Date: 20140514
Dockets:
T-1572-11
T-1723-12
Citation: 2014 FC 463
Ottawa, Ontario, May 14, 2014
PRESENT: The Honourable
Mr. Justice Russell
|
BETWEEN:
|
GREENPEACE CANADA,
LAKE ONTARIO WATERKEEPER, NORTHWATCH
AND CANADIAN ENVIRONMENTAL LAW ASSOCIATION
|
Applicants
|
and
|
ATTORNEY GENERAL OF CANADA,
MINISTER OF THE ENVIRONMENT,
MINISTER OF FISHERIES AND OCEANS,
MINISTER OF TRANSPORT,
CANADIAN NUCLEAR SAFETY COMMISSION
AND ONTARIO POWER GENERATION INC.
|
Respondents
|
|
AND
BETWEEN:
|
GREENPEACE CANADA
AND CANADIAN ENVIRONMENTAL
LAW ASSOCIATION
|
Applicants
|
and
|
ATTORNEY GENERAL OF CANADA AND
ONTARIO POWER GENERATION INC.
|
Respondents
|
REASONS FOR JUDGMENT AND JUDGMENT
TABLE OF CONTENTS
I. INTRODUCTION.. 5
II. BACKGROUND.. 5
III. DECISIONS UNDER REVIEW... 10
IV. ISSUES. 13
V. STANDARD OF REVIEW... 14
VI. STATUTORY PROVISIONS. 20
VII. ARGUMENT.. 28
A. Applicants. 28
EA Report - T-1572-11. 28
Failure to Comply with the CEAA.. 28
The PPE Approach. 30
Decommissioning and Waste Management 35
Procedural Errors. 37
Site Preparation License T-1723-12. 40
Legal Prerequisites. 41
Failure to Comply with Mandatory Requirements. 41
Procedural Fairness. 42
B. Respondents. 43
EA Report – T-1572-11. 43
Separate Scoping Decision – Collateral Attack. 44
There Was a Project to Assess. 45
The Bounding Approach. 46
Compliance with Section 16 of the Act 48
No Unlawful Delegation. 51
No Procedural Errors. 54
Site Preparation License T-1723-12. 55
Compliance with Statutory Scheme. 55
Procedural Fairness. 57
C. Applicant’s
Reply Submissions. 58
EA Report T-1572-11. 58
No Collateral Attack. 58
VIII. ANALYSIS. 61
D. The
Environmental Assessment – T-1572-11. 61
The Dispute. 61
The Law and Guiding Principles. 63
The Issues Raised. 71
No
Project to Assess. 71
Improper Collateral Attack. 73
Scope
of the Project 78
Scope
of the factors to be considered. 82
Was there a Failure to Assess the Project in Accordance
with the CEAA?. 93
What
did the CEAA require?. 101
Evidence
put forward by the Applicants. 118
Links
to the issue of improper delegation. 124
Gaps
in the bounding scenario regarding hazardous substance emissions and on-site 132
chemical
inventories. 132
Consideration
of spent nuclear fuel 149
Deferral
of the analysis of a severe common cause accident 165
Relevant
Case Law.. 172
West Vancouver. 172
Inter-Church
Uranium Committee. 175
Express
Pipelines. 178
Failure
to Assess “Need” and “Alternatives” to the Project 182
Unlawful Delegation. 189
Procedural Issues. 193
Conclusions. 195
E. The
Site Preparation License T-1723-12. 197
The Dispute. 197
Did the EA Comply with the CEAA?. 198
Did the CNSC Comply with the NSCA?. 198
Procedural Fairness. 202
The Motion to Strike. 204
Merits of the Procedural Fairness Issue. 207
IX. JUDGMENT.. 212
[1]
This judgment relates
to two applications for judicial review under s. 18.1 of the Federal Courts
Act, RSC 1985, c F-7 [Federal Courts Act] in relation to the Darlington New
Nuclear Power Plant Project (Project) proposed by Ontario Power Generation
(OPG). The first application challenges the adequacy of the federal
environmental assessment (EA) conducted by a joint review panel (JRP or Panel)
established under a March 2009 agreement between the federal Minister of the
Environment (Minister) and the Canadian Nuclear Safety Commission (CNSC) pursuant
to s. 40 of the Canadian Environmental Assessment Act, SC 1992, c 37
(CEAA or the Act). Because the assessment was concluded on August 25, 2011,
the governing statute is the CEAA, which has since been repealed and replaced.
The second application challenges a Site Preparation Licence (Licence) that was
issued by the CNSC to OPG on August 17, 2012 under the Nuclear Safety and
Control Act, SC 1997, c 9 (NSCA), following the completion of the EA and
the Government of Canada’s response to the Panel’s Environmental Assessment
Report (EA Report).
[2]
In June 2006, the
Ontario Minister of Energy directed OPG, which is wholly owned by the Province of Ontario, to begin the process of seeking federal approval for new nuclear power
generation units at an existing site. This directive coincided with a Supply
Mix Directive issued to the Ontario Power Authority, indicating that a
combination of new and refurbished nuclear units would be needed to meet future
base-load energy requirements in Ontario. The Government of Ontario later
selected the existing Darlington nuclear site as the preferred site for the Project.
In September 2006, OPG applied to the CNSC for a licence to prepare the Darlington site for the construction of a new nuclear power generation facility involving up
to four new nuclear reactors. The Darlington site is located in Bowmanville, Ontario, on the north shore of Lake Ontario, in the Municipality of Clarington, and is the location of the existing Darlington Nuclear Generating Station
(Darlington NGS).
[3]
Under the Law List
Regulations, SOR/94-636 (Law List Regulations), an environmental assessment
was required before the Licence could be granted. The Project proposed by OPG –
which includes the construction, operation, decommissioning and abandonment of
the proposed reactors and the management of the associated conventional and
radioactive waste – also required other federal approvals that would trigger a
CEAA assessment under the Law List Regulations, including authorizations under s.
35(2) of the Fisheries Act, RSC 1985, c F-14 (Fisheries Act) and s. 5 of
the Navigable Waters Protection Act, RSC 1985, c N-22 (NWPA) (now titled
the Navigation Protection Act). The CNSC requested that the Minister
refer the Project for review by a joint review panel, which the Minister did in
March 2008. The Panel was “joint” in the sense that it was to conduct an
environmental assessment of the Project under the CEAA, and was also to
function as a CNSC panel for the purpose of reviewing the Licence application.
[4]
In September 2008, the
Minister and the CNSC published drafts of the Environmental Impact Statement
Guidelines (EIS Guidelines) for the Project and the Joint Review Panel
Agreement (Agreement), including the Panel’s Terms of Reference (Terms of
Reference), for public comment. The EIS Guidelines provided direction to OPG on
how to develop its Environmental Impact Statement (EIS) for the Panel’s
consideration, and the Agreement outlined the framework for the establishment
of the Panel and the conduct of the joint review. The final versions of these
documents were published on March 12, 2009, after public comments were received
and considered. Both documents stated that a range of designs were being
considered and no decision had yet been made regarding reactor technology.
[5]
On September 30, 2009,
OPG filed its EIS, along with supporting documents and a revised Site Preparation
Licence application. Since no specific nuclear reactor technology had been
selected, OPG prepared its EIS based on what it called a “bounding approach” –
also referred to as a “plant parameter envelope” (PPE) or “bounding scenario”
approach – encompassing several possible reactor technologies. As described by
OPG in its submissions to the Court, this approach involves identifying the
salient design elements of the Project and, for each of those elements,
applying the “limiting value” (the value with the greatest potential to result
in an adverse environmental effect) based on the design options being
considered. In theory, this results in a composite picture of the maximum expected
environmental impact – the bounding scenario or PPE.
[6]
Initially, three
technology options were considered in developing the bounding scenario,
referred to as the ACR-1000, US EPR, and AP1000 options. Later in the process,
the Enhanced CANDU-6 (EC-6) reactor technology was added as an option, though
it was not addressed in the EIS. OPG says the EC-6 option was added to the PPE
model in July 2010 based on a letter from the CNSC to the Panel Chair. The
letter explained that the PPE approach is meant to provide a generic “technology-neutral”
EIS, and including the EC-6 technology in the Panel’s review would provide flexibility
at later stages of the Project and minimize the likelihood that another EA
would be required should the EC-6 technology be selected by OPG. The Panel
requested additional information from OPG to facilitate its assessment of the
EC-6 option. In October 2010, the Applicants objected to what they
characterized as the late inclusion of the EC-6 design based on fairness and
other grounds, but these objections were rejected by the Panel.
[7]
The three member Panel
was appointed on October 30, 2009. In November 2009, the Panel began its review
of the sufficiency of the EIS. This included the consideration of comments and
recommendations from the public, CNSC staff and other interested parties,
including government agencies and departments, over the course of 11 months. These
submissions included a letter from CNSC staff to the Panel secretariat dated November 2, 2009 stating that the EIS contained all of the
information required by the EIS Guidelines and the regulations applicable to
site preparation under the NSCA.
[8]
The Panel made 284
requests to OPG for additional information related to the EIS, and 26 requests
relating to the Licence application, based in part on the comments received. Technical
briefing sessions open to the public were held at CNSC headquarters in December
2009 and June 2010. Comments on the sufficiency of the EIS were accepted up
until October 8, 2010. The Panel concluded in December 2010 that the EIS and
the supplementary responses from OPG contained sufficient information to enable
the Panel to proceed to public hearings on the Project.
[9]
These hearings were
held over 17 days between March 21 and April 8, 2011. The Applicants
participated as interveners during both the public hearings and the pre-hearing
proceedings. On the final day of the hearings, the Panel released a revised
procedure for written comments, permitting hearing participants (other than
OPG) to make final written submissions by May 17, 2011, and OPG to make final
written submissions by May 22, 2011. On June 3, 2011, the Panel gave notice
that it had obtained and made public all of the information needed to prepare
its report, and closed the record for the EA.
[10]
On August 25, 2011,
the Panel completed the EA and submitted the EA Report to the Minister. The EA
Report concluded that the Project is not likely to cause significant adverse
environmental effects, provided the mitigation measures proposed and the
commitments made by OPG during the review, as well as the Panel’s 67 recommendations,
are implemented.
[11]
On September 23,
2011, the Applicants initiated the first of the judicial review applications
under consideration here (T-1572-11), challenging the adequacy of the EA and
the EA Report.
[12]
Once an EA Report is
submitted by a review panel, the responsible authorities prepare a Government
Response, which is presented to the Governor in Council (Cabinet) for approval.
“Responsible authorities” is a defined term referring in this case to federal
departments or agencies that must make some decision or take some action in
order for a project to move forward, and who are therefore responsible for
ensuring the EA is conducted (see CEAA, ss. 2(1), 5(1)(d), 11(1)). In this
case, the CNSC, the Department of Fisheries and Oceans (DFO) and Transport Canada are responsible authorities, and the Respondent Attorney General of Canada (AGC) indicates
that the Department of Natural Resources and Health Canada were also involved
in drafting the Government Response.
[13]
The Government
Response was issued on May 2, 2012, stating that the Government had concluded
that the Project is not likely to cause significant adverse environmental
effects. The Act requires responsible authorities to take a “course of action”
that is consistent with the Cabinet-approved Government Response (see CEAA, s.
37(1.1)(c)). On May 8, 2012, the responsible authorities announced their “course
of action decision” (or Final Decision) stating that the responsible authorities
may exercise any power or perform any duty or function with respect to the Project
because they are of the opinion that it is not likely to cause significant
adverse environmental effects.
[14]
On August 17, 2012,
the Panel, acting as a panel of the CNSC for the purposes of the Licence application,
issued a ten-year licence to OPG to undertake a range of site preparation
activities in relation to the Project.
[15]
The EA Report,
submitted by the Panel to the Minister on August 25, 2011, is 143 pages in
length (plus appendices) and includes 67 recommendations directed to federal,
provincial and municipal governmental authorities. The EA Report’s overall
conclusion was that “the Project is not likely to cause significant adverse
environmental effects, provided the mitigation measures proposed and
commitments made by OPG during the review and the Panel’s recommendations are
implemented”: EA Report at p. 143.
[16]
With respect to the use
of the PPE approach, the Panel made the following observations at page 45 of
the Report:
The Panel accepts the use of a plant parameter envelope for environmental
assessment purposes as an approach that allows the prediction of adverse
environmental effects for a select group of reactor technologies. The Panel
recognizes, however, that this is a departure from a more standard approach
where the major components of a project are defined in advance of an
environmental assessment.
Additionally, the Panel notes that aspects of the plant parameter envelope
were based on preliminary design information. As such, there will be a need for
ongoing verification of the conclusions reached on the significance of adverse
environmental effects.
[17]
The Panel stated that
if the Project is to go forward, the selected reactor technology “must be
demonstrated to conform to the plant parameter envelope and regulatory requirements,
and must be consistent with the assumptions, conclusions and recommendations of
the environmental assessment and the Government response to [the EA Report].” The
Panel noted that this will need to be evaluated by the responsible authorities
once a reactor technology is selected, and will be required to be demonstrated
as part of the Application for a Licence to Construct: EA Report at p. 11. If
the reactor technology selected is fundamentally different than those assessed,
the Panel stated, “then this review does not apply and a new environmental
assessment must be conducted”: EA Report at p. 143. This is reflected in
Recommendation 1 of the EA Report, which reads:
The Panel understands that prior to construction, the Canadian Nuclear
Safety Commission will determine whether this environmental assessment is
applicable to the reactor technology selected by the Government of Ontario for
the Project. Nevertheless, if the selected reactor technology is fundamentally
different from the specific reactor technologies bounded by the plant parameter
envelope, the Panel recommends that a new environmental assessment be
conducted.
[18]
The Licence, which is
valid from August 17, 2012 to August 17, 2022, authorizes OPG to undertake a
range of site preparation activities, including clearing and grubbing of
vegetation, excavation and grading of the site, installation of services and
utilities, construction of administrative and support buildings, and other
activities. It is supported by a Record of Proceedings, Including Reasons for
Decision, comprising over 50 pages (Reasons for the Licence Decision). Those
Reasons describe the matters to be decided and the conclusions of the Panel (acting
as the Commission) as follows:
9. In considering the application, the Commission was required to
decide whether the site is suitable for the construction of a nuclear
generating station, in accordance with the regulatory requirements of the Class
I Nuclear Facilities Regulations and the expectations set forth in CNSC
Regulatory Document RD-346. The Commission was also required to decide,
pursuant to subsection 24(4) of the NSCA:
a)
if OPG is qualified
to carry on the activities that the licence would authorize; and
b)
if, in carrying on
those activities, OPG would make adequate provision for the protection of the
environment, the health and safety of persons and the maintenance of national security
and measures required to implement international obligations to which Canada has agreed.
[…]
13. Based on its consideration of the matter, as described in more
detail in the following sections of this Record of Proceedings, the Commission
concludes that OPG is qualified to carry on the activities that the licence
will authorize. The Commission is of the opinion that OPG, in carrying on those
activities, will make adequate provision for the protection of the environment,
the health and safety of persons and the maintenance of national security and
measures required to implement international obligations to which Canada has agreed…
[19]
The issues raised in
these judicial review applications can be summarized as follows:
(a)
Did the Panel fail to
comply with the requirements of the CEAA in conducting the EA by:
i.
Failing to conduct an
environmental assessment of a “project” as defined in the Act;
ii.
Failing to consider
the “environmental effects” of the Project as required by s. 16 of the Act;
iii.
Failing to assess the
need for, and alternatives to, the Project as required by the Act and the
Panel’s Terms of Reference;
iv.
Failing to fulfill
its information gathering, public consultation and reporting duties under s. 34
of the CEAA; or
v.
Unlawfully delegating
its duties under the Act?
(b)
Did the Panel fail to
comply with the requirements of the CEAA and the NSCA in issuing the Licence
by:
i.
Failing to ensure
that an environmental assessment compliant with the CEAA was conducted prior to
issuing the Licence; or
ii.
Failing to comply
with s. 24(4) of the NSCA by considering and granting the Licence in the
absence of information specifically required by the relevant regulations?
(c)
Did the Panel breach
a duty of procedural fairness by preventing effective public participation in the
joint review through its procedural rulings, or by relying on extraneous
evidence in granting the Licence?
[20]
The Supreme Court of
Canada in Dunsmuir v New Brunswick, 2008 SCC 9 [Dunsmuir] held
that a standard of review analysis need not be conducted in every instance.
Instead, where the standard of review applicable to a particular question
before the court is settled in a satisfactory manner by past jurisprudence, the
reviewing court may adopt that standard of review. Only where this search
proves fruitless, or where the relevant precedents appear to be inconsistent
with new developments in the common law principles of judicial review, must the
reviewing court undertake a consideration of the four factors comprising the
standard of review analysis: Agraira v Canada (Public Safety and Emergency
Preparedness), 2013 SCC 36 at para 48.
[21]
There is no dispute
that issues of procedural fairness are reviewable on a standard of correctness:
see Mission Institution v Khela, 2014 SCC 24 at para 79; Canadian
Union of Public Employees (C.U.P.E.) v Ontario (Minister of Labour), 2003
SCC 29 at para 100; Sketchley v Canada (Attorney General), 2005 FCA 404
at para 53.
[22]
The Applicants submit
that failure to comply with a mandatory requirement of the CEAA is an error of
law reviewable on the correctness standard, and that this standard applies to
the question of whether the Panel in this case met its legal duties under the
Act: MiningWatch Canada v Canada (Minister of Fisheries and Oceans),
2007 FC 955 at paras 135-37 [MiningWatch (FC)], rev’d 2008 FCA 209,
rev’d 2010 SCC 2; Pembina Institute for Appropriate Development v Canada
(Attorney General), 2008 FC 302 at paras 37, 41 [Pembina Institute];
Alberta Wilderness Assn v Cardinal River Coals Ltd, [1999] 3 FC 425 (TD)
at paras 39-41 [Cardinal River Coals]; Friends of the West Country
Assn v Canada (Minister of Fisheries and Oceans), [2000] 2 FC 263 (FCA) at
para 25 [Friends of the West Country]; Prairie Acid Rain Coalition v
Canada (Minister of Fisheries and Oceans), 2006 FCA 31 at paras 9-12; Environmental
Resource Centre v Canada (Minister of the Environment), 2001 FCT 1423, [2001]
FCJ No 1937 (TD) at paras 154-59 [Environmental Resource Centre]; Georgia
Straight Alliance v Canada (Minister of Fisheries and Oceans) (sub nom Canada
(Fisheries and Oceans) v David Suzuki Foundation), 2012 FCA 40 at paras
88-90, 96-106 [David Suzuki].
[23]
The Respondents argue
that, in substance, the Applicants are attacking the adequacy or “quality” of
the evidence and the reasonableness of the conclusions based upon it, and the
Court has cautioned against mis-characterizing such matters as issues of
failing to comply with the requirements of the Act: Pembina Institute,
above, at paras 38-40. They note that the Panel’s consideration of the evidence,
including conclusions about its adequacy or the significance of environmental
effects, are to be reviewed on a reasonableness standard: Pembina Institute,
above, at para 37; Bow Valley Naturalists Society v Canada(Minister of
Canadian Heritage), [2001] 2 FC 461 (FCA) at para 55 [Bow Valley]; Inverhuron
& District Ratepayers’ Assn v Canada (Minister of the Environment),
2001 FCA 203 at paras 32-40 [Inverhuron (FCA)]; Alberta Wilderness
Assn v Express Pipelines Ltd (1996), 137 DLR (4th) 177, [1996]
FCJ No 1016 (FCA) at para 10 [Express Pipelines]. They argue that the
same is true with respect to questions of whether the Panel properly considered
the need for, and alternatives to, the Project: Grand Riverkeeper, Labrador
Inc v Canada (Attorney General), 2012 FC 1520 at paras 27-40 [Grand
Riverkeeper]. The Respondents point out that, while courts must ensure that
the requirements of the CEAA are followed, they must defer to substantive
determinations. A reviewing court is not to act as an “academy of science.”
Provided the statutory steps are followed, it is not for judges to decide what
projects should be authorized: Inverhuron (FCA), above, at para 36,
citing Bow Valley, above.
[24]
In addition, based on
recent developments in the law on judicial review, the Respondents argue that, even
in respect of many questions of law, the Panel’s findings are entitled to
deference: Canada (Canadian Human Rights Commission) v Canada (Attorney
General), 2011 SCC 53 at para 24; Alberta (Information and Privacy Commissioner)
v Alberta Teachers’ Association, 2011 SCC 61 at paras 33-34 [Alberta
Teachers]. Similarly, they note that this Court has established in the
context of a licence renewal application that the CNSC’s interpretation and
application of the NSCA is to be reviewed on a standard of reasonableness: Fond
du Lac Denesuline First Nation v Canada (Attorney General), 2010 FC 948 at
para 42, aff’d 2012 FCA 73 [Fond du Lac].
[25]
It is true that prior
to Dunsmuir, above, this Court and the Court of Appeal consistently
applied a standard of correctness when reviewing a review panel or other
administrative decision-maker’s interpretation of the CEAA and their duties
under that Act (Cardinal River Coals, above; Friends of the West
Country, above; Bow Valley, above, at para 55; Environmental
Resource Centre, above, at paras 138, 154; Pembina Institute, above,
at paras 37, 41), and applied a standard or reasonableness when reviewing a
panel’s weighing of the evidence and substantive conclusions based on the
evidence, such as whether a project is likely to cause significant adverse
environmental effects (Bow Valley, above, at para 55; Inverhuron (FCA),
above, at paras 39-40; Pembina Institute, above, at para 37). Thus, for
example, interpreting the duty to consider the factors set out in s. 16 (Environmental
Resource Centre, above, at paras 138, 152-154) and the statutory
information gathering and reporting duties of a review panel set out in ss. 34(a)
and (c) (Cardinal River Coals, above, at para 26) were seen as questions
of law reviewable on a standard of correctness.
[26]
In practice, it
sometimes proved difficult to discern the difference between questions engaging
a panel or decision-maker’s interpretation of their duties under the CEAA on
the one hand, and questions of the sufficiency or quality of the evidence
before the decision-maker on the other (see Cardinal River Coals, above,
at para 24; Pembina Institute, above, at para 39; Express Pipelines,
above, at para 10). This is not surprising, since fulfilling a duty to “consider,”
to obtain “the information required,” or to prepare a report setting out one’s
“rationale, conclusions and recommendations” is always a matter of degree; one
could always go further in considering factors, gathering information, or
setting out the rationale for one’s conclusions.
[27]
The post-Dunsmuir
jurisprudence tends to reflect an appreciation of this fact. I do not doubt
that there is an element of statutory interpretation involved in determining
how far to go in gathering information, considering a particular factor, or
reporting on one’s rationale, conclusions and recommendations. But this is
also a matter of judgment based on the facts and circumstances of each
particular case, and is a question upon which a review panel can be expected to
bring its experience and expertise to bear: see Grand Riverkeeper,
above, at paras 35-40; Conseil des Innus de Ekuanitshit v Canada (Attorney
General), 2013 FC 418 at paras 69-71 [Conseil des Innus de Ekuanitshit];
Canadian Transit Co v Canada (Minister of Transport), 2011 FC 515 at
paras 83-86, aff’d 2012 FCA 70 [Canadian Transit]. This is in keeping
with the now firmly established principle that an administrative decision-maker
interpreting its home statute or a closely related statute is entitled to
deference: see McLean v British Columbia (Securities
Commission), 2013 SCC 67, [2013] 3 S.C.R. 895 at paras
21-22 [McLean]; Alberta Teachers, above, at para. 34; Dunsmuir,
above, at para 54. The
Federal Court of Appeal has recently confirmed that the principle from David
Suzuki, above, holding that this presumption of deference does not apply in
the same manner to non-adjudicative decision-makers, has been superseded by later
Supreme Court jurisprudence: see Kandola v Canada (Minister of Citizenship
and Immigration), 2014 FCA 85 at paras 30-42 (per Noel JA, Webb JA
concurring) and para 86 (per Mainville JA).
[28]
It may be that
questions of law could arise under the CEAA or its successor legislation in
relation to which, based on a contextual analysis, the presumption of reasonableness
review would be rebutted and a standard of correctness would apply: see McLean,
above, at para 22; Rogers Communications Inc v Society of Composers, Authors
and Music Publishers of Canada, 2012 SCC 35, [2012] 2 S.C.R. 283, at para. 16;
Dunsmuir, above, at paras 58-61. However, I do not think any such
questions arise here. While there is an element of statutory interpretation
involved in answering issues a. i. through a. v, each is also a question of
mixed fact and law that engages the expertise and judgment of the Panel. As
such, in my view, each of these issues is reviewable on a standard of
reasonableness.
[29]
Similarly, as I found
in Fond du Lac, above, at para 42, “reasonableness is the appropriate
standard upon which to review the [CNSC’s] interpretation and application of
the [NSCA]” in the course of its licensing decisions. As such, a standard of
reasonableness applies in reviewing the Panel’s (functioning as the Commission)
decision to issue the Site Preparation Licence in this case, including issues
b. i. and b. ii. above.
[30]
For clarity, I would
note that because the CEAA sets out specific duties and responsibilities for a
review panel, a reviewing court must go beyond assessing whether a panel came
to a reasonable conclusion. The Court must have regard for the duties set out
in the Act, and ensure that the panel has complied with them. However, in
doing so, a degree of deference is owed to the panel’s judgment in terms of how
to fulfill those responsibilities in a given case. They are duties that must
be interpreted and carried out reasonably in the circumstances: see Grand
Riverkeeper, above, at para 62.
[31]
When reviewing a
decision on the standard of reasonableness, the analysis will be concerned with
“the existence of justification, transparency and intelligibility within the
decision-making process [and also with] whether the decision falls within a
range of possible, acceptable outcomes which are defensible in respect of the
facts and law.” See Dunsmuir, above, at para 47, and Canada (Citizenship and Immigration) v Khosa, 2009 SCC 12 at para 59 [Khosa].
Put another way, the Court should intervene only if the Decision was
unreasonable in the sense that it falls outside the “range of possible,
acceptable outcomes which are defensible in respect of the facts and law.”
[32]
The following
provisions of the CEAA are applicable in these proceedings:
Purposes
4. (1) The
purposes of this Act are
(a) to ensure
that projects are considered in a careful and precautionary manner before
federal authorities take action in connection with them, in order to ensure
that such projects do not cause significant adverse environmental effects;
(b) to
encourage responsible authorities to take actions that promote sustainable
development and thereby achieve or maintain a healthy environment and a
healthy economy;
[…]
(d) to ensure
that there be opportunities for timely and meaningful public participation
throughout the environmental assessment process.
[…]
Duties of
the Government of Canada
(2) In the
administration of this Act, the Government of Canada, the Minister, the
Agency and all bodies subject to the provisions of this Act, including
federal authorities and responsible authorities, shall exercise their powers
in a manner that protects the environment and human health and applies the
precautionary principle.
[…]
Factors to
be considered
16. (1) Every
screening or comprehensive study of a project and every mediation or
assessment by a review panel shall include a consideration of the following
factors:
(a) the
environmental effects of the project, including the environmental effects of
malfunctions or accidents that may occur in connection with the project and
any cumulative environmental effects that are likely to result from the
project in combination with other projects or activities that have been or
will be carried out;
(b) the
significance of the effects referred to in paragraph (a);
(c) comments
from the public that are received in accordance with this Act and the regulations;
(d) measures
that are technically and economically feasible and that would mitigate any
significant adverse environmental effects of the project; and
(e) any other
matter relevant to the screening, comprehensive study, mediation or
assessment by a review panel, such as the need for the project and
alternatives to the project, that the responsible authority or, except in the
case of a screening, the Minister after consulting with the responsible
authority, may require to be considered.
Additional
factors
(2) In
addition to the factors set out in subsection (1), every comprehensive study
of a project and every mediation or assessment by a review panel shall
include a consideration of the following factors:
(a) the
purpose of the project;
(b) alternative
means of carrying out the project that are technically and economically
feasible and the environmental effects of any such alternative means;
(c) the need
for, and the requirements of, any follow-up program in respect of the
project; and
(d) the capacity
of renewable resources that are likely to be significantly affected by the
project to meet the needs of the present and those of the future.
Determination
of factors
(3) The scope
of the factors to be taken into consideration pursuant to paragraphs (1)(a),
(b) and (d) and (2)(b), (c) and (d) shall be determined
(a) by the
responsible authority; or
(b) where a
project is referred to a mediator or a review panel, by the Minister, after
consulting the responsible authority, when fixing the terms of reference of
the mediation or review panel.
[…]
Assessment
by review panel
34. A review
panel shall, in accordance with any regulations made for that purpose and
with its term of reference,
(a) ensure
that the information required for an assessment by a review panel is obtained
and made available to the public;
(b) hold
hearings in a manner that offers the public an opportunity to participate in
the assessment;
(c) prepare a
report setting out
(i) the rationale, conclusions and
recommendations of the panel relating to the environmental assessment of the
project, including any mitigation measures and follow-up program, and
(ii) a summary of any comments received
from the public; and
(d) submit the
report to the Minister and the responsible authority.
|
Objet
4. (1) La
présente loi a pour objet :
a) de veiller
à ce que les projets soient étudiés avec soin et prudence avant que les
autorités fédérales prennent des mesures à leur égard, afin qu’ils
n’entraînent pas d’effets environnementaux négatifs importants;
b) d’inciter
ces autorités à favoriser un développement durable propice à la salubrité de
l’environnement et à la santé de l’économie;
[…]
d) de veiller
à ce que le public ait la possibilité de participer de façon significative et
en temps opportun au processus de l’évaluation environnementale.
[…]
Mission du
gouvernement du Canada
(2) Pour
l’application de la présente loi, le gouvernement du Canada, le ministre,
l’Agence et les organismes assujettis aux dispositions de celle-ci, y compris
les autorités fédérales et les autorités responsables, doivent exercer leurs
pouvoirs de manière à protéger l’environnement et la santé humaine et à
appliquer le principe de la prudence.
[…]
Éléments à
examiner
16. (1)
L’examen préalable, l’étude approfondie, la médiation ou l’examen par une
commission d’un projet portent notamment sur les éléments suivants :
a) les effets
environnementaux du projet, y compris ceux causés par les accidents ou
défaillances pouvant en résulter, et les effets cumulatifs que sa
réalisation, combinée à l’existence d’autres ouvrages ou à la réalisation
d’autres projets ou activités, est susceptible de causer à l’environnement;
b)
l’importance des effets visés à l’alinéa a);
c) les
observations du public à cet égard, reçues conformément à la présente loi et
aux règlements;
d) les mesures
d’atténuation réalisables, sur les plans technique et économique, des effets
environnementaux importants du projet;
e) tout autre
élément utile à l’examen préalable, à l’étude approfondie, à la médiation ou
à l’examen par une commission, notamment la nécessité du projet et ses
solutions de rechange, — dont l’autorité responsable ou, sauf dans le cas
d’un examen préalable, le ministre, après consultation de celle-ci, peut
exiger la prise en compte.
Éléments
supplémentaires
(2) L’étude
approfondie d’un projet et l’évaluation environnementale qui fait l’objet
d’une médiation ou d’un examen par une commission portent également sur les
éléments suivants :
a) les raisons
d’être du projet;
b) les
solutions de rechange réalisables sur les plans technique et économique, et
leurs effets environnementaux;
c) la
nécessité d’un programme de suivi du projet, ainsi que ses modalités;
d) la capacité
des ressources renouvelables, risquant d’être touchées de façon importante
par le projet, de répondre aux besoins du présent et à ceux des générations
futures.
Obligations
(3)
L’évaluation de la portée des éléments visés aux alinéas (1)a), b) et d) et
(2)b), c) et d) incombe :
a) à
l’autorité responsable;
b) au
ministre, après consultation de l’autorité responsable, lors de la
détermination du mandat du médiateur ou de la commission d’examen.
[…]
Commission
d’évaluation environnementale
34. La
commission, conformément à son mandat et aux règlements pris à cette fin :
a) veille à
l’obtention des renseignements nécessaires à l’évaluation environnementale
d’un projet et veille à ce que le public y ait accès;
b) tient des
audiences de façon à donner au public la possibilité de participer à l’évaluation
environnementale du projet;
c) établit un
rapport assorti de sa justification, de ses conclusions et recommandations
relativement à l’évaluation
environnementale
du projet, notamment aux mesures d’atténuation et au programme de suivi, et
énonçant, sous la forme d’un résumé, les observations reçues du public;
d) présente
son rapport au ministre et à l’autorité responsable.
|
[33]
The following
provisions of the NSCA are applicable in these proceedings:
Licences
24. (1) The
Commission may establish classes of licences authorizing the licensee to
carry on any activity described in any of paragraphs 26(a) to (f) that is
specified in the licence for the period that is specified in the licence.
[…]
Conditions
for issuance, etc.
(4) No licence
shall be issued, renewed, amended or replaced — and no authorization to
transfer one given — unless, in the opinion of the Commission, the applicant
or, in the case of an application for an authorization to transfer the
licence, the transferee
(a) is qualified
to carry on the activity that the licence will authorize the licensee to
carry on; and
(b) will, in
carrying on that activity, make adequate provision for the protection of the
environment, the health and safety of persons and the maintenance of national
security and measures required to implement international obligations to
which Canada has agreed.
[…]
|
Catégories
24. (1) La
Commission peut établir plusieurs catégories de licences et de permis; chaque
licence ou permis autorise le titulaire à exercer celles des activités
décrites aux alinéas 26a) à f) que la licence ou le permis mentionne, pendant
la durée qui y est également mentionnée.
[…]
Conditions
préalables à la délivrance
(4) La
Commission ne délivre, ne renouvelle, ne modifie ou ne remplace une licence
ou un permis ou n’en autorise le transfert que si elle est d’avis que
l’auteur de la demande ou, s’il s’agit d’une demande d’autorisation de
transfert, le cessionnaire, à la fois :
a) est
compétent pour exercer les activités visées par la licence ou le permis;
b) prendra,
dans le cadre de ces activités, les mesures voulues pour préserver la santé
et la sécurité des personnes, pour protéger l’environnement, pour maintenir
la sécurité nationale et pour respecter les obligations internationales que
le Canada a assumées.
[…]
|
[34]
The following
provisions of the Class I Nuclear Facilities Regulations, SOR/2000-204 (Regulations)
are applicable in these proceedings:
General
Requirements
3. An
application for a licence in respect of a Class I nuclear facility, other
than a licence to abandon, shall contain the following information in
addition to the information required by section 3 of the General Nuclear
Safety and Control Regulations:
(a) a
description of the site of the activity to be licensed, including the
location of any exclusion zone and any structures within that zone;
(b) plans
showing the location, perimeter, areas, structures and systems of the nuclear
facility;
(c) evidence
that the applicant is the owner of the site or has authority from the owner
of the site to carry on the activity to be licensed;
(d) the
proposed quality assurance program for the activity to be licensed;
(e) the name,
form, characteristics and quantity of any hazardous substances that may be on
the site while the activity to be licensed is carried on;
(f) the
proposed worker health and safety policies and procedures;
(g) the
proposed environmental protection policies and procedures;
(h) the
proposed effluent and environmental monitoring programs;
(i) if the
application is in respect of a nuclear facility referred to in paragraph 2(b)
of the Nuclear Security Regulations, the information required by section 3 of
those Regulations;
(j) the
proposed program to inform persons living in the vicinity of the site of the
general nature and characteristics of the anticipated effects on the
environment and the health and safety of persons that may result from the
activity to be licensed; and
(k) the
proposed plan for the decommissioning of the nuclear facility or of the site.
Licence to
Prepare Site
4. An
application for a licence to prepare a site for a Class I nuclear facility
shall contain the following information in addition to the information
required by section 3:
(a) a
description of the site evaluation process and of the investigations and
preparatory work that have been and will be done on the site and in the
surrounding area;
(b) a
description of the site's susceptibility to human activity and natural
phenomena, including seismic events, tornadoes and floods;
(c) the
proposed program to determine the environmental baseline characteristics of
the site and the surrounding area;
(d) the
proposed quality assurance program for the design of the nuclear facility;
and
(e) the
effects on the environment and the health and safety of persons that may
result from the activity to be licensed, and the measures that will be taken
to prevent or mitigate those effects.
[…]
|
Dispositions
générales
3. La demande
de permis visant une installation nucléaire de catégorie I, autre qu'un
permis d'abandon, comprend les renseignements suivants, outre ceux exigés à
l'article 3 du Règlement général sur la sûreté et la réglementation
nucléaires:
a) une
description de l'emplacement de l'activité visée par la demande, y compris
l'emplacement de toute zone d'exclusion et de toute structure s'y trouvant;
b) des plans
indiquant l'emplacement, le périmètre, les aires, les ouvrages et les
systèmes de l'installation nucléaire;
c) la preuve
que le demandeur est le propriétaire de l'emplacement ou qu'il est mandaté
par celui-ci pour exercer l'activité visée;
d) le
programme proposé d'assurance de la qualité proposé pour l'activité visée;
e) le nom, la
forme, les caractéristiques et la quantité des substances dangereuses qui pourraient
se trouver sur l'emplacement pendant le déroulement de l'activité visée;
f) les
politiques et procédures proposées relativement à la santé et à la sécurité
des travailleurs;
g) les
politiques et procédures proposées relativement à la protection de
l'environnement;
h) les
programmes proposés pour la surveillance de l'environnement et des effluents;
i) lorsque la
demande vise une installation nucléaire mentionnée à l'alinéa 2b) du
Règlement sur la sécurité nucléaire, les renseignements exigés à l'article 3
de ce règlement;
j) le
programme destiné à informer les personnes qui résident à proximité de
l'emplacement de la nature et des caractéristiques générales des effets
prévus de l'activité visée sur l'environnement ainsi que sur la santé et la
sécurité des personnes;
k) le plan
proposé pour le déclassement de l'installation nucléaire ou de l'emplacement.
