), 2001 FCA 203 at para 32, Bow Valley
Naturalists Society v. Canada (Minister of Canadian Heritage), [2001] 2 F.C. 461
at para. 78 and Pembina Institute for Appropriate Development v. Canada (Minister of Fisheries and Oceans), 2005 FC 1123 at para. 74. These decisions,
from this Court and the Federal Court, set out that a reviewing court must not
intervene in decisions of the Governor in Council or responsible authority
under section 37 of the CEAA, unless the statutory process was not
followed properly. The judge concluded his overview of the case law by citing
our Court at paragraphs 75 and 76 of his reasons as follows:
[75] In Canada
(Wheat Board) v. Canada (Attorney General),
2009 FCA 214, at para 37, Justice Noël described the limits imposed on the
Courts’ ability to review decisions made by the GIC pursuant to a
legislative power given to it by statute as follows:
It is well-settled law that when
exercising a legislative power given to it by statute, the Governor in Council must stay within the boundary of the
enabling statute, both as to empowerment and purpose. The Governor in Council
is otherwise free to exercise its statutory power without interference by the
Court, except in an egregious case or where there is proof of an absence of
good faith (Thorne’s Hardware Ltd. et al. v. The Queen et al., 1983
CanLII 20 (SCC), [1983] 1 S.C.R. 106, page 111; Attorney General of Canada
v. Inuit Tapirisat of Canada et al, 1980 CanLII 21 (SCC), [1980] 2 S.C.R.
735, p. 752).
[76] This Court agrees
with the above formulation of Justice Noël. As a result, the Court will only
intervene with the GIC and Responsible Ministers’ decisions under subsections
37(1.1) and 37(1) if it finds that: 1) the CEAA statutory process was
not properly followed before the section 37 decisions were made; 2) the GIC or
Responsible Ministers’ decisions were taken without regard for the purpose of
the CEAA; or 3) the GIC or Responsible Ministers’ decisions had no
reasonable basis in fact; which is tantamount to an absence of good faith.
[41]
I am of the view that the
judge rightfully concluded that the above-mentioned case law establishes in a
satisfactory manner that a reviewing court must show deference when reviewing
the exercise of power delegated by the Act to the Governor in Council or to a
Minister.
[42]
As this judicial review does not involve questions of jurisdiction or statutory interpretation, the
principles set out in MiningWatch at paragraph 135, and Georgia
Strait at paragraph 60, upon which the appellant relies, do not apply.
[43]
In addition, contrary to what the appellant
asserts, Catalyst Paper, does not substantially alter the applicable law
with respect to the judicial review of the exercise of a delegated authority.
Although it is correct to state that the Supreme Court of Canada abandoned the
distinction inherited from Thorne’s Hardware between policy, which is
theoretically exempt from judicial review, and legality, the Court nonetheless
reiterated the principle by which an authority “[i]n
passing delegated legislation … must make policy choices that fall reasonably
within the scope of the authority the legislature has granted it” (Catalyst
Paper at para. 14).
[44]
Therefore, in my view, the judge correctly found that deference was owed to the
decisions made pursuant to subsections 37(1) and 37(1.1) of the CEAA,
but that a reviewing court must ensure that the exercise of power delegated by
Parliament remains within the bounds established by the statutory scheme.
[45]
The appellant submits that the judge committed
three main errors in his analysis of the reasonableness of the impugned
decisions.
(a)
The absence of a construction date for the Gull Island plant
[46]
First, the appellant’s
essential argument is that the Governor in Council and responsible authorities
were not able to determine whether the Project’s negative consequences could be
justified in the circumstances, as required by subsections 37(1) and 37(1.1) of
the CEAA, since the Project as defined included the Gull Island plant,
when to this date only the construction of the Muskrat Falls plant has been
confirmed.
[47]
With regard to the
allegation of the abandonment of the construction of the Gull Island plant, the judge wrote as follows:
[91] The Applicant’s concerns regarding
the approval of Gull Island is fundamentally a
scoping argument which the Court has already concluded to be statute barred in
this instance. The Applicant submits that Gull Island should have been removed
or ¨scoped out¨ of the Project. The Supreme Court of Canada already decided
that the minimum scope of a project ¨is the project as proposed by the
proponent¨ (see MiningWatch, above, at para 39). The scope of the Project
can then be increased but not decreased. The rationale is easy to understand.
Why would a proponent propose a project larger than they intended to build?
They would only be rendering the EA process more onerous for no valid reason…
[48]
The judge concluded
that, in light of the evidence and the obligations provided for under the CEAA,
the decisions of the Governor in Council and responsible authorities were
reasonable:
[95] The evidence before the Court indicates that the federal government was properly
informed of the potential negative environmental impacts of the Project.
Furthermore it reasonably justified its decision to proceed in this instance
after having weighed the benefits against the negative environmental impacts
from its national perspective. As the Court reviewed the Response and Decision,
it is clear that both are carefully considered decisions that balance competing
objectives.
[49]
I point out that the impugned decisions were made under subsections 37(1) and 37(1.1) of
the CEAA, which provide as follows:
Decision of
responsible authority
|
Autorité responsable
|
37.(1) Subject to subsections (1.1) to (1.3), the responsible authority
shall take one of the following courses of action in respect of a project
after taking into consideration the report submitted by a mediator or a
review panel or, in the case of a project referred back to the responsible
authority pursuant to subsection 23(1), the comprehensive study report:
|
37.(1) Sous réserve des paragraphes (1.1) à (1.3),
l’autorité responsable , après avoir pris en compte le rapport du médiateur
ou de la commission ou, si le projet lui est renvoyé aux termes du paragraphe
23(1), le rapport d’étude approfondie, prend l’une des décisions
suivantes :
|
(a) where,
taking into account the implementation of any mitigation measures that the
responsible authority considers appropriate,
|
a) si, compte tenu de l’application des
mesures d’atténuation qu’elle estime indiquées, la réalisation du projet
n’est pas susceptible d’entraîner des effets environnementaux négatifs
importants ou est susceptible d’en entraîner qui sont justifiables dans les
circonstances, exercer ses attributions afin de permettre la mise en œuvre
totale ou partielle du projet :
|
(i) the
project is not likely to cause significant adverse environmental effects, or
|
|
(ii) the project is
likely to cause significant adverse environmental effects that can be
justified in the circumstances,
|
|
The
responsible authority may exercise any power or perform any duty or function
that would permit the project to be carried out in whole or in part; or
|
|
(b) where,
taking into account the implementation of any mitigation measures that the
responsible authority considers appropriate, the project is likely to cause
significant adverse environmental effects that cannot be justified in the
circumstances, the responsible authority shall not exercise any power or
perform any duty or function conferred on it by or under any Act of
Parliament that would permit the project to be carried out in whole or in
part.
