Docket: T-2292-14
Citation:
2015 FC 1030
Ottawa, Ontario, August 28, 2015
PRESENT: The
Honourable Mr. Justice Manson
BETWEEN:
|
PROPHET RIVER
FIRST NATION, WEST MOBERLY FIRST NATIONS
|
Applicants
|
and
|
ATTORNEY
GENERAL OF CANADA, MINISTER OF THE ENVIRONMENT, MINISTER OF FISHERIES AND
OCEANS, MINISTER OF TRANSPORT, AND BRITISH COLUMBIA HYDRO AND POWER AUTHORITY
|
Respondents
|
JUDGMENT AND REASONS
[1]
This application for judicial review is based
upon the decision of the Governor in Council [GIC] that the significant adverse
environmental effects the Joint Review Panel of the British Columbia and
Federal Governments [the JRP or Panel] and the Minister of the Environment [the
Minister] determined would likely result from the construction of the Site C Clean
Energy Project [the Project] on the Peace River in British Columbia were “justified in the circumstances.” The GIC is charged
under section 52(4) of the Canadian Environmental Assessment Act [CEAA
2012], to make such a determination after the Minister decides that a project
will likely cause significant adverse environmental effects under section 52(1)
of the CEAA 2012.
[2]
This application was heard consecutively with
Federal Court Action T-2300-14, Peace Valley Landowner Association v
Attorney General of Canada et al, for which a separate decision will be
issued.
I.
Background
[3]
The Project is a proposed dam and 1,100-megawatt
hydroelectric generating station on the Peace River, near Fort St. John,
British Columbia, which if constructed would flood the Peace River Valley. The
Project would be the third in a series of dams constructed on the Peace River
in British Columbia. The Project components would consist of an earthfill dam
1,050 metres long and 60 metres high, a 1,100-megawatt generating station and
associated structures, a 83-kilometre long reservoir, realignment of four
sections of Highway 29, and two 77-kilometre transmission lines along an
existing transmission line right-of-way connecting the Project to the Peace
Canyon Dam, one of the existing dams on the Peace River. The Project is
expected to generate an average of 5,100 gigawatts hours of electricity per
year for more than 100 years.
[4]
The Project had an estimated cost of 7.9 billion
dollars at the time of its environmental assessment and an estimated eight year
construction period. In oral argument, this estimated cost was increased to
about 9 billion dollars in the interim and could continue to increase.
II.
The parties
[5]
The Applicants are British Columbia Treaty 8
First Nations (the Treaty 8 First Nations) whose members exercise their
constitutionally protected treaty rights within the Project and surrounding
area.
[6]
The Respondent Attorney General of Canada is
named as a Respondent in place of the Governor in Council, the decision-maker
of the Justification Decision.
[7]
The Respondent Minister of Environment is the
Minister required to make the Significant Adverse Environmental Effects
Decisions, pursuant to subsections 5(1) and 5(2) of CEAA 2012 and is the
Minister who issued the Decision Statement containing the Justification
Decision.
[8]
The Respondent Minister of Fisheries and Oceans
is the Responsible Authority that may issue authorizations under subsection
35(2)(b) of the Fisheries Act, RSC 1985, c F-14, in relation to the
Project.
[9]
The Respondent Minister of Transport is the
Responsible Authority that may approve the Project and ancillary works under
subsection 6(1) of the Navigation Protection Act, RSC 1985, c N-22, and
may permit ancillary works under subsection 9(1) of that same act.
[10]
The Respondent BC Hydro [BC Hydro] is a
provincial Crown corporation and the Project proponent (collectively “the
Respondents”).
III.
The Process
[11]
On May 18, 2011, BC Hydro submitted a Project
Description Report for the Project to the British Columbia Environmental
Assessment Office [EAO] and the Canadian Environmental Assessment Agency [the
Agency], initiating the environmental assessment processes of both entities.
[12]
On September 30, 2011, the above authorities
announced they would conduct a cooperative environmental assessment [EA], which
would include the JRP. As well, a draft agreement for the process and draft Terms
of Reference were released that same day. The Terms of Reference listed
thirteen factors the Panel must consider in its assessment. Of particular note
are paragraphs 2.2 and 3.14; the first provides the list of factors and the
second provides the Panel’s mandate with respect to information related to the
justifiability of any significant adverse effects the project may cause.