Permis de
préparation de l'emplacement
4. La demande
de permis pour préparer l'emplacement d'une installation nucléaire de
catégorie I comprend les renseignements suivants, outre ceux exigés à
l'article 3 :
a) une
description du processus d'évaluation de l'emplacement, ainsi que des
analyses et des travaux préalables qui ont été et seront effectués sur
l'emplacement et dans les environs;
b) une
description de la vulnérabilité de l'emplacement aux activités humaines et
aux phénomènes naturels, y compris les secousses sismiques, les tornades et
les inondations;
c) le
programme devant servir à déterminer les caractéristiques environnementales
de base de l'emplacement et des environs;
d) le
programme d'assurance de la qualité proposé pour la conception de
l'installation nucléaire;
e) les effets
sur l'environnement ainsi que sur la santé et la sécurité des personnes que
peut avoir l'activité visée par la demande, de même que les mesures qui
seront prises pour éviter ou atténuer ces effets.
[…]
|
[35]
The Applicants
challenge the EA on a number of grounds. Their overall position is that in
conducting the EA, the Panel failed to comply with the mandatory requirements of
the CEAA and the Panel’s own Terms of Reference. They say that, as a matter of
law, the Panel failed to conduct an EA of a “project” within the meaning of the
CEAA, and failed to consider the mandatory factors set out in s. 16 of the Act
and the Terms of Reference. In addition, they say the Panel failed to comply
with the legal duties imposed by s. 34 of the Act in relation to
information-gathering, public participation and reporting, and unlawfully
attempted to defer or delegate its s. 34 duties to other entities and agencies.
The Applicants ask that the Court remit the EA back to the Panel for further
consideration in accordance with the legal requirements of the CEAA.
[36]
The Applicants contend
that the overall aim of the CEAA is to achieve sustainable development by
integrating environmental considerations into federal governmental
decision-making about projects. They characterize the Act as the federal “look
before you leap” law, noting that s. 4(1) requires “careful and precautionary”
consideration of projects and timely and meaningful public participation
throughout the EA process, and s. 4(2) imposes a positive legal duty upon “all
bodies subject to the provisions of this Act” to “exercise their powers in a
manner that protects the environment and human health and applies the
precautionary principle.”
[37]
The Applicants note
that the Supreme Court of Canada has endorsed the precautionary principle (R
v Hydro Quebec, [1997] 3 S.C.R. 213 at para 86; 114957 Canada Ltée
(Spraytech, Société d’arrosage) v Hudson (Town), 2001 SCC 40 at para 31 [Spraytech];
Sierra Club of Canada v Canada (Minister of Finance), 2002 SCC 41 at
para 84). Moreover, the Federal Court of Appeal has held that “the
precautionary principle states that a project should not be undertaken if it may
have serious adverse environmental consequences, even if it is not possible to
prove with any degree of certainty that these consequences will in fact
materialize” (emphasis added): Canadian Parks and Wilderness Society v
Canada (Minister of Canadian Heritage), 2003 FCA 197 at para 24 [Parks
and Wilderness Society]; see also Pembina Institute, above, at paras
29-31. In the Applicants’ view, the approach taken by the Panel in this case
amounts to a “leap before you look” approach.
[38]
The Applicants argue
that it was not possible to conduct an EA that met the requirements of the CEAA
when the reactor technology had not been chosen and other key Project
components, such as the site design layout, cooling system option, used nuclear
fuel storage option, and radioactive waste management option, remained
unspecified. Although s. 11(1) of the Act provides that an EA is to be
conducted as early as practicable in the planning stages of a project and
before irrevocable decisions are made, the EA must also be conducted at a stage
when it is possible to fully consider and determine whether the project may
cause adverse environmental effects: Friends of the Island Inc v Canada (Minister
of Public Works), [1993] 2 FC 229 at paras 41, 47, 53-54, 99 [Friends of
the Island].
[39]
While the Project
will require additional licences under the NSCA, the Applicants note that the
federal EA at issue here is the only EA that will be carried out for the
Project as a whole. Contrary to the Respondents’ characterization of environmental
assessment as an information-gathering and planning tool, the Applicants cite Friends
of the Oldman River Society v Canada (Minister of Transport), [1992] 1 SCR
3 at para 103 [Oldman River] for the proposition that it has “both
information-gathering and decision-making” components and provides
decision-makers “with an objective basis for granting or denying approval for a
proposed development.”
[40]
The Applicants take
issue in particular with the use of the “bounding scenario” or PPE approach
described above in conducting the EA. They argue, first, that this has the
consequence that the Panel did not review a “project” within the meaning of the
CEAA, because the specific nature of the physical work to be undertaken was not
identified. In the alternative, even if the proposal reviewed was a “project,”
the adoption of the bounding scenario approach prevented the Panel from
assessing the environmental effects of the Project as required by the CEAA.
[41]
Since it is “projects”
that must undergo EAs, the Applicants argue that the term is central to the
statutory scheme. Subsection 2(1) of the Act defines a “project” as either: (a)
an undertaking in relation to a physical work; or (b) an activity listed in the
Inclusion List Regulations. Here, it is the first branch of the
definition that is relevant. The Applicants say that, in order to be assessed
under this branch, the Project must: (a) be a physical activity by humans; (b)
be in the proposal stage and prior to construction actually starting; and (c)
have identifiable, concrete characteristics and results: Bennett
Environmental Inc v Canada (Minister of the Environment), 2005 FCA 261 at
para 77 [Bennett Environmental]; Canadian Transit, above.
[42]
In order for there to
be a “project,” the Applicants say, a proponent must have identified the
specific nature of the proposed physical work from start to finish, including the
preferred means of carrying it out. This is in contrast to plans, policies and
programs, which are broader and more vague and involve “various processes of
reforming, adding, and subtracting different elements”: Canadian Transit,
above, at paras 34-35; Stephen Hazell and Hugh Benevides, Federal Strategic Environmental
Assessment: Towards A Legal Framework, (1998) 7 JELP 349 at 371. When a
proponent is still considering alternative means to carry out a project, there
is not yet a specific “physical work” that can be practicably assessed in terms
of its environmental effects. The point of the CEAA is not to assess a
conceptual collection of options and alternatives, but to assess a specific
project, described with a level of detail that permits meaningful review of
potential environmental effects: Friends of the Island, above, at paras
41, 53, 99; Canadian Transit, above, at paras 53, 54, 139, 141. As the
Court noted in Friends of the Island at para 53: “Public hearings on a
generic proposal are not a substitute for a specific evaluation of the actual
project which is planned to construct.”
[43]
In this case, the
Applicants say, the EA was supposed to carefully assess the construction,
operation and decommissioning of an identifiable new nuclear power plant.
Instead, they argue, the EA Report defers or delegates the evaluation of a
specific reactor design to bodies other than the Panel. OPG presented, and the
Panel assessed, an over-generalized collection of conceptual options and vague
site development choices to be made in the post-EA period, without further
assessment under the CEAA. This amounts to a plan rather than a project. The Applicants
note that the Panel itself found that key information about the Project was
absent.
[44]
The Applicants
contend that by conducting an EA when the main components of the proposal
remained at a conceptual level, the Panel and the public were prevented from
meaningfully assessing the Project’s specific environmental effects. Federal
decision-makers still do not know: a) the particulars of the specific project
to be implemented at the Darlington site; b) the full range of site-specific or
cumulative environmental effects; or c) whether there are feasible mitigation
measures over the Project’s full lifecycle. The Panel’s approach, and its
conclusion that no significant environmental effects are likely – provided that
sizeable information gaps are eventually addressed by other bodies and numerous
to-be-determined mitigation measures are implemented – is the antithesis of the
precautionary principle enshrined in s. 4(2) of the Act and endorsed by the
Supreme Court of Canada.
[45]
Even if there was a
“project” within the meaning of the CEAA, the Applicants argue, it was an error
for the Panel to accept and apply the bounding approach, and this error
resulted in a failure to fully assess the environmental effects of the Project
as required by ss. 15(3), 16(1) and (2), and 34(a) and (b) of the CEAA. Subsection
15(3) imposes a mandatory duty to subject all components of the “physical work”
to EA scrutiny. Subsections 16(1) and (2) set out mandatory factors that must
be considered in relation to these components, including their environmental
effects: MiningWatch (FC), above, at para 39; Friends of the West
Country, above, at para 25; Pembina Institute, above, at paras 21,
33. Subsections 34(a) and (b) impose obligations on the Panel to gather,
disclose and hold public hearings on the information required for an assessment
of the factors set out in s. 16 of the Act and the Terms of Reference. This is
a non-delegable duty that does not depend upon the success or failure of the
proponent, public agencies or interveners to produce information: Cardinal
River Coals, above, at paras 39-41. Not only was the use of the bounding
approach in the present case a “departure” from the normal EA process, as
acknowledged by the Panel, it resulted in a fundamental failure to fulfill the
above-noted duties under the Act.
[46]
The Applicants argue
that s. 16 of the Act requires the Panel to first describe the environmental
effects associated with various aspects of the Project, and then make findings
about the significance of those effects, taking into account mitigation
measures that are technically and economically feasible: Cardinal River
Coals, above, at paras 54-56. The use of the bounding approach, and the
failure to assess a specific reactor technology, undermined the Panel’s ability
to properly evaluate the Project’s environmental effects. The Applicants point
in particular to the following findings and observations in the EA Report:
The Panel found that the assessment of potential environmental effects was
qualitative in many respects because it was conducted without specific
knowledge of potential releases. OPG explained that certain parameters of the
bounding scenario, such as hazardous substance emissions and on-site chemical
inventories, could not be developed until a specific reactor technology has
been selected by the Government of Ontario. (page 39)
[…]
In the absence of a choice of reactor technology for the Project, OPG did
not undertake a detailed assessment of the effects of liquid effluent and
stormwater runoff to the surface water environment. Instead, the proponent
committed to managing liquid effluent releases in compliance with applicable
regulatory requirements and to applying best management practices for stormwater.
(page 65)
[…]
In response to a Panel request for information on stored inventories of
hazardous materials and sources, types and quantities of non-radioactive wastes
predicted to be generated by the Project, OPG indicated that specific details
regarding the chemicals to be stored and used on the site could not be provided
before a reactor technology is selected for the Project. (page 78)
[…]
The Panel accepts the adoption of a safety goal-based approach for the
assessment of the consequences of an accident in a situation where there has
not been a choice of reactor technology. The Panel notes, however, that once
this choice has been made, the proponent must be required to complete an
assessment of the offsite effects of a severe accident that could arise for the
chosen technology. (page 124)
[47]
The Applicants argue
that, in light of these and other gaps in information, the Panel failed to meet
its obligations under s. 16 of the Act. They say that the environmental effects
of the following components of the Project were not fully assessed by the
Panel:
(a)
Specific reactor
technology;
(b)
Specific site design
layout;
(c)
Specific water
cooling option;
(d)
Specific used nuclear
fuel storage option; and
(e)
Long-term radioactive
waste management option.
[48]
With respect to the
decommissioning of the site and long-term management of nuclear waste, the
Applicants argue that the Panel accepted an optimistic and non-precautionary
prediction from OPG that “effective and practical mitigation options would be
available when required in the future,” contrary to this Court’s previous
direction that “vague hopes for future technology” or “the possibilities of
future research and development” do not constitute proper mitigation measures
under the CEAA: Pembina Institute, above, at paras 25-26, 69. The Panel
acknowledged that there were a number of information gaps with respect to
long-term radioactive waste management, but rather than requiring OPG to
provide the necessary information, the Panel merely recommended that future
study and analysis be conducted. In doing so, the Panel failed to consider
whether the radioactive waste from the Project will have significant adverse
effects, and whether there are any technically and economically feasible
measures which would mitigate them. There was no factual basis for its
conclusion that “radioactive and used fuel waste is not likely to result in
significant adverse environmental effects.”
[49]
According to the
Applicants, s. 34(a) and (b) of the Act do not permit the Panel to identify
missing information and then simply recommend future studies and information
gathering to address these gaps after the EA has concluded. Parliament clearly
intended that these steps take place, and be subject to public involvement, as
part of the EA process itself: Cardinal River Coals, above, at paras
39-41. Unless and until these evidentiary gaps are filled, the Panel has not
conducted an EA in accordance with the Act, and has not provided federal
decision-makers with the evidentiary basis required to make an informed
decision. The Panel therefore lacked the necessary jurisdiction under s. 34(c)(i)
to make any recommendations to the Minister: Cardinal River Coals,
above, at paras 40-41, 43, 51; Alberta Wilderness Assn v Canada (Minister of Fisheries and Oceans), [1999] 1 FC 483 at paras 17-21.
[50]
The Panel also failed
to properly consider cumulative effects as required by s. 16(1)(a) of the Act,
especially in view of OPG’s intention to refurbish the existing reactor units
at Darlington NGS. The Panel should have addressed the likelihood and
significance of cumulative effects from the new and existing units at Darlington, including the effects of a severe “common cause” accident at the site: Bow
Valley, above.
[51]
The Applicants further
argue that the Panel failed to properly consider the “need” for, and
“alternatives” to, the Project. Paragraph 16(1)(e) of the Act allows the
Minister to decide that these factors must be considered and, in this case, the
Minister included them in the Terms of Reference. At best, the Panel gave these
factors short shrift, simply accepting OPG’s statement in the EIS that the need
for the Project was to fulfill a Directive of the Ontario Minister of Energy to
seek federal approval of new nuclear reactors. As a matter of law, the
Applicants say, a provincial Minister or project proponent cannot bind the
Panel in the exercise of its statutory responsibilities, and the Panel
effectively declined its jurisdiction by treating the Directive as dispositive
of the issue of the “need” for the Project: Innisfil (Township) v Vespra
(Township), [1981] 2 S.C.R. 145 at 173.
[52]
Where a project poses
environmental risks, the Applicants say, the proponent must present detailed
evidence and analysis demonstrating that it is actually needed: West
Northumberland Landfill Site (Re) (1996), 19 CELR (NS) 181 (Ont Jt Bd) at
paras 88, 90; Canadian Transit, above, at paras 5, 27-28, 78, 111,
115-18. The Panel should have identified the functional purpose of the Project
– supplying a portion of “base load” electricity for Ontario – and should have considered
the need for and alternatives to the Project from that perspective. Instead,
the Panel erroneously concluded that these were issues of provincial energy
policy that were better left to future hearings before the Ontario Energy
Board. The only evidence on the actual need for the Project was a brief and
untested overview from the provincial Ministry of Energy, provided after the
hearings concluded and without an opportunity for the Applicants to file
responding evidence, contrary to the audi alteram partem principle.
[53]
The Applicants argue
that the alleged problems with the EA outlined above were compounded by
procedural errors, including the Panel’s refusal to: a) extend the public
comment period on the EIS to allow the addition of the EC-6 design to be more
fully addressed; b) allow cross-examination on evidence or answers to
undertakings; or c) adjourn the public hearing so that gaps in the evidence
could be filled and the relevant information publicly disclosed and carefully
assessed by the Panel.
[54]
These allegations are
closely related to the Panel’s rulings on a series of preliminary objections
raised by the Applicants on the first day of the public hearings, with prior
notice to the Panel that they would be raised. The Panel rejected each of these
objections, first orally and then in written reasons which are attached to the
EA Report as Appendix 3 (EA Report at pp. 163-168).
[55]
The Applicants say
that just before the close of the pre-hearing public comment period on the EIS,
they learned that the EC-6 reactor technology would be added as a fourth option
to be assessed within the EA. Since in their view this technology poses health
and environmental risks that significantly differ from those arising from the
three reactor designs addressed in the EIS, the Applicants objected to its late
inclusion on fairness and other grounds. They argued that the EA process
should be restarted or the deadlines for comments extended if the EC-6 design
were to be included in the EA. The Panel rejected this argument, finding that
the EA was intended from the beginning to be “technology neutral,” and it had
been known from the beginning that it would follow a plant parameter approach that
would not exclude the eventual selection of technologies not included in the
proposal or the EIS. The consideration of additional technologies such as the
EC-6 did not amount to a change in the scope of the Project being considered. The
Panel also found that the Applicants had sufficient time and notice to prepare,
and opportunities for further submissions or additional hearing days would be
provided if required to address this issue. The Applicants argue that this
ruling was in error, and compromised their ability to participate effectively
in the hearings.
[56]
In these same reasons,
the Panel rejected an argument that the hearings should be suspended in light
of the Fukushima Daiichi accident in Japan, which occurred just 10 days before
the start of the hearings, as any EA that did not include lessons learned from
that crisis would be incomplete. The Panel noted that, as fully independent
decision-makers, the Panel members could decide if new information related to
those events was required, and would continue to review the Project until
satisfied that they had all the relevant information for appropriate and
informed decision-making. Similarly, the Panel rejected an objection that
there was insufficient or inadequate information before the Panel on which to base
an EA or a licensing decision, and that the absence of a technology decision
deprived the public of the ability to participate. The Panel found that if it
were able to proceed to the public hearing stage only when it had all the
information required for the EA, this would effectively negate the need for
holding a public hearing. The Panel also rejected a request from the Applicant
Canadian Environmental Law Association (CELA) that the Panel receive
information from OPG and the relevant agencies as sworn evidence, finding that
it was not required to adopt the formal rules of evidence applicable to a civil
or criminal trial. The Applicants argue that these rulings were in error, and
deprived them of the ability to participate effectively in the EA process.
[57]
In addition, the
Applicants argue that after the close of the hearings, the Panel accepted
further evidence from two participants – OPG and the Ontario Ministry of Energy
– to which the Applicants were not provided an opportunity to file responding
evidence. The impugned evidence consists of responses to Undertakings 75 and 76
regarding the need for and alternatives to the Project, which were admitted despite
the objections of the Applicant CELA on procedural fairness grounds. They argue
that this was contrary to the audi alteram partem principle.
[58]
The Applicants argue
that the Panel also violated the well-established administrative law principle
of delgatus non potest delgare, which provides that a body to which a
power is delegated under a statute cannot further delegate that power unless
the statute explicitly or implicitly authorizes it to do so: Sara Blake, Administrative
Law in Canada, 5th ed (Toronto: LexisNexis, 2011) at 143-46. While
review panels do not decide whether projects should be permitted to proceed,
Parliament has entrusted them with the important, non-delegable responsibility
of assessing and reporting upon major projects so that responsible authorities
can make informed EA decisions. Since the Act does not expressly empower review
panels to delegate their obligations under s. 34, they must fully complete
their duties before they can lawfully report to the Minister. While a Panel
might be permitted to leave minor details of confirmation, monitoring or
mitigation for other agencies to deal with where a project has otherwise been
fully assessed, most of the Panel’s recommendations in this case were aimed at
generating critically important information to backfill significant evidentiary
gaps. This level of delegation is not permissible: Environmental Resource
Centre, above, at paras 154-59; Pembina Institute, above, at paras
20, 60-62, 67, 69.
[59]
The Applicants argue
that the CNSC committed three fundamental and reviewable legal errors when it
decided to issue the Licence: 1) it failed to ensure that the mandatory
prerequisites under the CEAA had been satisfied in the EA of the Project before
making its Licence decision; 2) it failed to comply with the mandatory
requirements of the NSCA and the associated Regulations, in that it failed to
make adequate provision for the protection of the environment and the health
and safety of persons. It also failed to ensure that OPG’s application for the
Licence contained required information regarding the environmental and health effects
that may result from the activity to be licensed, as well as the measures that
will be taken to prevent or mitigate those effects; and 3) the Panel breached
its duty of procedural fairness to the interveners who participated in the
public hearings on the Project by relying on extraneous documents not on the
record.
[60]
The first of these
arguments asserts that an EA in conformity with the CEAA is a legal
prerequisite to the issuance of the Licence, and that this prerequisite was not
satisfied in this case. This argument is based on the same errors that were
alleged in relation to the EA Report itself, as outlined above.
[61]
The second argument
asserts that the CNSC failed to fulfill the requirements of s. 24(4) of the
NSCA by failing to subject the Project to scrutiny under the NSCA and its Regulations.
In other words, regardless of the Court’s conclusions regarding the
requirements of the CEAA and whether they were met in the conduct of the EA in
this case, the Applicants argue that s. 24(4) of the NSCA and the associated
Regulations require that a detailed assessment of the Project occur, including
the facility design and reactor technology involved, before a site preparation licence
can lawfully be issued. They base this argument on the language of s. 24(4),
and the requirements set out in ss. 3 and 4 of the Class I Nuclear
Facilities Regulations, set out above, regarding the details that must be
included in a licence application. They argue that since OPG has not identified
a specific reactor technology for the Project, the required information was not
provided and the CNSC lacked jurisdiction to consider the application or grant the
Licence.
[62]
Finally, the
Applicants argue that the Panel breached a duty of fairness by relying upon two
documents generated after the close of public hearings – the Fukushima Task
Force Report, dated October 2011, and the associated CNSC Action Plan, dated
March 2, 2012 - in coming to its decision on the Licence. They argue that the
Panel also relied on documents cited in the CNSC’s Licence Condition Handbook
that existed only in draft form or not at all during the hearings. These
documents were not tendered as exhibits during the public hearings held by the
Panel, and were thus not subject to notice or comment opportunities by the
Applicants or other interveners. Had this been done, the Applicants say they
would have voiced serious concerns regarding the Task Force Report and CNSC
Action Plan and the Panel’s reliance on them, including the continued
inadequacy of the risk assessment performed by OPG and the fact that the Action
Plan could not fill the gaps in Project-specific information left by the EA.
[63]
The Applicants argue
that, based on the factors set out in Baker v Canada (Minister of
Citizenship and Immigration), [1999] 2 S.C.R. 817 [Baker], the decision
to issue the Licence is one that attracts a high degree of procedural fairness.
They say the decision-making process is close to a trial model, in that s.
40(5) of the NSCA mandates public hearings, s. 24(4) requires the Panel to make
many findings of fact, and intervening parties will often invest significant
time and resources: Baker, above, at para 23. Moreover, the statutory
scheme provides no avenue of appeal, and the Licence decision carries great
importance to the Applicants as it constitutes the first step toward
constructing new nuclear reactors on the Darlington site without, in their view,
a valid EA. They say this result is antithetical to their longstanding work in
the area of energy and nuclear power planning and risk management. Further, the
Applicants had a legitimate expectation that only evidence on the public record
would be relied upon because this is the “regular practice of administrative
decision-makers”: Baker, above, at para 26.
[64]
While each of the
Respondents – OPG, the CNSC and the Attorney General of Canada – have filed
separate submissions, there is substantial agreement and overlap among their
positions.
[65]
All of the Respondents
argue that the EA process and Report were fully compliant with the CEAA and
there is no basis upon which the Court should interfere. They say the use of
the “bounding scenario” approach was appropriate, and the Applicants’ argument
that the Panel improperly delegated its authority misunderstands the nature of
environmental assessment, which is fundamentally an information gathering and
planning tool. They note that the Project will be subject to further regulatory
approvals that will involve consideration of environmental effects, including a
requirement for licences from the CNSC at each phase of its development. In
their view, it was appropriate for the Panel to take this full regulatory
context into account in formulating its conclusions and recommendations.
[66]
The Respondents argue
that conducting the EA prior to the selection of a specific reactor technology
is consistent with the requirement to conduct the assessment as early as
practicable in the planning process and before irrevocable decisions are made
(see CEAA, s. 11(1)). In substance, they say, the Applicants are attacking the
Panel’s conclusions about the sufficiency of the evidence, not its compliance
with legal duties under the Act. The Panel’s conclusion that there was
sufficient information to conduct the EA is entitled to deference. Provided the
record contains information on which the Panel could rationally base its
conclusions, the Court should not intervene.
[67]
The Respondents argue
that the decision to proceed with the EA prior to the selection of a reactor
technology and based on the bounding approach was a separate scoping decision made
by the Minister with the release of the EIS Guidelines and the Panel’s Terms of
Reference on March 12, 2009. It was open to the Applicants at
that time to challenge this scoping decision through judicial review, but they
did not do so and the time for such a challenge has long passed: Citizens’
Mining Council of Newfoundland and Labrador Inc v Canada (Minister of the
Environment) (1999), 163 FTR 36 (FC) at paras 47-49; Hamilton-Wentworth
(Regional Municipality) v Canada (Minister of the Environment), 2001 FCT
381 at para 60, aff’d 2001 FCA 347; City of Ottawa v Canada (Human Rights
Commission) (sub nom Desormeaux v Ottawa-Carleton Regional Transit
Commission), 2004 FC 1778 at para 68. The Applicants’ argument that the
Panel erred by failing to assess a “project” as defined in the CEAA amounts to
an improper collateral attack on the scoping decision made by the Minister.
Parties must avail themselves of their remedial options in a timely manner and,
should they fail to do so, they generally are not permitted to bring collateral
attacks on final decisions: R v Wilson, [1983] 2 S.C.R. 594 at 599; Boucher
v Stelco Inc, 2005 SCC 64 at para 35.
[68]
The argument that the
proposal assessed was not a “project” as defined in the CEAA is in any case
without merit, the Respondents argue. There is a “project” under the first
branch of the definition in s. 2 of the Act if there is some “undertaking” in
relation to a “physical work.” Since construction, operation, decommissioning
and abandonment were all proposed here and are specifically included as
examples of undertakings in s. 2(1) of the Act, and since the proposed reactors
are physical works, the definition of a “project” is clearly met: see Bennett
Environmental, above, at para 77; Canadian Environmental Assessment
Agency, Canadian Environmental Assessment Act – An Overview, December
2011 (Updated) at p. 8 and Canadian Environmental Assessment Agency, Glossary
(2006) at pp. 20, 26 (Respondent’s Record (CNSC), Vol. 5, Tabs 4J and 4K).
[69]
The Respondents point
out that this conclusion is also supported by the scheme of the Act. Subsection
11(1) requires federal authorities to ensure that an EA is conducted as early
as practicable in the planning stages of a project, before irrevocable
decisions are made. The CNSC argues that it is preferable to identify environmental
concerns before a final design is selected, and to use the EA process as a
planning tool: Friends of the Island, above, at para 41; Quebec (Attorney General) v Canada (National Energy Board), [1994] 1 S.C.R. 159
at para 74. The case law recognizes that environmental assessment is “an early
planning tool”: Pembina Institute, above, at paras 33-34.
[70]
In Canadian
Transit, cited by the Applicants, the Court had no difficulty concluding
that a project existed and was relatively well-defined even though three bridge
design options were under consideration at the time of the assessment: Canadian
Transit, above, at paras 50-51. Similarly, in Inverhuron & District
Ratepayers’ Assn v Canada (Minister of the Environment) (2000), 191 FTR 20,
34 CELR (NS) 1 (TD) [Inverhuron (TD)], aff’d in Inverhuron (FCA),
above, both the Federal Court and the Federal Court of Appeal upheld a decision
of the Minister of the Environment approving a project to develop a dry storage
facility for spent nuclear fuel where the environmental impacts were considered
based upon alternative designs that were under consideration.
[71]
Friends of the
Island, cited by the
Applicants, is distinguishable on its facts. While the Court there found that a
general assessment comparing three concepts for crossing the Northumberland
Strait (two bridges and a tunnel) did not satisfy the requirements of the
Environmental Guidelines Order that preceded the CEAA, the assessment in that
case expressly stated that it was not fully considering potential environmental
implications, and emphasized that an assessment of the specific designs must be
undertaken: Friends of the Island, above, at para 41.
[72]
The Applicants’
argument that an EA must involve a detailed analysis of a specific technology is
not supported by the case law. There is no one prescriptive method for
conducting an EA; it must simply be conducted at a time and in a manner that
results in consideration of the factors outlined in the Act: Inverhuron (FCA),
above, at paras 54-57. The focus is on whether the environmental implications
of a project can be “fully considered”: Friends of the Island, above, at
para 41. This may mean the consideration of reference designs with
alternatives, a PPE approach, or any other approach that achieves this goal.
[73]
The use of a
“reference design” in conducting an EA – which the Respondents submit is no
different from the bounding approach at issue here – was specifically approved
in Inverhuron: Inverhuron (TD), above, at paras 46-56; Inverhuron
(FCA), above, at paras 54-56. The Federal Court stated at para 55:
…[T]o the extent that the challenge to the Minister's decision arises from
the use of a reference design which does not correspond to the final design
choice, the challenge must fail. As long as the statutory factors are
considered, it is not a ground of review that they were considered by
comparison to a reference design rather than by themselves. To the extent that
the applicant's case is that the process is flawed because the design studied
is not the design approved, which is in effect an attack upon the use of a
reference design for purposes of conducting an assessment, it must fail. The
choice of methodology is a matter within the competence of the responsible
authority and as long as it results in consideration of the factors which the
legislation requires to be considered, the Court cannot intervene.
According to Sexton JA in Inverhuron (FCA),
the relevant question was whether the EA report “provided the Minister with a
rational basis for arriving at her decision that the project was not likely to
cause significant adverse environmental effects,” and the reference design
approach used in that case met this requirement: Inverhuron (FCA),
above, at paras 57-58.
[74]
In the present case,
while the Panel would have found it “easier” to evaluate the environmental
effects of the Project had only one technology and design been presented, it concluded
that it could carry out its duties under the Act while considering multiple
technologies based on the bounding approach: EA Report at p. 11. This approach
assumed the worst case scenario for every environmental effect, and it is
reasonable to assume that if the maximum effect can be adequately mitigated,
lesser effects can be as well. Moreover, should a proposal arise that is beyond
the scope of what has been assessed, a new EA would be required.
[75]
The Respondents
reject the argument that the Panel failed to consider the environmental effects
of the Project as required by s. 16 of the Act. They say the record shows that
the Panel took into consideration all of the required environmental effects,
including radioactive and used nuclear fuel waste and cooling technology. While
the Applicants do not agree with the Panel’s conclusions, it was reasonable for
the Panel to conclude that the Project is not likely to cause significant
adverse environmental effects, provided the mitigation measures proposed, the commitments
made by OPG and the Panel’s recommendations are implemented. Courts have
recognized that information about the probable or possible future environmental
effects of a project can never be complete or eliminate all uncertainty. Assessing
these effects is a predictive exercise that involves a large measure of opinion
and judgment. The Panel’s conclusions about the adequacy and completeness of
the evidence regarding future effects and their significance are entitled to
deference: Inverhuron (FCA), above, at para 5; Express Pipelines,
above, at paras 10-12. Given the predictive nature of environmental assessment,
the Act recognizes the importance of follow-up mechanisms in addressing a
project’s effects: Pembina Institute, above, at paras 22-23.
[76]
Contrary to the
Applicants’ assertions, the Respondents CNSC and OPG argue that the record
shows the following:
(a)
There was evidence
before the Panel regarding liquid effluent and stormwater runoff and it was
able to conduct the EA in this regard;
(b)
OPG’s responses
provided sufficient evidence regarding the sources, types and quantities of non-radioactive
waste to be generated by the Project to allow the Panel to conduct the EA in
this regard;
(c)
The issue of
long-term management of radioactive waste was fully canvassed before the Panel,
which concluded based on the evidence that there would be no significant
adverse environmental effect; and
(d)
The Panel did conduct
an assessment of the off-site effects of a severe accident.
[77]
While OPG did not
provide an analysis regarding the cumulative effects of a “common cause” severe
accident involving both the new and existing reactors at the site, the Panel recommended
that the CNSC require such an analysis prior to construction.
[78]
Regarding the
requirement in s. 16(1)(d) of the Act that the Panel consider mitigation
measures, the Respondent CNSC argues that uncertainty is not fatal and that
future uncertain mitigation measures can be appropriate, even in cases where
the technology required to mitigate future adverse environmental effects has
yet to be developed. This is consistent with the ongoing and dynamic nature of
environmental assessment: Pembina Institute, above, at paras 57-58.
[79]
With respect to the
Panel’s consideration of the “need for” and “alternatives to” the Project, the
Respondents submit that the scope of a review panel’s consideration of the factors
set out in s. 16 of the Act is a discretionary decision made by the Minister,
and is outside the discretion of the Panel: CEAA s. 16(3); Friends of the
West Country, above, at paras 25-27; Inverhuron (TD), above, at
paras 51-52; Express Pipelines, above, at paras 11-12. The EIS
Guidelines required the need for and purpose of the Project to be identified
from OPG’s perspective, and stated that “the alternatives to the project need
not include alternatives that are contrary to Ontario’s formal plans or directives,”
since “an assessment of provincial energy policy is not within the terms of
reference of this joint review panel”: EIS Guidelines at p 17. The Panel would
be entitled to come to the same conclusion on its own, since it has discretion
to determine the parameters of the review required, and the CEAA is not
intended to be used as a back door means of economic regulation: Grand
Riverkeeper, above, at paras 53-54; Sharp v Canada (Canadian Transportation
Agency), [1999] 4 FC 363 (FCA) at paras 24-28 [Sharp]. The Terms of
Reference required OPG to prepare the EIS in accordance with the EIS
Guidelines. In any case, the Respondents say, the Panel heard from the Ontario
Ministry of Energy twice regarding the need for, and alternatives to, the
Project, and was provided with additional evidence on these issues through
responses to undertakings. The Applicants also had an opportunity to provide
evidence regarding possible alternatives to the Project.
[80]
In the end, the
Respondents argue, it was reasonable for the Panel to base its conclusions on
the “need for” and “alternatives to” the Project from the perspective of the
proponent in light of the directives issued to it by the Ontario government,
and to conclude that there were other more appropriate venues for public input regarding
Ontario’s energy policy.
[81]
Regarding the
Applicants’ position that the Panel unlawfully delegated its duties under the
Act, the Respondents argue that this argument must be rejected because it is
inconsistent with the scheme of the Act and would improperly narrow the
discretion of panels to conduct their reviews and recommend mitigation as
appropriate. Accepting the Applicants’ view that only “minor” or “secondary”
matters can be deferred to be dealt with by other agencies would involve the
courts in a detailed consideration of the substantive scientific and technical
evidence before a panel: Canadian Transit, above, at paras 7-9. The
Federal Court of Appeal addressed a similar argument in Express Pipelines,
above, and found as follows:
[14] Finally, we were asked to find that the panel had improperly
delegated some of its functions when it recommended that certain further
studies and ongoing reports to the National Energy Board should be made before,
during and after construction. This argument misconceives the panel's function
which is simply one of information gathering and recommending. The panel's view
that the evidence before it was adequate to allow it to complete that function
“as early as is practicable in the planning stages ... and before irrevocable
decisions are made” (see section 11(1)) is one with which we will not lightly
interfere. By its nature the panel's exercise is predictive and it is not
surprising that the statute specifically envisages the possibility of “follow
up” programmes. Indeed, given the nature of the task we suspect that finality
and certainty in environmental assessment can never be achieved.
[82]
The Respondent AGC
argues that an EA is a “planning tool” that provides “a process for integrating
environmental considerations into planning and decision-making”: Oldman
River, above, at para 103. As the Court observed in Pembina Institute,
“[t]he adequacy and completeness of the evidence must be evaluated in light of
the preliminary nature of a review panel’s assessment”: Pembina Institute,
above, at para 23. The CEAA is “a sophisticated legislative system for
addressing the uncertainty surrounding environmental effects,” and mandates
early assessment coupled with the flexibility of follow-up processes capable of
adapting to new information. This “dynamic and fluid” process means that
“perfect certainty regarding environmental effects is not required”: Pembina
Institute, above, at para 34. The Panel’s duties do not extend to the
elimination of uncertainty surrounding project effects.
[83]
The Respondents point
out that recommendations for follow-up programs to verify the accuracy of the EA
and determine the effectiveness of mitigation measures are specifically
authorized by s. 34(c) of the Act. They are also consistent with the principle
of “adaptive management” embraced by the CEAA, which “responds to the
difficulty, or impossibility, of predicting all the environmental consequences
of a project on the basis of existing knowledge,” and “counters the potentially
paralyzing effects of the precautionary principle on otherwise socially and
economically useful projects”: Parks and Wilderness Society, above, at
para 24; Inter-Church Uranium Committee Educational Co-operative v Canada
(Atomic Energy Control Board), 2004 FCA 218 at para 49 [Inter-Church
Uranium Committee] .
[84]
The Respondents note
that each of the five phases in the lifecycle of a nuclear power plant (site
preparation, construction, operation, decommissioning, and abandonment)
requires a licence from the CNSC. Each of these licence applications involves a
public hearing process, and the CNSC must be satisfied before issuing each
licence that OPG “will… make adequate provision for the protection of the
environment”: NSCA, s. 24(4)(b). The Project will also be expected to comply
with other federal, provincial and municipal regulatory requirements provided
they do not conflict with the NSCA and its associated regulations. The
Respondent AGC argues that it was appropriate for the Panel to take this regulatory
context into account, as this contributes to the efficiency and effectiveness
of the EA process. Subsequent permitting processes will effectively manage
certain Project effects, through the oversight of regulatory bodies with
specific expertise. Reliance on this regulatory context is both compatible with
the function and practical purpose of an EA as a planning tool, and consistent
with s. 37(2.1) of the Act, which allows a responsible authority to take into
account mitigation measures whose implementation the responsible authority can
ensure, or that it is satisfied will be implemented by another person or body.
[85]
In essence, the AGC
argues that the Panel viewed subsequent permitting processes, whether federal
or provincial, as mitigation measures, and was entitled to do so: Canadian
Transit, above, at para 183; West Vancouver (District) v British
Columbia (Ministry of Transportation), 2005 FC 593 at para 104 [West
Vancouver]; Inter-Church Uranium Committee, above, at paras 47 and
49; Pembina Institute, above, at para 24. The Panel need not describe
mitigation measures with exacting detail. Rather, it is sufficient to describe
general mitigation measures the details of which will be resolved in the
future, particularly when dealing with an industry with a well-established set
of “known” mitigation measures: Pembina Institute, above, at para 24; Union
of Nova Scotia Indians v Canada (Attorney General), [1997] 1 FC 325 (TD) at
paras 66-67 [Union of Nova Scotia Indians]; West Vancouver,
above, at para 102.