|
b) si, compte tenu de l’application des
mesures d’atténuation qu’elle estime indiquées, la réalisation du projet est
susceptible d’entraîner des effets environnementaux qui ne sont pas
justifiables dans les circonstances, ne pas exercer les attributions qui lui
sont conférées sous le régime d’une loi fédérale et qui pourraient permettre
la mise en œuvre du projet en tout ou en partie.
|
Approval of
Governor in Council
|
Agrément du
Gouverneur en Conseil
|
(1.1) Where a report is submitted by a mediator or review panel,
|
(1.1) Une fois pris en compte le rapport du
médiateur ou de la commission, l’autorité responsable est tenue d’y donner
suite avec l’agrément du Gouverneur en Conseil, qui peut demander des
précisions sur l’une ou l’autre de ses conclusions; l’autorité responsable prend
alors la décision visée au titre du paragraphe (1) conformément à l’agrément.
|
(a) the
responsible authority shall take into consideration the report and, with the
approval of the Governor in Council, respond to the report;
|
|
(b) the
Governor in Council may, for the purpose of giving the approval referred to
in paragraph (a), require the mediator or review panel to clarify any
of the recommendations set out in the report; and
|
|
(c) the responsible authority shall take a course of action
under subsection (1) that is in conformity with the approval of the Governor
in Council referred to in paragraph (a).
|
|
[50]
Under section 15 of the CEAA, it was up to the
Minister of the Environment to determine the scope of the Project that was to
be subject to the environmental assessment process and Joint Review Panel
Report, upon which the Governor in Council and responsible authorities were to
ultimately base their decisions:
Scope of project
|
Détermination de la portée du projet
|
15.(1) The scope of the project in relation to which an environmental
assessment is to be conducted shall be determined by
|
15.(1) L’autorité responsable ou, dans le cas où le
projet est renvoyé à la médiation ou à l’examen par une commission, le
ministre, après consultation de l’autorité responsable, détermine la portée
du projet à l’égard duquel l’évaluation environnementale doit être effectuée.
|
(a) the
responsible authority; or
|
|
(b) where the project is referred to a mediator or a review
panel, the Minister, after consulting with the responsible authority.
|
|
[51]
In the order, the Governor in Council thus
describes as follows the Project whose scope was determined, on January 8,
2009, by the federal Minister of the Environment (A.B., Vol. 1 at. 201):
[translation]
The Nalcor Energy
company proposes to build two hydroelectric generation facilities on the lower
Churchill River in central Labrador, the combined capacity of which will be
3,074 megawatts (MW). The Project consists of two dams located at Muskrat
Falls and Gull Island, two reservoirs and transmission lines between Muskrat Falls and Gull Island and between Gull Island and the existing Churchill Falls
facility. Other facilities would include access roads, temporary bridges and
construction camps; borrow pits and quarry sites, diversion facilities and
spoil areas.
[Emphasis added.]
[52]
In this instance the
responsible authorities had to decide, with the agreement of the Governor in
Council, whether to exercise their powers under their respective statutes,
thereby allowing the Project as defined by the federal Minister of the
Environment to proceed. To do so, the responsible authorities and the Governor
in Council had to determine whether the adverse environmental effects described
in the Joint Review Panel Report were justifiable given the positive effects of
the Project and the application of appropriate mitigation measures.
[53]
In the order, the Governor
in Council determined, after consulting the Joint Review Panel Report as well
as several government studies, that [translation] “the significant energy, economic, socio-economic and environmental
benefits outweigh the negative environmental impacts of the Project identified
in the Panel’s Report” (A.B.,
Vol. 1 at 206).
[54]
I share the appellant’s view
that the abandonment of the Gull Island plant, if this were proven to be true,
would raise serious questions about the validity of the environmental
assessment and the impugned decisions. The Project authorized by the Governor
in Council and responsible authorities following the balancing exercise imposed
by section 37 of the CEAA included the Muskrat Falls plant as well as
the Gull Island plant. I would note that this authorization was not a blank
cheque for Nalcor to postpone the construction of the Gull Island plant indefinitely. If Nalcor were to forego construction of the larger of the
two plants assessed (Gull Island), or if there was an unreasonable delay in its
construction, the balancing exercise carried out for one of the Report’s
findings would be necessarily compromised.
[55]
I note, however, that the
appellant adduced no evidence that the Gull Island plant had truly been
abandoned by the proponent. For its part, Nalcor contends that construction of
the Gull Island plant has not been abandoned and that it still has every
intention of building the plant. Nalcor explains its difficulty in providing a
construction start date by invoking its obligation to satisfy internal control
mechanisms that require, in particular, confirmation of access to commercial
markets likely to ensure the profitability of the Gull Island plant.
[56]
The sequence of construction
of the two plants was certainly modified in November 2010. Following this
modification, it was decided that the Muskrat Falls plant would be built first,
when it was initially supposed to be built after the Gull Island plant.
However, the reversal of the sequence of construction of the plants does not
suggest that Gull Island will never be built.