[13]
Prior to constituting the JRP, the Agency and
EAO oversaw the production of the environmental impact statement guidelines
[EIS Guidelines], which set out the scope of the factors listed in the Terms of
Reference and information to be submitted by BC Hydro in the form of an
environmental impact statement [EIS].
[14]
The first draft of the EIS Guidelines was
produced by BC Hydro and was subject to review by a Working Group who oversaw
amendments. On September 7, 2012, the Minister and the Executive Director of
the EAO determined the EIS Guidelines were adequate and issued them to BC
Hydro. They were then incorporated into the Terms of Reference pursuant to
paragraph 2.8.
[15]
On January 25, 2013, BC Hydro submitted the EIS
to the Agency and the EAO. It was then subject to review by the Working Group,
government agencies and the public. Each comment received was responded to and
29 technical memos were written to address common themes within those comments.
[16]
In June and July of 2013, the Agency and EAO
directed BC Hydro to amend the EIS on the basis of the comments and responses
received, and on August 1, 2013, they determined it was satisfactory and ready
for review by the Panel.
[17]
Between September and November of 2013, the JRP
requested information from BC Hydro three times, along with follow-up requests.
On November 7, 2013, the Panel decided that the amended EIS, along with the
additional information received, was sufficient to proceed to public hearing.
[18]
Public hearings were held over 26 days in
December of 2013 and January of 2014. During this period, sessions on December
9 and 10, 2013, as well as on January 23, 2014, addressed the topics “Need,
Purpose and Alternatives.”
[19]
After the public hearings had completed, on May
1, 2014, the JRP produced the Panel Report to the Minister and Executive
Director of the EAO.
[20]
The JRP made a number of findings in the JRP
Report, including:
a)
The Project would likely cause a significant
adverse effect on fishing opportunities and practices for the First Nations
represented by the Treaty 8 Tribal Association (“T8TA”) (Doig River First
Nation, Halfway River First Nation, Prophet River First Nation and West Moberly
First Nations), Saulteau First Nations and Blueberry River First Nations, the
effects of which could not be mitigated;
b)
The Project would likely cause a significant
adverse effect on hunting and non-tenured trapping for the First Nations
represented by T8TA and Saulteau First Nations, and that these effects could
not be mitigated;
c)
The Project would likely cause a significant
adverse effect on other traditional uses of the land for the First Nations
represented by T8TA, Saulteau First Nations and Blueberry River First Nations,
and that some of these effects could not be mitigated;
d)
The Project would likely cause significant
adverse cumulative effects on the current use of lands and resources for
traditional purposes;
e)
There would be significant cumulative adverse
effects on cultural heritage resources for both Aboriginal and non-Aboriginal
people;
f)
The Project would result in significant adverse
cumulative effects on fish and fish habitat, vegetation and ecological
communities, birds and migratory birds, large mammals and visual resources;
g)
The JRP questioned the maximization of the
hydraulic potential of the Peace River, which limited the consideration of
alternatives.
[21]
The JRP also made findings on the unique
qualities of the Peace River Valley that support the exercise of Treaty 8
rights such as fishing and concluded that an alternative comparable natural
setting could not be found nearby. The Panel found on the evidence that First Nations,
including some of the Applicant First Nations, have a strong cultural
attachment to the Peace River environment and that the area was highly valued
for the sustenance of their Aboriginal lifestyle.
[22]
On May 9, 2014, the JRP was made aware by BC
Hydro of an error in Chapter 15, Tables 16 and 18: the JRP had failed to
include low liquid natural gas [LNG] load in the load forecast (which was their
stated intention), which affects the Energy Load Resource Balance of the
Project. In response, the JRP issued an errata on June 10, 2014, to rectify the
issue and stated that they would modify the tables to include the omitted
information, but that the stated “conclusions remain as
noted” without further explanation.
[23]
In August of 2014, the Applicants were invited
to make a two page written submission to the Minister outlining their concerns
with the project. They stated they believed their treaty rights would be
infringed by the Project and that such an infringement required justification
under the Sparrow test. The Minister did not respond to these
submissions (R v Sparrow, [1990] 1 S.C.R. 1075).