[86]
The Respondents
submit that the Applicants’ arguments regarding procedural errors are also
without merit. They argue that:
• The addition of the EC-6 technology to
the options being assessed was outlined in a letter from the CNSC to the Panel
Chair available on the Environmental Assessment Agency’s public web site on
July 30, 2010, well before the public comment period on the EIS closed on
October 8, 2010, and discussed in subsequent correspondence between the Panel
and OPG (see CNSC letter to Panel Chair dated July 30, 2010, OPG letter to
Panel dated August 17, 2010, Panel letter to OPG dated August 20, 2010, and OPG
letter to Panel dated August 30, 2010, Respondent’s Record (OPG), Vol. 14, Tabs
A72, A77, A73, and A78 respectively);
• The Panel’s decision not to extend the
comment period and to proceed to public hearings was reasonable;
• The Panel was not required to permit
cross-examination, particularly since the NSCA requires proceedings to be dealt
with as informally and expeditiously as circumstances and the rules of fairness
permit;
• The denial of the Applicants’ request to
adjourn the hearing to allow for the collection of “information missing from
the record” was also reasonable, because the hearings themselves are intended
to perform an information gathering function; and
• While the Applicants claim that OPG and
the Ontario Ministry of Energy provided evidence after the conclusion of the
hearings to which the Applicants did not have the opportunity to respond, the
evidence in question (responses to certain undertakings) was made available
through the Registry more than a month before the deadline for participants to
file final comments, and the Applicants had a full opportunity to respond to it
(see list of documents from Canadian Environmental Assessment Registry
(07-05-29525), Respondent’s Record (OPG), Vol. 1, Tab 5 at p. 149; Transcript,
Applicant’s Record, Vol. 6, Tab 5V, pp. 2285-2288; Revised Procedure for
Written Final Comments, Respondent’s Record (OPG), Vol. 13, Tabs A59 and A60). Where,
as here, there are no specific rules laid down by statute or regulation, the
tribunal controls its own procedure, subject to the rules of fairness: Prassad
v Canada (Minister of Employment and Immigration), [1989] 1 S.C.R. 560 at
568-69 [Prassad].
[87]
In the Respondents’
view, the Applicants’ argument that the Panel failed to comply with s. 24(4) of
the NSCA and the associated Regulations ignores the statutory scheme. There
were two statutory prerequisites before the Panel could issue its licensing
decision, the Respondents argue. First, under s. 37 of the CEAA, the
responsible authorities’ response to the EA had to be approved by the Cabinet
before a responsible authority could exercise any power with respect to the Project.
Second, s. 24(4) of the NSCA prevents the CNSC from issuing any licence unless
it is of the opinion that the applicant will make adequate provision for, among
other things, the protection of the environment and the health and safety of
persons.
[88]
The first requirement
was met when the Cabinet approved the responsible authorities’ response to the EA.
The CNSC (here, the Panel) was not required to take further steps to
investigate the nature of the EA that the Cabinet approved.
[89]
The second
requirement was also met. To satisfy s. 24(4), the CNSC must evaluate the
record and form a view as to whether the licence applicant will comply with the
statutory criteria. Here, the Panel examined the record and provided 50 pages
of reasons supporting its conclusion that OPG will make adequate provision for
the protection of the environment and the health and safety of persons. The
Panel accepted that OPG had provided sufficient information to satisfy the
regulatory requirements. This is an exercise of discretion that is entitled to
deference from this Court.
[90]
The Respondents
reiterate that the Licence is one of five that OPG will be required to obtain
over the life of the Project, and state that the initial licensing process, up to
and including the licence to operate, is expected to last approximately nine
years. At each licensing stage, OPG will be required to provide, and the CNSC
and other regulatory authorities will review, further design and operational
details. The public will have an opportunity to take part in all of these
licensing proceedings.
[91]
With respect to the
alleged breaches of procedural fairness, the Respondents say that the level of
procedural fairness required in these circumstances is low, and the Panel’s
very limited references to the Fukushima Task Force Report and Action Plan in
no way breached the Applicants’ procedural fairness rights.
[92]
The Respondents note
that the duty of fairness is flexible and context specific: Baker,
above, at paras 27, 30; Canada (Attorney General) v Mavi, 2011
SCC 30 at paras 40-42. In this case, no individual rights were being determined
in the proceedings, and the NSCA provides that proceedings before the
Commission are to be “dealt with as informally and expeditiously as the
circumstances and considerations of fairness permit.” The level of procedural
fairness required was simply a meaningful opportunity to participate; the
Applicants had no reasonable expectation of anything more: Baker, above,
at paras 24, 25, 27; Mega International Commercial Bank (Canada) v Canada
(Attorney General), 2012 FC 407 at paras 33, 35; Amis de la Rivière
Kipawa v Canada (Attorney General), 2007 FC 1267 at paras 83-90.
[93]
The Applicants had
and exercised opportunities for timely and meaningful participation at the
public hearing stage of the Panel’s process, the Respondents say, including
opportunities to comment on concerns arising from the nuclear accident at Fukushima. Thus, the Applicants received all of the fairness to which they were entitled. In
addition, there were separate opportunities for public comment and
participation in relation to the work of the Task Force itself, and some of the
Applicants participated in those processes.
[94]
Furthermore, the
Respondents argue, before granting any remedy for an alleged breach of
procedural fairness the Court must be satisfied that prejudice resulted: Uniboard
Surfaces Inc v Kronotex Fussboden GmbH and Co, 2006 FCA 398 at para 22; Federal
Courts Act, s. 18.1(5). Here, there was no prejudice. The five limited
references to the Task Force report and Action Plan were all aimed at requiring
OPG to address the Task Force’s findings in future submissions to the CNSC.
They had no bearing on the Panel’s disposition of OPG’s Licence application.
They merely set out the CNSC’s expectations regarding the content of certain
documents that will be prepared in the future.
[95]
The Applicants argue
that, contrary to the Respondents’ characterization, the Minister’s scoping
decisions are not being challenged in this judicial review application. Rather,
the application focuses on the errors and omissions of the Panel itself, which
occurred after the scoping decisions and were not caused or legally required by
those decisions. There was no obvious error of law or jurisdiction in the
scoping decision that would have warranted the Court’s intervention; rather,
the problem is that the comprehensive EA required by law in this case has not
been completed, and the responsibility for this rests with the Panel.
[96]
The Applicants
distinguish between the contents and legal effects of the EIS Guidelines on the
one hand and the Agreement establishing the Terms of Reference on the other.
They say the effect of the EIS Guidelines was to establish the scope of the project
to be assessed, in exercise of the Minister’s powers under ss. 15(1) and 15(3)
of the CEAA. The Minister essentially adopted the Project as proposed by the
proponent, consistent with MiningWatch Canada v Canada, 2010 SCC 2 at
paras 39-40, 42.
[97]
By contrast, the
bounding approach, which was not mentioned in the Project description in the EIS
Guidelines, changed the scope of the assessment, not the scope of the Project.
The Applicants say the bounding approach has no basis in law, but was
nevertheless adopted and utilized by the Panel.
[98]
The Applicants
acknowledge that other portions of the EIS Guidelines provided direction to the
proponent regarding what factors its EIS should address prior to the hearing.
However, they argue that the Minister has no statutory authority under the CEAA
to approve EIS Guidelines that constrain the scope of the EA to be conducted by
the Panel. They argue that, as a matter of statutory interpretation, these
Guidelines did not, and cannot, trump, vary or waive the legislative
requirements of the CEAA in relation to the scope of the EA to be conducted by
the Panel, which includes mandatory consideration of the s. 16 factors. The EIS
is not the EA. It merely represents the proponent’s submissions, and has no
greater status or weight than any other document filed by interveners or
federal authorities during the EA process.
[99]
The only Ministerial
decision delineating the scope of the assessment, the Applicants argue,
was the Agreement, which set the Terms of Reference and identified the factors
to be considered by the Panel in conducting the EA. In law, the approval of
this Agreement represents the exercise of the Minister’s discretion under s.
16(3) of the CEAA. In this case, the Minister essentially adopted all of the
considerations listed in ss. 16(1) and 16(2) without limitations or
qualifications. There was no mention of the PPE or bounding approach in the
Terms of Reference or in the Act. The decision to adopt this approach in the
assessment was made by the Panel, and was not required by the Minister’s
scoping decisions. The question here is whether, through this decision or in
other ways, the Panel failed to comply with the requirements of the CEAA and
its Terms of Reference, and that question remains ripe for adjudication.
[100]
Even if there were
potential grounds to challenge the Minister’s scoping decision, the Applicants
argue, the case law establishes that interlocutory decisions should not be
judicially reviewed in the absence of any special or exceptional circumstances.
In fact, judicial review applications that fragment, delay, disrupt or prolong
administrative proceedings are to be discouraged unless there is a real risk of
injustice or fundamental unfairness: Halifax (Regional Municipality) v Nova
Scotia (Human Rights Commission), 2012 SCC 10 at para 36. In MiningWatch,
this Court granted relief on scoping-related grounds even though the
application was brought after the completion of the EA rather than at the time
of the scoping decision: MiningWatch (FC), above, at paras 145, 148-154.
It was reasonable, if not preferable, for the Applicants to participate in the
EA process rather than challenging the scoping decision separately. If the Panel
had recommended against the Project proceeding, the issue would have been moot:
Lorenz v Air Canada, [1999] FCJ No 1383 at paras 33-35.
[101]
Finally, the
Applicants argue that since the main relief claimed is not against the Panel per
se but against the decisions of the Cabinet and responsible authorities
which were not in existence at the time this application was filed, the 30-day
time limit prescribed in s. 18.1(2) of the Federal Courts Act does not apply: Krause
v Canada, [1999] 2 FC 476 (FCA) at paras 20-24.
[102]
The Court has been
asked whether, in conducting the EA for the Project, the Panel complied with
the CEAA. Behind the dispute lie two very different views of what the CEAA requires
of the Panel in these circumstances.
[103]
The Applicants say
that the CEAA requires the Panel to take a precautionary and restrictive
approach to environmental assessments. They point to and emphasize the positive
legal duties imposed by s.4(2) upon all parties subject to the provisions of
the Act to "exercise their powers in a manner that protects the environment
and human health” and to apply the "precautionary principle." They
characterize the CEAA as a "look before you leap" law and cite the
jurisprudence that has affirmed this aspect of the Act. In the present case,
the Applicants say that the Panel has leapt, and has caused others to leap,
before looking closely and far enough.
[104]
The Respondents, on
the other hand, stress the more fluid and "predictive" nature of
environmental assessment and the difficulties of assessing all of the
consequences of a project in advance on the basis of existing knowledge. They
say that the potentially paralyzing effects of the precautionary principle have
been recognized by the Courts, which have endorsed "adaptive management"
as a necessary counterbalance to ensure that socially and economically
desirable projects can come to fruition.
[105]
The whole nature of
environmental assessment involves balancing necessary caution with the flexibility
required to make a proposed development achievable, safe and sustainable. The
present application is a classic dispute over whether the appropriate balance
has been struck for this Project. In my view, however, the magnitude and
anticipated longevity of this Project made it especially difficult to get the
balance right.
[106]
The Applicants wish
to portray environmental assessment as a gatekeeping function that prevents
environmentally harmful projects before they get off the ground (or before
shovels go into the ground) (see Bennett Environmental, above, at paras
82-83). Indeed, there have been instances where a finding by a review panel
that significant adverse environmental effects are likely to result from a
project have caused decision-makers to decide not to permit that project to
proceed. However, the Panel’s role as it pertains to the decision-making aspect
of environmental assessment is to ensure that decision-makers have the
necessary factual basis to make a scientifically informed decision. Justice
Tremblay-Lamer described this division of roles and responsibilities in Pembina
Institute, above, which is discussed further below. This is consistent with
the Panel’s own view that its “mandate… was to assess the environmental effects
of the Project and determine whether it is likely to cause significant adverse
environmental effects, taking into account the implementation of mitigation
measures” (EA Report at p. 37). As discussed below, the Panel’s role does not
extend to the elimination of all uncertainty; rather, it must be possible for
decision-makers to reasonably conclude that a project is likely, or is not
likely, to cause significant adverse environmental effects, keeping in mind the
guiding principles set out below, including the principle of precaution.
[107]
The primary
responsibility for assessing whether significant adverse environmental effects
are likely to result from a project lies with the body conducting the
environmental assessment (here, the Panel) and the subsequent decision-makers, not
the Court. The Panel’s expertise, the resources available to it, and the nature
of its process, as illustrated in the EA Report in the present matter, make it
better placed to bear and discharge this responsibility. What the Court
provides is an added layer of accountability, ensuring that the process
followed by the Panel was in keeping with the rules of fairness, that the Panel
fulfilled its obligations as outlined in the CEAA, and that the conclusions
reached meet the standard of being reasonable as described at paragraph 31
above.
[108]
In order to assess
the Project properly, the Panel was obliged to conduct itself in accordance
with the CEAA and the judicial guidance that has attached itself to that Act.
The basic duty of the Panel was to assess OPG's proposal and prepare a report
in accordance with s.34 of the CEAA. As s. 2 of the CEAA tells us, an
"assessment by a review panel" means
an environmental assessment that is conducted by a review panel
established pursuant to section 33 and that includes consideration of the
factors required to be considered under subsection 16(1) and (2).
[109]
Subsections 16(1) and
(2) of the Act provide as follows:
Factors to
be considered
16. (1) Every
screening or comprehensive study of a project and every mediation or
assessment by a review panel shall include a consideration of the following
factors:
(a) the
environmental effects of the project, including the environmental effects of
malfunctions or accidents that may occur in connection with the project and
any cumulative environmental effects that are likely to result from the
project in combination with other projects or activities that have been or
will be carried out;
(b) the
significance of the effects referred to in paragraph (a);
(c) comments
from the public that are received in accordance with this Act and the
regulations;
(d) measures
that are technically and economically feasible and that would mitigate any
significant adverse environmental effects of the project; and
(e) any other
matter relevant to the screening, comprehensive study, mediation or
assessment by a review panel, such as the need for the project and
alternatives to the project, that the responsible authority or, except in the
case of a screening, the Minister after consulting with the responsible authority,
may require to be considered.
Additional
factors
(2) In
addition to the factors set out in subsection (1), every comprehensive study
of a project and every mediation or assessment by a review panel shall
include a consideration of the following factors:
(a) the
purpose of the project;
(b)
alternative means of carrying out the project that are technically and
economically feasible and the environmental effects of any such alternative
means;
(c) the need
for, and the requirements of, any follow-up program in respect of the
project; and
(d) the
capacity of renewable resources that are likely to be significantly affected
by the project to meet the needs of the present and those of the future.
|
Éléments à
examiner
16. (1)
L’examen préalable, l’étude approfondie, la médiation ou l’examen par une
commission d’un projet portent notamment sur les éléments suivants :
a) les effets
environnementaux du projet, y compris ceux causés par les accidents ou
défaillances pouvant en résulter, et les effets cumulatifs que sa
réalisation, combinée à l’existence d’autres ouvrages ou à la réalisation
d’autres projets ou activités, est susceptible de causer à l’environnement;
b)
l’importance des effets visés à l’alinéa a);
c) les
observations du public à cet égard, reçues conformément à la présente loi et
aux règlements;
d) les mesures
d’atténuation réalisables, sur les plans technique et économique, des effets
environnementaux importants du projet;
e) tout autre
élément utile à l’examen préalable, à l’étude approfondie, à la médiation ou
à l’examen par une commission, notamment la nécessité du projet et ses
solutions de rechange, — dont l’autorité responsable ou, sauf dans le cas
d’un examen préalable, le ministre, après consultation de celle-ci, peut
exiger la prise en compte.
Éléments supplémentaires
(2) L’étude approfondie d’un projet et
l’évaluation environnementale qui fait l’objet d’une médiation ou d’un examen
par une commission portent également sur les éléments suivants :
a) les raisons d’être du projet;
b) les solutions de rechange réalisables
sur les plans technique et économique, et leurs effets environnementaux;
c) la nécessité d’un programme de suivi
du projet, ainsi que ses modalités;
d) la capacité des ressources
renouvelables, risquant d’être touchées de façon importante par le projet, de
répondre aux besoins du présent et à ceux des générations futures.
|
[110]
Important for this
application is the relevant definition of "project" in s. 2; it means
(a) in relation to a physical work, any proposed construction, operation,
modification, decommissioning, abandonment or other undertaking in relation to
that physical work.
[111]
The Project in this
case required federal approvals under the NSCA, the Fisheries Act and the NWPA,
and this meant that an EA under the CEAA had to be completed and result in a
positive course of action decision by each responsible authority (see CEAA, s.
37(1)). That course of action is required to be “in conformity with the
approval of the Governor in Council” (CEAA, s. 37(1.1)(c)), meaning that the
federal Cabinet must give its approval before a project of this nature can move
forward. The responsible authorities involved were obliged by the Act to ensure
that an EA was conducted as early as practicable in the planning stages of the
Project:
Timing of assessment
11. (1) Where an
environmental assessment of a project is required, the federal authority
referred to in section 5 in relation to the project shall ensure that the
environmental assessment is conducted as early as is practicable in the
planning stages of the project and before irrevocable decisions are made, and
shall be referred to in this Act as the responsible authority in relation to
the project.
|
Moment de
l’évaluation
11. (1) Dans
le cas où l’évaluation environnementale d’un projet est obligatoire,
l’autorité fédérale visée à l’article 5 veille à ce que l’évaluation
environnementale soit effectuée le plus tôt possible au stade de la
planification du projet, avant la prise d’une décision irrévocable, et est
appelée, dans la présente loi, l’autorité responsable de ce projet.
|
[112]
The words "as
early as is practicable in the planning stages of the project" have a
particular significance for the present dispute because the principal argument
of the Applicants is that there was no “project” to assess, or the Project was
not sufficiently realized to permit a meaningful EA.
[113]
As OPG points out in
written submissions, proceeding with the Project requires both environmental
assessment and regulatory licensing. Each of the five phases in the lifecycle
of a nuclear power plant requires the proponent to acquire a licence from the
CNSC under s. 24(2) of the NSCA: (1) a licence to prepare site; (2) a licence
to construct; (3) a licence to operate; (4) a licence to decommission; and (5) a
licence to abandon. The Law List Regulations made under the CEAA provide that
an EA is required before any licence is issued under s. 24(2) of the NSCA. This
requirement applies to each of the five licences necessary in the lifecycle of
a nuclear power plant; however, as the Applicants note, this does not mean
there will be future EAs for this Project under the CEAA or its successor
legislation. The EA under consideration here covered all phases of the
Project’s lifecycle. Before issuing each licence, the CNSC must assure itself
that the EA still applies. If the Project has changed in some fundamental way,
a new EA may be required (see Government of Canada’s Response to the Joint
Review Panel Report, (Recommendation 1), Applicant’s Record in T-1723-12 at p.
920 [Government Response]; Reasons for the Licence Decision at para 96,
Applicant’s Record in T-1723-12 at p. 41; CEAA, s. 24(2)), but it may be that
this is the only EA that will be conducted throughout the lifecycle of the Project.
[114]
Like all other environmental
assessments under the CEAA, the EA in this case had to be conducted “as early
as is practicable in the planning stages of the project and before irrevocable
decisions are made.”
[115]
It was the
application for a Site Preparation License by OPG that triggered the EA in this
case. In March 2008, following a recommendation by the CNSC, the Minister of
the Environment referred the Project for an EA by a review panel. A joint
review panel approach was adopted because both the EA and the Licence to prepare
the site required a public hearing process. The appointments to the Panel were
announced on October 30, 2009 and the Panel got down to work.
[116]
As this brief outline
of the obligations of the Panel under the CEAA reveals, there is an inherent
and inevitable tension between the need to ensure that an EA is conducted “as
early as practicable in the planning stages of the project and before revocable
decisions are made” and the obligations of the Panel to ensure that the s. 16(1)
and (2) factors are given a meaningful consideration. This tension lies at the
heart of the present dispute. The Applicants say that the proposed Project was too
hypothetical and inchoate to allow for a meaningful EA in accordance with the
Act. The Respondents, of course, argue the contrary.
[117]
There is nothing in
the CEAA itself to tell us when a project is sufficiently realized to allow for
a meaningful EA in accordance with the Act, so we need to turn to the case law
for guidance on this central issue.
[118]
In this regard, the Applicants
rightly refer the Court to the words of Justice Reed in Friends of the
Island, above, to the effect that an EA decision should occur at a time
when the proponent selects a specific project, and describes it in a sufficient
level of detail to allow for and facilitate meaningful agency and public review
of potential environmental effects. In other words, there must be something
that goes beyond the concept stage. Justice Reed noted that “public hearings on
a generic proposal are not a substitute for a specific evaluation of the actual
project which it is planned to construct” (paras 53 and 59).
[119]
It seems to me,
however, that the issue of whether a proposed project has the detail required
to facilitate a meaningful EA and allow for agency and public review will always
be a question of fact in each case. There is no easy conceptual answer to this
issue, and it will always depend upon the particular project and the contents
of the particular proposal. What is more, this is a matter that the assessing panel
itself will always have to consider and decide, because it is an inherent
aspect of environmental assessment in accordance with the CEAA. In my view, all
the Court can do is to assess whether, on a given set of facts, and given the
nature of the project proposed, such a finding by any panel is reasonable. I
think this view is supported by other cases that have dealt with this issue.
[120]
For example, I think
the Federal Court of Appeal decision in Inverhuron (FCA), above,
confirms the inevitability of this approach:
[56] Given the nature of the process and the differences between the
various types of projects subject to environmental assessment, there can be no
one prescriptive method for conducting an environmental assessment. Indeed, the
appellant was unable to direct the Court to any authority for a rule of law
that would require Ontario Hydro to conduct the sort of detailed analysis of
radiological effects that it seeks. The appellant did point to the case of Friends
of the Island v Canada (Minister of Public Works) as standing for the
proposition that a generic environmental assessment was not sufficient.
However, that case dealt with an assessment conducted under the very different
scheme of an order in council that preceded the current Canadian Environmental
Assessment Act. Moreover, in that case, Reed J. refused to consider whether the
order even required that a proposed project be assessed "at the concept
stage or at a more specific design stage." She simply held that the
assessment must take place when the environmental implications of a project can
be fully considered. In my opinion, the assessment at issue in the present case
was conducted at such a time.
[emphasis added, footnotes omitted]
[121]
In his recent
decision in Grand Riverkeeper, above, Justice Near (as he then was) reiterated
and summarized the role and purpose of a joint review panel in the EA process:
[29] A JRP is established to fulfill an information gathering and
recommending function under CEAA (section 34 of CEAA; Express Pipelines,
above, at para 14). The Panel does not render any final decisions with respect
to the Project, nor does it make absolutely binding recommendations. Rather,
its primary goal is to assist the RAs - the ultimate decision-makers - in
obtaining the information they need to make environmentally informed decisions.
It is one piece of the decision-making process mandated by CEAA.
[…]
[43] The basic goals of the EA process writ large are to ensure “(1)
early identification and evaluation of all potential environmental consequences
of a proposed undertaking; [and] (2) decision making that both guarantees the
adequacy of this process and reconciles, to the greatest extent possible, the
proponent’s development desires with environmental protection and preservation”
(Friends of the Oldman River Society v Canada (Minister of Transport),
[1992] SCJ No 1, [1992] 1 S.C.R. 3 at para 95)…
[…]
[122]
In the present case, the record
shows that, in September
2008, the Canadian Environmental Assessment Agency and the CNSC released draft
Environmental Impact Statement (EIS) Guidelines and a draft Joint Review Panel Agreement.
The purpose of the EIS Guidelines was to identify the information OPG would
need to include in the EIS, a document that would provide a detailed analysis
of the potential environmental effects of the Project. The purpose of the
Agreement was, among other things, to set out the Terms of Reference the Panel
would follow in conducting the EA. Those documents were finalized in March 2009
following a public comment period.
[123]
As outlined below in
greater detail, the Terms of Reference set out in the Agreement were the
mechanism through which the Minister, in accordance with s. 15(1)(b) and (3)(b)
and s. 16(3) of the CEAA, fixed the scope of the Project and the factors to be
considered in the EA. The EIS Guidelines, which were issued simultaneously,
offer some assistance to the Court in interpreting what the Minister intended.
[124]
The Applicants say
that the Panel failed to conduct an EA of a “project” because the Project
contained in OPG’s proposal did not satisfy the definition of “project” in s. 2
of the CEAA. They argue it was not a physical work containing sufficient detail
to allow for a meaningful EA. The essence of the Applicants’ argument is as follows:
In this case, however, the Applicants submit that the EA conducted by the [Panel]
should have obtained specific and reasonably detailed information regarding
OPG’s proposed construction, operation, modification, decommissioning,
abandonment or other undertakings that form part of the life cycle of the
physical work itself, or that are subsidiary or ancillary to the physical
work. In essence, OPG has presented an over-generalized collection of
conceptual options and vague site development choices that it would make in the
post-EA period, but without further assessment under the CEAA. Thus, what the [Panel]
purported to assess was a plan – a proposed or tentative course of future
action – rather than a “project” within the meaning of the CEAA.
[125]
In other words, the
Applicants say that what the Panel had before it was not a “project,” but “merely
a plan for future planning, assessment, and decision-making,” and this
undermines and is inconsistent with the precautionary principle of
international law enshrined in s. 4(2) of the CEAA and endorsed by the Supreme
Court in Spraytech, above, and other cases.
[126]
The Applicants make
much of the distinction between a “plan for future planning” and the need for a
“physical work” in the first branch of the definition of “project.” There is no
definition of “physical work” in the CEAA. However, it seems to me that the OPG
proposal was to construct, operate, modify, decommission and abandon a nuclear
power facility on the site of the present facility at Darlington. If the
proposal is carried out it will result in a physical work. In my view, this is
no different from any other proposal for a project. The real issue is whether
the proposal for the Project in this case contains sufficient detail to permit a
meaningful EA in accordance with the terms of the Act. This does not, in my
view, give rise to an issue of statutory interpretation. As I said earlier, it
was basically a question of fact to be determined by the Panel as part of its
assessment of the proposed Project, or it is a question of mixed fact and law (inevitably
fact-heavy) that determines whether the OPG proposal contained sufficient
detail to permit a meaningful EA in accordance with the terms of the Act,
including the extent of the obligations set out in ss. 16 and 34.
[127]
The Applicants’ essential
complaint can be summarized as follows:
As identified in the Report, the [Panel] itself found that key information
about the proposed Project was absent from the EA documentation. For example,
the Panel found that no specific nuclear reactor technology, site design
layout, cooling water option, used nuclear fuel storage option, or radioactive
waste management option has been selected. Thus, at the present time, federal
decision-makers still do not know: (a) the particulars of the specific project
to be implemented at the Darlington site; (b) the full range of site-specific
or cumulative environmental effects; or (c) whether there are feasible
mitigation measures over the project’s full lifecycle. These and other fundamental
gaps are attributable to the fact that what the [Panel] had before it was not a
“project”, but merely a plan for future planning, assessment, and
decision-making.
[128]
The understandable
concern of the Applicants is that until a specific reactor technology is chosen
it is not possible to assess the environmental impact of the Project. This
concern was placed before the Panel and rejected. In my view, the issue for the
Court is whether that rejection was reasonable, not whether the proposal
contained a “physical work.”
[129]
The proposal was not,
in my view, hypothetical. It referred to four specific reactor options. Hence,
the task of the Panel was to assess the environmental impact of a project that
would eventually select one of those options. A project that contains
technological options is not necessarily inchoate or merely conceptual in
nature. It simply means that the EA must consider and address environmental impact
in a way that accounts for all four options, and irrespective of which option
is eventually chosen. This complicates the assessment but, in my view, it does
not necessarily render it hypothetical, or remove the Project in this case from
the definition of “project” contained in the CEAA.
[130]
The Respondents
complain that the Applicants’ allegation that the Panel failed to assess a “project”
as defined by the CEAA is an improper collateral attack on the scoping decision
of the Minister, which fixed the Terms of Reference and the contents of the EIS
Guidelines and determined what it was the Panel had to assess in this case.
[131]
I have already
concluded that the bounding approach included in the OPG proposal and accepted
by the Panel was not inconsistent with the definition of “project” under the
CEAA, and that the real issue is whether it was possible to conduct a
meaningful EA based on the information available. Nevertheless, it is necessary
to consider the Respondents’ argument about the nature of the Minister’s
scoping decision, because it has potential implications for the main issue in
this application, which is whether the EA was conducted in a manner that
complied with the requirements of the CEAA.
[132]
Essentially, the
Respondents’ position on improper collateral attack is set out by the AGC in
written submissions:
36. The OPG Project Description, incorporated by reference into the
scoping decision, contains an explanation of the “bounding approach”. The
Applicants participated in the public comment period on the draft [Panel]
Agreement and, accordingly, had notice of its contents. The Applicants could
have applied for a judicial review of the scoping decision. They did not.
37. The scoping decision and the EA decision were made by separate
decision-makers (the Minister and the [Panel], respectively), at different
times (March 2009 and August 2011, respectively). Moreover, the decisions
involve distinct issues: the scoping decision set the parameters for the EA
pursuant to paragraph 15(1)(b) and 15(3)(b) of the CEAA; the [Panel]decision
evaluates the environmental effects of the Project, pursuant to section 34 and
subsections 16(1) and (2) of the CEAA.
38. The Applicants seek to overturn the scoping decision by
stretching the boundaries of this judicial review beyond the subject [Panel]
decision and the forms of relief sought in their Notice of Application. In
light of the scoping decision, the [Panel] properly proceeded on the premise
that the scope of the Project was based on the bounding approach [Court’s
emphasis]. Even if the Applicants had chosen to properly challenge the
scoping of the project, when they had the opportunity, they have failed to
establish how it was erroneous, given the requirement to assess a project “as
early as is practicable in the planning stages” and before irrevocable
decisions are made [AGC’s emphasis].”
[133]
The Applicants’
answer to these allegations is that they are not challenging the Minister’s
scoping decisions. They say that the "overarching problem addressed by the
present judicial review application is that the comprehensive environmental
assessment required by law – and by the Minister’s scoping decisions – has not
been completed to date…" In more detail, their argument is as follows:
14. In arguing that this aspect of the application for judicial
review is time-barred, the Respondents appear to have mischaracterized the
relevant submissions in the Applicants’ memorandum of fact and law (pages
12-17). In essence, the Applicants’ submission is that in order for there to be
a “project” as defined in section 2 of the CEAA, a proponent must identify the
specific nature of the proposed physical work(s), and must have selected the
preferred means of carrying it out. The Applicants submit that the [Panel] was
legally required to gather and analyze the information needed to assess the
environmental effects of an identifiable new nuclear power plant project.
Thus, the Applicants are specifically challenging the [Panel]’s exercise of its
mandate under the CEAA, and are not challenging the Minister’s decision
regarding the “scope of the project” under subsections 15(1) and 15(3) of the
CEAA. This distinction is consistent with the Supreme Court of Canada’s
decision in Miningwatch, where the Court held that the word “project” as
contained in the CEAA refers to a “project as proposed” by the proponent, and
not the “project as scoped.”
[134]
I think the
Respondents are mixing issues when they argue the Minister’s decision regarding
the scope of the Project included a decision that the “bounding scenario”
approach must be followed in conducting the EA.
[135]
The scope of the
Project relates to the physical works to be constructed and the activities to
be carried out in relation to them. The bounding scenario approach describes a
methodology for conducting the assessment of the Project. In my view, the two
are separate issues.
[136]
However, the Minister
also has authority under the CEAA to determine “[t]he scope of the factors to
be taken into consideration pursuant to paragraphs (1)(a), (b) and (d) and
(2)(b), (c) and (d)” of the Act (CEAA, s. 16(3)). It may be that the Minister
could restrict the scope of the factors to be considered in a manner that would
confine the Panel to considering a bounding scenario, or PPE. The question is
whether the Minister did so here.
[137]
The CEAA required and
empowered the Minister to make two separate scoping decisions with respect to
environmental assessments referred to a review panel.
[138]
First, under s. 15(1)(b),
the Minister, after consulting with the responsible authority, was to determine
the “scope of the project in relation to which an environmental assessment is
to be conducted.” Paragraph 15(3)(b) states that where, as here, the project
is in relation to a physical work, the EA must include “every construction,
operation, modification, decommissioning, abandonment or other undertaking in
relation to that physical work that is proposed by the proponent or that is, in
the opinion of [the Minister] likely to be carried out in relation to that
physical work.” Subsection 15.1, which was enacted after the scoping decision
under consideration here, and is therefore not relevant, provides the Minister
with discretion to depart from the principle just stated. So, under s. 15, the
Minister was to determine the scope of the Project.
[139]
Second, s. 16(3)(b)
empowers the Minister, “when fixing the terms of reference of the… review
panel,” to determine the “scope of the factors to be taken into consideration
pursuant to paragraphs [16](1)(a), (b) and (d) and [16](2)(b), (c) and (d).”
Thus, consideration of most of the mandatory factors under s. 16 could be
circumscribed by the Minister. The exceptions are “comments from the public…
received in accordance with this Act and the regulations” (s. 16(1)(c)), and
“the purpose of the project” (s. 16(2)(a)). In addition, the Minister had
discretion as to whether certain other factors were considered at all,
including “the need for the project and alternatives to the project” (s.
16(1)(e)). So, under s. 16, the Minister was to determine the scope of most of
the factors considered in relation to the Project.
[140]
The Respondents say
that three documents are relevant to these decisions: the Agreement (which
includes the Panel’s Terms of Reference), the EIS Guidelines, and the Project
Description, which the Respondents argue was incorporated by reference. The
Project Description is a document prepared by OPG that was issued with the
Notice of Commencement of the EA process in May 2007 (see Applicant’s Record,
Vol. 4., Tab 4A, Project Description for the Site Preparation, Construction and
Operation of the Darlington B Nuclear Generating Station, April 12, 2007
[Project Description]).
[141]
The Applicants say
that only the Agreement could define the scope of the Project, though they
appear to concede that the EIS Guidelines are relevant to the “scope of the
assessment,” by which, presumably, they mean the scope of the factors to be
considered.
[142]
Both the scope of the
Project and the scope of the factors to be considered are explicitly addressed
in the Agreement, and in particular the Terms of Reference that form a part of
it. The Panel was of the view that both the scope of the Project and the scope
of the factors to be considered were set out in the Terms of Reference (see EA
Report at p. 6), and I agree with this assessment. It may be that the EIS
Guidelines can assist the Court in interpreting what the Minister intended,
since they were issued simultaneously.
[143]
In my view, neither
the Agreement nor the EIS Guidelines restricted the Panel to considering a
bounding scenario, or mandated the PPE approach.
[144]
The Agreement defined
the term “Project” as follows:
“Project” means the preparation of a site for, and the construction,
operation, decommissioning and abandonment of, up to four
new nuclear power reactors on the existing Darlington Nuclear Site within the
Municipality of Clarington, Ontario described in Part I of the Appendix to this
Agreement;
[emphasis added]
[145]
The attached Terms of
Reference include the following Project Description:
Part I - Project Description
Pursuant to subsections 15(1)(b) and 15(3)(b) of the Canadian
Environmental Assessment Act, the Minister of the Environment is proposing
that the scope of the project include the site preparation, construction,
operation, decommissioning and abandonment of the project components and
activities proposed by OPG as described in OPG New Build Project Environmental
Assessment – Project Description.
The scope of the Darlington NNPP Project includes site preparation,
construction, operation, decommissioning and abandonment of up to four new
nuclear power reactors
for the production of up to 4,800 megawatts of electrical generating capacity
for supply to the Ontario grid.
Operations would involve activities required to operate and maintain the
Darlington NNPP, including management of all conventional and radioactive
wastes. The Province of Ontario is considering a range of reactor designs.
It is anticipated that each new reactor constructed would have an approximate
60-year operating life and could include a mid-life refurbishment depending on
the reactor design technology chosen by the proponent.
The project includes up to four units, consisting of the following
principal components:
•
Reactor Building – contains the reactor vessel, fuel handling
system, heat transport system, moderator, reactivity control mechanisms, shut
down systems and containment.
•
Turbine Generator
Powerhouse – contains the turbines, generators and related systems and
structures that convert steam from the operation into electrical energy.
The project also includes the following shared facilities between
reactors:
•
Condenser Cooling
Systems and Structures: including cooling towers or the once-through cooling
system with all of its associated submerged intake, forebay and discharge
systems.
•
Low and Intermediate
Level Waste Management Facility (on or off-site)
•
Expansion of the
existing Darlington Waste Management Facility for storage of used nuclear fuel
or construction of a new facility.
Ancillary activities that may be required include the transportation of
low and intermediate level waste to be managed offsite at an appropriate
licensed facility.
[emphasis added]
[146]
This is followed by a
more detailed description of the preparation, construction, operation and
maintenance, decommissioning and abandonment phases of the Project.
[147]
In my view, all of
this makes it clear that the Project scope relates to the activities to be
carried out in relation to the physical works in question – i.e. the “site
preparation, construction, operation, decommissioning and abandonment of up to
four new nuclear power reactors.” It has nothing to do with the methodology by
which the assessment is to be carried out.
[148]
The Respondent AGC
argues that OPG’s Project Description was “incorporated by reference” into the
Panel’s Terms of Reference, and included an explanation of the “bounding
approach” (see Appendix A: Plant Parameter Envelope Description & Reactor
Technology Descriptions). However, in my view, it is not possible to read the
reference to the Project Description document in the Terms of Reference as a
decision that the PPE approach must be adopted as a methodology (much less the
sole methodology) for conducting the EA. As the AGC points out, the Terms of
Reference state:
•
That the site
preparation includes “the site preparation, construction, operation,
decommissioning and abandonment of the project components and activities
proposed by OPG as described in the [Project Description]”;
- That the Project “includes up to four units,”
each consisting of a reactor building and a turbine generator powerhouse;
and
- That the Project includes the following shared
facilities between reactors: condenser cooling systems and structures (cooling
towers or the once-through cooling system); low and intermediate level
waste management facility (on or off-site); and expansion of an
existing facility or construction of a new facility for storage of
used nuclear fuel.