[57]
At best, it appears that,
unlike the Muskrat Falls plant, there is no scheduled construction date
currently planned for the Gull Island plant. The appellant has provided no
statutory or judicial authority requiring that a proponent provide a specific
construction date in advance for each component of a project of this magnitude.
Indeed, if it is true that there is no basis for concluding that the Gull Island plant will actually be built, it is equally true that there is no evidence to
the contrary either.
[58]
In the absence of evidence
of the abandonment of the construction of the Gull Island plant or of an
unreasonable delay in its construction, the appellant has not established that
it was unreasonable for the Governor in Council and responsible authorities to
conclude that, in light of the positive effects and proposed mitigation
measures, the adverse environmental effects of the Project including the two
plants were justified.
[59]
Therefore, I share the
judge’s conclusion and find that this ground of appeal must fail.
(b)
Section 24 of the CEAA
[60]
Second, the appellant
submits that the judge erred by stating that section 24 of the CEAA
would apply if the Gull Island facility was not built within a reasonable
timeframe. At first instance, the appellant argued that approving the Project
when there is no planned construction date for the Gull Island facility would
be tantamount to granting indefinite approval for the Project, which was
prejudicial to the appellant given the negative environmental impacts that
would result.
[61]
In upholding Nalcor’s
argument, the judge concluded that section 24 of the CEAA prevents the
indefinite approval of the Project decried by the appellant:
[91] …Furthermore, section 24 of the CEAA
will prevent the indefinite approval of any component of a project which is not
built within a reasonable timeframe.
[62]
Section 24 of the CEAA
provides, among other things, that when a proponent proposes to carry out a
project for which an environmental assessment has previously been conducted,
the responsible authority must use the assessment and corresponding report,
while making any adjustments made necessary by changes in circumstances:
Use of
previously conducted environmental assessment
|
Utilisation
d’une évaluation antérieure
|
24.(1) Where a proponent proposes to carry out, in whole or in part, a
project for which an environmental assessment was previously conducted and
|
24.(1) Si un promoteur se propose de mettre en
œuvre, en tout ou en partie, un projet ayant déjà fait l’objet d’une évaluation
environnementale, l’autorité responsable doit utiliser l’évaluation et le
rapport correspondant dans la mesure appropriée pour l’application des
articles 18 ou 21 dans chacun des cas suivants :
|
(a) the
project did not proceed after the assessment was completed,
|
a) le projet n’a pas été mis en œuvre après
l’achèvement de l’évaluation;
|
…
|
[…]
|
The
responsible authority shall use that assessment and the report thereon to
whatever extent is appropriate for the purpose of complying with section 18
or 21.
|
|
Necessary
adjustments
|
Ajustements
nécessaires
|
(2) Where a
responsible authority uses an environmental assessment and the report thereon
pursuant to subsection (1), the responsible authority shall ensure that any
adjustments are made to the report that are necessary to take into account
any significant changes in the environment and in the circumstances of the
project and any significant new information relating to the environmental
effects of the project.
|
(2) Dans les cas
visés au paragraphe (1), l’autorité responsable veille à ce que soient
apportées au rapport les adaptations nécessaires à la prise en compte des
changements importants de circonstances survenus depuis l’évaluation et de
tous renseignements importants relatifs aux effets environnementaux du
projet.
|
[63]
The respondents
acknowledge that the
conditions for applying section 24 of the CEAA are uncertain. Nalcor
further concedes that the judge’s words create confusion and that it is
inaccurate to assert that section 24 of the CEAA “will prevent” the
indefinite approval of a project or one of its components. According to Nalcor,
this provision nonetheless implies that Parliament contemplated situations in
which a project, after undergoing an environmental assessment, was not carried
out and for which the initial assessment must be adjusted in order to take into
account changes in circumstances that occurred in the intervening period.
[64]
Section 24 of the CEAA
has until now received only summary treatment in the case law. The section does
appear to apply to situations in which a proponent submits for approval by the
government a project that has already been assessed but never carried out. By
requiring the responsible authority to use, with the necessary adjustments, the
previous environmental assessment, section 24 of the CEAA appears geared
toward achieving greater administrative efficiency by avoiding unnecessary
duplication and minimizing the risks of the impacts resulting from the approval
of projects not built within a reasonable timeframe.
[65]
The relevance of such a
provision in the context of this judicial review is unclear. Not only has the
Project barely begun to move forward in this case, but it is difficult to
fathom how the mechanism set out in section 24 of the CEAA, which deals
with situations likely to occur long after a project has been approved, could
be employed in a judicial review of a decision to approve made pursuant to
section 37 of the CEAA.
[66]
Even if the judge did not
have to decide in the circumstances of this case on the application of section
24 of the CEAA, his findings are of no consequence. Indeed, any
discussion surrounding the abandonment of the construction of the Gull Island facility, when less than three years have passed since the Project was
approved, is at this point entirely hypothetical and speculative and cannot
compromise the reasonableness of the impugned decisions.
(c)
Limits on the Governor in Council’s power under
the CEAA
[67]
Third, the appellant maintains that the judge erred by concluding that the
Governor in Council’s power is limited by the decision on the scope of the
Project made by his Environment Minister, who is subordinate to the Governor in
Council. The appellant claims that in making this finding, the judge violated
the principle according to which the powers of the Governor in Council, who
represents the democratically elected government, [translation] “must be presumed to trump those of a mere Environment
Minister” (memorandum of the appellant at para. 122).
[68]
Dealing with the power of
the Governor in Council or of the responsible
authorities to modify the scope of the Project so as to take into account the
fact that no construction date had been submitted by the proponent, the judge
concluded as follows:
[91] … The Supreme
Court of Canada already decided that the minimum scope of a project “is the
project as proposed by the proponent” (see MiningWatch,
above, at para 39). The scope of the Project can then be increased but not
decreased …
[69]
The discretionary
power of the Governor in Council and responsible authorities to authorize a project
in spite of its adverse environmental effects is circumscribed by the CEAA.