[24]
On September 8, 2014, a memo was sent to the
Minister, which, once signed and dated by her, constituted the Minister’s
decision under section 52 of the CEAA 2012. She signed the memo and concurred
with the statement that significant adverse environmental effects were likely
to occur if the project proceeded.
[25]
The GIC released Order-in-Council 2014-1105 on
October 14, 2014, which set out its decision that the potential significant
adverse environmental effects likely to ensue should the Project be built were “justified in the circumstances.”
[26]
Also on October 14, 2014, the Minister issued a
decision statement under the CEAA 2012 (re-issued with minor corrections on
November 25, 2014), allowing the project to proceed.
[27]
The Order in Council which forms the impugned
decision reads as follows:
Whereas BC Hydro has proposed the
development of the Site C Clean Energy Project (the “Project”), near Fort St.
John, British Columbia;
Whereas, after having considered the Report
of the Joint Review Panel – Site C Clean Energy Project and taking into account
the implementation of mitigation measures that the Minister of the Environment
considered appropriate, the Minister has decided that the Project is likely to
cause significant adverse environmental effects;
Whereas, after having made this decision,
the Minister has, in accordance with subsection 52(2) of the Canadian
Environmental Assessment Act, 2012 (the “Act”), referred to the Governor in Council
for its consideration and decision the matter of whether those effects are
justified in the circumstances;
Whereas the Government of Canada has
undertaken a reasonable and responsive consultation process with Aboriginal
groups potentially affected by the project;
Whereas the consultation process has
provided the opportunity for dialogue and for the exchange of information to
ensure that the concerns and interests of the Aboriginal groups have been
considered in the decision-making process;
Whereas the consultation process has
included opportunities for the Aboriginal groups to review and comment on
conditions for inclusion in a decision statement to be issued by the Minister
under the Act that could mitigate environmental effects and potential impacts
on the Aboriginal groups;
Whereas the Minister will consider the views
and information provided by the Aboriginal groups when the Minister determines
the conditions to be imposed on the proponent in the decision statement;
Whereas the consultation process undertaken
is consistent with the honour of the Crown;
And whereas the concerns and interests of
Aboriginal groups have been reasonably balanced with other societal interests
including social, economic, policy and the broader public interest;
Therefore, His Excellency the Governor
General in Council, on the recommendation of the Minister of the Environment,
pursuant to subsection 52(4) of the Canadian Environmental Assessment Act,
2012, decides that the significant adverse environmental effects that Site C
Clean Energy project proposed by BC Hydro in British Columbia is likely to
cause are justified in the circumstances.
IV.
Issues
[28]
The issues are:
A. Did the GIC have the jurisdiction under section 52(4) of the CEAA
2012 to decide whether the project would constitute an infringement of the
Applicants’ treaty rights, and should the GIC have considered this issue in
determining that the Project was justified?
B.
Did the Applicants have a legitimate expectation
that the issue of infringement would be addressed by the GIC, based on
representations that had been made to them by the Agency?
C.
Has the duty to consult and accommodate the
Respondent First Nations been met in this case?
D. Was the GIC’s decision and Order in Council under section 52(4) of
the CEAA 2012, that the significant adverse environmental effects the Project
is likely to cause are justified, within the range of reasonable outcomes?
V.
Standard of Review
[29]
The Applicants submit that the appropriate
standard of review to be applied is correctness. They base their submissions on
the idea that the GIC violated procedural fairness in not taking into account
all relevant information or considerations. They further base their submissions
on the engagement of constitutional issues, the application of an incorrect
legal test, as well as the failure of the CEAA 2012 to explicitly shield the
GIC from review on a correctness standard, in its interpretation of the CEAA
2012 (Georgia Strait Alliance v Canada (Minister of Fisheries and Oceans),
2012 FCA 40 at paras 101, 102 [Georgia Strait]; Paul v British Columbia
(Forest Appeals Commission), 2003 SCC 55 at para 47).