[AGC’s emphasis]
[149]
The first of these
observations merely confirms what has already been set out above: that the
Project consists of the “site preparation, construction, operation,
decommissioning and abandonment of up to four new nuclear power reactors.”
This says nothing about the methodology by which the assessment is to be
carried out. The reference in the Terms of Reference to the Project Description
prepared by OPG is not a blanket endorsement of everything that document
contains, including the description of the PPE approach in Appendix A. Rather,
it is a specific observation that the Project consists of “the site
preparation, construction, operation, decommissioning and abandonment of the
project components and activities proposed by OPG as described in the
[Project Description]” (emphasis added).
[150]
The second and third
observations acknowledge that technology and design options are still being
considered for a number of components of the Project. Again, this says nothing
about how those options are to be presented and evaluated in the course of the
EA. If it proved necessary, in order to comply with the CEAA, to describe and
evaluate each of the options and their potential effects in the same level of
detail that would normally be provided if the technology and design choices had
already been made, such an approach would be consistent with the language of
the Agreement and the Terms of Reference.
[151]
In short, as will be
seen below in considering the EIS Guidelines, the acknowledgment that “The
Province of Ontario is considering a range of reactor designs” does not dictate
a particular methodology for conducting the EA.
[152]
In relation to the
scope of the factors to be considered, it is appropriate to consider both the
explicit description of these factors and the Minister’s descriptions of the
process to be followed in carrying out the assessment.
[153]
The Terms of
Reference state the following in this regard:
Part IV – Scope of the Environmental Assessment and Factors to be
Considered in the Review
The Review will include a consideration of the following factors listed in
paragraphs 16(1) (a) to (d) and in subsection 16(2) of the CEAA:
a.
The environmental
effects of the project, including the environmental effects of malfunctions,
accidents or malevolent acts that may occur in connection with the Project and
any cumulative environmental effects that are likely to result from the project
in combination with other projects or activities that have been or will be
carried out;
b.
The significance of
the effects referred to in (a);
c.
Comments that are
received during the Review;
d.
Measures that are
technically and economically feasible and that would mitigate any significant
adverse environmental effects of the Project;
e.
Purpose of the
Project;
f.
Need for the Project;
g.
Alternatives to the
Project;
h.
Alternative means of
carrying out the Project that are technically and economically feasible and the
environmental effects of any such alternative means;
i.
Measures to enhance
any beneficial environmental effects;
j.
The requirements of a
follow-up program in respect of the Project;
k.
The capacity of
renewable resources that are likely to be significantly affected by the Project
to meet the needs of the present and those of the future; and
l.
Consideration of
community knowledge and Aboriginal traditional knowledge.
Part V – Scope of Assessment of the Application for Licence to Prepare
Site
Pursuant to section 24 of the NSCA and its regulations, the JRP process
will include consideration of:
•
Whether the applicant
is qualified to perform the activity to be licensed; and
•
Whether in carrying
on that activity the applicant will make adequate provisions for the protection
of the environment, the health and safety of persons and the maintenance of
national security and measures required to implement international obligations
to which Canada has agreed.
There is no reference here to a “bounding scenario” or PPE approach, nor
do any restrictions appear to be placed on the consideration of the factors
under s. 16.
[154]
The terms of the
Agreement itself reinforce this view:
2.2 Nothing in this JRP Agreement shall be construed as limiting the
ability of the JRP to have regard to all considerations that appear to be
relevant pursuant to section 24 of the NSCA and to include a consideration of
the factors set out in sections 16 and 16.1 of the CEAA.
[155]
The same descriptions
of the Project, the scope of the assessment and the factors to be considered
are essentially repeated in the EIS Guidelines.
[156]
In my view, the
language of the EIS Guidelines largely supports the Applicant’s view that they
are addressed primarily to the proponent, and not the Panel. The EIS Guidelines
state (at p. 1):
The purpose of this document is to identify for the proponent, Ontario
Power Generation (OPG), the nature, scope and extent of the information that
must be addressed in the preparation of the Environmental Impact Statement
(EIS) for its proposed New Nuclear Power Plant project (the OPG Darlington NNPP
project) for the creation of approximately 4,800 MW of electrical generation
capacity…
[157]
While the EIS
Guidelines use mandatory language for the information to be included, in my
view, they leave it to the proponent to determine the method or methods to be
employed in advancing evidence to satisfy the Panel that the Project will not
have significant adverse environmental effects, stating (at p. 1):
While the EIS guidelines provide a framework for preparing a complete and accessible EIS, it
is the responsibility of the proponent to provide sufficient data and analysis
on any potential environmental effects to permit proper evaluation by a joint
review panel, the public, and technical and regulatory agencies. The EIS
guidelines outline the minimum information requirements while providing the
proponent with flexibility in selecting methods to compile and analyze data for
the EIS.
[emphasis added]
[158]
The proponent is free
to disagree with the views expressed in the EIS Guidelines as to the
information required, but is expected to justify the choices put forward. It is
up to the Panel to determine if further information is required (at p. 7):
The proponent is expected to observe the intent of the EIS guidelines and
to identify all environmental effects that are likely to arise from the project
(including situations not explicitly identified in these guidelines), the
mitigation measures that will be applied, and the significance of any residual
adverse effects. It is possible that the EIS guidelines include matters
that, in the judgement of the proponent, are not relevant or significant to the
project. If such matters are omitted from the EIS, they must be clearly
identified in the EIS with appropriate justification so that the public and
other interested parties have an opportunity to comment on this judgement. Where
the joint review panel disagrees with the proponent's decision, it may require
the proponent to provide additional information.
[emphasis added]
[159]
Nonetheless, it is
clear that there is intended to be a connection between the framework set out
in the EIS Guidelines and the decision-making of the Panel. For example, the
Panel was to determine whether there was sufficient information to proceed to a
hearing according to how well the proponent had responded to the EIS
Guidelines. The Terms of Reference state, under Components of the Review:
6. The JRP shall schedule and announce the start of the JRP
Hearings once it is satisfied that the Proponent’s EIS and any additional
information has adequately responded to the EIS Guidelines.
[emphasis added]
However, even if the EIS Guidelines could be seen to be restrictive of the
Panel’s deliberations in certain respects, in my view, they do not dictate the
“bounding scenario” approach. On the contrary, the EIS Guidelines suggest that
a significant level of detail must be provided regarding each of the reactor
technologies under consideration and their respective environmental
implications. For example, Section 8.1 of the EIS Guidelines states that the
following information was to be included in the EIS:
For each reactor design being considered, include information on the:
•
basic configuration,
layout, shape, size, design and operation of the facility;
•
performance
specifications, design philosophy, reactor type, plant configuration, and all
structures, systems and components important to safety;
•
safety
characteristics;
•
planned operational
life;
•
description of any
special commissioning or 'start-up' procedures and requirements;
•
requirements for
refurbishment;
•
ageing and wear
issues and management of these issues, where relevant to future environmental
performance and reliability;
•
physical security
systems (excluding prescribed information), designed specifically to isolate
the project from the surrounding environment, or to prevent, halt or mitigate
the progress or results of malfunctions, accidents or malevolent acts;
•
engineered and
administrative controls, including the use of an approved margin of sub-criticality
for safety, which assure that the entire (out of reactor) process will be
sub-critical under normal conditions and credible abnormal conditions –
accidents or accident sequences – that have a frequency of occurrence equal to
or more than one in a million years;
•
stored inventories of
radioactive and other hazardous materials, including locations and storage
methods, and criticality control plans;
•
sources, types and
quantities of radioactive and non-radioactive waste, including hazardous waste,
predicted to be generated;
•
processes and
facilities for the management of radioactive and non-radioactive waste,
including low, intermediate and spent fuel waste, conventional, sanitary and
hazardous wastes, to be generated by the project, including processes such as
collection, handling, storage and transportation;
•
sources and
characteristics of any fire hazards;
•
sources and
characteristics of any noise, odour, dust and other likely nuisance effects
from the project; and
•
sources and
characteristics of any potential risks (including radiological risks) to
workers, the public or the environment from the project.
[160]
The Guidelines
regarding the more detailed descriptions of each of the phases of the Project
that were to be included in the EIS (see EIS Guidelines at sections 8.2 through
8.6) make no mention of a “bounding scenario” approach. For example, the
section relating to the operations and maintenance stage states:
Description of the operation and maintenance phase and timeframe of the
project and of the associated activities should include, but are not limited
to:
•
the commissioning
activities such as general verification of equipment and systems, fuelling of
reactor;
•
pressure testing of
containment building, approach to criticality and eventually to full power and
connection to the grid;
•
the operation and
maintenance activities required for systems such as the nuclear steam supply
system, turbine generator and feed water systems, cooling water systems,
electrical power systems, nuclear safety systems, ancillary systems, systems
for operating and maintaining facility security, activities associated with the
maintenance program, materials handling systems, solid waste handling systems
and administration and support systems;
•
activities associated
with mid-life refurbishment for CANDU-type reactors as well as activities
relating to outages to refuel or for the refurbishment of light water reactors;
•
operation of
equipment for production of electricity;
•
verification,
sampling, testing and maintenance during operation at power;
•
maintenance, repairs,
cleaning, and decontamination during planned shutdowns and outages;
•
fuelling and
refuelling of the reactor; management of low and intermediate waste and used
fuel, including transfer to interim or long-term waste storage facilities;
•
past events that are
relevant to the assessment of future environmental performance and reliability:
•
the sources,
quantities and points of release from routine radiological and non-radiological
emissions and effluents, including thermal (heat) releases;
•
the area of exposure
to the physical effects of the discharge jet and intake suction;
•
where applicable,
characterization of the waste, including estimated activity in becquerels, that
will be generated and stored at each of the waste management areas as a result
of operation and any future refurbishment;
•
predictions of future
emissions and effluents from the project under normal operating conditions;
•
standard design
features and key operational procedures relevant to protection of workers, the
public and the environment relating to the project, including the nuclear
criticality safety program;
•
operations workforce,
composition of workforce and any infrastructure requirements;
•
systems for operating
and maintaining the facility security program;
•
emission and effluent
control, treatment and monitoring and environmental monitoring;
•
non-radioactive waste
handling, storage and disposal; and
•
activities relating
to environmental protection and radiation protection.
[161]
The portion of the EIS
Guidelines relating to “Study Strategy and Methodology” also makes no reference
to the bounding scenario or PPE approach. Rather, it says that (at p. 8):
…The sections in the EIS regarding existing environment and potential
adverse environmental effects predictions and assessment must be prepared using
best available information and methods, to the highest standards in the
relevant subject area. All conclusions must be substantiated.
The EIS must identify all significant gaps in knowledge and understanding
where they are relevant to key conclusions presented in the EIS. The steps to
be taken by the proponent to address these gaps must also be identified…
[162]
The EIS Guidelines
refer to a “bounding scenario” or approach in only three places, none of which
suggest to me that this was a mandatory overall methodology for assessing the
Project in advance of a reactor technology decision. There is no mention of a
“plant parameter envelope.”
[163]
Section 9 of the EIS
Guidelines discusses the need to establish spatial and temporal boundaries for
the assessment – that is, to define the geographical area and period of time
with respect to which environmental effects were to be assessed. It says the
following with respect to temporal boundaries:
At a minimum, the assessment must include the period of time during which
the maximum effect is predicted to occur. “Maximum” refers to the greatest
change from baseline conditions to what is predicted and should be bounding
across reactor types.
[emphasis added]
[164]
Section 11.1 of the
EIS Guidelines discusses effects prediction, and includes the following with
respect to risk modelling:
The EIS must describe comprehensive analyses of both the short and long
term effects of the project on the environment. The proponent must indicate the degree of
uncertainty in predicting the environmental effects identified. When numerical
models are used (e.g., a quantitative ecological risk assessment model, a
population level ecological risk assessment model) scientific defensibility
must be demonstrated by performing model verification (e.g., peer review of
model theory), calibration (e.g., adjusting key parameters to site-specific
data), validation (e.g., comparison of predicted to observed), sensitivity and
uncertainty analysis. Risk modelling of VEC exposure to releases of
radionuclides, or hazardous substances (including thermal) shall be determined
through the use of upper bounding scenarios or a combination of expected
average releases and an upper bounding scenario.
[emphasis added]
[165]
Section 12.2 of the
EIS Guidelines says the following with respect to nuclear accidents:
The EIS must identify and describe the probability of possible
malfunctions or accidents associated with each reactor design considered and with other facilities in the nuclear
power plant that contain radiological substances and must consider the
potential adverse environmental effects of these events.
The proponent must credibly demonstrate that it meets the safety goals
defined in CNSC Regulatory Document RD-337, “Design of New Nuclear Power Plants”, [Reference 10], with some margin on
frequency, consequence or both. These safety goals are meant to ensure that the
risk posed by a nuclear power plant to members of the public living near the
plant is small compared with the risks to which they are normally exposed, and the
releases they describe are bounding for all designs.
[emphasis added]
[166]
The first and third
occurrences use the term “bounding” to indicate that OPG was required to ensure
that the full scope of potential effects or impacts was captured in the
analysis. The second indicates that a “bounding scenario” approach should be
used, alone or in combination with other information, in assessing the risks of
exposure to releases of radionuclides or hazardous substances.
[167]
I see nothing in any
of these descriptions that limits the Panel to a “bounding scenario” analysis,
or prevents it from requesting further information if necessary to adequately
assess effects on the environment and human health or their significance.
[168]
Ultimately, it seems
to me that the PPE or “bounding scenario” approach was not dictated by the
Agreement or the EIS Guidelines.
[169]
Rather, it was
selected by OPG, and ultimately accepted by the Panel, as an appropriate method
of evaluating the likely environmental effects of the Project in advance of a
reactor technology decision. It was open to the Panel to come to a different
conclusion, and it is open to the Court to find the Panel’s conclusion to have
been in error.
[170]
This conclusion is
relevant both to the Applicants’ argument that the EA did not assess a
“project” (and the Respondents’ allegation that this is a collateral attack on
the scoping decision), and to the Applicants’ argument that the Panel did not
properly assess the Project’s environmental effects.
[171]
I have already
concluded that the Applicants’ argument that there was no “project” to assess
fails on its merits. Thus, it is not strictly speaking necessary to consider
whether it is a collateral attack on the scoping decision, but I include my conclusion
on this point here for purpose of completeness.
[172]
It is my view that
what the Applicants are really attacking is not the scoping decision, but the
Minister’s decision to refer the Project to a review panel. It seems to me that
there must be a “project” before this can occur. It may be that the absence of
a “project” would not be plain until the scoping decision is issued, but this
is a separate issue.
[173]
In any case, it is
clear from the Project Description, the Agreement and the EIS Guidelines that there
was a “project” to be assessed here.
[174]
The real issue, to
which I turn below, is whether a CEAA-compliant EA could be (and was) carried
out based on a bounding scenario approach. In assessing this, the Minister’s
power to determine the scope of the factors to be considered, and the use of
that power in this case, will need to be considered.
[175]
This is the principal
determinative issue before me. The Applicants say that even if there was a
"project" to assess in this case, the Panel failed to conduct an EA
in accordance with the CEAA. Their essential point is that OPG's failure to
designate a single and specific reactor technology for the Project meant that
the Panel could not, and did not, produce an EA that complied with its obligations
under s. 34 of the Act, or take into account the factors stipulated in ss.16(1)
and 16(2) of the Act. Once again, in my view, this is a factual issue or a
question of mixed fact and law. The Panel found that it did have the requisite
information and input to assess the environmental impact of the Project in
accordance with the Act. The issue for the Court is whether this conclusion was
reasonable.
[176]
The main problem identified
by the Applicants is, once again, that OPG's failure to select a particular
reactor option in its proposal prevented a meaningful EA in accordance with the
Act.
[177]
OPG's approach to this
issue in the Project proposal was the “plant parameter envelope” or “bounding”
approach. As noted above, OPG’s Project Description contained an appendix
(Appendix A) titled “Plant Parameter Envelope Description & Reactor
Technology Descriptions,” which discussed the use of the PPE method and stated
that OPG was “considering several types of reactor designs for the potential
new nuclear power generating station” at the Project site. OPG explained that a
PPE was developed by examining each reactor design, and for each parameter
(e.g., radiological emissions) using the value with the greatest potential to
cause an adverse environmental effect.
[178]
The Panel describes
the PPE approach in its EA Report as follows at pages 11-12 of the EA Report:
2.1
MULTIPLE TECHNOLOGY
APPROACH
A number of vendors and reactor technologies were considered in the
procurement process initiated by the Government of Ontario. No decision was
made on the choice of a reactor technology prior to the start of the
environmental assessment. This approach led to the development of a plant
parameter envelope to encompass the range of reactor technologies under
consideration. The plant parameter envelope is a set of data derived from
available vendor information for multiple reactor technologies, and provides a
bounding envelope of plant design and site parameter values for use in the
Application for a Licence to Prepare Site and environmental assessment.
OPG explained that the plant parameter envelope identified a set of design
parameters and associated limiting values, such as a worst-case scenario, from
the multiple technologies that are used to describe the bounding features of
the Project, OPG stated that this approach is consistent with Canadian
Nuclear Safety Commission Information Guide INFO-0756, Rev 1, Licensing Process
for New Nuclear Power Plants in Canada (May 2008), which provides an
overview of the process for licensing new nuclear power plants in Canada,
taking into consideration the requirements of the Nuclear Safety and Control
Act and associated regulations, as well as an environmental assessment.
The bounding plant parameter envelope used in the assessment of effects is
based on the limiting values for parameters either from:
•
the reactor
technology examples;
•
the reactor class,
such as pressurized water reactor, pressurized heavy and light water hybrid
reactor and pressurized heavy water reactor; or
•
the site itself.
OPG explained that the framework bounded by the plant parameter envelope
was established to ensure that the potential adverse effects of any of the
reactor types currently under consideration by the Government of Ontario are
included for the purposes of the effects analysis. As such, the significance of
the potential adverse effects of any reactor technology that is bounded by the
analysis has been considered.
If the Project is to go forward, the reactor technology selected by the
Government of Ontario must be demonstrated to conform to the plant parameter
envelope and regulatory requirements, and must be consistent with the
assumptions, conclusions and recommendations of the environmental assessment
and the details of the Government response to this Joint Review Panel
Environmental Assessment Report. This evaluation will be required to be
performed by the responsible authorities once a reactor technology is selected
and will be required to be demonstrated as part of the licence process for an
Application for a Licence to Construct.
2.2
REACTOR DESIGNS
The following reactor technologies formed the
basis of the plant parameter envelope:
•
ACR 1000 by Atomic
Energy of Canada Limited;
•
EPR by AREVA;
•
AP 1000 by
Westinghouse; and
•
Enhanced CANDU 6
(EC6) by Atomic Energy of Canada Limited.
For environmental assessment purposes, the number of reactors that would
represent full build-out of the Project for each reactor type was adopted to
consider the potential effects during the operation and maintenance phase of
the Project. The scope of the Project includes the maximum potential
development of the site within the upper limit of 4,800 megawatts. This type
that would be required to achieve the upper limit of 4,800 megawatts of electrical
power generation will vary, depending on the reactor technology, as follows:
•
ACR 1000 to achieve
approximately 4,300 megawatts;
•
EPR to achieve
approximately 4,700 megawatts;
•
AP 1000 to achieve
approximately 4,200 megawatts; and
•
EC6 to achieve approximately
2,960 megawatts.
During the review and comment period, CNSC staff recommended to the Panel
that OPG should update the plant parameter envelope for the Project to include
the EC6 reactor technology by Atomic Energy of Canada Limited. The basis for
the CNSC staff recommendation was that the procurement process for the
Government of Ontario reactor selection had been suspended and no reactor had
yet been selected. CNSC staff expressed the view that the EC6 technology was a
possible technology choice for the Project, and as such, it should be
encompassed by the plant parameter envelope. CNSC staff noted that in the
interest of regulatory efficiency and to minimize the likelihood that another
environmental assessment would be required should the EC6 reactor technology be
put forth as the technology to be constructed on the Darlington Nuclear site,
it would be prudent to also consider this technology option within the current
review process being conducted by the Panel.
OPG responded that the plant parameter envelope for the Project was
sufficiently broad to include other alternative technologies that are
commercially available that may be selected by the Government of Ontario,
including boiling water reactors and the EC6 reactor technology. OPG was of the
view that the conclusions of the environmental assessment would not change
should an alternative reactor technology be selected.
In consideration of the CNSC staff recommendation and the OPG response,
the Panel directed OPG to provide a description of the elements of those
technologies that could be outside the plant parameter envelope defined in the
EIS. OPG was to provide details on how this could change the potential effects
of the Project on components of the environment and any other aspects of the
environmental assessment, and any required changes to the responses to
information requests that OPG had already provided to the Panel.
OPG responded to this request by providing an update to the plant
parameter envelope and responses to information requests, taking the EC6
reactor technology into consideration. Following further requests for
information from the Panel, a revised version of the plant parameter envelope
was submitted by OPG on November 30, 2010. OPG noted that a similar assessment
was not performed for a boiling water reactor as insufficient information was available
to allow OPG to do so. OPG noted that should the Government of Ontario decide
to include boiling water-type reactors in its procurement process, the plant
parameter envelope would be updated accordingly.
Furthermore, OPG stated that although some plant parameter envelope values
changed as a result of the EC6 consideration and other considerations, no
additional environmental effects were anticipated and no additional mitigation
measures would be required.
[179]
The Panel then
assessed and accepted the PPE approach in the following terms at pages 45-46 of
the EA Report (in section 4.5.1 Alternative Reactor Technologies):
Panel Assessment
According to CNSC staff, the reactor designs that were assessed as bounded
by the plant parameter envelope are all enhancements of designs of
currently-operating reactors. These designs incorporate characteristics that
provide improvements in safety from previous designs. Among the changes is the
incorporation of passive safety features, such as the capability to continue to
maintain safety functions, even in instances of loss of power. CNSC staff
stated that the designs provide overlapping redundant measures for the
prevention and mitigation of effects from reactor malfunctions and accidents
and that all of these alternative designs have robust containment structures.
CNSC staff noted that much of the design and safety information considered
for the reactor designs covered in the plant parameter envelope is preliminary
information that may be accepted for the purposes of the environmental
assessment. CNSC staff indicated that final detailed design information and
safety analyses will be required to confirm compliance with regulatory
requirements at the time of an Application for a Licence to Construct a
reactor.
CNSC staff concluded that the plant parameter envelope approach allowed
for the assessment of the potential adverse effects of a reasonable range of
reactor designs in accordance with the EIS Guidelines.
The Panel accepts the use of a plant parameter envelope for environmental
assessment purposes as an approach that allows the prediction of adverse
environmental effects for a select group of reactor technologies. The Panel
recognizes, however, that this is a departure from a more standard approach
where the major components of a project are defined in advance of an
environmental assessment.
Additionally, the Panel notes that aspects of the plant parameter envelope
were based on preliminary design information. As such, there will be a need for
ongoing verification of the conclusions reached on the significance of adverse
environmental effects.
The selection of a reactor technology that is not one of the four designs
considered will require careful review to confirm the continued applicability
of the assumptions and conclusions of this environmental assessment. A
determination of the applicability of this environmental assessment will be
made by the responsible authorities when a reactor technology for the Project
is selected by the Government of Ontario.
It is noted that, of the four reactor designs described in the EIS, only
the Atomic Energy of Canada Limited EC6 has entered operational service and has
environmental performance data from operating plants. However, with respect to
technology safety and expected environmental performance, all of these reactors
incorporate passive safety features and are designed to mitigate the effects of
malfunctions and accidents. The safety features provide defence in- depth and
systems to control and cool the reactor and to contain radioactivity in the
plant. These attributes are common features of modern reactor designs.
Recommendation # 1:
The Panel understands that prior to construction, the Canadian Nuclear
Safety Commission will determine whether this environmental assessment is
applicable to the reactor technology selected by the Government of Ontario for
the Project. Nevertheless, if the selected reactor technology is fundamentally
different from the specific reactor technologies bounded by the plant parameter
envelope, the Panel recommends that a new environmental assessment be conducted
[180]
The Applicants point
out that the CEAA does not refer to such concepts as a PPE or “bounding
scenario,” or any similar concept. However, it is noteworthy in my view that the
CEAA does not refer to any particular approach to environmental assessment and,
as the Federal Court of Appeal made clear in Inverhuron (FCA), above, at
para 56, “given the nature of the process and the differences between the
various types of projects subject to environmental assessment, there can be no
one prescriptive method for conducting an environmental assessment.” It seems
to me that, by necessity, the issue in every case will be whether the method
chosen permits a meaningful EA to take place in accordance with the CEAA. In
the present case, the Panel concluded that a PPE approach did allow it to
assess the Project appropriately and concluded that it “is not likely to cause
significant environmental effects, provided mitigation measures proposed and
commitments made by OPG during the review and the Panel's recommendations are
implemented.”
[181]
The Applicants have
made it clear that they disagree with the PPE approach and the Panel's
assessment of that approach. In my view, however, they have not demonstrated,
given the obligations of the Panel under ss. 34, 15, 16(1) and 16(2) and the
Terms of Reference contained in the Agreement, that the PPE approach was
inherently incapable of achieving a meaningful EA. Nor have they shown that it failed
to do so in this case, in such a way as to render the Panel's EA Report
unreasonable, except for those matters that I specifically refer to below in
these reasons.
[182]
The bounding
framework incorporated the PPE, which is a set of design parameters that
delimit key features of the Project. The PPE represents the limiting values
which have the greatest potential to result in an adverse environmental effect for
salient elements of the design options that were identified in the proposed Project.
The different reactor types were presented as alternative methods of carrying
out the Project. For any given environmental component, the Panel based its
analysis on whichever of the four reactor designs would have the greatest
effect on that component. The reasoning is that if the maximum effect on each
component can be adequately mitigated, then the lesser impacts of the other
alternative technology options can also be adequately mitigated. The Panel
concluded that the proposed PPE approach allowed it to assess the potential
environmental impact of all of the potential reactor designs and configurations
put forward by OPG as options for the Project.
[183]
The Panel made it
clear that if the reactor technology ultimately selected for the Project is
fundamentally different from the specific reactor technologies bounded by the
PPE, then a new EA would need to be conducted. The Panel also acknowledged that
the PPE approach was “a departure from a more standard approach where the major
components of the project are defined in advance of an environmental
assessment,” yet nevertheless accepted “the use of a plant parameter envelope
for environmental assessment purposes as an approach that allows the prediction
of adverse environmental effects for a select group of reactor technologies.”
[184]
On the evidence
before me in this application, and apart from the specific instances referred
to below, the Applicants have not established that this conclusion was
unreasonable, given the facts before the Panel. In Friends of the Island,
above, Justice Reed made it clear that the issue is not whether a project is at
the concept stage or at a more specific design stage, but whether a project is
at a stage when its environmental impact can be fully considered. This approach
was endorsed by the Federal Court of Appeal in Inverhuron (FCA), above,
where Justice Sexton accepted the reference design approach put forward in that
case and concluded that the methodology selected by the proponent provided the
Minister with a rational basis to conclude that the project was not likely to
cause significant adverse environmental impacts.
[185]
The CEAA contains no prescriptive
method for conducting an assessment. The Applicants say that a meaningful
practical assessment requires, in this case at least, that a specific reactor
technology be chosen and identified to the Panel. However, s. 11(1) of the CEAA
expressly requires that federal authorities ensure that an EA is conducted as
early as is practicable in the planning stages of a project and before irrevocable
decisions are made. So the statutory language of practicability, in my view, is
the key concept for determining how and when an EA should be conducted. This
will be a question of fact in each case. In the present case, the Panel found
that, given all of the submissions that had been made, it was in a position to
conduct an EA of the Project in accordance with the CEAA. The Applicants have
not demonstrated that this was an unreasonable conclusion. This does not mean,
however, that all aspects of the Project were appropriately dealt with by the
Panel, and I have set out later in these reasons where I think the Panel did
not reasonably address specific topics of concern.
[186]
I agree with the
Applicants that the Panel was obliged to act, in particular, in accordance with
ss. 15(3), 16(1) and (2) and 34 of the CEAA. The basic complaint is that the
Panel did not assess key aspects of the Project and left too much to future
study, analyses and decisions that would be made by others. The fundamental
issue is whether, given the information and submissions before the Panel, its
conclusion that the Project would not likely give rise to adverse environmental
consequences was reasonable, and whether the Panel reasonably complied with the
CEAA and set out the evidentiary basis upon which the s. 37 decision-makers
could make their decisions.
[187]
Section 15 of the Act
relates to the Minister’s scoping decision, and s. 15(3) must be read in that
context. It says that where a project is in relation to a physical work, the EA
must include “every construction, operation, modification, decommissioning,
abandonment or other undertaking in relation to that physical work that is
proposed by the proponent or that is, in the opinion of… the Minister, after
consulting with the responsible authority, likely to be carried out in relation
to that physical work” (CEAA, s. 15(3)). This ensures that project components
or activities are not scoped out of the assessment. The Applicants have not
pointed to any Project components (activities or undertakings relating to the
Project) that were completely left out of the assessment in this case; rather,
their complaint is with the level of information that was available to assess
some of the project components. Thus, the real focus of the analysis here must
be on the obligations set out in ss. 16 and 34 of the Act.
[188]
As the Court has
previously observed, certain “guiding tenets” can help to interpret the scope
of these duties, including the precautionary principle and that of adaptive
management (Pembina Institute, above, at para 33). In assessing where
the line should be drawn between applying the “precautionary approach” and
allowing for “adaptive management,” there is considerable guidance in the CEAA
itself and in the case law.
[189]
First of all, we know
that, in accordance with s. 11(1) of the CEAA, an EA has to be conducted as “early
as practicable in the planning stages of the project and before irrevocable
decisions are made… .” Several cases have pointed out that a panel's role is
one of information gathering and recommending, and that finality and certainty
in EAs are simply not possible. In Express Pipelines, above, for
example, Justice Hugessen describes the role of the panel as follows:
[14] Finally, we were asked to find that the panel had improperly
delegated some of its functions when it recommended that certain further
studies and ongoing reports to the National Energy Board should be made before,
during and after construction. This argument misconceives the panel's
function which is simply one of information gathering and recommending. The
panel's view that the evidence before it was adequate to allow it to complete
that function "as early as is practicable in the planning stages ... and
before irrevocable decisions are made" (see section 11(1)) is one with
which we will not lightly interfere. By its nature the panel's exercise is
predictive and it is not surprising that the statute specifically envisages the
possibility of "follow up" programmes. Indeed, given the nature of
the task we suspect that finality and certainty in environmental assessment can
never be achieved.
[emphasis added]
[190]
It is the principle
of adaptive management that, as the Federal Court of Appeal pointed out in Parks
and Wilderness Society, above, is required to deal with the difficulties of
predicting all of the consequences of a project on the basis of existing
knowledge:
[24] The concept of "adaptive management" responds to the
difficulty, or impossibility, of predicting all the environmental consequences
of a project on the basis of existing knowledge. It counters the potentially
paralysing effects of the precautionary principle on otherwise socially and
economically useful projects. The precautionary principle states that a project
should not be undertaken if it may have serious adverse environmental
consequences, even if it is not possible to prove with any degree of certainty
that these consequences will in fact materialise. Adaptive management
techniques and the precautionary principle are important tools for maintaining
ecological integrity.
[191]
In Pembina
Institute, above, Justice Tremblay-Lamer of this Court followed Justice
Hugesson in Express Pipelines, above, and emphasized the “ongoing and
dynamic” nature of environmental assessment:
[23] The adequacy and completeness of the evidence must be evaluated
in light of the preliminary nature of a review panel's assessment. In Express
Pipelines, supra, at para. 14, Hugessen J.A. discussed the predictive and
preliminary nature of the panel's role:
The panel's view that the evidence before it was adequate to allow it to
complete that function "as early as is practicable in the planning stages
... and before irrevocable decisions are made" (see section 11(1)) is one
with which we will not lightly interfere. By its nature the panel's exercise is
predictive and it is not surprising that the statute specifically envisages the
possibility of "follow up" programmes. Indeed, given the nature of
the task we suspect that finality and certainty in environmental assessment can
never be achieved.
This view was echoed in Inverhuron & District Ratepayers'
Association v. Canada (Minister of the Environment), 2001 FCA 203, [2001]
F.C.J. No. 1008 (QL), at para. 55, by Sexton J.A. Therefore, given the
predictive function of an environmental assessment and the existence of
follow-up mechanisms envisioned by the CEAA, the Panel's assessment of
significance does not extend to the elimination of uncertainty surrounding
project effects.
[24] Similarly, it is evident that the assessment of environmental
effects, including mitigation measures, is not to be conceptualized as a
single, discrete event. Instructively, in Union of Nova Scotia Indians
v. Canada (Attorney General), [1997] 1 F.C. 325, [1996] F.C.J. No. 1373
(QL), Mackay J. indicated, at para. 32 that he was not persuaded that the CEAA
requires that all the details of mitigating measures be resolved before the
acceptance of a screening report. He further asserted that the nature of the
process of assessment was "ongoing and dynamic" with continuing
dialogue between the proponent, the responsible authorities and interested
community groups.
[emphasis added]
[192]
Subsection 16(1)(d) of
the CEAA mandates the Panel to consider
measures that are technically and economically feasible and that would
mitigate any significant adverse environmental effects of the project…
[193]
Likewise, s. 16(2)(c)
requires the Panel to consider
the need for,
and the requirements of, any follow-up program in respect of the project…
As the Panel notes at p. 40 of the EA
Report, mitigation and follow-up are distinct concepts. Both are defined in s.
2(1) of the Act. Mitigation is about eliminating, reducing or controlling a
project’s adverse effects; follow-up is about verifying the accuracy of the EA,
or the effectiveness of mitigation measures.
[194]
Subsection 34(c)(i)
requires the Panel, in its report, to deal with mitigation measures and
follow-up programs.
[195]
Under s. 16(1) and
16(2) of the CEAA, the Panel was obliged to undertake a “consideration” of the
designated factors. The definition of “assessment by a review panel” in the Act
also refers to a “consideration” of the factors to be considered under s. 16(1)
and 16(2). The form and extent of any such consideration is not stipulated.
However, the scheme of the Act suggests to me that an expert panel, such as the
one established in this case, is required to use its expertise to gauge the
extent and form of “consideration” required in each particular case in order to
facilitate the purposes of the Act as set out in s. 4(1), which reads as
follows:
Purposes
4. (1) The purposes of this Act are
(a) to ensure
that projects are considered in a careful and precautionary manner before
federal authorities take action in connection with them, in order to ensure
that such projects do not cause
significant
adverse environmental effects;
(b) to
encourage responsible authorities to take actions that promote sustainable
development and thereby achieve or maintain a healthy environment and a
healthy economy;
[…]
(d) to ensure
that there be opportunities for timely and meaningful public participation
throughout the environmental assessment process.
|
Objet
4. (1) La présente loi a pour objet :
a) de veiller à ce que les projets soient
étudiés avec soin et prudence avant que les autorités fédérales prennent des
mesures à leur égard, afin qu’ils n’entraînent pas d’effets
environnementaux négatifs importants;
b) d’inciter ces autorités à favoriser un
développement durable propice à la salubrité de l’environnement et à la santé
de l’économie;
[…]
d) de veiller à ce que le public ait la
possibilité de participer de façon significative et en temps opportun au
processus de l’évaluation environnementale
|
[196]
In my view, these
provisions make it obvious that the Panel in the present case was obliged to
consider whether, in its expert opinion, the Project would, or would not, cause
significant adverse environmental effects. In so doing, it was also obliged
under s. 34 of the Act to, inter alia, prepare a report setting out
the rationale, conclusions and recommendations of the panel relating to
the environmental assessment of the project, including any mitigation measures
and follow-up program…
[197]
Once again, the form
of the report, its rationale, conclusions and recommendations are left to the
expert Panel to determine in accordance with the objectives of the CEAA.
[198]
In attacking the EA Report
as inadequate, the Applicants are to a considerable extent asking the Court to
assess and reweigh the methodology and conclusions of an expert panel. This is
not the role of the Court. It is true that s. 16(1) and (2) of the CEAA mandate
the “consideration” of certain factors, but the way this is done and the weight
to be ascribed to each factor is left to the expert Panel to be assessed in
accordance with the purposes of the Act.
[199]
Subsection 16(1) and
(2) also compel the Panel to consider mitigation and the need for, and
requirements of, any follow-up program. The Act does not say that the Panel itself
is responsible for mitigation and follow-up and, as the purposes of the Act set
out in s. 4 and the governing case law make clear, environmental protection is
an ongoing, cooperative responsibility.
[200]
Overall, then, it
seems to me that what the Panel was obliged to do in this case was to assess
the environmental impacts of a project that will extend many years into the
future, and that will require the involvement and cooperation of different
levels and agencies of government, and that will also require future mitigation
and follow-up. This is a highly complex exercise and the Federal Court of
Appeal has said that “given the nature of the task we suspect that finality and
certainty in environmental assessment can never be achieved.” See Express
Pipelines, above, at para 14.