Section 15 of the CEAA clearly sets out that the decision that the
Governor in Council and the responsible authorities must make under section 37
of the CEAA concerns a project whose scope has previously been
determined by the Minister of the Environment. The wording of section 15
further specifies that the Minister of the Environment must consult the
responsible authority before determining the scope of the project: “… [t]he scope of the project in relation to which an
environmental assessment is to be conducted shall be determined by […], where
the project is referred to a mediator or a review panel, the minister, after
consulting with the responsible authority”.
[70]
As the judge noted, the Supreme Court of Canada
concluded, in MiningWatch at paragraph 39, that “the minimum scope is the
project as proposed by the proponent, and the [responsible authority] or
Minister has the discretion to enlarge the scope when required by the facts and
circumstances of the project”. Therefore, once the proponent has proposed a project for the purposes of
assessment, the minister may enlarge the scope, but not restrict it.
[71]
The appellant
maintains that [translation] “the determination of the
scope of the project by the Minister … is subject to the discretion of the
Governor in Council to make a determination that the project has changed and to
refer the report of the JRP [Joint Review Panel] to the responsible
authorities” in order for
them to be able to amend their report based on the changes that have occurred
after the initial environmental assessment. The appellant quotes as principal
authority in support of this claim subsection 24(2) of the CEAA. As
previously noted, the subsection provides that, where a proponent proposes a
project for which an environmental assessment was previously conducted but
which has not proceeded, the responsible authority must use that assessment and
“ ensure that any adjustments are
made to the report that are necessary to take into account any significant
changes in the environment and in the circumstances of the project and any
significant new information relating to the environment effects of the project”.
[72]
As with the first two
arguments of the appellant, this claim is ultimately based on the hypothesis
that the Gull Island facility will not proceed. Even if it were for the
Governor in Council to determine that a project or part of a project has not
been carried out within the meaning of subsection 24(1) of the CEAA,
which has not been demonstrated, there is no basis for concluding that the lack
of a precise construction date, less than three years after the Order in
Council approval, means that the Gull Island facility will not proceed within a
reasonable timeframe.
[73]
Be that as it may, the fact
that the Governor in Council and responsible authorities exercised their
discretion to approve a project whose scope was defined by the minister with
the statutory authority to do so tends to favour the reasonableness of the
impugned decisions, rather than the reverse.
[74]
For these reasons, I
am of the view that the judge’s finding is consistent with the scheme of the CEAA,
the rulings of the Supreme Court of Canada and the facts in this case.
(d)
Other grounds of appeal
[75]
It should be noted that the appellant raised two other grounds of appeal that need not be decided
by this Court.
[76]
The appellant first submits
that the judge erred in finding that the real decision impugned by the
appellant was the one made by the Minister pursuant to section 15 of the CEAA
(judge’s reasons at paras. 41-68).
[77]
Although it appears that the
scope of the Project was in fact the subject of much discussion during the
hearing at first instance, the appellant acknowledged on appeal before this Court
that it was not challenging the decision of the federal Minister of the
Environment to maintain the scope of the Project as proposed by Nalcor or the
conclusions of the Joint Review Panel Report. It is therefore unnecessary to
address the judge’s findings in this regard as they cannot have any impact on
the present appeal.
[78]
The appellant further
contends that the judge erred in finding that the appellant was seeking to
re-scope the Project or restart consultations, when it was merely asking that
the Court order the Governor in Council and responsible authorities to make a
new decision based on the Project as it has actually proceeded, which does not
include the Gull Island facility (judge’s reasons at para. 2).
[79]
As indicated previously, it
appears that the appellant made submissions in the hearing at first instance
with respect to the appropriate scope of the Project. The appellant
nonetheless emphasizes that the principal remedy sought at first instance and
on appeal is to refer the Report back to the Governor in Council and
responsible authorities in order for them to make the appropriate decisions on
the basis of what it considers to be the real Project. Given that the appellant
asserts that it did not seek the remedies it claims the judge attributed to the
appellant in his reasons and that the judge took into account those actually
pursued by the appellant, any alleged error of the judge on this point has no
bearing in this appeal.
[80]
The appellant has not persuaded me that the judge committed an error in
his analysis regarding the reasonableness of the decision of the Governor in
Council and the decision of the responsible authorities that would warrant the
intervention of this Court.
[81]
I will now address the second issue regarding
the Crown’s duty to consult.
[82]
The judge noted in his
reasons that issues relating to the existence and content of the duty to
consult attract a standard of correctness. He further asserted that a decision
as to whether the Crown met its duty to consult is reviewable on a reasonableness
standard, as it is a mixed question of fact and law. In the present instance,
the parties acknowledge that the Crown recognized its duty to consult from the
outset. The issue is therefore not whether the Crown has a duty to consult but
rather whether the efforts of the Crown met the requirements of its duty to
consult. As Justice Binnie writes in Beckman v. Little Salmon/Carmacks First
Nation, 2010 SCC 53, [2010] 3 S.C.R. 103 at paragraphs 48 and 77 [Little
Salmon]: “the standard of
review in that respect, including the adequacy of the consultation, is
correctness” , but nonetheless it “must be assessed in light of the role and
function to be served by consultation on the facts of the case and whether that
purpose was, on the facts, satisfied”.
[83]
It
is through that lens that the following issues will be examined.