[30]
The Applicants also submit that pursuant to the
decision in Council of the Innu of Ekuanitshit v Canada (Attorney General)
et al, 2013 FC 418 at para 76, aff’d 2014 FCA 189 at paras 40-42, 44 [Innu],
the GIC’s decision is only owed deference in situations that fall outside of
the three exceptions, outlined at paragraph 76 of the trial decision, namely “(1) whether the CEAA statutory process was not properly
followed before the decision was made; (2) the Governor in Council decision was
taken without regard for the purpose of the CEAA; or (3) the Governor in
Council decision had no reasonable basis in fact.” They argue that since
at least the second of these exceptions was engaged, the GIC is not owed
deference in their decision.
[31]
Moreover, the existence and extent of the duty
to consult are legal questions, reviewable on the standard of correctness. The
adequacy of the Minister’s, as well as the GIC’s, consultation is reviewable on
the reasonableness standard (Yellowknives Dene First Nation v Canada
(Minister of Aboriginal Affairs and Northern Development), 2015 FCA 148 at
para 46 [Yellowknives Dene]; Haida Nation v British Columbia
(Minister of Forests), 2004 SCC 73 at paras 61, 62 [Haida]; Adam
v Canada (Minister of the Environment), 2014 FC 1185 at para 65).
[32]
The Respondents submit that the appropriate
standard of review to be applied to the GIC’s statutory interpretation of its
role under the CEAA 2012 is reasonableness, given its central legislated role
in the EA process and determining whether significant adverse environmental
effects can be justified in the circumstances. The CEAA 2012 is clearly a
statute with which the GIC is particularly familiar (Dunsmuir v New Brunswick,
2008 SCC 9 at paras 53-54).
[33]
The Respondents further submit that the GIC’s
determination was highly discretionary, policy based and fact driven, to which
a standard of considerable deference should apply (Innu, above, at para
40; Canada (National Revenue) v JP Morgan Asset Management (Canada) Inc,
2013 FCA 250 at para 74).
[34]
In addition, the Respondents argue that the
Applicants’ reliance on the Georgia Straight case, above, to advocate
for a correctness standard is misplaced, as more recent authority confirms that
reasonableness applies when the decision under review intertwines discretion
and policy with questions of fact and an interpretation of the decision maker’s
own statute, or those closely connected to its function with which it would
have particular familiarity (Agraira v Canada (Public Safety and Emergency Preparedness)
et al, 2013 SCC 36 at para 50; Celgene Corp v Canada (Attorney general),
2011 SCC 1 at paras 33-34).
[35]
The polycentric decision of the GIC, itself an
elected body, assigned under legislation with which it is familiar, further
supports the application of a reasonableness standard.
[36]
The issues of procedural fairness and the
existence of the duty to consult and the extent of that duty (which are legal
questions) attract a standard of review of correctness (Mission Institution
v Khela, 2014 SCC 24 at para 79; Canada (Citizenship and Immigration) v
Khosa, 2009 SCC 12 at para 43; Yellowknives Dene, above, at para 46).
Reasonableness is the appropriate standard for all other issues, as the consultation
process and adequacy of consultation is a question of mixed fact and law (Haida,
above, at paras 61-62; Rio Tinto Alcan Inc v Carrier Sekani Tribal Council,
2010 SCC 43 at para 64 [Rio]).
VI.
Analysis
[37]
The relevant statutory provisions are attached as
Annex A hereto.
A.
Preliminary Evidentiary Objections
[38]
Given that the Applicants have withdrawn
Exhibits 10, 11 and paragraphs 21 and 22 of the Raphal affidavit which were
objected to, the Respondents have agreed that there is no need for Exhibits D
to M of the Savident affidavit, effectively negating the parties’ evidentiary
objections.
B.
Did the GIC have jurisdiction under section
52(4) of the CEAA 2012 to decide whether the project would constitute an
infringement of the Applicants’ treaty rights, and should the GIC have
considered this issue in determining that the Project was justified?
[39]
The Applicants argue that an action would not be
an appropriate forum to pursue a determination on infringement. Counsel stated
in oral argument that an action could only provide the after-the-fact remedy of
damages and would take so long that the immitigable environmental effects the
Project will cause would have already been suffered. As such, it is an
inappropriate and ineffective course of action for the Applicants.