[201]
In the present case,
the Applicants take the view that the CEAA required the Panel to deliver
considerably more finality and certainty than the Panel, in its expert opinion,
felt the need to provide, given the nature of this Project. As the record shows,
the Applicants and other interveners were able to bring before the Panel their
strong objections to the Project and the Panel’s approach to assessing its environmental
impacts throughout the assessment process. The Panel did not accept the Applicants’
criticisms of the PPE and bounding approach and the Applicants’ assessment as
to why such an approach would not produce a meaningful EA in accordance with
the Act. Disagreement is not a ground for judicial review. Hence, provided the
Panel acted in accordance with the CEAA and observed contextual rules of
procedural fairness, the Court cannot interfere. In my view, then, many of the
issues raised by the Applicants relate to the weighing and significance of the
evidence and conclusions drawn from that evidence by the Panel. Justice Scott (as
he then was) recently had occasion to emphasize that this kind of issue
requires review on a standard of reasonableness in Conseils des Innus de
Ekuanitshit, above:
[69] In Pembina Institute for Appropriate Development v Canada (Attorney General), 2008 FC 302 at para 37 [Pembina], Justice
Tremblay-Lamer summarized the jurisprudence regarding the standard of review to
be applied to decisions taken under section 16 of the CEAA:
All parties agree that to the extent that the issues posed involve the
interpretation of the CEAA, as questions of law, they are reviewable on a
standard of correctness (Friends of West Country Assn. v. Canada (Minister
of Fisheries and Oceans), [2000] F.C. 263, [1999] F.C.J. No. 1515 (QL), at para.
10; Bow Valley Naturalists Society v. Canada (Minister of Canadian Heritage),
2001 CanLII 22029 (FCA), [2001] 2 F.C. 461, [2001] F.C.J. No. 18 (QL), at para. 55). However, issues relating to weighing the significance of the evidence
and conclusions drawn from that evidence including the significance of an
environmental effect are reviewed on the standard of reasonableness simpliciter
(Bow Valley, cited above, at para. 55; Inverhuron, cited above,
at paras. 39-40).
[70] The issue in the present case is whether the JRP could, despite
a lack of certain information, validly conclude that the Project's impact on
the Applicant's use of the land for traditional purposes would be negative but
not significant after mitigating matters are implemented. This is clearly a
question dealing with 'weighing the significance of the evidence and
conclusions drawn from that evidence including the significance of an
environmental effect'. The standard of review on such a question is
reasonableness (see Pembina, cited above, at para 37).
[71] It is also worth noting that much more recently, in Grand
Riverkeeper, Labrador Inc v Canada (Attorney General), 2012 FC 1520 [Grand
Riverkeeper], Justice Near re-assessed the standard of review applicable to
the same question in light of the four factors described in Dunsmuir v New
Brunswick, 2008 SCC 9, [2008] S.C.J. No. 9 [Dunsmuir], namely (1)
the existence of a privative clause; (2) the purpose of the tribunal as
determined by interpreting the enabling legislation; (3) the expertise of the
tribunal; and (4) the nature of the question at issue (Dunsmuir, above,
at para 64). He also concluded that the standard of review on such questions is
reasonableness (see Grand Riverkeeper, above, at para 40).
[202]
As Justice Hugessen
pointed out in Express Pipelines, above, at para 14, the “panel’s view
that the evidence before it was adequate to allow it to complete that function
‘as early as is practicable in the planning stages…and before irrevocable
decisions are made’ (see section 11(1)) is one with which we will not lightly
interfere.”
[203]
The Applicants assert
reviewable error in this application in two principal ways. First of all, they
say that the Panel’s failure to assess or specify a reactor technology undermined
its ability to properly evaluate the environmental effects of the Project and
to otherwise fulfill its duties under the CEAA and the Terms of Reference.
Secondly they say that the vague and schematic nature of the Project led the
Panel to unlawfully delegate its duties under the CEAA to other bodies.
[204]
The Applicants say
that the Panel’s failure to discharge its CEAA duties in key areas is
particularly evident in its handling of specific reactor technology, specific
site design layout, a specific water cooling option, a specific used nuclear
fuel storage option, and a long-term radioactive waste management option.
[205]
The Applicants argue (at
paragraph 58 of their Memorandum) that:
In failing to gather necessary information about the environmental effects
of the Project, the [Panel] failed to discharge its duties under subsections
34(a) and (b) of the CEAA to gather, disclose, and hold public hearings on
information required by subsections 16(1) and (2) and the [Panel] Terms of
Reference. This non-delegable duty falls upon the [Panel] itself, and does not
depend upon the success or failure of the proponent, public agencies or
interveners in producing information at the public hearing. Moreover, it is
impossible to have a meaningful public hearing on a “project” that lacks
specificity or where fundamental information is absent. Thus, it is not
sufficient for the purposes of subsections 34(a) and (b) for the [Panel] to
identify missing information, but then simply recommend future studies,
information-gathering, and analysis to fill these gaps after the EA process has
concluded. By establishing the “stringent” review panel process, Parliament
clearly intended that such steps take place, and be fully subject to public
involvement, as part of the EA process itself.
[206]
When I examine each
of these important areas in the EA Report, it seems to me that they are
addressed by the Panel, but not necessarily in the way that the Applicants feel
they should have been addressed. The Applicants are advocating a particular
approach to environmental assessment under the CEAA that would require of
proponents much more in the way of specifics than OPG provided in this case.
Whether or not that would be a better approach to environmental assessment is
not the issue before me. The issue is whether the scheme of the Act, and the
guidance in the jurisprudence, required the Panel to go further than it did in
this case.
[207]
The Panel makes clear
in its conclusions that
the Project is not likely to cause significant adverse environmental
effects, provided the mitigation measures proposed and commitments made by OPG
during the review and the Panel’s recommendations are implemented.
(EA Report at p. 143)
[208]
In other words, the
Panel’s general conclusion is contingent upon mitigation and the future fulfilment
of commitments. The safety and environmental impacts of the Project are
dependent upon what OPG and other agencies do in the future as the Project evolves,
and as OPG applies for the separate licences required for each successive phase.
The Panel is rendering an opinion on environmental impact at a very early stage
in life of this Project. The EA Report amounts to an opinion that, based upon
present knowledge, and if appropriate measures are taken, then the Project is
not likely to cause significant adverse environmental effects. Many will
disagree but, as things presently stand, Parliament has decided that this is
the range and function of an EA under the CEAA. The Panel must ensure that s.37
decision-makers have a sufficient evidentiary record upon which to base their
decisions, and it can make recommendations for follow-up and mitigation to
ensure that its conclusions continue to hold. However, it is not required and
has no jurisdiction to monitor those recommendations and ensure that
commitments and expectations are met. That role must, by necessity, be left to
other agencies and responsible authorities.
[209]
In essence, the
Applicants are saying that the information available to the Panel in this case
was not specific enough to even make contingent predictions about the environmental
effects of this Project. In my view, however, apart from those instances that I
set out below, I cannot say that the Panel’s approach was, given the nature of
this Project and the full context in which the EA Report was produced, not in
accordance with the requirements of the Act or that it was unreasonable.
Section 34(1) of the Act specifically directs the Panel to set out any
mitigation measures and follow-up program which it feels are required. Such
mitigation measures and follow-up must, inevitably, be assessed, executed and
monitored by others in the future.
[210]
As Justice
Tremblay-Lamer pointed out in Pembina Institute, above,
[34] In sum, the CEAA represents a sophisticated legislative system
for addressing the uncertainty surrounding environmental effects. To this end,
it mandates early assessment of adverse environmental consequences as well as
mitigation measures, coupled with the flexibility of follow-up processes
capable of adapting to new information and changed circumstances. The dynamic and
fluid nature of the process means that perfect certainty regarding
environmental effects is not required.
[211]
As the AGC points out
in this application, the full regulatory context in which this decision was
made by the Panel includes the subsequent permitting and licensing processes
that will, in their turn, assess and manage certain Project effects. See, in
this regard, West Vancouver, above, at para 104; and Inter-Church
Uranium Committee, above, at paras 47 and 49. As discussed below in
relation to these cases, this does not relieve the Panel of the responsibility
of assessing the Project’s effects; it is simply an acknowledgment that the
process of assessing and managing those effects does not end with the
completion of the EA.
[212]
In Inter-Church
Uranium Committee, above, the Federal Court of Appeal provided the
following guidance on point:
[47] That does not mean that the end of the work of the Panel means
an end to all environmental review for the McClean Lake Project. Environmental
issues must be considered for each licence issued under the Uranium and Thorium
Mining Regulations and their successor, the Uranium Mines and Mills
Regulations. In addition, the CEAA environmental screening and assessment
process may be triggered in future if subsection 74(3) of the CEAA applies.
That would be the case if, for example, there is a proposal to undertake some
activity relating to the McClean Lake Project that was not within the Panel's
terms of reference (such as the increase in production proposed and permitted by
the Commission in 2001, which had not been considered by the Panel established
under the Guidelines).
[…]
[49] …The Panel recognized that changes in science and technology
would occur over the life of the Project and acknowledged that it would be the
Board's responsibility to evaluate the effects of these developments in the
context of its licensing responsibilities.
[213]
This approach is also
consistent with Pembina Institute, above, where Justice Tremblay-Lamer,
following Justice Mackay in Union of Nova Scotia Indians, above, pointed
out that the assessment of environmental effects, including mitigation
measures, is not to be conceptualized as a single, discrete event, but is
ongoing and dynamic “with continuing dialogue between the proponent, the
responsible authorities and interested community groups.”
[214]
The Applicants are
correct to point out that the Panel is not a “responsible authority,” but s. 34(c)(i)
of the Act clearly requires the Panel to address mitigation measures and
follow-up programs which, inevitably, will be part of an ongoing process
involving, among others, responsible authorities and regulatory agencies. This
does not relieve the Panel from compliance with ss. 34, and 16(1) and (2) of
the Act; it simply means that the full context has to be considered in
accordance with the purposes of the Act set out in s. 4. The Panel explains its
cautionary approach to assessing environmental effects in the EA Report and
makes it clear that “adaptive management” should not be used as a substitute
for scientific data:
4.1.1 The Precautionary Approach
OPG described how it applied the precautionary principle in the
preparation of the EIS, as required by the EIS Guidelines and based on the
Canadian Privy Council Office document A Framework for the Application of
Precaution in Science-based Decision Making About Risk (Government of Canada,
2003). OPG stated that it considered this principle in the design of the
Project and in its assessment of environmental effects.
The Panel notes that the application of the precautionary principle
according to the Canadian Privy Council Office framework is not necessarily in
line with the wishes of some of the participants in the review and that
different interpretations of the concept were put forward.
One of the purposes of the Canadian Environmental Assessment Act is to
ensure that projects are considered in a careful and precautionary manner so
that they do not cause significant adverse environmental effects. In the administration
of the Act, the Government of Canada, the Minister of the Environment, the Canadian
Environmental Assessment Agency and all federal and responsible authorities are
required to exercise their powers in a manner that protects the environment and
human health and that applies the precautionary principle. The Panel notes that
the Canadian Privy Council Office framework was issued to improve the predictability,
credibility and consistency of the federal government’s application of
precaution to ensure adequate, reasonable and cost-effective decisions.
The framework outlines five guiding principles for the application of
precaution to science-based decision making in areas of federal regulatory activity
for the protection of health and safety and the environment and the
conservation of natural resources. They are:
1.
The application of
precaution is a legitimate and distinctive decision-making approach within risk
management;
2.
It is legitimate that
decisions be guided by society’s chosen level of protection against risk;
3.
Sound scientific
information and its evaluation must be the basis for applying precautions; the
scientific information base and responsibility for producing it may shift as
knowledge evolves;
4.
Mechanisms should
exist for re-evaluating the basis for decision and for providing a transparent
process for further consideration; and
5.
A high degree of
transparency, clear accountability and meaningful public involvement are
appropriate.
The Panel agrees with these guiding principles for the application of
science-based decision making but highlights the importance of defining the
affected society when considering the concept of society’s level of tolerance
for risk. The Panel notes that people in Durham Region are the group with the
highest potential to be affected by the Project but, in general, are also more
accepting of the risks of or potential for environmental effects. Neighbouring
populations around Lake Ontario, including the Greater Toronto Area, could also
be affected by the Project, but, anecdotally have less tolerance for project-associated
risks.
The framework also outlines the five following principles for
precautionary measures:
1.
Precautionary
measures should be subject to reconsideration on the basis of the evolution of
science, technology and society’s chosen level of protection;
2.
Precautionary
measures should be proportional to the potential severity of the risk being
addressed and to society’s chosen level of protection;
3.
Precautionary
measures should be non-discriminatory and consistent with measures taken in
similar circumstances;
4.
Precautionary
measures should be cost-effective, with the goal of generating (i) an overall
net benefit for society at least cost, and (ii) efficiency in the choice of
measures; and
5.
Where more than one
option reasonably meets the above characteristics, then the least trade-restrictive
measure would be applied.
In consideration of the Project and the five principles for precautionary
measures, the Panel notes that for principle 2, the required measures could be
extensive if proportional to the severity of the risk. Furthermore, where there
are threats of serious or irreversible damage, the Panel is of the view that
the federal government should be proactive and not wait for scientific
certainty or occurrence of an incident to take action, as for instance with a
severe nuclear accident or events resulting from climate change. Because of the
potential for high magnitude effects as a result of nuclear projects, the Panel
believes that the precautionary principle should be applied to prevent
environmental degradation and protect citizens in the context of society’s
chosen level of protection.
With respect to principles 3 and 5, the Panel acknowledges that the
nuclear industry is continually adjusting to new circumstances. Security
systems and environmental protection measures have to evolve with each
malfunction or accident. The Panel is of the view that the protection of
citizens and physical environmental components may require the development of
new or improved measures that do not necessarily have similar circumstances, or
are least-trade restrictive.
In considering principle 4, the Panel emphasizes that while cost is a
consideration, safety and security must always take precedence.
The Panel therefore underlines the need to identify and recommend measures
beyond existing standards and practices, when appropriate, to protect the
public and the environment.
[…]
4.1.3 Assessment of Environmental Effects
The first major task of the Panel was to review the proponent’s assessment
of the environmental effects of the Project. The Panel found that the
assessment of potential environmental effects was qualitative in many respects
because it was conducted without specific knowledge of potential releases. OPG
explained that certain parameters of the bounding scenario, such as hazardous
substance emissions and on-site chemical inventories, could not be developed
until a specific reactor technology has been selected by the Government of
Ontario. Where information specific to the chosen reactor technology is required,
the Panel recommends that certain actions be taken before the Project can
proceed.
The Panel is responsible for determining the likelihood that the Project
will cause significant adverse environmental effects, taking into account the
implementation of any mitigation measures that it considers appropriate. In
this matter, the Panel followed the Canadian Environmental Assessment Agency
reference guide entitled Determining Whether a Project is Likely to Cause
Significant Adverse Environmental Effects (November 1994).
The Panel first determined whether an environmental effect would be
adverse by comparing the quality of the existing environment with the predicted
quality once the Project is in place. When an effect was determined to be
adverse, the Panel proceeded to determine its significance. In this regard, the
Panel considered the magnitude, geographic extent, duration and frequency,
reversibility, and ecological context, as applicable, of the effect. Finally,
the Panel determined whether the significant adverse effect is likely to occur.
Two criteria are considered when determining the likelihood: the probability of
occurrence and scientific uncertainty, which is often referred to as confidence
limits.
Contrary to the 1994 guide, OPG included likelihood as a parameter in the
assessment of significance. To ensure that the application of mitigation
measures or follow-up programs is carefully considered, the Panel believes that
the significance of an effect should be determined before assessing its
likelihood. For instance, to ensure that mitigation is developed for a severe nuclear
accident, the significance of the effects of the accident should be determined
before concluding that its likelihood is so remote that its effects are not
significant. The Panel believes that a prudent approach should be taken in this
situation to identify appropriate mitigation measures despite the remote
likelihood of occurrence.
The Panel considered technically and economically feasible measures to
mitigate any significant adverse environmental effects of the Project and
alternative means to undertaking the Project. OPG provided a number of
mitigation measures and plans, and indicated that details would be forthcoming
at later stages of the Project, such as following the Government of Ontario
selection of a reactor technology.
To address the absence of detailed mitigation plans, CNSC staff have
recommended to the Panel that a condition of the Licence to Prepare Site be
that OPG shall have the requisite plans accepted by the Canadian Nuclear Safety
Commission or CNSC staff prior to commencing applicable licensed activities.
The Panel accepts this recommendation and adds that the monitoring program and compensation
plans should be treated in the same manner.
Finally, the Panel notes the distinction between monitoring and follow-up
programs, as well as between mitigation measures and compensation plans. The
Panel regards monitoring to be observation and the acquisition of knowledge, whereas
follow-up is specifically developed to confirm predictions from the
environmental assessment and the effectiveness of mitigation. The Panel is
of the view that adaptive management, a systematic process for the continuous
improvement of environmental management practices, should only be applied in cases
where thresholds can be defined. Adaptive management should not be used to
overcome a situation where there is a lack of scientific data or certainty.
[emphasis added]
[215]
Notwithstanding the
Applicants’ understandable concerns about a project of this size and duration,
and their views and able arguments about what the Panel should have done, apart
from the specific instances referred to below, I can find no evidence to
suggest that the Panel did not follow these guiding principles to reach a
science-based decision that the s. 37 decision-makers could rely upon, or that
it substituted adaptive management for scientific data or certainty.
[216]
The evidence put
forward by the Applicants before me relates primarily to information gaps
before the Panel. The alleged gaps and deficiencies are set out most
comprehensively in the affidavit of Kathleen Cooper, a Senior Researcher at CELA
(Applicant’s Record, Vol 4, Tab 4) at paras 104-130 [Cooper affidavit]. Ms.
Cooper alleges that the EA Report itself identified the following gaps (with
references to the EA Report), renumbered and condensed here for convenience:
- No specific reactor technology has
been selected (pp. 45-46)
- No specific method or location (i.e.
on-site, off-site or lake infill) for managing excavated soil or rock has
been selected (p. 46)
- No specific condenser technology has
been selected (p. 48-49)
- OPG’s assessment of condenser
cooling systems “did not provide a definitive comparison of alternative
options with respect to environmental effects” (p. 49)
- No specific site layout design has
been selected, although three “conceptualized” scenarios were presented by
OPG (pp. 12, 13, 49)
- The assessment of potential
environmental effects “was conducted without specific knowledge of
potential releases” from the Project because a reactor technology has not
been selected (p. 39)
- Certain “parameters of the bounding
scenario, such as hazardous substance emissions and on-site chemical
inventories, could not be developed until a specific reactor technology
has been selected” (p. 39)
- There was an “absence of detailed
mitigation plans” because a specific reactor technology had not been
selected (p. 39)
- Only a “conceptual” decommissioning
plan was presented in the EIS (pp.51-53)
- OPG did not provide a detailed
monitoring program or compensation plan in relation to potential
environmental effects (pp. 39-40)
- OPG did not present a follow-up
program, adaptive management program, or action plan in relation to
certain air contaminants of concern (pp. 59-60)
- OPG’s description of baseline
geological conditions “is based on an investigation that appears to be
limited in scope” (p. 63)
- OPG acknowledged that radiological
and non-radiological contaminants from the Project would enter the aquatic
environment, but did not specify any release points for discharges into Lake Ontario , provide baseline data for water quality and sediment, or complete “an
assessment of bounding scenarios for conventional liquid effluents”. It
also provided “little information about the pollutants and contaminant
loadings that would enter the surface water from stormwater runoff” (pp.
64-65)
- OPG did not undertake a detailed
assessment of ingress or transport of groundwater contaminants due to
on-site activities, or the cumulative effects of quarrying activities or
dewatering on nearby lands (pp. 66-67)
- OPG “did not provide a thorough
examination of potential site layout options” (p. 73)
- OPG did not present a follow-up
program to verify environmental assessment predictions or assess the
effectiveness of mitigation measures in relation to birds, mammals,
insects, amphibians, reptiles, or landscape connectivity (pp. 68, 75, 78)
- OPG did not present a management
plan for the several species at risk known to occur at the Project site
(pp. 75-77)
- OPG did not provide specific details
on the types or amounts of chemicals to be stored or used at the site, and
cannot do so until a reactor technology is selected (p. 78)
- Only a “limited amount” of fish data
and sampling information was available, and more studies are needed to
understand the effects of shoreline alteration (pp. 80-81)
- OPG’s “assessment of effects of
geotechnical and seismic hazards [was] based on limited baseline
information” (p. 86)
- OPG’s climate change assessment “was
based on very general projections that are not specific to the Project”
(p. 88)
- OPG did not present a contingency
plan for all Project phases to account for flooding or other extreme
weather events (p. 89)
- No specific on-site facility (or
location) for interim or long-term storage of used nuclear fuel or low and
intermediate level radioactive waste has been selected (pp. 116-118)
- OPG did not present a detailed
analysis of the offsite health and environmental effects of a severe
reactor accident since no reactor technology had been selected (pp.
124-125)
- OPG did not present a cumulative
effects analysis in relation to “common cause” severe accidents affecting
multiple reactors at the Darlington site (p. 133)
[217]
Some of these alleged
information gaps are linked to the fact that technology and design choices for
the Project had not yet been made, and some are not.
[218]
In addition to these
alleged gaps, the Cooper affidavit notes the following with respect to the EA
Report’s findings with respect to the Project’s environmental effects:
- The Project’s cumulative effect upon
the aquatic environment “would be significant and likely to occur” unless
“appropriate” mitigation measures are put in place (p. 131)
- There may be a cumulative effect
upon regional air quality from several sources in the vicinity of the
Project (p. 132)
- The radioactive waste generated by
the Project could result in significant cumulative effects “related to
doses to workers, the public and the environment if it is not properly
managed should it remain permanently on site” (p. 132)
- Despite OPG’s proposed mitigation
measures and compensation plans, “there may still be a risk of losing
biodiversity” (p. 134)
- There will be a change to “surface
water quality in Lake Ontario in relation to tritium due to the increase
in tritium releases from the Project” (p. 135)
- The Project’s effects on the round
whitefish “may be greater than were originally predicted by OPG” (p. 135)
[219]
Other affidavits
filed by the Applicants identify similar concerns (see Affidavit of Mark Mattson,
President of Lake Ontario Waterkeeper, Applicant’s Record, Vol. 6, Tab 5 at
paras 101-103 [Mattson affidavit]; Affidavit of Shawn-Patrick Stensil, Energy
Analyst and Campaigner for Greenpeace Canada, Applicant’s Record, Vol.1, Tab 3
at paras 78-81 [Stensil affidavit]; Affidavit of Brennain Lloyd, Project
Coordinator with Northwatch, Applicant’s Record, Vol. 7, Tab 6 at paras 30, 33,
36-37 [Lloyd Affidavit]).
[220]
The Mattson affidavit
covers many of the same concerns identified in the Cooper affidavit, and also
says that:
- The available cooling options have
vastly different potential impacts on fish and fish habitat, and
technologies to reduce fish impacts could not be specifically considered
during the hearing because of the lack of a detailed plant design (para
101 d. and e.)
- The Panel did not require OPG to
conduct or assess a “bounding scenario” for the release of hazardous
substances or conventional liquid effluents from the Project and what
impacts would result, and therefore there is no information on the record
regarding the pollution that may be released from the project to the air,
soil, groundwater, and Lake Ontario (para 101 h.)
[221]
In terms of evidence
to show that these information gaps made the EA non-compliant with the CEAA or
the Panel’s findings unreasonable, the Applicants have placed a particular
emphasis on the management of radioactive waste, as discussed below.
[222]
The Applicants’
central criticism of the EA Report is that it contains many information gaps as
a result of the use of the bounding scenario or PPE approach and the fact that
a reactor technology and a cooling option have not yet been chosen. Thus, an
important question before me is whether such information gaps make the EA
Report non-compliant with the CEAA.
[223]
In my view, in order
to substantiate an argument that the EA failed to comply with the CEAA, it is
necessary to go beyond identifying information gaps. There is no limit to the
amount of information that could be gathered, and thus “full” or perfect
information about a project or its effects will never be achieved.
[224]
The Applicants’
central point is that too much remains unknown about this Project for a proper
EA to have been conducted. Read as a whole, the EA Report reveals that the
Panel dealt with uncertainty in several different ways.
[225]
In some cases the
Panel called for further study of potential effects and how to mitigate them,
despite the fact that these effects were not expected to rise to the level of
significance. In my view, this reflects the principle of precaution and the
function of environmental assessment as an information gathering and planning
tool.
[226]
More controversially,
in several instances the Panel found that despite information gaps, it was
reasonable to conclude that the effects of the Project would not rise to the
level of significance, or could be mitigated so as to fall below the level of
significance. In doing so, the Panel appears to rely upon:
- bounding scenarios that assess or
estimate the Project’s maximum expected effects across all technology
options and design choices;
- information about options for
managing or mitigating the effects in question, including existing
practices in the nuclear industry; and
- an assessment that existing
regulatory regimes will adequately manage the Project’s effects, or that the
Project will not be permitted to proceed through subsequent licensing
stages unless adverse environmental impacts are appropriately managed and
mitigated.
[227]
All of these are seen
as problematic by the Applicants, to varying degrees. The latter in particular
is singled out for criticism as a form of impermissible delegation of the
Panel’s duties under the Act.
[228]
A careful reading of the EA Report shows that,
despite some information gaps about which the Applicant’s have expressed
understandable concerns, the Panel had sufficient information to conduct, and
did conduct, an EA that provided the s. 37 decision-makers with a proper
evidentiary foundation for the decisions they were required to make. That is,
the Panel enabled those decision-makers to make reasonable and science-based
decisions, despite some continuing uncertainties that will have to be managed
over time. However, three
aspects of the EA Report appear to me to be problematic and to require further
re-assessment by the Panel or a duly constituted alternative panel. They are:
- The alleged failure of the Panel to
insist on a bounding scenario analysis for hazardous substance emissions,
in particular liquid effluent and stormwater runoff to the surface water
environment, and for the sources, types and quantities of non-radioactive
wastes to be generated by the project;
- The Panel’s treatment of the issue
of radioactive waste management; and
- The Panel’s conclusion that an
analysis of the effects of a severe common cause accident at the facility
was not required at this stage, but should be carried out prior to
construction.
[229]
Because the Panel
dealt with several uncertainties by recommending future study and analysis, or
by taking into account future licensing steps, the issue of whether the Panel’s
conclusions regarding significant adverse effects were reasonable is closely
tied to the question of whether the Panel improperly delegated its duties in
some instances.
[230]
In assessing this
argument, I think it is important to be mindful of the structure of the
decision-making process Parliament put in place through the CEAA. The
Applicants say – unchallenged by the Respondent – that while there will be
further licensing steps for the Project that will consider environmental
impacts, this EA is likely to be the only environmental assessment of the
Project that will occur under the CEAA or its successor legislation. They
argued both before the Panel and before the Court that, while further steps may
involve opportunities for public participation and consideration of
environmental impacts, the licensing process differs from an EA in important
respects (see for example the Mattson affidavit at paras 58, 65-66). In their
view, this difference is not merely one of timing, but involves the very nature
of the process within which environmental effects are considered.
[231]
I see merit in this
submission. CNSC licensing decisions differ from EAs in terms of the
legislative framework being applied and the identity of the decision-maker, and
this may have implications for how environmental considerations are evaluated.
[232]
Under the CEAA, the
ultimate decision-maker for projects referred to review panels is the Governor
in Council (in practical terms, the federal Cabinet), which decides whether the
responsible authorities will be permitted to take steps to enable the project
to move forward. Parliament chose to allocate this decision to elected
officials who are accountable to Parliament itself and, ultimately, to the
electorate.
[233]
Future licensing
steps for the Project involve decisions that will be made by the CNSC (as well
as DFO and others). The CNSC is a specialized body with extensive technical
expertise at its disposal, and will be required to assure itself at several
stages of the Project that OPG will make adequate provision for the protection
of the environment and human health (NSCA, s. 24(4)). However, the EA under
review here represents the only occasion when democratically elected and
accountable federal decision-makers will directly make a decision on whether
the Project should proceed.
[234]
In my view,
Parliament’s intention in allocating certain roles and decisions to expert
bodies, and others to democratic bodies such as the federal Cabinet, must be
considered and respected.
[235]
The most important
role for a review panel is to provide an evidentiary basis for decisions that
must be taken by Cabinet and responsible authorities. The jurisprudence
establishes that gathering, disclosing, and holding hearings to assemble and
assess this evidentiary foundation is an independent duty of a review panel,
and failure to discharge it undermines the ability of the Cabinet and
responsible authorities to discharge their own duties under the Act.
[236]
In Pembina
Institute, above, Justice Tremblay-Lamer discussed the interconnection
between the role of a review panel, which is charged with conducting a
fact-based assessment, and that of political decision-makers, who are “mandated
to take into account the wider public policy factors in granting project approval”:
[14] The CEAA establishes a two-step decision-making process. The
first step is an environmental assessment where potentially adverse
environmental effects of a project are analysed (s. 5). The second step
involves decision-making and follow-up where a federal authority decides,
taking into consideration that assessment, if a particular project should be
authorized and what follow-up measures, if any, are required to verify the
accuracy of the assessment and the effectiveness of mitigation measures (ss. 37
and 38).
[…]
[20] Specifically, the general duties that a review panel is mandated
to fulfill are four-fold (s. 34). First, it must ensure that the information
required for an assessment is obtained and made available to the public (s.
34(a)). Second, the panel is required to hold hearings in a manner that offers
the public an opportunity to participate in the assessment (s. 34(b)). Third,
the panel is charged with fulfilling a reporting function whereby it must
prepare a report setting out “the rationale, conclusions and recommendations of
the panel relating to the environmental assessment of the project, including
any mitigation measures and follow-up program” as well as a summary of public
comments received (s. 34(c)). Finally, it must submit that report to the
Minister and the responsible authority (s. 34(d)).
[…]
[72] While I agree that the Panel is not to engage in policy
recommendation, nevertheless, it is tasked with conducting a science and
fact-based assessment of the potential adverse environmental effects of a
proposed project. In the absence of this fact-based approach, the political
determinations made by final decision-makers are left to occur in a vacuum.
[73] I recognize that placing an administrative burden on the Panel
to provide an in-depth explanation of the scientific data for all of its
conclusions and recommendations would be disproportionately high. However, given
that the Report is to serve as an objective basis for a final decision, the
Panel must, in my opinion, explain in a general way why the potential
environmental effects, either with or without the implementation of mitigation
measures, will be insignificant.
[74] Should the Panel determine that the proposed mitigation measures
are incapable of reducing the potential adverse environmental effects of a
project to insignificance, it has a duty to say so as well. The assessment
of the environmental effects of a project and of the proposed mitigation
measures occur outside the realm of government policy debate, which by its very
nature must take into account a wide array of viewpoints and additional factors
that are necessarily excluded by the Panel's focus on project related
environmental impacts. In contrast, the responsible authority is
authorized, pursuant to s. 37(1)(a)(ii), to permit the project to be carried
out in whole or in part even where the project is likely to cause significant
adverse environmental effects if those effects “can be justified in the
circumstances”. Therefore, it is the final decision-maker that is mandated
to take into account the wider public policy factors in granting project
approval.
[emphasis added]
[237]
In short, Parliament
has designed a decision-making process under the CEAA that is, when it
functions properly, both evidence-based and democratically accountable. The
CNSC, in considering future licensing decisions, will be in a fundamentally
different position from the Panel that has conducted the EA. The CNSC will be
the final authority making the decision, not merely an expert panel. Although
the CNSC approaches this role with considerable expertise, it does not have the
same democratic legitimacy and responsibility as the federal Cabinet.
[238]
This distinction is
particularly relevant, in my view, where issues require reference not simply to
scientific evidence, but to societal values and associated public policy
choices. For example, the document intended to provide federal decision-makers
with guidance on how to apply the precautionary principle set out in s. 4(2) of
the CEAA makes repeated reference to the need to consider and make decisions in
light of “society’s chosen level of protection against risk” (see Privy Council
Office, A Framework for the Application of Precaution in Science-based Decision
Making About Risk (Government of Canada, 2003)). This is conspicuously the type
of consideration that elected representatives, rather than expert bodies, seem
well-placed to evaluate.
[239]
Choices by the Panel
that could diminish the Cabinet’s ability to consider and decide such matters,
deferring them instead for consideration at a future date by an expert body,
could signal a departure from Parliament’s intention regarding the structure of
decision-making under the CEAA. The issue is not timing so much as Parliament’s
intention as to who should decide what.
[240]
In some cases, what
is left for the future will be verification that actual performance will
conform to the accepted standard of environmental or health protection (see EA
Report at p. 45). If this were the only purpose of environmental assessment,
presumably it could be left entirely to expert bodies. However, when it is the
appropriate standard itself that is at issue, or no standards exist, such an
approach can become problematic.
[241]
This does not mean
that future regulatory processes have no role to play in managing and
mitigating a project’s environmental effects, or that they should not factor
into a review panel’s analysis. Several examples in the present case illustrate
this point and are discussed later in these reasons.
[242]
The key substantive
point with respect to the decision-making structure of the CEAA is, in my view,
that it is the role of s. 37 decision-makers to decide what is an acceptable
level of environmental impact or risk. This decision-making component of the
Act is not its only important feature, but the language of s. 37, the
structure of the Act, and more than two decades’ experience with its
implementation make it undeniable that it is an important feature (see Pembina
Institute, above, at para 15 applying Oldman River, above, at para
103). We cannot simply read it out of the Act, and the courts and those charged
with its implementation must seek to maintain the integrity of the
decision-making structure that Parliament has put in place.
[243]
At the same time, one
cannot ignore the reality that many projects are subject to regulation by
specialized bodies with a public interest mandate that includes managing and
controlling the project’s environmental and health impacts. Indeed, over the
life of a project such as the one under consideration here, these other bodies may
well have the greatest effect in minimizing a project’s adverse effects if it
does gain Cabinet approval. Determining when these processes are a reliable
indicator that a project will not have significant adverse environmental
effects is not a simple matter. It may be necessary to consider the nature of
a regulatory regime itself, as regimes will vary widely in purpose and effect.
[244]
As a broad principle,
however, I think it is possible to say that in order to comply with its
obligations under ss. 16 and 34 of the CEAA, the Panel’s assessment should
provide an analysis of the actual expected effects of the Project, or some
established standard (or set of standards) to which the Project will be held
through subsequent regulatory steps. The latter is something of a substitute
for the former; after all, the CEAA requires the Panel to consider “the
environmental effects of the project” and their significance. Where neither of
these components is present, and there is evidence that an effect may be
significant, it is difficult to see how the Panel’s report can properly inform
the future decisions that must be made.
[245]
In the present case,
the PPE approach purports to deal with this issue by setting a boundary; if it
becomes clear later on that the Project will not conform to the boundary in
some important respect, a new EA may be required. In the current context, both
the EA Report and the Government Response state, and the parties appear to
agree, that the CNSC must assure itself prior to each new licence being issued
that the EA conducted on the Project still applies. The problem with any
significant gaps in the PPE is that they will compromise the integrity of this
rationale.
[246]
The rationale
underlying the bounding scenario or PPE approach is that it gives a
comprehensive picture of the maximum adverse effects that are likely to result
from the Project across a range of technology or design choices. The Panel
accepted the PPE as a valid approach based on this rationale, while acknowledging
that it is a departure from typical EA practices and posed some challenges for
the Panel. In my view, there is nothing unreasonable about this conclusion on
its face.
[247]
However, having
accepted this rationale and noted the associated challenges, I think it was
incumbent on the Panel to ensure the methodology was fully carried out, or to
explain why significant departures from it (that is, gaps in information about
the bounding scenario) did not make the assessment non-compliant with the CEAA.
[248]
No doubt, the reasons
must be read as a whole, in keeping with the principles from Newfoundland
and Labrador Nurses' Union v Newfoundland and Labrador (Treasury Board),
2011 SCC 62, [2011] 3 S.C.R. 708. That is, where the Panel does not explicitly
state such an explanation, the EA Report read as a whole may make it plain why
the Panel thought that gaps in the PPE were not fatal to its assessment.
However, where such explanations are neither explicit nor clearly implicit in
the Panel’s analysis, this could indicate a reviewable error that requires
further consideration.
[249]
This is particularly
so when one considers the challenges the PPE approach may pose for effective
public participation. The less specific the information provided about the
design features and specific impacts of a project, the more difficult it may be
for interested parties to challenge assumptions, test the scientific evidence,
identify gaps in the analysis, and ensure their interests are fully considered
(see EA Report at p. 32 regarding Environmental Assessment Transparency, and p.
33 regarding water quality and air quality).
[250]
The Applicants allege that there were gaps in
the bounding scenario that were so significant that, in law, the Panel did not
consider the environmental effects of the Project as required by s. 16 of the
CEAA. They point to the following observations in the EA Report as evidence of
this (emphasis added):
…The Panel found that
the assessment of potential environmental effects was qualitative in many
respects because it was conducted without specific knowledge of potential
releases. OPG explained that certain parameters of the bounding scenario,
such as hazardous substance emissions and on-site chemical inventories, could
not be developed until a specific reactor technology has been selected by the
Government of Ontario. Where information specific to the chosen reactor
technology is required, the Panel recommends that certain actions be taken
before the Project can proceed.
(EA Report at p. 39)
In the absence of
a choice of reactor technology for the Project, OPG did not undertake a
detailed assessment of the effects of liquid effluent and stormwater runoff to
the surface water environment. Instead, the
proponent committed to managing liquid effluent releases in compliance with
applicable regulatory requirements and to applying best management practices
for stormwater. This strategy does not comply with the expectations given in
the EIS Guidelines. Nevertheless, CNSC staff indicated that there is experience
of similar regulatory release limits and management practices being applied at
other nuclear facilities to control and minimize effects in the surface water
environment.
(EA Report at p. 65)
In response to a
Panel request for information on stored inventories of hazardous materials and
sources, types and quantities of non-radioactive wastes predicted to be
generated by the Project, OPG indicated that specific details regarding the
chemicals to be stored and used on the site could not be provided before a
reactor technology is selected for the Project. CNSC staff stated that the
OPG response was conditionally acceptable based on its review of previous
ecological risk assessments conducted at the site, an assessment of current
practices for hazardous chemical management at the Darlington Nuclear
Generating Station, and the need for a comprehensive assessment of hazardous
releases.