[84]
The Crown’s duty to
consult Aboriginal peoples, if any, and its duty to accommodate, even prior to
a decision on asserted Aboriginal rights and title, was recognized in 2004 by
the Supreme Court of Canada in Taku River Tlingit First Nation v. British
Columbia (Project Assessment Director), 2004 SCC 74, [2004] 3 S.C.R. 550 [Taku
River] and Haida Nation v. British Columbia (Minister of Forests),
2004 SCC 73, [2004] 3 S.C.R. 511 [Haida Nation]. The Crown’s
duty to consult is grounded in the principle of the honour of the Crown and
this duty “arises when the Crown
has knowledge, real or constructive, of the potential existence of the
Aboriginal right or title and contemplates conduct that might adversely affect
it” (Haida Nation at para. 35; Rio
Tinto Alcan Inc. v. Carrier Sekani Tribal Council, 2010 SCC 43,
[2010] 2 S.C.R. 650 at paras. 31, 40 and 41 [Carrier Sekani]).
It requires the government to undertake a meaningful
consultation in good faith with the Aboriginal people concerned on matters that
may adversely affect their rights and to accommodate those interests in a
spirit of reconciliation (Haida Nation at paras. 20 and 25; Carrier
Sekani at para. 31). The duty to act honourably derives from the Crown’s
assertion of sovereignty and the fact that Canada’s Aboriginal peoples were
here when the Europeans arrived (Haida Nation at para. 25). Subsection
35(1) of the Constitution Act, 1982, which recognizes and affirms
existing Aboriginal rights and title, enshrines this principle (Taku River at para. 24). Thus, the honour of the Crown is always at stake in
its dealings with Aboriginal peoples (R v. Badger, [1996] 1 S.C.R. 771; R
v. Marshall, [1999] 3 S.C.R. 456).
[85]
The Crown’s duty to consult cannot be defined in
isolation, and the extent of the duty will vary with the circumstances. On the
basis of the proportionality test, the nature and scope of the duty of
consultation is “proportionate to
a preliminary assessment of the strength of the case supporting the existence
of the right or title, and to the seriousness of the potentially adverse effect
on the right or title claimed” (Haida Nation at paras. 39, 43-45; Taku
River at paras. 29 to 32; Carrier Sekani at para. 36).
(a)
The decision of the Supreme Court of Canada in Tsilhqot’in Nation
[86]
It should first be
mentioned
that the Supreme Court of Canada handed down its decision in Tsilhqot’in
Nation v. British Columbia, 2014 SCC 44 [Tsilhqot’in Nation]
after this Court heard the present matter. The parties were however provided
with an opportunity to submit additional written submissions regarding the
impact of Tsilhqot’in Nation. The case at bar will therefore be examined
taking into account the principles set out by the Supreme Court of Canada in Tsilhqot’in
Nation.
[87]
Tsilhqot’in Nation focuses on the existence and characteristics of
Aboriginal title as well as on the Crown’s duty to consult. This Supreme
Court of Canada decision clarifies the existing principles regarding the manner
in which the Crown must deal with the potential existence of Aboriginal title
where planned actions could adversely affect that Aboriginal title. In
Tsilhqot’in Nation, after reviewing the evidence over a 339-day trial
spanning a five-year period, Justice Vickers of the British Columbia Supreme
Court found that the Tsilhqot’in people were in principle entitled to a
declaration of Aboriginal title on a portion of the claim area. The Supreme
Court of Canada, for its part, granted a declaration of Aboriginal title over
the area at issue.
[88]
The Supreme Court of Canada further determined
that the
Crown had breached its duty to consult in relation to certain forestry
activities on Aboriginal title lands that occurred without any meaningful
consultation with the Tsilhqot’in (Tsilhqot’in Nation at paras. 95-96).
(b)
The case at bar
[89]
In this case, the federal
government agreed in 1979 to negotiate land claims with the Innu of Ekuanitshit
for the purpose of concluding a treaty on the basis of the traditional
occupation of the lands. Although the land claims of the Innu of Ekuanitshit
remain unresolved, the traditional occupation of the lands in question has been
accepted as a background by the federal government and by Nalcor, even though
Nalcor at first denied this traditional occupation, but later reversed its
position.
[90]
Given
the use and occupation of their traditional lands, it is understandable that
the Innu of Ekuanitshit were wary when Nalcor presented the hydroelectric
Project in issue. In the context of a land claim that had been accepted for
negotiation by the government, it is reasonable to think that this Project
could a
priori affect the yet to be
established rights of the Innu of Ekuanitshit over the lands claimed. This is
indeed what led the judge to state at paragraph 104 of his reasons that “the [appellant] has a strong prima facie
case for land use rights in the Project area”. Pursuant
to established principles of case law, the Crown therefore had a duty to consult
the Innu of Ekuanitshit and that consultation had to be carried out at a level
higher that the bare minimum of the spectrum.
[91]
As
I previously noted, the appellant does not dispute the fact that the Crown did
consult the Innu of Ekuanitshit. This is not a situation in which the Crown
denied its duty to consult or made a decision that may affect the rights of an
Aboriginal group without consultation (Haida Nation; Mikisew Cree;
Tsilhqot’in Nation). The issue raised by the appellant and which must be
decided is rather whether the consultation process carried out so far by the
Crown was adequate and proportionate not only to the strength of the claim but
to the seriousness of the adverse impact the contemplated government action would have on the claimed right (Haida Nation
at para. 39; Tsilhqot’in Nation at para. 79).
[92]
At this stage it is appropriate to examine the
unfolding of the process used by the government in its consultation with the
Innu of Ekuanitshit. I have already indicated that the federal government
acknowledged from the outset its duty to consult. In order to fulfill this
duty, the federal government began by establishing its framework for
consultation, which set out five dialogue phases between the government and the
Aboriginal people prior to the Project being executed. The five phases are the
following:
[translation]
- Phase I: Initial
participation and consultation on the draft Joint Review Panel Agreement, the
appointment of the Joint Review Panel’s members and the Environmental Impact
Study Guidelines;
- Phase II: Joint Review
Panel Process leading up to the hearings;
- Phase III: Hearings and
drafting of the Joint Review Panel’s environmental assessment report;
- Phase IV: Consultation on
the Joint Review Panel’s environmental assessment report;
- Phase V: Issuance of
regulatory permits.