[40]
Moreover, as the Applicants’ rights are
established in a treaty and are not asserted rights, the Applicants argue that
the Crown’s obligations to them are more clearly delineated and established than
in a situation where a First Nation has yet to have their rights affirmed and
recognized.
[41]
The Applicants’ position is that the taking up
clause in Treaty No. 8 allows the Government to take up lands from time to time
and it should be interpreted in line with R v Badger, [1996] 1 S.C.R. 771. Badger
speaks to the need to interpret the treaty by applying the “visible and
incompatible use” test to taking up land, and that there was a belief among the
parties to the treaty that most of the land covered by it would remain
unoccupied, despite the provision for taking up.
[42]
The Applicants also argue that their treaty
rights will be infringed by the construction of the Project and that such an
infringement must be justified under the Sparrow test. The Government’s
taking up of the land exceeds what was contemplated by Treaty No. 8, in that
they are taking up too much, too often. While the infringement might well be
justified under Sparrow, there was no determination of infringement made
and the JRP specifically acknowledged infringement of treaty rights was not
part of their mandate. Even if the GIC had the benefit of the JRP, the GIC was
required to act in accordance with the Constitution, and failing to deal with
infringement in making the impugned decision was an error (R v Sparrow, [1990]
1 SCR 1075). This failure to deal with infringement of treaty rights is the
kernel of the Applicant’s position that the GIC’s decision is both incorrect
and unreasonable.
[43]
Accordingly, the Applicants insist that the
GIC’s failure to determine infringement of their treaty rights makes this a
decision that cannot stand, despite the fact that the intent of this application
is not to attempt to pursue a particular outcome. It is the failure to deal
with the infringement issue at all, not the outcome itself, which the
Applicants say is both wrong and unreasonable.
[44]
Finally, the Applicants argue they had a
legitimate expectation that the issue of infringement would be dealt with by
the GIC. They base this argument largely on the distribution of a “schematic”
at different points throughout the consultation process, which showed that the
Federal Government would be dealing with infringement.
[45]
The Applicants rely on the decisions in West
Moberly and Beckman for the assertion that a judicial review
application in the Federal Court is capable of dealing with the issue of
infringement of treaty rights (West Moberly First Nations v British Columbia
(Chief Inspector of Mines), 2011 BCCA 247 at paras 92-97; Beckman v
Little Salmon/Carmacks First Nations, 2010 SCC 53 at para 47).
[46]
However, the GIC is not a tribunal, nor is it a
Minister. It exercises its discretion to decide on a different platform, based
on polycentric considerations and a balancing of individual and public
interests, including Aboriginal interests and concerns. It is properly afforded
considerable deference under review.
[47]
Parliament was clear in its intention to put the
decision as to whether significant adverse environmental effects are justified
in the hands of the GIC, knowing the considerable deference owed to their
determinations and their entitlement to privilege.
[48]
The case law shows that decisions of the GIC are
owed such considerable deference, as they are inherently polycentric and take
into account not only scientific facts and figures, but political and social
considerations as well. The GIC is made up of elected officials, each of which
is accountable to the Canadian public as represented by their constituencies
and in this case included the Ministers named as Respondents (Greenpeace
Canada v Canada (Attorney General), 2014 FC 463 at paras 232-236, 280-281).
[49]
I agree with the Respondents that judicial
review is not the appropriate course of action to determine whether Treaty No.
8 rights have been infringed. In oral argument, Applicants’ Counsel stated that
she believed that an action would not be able to award the Applicants what they
request and could only result in a monetary award of damages and costs should
they be successful. Further, she argued that the length of time it would take
for the action to be heard would give ample time for the Respondents to pursue
the Project and render the Applicants’ requests meaningless.
[50]
However, pursuit of an action may provide a
variety of remedies for the Applicants, including a summary trial, an
interlocutory injunction, or an expedited trial on the merits of the
infringement question, which if applied for, may properly and definitively, on
a full evidentiary record, deal with this issue.
