Date: 20070925
Docket: T-954-06
Citation: 2007 FC 955
Ottawa, Ontario, September 25, 2007
PRESENT: The Honourable Mr. Justice Martineau
BETWEEN:
MININGWATCH
CANADA
Applicant
and
MINISTER OF FISHERIES AND
OCEANS,
MINISTER OF NATURAL RESOURCES,
ATTORNEY GENERAL OF CANADA,
RED CHRIS DEVELOPMENT COMPANY LTD.
and BCMETALS CORPORATION
Respondents
REASONS FOR ORDER AND ORDER
TABLE OF CONTENTS
I – INTRODUCTION
II – THE PROJECT
III – REQUIREMENT OF AN ENVIRONMENTAL
ASSESSMENT (EA)
A.
DIVIDED
AUTHORITY
B.
PARTICULAR
ASPECTS
1) Protection
of fish habitat
2) Air-borne
contaminants and other environmental risks
3) Endangered
species
C.
TRIGGERS
TO THE EA OF THE PROJECT
1) Provincial
triggers
2) Federal
triggers
a) Definition
of “project”
b) Federal
authority
D. EA PROCESS
UNDER THE CEAA
IV – FACTUAL BACKGROUND
A. PROVINCIAL
ASSESSMENT
1) Preliminary
decision
2) Terms
of reference
3) Section
11 order
4) The
Application and the Application Supplement
5) Public
consultation
6) Consultations
with First Nations
7) Assessment
report
8) Environment assessment
certificate
B. FEDERAL
ASSESSMENT
1) Preliminary
decision
2) Notice
of Commencement
3) Initial
tracking decision
4) Departments’ responses
5)
Minister
of Environment
6)
Work
plan
7)
Subsequent
tracking decision
8)
Unresolved
issue respecting the amount of water
9)
The Scoping Decision of March
2005
10)
Provincial
assessment
11)
Consultations
with First Nations
12)
Screening
Report
13)
The Course
of Action Decision
V – THE PRESENT APPLICATION
VI – STANDARD OF REVIEW
VII – PRELIMINARY ISSUES RAISED BY THE
RESPONDENTS
VIII – MERITS OF THE CASE
c) Review
panel or mediator
2) The
nature of scoping
C. CASE
LAW
1) Bowen
2) Manitoba's Future Forest Alliance
a) Factual
background
b) Judicial
review application
c) Decision
in first instance
d) Decision
in appeal
D. COURSE
OF ACTION DECISION REVIEWABLE
IX - CONCLUSION
REASONS FOR ORDER AND ORDER
I – INTRODUCTION
[1]
Red
Chris Development Company Ltd. (RCDC), a wholly-owned subsidiary of bcMetals
Corporation (bcMetals), (collectively the Proponent), wishes to develop an open
pit mining and milling operation for the production of copper and gold in the
form of copper concentrates from deposits located in north-western British
Columbia. This proposed mine development is known as the “Red Chris porphyry
copper-gold mine project” (the Project).
[2]
MiningWatch
Canada (the Applicant)
is a federally registered non-profit society. Functioning as a coalition of
member organizations, the Applicant is principally interested in the
environmental, social, economic, health and cultural effects of mining, in particular
its effects on indigenous peoples.
[3]
The
Applicant challenges the legality of decisions or actions taken by the
department of Fisheries and Oceans (DFO) and Natural Resources Canada (NRCan) in
conducting the environmental assessment (EA) of the Project under the purported
authority of various provisions of the Canadian Environmental Assessment Act,
S.C. 1992, c. 32, as amended (the CEAA).
[4]
The
minister of Fisheries and Oceans and the minister of Natural Resources are
represented in this proceeding by the Attorney General of Canada (collectively
the Crown). The Proponent and the Crown are respondents in this judicial review
application (collectively the Respondents). The Respondents support the
decisions or actions taken by the DFO and NRCan (collectively the responsible
authorities or the RAs).
[5]
For
the reasons below, I have decided to allow the present application. Current legislative
and regulatory provisions mentioned in the present reasons for order are
reproduced in Appendix “A”.
II – THE PROJECT
[6]
The
“Red Chris property” is the sole asset of RCDC and consists of mineral claims
that cover an area of approximately 110 square km surrounding the proposed mine
site. It is located within the Tahltan Nation traditional territory, in a sparsely
populated area which is about 18 km southeast of the village of Iskut, 80
km south of Dease
Lake and 450 km
north of Smithers.