(A. B., Vol. 12, Tab 22 at 4049)
[93]
This consultation framework provided the
Aboriginal people with the opportunity to present their perspective on the
following matters:
[translation]
- Their traditional knowledge with
respect to the environmental effects of the Project;
- The effect that environmental
change caused by the Project may have on the current use of lands and resources
for traditional purposes;
- The nature and scope of their
recognized or asserted Aboriginal rights or treaty rights, the potential
impacts of the Crown’s activities in relation to the Project on those rights
and the appropriate measures to avoid or mitigate those impacts.
(A.B., Vol. 12, Tab 22 at 4040)
[94]
In this context, the government identified the
Aboriginal groups that could be affected by the Project. The Innu of
Ekuanitshit were among the groups identified by the government and the judge
noted in his decision that the appellant’s participation was active and began
early in the consultation process, in particular through the environmental
assessment process.
(c)
Environmental assessment process
[95]
In the case at bar, the appellant submits that
the judge erred when he stated that the environmental assessment process
provided under the CEAA allowed the Crown to include it in the
consultation in order to partially meet its constitutional duties.
[96]
Within the framework of the environmental
assessment process of the Project, the Joint Review Panel was tasked with
inviting Aboriginal groups to explain their use of the territory and how the
Project would impact them. In carrying out its mandate, the Joint Review Panel
was to consider a number of factors following the environmental assessment in
accordance with subsections 16(1) and 16(2) of the CEAA and sections 57
and 69 of the Environmental Protection Act of Newfoundland and Labrador,
including [translation] “the comments of Aboriginal groups and
peoples, the public and interested parties received by the Panel during the
(environmental assessment)…” (A.B.,
Vol. 3 at 909).
[97]
The Joint Review Panel’s mandate with respect to
considerations touching on Aboriginal rights did not include making any
determinations or interpretations of:
-
the validity or strength of any Aboriginal group’s claim to
Aboriginal rights and title or treaty rights;
-
the
scope or nature of the Crown’s duty to consult Aboriginal persons or groups;
-
whether
Canada or Newfoundland and Labrador has met their respective duty to consult
and accommodate in respect of potential rights recognized and affirmed by
section 35 of the Constitution Act, 1982;
-
the
scope, nature or meaning of the Labrador Inuit Land Claims Agreement.
[98]
In other words, the Joint Review Panel could
not determine the strength of the Innu of Ekuanitshit’s claim to Aboriginal
rights or the scope of the duty to consult but was to consider the Project’s
impacts on their claimed rights.
[99]
In
Taku River, the Supreme Court held that
participation in a forum created for other purposes, such as a social and
environmental impact assessment process, may nevertheless satisfy the duty to
consult if, in substance, an appropriate level of consultation is
provided. This principle was recently explicitly reiterated in Little Salmon
at paragraph 39 and in Carrier Sekani at paragraphs 55 to 58. The
Supreme Court of Canada, per Justice Binnie, further teaches that, under the
appropriate circumstances, the environmental assessment process provided under the CEAA
may be applied by the federal government to carry out consultations and fulfill
its duty to consult Aboriginal peoples (Quebec (Attorney General) v. Moses,
2010 SCC 17, [2010] 1 S.C.R. 557 at para. 45).
[100] An invitation on the part of the Crown to an Aboriginal group to
participate in an environmental assessment is not necessarily sufficient to
discharge the Crown of its duty to consult (Mikisew Cree First Nation v. Canada (Minister of Canadian Heritage), 2005 SCC 69, [2005] 3 S.C.R. 388). The
Aboriginal group must be consulted “as a First Nation” and not “as members of the general public” (Little Salmon at para. 79). In the case at bar, it would be inaccurate to claim
that the appellant did not participate as a First Nation in the environmental
assessment process. More specifically, the appellant provided feedback on the
contents of Nalcor’s impact study, it was invited to make submissions on the
draft agreement on the establishment of a Joint Review Panel and to appoint
members. The appellant also received financial assistance from the Participant
Funding Program of the Environmental Assessment Agency, which provided it with
an opportunity to file its written submissions on Nalcor’s impact study. The
appellant also presented its oral submissions in Sept-Îles in 2011 (judge’s
reasons at paras. 114-116).
[101] Following Phase IV of the consultation process regarding the “consultation
on the Joint Review Panel’s environmental assessment report”, the Joint Review Panel
issued its Report. The findings of the Joint Review Panel regarding the Innu of
Ekuanitshit and the territory covered by the Project are determinative in this
case. Under its mandate, the Joint Review Panel found, among other things, that
contemporary land use by the Innu of Ekuanitshit in the Project area was
seasonal, sporadic, and of short duration, and that the impacts, although
negative, would not be significant. The Joint Review Panel conveyed this in the
following terms:
In addition to caribou hunting, the Panel
noted that other use of lands and resources by Quebec Aboriginal groups in the
Project area appeared to be seasonal, sporadic and of short duration, including
incidental harvesting along the Trans Labrador Highway.
The
Panel also noted that many land and resource use locations reported to be
frequented by Aboriginal persons living in Quebec are outside the Project area
and would remain unaffected and accessible.
Based
on the information on current land and resource use identified through the
environmental assessment process, there are uncertainties regarding the extent
and locations of current land and resource use by Quebec Aboriginal groups in
the Project area. The Panel recognizes that additional information could be
forthcoming during government consultations. To the extent that there is
current use of the land in the Project area, the Panel concludes that the
Project’s impact on Quebec Aboriginals land and resource uses, after implementation
of the mitigation measures proposed by Nalcor and those recommended by the
Panel, would be adverse, but not significant. (A.B., Vol. 3 at 756)
[Emphasis
added.]
[102] It is important to note that this finding of the Joint Review Panel is
not disputed by the appellant.