(EA Report at p. 78)
[251] Additional observations about gaps in the information provided due
to the absence of technology decisions can be found at page 21 (OPG did not
provide a bounding scenario for the release of hazardous substances for the
Project), pages 12-14 (details of site layout and development could not be
determined), page 15 (details regarding the manner in which the Project
facility will be operated could not be determined) and page 45 (aspects of the
PPE were based on preliminary design information that requires ongoing
verification).
[252]
On the other hand, the Respondents argue that:
- There was evidence before the Panel
regarding liquid effluent and stormwater runoff and it was able to conduct
the EA in this regard (Memorandum of CNSC at para 61). As evidence of
this, the CNSC points to: CNSC Panel Member Document [PMD], 11-P1.2
(January 31, 2011) at pp. 45-51 (Respondent’s Record (CNSC), Vol. 3, Tab
BB); CNSC Commission Member Document [CMD], 11-P1.3 (January 31, 2011) at
pp. 82-86 (Respondent’s Record (CNSC), Vol. 3, Tab BB; and OPG’s Environmental
Impact Statement [EIS] at pp. 5-1 to 5-195 (Chapter 5) (Respondent’s
Record (OPG), Vols. 2 – 5, Tab 10); and
- OPG’s responses provided sufficient
evidence regarding the sources, types and quantities of non-radioactive
waste to be generated by the Project to allow the Panel to conduct the EA
in this regard (Memorandum of CNSC at para 62). As evidence of this, the CNSC
points to the EA Report at p. 118 and OPG’s response to Information
Request #19 (Respondent’s Record (OPG), Vol. 6, Tab 19).
The PMD and CMD
cited by the Respondents are reports prepared by CNSC staff to assist the Panel
in its deliberations. In my view, however, the cited portions are not
particularly helpful with respect to liquid effluent and stormwater runoff.
[253]
Chapter 5 of the EIS presents a detailed
analysis of the likely environmental effects of the Project and possible
mitigation measures. Section 5.3 relates to effects on the surface water
environment. It notes at 5.3.2.3 that:
The chemical
constituents and their concentrations (which are proprietary and
vendor/technology specific) in the various liquid effluent discharges from the
plant, including the presence and type of water treatment systems for
discharges, are currently not known in sufficient detail to conduct a water
quality assessment for the individual parameters. However, dilution factors
within Lake Ontario for the cooling water systems were calculated to support a
screening level assessment.
(EIS at p. 5-25)
[254]
With respect to the sources, types and
quantities of non-radioactive waste to be generated by the Project, Information
Request #19 made the following request of OPG:
Provide additional
information for the chemicals that are in use at the existing Darlington
Nuclear Generating Station as well as all likely chemicals to be used for the
operational phase of the Project as well as any sources, release points, types
and quantities of non-radioactive wastes, including hazardous waste, predicted
to be generated.
Provide a specific
description of how the chemicals will be used and an assessment of their
releases and potential effects on the environment (e.g. surface water quality,
aquatic environment, atmospheric environment).
[255]
OPG’s response noted that a representative list
of chemicals that would typically be stored and used at such a facility had
been provided in a previously submitted technical document, but that specific
details on the type of chemicals to be stored and used could not be provided
until a vendor was selected. OPG pointed to an example of expected chemical
concentrations in liquid effluent streams for one of the technologies under
consideration (the AP 1000 option), obtained from a licensing application in
the United States. OPG then stated (Respondent’s Record (OPG) at p. 1569):
Regardless of the
specific chemicals used … procedural controls will be in place to ensure their
safe transport, storage and handling. Hazardous chemicals will be managed using
the Workplace Hazardous Materials Information System (WHMIS) principles.
The environmental effects
of such chemicals and hazardous waste will be mitigated by the incorporation of
Good Industry Management Practices into Project implementation. As the Project
planning and design evolves, all Good Industry Management Practices
(incorporating Good Utility Practices), will be integrated into a comprehensive
and overarching Environmental Management Plan (EMP).
The generation of
non-radioactive wastes will be minimized to the extent practicable through
re-use and recycling programs. All residual waste will be collected regularly
by licensed contractors and transferred to appropriately licensed off-site
disposal facilities. Hazardous wastes will be handled in accordance with
applicable regulations.
[256]
I have found it helpful to refer to the written
submissions of Environment Canada (EC), one of the federal authorities listed
as having expertise in relation to the Project, in understanding the process by
which hazardous emissions from the project were assessed during the EA (see
Submission of the Department of the Environment (Environment Canada), January
31, 2011, Applicant’s Record, Vol. 5, Tab EE). EC is only one of the interested stakeholders
that made submissions to the Panel, and the Panel was ultimately responsible
for assessing the Project’s expected environmental effects. Nevertheless, EC
has relevant expertise that was relied upon by the Panel, and has provided
useful contextual information regarding how contaminants are expected to enter
the environment and how they were considered in the course of the EA.
[257]
With respect to liquid effluent, the EC
submissions note (at pp. 25-26):
Various contaminants,
both conventional and radiological, are emitted in liquid effluents from
nuclear power plants. Generally speaking, emissions will depend on the reactor
technology, how it is operated, and the treatment that is undertaken prior to
the effluent being released to the environment. Releases typically include
heavy metals, organic chemicals, biocides, nutrients, grease, and
radionuclides.
[…]
Additionally, the
Once-Through Cooling Water system can release heavy metals from the abrasion of
pipes. Cooling Towers will release contaminants in effluent from the blowdown
circuit.
[…]
EC’s review of the
EIS identified that a bounding scenario for conventional contaminants was not
provided by OPG. Based on EC advice, the JRP
issued various Information Requests to request the characterization of process
effluents including a bounding scenario for conventional contaminants, in order
to understand what contaminants will be released, and the maximum quantities
and maximum concentrations expected for these contaminants. OPG did provide
an indication of the types of chemicals typically used at nuclear power plants,
but did not provide a bounding scenario assessment in its responses to the
Information Requests.
Although EC
acknowledges that some additional information had been provided in OPG’s
responses, the overall intent of the Information Requests had not been fully
met (i.e. providing a sufficiently detailed bounding scenario that would allow
potential effects to be assessed during the EA).
OPG did provide some
discussion about effluent quality anticipated based on a licence application
submitted in the United States for the William States Lee III Generating
Station. OPG did not discuss the effluent quality from the existing Darlington
NGS, arguing that it was not relevant to the reactor technologies being
considered for the Project. However, the subsequent incorporation of the EC6
reactor technology into the EA process does now make the Darlington NGS data
relevant, since the EC6 is similar to the CANDU design employed at the
Darlington NGS.
Ultimately, OPG
contends that the lack of a final reactor technology has prevented them from
conducting the detailed evaluation of process effluent quality and the options
for treatment, at this time. OPG’s position has been that they can only provide
information about conventional effluent quality after a vendor (i.e. a reactor
technology) has been selected and detailed design is under development. This
approach defers government and public review of process effluents until the
CNSC’s regulatory review for the consideration of a Licence to Construct under
the Nuclear Safety and Control Act (NSCA).
Given this
limitation, EC’s approach was to look at information from the existing ambient
conditions in the vicinity of the Project and attempt to identify any concerns
that may have arisen as a result of operations at the Darlington NGS during the
past two decades. EC considered the ambient water and sediment quality that
exists in the vicinity of the Project and the Ecological Risk Assessment (ERA)
that evaluated the risks posed by these existing conditions. The lack of a
bounding scenario for conventional contaminants did not allow for a
quantitative ERA for conventional contaminants based on the future scenario of
combined emissions from the Project and the existing Darlington NGS.
[…]
OPG made various
commitments, stating that all effluent that is released during the construction
and operation of the nuclear facilities will comply with all legal requirements, including the requirements in section 36 of the Fisheries Act
respecting the discharge of deleterious substances. OPG has committed to
undertake treatment of all effluents, as necessary, to meet applicable quality
standards before discharging effluent to the receiving environment.
From a conceptual
standpoint, OPG’s commitments would be environmentally acceptable since they
are consistent with our expectations. However, given the lack of information
available at this time on likely contaminant releases, it would be prudent to
verify process effluent quality during the CNSC licensing phase.
[emphasis added]
[258]
With respect to the emission of radionuclides
through liquid effluent, EC took the view that (at p. 26):
A bounding scenario
was provided for radionuclides. This bounding scenario allowed for a
quantitative ERA to be performed for radiological parameters based on the
future scenario of combined emissions from the Project and the existing
Darlington NGS.
[259]
With respect to stormwater runoff, EC noted (at
pp. 28-29):
As was noted in EC’s
prior submissions to the JRP, data presented by OPG has shown that there
have been some occurrences of acute toxicity in stormwater discharges at the
existing Darlington NGS. This highlights the importance of a properly
designed and operated
stormwater management
system.
A variety of
conventional and industry-specific contaminants will be entrained in stormwater
at any industrial site. At a nuclear power plant, radionuclides can also be
entrained in stormwater. Stormwater for the Project is expected to be
contaminated with conventional parameters (e.g. metals, nutrients, etc.) and
with radionuclides, particularly since a sizeable fraction of the radionuclides
emitted are expected to be deposited on the Project site (based on monitoring
data and atmospheric dispersion modelling).
[…]
EC had requested
additional information regarding the stormwater management plan for both the
site preparation/construction phases and the operating phase. The JRP issued
several Information Requests pertaining to stormwater management. Although
EC acknowledges that some additional information had been provided in OPG’s
responses, the overall intent of the Information Requests had not been fully
met (i.e. providing sufficiently detailed stormwater management plans that
would allow potential effects to be assessed during the EA).
From a conceptual
standpoint, OPG responses to these Information Requests explained the type of
measures they would undertake for stormwater management. OPG has also made
commitments to implement Good Industry Management Practices, and to meet all
applicable regulatory objectives and any loading limits that may be imposed.
These conceptual measures and commitments are consistent with our expectations. However, OPG’s response was not specific about which parameters
they would focus on and the water quality objectives they would establish and
design the facility to meet. Ideally, we would have liked OPG to provide a
specific analysis based on historical stormwater quality at the Darlington NGS,
the identification of any additional parameters of concern based on the reactor
technologies being considered, and any other considerations arising from site layout
options. For example, which radiological parameters does OPG intend to address,
what are the water quality objectives for these radiological parameters, and
what design options can be used to achieve this?
Ultimately, the
lack of a final reactor technology has prevented the evaluation of realistic
facility layout options and a more detailed evaluation of stormwater management
options. OPG’s position has been that decisions regarding stormwater management
will be made during detailed design phase of the Project. This approach defers
government and public review of the detailed stormwater management plans until
the CNSC’s regulatory review for the consideration of a Licence to Construct
under the Nuclear Safety and Control Act (NSCA). In the overall context of
potential impacts from the Project, EC feels this approach is acceptable
considering that the application of Best Management Practices (i.e. what OPG
refers to as Good Industry Management Practices) and various mitigation
measures (such as treatment) can be implemented to ensure the protection of
water quality in waters that receive inputs of stormwater runoff.
[emphasis added]
[260]
EC also provided its assessment of the
information provided by OPG regarding the release of contaminants into the air.
With respect to conventional (i.e. non-radiological) hazardous air pollutants,
EC observed that (at p. 41):
OPG used a bounding
approach for chemicals such as hydrazine, ammonia, acetic acid, etc., by
prorating the existing Darlington NGS emissions based on a comparison of
existing and future electrical generating capacity at the Darlington site.
Although this provided a numerical basis for evaluating effects, the validity
of these estimates could not be verified for the Project since detailed design
was unavailable.
These issues are also addressed in the EA
Report itself.
[261]
In section 2.6, Management of Conventional and
Hazardous Waste, the Panel identifies the main uses of hazardous chemicals
during the operation and maintenance of the Project facility as water
treatment, the boric acid system used for reactivity control in light water
reactors, and the use of small quantities of hazardous chemicals in
laboratories. The Panel notes OPG’s commitment that hazardous chemicals would
be managed using the WHMIS principles, and special precautions would be taken
in relation to boric acid, which is highly corrosive to carbon steel. The Panel
notes, as quoted above, that:
OPG did not provide a
bounding scenario for the release of hazardous substances for the proposed Project.
OPG explained that it has no plan to do so until a reactor technology is
selected for the site.
[262]
In section 5.3, Surface Water Environment (under
Effects Assessment of the Biophysical Environment), the Panel notes that the
greatest potential surface water impact is to Lake Ontario, which is adjacent
to the site. It notes that while surface water quality in Lake Ontario within the study area generally meets federal and provincial guidelines and objectives,
there have been occasional exceedances due to inflows to the lake. OPG
identified cadmium, copper, lead and selenium as contaminants of potential
concern based on baseline sediment quality data which indicate that
concentrations exceed regulatory criteria and background levels. OPG identified
certain other substances (phosphorus, nitrates, conductivity, sodium, aluminium,
boron, cobalt, iron and zirconium) as being present in on-site water bodies in
elevated levels. OPG attributes the latter to the use of road-salt in the area,
runoff from an existing landfill and applications of fertilizers by local
farmers. OPG provided the following information about the Project’s likely
effects on surface water quality:
OPG stated that a
number of contaminants would enter the aquatic environment due to operation of
the reactors. Releases of radiological contaminants would arise from the
operation of the radioactive liquid waste management system. Thermal discharge
and conventional contaminants would be released through the operation of the
condenser circulating water, service water and cooling systems. OPG also stated
that discharges of stormwater would also be expected to release chemical
constituents particularly during the site preparation and construction phases. The
proponent stated that the contaminants from these various systems would be
managed with appropriate treatments to comply with regulatory requirements.
OPG stated that over
different phases of the Project, marine and shoreline construction work would
affect water quality, alter currents and local surface water conditions, and
affect the transport of sediments. Again, OPG proposed measures such as good
industry management practices and sediment control to manage and limit adverse
effects.
[…]
OPG concluded that
with the proposed mitigation measures, the Project would not result in
significant adverse effects on the surface water environment.
(EA Report at p. 64,
emphasis added)
[263]
The Panel noted a number of limitations on what
could be analyzed based on the information provided by OPG, but ultimately determined
that the combination of commitments by OPG, available mitigation options and
regulatory controls meant that the Project would not have significant adverse
environmental effects.
[264]
With respect to the limitations, the Panel
observed (EA Report at pp. 64-65):
5.3.2 Panel
Assessment
As a consequence of
the bounding approach in the environmental assessment, specific site layout and
points of release into Lake Ontario were not defined…
[…]
The proponent did not
complete an assessment of bounding scenarios for conventional liquid effluents
with implementation of mitigation measures. The Panel notes that such an
assessment would have enabled confirmation of the conclusions reached
concerning possible environmental effects from liquid effluents.
OPG provided little
information on the pollutants and contaminant loadings that would enter the
surface water environment with stormwater runoff…
In the absence of a
choice of reactor technology for the Project, OPG did not undertake a detailed
assessment of the effects of liquid effluent and stormwater runoff to the
surface water environment…
[265]
With respect to OPG’s commitments, controls and
mitigation measures, the Panel observed (EA Report at p. 65):
…[T]he proponent
committed to designing stormwater management facilities in accordance with
requirements in the Ontario Stormwater Management Planning and Design Manual
(March 2003). This was supported by a commitment to develop a follow-up program
where parameters to be measured and the frequency of sampling would be
specified. Based on these commitments and additional information provided by
the proponent, the Panel is of the view that adequate controls and mitigation
measures would be in place to prevent significant adverse environmental effects
in the surface water environment.
And:
… [T]he proponent
committed to managing liquid effluent releases in compliance with applicable
regulatory requirements and to applying best management practices for
stormwater. This strategy does not comply with the expectations given in the
EIS Guidelines. Nevertheless, CNSC staff indicated that there is experience of
similar regulatory release limits and management practices being applied at
other nuclear facilities to control and minimize effects in the surface water
environment.
[266]
Based on this analysis, the Panel concluded as
follows on this point (EA Report at p. 65):
The Panel is of the
view that the Project is not likely to result in significant adverse
environmental effects, given the proposed mitigation measures and commitments
made by the proponent, along with the following recommendations.
[267]
The Panel then made several relevant
recommendations, including:
Recommendation #
14:
The Panel recommends
that following the selection of a reactor technology for the Project, the
Canadian Nuclear Safety Commission require OPG to conduct a detailed assessment
of predicted effluent releases from the Project. The assessment should include
but not be limited to effluent quantity, concentration, points of release and a
description of effluent treatment, including demonstration that the chosen
option has been designed to achieve best available treatment technology and
techniques economically achievable. The Canadian Nuclear Safety Commission
shall also require OPG to conduct a risk assessment on the proposed residual
releases to determine whether additional mitigation measures may be necessary.
Recommendation #
15:
The Panel recommends
that following the start of operation of the reactors, the Canadian Nuclear
Safety Commission require OPG to conduct monitoring of ambient water and
sediment quality in the receiving waters to ensure that effects from effluent
discharges are consistent with predictions made in the environmental impact
statement and with those made during the detailed design phase.
Recommendation #
16:
The Panel recommends
that prior to the start of construction, the Canadian Nuclear Safety Commission
require the proponent to establish toxicity testing criteria and provide the
test methodology and test frequency that will be used to confirm that
stormwater discharges from the new nuclear site comply with requirements in the
Fisheries Act.
[268]
Recommendations 14 and 15 were accepted by the
Government of Canada. The Government accepted the intention of Recommendation
16, while stating that it would also support such an approach for process
effluents.
[269]
The Panel also addressed potential effects
relating to conventional hazardous substances in section 5.5, Terrestrial
Environment. It reiterated the information set out above regarding OPG’s
inability to provide details regarding the chemicals to be stored and used on
the site until a reactor technology is chosen. The Panel then noted the input
of CNSC staff and Environment Canada (EA Report at p. 78):
…CNSC staff stated
that the OPG response was conditionally acceptable based on its review of
previous ecological risk assessments conducted at the site, an assessment of
current practices for hazardous chemical management at the Darlington Nuclear
Generating Station, and the need for a comprehensive assessment of hazardous
releases.
Environment Canada summarized the requirements associated with the presence of hazardous substances within any
facility in Canada. Under the Canadian Environmental Protection Act
(S.C. 1999, c. 33), Environment Canada would evaluate if there are substances
meeting certain quantity thresholds that would require a proponent to inform
the public and prepare emergency plans. Depending on the situation, Environment
Canada would evaluate substance dispersion, response strategy development,
cleanup priorities, sampling and monitoring requirements. Environment Canada advised the Panel that ammonia and hydrazine would have to be evaluated after the
reactor technology has been chosen.
[270]
The Panel concluded that, provided the proposed
mitigation measures and the Panel’s recommendations were carried out, the
Project was not likely to cause significant adverse environmental effects to
the terrestrial environment, and made the following recommendation:
Recommendation #
26:
The Panel recommends
that the Canadian Nuclear Safety Commission require OPG to develop a
comprehensive assessment of hazardous substance releases and the required
management practices for hazardous chemicals on site, in accordance with the
Canadian Environmental Protection Act, once a reactor technology has been
chosen.
[271]
On the whole, then, in the absence of bounding
scenarios representing the use, storage and release of hazardous substances
from the Project, the Panel relies upon an assessment that various commitments,
recommendations, and regulatory controls will ensure the Project does not have
significant adverse effects on the terrestrial and surface water environments.
[272]
This may well be a reasonable conclusion. The
question, though, is whether it complies with the Panel’s obligations to
consider the Project’s environmental effects and their significance (CEAA, s.
16(1)(a) and (b)), to ensure that the information required for an assessment is
obtained and made available to the public (CEAA, s. 34(a)), to prepare a report
setting out the rationale, conclusions and recommendations of the panel
relating to the EA of the project (CEAA, s. 34(c)), and, as the jurisprudence
and the scheme of the Act make clear, to ensure that those required to make
decisions under s. 37 have a proper evidentiary foundation before them. To
repeat what is stated above, because of its unique role in the statutory
scheme, a review panel is required to do more than consider the evidence and
reach a reasonable conclusion. It must provide sufficient analysis and
justification to allow the s. 37 decision-makers to do the same, based on a
broader range of scientific and public policy considerations. One could say
that the element of “justification, transparency and intelligibility within the
decision-making process” (Dunsmuir, above, at para 47; Khosa,
above, at para 59) takes on a heightened importance in this context.
[273]
In this case, there are references to
commitments by OPG to comply with unspecified legal and regulatory requirements
or applicable quality standards, and to apply good management practices. There
are references to instruments that may or may not contain relevant standards or
thresholds based on the information before the Court (e.g. the Ontario
Stormwater Management Planning and Design Manual (March 2003)). And there
are references to thresholds or standards in statutory instruments (e.g. Fisheries
Act, Canadian Environmental Protection Act) without specific
information about how these are relevant to or will bound or control the
Project’s effects.
[274]
It is notable that the Panel itself concluded
that, with respect to liquid effluent releases, OPG’s “strategy does not comply
with the EIS Guidelines” (EA Report at p. 65), and that the Panel’s “assessment
of potential environmental effects was qualitative in many respects because it
was conducted without specific knowledge of potential releases” (EA Report at
p. 39). In the same vein are Environment Canada’s observations that there was
insufficient information to assess the potential effects of either liquid
effluent or stormwater runoff from the Project during the EA. There is nothing
in the EA Report to contradict these observations; rather, the Panel decides
that, in spite of this, it is possible to conclude that the Project is not
likely to have significant adverse effects based on proponent commitments,
mitigation measures and regulatory controls.
[275]
In essence, the Panel takes a short-cut by
skipping over the assessment of effects, and proceeding directly to consider
mitigation, which relates to their significance or their likelihood. This is
contrary to the approach the Panel says it has adopted (see EA Report at p.
39), and makes it questionable whether the Panel has considered the Project’s
effects at all in this regard.
[276]
In my view, such a short-cut might be
permissible where there is a clear standard or threshold that can serve as a
proxy for actual effects. In such a case, the s. 37 decision-makers can
evaluate the standard or threshold as a measure of the “significance” of the
potential effects, and can evaluate the likelihood that the standard will be
applied (e.g. is it enforceable, within their control, or routinely applied?)
as a measure of the likelihood that adverse effects above the level of
significance will occur. The present case offers several examples.
[277]
For instance, participants in the Panel hearings
noted that the Ontario Drinking Water Advisory Council has recommended that
Ontario reduce its Drinking Water Quality Standard for tritium, a radioactive
substance, to about one 350th of its current level (from 7,000 becquerels per
Litre (Bq/L) to 20 Bq/L) (see EA report at p. 28). Some participants argued
that the Project’s effects should be evaluated in light of this more stringent
standard. This is a question that, in my view, relates not just to scientific
evidence, but to “society’s chosen level of protection against risk.” The
Panel examined the evidence regarding exposure to tritium in drinking water,
and recommended, based on a precautionary approach, that the CNSC “require OPG
to implement measures to manage releases from the Project to avoid tritium in
drinking water levels exceeding a running annual average of 20 Bequerels per
litre at drinking water supply plants in the regional study area.” The Government
of Canada took a different view in its Cabinet-approved response. It accepted
“the intent of this recommendation to safeguard drinking water,” but stated
that “any proposed limits should be consistent with the tritium standards put
in place by the relevant regulatory authorities.” Thus, deliberation regarding
the appropriate threshold served as an appropriate proxy for the significance
of the potential adverse effect, and CNSC regulation of this aspect of the Project
serves as a proxy for “likelihood.”
[278]
Similarly, with respect to the transportation of
radioactive materials, the Panel made reference to the relevant regulatory
limits (a maximum dose rate on the surface of a package of two millisieverts
per hour on contact and 0.1 millisieverts at a distance of one meter), and made
an explicit finding that:
Based on the
information provided by Transport Canada and CNSC staff, the Panel is of the
view that the transportation of dangerous goods is sufficiently regulated under
the Transportation of Dangerous Goods Act and the Packaging and Transport of
Nuclear Substances Regulations under the Nuclear Safety and Control Act to
protect the health and safety of persons and the environment. The Panel
therefore concludes that the transportation of dangerous goods is not likely to
result in significant adverse environmental effects.
(EA Report at p. 116)
[279]
In other cases, an analysis of potential effects
was conducted based on preliminary or baseline data that must be verified or
augmented through further study or analysis (see for example section 5.9.1
Geotechnical and Seismic Hazards and Effects and various recommendations
regarding the project’s effects on fish and fish habitat). This is the purpose
of follow-up programs as defined in s. 2(1), but as noted elsewhere in this
judgment, such programs are not to be used where no baselines or thresholds
exist.
[280]
It seems to me that a conceptual distinction can
be drawn between situations where the Panel concludes, despite a degree of
uncertainty, that significant adverse environmental effects are unlikely to
occur based upon:
(a) Reliance upon an established standard or practice and the likelihood
that the relevant regulatory structures will ensure compliance with it; or
(b) Confidence in the ability of regulatory structures to manage the
effects of the Project over time.
[281]
The problem with the latter approach is that it
may undermine Parliament’s intention with respect to who decides the level of
acceptable environmental impact from a project. That is, it may short-circuit
the two-stage process whereby an expert body evaluates the evidence regarding a
project’s likely effects, and political decision-makers evaluate whether that
level of impact is acceptable in light of policy considerations, including
“society’s chosen level of protection against risk.”
[282]
This does not rule out the possibility that a
more “qualitative” assessment of effects and their significance may be
appropriate in some cases. Some effects may be difficult to quantify even where
reliable information is available. However, there is nothing in the EA Report
that suggests a qualitative assessment of the effects of hazardous substance
releases. Rather, it seems to me that what the Report reflects is a qualitative
assessment of the mitigation measures that are available to manage and control
those effects. In this respect, it does not fully comply with the requirements
of the CEAA.
[283]
The Applicants
argue in their memorandum that:
53. Although used nuclear fuel will require long-term storage and
monitoring for thousands of years as a hazardous substance, the [Panel] failed
to conduct an assessment of the effects of radioactive waste management before
making a conclusion regarding the significance of the adverse environmental effects
of the Project. In particular, the [Panel] erred in law by failing to consider
whether the radioactive waste from the Project will have significant adverse
environmental effects, and whether there are any technically and economically
feasible measures which would mitigate any significant adverse environmental
effects arising from the Project in accordance with subsection 16(1)(d) of the
CEAA.
54. The [Panel] found that the radioactive waste generated by the
Project could result in significant cumulative effects “related to doses to
workers, the public and the environment if it is not properly managed should it
remain permanently on-site.” The [Panel] also acknowledged that a number of
significant gaps in information regarding long-term radioactive waste
management exist. Rather than requiring OPG to provide this information at the
hearing, the [Panel] merely recommended future study and analysis be
conducted. The [Panel] erred by failing to assess the environmental effects of
radioactive waste, and therefore had no factual basis to conclude that
“radioactive and used fuel waste is not likely to result in significant adverse
environmental effects.”
[284]
The Stensil affidavit
points to two reports submitted to the Panel by Greenpeace Canada in this regard. One was dated September 2010 and is entitled Rock Solid? A scientific
review of geological disposal of high-level radioactive waste. It was
commissioned by Greenpeace International and written by Helen Wallace of
GeneWatch UK (Applicant’s Record, Vol. 2, Tab F1 [GeneWatch Report]). The other
was dated May 2010 and prepared by Marvin Resnikoff, Ph. D., Jackie Travers and
Ekaterina Alexandrova of Radioactive Waste Management Associates, under the
sponsorship of Greenpeace Canada. It is entitled The Hazards of Generation
III Reactor Fuel Wastes: Implications for Transportation and Long-Term
Management of Canada’s Used Nuclear Fuel (Applicant’s Record, Vol. 2, Tab
F3 [Resnikoff Report])
[285]
The affidavit of
Brennain Lloyd, Project Coordinator with Northwatch, also addresses this issue,
and noted that three reports commissioned by Northwatch, all dated February 21,
2011, were submitted to the Panel on March 29, 2011 (Lloyd affidavit, Applicant’s
Record, Vol. 7, Tab 6, para 30, and hearing transcript at Applicant’s Record,
Vol. 7, Tab K, pp. 11-85).
[286]
The central thesis of
the Resnikoff Report is that the spent fuel from the reactor designs under
consideration for the Project will be more difficult to manage than nuclear
waste from existing nuclear plants in Canada, and that there is no adequate
plan in place to manage this waste. The report states that, unlike all
currently operating CANDU reactors in Canada, which use natural uranium fuel,
all of the reactors being considered for the Project use enriched uranium fuel
(this would not be true of the later-added EC-6 design). The Resnikoff Report
says that the fuel waste from these reactors will be between 2 and 158 times
more radioactive than the waste produced by existing CANDU reactors, will
contain higher levels of long-lived hazardous radionuclides such as americium,
curium and plutonium (though there will be less spent fuel by weight), and will
take much longer (2.6 million years compared to approximately 1 million years)
to decay to levels of radioactivity equivalent to that of natural uranium. In
short, the report says that the spent fuel will be more hazardous and more
difficult and costly to manage. It emphasizes (at p. 22) that:
The proposed shift to Generation III reactor designs which use enriched
reactor fuel with an increased fuel burn-up will lead to the production of used
nuclear fuel that is much more hazardous than the fuel generated by Generation
II reactors.
In its environmental assessment of the construction of new reactors at Darlington, OPG did not analyze the hazards associated with the transportation and
long-term management of Generation III used nuclear fuel at a centralized
repository, as it assumes that any off-site facility “will have been subject to
its own approval process.” Since the NWMO’s APM for a centralized deep
geological repository is limited to the projected used nuclear fuel inventory
of Generation II reactors in Canada, the addition of Generation III–type
reactor wastes to the repository falls outside the scope of the NWMO’s APM. If
OPG’s new reactor builds continue as planned at the Darlington site, then
Generation III reactors, which have not yet been tested or operated anywhere in
the world, will be allowed to operate in Canada without any analysis of the
hazards and consequences of their used nuclear fuel waste.
The addition of the Generation III used nuclear fuel with its higher
burn-up will impose increased environmental and human health risks at every
stage of the APM process, from the operation of the nuclear reactors to the long-term
monitoring of the used nuclear fuel disposed of in the deep geological
repository. Generation III reactor used nuclear fuel will not only affect the
cost of construction and the size of the deep geological repository, but also
the interim-storage and the transportation of the used nuclear fuel. Since
nuclear fuel with higher burn-up contains a greater inventory of radionuclides,
the health hazards imposed on the workers handling it, as well as on members of
the public who reside along its shipping routes or within the vicinity of the
deep geological repository, will be greatly affected also.
[287]
The Resnikoff Report
goes on to describe in greater detail the authors’ view that the use of fuel
with a higher burn-up rate imposes additional hazards during operation (p. 23),
during interim storage, which may need to occur for much longer periods (pp.
24-25), during transportation (pp. 26-28), and during any future long-term
disposal in a geologic repository (pp. 29-33). In the authors’ view, all of
this makes the OPG’s cost estimates for fuel management highly uncertain and
speculative (p. 34).
[288]
The Resnikoff Report
says that this type of waste is outside of the parameters of what has been
studied or planned for by the Nuclear Waste Management Organization (NWMO), an
industry-funded body tasked through legislation with managing nuclear fuel
waste in Canada, and will require techniques that have not yet been proven.
The report emphasizes that current planning by NWMO encompasses only the
projected spent fuel from existing reactors. It cites a NWMO Advisory Council
report stating that any consideration of new nuclear development that would
create additional spent fuel, or a different type of spent fuel (due to
enrichment) “should trigger a review of the work undertaken by the NWMO to
date,” and should entail “broad public discussion of Canadian energy policy
prior to a decision about future nuclear energy development” (Resnikoff Report
at p. 8).
[289]
The Resnikoff Report
also states that the higher “burn-up” of fuel in Generation III reactors poses
new challenges for the safe operation of these reactors, and will result in
increased environmental and human health consequences in the event of an
accident. Since all of the reactors being considered are “untested prototypes,”
the report says there is no empirical evidence to support the claims of safety.
[290]
In addition to
feasibility and safety concerns, the Resnikoff Report raises a concern that the
higher toxicity and longer lifespan of the radioactive wastes from the Project
will increase the cost of near-term, mid-term and long-term radioactive waste
management, and that without a proper assessment of these costs, the Project
will impose an unfair financial burden on tax-payers, electricity ratepayers
and future generations.
[291]
The GeneWatch Report
undertakes a literature review of papers in scientific journals regarding the
concept of long-term underground disposal (i.e. geographic repository) of
highly radioactive wastes. It points to a number of uncertainties and phenomena
that could, in the author’s view, compromise the containment barriers of such
facilities and lead to significant releases of radioactivity. It says that
until such difficulties can be resolved, a number of scenarios exist in which a
significant release of radioactivity from a deep repository could occur, with
serious implications for the health and safety of future generations.
[292]
In terms of the
Respondents’ submissions, this issue is addressed most directly by OPG, at
paragraphs 67-71 of its memorandum. OPG points to paragraphs 240-241 and
245-248 of the Affidavit of Laurie Swami (Respondents’ Record (OPG), Vol. 1,
Tab A at pp. 58-59 [Swami affidavit]). The Swami affidavit, in turn, points to
pages 2-8, 2-17 and 13-11, as well as section 2.4.3 of the Panel Member
Document (excerpt at exhibit 82 to the Swami Affidavit), and the hearing
transcript from the morning of Tuesday, March 29, 2011, when the issue of
radioactive waste management was addressed. There was a presentation by a
representative of OPG, presentations by individuals associated with Northwatch,
and questioning by Panel members of representatives of OPG, CNSC staff, NWMO,
and the Northwatch presenters.
[293]
The excerpts from the
EIS and the Panel Member Document confirm that there was no extended treatment
of the issue of long-term nuclear spent fuel management and disposal in OPG’s
EIS or its responses to inquiries. Rather, OPG took the view that the
development and implementation of a long-term management approach for used fuel
is the responsibility of NWMO, and is subject to a separate federal approvals
process (EIS at p.2-8). There was no discussion of NWMO’s proposed approach,
what studies and regulatory approvals have or have not been completed, and
whether spent fuel from reactors using enriched uranium would present
additional challenges. The description of on-site (interim) management of
spent fuel was general in nature, as the means of storage is unique to each
reactor type (Panel Member Document at p. 22, Respondent’s Record (OPG) at p.
4146), but OPG indicated in the EIS that the assessment of effects established
that all considered forms of dry storage of used fuel will be acceptable from
an environmental perspective” (EIS at p. 13-11).
[294]
At the hearing before
the panel, there was discussion of issues relating to the feasibility and risks
associated with a deep geological repository, and whether it would be possible
to store and manage the spent fuel at the Darlington site for much longer than
the operating life of the reactors – possibly for hundreds of years – if such a
repository were not available. My reading of the transcript suggests that there
was a considerable divergence of views on these issues, and that it would be
difficult to draw any firm conclusions based solely on the information
presented and discussed at the hearing.
[295]
On the issue of
whether OPG would be able to manage the waste indefinitely – or into the
hundreds of thousands of years – should this become necessary, OPG’s position
was ultimately that this is what the Government of Canada has mandated NWMO to
study (see Transcript at pp. 164-65, Respondent’s Record (OPG) at pp. 4135-36,
response of Dr. Herminia Roman).
[296]
It was confirmed at
the hearing before the Panel that OPG will continue to be responsible for the
management of the spent fuel unless and until it is transferred to another
licensee (i.e. NWMO) to manage it. While OPG will remain the “owner” of the
waste in perpetuity, CNSC staff noted that ownership is not the relevant
criterion with respect to who is responsible to manage it and ensure its
safety. Rather, the question is which licensee has control of the waste
(Transcript at p. 127, Respondent’s Record (OPG) at p. 4098, response of
Barclay Howden, CNSC, at lines 8-16).
[297]
In my view, the
record confirms that the issue of the long-term management and disposal of the
spent nuclear fuel to be generated by the Project has not received adequate
consideration. The separate federal approvals process for any potential NWMO
facility, which has not yet begun (see Transcript at p. 99, Respondent’s Record
(OPG) at p. 4070, response of Barclay Howden, CNSC, at lines 9-12) will
presumably ensure that such a facility is not constructed if it does not ensure
safety and environmental protection. But a decision about the creation of that
waste is an aspect of the Project that should be placed before the s. 37
decision-makers with the benefit of a proper record regarding how it will be
managed over the long-term, and what is known and not known in that regard.
[298]
The issue of the
transportation of used nuclear fuel was also discussed at the hearing before
the Panel, and may be an issue that requires further consideration by the Panel
as part of its consideration of the long-term management of spent nuclear fuel
from the Project.
[299]
The EA Report
discusses the management of spent nuclear fuel in several sections, including
section 2.5.3 Waste Management (under Alternative Means of Carrying Out the
Project), section 3.3 Overview of Public Comments at the Hearing, section 4.6.6
Decommissioning and Abandonment, and section 6.8 Waste Management (under
Analysis of the Human Environment).
[300]
OPG explained that
managing spent fuel is a two-stage process, involving wet storage for initial
cooling, lasting approximately 10 years, followed by dry storage. Except for
the EC-6 design, each of the reactor technologies under consideration will
require enriched fuel, in contrast to the CANDU reactors currently operating in
Canada, which use natural uranium fuel. This “introduces elements of
criticality control requirements for storage as well as potential heat load
issues for dry storage and eventual long-term management.” The Panel notes that
“[s]ome processing modifications may be required” depending on the reactor
technology chosen “due to new fuel dimensions, higher burn-up and heat load.”
Interim storage is intended to take place on-site, with specific containers for
dry storage to be “selected to suit the chosen reactor technology and licensed
for their function prior to use” (EA Report at p. 18).
[301]
OPG assumed for
planning purposes that only 50% of used fuel would require interim storage on-site,
noting that NMWO is responsible for long-term management of used fuel. OPG
assumed that a long-term used nuclear fuel repository would be in service by
about 2035, and all used fuel would be removed from the Darlington Waste
Management Facility to that repository by 2064. With respect to space
requirements, OPG stated that there would be sufficient space on the Darlington site to store all of the used fuel from the Project in perpetuity, should the
long-term used nuclear fuel repository not be in service (EA Report at p. 19).