[7]
More
particularly, the proposed mine is situated on a terrace located on the Togadin
Plateau on the boundary of two regional watersheds: the Klappan and Iskut River. The
Project site is divided by White Rock Canyon Creek flowing into Coyote Creek
and the Iskut River to the northwest; Quarry Creek, flowing into the Klappan
River to the northeast; and the Trail Creek System draining to the south
through Kluea and Todagin Lakes and the Iskut River.
[8]
The
Project falls within the Togadin Resource Management Zone of the Cassiar Iskut-Stikine Land and Resource
Management Plan (CIS-LRMP), which recognizes mineral exploration, mine
development and mine access as appropriate activities.
[9]
The
Project is based on the mill production rate of 30 000 tonnes of ore per day for
sale to the export market, over a projected mine life of 25 years. The mine
site would be accessed by a new long access road which would intersect highway
37 on the south side by Coyote Creek. The 550 tonnes of concentrate produced
per day at the mill would be transported to the deep-sea port of Stewart situated
about 200 km to the south of the proposed development. The Project is expected
to require 228 million in capital expenditures and would generate 250 direct
full-time jobs.
[10]
Apart
from the Project, current or reasonable foreseeable projects and mining
activities in this area include: the Galore Creek project, an open pit mine
that would process up to 60,000 tonnes per day of ore and produce up to 2,000
tonnes per day of gold-copper concentrate; the existing Tom McKay Lake waste
rock and tailings project, near the Eskay Creek mine; the current and proposed
Kemess North and existing Kemess South projects; and the Mount Klappan project.
[11]
The
power requirements for the Project are estimated at 37 megawatts (mw).
Currently, the nearest existing source of power is BC Hydro’s substation
located at Meziadin Junction, approximately 220 km south of the proposed mine
site. RCDC proposes the construction of a new power line that would run parallel
to the proposed new mine access road and link with the anticipated BC Hydro
power line. RDCC has made a commitment not to begin construction until there is
a commitment by the Province to build the power line.
[12]
The
proposed mining operation is a conventional shovel and truck open pit mine.
Blast holes will be loaded with bulk explosives. Mine explosives would be
stored in two separate areas close to the open pit. The explosives facilities
would comprise a powder magazine, an emulsion tank with a 20,000 kg capacity,
silos holding ammonium nitrate, and an explosives plant and garage (the
explosives factory and magazine).
[13]
It
is expected that open pit mining would continue at a rate of 10.95 million
tonnes (mt) of ore per year for 17 years, after which low-grade ore recovered
from the stockpile would be processed for the remaining eight years. Plant
design would be based on a standard porphyry copper flow sheet employing SAG
and ball milling, flotation, regrinding, thickening and filtering to produce a
concentrate for export with a moisture content of 8%. The Project would produce
a total of 1.85 billion pounds of copper and 1,187,000 ounces of gold contained
in concentrate.
[14]
During
the lifetime of the mine, the owner or operator would be depositing a
deleterious substance (tailings) into a tailings impoundment area (TIA). The
site proposed is in a Y-shaped valley approximately 3.5 km northeast of the Red
Chris’ deposit. Construction of three dams would be required at the south,
north, and the northeast arms of the valley. The total catchment area for the tailings
impoundment including diverted areas would be around 2700 ha. The total
diverted area would be around 1100 ha.
[15]
During
operations, water from the TIA would be discharged into Quarry Creek and
following closure, water would be discharged into the unnamed Creek below
Northeast Dam. Flows in Quarry Creek would likely increase by a predicted 119%.
In the post-closure period, both water quantity and quality within Quarry Creek
are predicted to return to pre-development conditions, as discharges from the
TIA would then be released around the Northeast Dam into Northeast Arm Creek.
Flow changes in the creek system downstream of the Northeast Dam are expected
to be small during the mining operation but will increase substantially
following closure due to the release of runoff water from the TIA through the Northeast
Dam. In the post closure period, the tailings impoundment overflow through the Northeast
Dam is expected to increase the new annual discharge by 157%.