[51]
Furthermore, as pointed out by the Respondents,
taking up of land under Treaty 8 is exclusively within the power of British
Columbia and not every taking up of lands under a treaty will constitute an infringement
of treaty rights, provided the taking up of that land does so in a manner that
respects the requirements set out in Mikisew (Mikisew Cree First
Nation v Canada (Minister of Canadian Heritage), 2005 SCC 69 at paras
54-59, 64-66 [Mikisew]; Grassy Narrows First Nation v Ontario
(Natural Resources), 2014 SCC 48 at paras 30, 52-53.
[52]
In my view, the evidentiary record developed for
an action is the appropriate basis for a Court to make a determination on the
issue of infringement of the Applicants’ treaty rights. While in Beckman v
Little Salmon/Carmacks First Nations, above, at para 47, the Supreme Court
made it clear that the judicial review process is a flexible one, capable of
dealing with an array of issues presented in that context, it cannot reasonably
be construed as saying that it is flexible enough to deal with all issues, in
all contexts and, as here, not for a determination of infringement of Treaty
No. 8 rights.
[53]
Where consultation is required at the deep end
of the spectrum and a specific determination on infringement on established
treaty rights is at issue, the Court is ill-equipped to make a determination
with an incomplete record or an informal evidentiary process before it on
judicial review. The infringement of those important and fundamental treaty
rights require a complete evidentiary record, that has reached the standard of
admissibility at trial, to be reasonably and fairly determined. Nevertheless,
it is without question that consideration of the issue of infringement of those
treaty rights, short of making an ultimate decision or determination, needs to
be part of the consultation process, as discussed below.
C.
Legitimate Expectations
[54]
The Applicants have failed to establish that
they had a legitimate expectation that the issue of treaty infringement would
be dealt with by the GIC. The doctrine is meant to deal only with the clearest
of cases and this is not one of them. The inclusion of a flowchart in a handful
of communications and one that was later altered during the process and
redistributed to the Applicants, without specifically referring to infringement
of treaty rights, is not sufficient to reach the high threshold required for
the Court to invoke the doctrine of legitimate expectation that this issue
would be determined, and not merely considered, as part of the consultation and
accommodation process.
D.
Has the duty to consult and accommodate the
Respondent First Nations been met in this case and was the GIC justification
decision reasonable?
[55]
The Supreme Court of Canada summarized the
framework governing the duty to consult in Rio, above, at para 51:
51 As we
have seen, the duty to consult arises when: (1) the Crown has knowledge, actual
or constructive, of potential aboriginal claims or rights; (2) the Crown
proposes conduct or a decision; and (3) that conduct or decision may have an
adverse impact on the Aboriginal claims or rights. This requires demonstration
of a causal connection between the proposed Crown conduct and a potential
adverse impact on an Aboriginal claim or right.
[56]
As stated in Ktunaxa Nation v British
Columbia (Minister of Forests Lands and Natural Resource Operations), 2015
BCCA 352 at paras 77-79:
77 The scope
of the duty to consult is proportionate to a preliminary assessment of the
strength of the case supporting the existence of the asserted rights, and to
the seriousness of the potentially adverse effect upon the right claimed (Haida,
at para 39). Fundamentally, the Crown is not under a duty to reach an
agreement; the commitment is to a meaningful process of consultation in good
faith (Haida, at para 41). Good faith is central, as the Court explains
in Haida at para 42:
42 At
all stages, good faith on both sides is required. The common thread on the
Crown's part must be "the intention of substantially addressing
[Aboriginal] concerns" as they are raised (Delgamuukw, supra, at
para. 168), through a meaningful process of consultation. Sharp dealing is not
permitted. However, there is no duty to agree; rather, the commitment is to a
meaningful process of consultation. As for Aboriginal claimants, they must not
frustrate the Crown's reasonable good faith attempts, nor should they take
unreasonable positions to thwart government from making decisions or acting in
cases where, despite meaningful consultation, agreement is not reached: see Halfway
River First Nation v. British Columbia (Ministry of Forests), [1999] 4
C.N.L.R. 1 (B.C.C.A.), at p. 44; Heiltsuk Tribal Council v. British Columbia
(Minister of Sustainable Resource Management) (2003), 19 B.C.L.R. (4th) 107
(B.C.S.C.). Mere hard bargaining, however, will not offend an Aboriginal
people's right to be consulted.