With respect to technical issues, the EA Report notes that:
The main technical points that would need to be addressed for used nuclear
fuels from the Project reactors in the Nuclear Waste Management Office
repository are the effect of different physical configuration, the effect of
higher burnup, the effect of higher initial enrichment and the capacity of the
repository to handle the additional fuel.
(EA Report at p. 19)
[302]
The Panel noted the
concerns expressed by many hearing participants regarding the proposed
approach:
Many participants expressed concerns regarding the long-term management of
the nuclear waste generated by the Project, used fuel in particular.
Participants were of the view that OPG had not adequately addressed many of the
issues related to long-term fuel waste management, and noted that a proven
solution for the disposal of used fuel had not yet been developed by the nuclear
industry. Participants expressed the view that no further nuclear waste should
be created until a proper solution is found.
Many participants were of the view that used fuel would be a burden on
future generations as it will require long-term storage and monitoring for the
duration of its life as a hazardous substance, which could be for thousands of
years. In this regard, participants felt that long-term storage of used fuel on
the Project site had not been properly assessed.
Participants noted that although the responsibility for the long-term
management of used nuclear fuel waste in Canada had been assigned to the
Nuclear Waste Management Organization by the federal government through the Nuclear
Fuel Waste Act (S.C. 2002, c. 23), the Organization’s Adaptive Phased
Management approach was developed for application to the existing fleet of
nuclear reactors and does not include consideration of used fuel from new
reactors.
[…]
Contrary to these views, some participants were of the opinion that OPG
has demonstrated that used fuel waste has been safely managed at its existing
waste management facilities and were hopeful that a solution for waste would
eventually be found. Other participants were of the view that used fuel could
be reprocessed for use as fuel by future generations in new reactor
technologies.
(EA Report at pp. 27-28)
[303]
In the context of
considering the decommissioning phase of the Project, the Panel states the
following regarding used nuclear fuel management:
The Panel is of the view that the preliminary decommissioning plan shall
reflect that no solution has yet been implemented for the longterm management
of used fuel. The Panel acknowledges that the preliminary decommissioning plan
would be updated as required by the Nuclear Safety and Control Act and
Regulations.
(EA Report at p. 53)
[304]
The Panel’s
evaluation of OPG’s proposed approach to used nuclear fuel management and its
effects on the environment can be found primarily in section 6.8 Waste
Management (under Analysis of the Human Environment). The Panel outlined OPG’s
submissions on the issue, including the following:
OPG stated that the plant parameter envelope included information on the
differences in the design of fuel required by the various reactor technologies.
OPG noted that these design differences would require different provisions for
dry storage, particularly with the use of enriched uranium fuel. OPG further
noted that ensuring criticality safety and adequate cooling for dry nuclear
fuel storage would be achieved as a design requirement for all reactor types.
At the hearing, OPG confirmed that radiation doses from the used fuel
management operation would not result in significant adverse effects to the
workers and the public. The proponent also confirmed that, if necessary, used
fuel could be loaded into a new dry storage container in the event of damage or
aging degradation of an existing container. OPG indicated that this could be
achieved without any significant adverse effects in the reactor fuel handling
bays. The proponent indicated that the dry storage canisters would be robust
and would withstand high energy impact loads without release of stored used
nuclear fuel components.
[305]
The Panel then set
out its own assessment, stating that:
Based on the assessment completed by CNSC staff, the Panel accepts the
conclusion that the measures described for the on-site management of low and
intermediate-level radioactive waste, used nuclear fuel waste, conventional
waste and other hazardous waste will ensure that there will be no
significant adverse environmental effects on site from this activity,
taking into account the mitigation measures and controls established for the
management of waste.
(EA Report at p. 117, emphasis added)
[306]
The Panel notes that
OPG’s assumption regarding the relocation of used fuel to an off-site facility
was dependent on the outcome of a NWMO initiative. It found that “the
availability of the proposed used nuclear fuel repository could be delayed
because of a number of factors,” including “difficulties in obtaining a willing
host community, an acceptable site from a geotechnical perspective, regulatory
approval… public acceptance of the facility, or public acceptance of provisions
for transport of the used fuel to the repository” (EA Report at p. 117). In
view of this, the Panel found that provision should be made for on-site storage
of the used fuel for longer than anticipated by OPG. It therefore made the
following recommendation:
Recommendation # 52:
The Panel recommends that prior to construction, the Canadian Nuclear
Safety Commission require OPG to make provisions for on-site storage of all
used fuel for the duration of the Project, in the event that a suitable
off-site solution for the long-term management for used fuel waste is not
found.
[307]
Though it refers to
potential delays in the availability of an off-site repository, the Panel makes
no mention here of the implications of using enriched nuclear fuel. Yet, if the
Applicants are correct – and the Respondents have not pointed to any contrary information
– NMWO has made no assessment of the suitability or availability of a deep
geological repository, or its Adaptive Phased Management approach more broadly,
for this type of fuel waste. Indeed, the Applicants contend there has been no
planning for any used nuclear fuel beyond what already exists and what is
expected to be produced by the existing CANDU reactors during their remaining
expected use.
[308]
The Panel noted
earlier in the EA Report that enriched fuel poses new technical issues for a
potential NWMO repository, including “the effect of different physical
configuration, the effect of higher burnup, the effect of higher initial
enrichment and the capacity of the repository to handle the additional fuel”
(EA Report at p. 19). It also notes that “no solution has yet been implemented
for the longterm management of used fuel” (EA Report at p. 53). And yet, the
Panel has provided no discussion of the suitability of the current NMWO plan
for the type of waste to be generated by the Project, or the feasibility of
alternatives should that plan prove unworkable for the waste from this new
facility.
[309]
The Panel recommends
that OPG be required to make provisions for on-site storage “of all used fuel
for the duration of the Project.” However, if “a suitable off-site solution
for the long-term management for used fuel waste is not found,” the “duration
of the Project” will extend to however long the used fuel must be managed. This
is essentially an indefinite period of time given that used nuclear fuel remains
radioactive for hundreds of thousands of years. The Panel provides no analysis
of the feasibility of storing and managing used nuclear fuel at Darlington in perpetuity.
[310]
In my view, there is
a significant gap in the analysis here that deprives political decision-makers
of an important part of the evidentiary record required to discharge their
responsibilities under s. 37 of the CEAA. Without information regarding the
suitability of existing plans for used nuclear fuel management to deal with
waste from the Project, they cannot realistically assess whether the risks and
impacts are in line with “society’s chosen level of protection against risk.”
It may be that the s. 37 decision-makers are entitled to trust that the
necessary technologies will be available when they are needed; that is not the
question before the Court. If they are to do so, however, they must at least
have the benefit of a full factual record. It would seem appropriate for that
record to include analysis regarding:
- What effect the addition of spent
fuel from enriched uranium would have on current plans for the management
and disposal of spent nuclear fuel;
- The likelihood that a deep
geological repository – the proposed end state of the Adaptive Phased
Management approach – will be available or appropriate for that type of
fuel, or at least an analysis of the degree to which this has or has not
been assessed, to provide a sense of the level of uncertainty involved;
- If such a facility proves not to be
appropriate or available, what alternative means exist for managing this
type of fuel in perpetuity to isolate it from people and the environment;
and
- The cost implications of the above
scenarios for current and future generations.
[311]
I realize that we are
dealing here with an issue that has time horizons in the hundreds, and
potentially hundreds of thousands, of years, and the Panel cannot be expected
to describe in exacting detail everything that is likely to occur over that
length of time, or the technologies that will or will not be available. However,
precisely because of the scale of the impact, in terms of time horizon and
potential severity, it is not an issue that can be glossed over. The Panel
should at minimum set out what is known and not known about how spent fuel from
enriched uranium will be managed in the future, including what planning and
assessments have and have not been completed.
[312]
In my view, this is
not a “separate issue” that can be deferred to be dealt with when and if NWMO
seeks approval for a facility to permanently manage and dispose of the waste
generated. The EA is the only occasion, in relation to this Project, on which
political decision-makers at the federal level will be asked to decide whether
that waste should be generated in the first place. They must be in a position
to understand whether they are being asked to take a leap of faith, and if so,
how big a leap it is.
[313]
Nor do the Terms of
Reference or the EIS Guidelines say anything that suggests that this issue was
not to be addressed as part of the EA. The Guidelines state:
In addition to the project-phase specific requirements for waste provided
in the preceding subsections, the EIS must present the proponent’s proposed
plan for the disposition of all radioactive and hazardous wastes and used
fuel. The proponent’s activities related to the site preparation,
construction, operation, decommissioning and abandonment of low and
intermediate level waste management facilities, and used fuel storage
facilities, must be described. Where this plan identifies that radioactive or
hazardous wastes or used fuel are expected to be managed by an organization
other than the proponent, the EIS must describe at a conceptual level the
methods that can be used to ensure that these materials are managed in a manner
that protects health, safety and the environment.
(EIS Guidelines at p. 24)
The words “the methods that can be used” implies that feasibility is to be
part of the assessment.
[314]
With respect to the
relevant time horizons, the EIS Guidelines state:
At a minimum, the assessment must include the period of time during which
the maximum effect is predicted to occur. “Maximum” refers to the greatest
change from baseline conditions to what is predicted and should be bounding
across reactor types. The approach taken to determine the temporal boundary of
assessment should take into account the following elements:
•
hazardous lifetime
of the contaminants, including those associated with waste and used fuel, or with releases to the
environment during both normal operation and postulated accidents, malfunctions
and malevolent acts;
[…]
(EIS Guidelines at p. 27, emphasis added)
[315]
The fact that NWMO
may at some point assume control of the waste from OPG is immaterial to its
potential to cause significant adverse effects; the waste must in any case be
managed.
[316]
The fact that the EC-6
option would not use enriched uranium is also immaterial; as with all other
elements of the “bounding scenario,” OPG must be prepared to demonstrate an
acceptable level of environmental risk with respect to each of the technologies
under consideration.
[317]
It bears noting that
this is the first proposed nuclear new build in Canada in over a generation,
the first since the CEAA was enacted, and the first to potentially use enriched
uranium fuel. If it seems as though this Project is being held to a higher
standard than those that came before it in terms of planning for the used
nuclear fuel it will generate, this is nothing more than a consequence of the
statutory environment within which it has been proposed. It should not be
surprising that Canada’s approach to environmental approvals has developed and
evolved over the past several decades.
[318]
I conclude on this
issue that the Panel did not reasonably address the issue of the long-term
management and disposal of used nuclear fuel in accordance with its obligations
under the CEAA, and must supplement or amend its Report accordingly. Whether
this requires additional research or consultation should be for the Panel to
determine as the master of its own process, but it should at a minimum address
the points outlined above.
[319]
The possibility of a
severe “common cause” accident affecting multiple reactors at the Darlington site was considered by the Panel in the context of assessing “cumulative
effects” that could result from the Project in combination with other projects
or activities. Notably, the public hearings for the EA took place immediately
following the Fukushima Daiichi nuclear disaster, to which the Panel makes reference
in its analysis.
[320]
The Panel noted that
the Project would be added to the site of the existing Darlington NGS, and “the
resulting cumulative dose should also be evaluated as a cumulative effect” (EA
Report at p. 133). The Panel observed that OPG had not analyzed cumulative
effects of the existing and new facilities for malfunction and accident
scenarios “because they were considered hypothetical and to have a very low
probability of occurring.” It noted that OPG took the view that this was
consistent with guidance from the Canadian Environmental Assessment Agency,
stating that accidents should be considered as unique scenarios, but the Panel
took a different view of the relevant guidance:
The Panel notes OPG’s interpretation of this aspect of the Canadian
Environmental Assessment Agency Cumulative Effects Practitioners Guide.
The Panel is of the view that a more appropriate interpretation, in this
instance, would have been to include a cumulative effects assessment of a
common cause accident involving multiple reactors in the site study area.
The Panel has concluded that conventional malfunctions and accidents are
not likely to cause significant adverse environmental effects, taking into
account the proposed in-design safety systems, mitigation measures, including
preventive measures and emergency response capabilities. However, based on the
views expressed by participants during the review and the concerns regarding
accident scenarios such as the Fukushima Daiichi nuclear accident, the Panel is
of the view that for emergency planning purposes, OPG should perform an
evaluation of the cumulative effect of a common-cause severe accident scenario
that would include all of the nuclear generating reactors in the site study
area.
(EA Report at p. 133)
[321]
The Panel then made
the following recommendation:
Recommendation # 63:
The Panel recommends that prior to construction, the Canadian Nuclear
Safety Commission require OPG to evaluate the cumulative effect of a
common-cause severe accident involving all of the nuclear reactors in the site
study area to determine if further emergency planning measures are required.
[322]
It is useful to place
this analysis and recommendation in the context of the Panel’s earlier analysis
of “conventional” accidents and malfunctions, referred to in the quotation
above and found at pages 122-125 of the EA Report. There, the Panel notes that
OPG had analyzed “a number of bounding radiological malfunctions and accidents”
as part of its EIS. The analysis of accident scenarios was conducted based on
CNSC’s regulatory document RD-337, Design of New Nuclear Power Plants I [RD-337].
The scenarios analyzed included accidents that could occur during waste
handling, an “out-of-core criticality event” (such as an accident while
handling new nuclear fuel), an accident during off-site transportation of low
or intermediate-level radioactive waste, and malfunctions or accidents that
could affect a reactor itself.
[323]
For the majority of
these scenarios, OPG concluded (and the Panel accepted) that no significant
adverse environmental effects would result, and potential radiological doses to
workers and the public would be below regulatory exposure limits.
[324]
For certain scenarios
involving damage to the reactor core, whether regulatory limits were exceeded
at the boundaries of the Project site would depend on certain variables;
namely, “the calculation methodology adopted and use of a site-specific
atmospheric dispersion factor” (EA Report at p. 124).
[325]
This meant that “a
number of uncertainties remained in the proponent’s analyses of the
consequences of reactor accidents.” The Panel stated that these concerns needed
to be addressed once the designs for the Project were more complete, but that
the analysis of “bounding scenarios” provided by OPG was sufficient for EA
purposes because the qualitative and quantitative safety goals set out in
RD-337 would be enforced at a later stage:
CNSC staff stated that the bounding approach adopted by OPG for its
assessment of the health consequences of a nuclear accident were acceptable for
the purpose of the environmental assessment. CNSC staff noted that this
approach was acceptable because a reactor that does not meet the specified
safety goal-based release limits of RD-337 would not be accepted for operation
on the grounds that it would not be compliant with regulatory requirements in Canada.
The Panel accepts the adoption of a safety goal-based approach for the
assessment of the consequences of an accident in a situation where there has
not been a choice of reactor technology. The Panel notes, however, that once
this choice has been made, the proponent must be required to complete an
assessment of the offsite effects of a severe accident that could arise for the
chosen technology.
[…]
The Panel is of the view that once a technology has been selected for the
Project there will be a need for more specific analysis of potential accidents
and the consequent releases and health effects. The review of the Application
for a Licence to Construct the reactor would require confirmation that the
health effects conclusion from the present assessment remains valid for the
predicted accident conditions.
[…]
The Panel concludes that the Project is not likely to result in
significant adverse environmental effects on the health and safety of workers
and the public during accidents and malfunctions, taking into account the
implementation of mitigation measures, such as the functioning of reactor
safety systems and the on-site Consolidated Nuclear Emergency Plan and offsite
emergency measures, along with the following recommendations.
[emphasis added]
[326]
The Panel then made
the following recommendations:
Recommendation # 57:
The Panel recommends that prior to construction, the Canadian Nuclear
Safety Commission require OPG to undertake an assessment of the off-site
effects of a severe accident. The assessment should determine if the off-site
health and environmental effects considered in this environmental assessment
bound the effects that could arise in the case of the selected reactor technology.
Recommendation # 58:
The Panel recommends that prior to construction, the Canadian Nuclear
Safety Commission confirm that dose acceptance criteria specified in RD-337 at
the reactor site boundary—in the cases of design basis accidents for the
Project’s selected reactor technology—will be met.
[327]
While not without its
critics (see EA Report at p. 29), it appears that RD-337 sets out a
multi-layered methodology for assessing the ability of a nuclear plant to
withstand accidents and the risk of dangerous levels of radiation exposure to
workers and the public. The evidence before the Court is that a plant that does
not comply with the qualitative and quantitative safety goals set out in RD-337
will not be approved for construction or operation. One can debate the
methodology, but there is nothing on the record that would allow the Court to
say that reliance upon it by the Panel or the s. 37 decision-makers amounts to
non-compliance with any of the requirements of the Act. This is a matter upon
which the Court must defer to the Panel’s expertise.
[328]
RD-337 sets out a
clear (though complex) standard with respect to safety that new nuclear
facilities must meet. This standard and the knowledge that it will be enforced
allows both the Panel and the s. 37 decision-makers to fulfill their
responsibilities under the Act, even in the absence of complete design
information at the outset of the Project.
[329]
In other words, it is
my view that with respect to the safety of the Project itself, the Panel’s
analysis provides a sufficient factual basis for the decisions that needed to
be made, and fulfills the Panel’s obligations under the Act.
[330]
What the Panel raised
in its discussion of cumulative effects was that, in the specific circumstances
of this case, where the Project is being built on the site of an existing
nuclear generating station, accidents or malfunctions that affect both the
existing and new plants could have effects that go beyond those contemplated by
the RD-337 methodology. It found that these were effects that need to be
contemplated, particularly in relation to emergency planning measures.
[331]
This seems to engage
the realm of highly improbable, but possibility catastrophic, events. On
policy grounds, it is logical that such scenarios should be considered by
political decision-makers, because once again they seem to engage mainly
questions of “society’s chosen level of protection against risk” that will be
difficult for a specialized regulator to assess with legitimacy. On this view,
having found that such an analysis was required, it would seem more appropriate
for the Panel to have insisted it be completed within the EA process, so that
it could be considered in the s.37 context.
[332]
However, the language
of the statute introduces some uncertainty on this point. Section 16(1)(a)
says that a review panel shall consider:
the environmental effects of the project, including the
environmental effects of malfunctions or accidents that may occur in
connection with the project and any cumulative environmental effects
that are likely to result from the project in combination with other
projects or activities that have been or will be carried out;
[emphasis added]
[333]
Thus, cumulative
effects are to be considered if they are likely to occur, whereas
accidents and malfunctions that may occur in connection with the
project are to be considered. So, whether a common cause severe accident
affecting both the existing and proposed nuclear reactors at Darlington – a low
probability event – had to be considered in the context of the EA depends upon the
category in which it is placed: a cumulative effect relating to both the new
and existing facilities, or an accident “that may occur in connection
with the project” (emphasis added). In my view, the latter category is
sufficiently broad to encompass the proposed analysis. The statutory language does
not limit the consideration of accidents to those pertaining solely to the
Project, or exclude consideration of interactions with the surrounding
environment, including other facilities nearby.
[334]
In my view, the one
conclusion that is not supported by the language of the statute is the Panel’s
conclusion that the analysis had to be conducted, but could be deferred until
later. Rather, in my view, it had to be conducted as part of the EA so that it
could be considered by those with political decision-making power in relation
to the Project.
[335]
I recognize that, in
responding to the Panel’s recommendation, the Government of Canada stated as
follows:
The Government of Canada accepts the intent of this recommendation to
require OPG to evaluate the cumulative effect of a common-cause severe accident
in the site study area. The Government of Canada notes that the CNSC has
established a task force to examine the lessons learned from the Japan
Earthquake and will evaluate the operational, technical and regulatory
implications of the nuclear event in Japan in relation to Canadian nuclear
power plants.
Earlier in its response, the Government of Canada indicated that where it
“accepts the intent” of a recommendation, this means that it “agrees with the
underlying spirit of the recommendation but may not implement it precisely as
written by the Joint Review Panel.”
[336]
The existence of a
broader review related to the Fukushima Daiichi incident, which the record suggests
has now been completed, takes nothing away from the need to conduct a
site-specific analysis for new proposed nuclear plants. Indeed, one would
expect that the lessons articulated in the broader review would serve to
strengthen the site-specific analysis.
[337]
In my view, then, the
Panel’s approach to this issue was unreasonable and not in accordance with its
obligations under the CEAA and it needs to be revisited in some supplement or
amendment to the Report.
[338]
It is impossible to
discuss in detail all of the case law relied upon by the parties in this
application. However, in view of my findings on reviewable errors as set out
above, I think that it is necessary to address the following cases:
[339]
The West Vancouver
case, cited above, illustrates that the question of whether a decision-maker
had sufficient information to assess the environmental effects of a project and
their significance (taking into account feasible mitigation measures) is a
question to be determined on the facts of each case.
[340]
I have already noted
that, in some cases, it may be difficult to quantify effects, and a more
qualitative assessment may be necessary or appropriate. In the case at hand,
there was no real “qualitative” assessment of hazardous substance releases, and
in particular the effects of liquid effluent and stormwater runoff, but rather
only a consideration of potential mitigation measures. In my view, Justice
Lemieux’s analysis in West Vancouver can be distinguished on that basis:
West Vancouver was a case where the Court explicitly found that an
adequate qualitative assessment of the effect in question was completed based
on adequate evidence, and the case turned on that finding.
[341]
Though not
determinative, it should also be noted that the level of assessment at issue in
West Vancouver was a “screening assessment,” which is typically less
rigorous than an assessment by a review panel.
[342]
The framing of the
question was as follows:
[4] West Vancouver contends the federal screening assessment and
decision does not comply with the CEAA for three reasons:
(1) The RAs in their environmental assessment failed to conduct a risk
analysis of a material environmental effect, namely, the impact of blowdown or
windthrow of trees likely to be caused by the construction of a new four-lane
highway over the area adjacent to Eagleridge Bluffs and the Larsen Creek
Wetlands. Alternatively, West Vancouver says if the RAs made a finding that
windthrow of trees was not a significant adverse environmental effect, the
decision could not be rationally sustained having regard to the level of the
assessment actually conducted. Counsel for West Vancouver framed the
question on this issue as "[I]s it an error of law to identify an
environmental issue, defer the assessment to a later date but conclude before
the assessment that the Project is not likely to cause any significant
environmental effect ?"
[…]
[5] Canada conceded if the factual assumption underlying the
question framed by counsel for West Vancouver were true, the RAs' decision
would contain an error of law. However, he argued, no error was committed
because factually the assessment was made based on available and cogent
information. The assessment was not deferred. On this issue, counsel for B.C.
denied the scenario would constitute an error of law because mitigation was a
function of the final design.
[343]
The applicant in West Vancouver cited portions of a report completed for the BC Ministry of Transport
which appeared to show that there was not enough information available as of
the date when the screening assessment was completed to determine the impact of
blowdown or windthrow of trees and the significance of this impact. Justice
Lemieux emphasized that it was essential to look at this information in
context, having regard to the other information available to the
decision-makers:
[102] I agree with counsel for Canada and B.C. there was ample
evidence before the RAs to enable them to assess the environmental impact of
windthrow in the affected area and to consider its significance measured
against known mitigation techniques which cannot be implemented at the
preliminary design stage but rather must be implemented when the design of the
highway has taken shape.
[103] Specifically, based on the Dunster Report read in its entirety
and the other accumulated evidence, federal and provincial reviewers, on May 7,
2004, being aware of the windthrow issue which was specifically discussed at
this meeting, reached a tentative conclusion neither Option B nor Option D had the
potential for significant adverse environmental effect if mitigation was
applied, an opinion which was reasonably open to them to reach and to
subsequently confirm after the May 10th meeting with West Vancouver.
[104] In the circumstances, it was reasonable for the RAs to rely
upon B.C.'s (MOT) commitment to mitigate through follow up studies when the
timing to do such studies is appropriate.
[emphasis added]
[344]
In my view,
paragraphs 102 and 104 of West Vancouver must be read together, not in
isolation. The responsible authorities had “ample evidence… to assess the
environmental impact of windthrow in the affected area and to consider its
significance measured against known mitigation techniques….” In light of this,
“it was reasonable for the [responsible authorities] to rely upon B.C.’s…
commitment to mitigate through follow up studies when the timing to do such
studies is appropriate.”
[345]
In my view, Inter-Church Uranium Committee, above, is of limited assistance to the Respondents.
The case related to the operation of a uranium mine in northern Saskatchewan (the McClean Lake Project). The project was proposed while the Environmental
Assessment and Review Process Guidelines Order, SOR/84-467 (the
“Guidelines Order”) which preceded the CEAA was in effect, and an EA was
conducted under the Guidelines Order. Similar to the case at hand, the relevant
licensing scheme was a staged one, with separate licences issued for successive
stages of the project. After the CEAA and new regulations had come into effect,
the applicants challenged the issuance of an operating licence by the Atomic
Energy Control Board (predecessor to the CNSC) for a mill and tailings
management facility associated with the mine – the fifth operating licence to be
issued to the project, in addition to a site clearing licence and three
construction licences that preceded the operating licences. The applicants
argued that a new EA was required under the CEAA. The Federal Court (per
Campbell J) accepted this argument based on its interpretation of the
transitional provisions of the CEAA (specifically s. 74(1)), but the Court of
Appeal interpreted those provisions differently and reversed the Federal
Court’s decision. The case turned entirely on the interpretation of the
transitional provisions of the CEAA.
[346]
In the EA, the review
panel in Inter-Church Uranium Committee had expressed concern over the
proposed tailings management method, which was somewhat unproven, and had
recommended that the project be delayed for at least five years so that more
could be learned about its viability based on a similar facility then in
operation. The responsible authorities rejected that approach, and allowed the
project to proceed under the staged licensing process, since it was anticipated
that the licensing process would take several years and would, over time, deal
with the issues raised by the panel regarding tailings management. That
decision by the responsible authorities was not at issue before the Court.
[347]
Rather, as noted
above, at issue was whether a new EA was required before a new licence could be
issued following the coming into force of the CEAA. The Court of Appeal
addressed this issue in the following terms:
[47] That does not mean that the end of the work of the Panel means
an end to all environmental review for the McClean Lake Project. Environmental
issues must be considered for each licence issued under the Uranium and Thorium
Mining Regulations and their successor, the Uranium Mines and Mills
Regulations. In addition, the CEAA environmental screening and assessment
process may be triggered in future if subsection 74(3) of the CEAA applies.
That would be the case if, for example, there is a proposal to undertake some
activity relating to the McClean Lake Project that was not within the Panel's
terms of reference (such as the increase in production proposed and permitted
by the Commission in 2001, which had not been considered by the Panel
established under the Guidelines).
[48] The ICUC is concerned that too narrow an interpretation of
subsection 74(1) of the CEAA could mean that when the McClean Lake Project is
finally decommissioned many years from now, there will be no new environmental
assessment. Such concerns are speculative at this stage. The extent to which a
new environmental assessment will be required for a decommissioning licence
will depend on the circumstances at that time, and the precise proposal that is
presented to the Commission in the application for a decommissioning licence.
[49] The ICUC also argued that subsection 74(1) of the CEAA does not
apply because the current McClean Lake Project is not the same
"proposal" that was reviewed by the Panel under the Guidelines. The
ICUC points to several changes in the Project since 1993, including a change in
the proponent and majority owner, design changes, the discovery of new
environmental threats from arsenic, a scientific study indicating radioactive
contaminant can migrate over long distances in groundwater faster than
originally thought, a new regulatory climate with regard to water quality
guidelines for arsenic, and the addition of radionuclides from uranium mills to
the List of Toxic Substances in Schedule I to the Canadian Environmental
Protection Act, S.C. 1999, c.33. In my view, none of these changes transform
the McClean Lake Project into a new proposal. The Panel recognized that changes
in science and technology would occur over the life of the Project and
acknowledged that it would be the Board's responsibility to evaluate the
effects of these developments in the context of its licensing responsibilities.
[…]
[51] As subsection 74(1) of the CEAA is dispositive of these
appeals and the application for judicial review, it is unnecessary to
consider the remaining arguments made by the appellants.
[emphasis added]
[348]
Read in their
context, paragraphs 47 and 49 of this decision do not, in my view, support the
Respondents’ position. They merely point out that, while a valid EA had been
conducted under the Guidelines Order and was still applicable to the project,
environmental concerns would continue to receive consideration through the
licensing process. If anything, this reinforces the Applicants’ point that it
is likely that only one EA will be conducted on the Project at issue in the
present case, despite the fact that there will be several subsequent licensing
steps that will include consideration of environmental effects. The case recognizes that the process of assessing and managing a project’s effects does not end
with the completion of the EA, but beyond this, it does not assist the
Respondents.
[349]
The question at issue
in the current matter is whether a valid EA was conducted. This was answered in
Inter-Church Uranium Committee by reference to the transitional
provisions of the CEAA, which have no relevance here. The substantive adequacy
of the assessment of the assessment conducted under the Guidelines Order was
not at issue, since it was “not alleged that the Guidelines are deficient in
any substantial way, or that an environmental problem associated with the
McClean Lake Project was missed or ignored because of the application of the
Guidelines and not the CEAA” (para 33 above). Therefore, in my view, the case
provides no assistance to the Respondents with respect to whether the
assessment in the current matter was conducted in accordance with the
requirements of the Act.
[350]
Express Pipelines, above, addresses closely related
issues. This was the first case in which the Federal Court of Appeal considered
the CEAA. The application for judicial review was considered by the Court of
Appeal at first instance (see paras 6 and 7). Of particular relevance are
paragraphs 13 and 14:
[13] It was argued, and in this the applicants echoed the views of
the dissenting panel member, that subsection 16(1) requires a sequential
examination of the factors enumerated therein. In particular, it was said that
the panel erred in not considering the possible environmental effects of the
project before looking at any possible mitigating measures. Nothing in the
statute supports such a view. Section 16 certainly does not say or imply that
the listed factors must be considered sequentially while section 37 (as well as
sections 20 and 23 which do not apply in this case) strongly suggests that
mitigation measures and environmental effects must be considered together. In
our view, logic and common sense point the same way: there can be no purpose
whatever in considering purely hypothetical environmental effects when it is
known and proposed that such effects can and will be mitigated by appropriate
measures.
[14] Finally, we were asked to find that the panel had improperly
delegated some of its functions when it recommended that certain further
studies and ongoing reports to the National Energy Board should be made before,
during and after construction. This argument misconceives the panel's function
which is simply one of information gathering and recommending. The panel's view
that the evidence before it was adequate to allow it to complete that function
"as early as is practicable in the planning stages ... and before
irrevocable decisions are made" (see section 11(1)) is one with which we
will not lightly interfere. By its nature the panel's exercise is predictive
and it is not surprising that the statute specifically envisages the
possibility of "follow up" programmes. Indeed, given the nature of
the task we suspect that finality and certainty in environmental assessment can
never be achieved.
[351]
The Federal Court of
Appeal’s decision in Express Pipelines, delivered orally from the bench,
is brief. It does not provide a great deal of context regarding how the
effects of the project under consideration and their potential mitigation were
actually considered by the panel. Nor does it elaborate on the applicants’ argument
that “the panel had improperly delegated some of its functions when it
recommended that certain further studies and ongoing reports to the National
Energy Board should be made before, during and after construction.” In my view,
it is necessary to carefully consider the Court of Appeal’s analysis, to avoid
reading in principles that were not intended.
[352]
In paragraph 13, the
Court of Appeal found that the panel was not required to conduct “a sequential
examination of the factors enumerated” in s. 16(1). In other words, it was not
required to consider the adverse effects of the project first, their
significance second, and possible mitigation third, though the Panel in the
present matter stated that this is the best approach and the one it intended to
follow (see EA Report at p. 39). Rather, the Court of Appeal stated,
“mitigation measures and environmental effects must be considered together,”
based on the language of the Act and the common sense conclusion that “there
can be no purpose whatever in considering purely hypothetical environmental
effects when it is known and proposed that such effects can and will be
mitigated by appropriate measures” (emphasis added).
[353]
In my view, this
finding has most relevance in the present case to the question of whether the
gaps in the bounding scenario relating to the expected releases of hazardous
substances from the Project (in particular through liquid effluent and
stormwater runoff) mean that the Panel did not reasonably consider the
Project’s effects in this regard – one of the three potential inadequacies
being analyzed.
[354]
In my view, the
statement that mitigation measures and environmental effects “must be
considered together” does not, at least in the case at hand, obviate the need
to consider the potential effects at all. Rather, it is unnecessary to consider
“purely hypothetical environmental effects when it is known and proposed
that such effects can and will be mitigated by appropriate measures” (emphasis
added).
[355]
On the facts of this
case, it is in my view not possible to know that the potential effects in
question “can and will be mitigated” to below the level of significance
(which the Court identified at paragraph 10 as the “principal criterion” set by
the statute) without having some sense of what level of effect would be
significant, which is a decision for the s. 37 decision-makers. Where there is
no available standard or set of standards that can serve as a proxy for
significance (and the Panel has not pointed to one in this case with respect to
hazardous substance releases), in my view, those decision-makers must be
provided with information about the actual expected effects and the degree to
which they will be mitigated. In some cases (as in West Vancouver), this
analysis will be more qualitative, whereas other circumstances will permit and
call for a more quantitative approach, as I would argue is the case here. In
any case, where an effect is potentially significant, simply stating that an
unknown level of effect will be mitigated to another unknown level is not
sufficient to permit the s. 37 decision-makers to discharge their
responsibilities.
[356]
As for paragraph 14,
it tells us two things. First, it is not inappropriate for a review panel to
recommend that further studies be conducted and ongoing reports be made to a
regulatory body during and after the construction of a project. This is not a
surprising finding in any way.
[357]
The second point is
of more central significance to the present matter. It is that a “panel’s view
that the evidence before it was adequate to allow it to complete” its function
of information gathering and recommending as set out in the statute “as early
as is practicable” is “one with which [a court should] not lightly interfere.”
In my view, this point is fully addressed through the standard of review the
Court has chosen to adopt in this matter: the Court will only interfere if and
to the degree that the Panel’s approach to some important aspect of its
analysis was unreasonable. In my view, the Court’s analysis in this case fully
reflects and incorporates the principles stated in Express Pipelines.
[358] The Applicants say that the Panel’s
consideration of “need” is so fundamentally incomplete and lacking in
information, evidence or analyses as not to comply with the Panel’s duties
under the CEAA and the Terms of Reference.
[359]
The “need” issue is
addressed in section 4.3 of the EA Report, and the Panel’s conclusions are as
follows:
The Panel is of the view that the Ontario Ministry of Energy has explained
the need for the Project and the rationale behind the Ontario Government
direction to OPG. The Panel further notes that the Ontario Government posted
the draft Supply Mix Directive to the Ontario Environmental Registry for a
45-day public review before Cabinet approved the final Directive in February
2011. Further, the Ontario Power Authority consulted the public in May and June
2011 on its draft Integrated Power System Plan and is expected to submit the
plan to the Ontario Energy Board for public review later in 2011. In accordance
with his authority granted under the Electricity Act, 1998 (O. Reg. 164/99),
the Minister of Energy has directed the Ontario Energy Board to review the
proposed Integrated Power System Plan at public hearings, no later than 12
months after the Ontario Power Authority submits it. The Panel believes that
these public consultation opportunities are the proper venues for the public to
express their views regarding Ontario energy policy.
[360]
The Applicants submit
that the provincial Minister’s Directive does not in law amount to a proper
analysis or demonstration of the “need” for the Project pursuant to the CEAA. They
say that, if accepted by the Court, such an approach will allow the Panel to
avoid its legal duty to fully consider the mandatory factors required by s. 16
of the CEAA in combination with the Terms of Reference, including “purpose” and
“need.” Moreover, they say that, as a matter of law, a provincial Minister or
project proponent cannot constrain or bind the Panel in the exercise of its
statutory responsibilities under federal law. Thus, the Applicants submit that
the Panel declined its jurisdiction by erroneously treating the Directive as
dispositive of the “need” issue under the CEAA.
[361]
Subsection 16(1)(e)
of the CEAA requires the Panel to consider the following:
16. (1) Every
screening or comprehensive study of a project and every mediation or
assessment by a review panel shall include a consideration of the following
factors:
[…]
(e) any other
matter relevant to the screening, comprehensive study, mediation or
assessment by a review panel, such as the need for the project and
alternatives to the project, that the responsible authority or, except in the
case of a screening, the Minister after consulting with the responsible
authority, may require to be considered.
|
16. (1) L’examen
préalable, l’étude approfondie, la médiation ou l’examen par une commission
d’un projet portent notamment sur les éléments suivants :
[…]
e) tout autre
élément utile à l’examen préalable, à l’étude approfondie, à la médiation ou
à l’examen par une commission, notamment la nécessité du projet et ses
solutions de rechange, — dont l’autorité responsable ou, sauf dans le cas
d’un examen préalable, le ministre, après consultation de celle-ci, peut
exiger la prise en compte.
|
[362]
In the present case,
the Panel clearly considered “need” and decided to defer to the EIS Guidelines
(which said that provincial energy policy was not within the Terms of
Reference) and the process carried out by the Ontario Ministry of Energy.
[363]
The Applicants appear
to be of the view that the Panel was obliged to conduct a detailed analysis of
its own on “need.” Legal authority suggests otherwise. In Sharp,
above, the Federal Court of Appeal said that “paragraph 16(1)(e) is not a back
door means of re-empowering [the Canadian Transportation Agency (CTA)] with
economic regulatory control over the construction of railway lines” (para 28).
The context was that Parliament had intentionally adopted a hands-off approach
that left the decision of whether particular railway lines were needed primarily
up to railway companies. Except where there was a serious conflict (e.g. the
environmental impact of a proposed project was extremely high), the CTA had to
try to reconcile its responsibilities under the CEAA with “Parliament’s express
deregulatory intention” under the relevant statutory scheme. In this case, the
relevant contextual consideration is not a “deregulatory intention” of
Parliament, but rather the constitutional division of powers. In my view, the
principle stated by the Court in Sharp applies with even more force in
this context. The Minister was careful to note that matters of Ontario energy policy were outside of the Panel’s purview. CEAA is not a back-door means of
empowering the Panel with economic regulatory power over Ontario energy policy.