[103] The government’s acceptation to negotiate comprehensive land claims
and Nalcor’s acknowledgement of the traditional use of the lands claimed
supports the finding that, at first glance, a project such as Nalcor’s could
have adverse impacts on claimed rights and title. However, the factual
background and the evidence with respect to the appellant’s current use of the
land in the Project area are important elements in assessing the strength of
the rights but also in identifying the true impact and seriousness of the
potentially adverse impacts of the Project on the appellant’s rights.
[104] As I have noted above, the assessment of whether the duty to consult
was met must be carried out on the basis of two inextricably linked elements,
namely, the strength of the claim and the severity of the impact of the
proposed Project. The Joint Review Panel, after
holding its hearings, concluded that the appellant’s current interests in the
Project area were seasonal, sporadic and of short duration. Furthermore, if the
use and occupation of the lands claimed for traditional purposes is not
challenged by either the federal government or Nalcor, I would add that the
evidence in the record adduced by the appellant in support of the interest of
the Innu of Ekuanitshit in the Project zone remains, on the whole, limited.
[105] In Tsilhqot’in
Nation, the evidence revealed, a priori, the existence of a strong Aboriginal title
and the existence of that Aboriginal title in the designated area had
previously been established by a court following an adversarial debate with
regard to proof of title. Once the existence of Aboriginal title has been
established, it stands to reason that the level of consultation and
accommodation is necessarily higher (Tsilhqot’in Nation). In the case at
bar, the issue of Aboriginal title was not directly raised by the appellant.
[106] Even if it were
granted that the Innu of Ekuanitshit exercised traditional use of the land in
the Project area, as was noted by the Joint Review Panel in its findings, which
are not disputed, the interest the Innu of Ekuanitshit could claim and the
seriousness of the adverse impact the proposed Project
would have on their claimed rights remain limited.
(d)
Premature challenge
[107] Unsatisfied with the way the consultation was proceeding,
the appellant did not wait until the end of the process before applying to the
Federal Court for judicial review alleging the insufficient nature of the
consultation during the phases prior to Phase V of the consultation framework.
The judge concluded that it was premature to determine whether there had been
adequate consultation in light of the fact that the consultation was not
finished and Phase V of the consultation process had yet to begin.
Nevertheless, the judge analyzed the way the consultation had unfolded up to
phase V and concluded that it had been adequate. Before this Court, the
appellant is challenging the merits of the judge’s decision.
[108] With respect, I find
it difficult to conclude that the judge erred in finding that the appellant had
been adequately consulted prior to the government’s order being issued. Phase V
of the consultation framework confirms that the consultation process between
the Crown and the Aboriginal people continues up to the issuance of licences by
Transport Canada and Fisheries and Oceans. These licences will authorize Nalcor
to undertake certain activities, including the construction of dams that could
have consequences on the navigable waters under the Navigable Waters
Protection Act or on fish habitat under the Fisheries Act. But we
are not at that point yet. As confirmed and acknowledged by the lawyers of the
Attorney General of Canada, the federal government’s consultation has not been
completed and will remain ongoing until the final phase, namely, the issuance
of licences.
[109] Also, as explained
in Haida Nation, the consultation process may lead to a duty to
accommodate Aboriginal concerns by adapting decisions or policies in response
(see in this regard Taku River at para. 42). The Joint
Review Panel found that certain studies should be carried out at a later stage
in order to better appreciate the concerns of Quebec Aboriginal peoples,
including the appellant. There is no doubt that the Joint Review Panel, and as
a consequence the respondents in this matter, examined the issue regarding the
extent to which the appellant’s concerns should be accommodated at the approval
stage of the Project and the circumstances under which the appellant could
continue to participate in the process so as to ensure that its concerns were
taken into consideration and, if required, accommodated. It is therefore
expected that at each stage (permits, licences and other authorizations) as
well as during the assessment of the adequacy of corrective measures taken by
Nalcor and the relevant government authorities to address any adverse
consequences of the Project, particularly on the caribou which is of interest
to the appellant, the Crown will continue to honourably fulfill its duty to
consult the appellant and, if indicated, to accommodate its legitimate concerns
(see in this regard Taku River at para. 46).
[110] In view of the
foregoing and taking into account the following: (i) the unfolding of the
environmental assessment process, (ii) the consultation process implemented by
the government, (iii) the appellant’s participation in the process, (iv) the
consultation carried out at each stage and (v) the Joint Review Panel’s finding
on contemporary use and the impacts of the Project, elements that are not
disputed by the appellant, it is difficult for me to conclude that the
government failed to comply with the established principle of the honour of the
Crown. I would like to note, however, that the Crown must continue to
honourably fulfill its duty to consult the Innu of Ekuanitshit until the
conclusion of the process.
(e)
Evidence and essential issues
[111] Secondary to its main argument regarding the Crown’s duty to consult, the
appellant further contends that the judge erred by failing to take into account
the evidence on several essential issues. I will address each of the issues
raised by the appellant in turn.
[112] The appellant first notes that the Innu of Ekuanitshit are not named in the
government’s response to the Joint Review Panel Report as it only refers
generally to [translation]
“Aboriginal groups in Quebec” (A.B., Vol. 2 at 484-531). At the outset, the
appellant argues that it is impossible to conclude that the concerns of the
Innu of Ekuanitshit were taken seriously or accommodated. However, the
appellant’s complaint in this regard cannot be accepted. Several Aboriginal
groups from Quebec and Labrador participated in the environmental assessment
process. In particular, the Appendix of the Joint Review Panel Report lists all
of the participants in the public hearings held by the Joint Review Panel. The
Innu of Ekuanitshit are listed among the participants. Furthermore, Chapters 9
and 10 of the report contain an analysis of the use of the lands by all of the
Aboriginal groups concerned as well as an analysis of their established or
asserted rights and titles.