78 The duty
to accommodate requires a balancing of interests. The Court in Taku River
Tlingit First Nation v British Columbia (Project Assessment Director), 2004
SCC 74, explained at para 2:
…Where consultation is meaningful,
there is no ultimate duty to reach agreement. Rather, accommodation requires
that Aboriginal concerns be balanced reasonably with the potential impact of
the particular decision on those concerns and with competing societal concerns.
Compromise is inherent to the reconciliation process.
79 The
applicable standard of review was set out at para 62 of Haida as
reasonableness. The focus is not on the outcome, but on the process of
consultation and accommodation (Haida, at para 63). The Court explained
as follows at para 62:
…Perfect satisfaction is not
required; the question is whether the regulatory scheme or government action
"viewed as a whole, accommodates the collective aboriginal right in
question": Gladstone, supra, at para. 170. What is required is not
perfection, but reasonableness. As stated in Nikal, supra, at para. 110,
"in ... information and consultation the concept of reasonableness must
come into play[...]. So long as every reasonable effort is made to inform and
to consult, such efforts would suffice." The government is required to
make reasonable efforts to inform and consult…
[57]
The parties agree that the consultation required
was at the deep end of the spectrum (Haida, above, at paras 47-50).
[58]
However, while there is no dispute that
consideration of possible infringement of treaty rights should form part of the
Crown’s duty of consultation and accommodation, the Respondents argue that
consideration does not extend to a determination of infringement of those
rights. While the Applicants’ Treaty No. 8 rights have been established and it
is clear that significant adverse environmental effects will result from the
Project, the parties do not agree as to whether the consultation and
accommodations that took place were adequate (Haida, above).
[59]
As stated above, it is the Applicants’ position
that the consultation process never did reach the deep consultation threshold, as
it failed to consider infringement of their Treaty No. 8 rights. It is not the
quantity but the quality of consultation that determines the substance of the
depth of consultation (Kwikwetlem First Nation v British Columbia (Utilities
Commission), 2009 BCCA 68 at paras 66-70).
[60]
However, the JRP’s Panel Report, considered by
the Minister and implicitly by the GIC, entailed information gathering and
reporting, which necessarily does not encompass the wide array of viewpoints
and factors additionally considered by the Minister and the GIC.
[61]
Based on the record before me, and contrary to
the assertions made by the Applicants, the Crown did not need to determine
infringement of the Applicant’s treaty rights; they did consider those rights,
did not ignore the impact of the Project on those treaty rights or find that
the negative impact could be mitigated, and did assess the cumulative effects
of the prior existing two dams on the historical rights of the Applicants (EIS
Guidelines, clauses 8.5.3 and 9-1).
[62]
Consultation by BC Hydro with the Applicants
began in November 2007. It is summarized in the EIS, at Volume 5, Appendix A06
Parts 2 and 2(a) and outlined in Affidavit #1 of Seanna McConnell. In my view,
BC Hydro’s consultation has been extensive and conducted in good faith. The
Applicants, however, expressed their strong opposition to the Project, signing
a declaration “vow[ing] to use all lawful means to stop
the Site C Dam from proceeding” (EIS Volume 5, Appendix A06 Part 5, pp.
16-30 (Applicants’ Record, Tab 7C); Willson Affidavit, Exhibit 14 (Applicants’
Record, Tab 3); McConnell Affidavit #1, para 123 (BC Hydro’s Record, Tab11)).
[63]
In the seven year period from November 2007 to
December 2014, BC Hydro met with the interested Treaty 8 First Nations 177 times
and provided them with $5,879,039.78 in capacity funding to, inter alia,
conduct their own traditional land use and community baseline studies; retain
consultants; participate in the environmental assessment process including the
Panel hearings; attend meetings with BC Hydro; review material; and prepare
reports and comments from BC Hydro, the Agency, EAO, and the Panel. This amount
is in addition to funding provided by the provincial and federal governments.