[16]
The
proposed TIA would adversely affect some fish habitat, watercourses and aquatic
resources. The two beaver dam colonies within the TIA site would be displaced
from the TIA site during mine operations, as would mink, waterfowl and Western
Toad, with the potential for their gradual return after reclamation of the site
following mine closure. The water quality may also be affected by acid rock drainage
and metal leaching (ARD/ML), a natural geologic event caused by the oxidation
of acid rocks. Subsequent metal leaching and acidic runoff may reduce local
water quality in the receiving environment if management of materials and
treatment of runoff is not undertaken.
[17]
All
waste rock generated by the Project would be placed within the North waste rock
dump by the operator of the mine. The North dump has been sited by RCDC so that
all drainage from the dumpsite would gravity-flow into the TIA during the
mine’s operation and life. The TIA would operate under a surplus water balance
requiring the discharge of water to the receiving environment. Over the
operating life of the mine (years 1 through 18) the amount of excess water to
be discharged in the environment has been estimated by RCDC to average 6
million m3 per year (16,400 m3 per day). In the
post-closure period, the amount of water to be discharged to the receiving
environment would be 13 million m3 per year (35,600 m3
per day). RCDC would treat or otherwise manage the excess-tailings impoundment
water to be released to the receiving environment, if necessary. During the
mine’s operation life, the excess water to be released from the proposed tailings
impoundment would be discharged by pump and pipeline to the north of the
impoundment into the upper reaches of Quarry Creek that drains toward the Klappan River.
III – REQUIREMENT OF
AN ENVIRONMENTAL ASSESSMENT (EA)
A. DIVIDED AUTHORITY
[18]
The
contemplated mine and mill, as well as associated works and activities related
to the Project, all fall under the heads of local works and undertakings, property
and civil rights, and matters of a purely local nature, and are thus under the
jurisdiction of the Province of British Columbia (sections 92(10), (13) and
(16) of the Constitution Act, 1867, 30 and 31 Victoria, c.3 (U.K.), as
amended (the Constitution Act, 1867)).
[19]
However,
the effect of the Supreme Court decision in Friends of Oldman River Society
v. Canada, [1992] 1 S.C.R. 3, is to confer on Parliament the power to
provide for an environmental impact assessment in any matter within federal
jurisdiction. This includes, among other matters, navigation (s. 91(10)),
fisheries (s. 91(12)), federal public lands and Indian reserves (ss. 91(1A) and
91(24)), international and interprovincial rivers, interprovincial and
international transportation and communication (s. 92(10)(a)), and the
activities of industries within federal jurisdiction (s. 91, opening words and
s. 92(10)(a), (b) and (c)).
[20]
Indeed,
in Friends of Oldman River Society, above, the dam on the Oldman River had an
effect on navigable waters, fisheries and lands reserved for the Indians (there
was an Indian reserve downstream from the dam site). These effects justified a
wide-ranging environmental assessment encompassing the impact of the dam on
those three subject matters, as well as any other federal matters that turned
out to be implicated. Parliament had the power to provide for an environmental assessment
as an incident of any institution or activity that was otherwise within federal
jurisdiction. Moreover, “the scope of the assessment is not confined to
the particular head of power under which the Government of Canada has a
decision-making responsibility” [emphasis added]. On the other hand, the
province also had authority to provide for environmental impact assessment of
the project, both under provincial powers over natural resources and property
and civil rights and also by virtue of its power to spend money.
[21]
That
being said, the criminal law power under section 91(27) of the Constitution
Act, 1867 provides broad power to Parliament to prohibit activities that are
harmful to the environment. This power has been used to uphold the Canadian
Environmental Protection Act, R.S.C. 1985, c.16 (4th suppl.),
which establishes a regulatory structure for the identification and control of
toxic substances (R. v. Hydro-Québec, [1997] 3 S.C.R. 213).
B. PARTICULAR
ASPECTS
1) Protection
of fish habitat
[22]
In
the present case, the proposed mine development contemplates the construction
of barriers and seepage dams, water supply and associated works, and of a
tailings management facility as well as a water diversion system. This attracts
Parliament’s jurisdiction over water resources and fisheries. Indeed, the Fisheries
Act, R.S.C. 1985, c.F-14, as amended (the Fisheries Act) deals with the
protection of fisheries and fish habitat. The two primary sections of the
Fisheries Act that deal with environmental protection are section 35,
protecting fish habitat and paragraph 36(3), prohibiting the deposit of any
“deleterious substance” in water frequented by fish unless the deposit is
authorized by regulations made by the Governor in Council.