[113] The appellant further claims that the Joint Review Panel had suggested a more
in-depth consultation that never materialized. However, a careful reading of
the Joint Review Panel’s findings at pages 185 and 186 of its report (A.B.,
Vol. 3 at 755-756) in fact shows that the Joint Review Panel specifically
stated that additional information could be gathered during the government’s
consultation process which has yet to be completed.
[114]
The appellant further insists that the
judge erred with respect to the negotiations that were held between the Innu of
Ekuanitshit and Nalcor in order to agree to an amount to facilitate its
participation in the environmental assessment process. The initial amount
proposed by the appellant was approximately $600,000 and was based on an environment
impact study carried out for a hydroelectric project in Quebec, namely, the
Romaine project. That study noted, inter alia, the small size of the
population of the Innu of Ekuanitshit in the 20th century. The study also
confirmed that the traditional territory of the Innu of Ekuanitshit was
primarily used for hunting, fishing and gathering.
[115] For its part, Nalcor was of the view that
the sum of $600,000 was not needed in order to be able to identify land use for
traditional purposes by the Innu of Ekuanitshit in the Project area. Nalcor
therefore proposed a budget of $87,500. This sum was rejected as insufficient
by the appellant.
[116] The judge concluded that, having refused the $87,500 offered by Nalcor, it
was up to the appellant to submit a counter offer, which it apparently did not
do (judge’s reasons at para. 129). The appellant claims that the counter offer
was made and that it can be found in a letter dated November 9, 2010 (A.B.,
Vol. 18, Tab FF at 6241-6242). In failing to refer to this letter in his
reasons, the appellant maintains that the judge committed an error. The
appellant then contends that Nalcor replied to its counter offer only three (3)
months later, namely, on January 14, 2011 (A.B., Vol. 15, Tab A.1 at 4901) just
days before the Joint Review Panel’s hearings were about to begin. Essentially,
in the appellant’s view, there was therefore no follow up to their counter
offer.
[117] The judge noted, at
paragraph 129 of his reasons, that “the Court reviewed the correspondence exchanged in the negotiations”, but concluded nonetheless that no counter offer had been made. However, the letter
dated November 9, 2010, referenced by the appellant, which proposes that the
parties agree on a mandate of an expert is in fact a counter offer. Therefore,
I agree with the appellant that the judge wrongly asserted that the appellant
had not made a counter offer.
[118] Be that as it may,
this omission on the judge’s part is of no real consequence. Indeed, echoing
the conclusions of the Joint Review Panel, the judge at paragraph 84 of his
reasons noted that the current land use by Innu of Ekuanitshit in the Project
area was “seasonal, sporadic and
of short duration” and that he “fails to see how further details would have
significantly modified the JRP (Joint Review Panel)’s ultimate conclusion in
this instance”. The appellant provided no convincing arguments explaining how a
response and follow up to the counter offer would have actually altered the
conclusion of the Joint Review Panel.
[119] Lastly, the
appellant suggests that the judge committed another error in his finding
regarding the mitigating measures that were to be taken to minimize the impact
on the caribou herds in the Project area. The appellant was particularly
insistent with regard to the caribou herd at Lac Joseph and on the appellant’s
request that the federal government refrain from authorizing the Project. The
appellant alleges that its request went unanswered and that the Project was
later approved. The consultation process would thus be fundamentally flawed.
[120] However, the
mitigation measures proposed by Nalcor to minimize the impacts of the Project
on the caribou were intended for the herd of caribou on Red Wine Mountain, a herd particularly vulnerable to the impacts of the Project (A.B., Vol. 3 at
692-696). The judge was of the view that the mitigating measures applied to the
more at risk Red Wine Mountain herd could also be applied to the Lac Joseph
herd. The judge wrote as follows at paragraph 132 of his reasons:
[132] Furthermore, while the federal government did
not respond to the Applicant’s letter regarding the Lac Joseph herd, its
concern was addressed by the mitigating measures proposed in the JRP [Joint
Review Panel] report and confirmed in the Decision (see NR, vol. 3, p. 638).
Nalcor chose to focus on the Red Wine herd in its EIS [Environmental Impact
Study] (i.e., to use as its “key indicator”) because it was the species most at
risk. The mitigating measures introduced to prevent serious harm to the Red
Wine caribous can also be applied to the Lac Joseph herd (see N.R., vol. 8,
page 1914).
[Emphasis
added.]
[121] As far as the more specific mitigating measures regarding the caribou
and the recommendations contained in the government of Canada’s response, the
federal government took into account in its decision the measures envisaged by
the province with respect to management and recovery of the caribou herds. The
conclusions found in the government of Canada’s response are clear as far as
its role under subsections 37(2.1) and 37(2.2) of the CEAA in
that it would [translation] “require certain mitigating measures, the
monitoring of environmental impacts and adaptive management on the part of
Nalcor, as well as further studies on the effects over time” (A.B., Vol. 13, Tab 57 at 4306-4308). The appellant adduced no evidence
to indicate that this would not be done.
[122] The appellant has not demonstrated, in the
circumstances of this case, that the government neglected its duty to consult
prior to the issuance of the order. Therefore, in light of the evidence in the
record, I am of the view that the judge did not err in finding that the
appellant was consulted in an adequate manner and that the mitigating measures
address, for now, its concerns. Indeed, the consultation conducted at this
stage, given the strength of the claim and the
seriousness of the adverse impact that the government-proposed measure would
have on the asserted right, meets “the idea of
proportionate balancing” referred to in Haida Nation. (Haida
Nation at para. 39; Tsilhqot’in Nation at para. 79).
[123] In short, I find that the consultation carried out is adequate for now, to
maintain the honour of the Crown and meet its constitutional obligations.
[124] For all of these
reasons, I would dismiss the appeal. In my opinion, there is no reason to order
costs against the appellant given the nature of the dispute and the particular
circumstances of the case.
“Richard Boivin”
“I agree
Johanne Gauthier J.A.”
“I agree
Robert M. Mainville J.A.”