Rather, the Panel’s primary duty was to determine whether the proposed Project
would result in significant adverse environmental effects. Absent some
indication that this mandate could not otherwise be fulfilled, the Panel was
neither required nor entitled to engage in an in-depth analysis of the pros and
cons of various means of meeting Ontario’s energy demand. It was “entitled to
base its decision on need and alternatives on what it was told” by the
proponent and the Ontario Ministry of Energy (Sharp, above, at para 25).
[364]
In other words, in
the circumstances of this case, it was reasonable for the Panel to conclude
that need had been decided as a matter of Ontario energy policy, which process
had provided, or would provide, opportunities for the public, including the
Applicants, to express their views.
[365]
Similar
considerations arise in relation to the Panel’s treatment of “alternatives”
which is found at section 4.4 of the Report.
[366]
In dealing with this
issue, the Panel requested OPG provide additional information on alternatives
to the Project, and OPG produced a table and an Alternative Analysis which
concluded that there were no reasonable alternatives to the Project that were
both within its interest and control and consistent with “the direction and
clarification provided by the Government of Ontario.”
[367]
The Panel also
pointed out that the EIS Guidelines framed the way it was to approach this
issue. It accepted the constraints preventing OPG from considering other forms
of energy. Notwithstanding that “an assessment of provincial energy policy” was
“not within the panel's terms of reference” and that “alternatives to the
project need not include alternatives that are contrary to Ontario's formal
plans and directives,” (p. 42) the Panel nevertheless went on to assess and
express concerns:
The Ontario Ministry of Energy provided an overview of alternatives and
considerations that led to the proposed supply mix in the Long-Term Energy
Plan. In its final comments, the Ministry presented a summary of the need for a
balanced supply mix and the options considered.
The Panel understands the constraints preventing OPG from considering the
development of other forms of energy. The Ontario Government Long-Term Energy
Plan and Supply Mix Directive
dictate the projects the proponent shall pursue. However, if at a later
date the Ontario Government revises the current energy supply mix and reduces
the nuclear baseload capacity, it would be possible to develop a different
portfolio within the competence of OPG. While the Panel acknowledges the public
consultation to date on the Ontario Government energy policy, it regrets the
fact that the new Darlington Project is being evaluated before the Ontario
Energy Board hearings on the Integrated Power System Plan are completed.
The Panel also notes that the Long-Term Energy Plan and Supply Mix
Directive were developed before the Fukushima Daiichi nuclear accident. Since
this accident, more concerns have been raised about nuclear power generation
globally. The Panel understands the challenges the Ontario Government faces as
it proceeds with phasing out coal to reduce greenhouse gas emissions and
permanently shutting down the Pickering Nuclear Generating Station. However,
the Panel wishes to acknowledge the desire expressed by many participants for a
re-examination of the Ontario energy alignment.
[368]
Section 16(1)(e) gives
the Minister discretion as to whether the need for and alternatives to the Project
are to be considered at all in the EA. In my view, it is implicit that, should
the Minister decide that these factors should be included, he or she has the
discretion to determine the scope of their consideration.
[369]
The Minister did not
speak directly to this in the Agreement or the attached Terms of Reference. The
list of the factors to be considered included the “Need for the Project” and
“Alternatives to the Project” without qualification. However, the Minister did
say in the EIS Guidelines that (at p. 17):
7.1 Purpose and Need for the Project
The proponent must clearly describe the need for the proposed new nuclear
power plant. This description must define the problem or opportunity the
project is intending to solve or satisfy and should establish the fundamental
justification or rationale for the project.
The proponent must describe the purpose of the project by defining what is
to be achieved by carrying out the project.
The “need for” and “purpose of” the project should be established from the
perspective of the project proponent and provide the context for the consideration of
alternatives in Sections 7.2 and 7.3 below.
7.2 Alternatives to the Project
An analysis of alternatives to the project must describe functionally
different ways to meet the project’s need and achieve the project’s purpose
from the perspective of the proponent. This section must therefore identify and
discuss other technically and economically feasible methods of producing
electricity other than the construction and operation of the OPG Darlington
NNPP that are within the control and/or interests of OPG. As an
assessment of provincial energy policy is not within the terms of reference of
this joint review panel, the alternatives to the project need not include
alternatives that are contrary to Ontario’s formal plans or directives.
However, the EIS must explain where this rationale has been applied to exclude
consideration of possible alternatives to the project.
[emphasis added]
It would have been preferable for the Minister to state these restrictions
on the scope of the factors to be considered in the Agreement and Terms of
Reference, as this was the most direct mechanism available to the Minister for
this purpose.
[370]
The scope of
consideration of the mandatory factors in ss. 16(1)(a), (b) and (d) and
16(2)(b), (c) and (d) was to be determined by the Minister “when fixing the
terms of reference of the mediation or review panel” (CEAA, s. 16(3)(b)). By
contrast, paragraph 16(1)(e) is not specific about the mechanism by which the
Minister indicates his or her decision about the inclusion of non-mandatory
factors under that paragraph, stating only that a review panel shall include
consideration of “any other matter relevant to the… assessment…, such as the
need for the project and alternatives to the project, that the responsible
authority or… the Minister after consulting with the responsible authority, may
require to be considered” (CEAA, s. 16(1)(e)).
[371]
Given the less
specific wording of s. 16(1)(e), I accept that the Agreement and the EIS Guidelines
should be read together for the purpose of determining whether and to what
extent the “need for” and “alternatives to” the Project were to be considered
in the EA. While these factors were included without qualification in the list
of factors to be considered as set out in the Terms of Reference, the language
of the EIS Guidelines imposes restrictions that were appropriately taken into
account by the Panel.
[372]
I also find, as the
Respondents argue, that the Panel was entitled to come to the same conclusions
on its own about the proper approach to considering these factors. In my view,
the Panel was entitled to keep the constitutional division of powers and prior
jurisprudence in mind when interpreting its mandate. The electricity supply mix
in Ontario is a matter of provincial jurisdiction. A federal EA should not
become an alternative forum for deciding that issue, or a back door means of
economic regulation: Sharp, above, at para 28; Grand Riverkeeper,
above at paras 53-54.
[373]
It seems to me, then,
that the Panel’s analysis of "alternatives," as with
"needs," was undertaken in accordance with the Terms of Reference and
EIS Guidelines set out by the Federal Minister of the Environment and that,
given these constraints, the Panel went as for as it could with its
consideration of alternatives under subsection 16(1)(e) of the CEAA. I can see
no reviewable error here.
[374] The Applicants say that, since the CEAA
does not expressly empower review panels to delegate their s. 34 obligations,
the Panel in this case did not fulfill its duties before reporting to the
Minister and before recommending that certain matters should receive further
attention by other bodies. The complaint is that the Panel went beyond
permissible limited types of delegation and, instead, made recommendations
intended to generate critically important information that would backfill
significant evidentiary gaps. These are said to relate to the specific project
design, baseline conditions, environmental effects, site development and layout
and other key matters the Panel was legally obliged to assess, disclose,
solicit public input on, and report upon pursuant to s. 34.
[375]
This is, essentially,
part of the Applicants’ argument that the lack of a designated reactor
technology in the proposed Project prevented a meaningful assessment under the
CEAA and forced improper delegation to other agencies in the future.
[376]
As the EA Report
makes clear, the Panel itself endorses the Applicants’ view of its duties under
the CEAA. In discussing the analytical framework for the Report in section 4.1,
the Panel tells us that it “applied a precautionary approach and considered the
principles of sustainable development in its review.” The Panel goes into
considerable detail as to what the precautionary approach to assessment means
and the “guiding principles for the application of precaution to science-based
decision-making in areas of federal regulatory activity for the protection of
health and safety and the environment and the conservation of natural resources”
(EA Report at p. 38).
[377]
The Panel
specifically makes the following point about its approach to the Assessment of
Environmental Effects in its conclusion to section 4.1.3 of the EA Report:
The Panel is of the view that adaptive management, a systematic process
for the continuous improvement of environmental management practices, should
only be applied in cases where thresholds can be defined. Adaptive
management should not be used to overcome a situation where there is a lack of
scientific data or certainty.
[emphasis added]
[378]
I see nothing here
that, in principle at least, is in conflict with the Panel's duties under s.34
or any other provision of the CEAA.
[379]
These statements of
principle by the Panel have to be considered in conjunction with its specific
finding that, following the process of submissions and hearings required under
the CEAA, it had the information and data required to complete the EA in
accordance with the Act and the principles referred to in the Report and which
I have noted above. The Panel does, however, explicitly link this finding to
the existence of future licensing steps. At p.50 of the EA Report it says:
The Panel notes that there is a licensing phase for operation and
maintenance during which the proponent would be required to submit specific
details. Because of this and in light of the data submitted, the Panel
determined that for environmental assessment purposes it has sufficient
information to determine the likelihood of significant adverse environmental
effects of the Project.
As I have said previously, this was an expert, scientific panel and it
tells us in its Report that it has the wherewithal to assess whether the
necessary thresholds have been met in accordance with the precautionary approach
to assessment. But it would appear that the Panel’s conclusion on this point was
as much interpretation of the appropriateness of deferring certain matters to
the CNSC as it was a scientific or factual determination about the sufficiency
of the evidence before it.
[380]
The Applicants have
attempted to characterize the Report in particular ways and attack its approach
conceptually. They say it does not assess a “project,” that the bounding
approach is incompatible with an EA under the CEAA, and that the Panel engaged
in improper delegation in order to backfill information and data gaps that were
an inevitable consequence of the Panel’s failure to insist upon a specific
reactor type as a prerequisite for a meaningful assessment.
[381]
All of these issues are
certainly arguable but, in the end, the Applicants are really saying that the
Panel did not have the necessary information and other inputs to produce a
meaningful EA in accordance with the Act. They are attacking the Panel's
foundational finding on this point and they are asking the Court to disagree
with the assessment of the expert Panel on a finding of scientific fact. I
think it goes without saying that the Court must be very reluctant to interfere
with such a finding.
[382]
This does not mean,
of course, that the Court simply accepts at face value the Panel's own
statements about its methodology, its adherence to the precautionary approach,
or its awareness of the dangers of adaptive management without the scientific
data to establish the necessary thresholds. The Applicants have pointed to
specific instances throughout the Report where they believe improper delegation
was relied upon by the Panel. I have examined each instance in turn, and it
seems to me that the Panel acknowledges the contingencies that a Project of
this nature and duration necessarily throws up and that will require
mitigation, follow-up, reliance upon other bodies, and future assessment. But
the necessary thresholds, and the scientific data and advice to support those
thresholds are, generally speaking, there and allow the Panel to say that this
Project is not likely to give rise to significant adverse environmental
impacts. The only instances where this is not the case, in my view, and where
improper delegation occurs are those instances I have listed above where I do
not think thresholds are sufficiently specified and where the scientific data
is not available to arrive at reasonable assessments.
[383]
For the most part,
however, the Panel’s approach appears to me to be in accordance with the guidance
of the Federal Court of Appeal in Express Pipelines, above:
[14] Finally, we were asked to find that the panel had improperly
delegated some of its functions when it recommended that certain further
studies and ongoing reports to the National Energy Board should be made before,
during and after construction. This argument misconceives the panel's function
which is simply one of information gathering and recommending. The panel's view
that the evidence before it was adequate to allow it to complete that function
"as early as is practicable in the planning stages ... and before
irrevocable decisions are made" (see section 11(1)) is one with which we
will not lightly interfere. By its nature the panel's exercise is predictive
and it is not surprising that the statute specifically envisages the
possibility of "follow up" programmes. Indeed, given the nature of
the task we suspect that finality and certainty in environmental assessment can
never be achieved.
[384]
Except for the
specific instances I have cited, the Panel’s approach is to ensure that the
necessary thresholds are there for a project of considerable magnitude and
duration that, by its very nature, obliges the Panel to take into account and
assess the scientific and regulatory safeguards that will be in place for each
successive step. As the AGC points out, nuclear power facilities are subject to
several different areas of regulatory oversight. Under the NSCA, a nuclear
power plant is subject to a staged licensing process. OPG has to seek separate
licenses for the site preparation, construction, operation, decommissioning,
and abandonment of the Project. At each stage, OPG will be required to supply
additional information on the Project design specifications and the
environmental effects of the Project. The CNSC will not issue a license unless
it is of the opinion that OPG “will, in carrying out the activity, make
adequate provision for the protection of the environment.”
[385]
In my view, this is
not improper delegation or crystal-ball gazing. Other than for the exceptions I
have already noted, it seems to me that the Panel’s approach accords with the
guidance from this Court in such cases as Pembina Institute, above, at
paras 23 and 34.
[386]
The Applicants
contend that the Panel’s failure to assess the Project in accordance with ss. 15(3),
16(1) and (2) and 34 of the CEAA was compounded by procedural errors in that
the Panel refused to:
(a)
extend the public
comment period or the EIS;
(b)
allow
cross-examination on evidence or undertaking answers; and
(c)
adjourn the public
hearing so that missing information could be obtained, publicly disclosed and
carefully assessed by the Panel.
[387]
My review of the
record confirms the factual background on these issues provided by OPG:
50. The Applicants wrote to the Panel requesting that OPG and CNSC
staff be required to present evidence at the hearing under oath. Waterkeeper
had made a similar request of the Agency, which was not accepted, prior to the
establishment of the Panel. The Panel rejected the Applicants’ requests in
oral reasons delivered on the first day or the hearing. The Panel stated that
it was not a court of law and had the discretion to review and accept evidence
and information it considered appropriate. Neither CEAA not the NSCA
required decision-makers to accept or reject evidence based on the formal rules
of evidence applicable to a civil or criminal trial.
51. The Applicants CELA and Waterkeeper also requested that the
Panel adjourn the hearing to allow for the collection of what they described as
“information missing from the record.” The Panel rejected this request in the
same oral reasons. It indicated that if public hearings were only to be held
once the Panel had obtained all the information it needed to make its
recommendations, the assessment would never get to the hearing stage. The
Panel stated that once it heard from all participants, it would review the
evidence gathered and make a decision with regard to the sufficiency of the
information provided.
52. The Panel also addressed in its ruling the Applicants’ request
that the hearing be adjourned because they did not have adequate time to deal
with the EC-6 design. The Panel expressly rejected “the intervenors’
assertions that they did not have sufficient time or notice to prepare.” The
Panel explained that it had provided direction on its process in both 2010 and
March 2011, that its directions had made clear that the review process was
technology neutral, and that if it determined that further information was
required regarding EC-6 it would provide participants with an opportunity to
file further submissions. After considering all of the submissions on the
issue, the Panel concluded that it did not need to adjourn the proceeding as
the EC-6 technology would be considered during the hearing.
[388]
The Panel was obliged
under its Terms of Reference to direct procedures in accordance with the CEAA,
the NSCA, and the Panel Agreement. As the Supreme Court of Canada made clear in Prassad, above, at pp 568-569,
We are dealing here with the powers of an administrative tribunal in
relation to its procedures. As a general rule, these tribunals are considered
to be masters in their own house. In the absence of specific rules laid down
by statute or regulation, they control their own procedures subject to the
proviso that they comply with the rules of fairness and, where they exercise
judicial or quasi-judicial functions, the rules of natural justice.
Adjournment of their proceedings is very much in their discretion.
[389]
In the present case,
the CEAA, the NSCA and the Panel Agreement do not stipulate any specific
applicable rules for the hearing process that was conducted by the Panel. I
can find nothing unreasonable or procedurally unfair about the way the Panel
handled these issues.
[390]
Given the Panel’s
acknowledgment that the PPE “is a departure from a more standard approach where
the major components of a project are defined in advance of an environmental
assessment,” this was bound to be a highly controversial EA that strained the
boundaries found in the CEAA. However, in my view, the record shows that,
through input and the hearing process the Applicants and other like-minded
participants were given ample opportunity to present their views of the
inadequacies of the PPE as an approach to environmental assessment and the specific
problems to which it gave rise for this particular Project. The arguments
against the PPE approach and the failure of OPG to identify a specific reactor
technology are fully acknowledged and discussed in the EA Report itself (see
section 3.3.10 for example) and the Panel shows itself to be alive to the
criticisms of the Applicants and others through the Report.
[391]
This debate has been
continued before the Court in this application. However the legal issues are
characterized (no “project,” failure to apply ss. 34, 16(1) and (2) of the CEAA
etc.), the principal complaint is that the PPE approach did not allow for a
meaningful EA as required by the CEAA. The Panel, however, makes a specific
finding that the PPE approach used in this case does permit a meaningful
assessment:
The Panel accepts the use of a plant parameter envelope for environmental
assessments purposes as an approach that allows the prediction of adverse
environmental effects for a select group of reactor technologies.
[392]
In the end, the
Applicants are asking the Court to disagree with this finding. Many of the Applicants’
objections to the approach do not strike me as unreasonable. However, the issue
is not whether I agree or disagree with the Applicants or the Panel. Paragraph
47 of Dunsmuir, above, requires me to examine “justification,
transparency and intelligibility within the decision‑making process” and
to decide “whether the decision falls within a range of possible, acceptable
outcomes which are defensible in respect of the facts and law.”
[393]
It is certainly
possible to disagree with both the Panel’s conclusion that the PPE approach
allows for a meaningful EA and with the PPE’s application to the factors
mandated by the CEAA, but I don’t think it is possible to say that it falls
outside of the range posited in Dunsmuir, above. And I do not think it
is possible to say that the Panel’s deployment of the PPE approach throughout
its analysis, other than those instances I have cited above, was not in compliance
with the CEAA, even though the nature and duration of this Project, and OPG's
failure to designate a specific reactor technology undoubtedly caused the Panel
to rely heavily upon mitigation, follow-ups, commitments and future actions and
measures that will need to be considered and implemented as the Project
advances through its various stages. In the end, however, the Panel was of the
view that it could all be done in a way that would not be likely to cause
adverse environmental and health impacts. Notwithstanding the strong concerns
of the Applicants, other than those instances I have already pointed out, the
Court cannot say that this conclusion was unreasonable or that the references
to future actions mean that a meaningful assessment of environmental impacts
was not conducted in accordance with the Act.
[394]
My specific findings
of inadequacies and unreasonableness in the EA Report do not vitiate the whole
Report, although it seems to me that some reconsideration and corrective action
is required that will allow the Cabinet and s. 37 decision-makers to assess, or
re-assess, the whole Project and make their decision accordingly. I have
attempted to craft a remedy that will allow this to happen without discarding
what appears to me to be the highly competent work accomplished by the Panel.
[395]
The Panel’s dual
mandate was to conduct the EA required under the CEAA and (acting as the
Commission) to review OPG's application under the NSCA for a license to prepare
the Darlington site.
[396]
The background to
this application involves the issue of whether the Panel conducted an EA in
accordance with the CEAA (dealt with above under T-1572-11) as well as other
allegations that, in issuing the License, the Panel failed to comply with
certain mandatory requirements under the NSCA, and also breached procedural
fairness by relying upon extraneous documents that were not part of the record.
[397]
In conjunction with
this application, the Applicants have also brought a motion to strike portions
of the affidavit of Ms. Laurie Swami served by the Respondent OPG on the
grounds that the portions of the affidavit to which the Applicants object are
not connected to the licensing decision at issue in this application and are
not relevant to whether the Panel afforded the Applicants procedural fairness.
[398]
This ground of
complaint involves a repetition of the grounds and issues I have already dealt
with in T‑1572-11 above. Consequently, I refer to my reasons given in
T-1572-11 and adopt them for the purpose of review in this application
T-1723-12.
[399]
Because I have concluded that the EA was
deficient in certain respects, the statutory prerequisites for the issuance of
the Licence were not fulfilled, and the Licence is therefore invalid. However,
the Applicants’ other arguments attacking the Licence Decision fail for the
reasons outlined below.
[400]
The Applicants argue
that, since OPG did not identify a specific reactor technology for the Project
in its license application, that application was premature and, more
importantly, it also meant that the CNSC lacked the jurisdiction to grant a
license because the CNSC did not have sufficient information on matters
prescribed by the Class 1 Nuclear Facilities Regulations.
[401]
It seems to me that
this argument is based upon a particular reading of the NSCA and the
Regulations that cannot be sustained. This was an application for a Site Preparation
License. I see nothing in the NSCA or the Regulations that require the reactor
technology to be specifically identified before such a license can be issued.
It may be, of course, that the failure to identify the reactor technology may
prevent the Panel (Commission) from complying with the governing provisions,
but that will be a question of fact in each case.
[402]
Under s. 24(4) of the
NSCA no license can be issued unless “in the opinion of the Commission” the
applicant
(b) will, in carrying on that activity, make adequate provision for
the protection of the environment, the health and safety of persons and the
maintenance of national security and measures required to implement
international obligations to which Canada has agreed.
[403]
The “activity” in
question here is clearly site preparation and not the Project as a whole, which
will require further licenses in the future if decisions are made to proceed to
construction, operation, abandonment and decommissioning.
[404]
Hence, the issue here
is whether, in the opinion of the Panel (Commission), OPG would make adequate
provision for the protection of matters referred to in s. 24(4)(b) if OPG
carries out site preparation.
[405]
Throughout its licensing
decision the Panel (Commission) makes it clear that there are certain matters,
such as Safety Analysis, Physical Design, Fitness for Service, Radiation
Protection, that are not within the scope of the LTPS and which will later be
assessed once the design of the reactor technology has been selected for
construction and an application is made for a license to construct.
[406]
This position is emphasized
in the Panel's “conclusion on site evaluation” at para 102 of the Reasons for
the Licence Decision:
Based on the above information, the Commission is satisfied that, given
the mitigation measures in place and to be in place, as well as the commitments
made by OPG during the environmental assessment for the project, the site meets
the requirements for a new nuclear power plant in accordance with RD-346. As
such, the Commission concludes that the site is suitable for the construction
of the proposed nuclear generating station. The Commission notes that the
reactor design to be chosen by the Province of Ontario for construction at the
site will be reviewed and assessed as part of an application for a Licence to
Construct, and that the chosen reactor design must meet regulatory requirements
for a Licence to Construct, including conformance with the PPE, in order to
proceed to the construction phase.
[407]
It is also made clear
in the License itself, part 4 of which says that the "License Activity"
is confined to “site preparation activities.”
[408]
The Applicants refer
the Court to ss. 3(b) and (e) and 4(e) of the Regulations. Section 4(e) refers
to “the activity to be licensed,” which in this case is site preparation and
not the construction of the reactor technology. A reading of the Reasons for
the Licence Decision reveals that the Panel (Commission) clearly addressed the
plans for the site and the hazardous substances that “may be on site while the
activity to be licensed is carried on,” in forming its opinion.
[409]
Subsection 3(b) of
the Regulations is somewhat of a departure from the language of the provisions
that surround it, in that it speaks to a requirement for “plans showing the
location, perimeter, areas, structures and systems of the nuclear facility”,
and not merely the activities to be authorized by the specific licence being
issued. However, I think it is clear from the EA Report that this criterion was
satisfied. That Report states that OPG developed “three separate model plant
layout scenarios” depicting “the maximum extent of development from different
planning perspectives for each of the reactor technologies and cooling
technologies”, and “provided updated and alternative site layouts” as the
review proceeded (EA Report at p. 12). These plans were far from final, but
given the stage of the Project and considering the statutory scheme as a whole, I
think it was reasonable for the Panel (Commission) to accept them as meeting
the requirements of s. 3(b) for the purposes of the Site Preparation Licence
application. The Panel (Commission) found at paras 124-125 of its Reasons that
the “physical design” of the nuclear facility itself was not within the scope
of the Site Preparation Licence application, and the Applicants have not
demonstrated that this was an unreasonable conclusion in view of the language
of s. 3(b) of the Regulations, which requires only “plans showing the…
structures and systems of the nuclear facility”. The Panel (Commission) also
stipulated at paragraph 15 of its Reasons for the Licence Decision that:
… [I]n order to minimize the overall effects on the terrestrial and
aquatic environments and maximize the opportunity for quality terrestrial
habitat rehabilitation, OPG must perform a thorough evaluation of site layout
opportunities before site preparation activities can begin.
Thus, I am satisfied that the Panel (Commission) complied with both the
letter and the spirit of s. 3(b) of the Regulations in issuing the Site
Preparation Licence.
[410]
In my view, the
Applicants have not demonstrated that, in the absence of a chosen reactor
technology, it was unreasonable for the Panel (Commission) to form the opinion
expressed in the Reasons for the Licence Decision or that, in doing so, the
Panel (Commission) failed to address, or comply with, any provision of the NSCA
or the Regulations.
[411]
The Applicants’
complaint here is that, in reaching its licensing decision, the Panel
(Commission) made reliance in its Reasons for the Licence Decision on the
Fukushima Task Force Report and Action Plan, as well as a number of documents
cited in the License Condition Handbook which existed only in draft form, or
not at all, during the hearings. They say these documents were not part of the
record so that, in accordance with the principles of procedural fairness
outlined in Baker, above, and the doctrine of reasonable expectations,
the Applicants were deprived of an opportunity to make submissions on issues
that went into the License Decision.
[412]
In this regard, it is
necessary to understand how the Fukushima incident and the eventual Task Force
Report and Action Plan entered the proceedings for the EA in T-1572-11 and the Site
Preparation License application under review here. OPG has provided a summary which
has not been challenged by the Applicants:
27. At the hearing the Panel requested that information be presented
regarding the Fukushima Daiichi nuclear accident. This information included a
presentation by CNSC staff on the implications of the accident (including the
earthquake and tsunami) for the project, a presentation by the Geological
Survey of Canada on earthquakes in Canada and a presentation by OPG on the
seismic hazard assessment of the Project.
28. In its report the Panel recognized “that the Fukushima Daiichi
nuclear accident did have an effect on the hearing. Many participants referred
to the recent events in Japan with expressions of sympathy, and cited it as an
example of what could happen if a beyond design basis accident were to occur at
the Project site.” Participants raised the Fukushima Daiichi nuclear accident
in respect of a number of issues considered by the Panel, including accidents
and malfunctions, emergency planning, costs and economic effects,
seismicity/geology and alternatives to the Project. The Panel also considered
the Fukushima Daiichi nuclear accident in its findings on the estimated costs
of the Project and land use and development.
29. The Panel concluded in its report that conventional accidents or
malfunctions were not likely to cause significant adverse environmental
effects. However, it went on to conclude, “based on the views expressed by
participants during the review and the concerns regarding accident scenarios
such as the Fukushima Daiichi nuclear accident,” that OPG should evaluate the cumulative
effect of a common-cause severe accident scenario “that would include all of
the nuclear generating reactors in the site study area.” The Panel recommended
that CNSC require OPG to perform such an evaluation prior to reactor
construction.
[413]
As regards the
proceedings for the Site Preparation Licence, the Applicants point out that:
19. Despite the applicants’ demonstrated interest in the Fukushima disaster and the relevance of the lessons that could be learned from it at the
public hearings, the CNSC subsequently considered documents generated by an
external CNSC Task Force after the close of public hearings. The CNSC’s
Reasons for Decision for issuing the Licence contains multiple references to
the CNSC’s Fukushima Task Force Report and Action Plan (at pp. 4, 13, 15, 18,
48). The Fukushima Task Force Report is dated October 2011 (approximately four
months after the close of the public record by the Panel and six months after
the end of the public hearing in relation to the project). The Action Plan is
dated March 2, 2012 (approximately 9 months after the close of the public
record by the Panel and 11 months after the public hearings concluded).
20. In response to the applicants’ Rule 317 request for the Panel’s
record in this application for judicial review, counsel for the CNSC advised
the applicants that the Panel’s record for the Licence decision is identical to
the Panel’s record for the EA, and that no new documents would be disclosed or
produced. That record does not include the Fukushima Task Force Report or
Action Plan.
21. The Fukushima Task Force Report and Action Plan were not
tendered as exhibits during the public hearings held by the Panel, and thus
were not subject to notice or comment opportunities for the applicants or other
interveners in the hearings.
22. Had the Fukushima Task Force Report and Action Plan been duly
tendered as exhibits and intervenors given notice or comment opportunities in
relation to them, the applicants would have voiced serious concerns regarding
these documents and the Panel’s reliance on them, including the continued
inadequacy of the risk assessment performed by OPG and the fact that the Task
Force Report and associated Action Plan could not fill the Project-specific
information gaps left by the Panel’s assessment.
[414]
The Applicants have
not developed their procedural fairness arguments based upon documents in the
License Condition Handbook that were only in draft form or were not part of the
proceedings. Hence, although the Panel (Commission) may have referred to such
documentation, the Applicants have not demonstrated that it was a material
basis for the Panel’s Reasons in granting the Site Preparation Licence.
[415]
The Applicants seek
to exclude portions of an affidavit filed by the Respondents describing the
public consultation process in relation to the Fukushima Task Force Report and
the CNSC Action Plan (Swami affidavit, paras 12-22), on the grounds that
neither the Report nor the Action Plan were entered as evidence before the Panel
(Commission) whose decision is the subject of judicial review in T-1723-12.
[416]
Generally speaking,
the only documentation of relevance in a judicial review application is the
record that was before the decision-maker. However, there are certain
well-recognized exceptions to this rule in applications that raise bias,
jurisdiction, and procedural fairness. See Tl'Azt'En First Nation v Joseph,
2013 FC 767 at para 16; International Relief Fund for the Afflicted and
Needy (Canada) v Canada (Minister of National Revenue), 2013 FCA 178 at
paras 9-10; Assn of Universities and Colleges of
Canada v Canadian Copyright Licensing Agency, 2012
FCA 22 at paras 19-20.
[417]
In the present case,
the Applicants allege that it was procedurally unfair for the Panel
(Commission) to refer to and rely upon the Task Force Report and Action Plan
because they had no notice of these documents and no opportunity to comment
upon them before the Panel rendered its licensing decision. In order to
support this allegation, the Applicants have filed the Stensil and Cooper
affidavits. Mr. Stensil says that the Task Force Report and Action Plan “were
not subject to notice or current opportunities for Greenpeace or other
interveners” (para 111). Ms. Cooper says that the Task Force Report and Action
Plan were “not subject to notice or current opportunities for CELA or other
interveners.”
[418]
It seems clear that
the Task Force Report and Action Plan were not produced under Rule 317 as part
of the record that was before the Panel (Commission) in the licensing
proceedings and were not listed as exhibits. However, procedural fairness is
concerned with substance, not form. One of the issues for the Court in the
T-1723-12 application is whether the Task Force Report and Action Plan “were
not subject to notice or current opportunities for the applicants or other
interveners in the hearing” (para 2 of the Applicant’s Memorandum of Fact and
Law).
[419]
The paragraphs of the
Swami affidavit to which the Applicants object dealt with this very issue.
They say that the Task Force Report and Action Plan were posted for comment,
and outline the public consultation process in relation to them, which occurred
between October 2011 and May 2012. This was after the Panel’s (Commission’s)
public hearings for the purposes of both the EA and the Site Preparation
Licence, but before the Licence Decision, which was issued August 17, 2012. The
affidavit shows that two of the Applicants, Greenpeace and Lake Ontario
Waterkeeper, provided written comments during that process, and that Greenpeace
made a presentation to the CNSC at a meeting in May 2012 concerning the two
documents.
[420]
The Respondents argue
that this public consultation process satisfied the requirements of procedural
fairness in relation to the Fukushima Task Force Report and Action Plan for the
purposes of the Site Preparation Licence application as well.
[421]
The Applicants reply
that the Respondents are blurring the distinction between the Panel who decided
the Site Preparation Licence application and the CNSC at large, which conducted
the public consultation on the Fukushima accident.
[422]
The merits of the
Respondents’ argument based on the Swami affidavit remains to be considered below,
but it was certainly a reasonable argument for them to make. Both processes
were the work of the Commission, and the Applicants (or some of them)
participated in both. Whether a distinction can be made between the licence
proceedings and more general public consultation on Fukushima is the factual
and legal question to be answered, and the Court requires a factual record to
answer it. Ms. Swami’s evidence is directly relevant to that very issue and
needs to be part of the review record.
[423]
In short, the
impugned portions of the Swami affidavit are directly relevant to the
procedural fairness issue that the Applicants have placed before the Court in
their T-1723-12 application and are admissible evidence.
[424]
The relevant rule of
procedural fairness, as stated by Dickson CJ in Kane v Board of Governors
(University of British Columbia), [1980] 1 S.C.R. 1105 at pages 1115-1116, is
that “each party to a hearing is entitled to be informed of, and to make
representations, with respect to evidence which affected the disposition of
the case” (emphasis added) (see also Pfizer Co v Canada (Deputy Minister
of National Revenue, Customs and Excise), [1977] 1 S.C.R. 456 at page 463).
[425]
In my view, if the
Panel had placed substantive reliance on the documents in question in their
licensing decision, this may have amounted (depending on the nature of that
reliance) to a breach of procedural fairness. This is because, while the
Applicants had an opportunity to comment on those documents generally in a
separate process, they did not have the opportunity to address the actual
decision-makers – the members of the Panel (Commission) making the licensing
decision – regarding their relevance and application to the Project itself.
Indeed, it would appear that none of the members of the Panel were present for
the CNSC’s public hearing on those documents where Greenpeace presented. The
Panel’s own public hearings took place before the draft Task Force Report and
Action Plan were first released for public comment. It was in this context that
Waterkeeper requested that the Project proposal be sent back to the Panel for
reconsideration with specific reference to the Task Force Report.
[426]
However, what is
decisive here is that the Panel (Commission) placed no reliance on the
Fukushima Task Force Report and Action Plan in coming to its Licence decision.
Rather, it directed that future reports on the Project to the CNSC incorporate
the findings of the Task Force report, and reiterated its recommendation from
the EA report that any increased regulatory requirements resulting from the
Task Force Report and Action Plan should be incorporated into the Project as
early as possible.
[427]
The Panel
(Commission) makes five references to the Fukushima Task Force Report and
Action Plan in its Reasons for the Licence Decision. They are as follows:
16. The Commission directs OPG to prepare a mid-term report on the
conduct of the licensed activities and the implementation status of commitments
made during the environmental assessment. This report should also take into
account the findings of CNSC Fukushima Task Force.
[…]
58. The Commission is satisfied that the information presented by
OPG meets the regulatory requirements for an application for a LTPS and the
expectations set forth in RD-346. The Commission notes, however, that the EA
Report raised the issue that lessons leaned from the 2011 Fukushima Daiichi
nuclear accident would likely result in changes to regulatory requirements and
suggested that any resulting increased regulatory requirements should be
incorporated into the Project as early as possible. The Commission further
notes that the CNSC has issued an action plan to address the lessons learned
from the Fukushima Daiichi nuclear accident and reiterates the suggestion from
the EA Report.
[…]
68. Furthermore, the Commission notes that analysis of
low-probability events is underlined in the CNSC Fukushima Task Force Report as
a means of identifying possible mitigating strategies.
[…]
84. The Commission notes that an Action Plan was prepared by the
CNSC task force and subject to public consultations and a public meeting in May
2012. The Commission expects findings from the CNSC Fukushima Task Force report
to be considered as part of the mid-term review for the LTPS.
[…]
235. The Commission accepts the proposed reporting requirements from
CNSC staff, including the presentation of the CNSC’s annual CNSC Staff
Integrated Safety Assessment of Canadian Nuclear Power Plants. In addition,
the Commission directs OPG and CNSC staff to prepare more detailed mid-term
reports on the conduct of the licensed activities and the implementation status
of commitments made during the environmental assessment, taking into account
the findings of the CNSC Fukushima Task Force. The CNSC staff report should
also include detailed information on the control of land use around the site over
the operating life of the nuclear generating station, as well as on the
environmental monitoring and follow-up program.
[428]
Bearing in mind how
the Fukushima incident entered the EA proceedings and the discussions and
submissions that took place surrounding it, it is hardly surprising that the Panel
felt it appropriate to refer to the incident, as well as the Task Force Report and
Action Plan in its Reasons for the License Decision. However, what the
Applicants have not demonstrated before me is how the Fukushima incident and
the Task Force Report and Action Plan are made a material aspect of the Panel’s
site evaluation, which formed the basis for the issuance of the Licence and the
opinion that the Panel (Commission) came to in accordance with s. 24(4) of the
NSCA and ss. 3 and 4 of the Regulations which the Applicants cite as the key
provisions. The references to the Task Force Report and Action Plan referred
to above are either passing notices of that report or directions that future
reporting should take it into account. Clearly, the Panel (Commission) did not
feel that the Fukushima incident or the Task Force Report and Action Plan were
material to its decision to issue the Site Preparation Licence.
[429]
In pointing out that
the record before the Panel did not include the Fukushima Task Force Report or
Action Plan, the Applicants are correct, but they are placing form ahead or
substance. This omission could only be of significance if:
(a)
The Panel relied upon
these documents for its licensing decision; and
(b)
If reliance was made,
that the Applicants were, in fact, deprived of the opportunity to voice their
“serious concerns regarding these documents” and the fact that the documents
“could not fill the Project-specific information gaps left by the Panel’s assessment.”
[430]
The Applicants have
not made clear what might be included in their term “serious concerns,” and
they have not demonstrated how the Task Force Report and Action Plan were used
by the Panel to fill information gaps left by the Panel’s assessment. In my
view, if the Panel (Commission) had relied upon the Task Force Report in a substantive
way in coming to its conclusions on the License application, the Applicants
might have a legitimate argument that they did not have an opportunity to
address what these documents have to say about the Project and whether the
License should be granted. However, in my view, the record shows that no such
reliance is demonstrated. In fact, it seems clear that no such reliance was
made by the Panel (Commission).
[431]
Procedural fairness
attracts a correctness standard of review. For reasons given, I conclude that
there was no breach of procedural fairness in this case.