[23]
Apart
from the contemplated harmful alteration, disruption or destruction of fish
habitat (HADD), which requires an authorization from the Minister of Fisheries
and Oceans pursuant to subsection 35(2) of the Fisheries Act, once the mine and
mill will be in operation, deleterious substances (tailings) are likely to be
deposited in water frequented by fish. The metals will come from milling
operations, and from the precipitation runoff and groundwater draining through
the North waste dump and across and through the exposed rock and the open pit
walls.
[24]
Moreover,
over time, a significant proportion of the waste rock in the North waste dump
and in the exposed wall rock is expected to become acidic, generating increased
concentrations of metal contaminants that will require treatment to produce an
acceptable quality of effluent for release to receiving waters.
[25]
The
Metal Mining Effluent Regulations, SOR/2002-222, as amended (the MMER)
applies in respect of mines that exceed the threshold of an effluent flow rate
of 50 m3 per day and deposit a “deleterious substance” in any water
or place referred to in subsection 36(3) of the Fisheries Act (paragraph 2(1)
of the MMER). The substances are set out in column 1 of Schedule 4 of the MMER
and any acutely lethal effluent is prescribed as deleterious substances.
[26]
Paragraph
1(1) of the MMER defines an “effluent” as “an effluent — mine water effluent,
milling facility effluent, tailings impoundment area effluent, treatment pond
effluent, treatment facility effluent other than effluent from a sewage treatment
facility, seepage and surface drainage — that contains a deleterious substance.”
Pursuant to section 4 of the MMER, the deposit of the deleterious substance in
an effluent must not exceed certain levels of concentration and the deposit is
conditional on the owner or operator complying with sections 6 to 27 of the
MMER which prescribes effluent monitoring conditions. In the present case, RCDC
recognizes that the MMER would apply and that monitoring will be necessary
under the MMER if the Project is carried forward.
[27]
In
particular, section 6 of the MMER prohibits an owner or operator of a mine to
combine an effluent with water or any other effluent for the purpose of diluting
the effluent before it is deposited. However, the prohibition mentioned at
section 6 of the MMER does not apply, and the owner or operator of a mine may
deposit or permit the deposit of waste rock on an effluent that contains any
concentration of deleterious substance into a TIA that is a water or place set
out in schedule 2 of the MMER. Again, such authority to deposit will be
conditional on the owner or operator complying with sections 7 to 28 of the
MMER.
[28]
In
British Columbia, there are three TIAs currently mentioned in schedule 2 of the
MMER: South Kemess Creek; Albino Lake and Tom MacKay Lake. Therefore,
an amendment by the Governor in Council will be required to add the headwaters
of Trail Creek as a TIA.
[29]
Moreover,
section 27.1 of the MMER (which came into force on October 3, 2006), obliges
the owner or operator of the mine to prepare a “habitat compensation plan” for
approval by the minister of Fisheries and Oceans. The purpose of a habitat
compensation plan is to offset the loss of fish habitat resulting from the
deposit of a deleterious substance into the TIA. The basis of this requirement
is DFO’s “Policy for the Management of Fish Habitat” (1988). Key to this policy
is the principle of “no net loss” with regard to works and undertakings. This
policy has been applied to mining projects since 1986, and habitat compensation
agreements have been negotiated for a number of mining projects.
2) Air-borne
contaminants and other environmental risks
[30]
In
the case at bar, potential sources of air-borne contaminants from the Project
include the construction and operation of the TIA and the explosives factory.
Indeed, in its material submitted to the provincial and federal authorities,
RCDC has identified air contaminants generated by construction equipment,
drilling, blasting, loading, hauling and grading associated with construction of
the tailings dams.
[31]
Environmental
effects pertaining to the explosives factory and magazine are general safety
concerns, effluent management, waste handling, spill contingency and
malfunction and accidents. The explosives factory also has associated exhaust
gases and potential fugitive dust generated during construction by bulldozing,
levelling, hammering, lifting and hauling equipment.