[64]
This funding was provided pursuant to several
agreements with the Treaty 8 First Nations:
- Stage 2 Consultation Agreement (December 1, 2008 to March 31, 2010), for consultation prior
to the environmental assessment;
- Agreement to Negotiate a Traditional
Land Use Study Agreement (December 18, 2009), established
a process for negotiating a Traditional Land Use Study Agreement;
- Traditional Land Use Study Agreement (December 16, 2010), to conduct a traditional land use study
related to the Project on October 4, 2011, at the request of several First
Nations, the agreement was amended to drastically reduce the size of the
study area;
- Environmental Assessment Participating
Agreement (April 21, 2011 to October 14,
2014), established a process for consultation during the environmental
assessment;
- Letter of Understanding (March 6, 2012),
established terms of reference for the collection and reporting of
socio-economic baseline information by the First Nations;
- Various Letters of Understanding drafted
pursuant to the Environmental Assessment Participation Agreement
for specific consultation activities, including, e.g., with respect to
alternative dam sites;
- Discussion Framework (October 2, 2014), established a framework for post-Panel
consultation on the need for and alternatives to the Project.
[65]
Pursuant to these agreements, BC Hydro consulted
with the Treaty 8 First Nations prior to preparing the first draft of the EIS
Guidelines, prior to designing and implementing its field studies, finalizing
the design of the Project, and preparing the EIS, including the technical
reports and proposed mitigation measures contained therein, and prior to the
Province’s decision as to whether to proceed with the Project.
[66]
In March 2012, BC Hydro offered to enter
negotiations toward concluding impact benefit agreements with the Applicants.
In April 2014, Doig River advised BC Hydro they were interested in pursuing
impact benefit agreement negotiations. In their comments on the EIS, the Treaty
8 First Nations stated that they would consider negotiation of a benefit
sharing agreement in relation to alternatives to the proposed Project, with the
proviso that the Proponent first abandon plans to develop the proposed Project.
[67]
As well, alternatives to the Project as a source
of energy were also considered (EIS, clause 4.1.2, pages 291, 294, 304 and page
431 of the JRP).
[68]
From the beginning of the environmental
assessment process in May 2011, until its conclusion in October 2014, a number
of steps were built into the process so that the Minister and Cabinet were
provided with the information they reasonably required in order to make their
decisions. This information included a review of the BC/Canada Agreement and
the Terms of Reference, and a multi-staged review of the EIS Guidelines and the
EIS, after which the Agency and EAO determined the EIS was satisfactory. The
Minister and Cabinet reached their decisions after extensive input from the
public, government agencies and Aboriginal groups, including the Applicants. At
the Panel Stage, the Panel reviewed the EIS and requested additional information
from BC Hydro until it was satisfied the EIS was sufficient. The Panel then
held public hearings, received further submissions and at the end of the
process, produced a lengthy report in which it noted that it conducted its
assessment in accordance with the Terms of Reference.
[69]
The depth of consultation is also evident from
the three consultation plans initiated during the JRP process and the
post-panel stage consultation meetings. As set out in the affidavit of Seanna
McConnell, BC Hydro’s consultation with the Applicants was a lengthy process, was
in good faith and was extensive both qualitatively and quantitatively. It is
also apparent from the Record that while the Crown engaged with the Applicants
to address mitigation and measures to be taken after issuance of the JRP, the
Applicants refused to engage in such a dialogue once it was decided by the
Applicants that the Project not proceeding was the only viable solution for the
Applicants, as the end result of the process.
[70]
A commitment to the process does not require a
duty to agree – what is required is good faith efforts to understand the
concerns of the Applicants and the Respondents made such efforts, which the Minister
and GIC reasonably considered.
VII.
Submissions of the Intervener
[71]
While I appreciate the submissions of Amnesty
International, the crux of this judicial review involves whether or not the
Applicants should pursue a determination on infringement of their treaty rights
in the form of an action and whether judicial review is the proper approach.
Amnesty International presented interesting information regarding the value of
international law, in the form of both ratified and non-ratified treaties, in
interpreting the requirements of a body like the GIC in making determinations
on justification. It was informative; however I give their submissions little
weight, as they are not relevant to the central issues of this application.
[72]
For the reasons above, I would dismiss the
application for judicial review.
[73]
Given the public interest concerns, including
particularly the Treaty 8 First Nations’ concerns with the unmitigable
significant adverse environmental effects of the Project, which are legitimate,
I would have each of the parties bear their own costs.