[32]
Furthermore,
licences will be required for the explosives factory and magazine contemplated
in the Project. Under federal statutory law, the minister of Natural Resources
may issue licences for factories and magazines under paragraph 7(1)(a)
of the Explosives Act, R.S.C., 1985, c. E-17, as amended(the Explosives
Act). The Explosives Regulatory Division (ERD) within NRCan also issues
mechanical ammonium nitrate fuel oil (AN/FO) certificates, which are granted to
companies producing AN/FO with powered equipment to be discharged directly into
a borehole at a specified location, mine or quarry owned by the company to
which the certificate is issued.
3) Endangered
species
[33]
In
2002, Parliament adopted comprehensive legislation binding on Her Majesty in
right of Canada or a province to prevent wildlife species from being extirpated
or becoming extinct, to provide for the recovery of wildlife species that are
extirpated, endangered or threatened as a result of human activity; and to
manage species of special concern to prevent them from becoming endangered or
threatened: the Species at Risk Act, S.C. 2002, c. 29, as amended
(SARA), sections 5 and 6.
[34]
Pursuant
to subsection 79(1) of SARA, every person who is required by or under an Act of
Parliament to ensure than an EA of a project is conducted, must notify the
minister of the Environment that a project is likely to affect a listed wildlife
species or its initial habitat.
[35]
In
the case at bar, such notice was given to the minister of the Environment by
DFO in February 2005. In this regard, the Western Toad, found within the
proposed TIA site, is listed in Schedule 1 of SARA.
[36]
Accordingly,
pursuant to subsection 74(2), the RAs must ensure that measures are taken to
avoid or lessen those effects and to monitor them. Further, these measures must
be taken in a manner that is consistent with any applicable recovery strategy
and actions plans.
C. TRIGGERS
TO THE EA OF THE PROJECT
[37]
In
the case at bar, the Project is subject to the requirement of an EA under both the
Environmental Assessment Act, S.B.C. 2002, c. 43, as amended (the
Provincial Act) and the CEAA.
1) Provincial
triggers
[38]
For
the purposes of the present judicial review application, it is not necessary to
undergo a detailed analysis of all relevant provisions of the Provincial Act
except to note that under section 8 of same, an environmental assessment
certificate is required before a “reviewable project” can proceed.
[39]
Indeed,
RCDC’s proposal to construct, operate, dismantle and abandon the Project
constitutes a reviewable project, as contemplated by Part 3 of the Reviewable
Projects Regulation, B.C. Reg. 370/02, as amended, because the proposed copper-gold
mine is a new facility with a production capacity of greater than 75,000 tonnes
per year of mineral ore.
[40]
An
environmental assessment certificate under the Environmental Assessment Act,
S.B.C. 2002, c.43, as amended (the EAA); a permit under the Mines Act,
R.S.B.C. 1996, c. 293, as amended (the MA); a special use permit under the Forest
Practices Code of British Columbia, R.S.B.C. 1996, c. 159, as amended (the
FPC); and a licence to cut under the Forest Act, R.S.B.C. 1996, c. 157,
as amended (the FA) must be delivered or issued by the responsible provincial
authorities for the purpose of enabling the Project to be carried out in whole
or in part.
2) Federal
triggers
[41]
Under
federal law, pursuant to paragraph 5(1) of the CEAA, an EA is required for a “project”
if a “federal authority” is the proponent of the project; provides financial
assistance to enable the project to be carried out; administers federal lands
or transfers the administration and control of those lands to a province for
the purpose of enabling the project to be carried out; or issues a
prescribed permit or licence or grants a prescribed approval or takes any other
action for the purpose of enabling the project to be carried out in whole or in
part [emphasis added].
[42]
However,
an EA is not required under section 5 of the CEAA where the project is
described in the “Exclusion List” (EL) found in the Exclusion List
Regulations, SOR94-634, as amended (the ELR), made under paragraph
59(c)(ii) of the CEAA (see section 7 of the CEAA). The EL applies to the
following general areas: agriculture; electrical and nuclear energy; oil and
gas pipelines; forestry; water projects; transportation; national parks;
national parks reserves; national historic sites; and historic canals. The EL
exempts projects with insignificant environmental effects from EAs. The Project
is not mentioned on the EL.
[43]
As
can be seen, an EA under the CEAA can only be conducted with respect to a
“project” and there must be a “federal authority” involved. Both of these
conditions are met in the present case.
a) Definition
of “project”
[44]
The
Project has been fully described in the preceding section of the present
reasons (see above, I - The Project). To summarize, the Project comprises the
following undertakings: two open pits; a mine camp, maintenance shop and
associated works; a processing plant; a TIA and associated water diversion
system; waste rock dump and low grade ore stockpiles; an explosives factory and
magazine; water supply and associated works; any off-site or on-site
compensation or mitigation projects as may be required; a new access and haul
road and related infrastructure; a new power line; any other physical works on
facility activities included in constructing, operating and decommissioning the
above facilities.
[45]
In
relation to a “physical work”, paragraph 2(1) of the CEAA defines a “project”
as being “any proposed construction, operation, modification,
decommissioning, abandonment or other undertaking in relation to that
physical work”. Moreover, a project can also be “any proposed physical
activity not relating to a physical work that is prescribed or is within a
class of physical activities that is prescribed pursuant to regulations made
under paragraph 59(b)” [emphasis added]. The Project comes within the scope of
the definition of project found in paragraph 2(1) of the CEAA.
[46]
In
this regard, the Inclusion List Regulations, SOR/94-637, as amended (the
ILR), made pursuant to paragraph 59(b) of the CEAA, sets out those physical
activities and classes of physical activities not relating to physical works
which, nonetheless, must be considered as a “project”. The broad areas to which
the ILR applies include: national parks and protected areas; oil and gas
projects; nuclear and related facilities; defence; transportation; waste
management; fisheries; flora and fauna; projects on aboriginal lands; northern
projects (Yukon and Northwest Territories); and forests. Part VII of the Schedule
entitled “Physical activities and classes of physical activities” (the IL)
deals with “fisheries”.
[47]
More
particularly, the IL applies to a number of activities carried out in the water
body or adjacent to a water body, which includes: 1) the harmful alteration,
disruption or destruction of fish habitat (HADD) by means of physical
activities, or by means of draining or altering the water levels of a water
body, or by means of erosion control measures, that require the authorization
of the Minister of Fisheries and Oceans under subsection 35(2) of the Fisheries
Act; and 2) the deposit of a deleterious substance in an effluent that requires
authorization under regulations made by the Governor in Council pursuant to
subsection 36(5) of the Fisheries Act (see items 42 to 47 of the Schedule to
the ILR). Accordingly, any such physical activities contemplated in the Project
are covered by the IL, and thus come under the ambit of the CEAA.
b) Federal
authority
[48]
In
the case at bar, no federal authority is the proponent of the Project or
provides financial assistance to enable the Project to be carried out. However,
as explained below, at least two federal authorities, DFO and NRCan, must take
certain regulatory actions in order to permit the Project to be carried out in
whole or in part. Paragraph 5(2) of the CEAA further makes it clear that an EA
is also required before the Governor in Council issues a prescribed permit or
licence or grants a prescribed approval or takes any other action for the
purpose of enabling the project to the carried out in whole or in part.
[49]
In
this regard, the Law List Regulations, SOR 194-636 as amended, (the LLR)
made pursuant to subsections 59(f) and (g) of the CEAA, lists the provisions of
any Act of Parliament or any regulation made pursuant to any Act of Parliament
that confer powers, duties or functions on federal authorities or the Governor
in Council (Cabinet), the exercise of which requires an EA under paragraph
5(1)(d) or subsection 5(2) of the CEAA. This list is exhaustive, not open, and
therefore any powers, duties or functions found outside the law list will not
require an EA.
[50]
In
the case at bar, an EA is mandatory under paragraph 5(1)(d) and 5(2)(a) of the
CEAA because the Project requires: 1) an authorization from the minister of
Fisheries and Oceans pursuant to subsection 35(2) of the Fisheries Act for the
HADD of fish habitat; 2) the issuance of a licence by the minister of Natural
Resources under paragraph 7(1)(a) of the Explosives Act for the
contemplated explosives factory and magazine; and, 3) an amendment by the
Governor in Council of Schedule 2 of the MMER taken under the authority of
subsection 36(5) of the Fisheries Act to include the headwaters of Trail Creek
as a TIA (see Schedule I, Part I, items 5 and 6 and Schedule II, items 5 of the
Law List Regulations).
D. EA
PROCESS UNDER THE CEAA
[51]
In
conducting an EA under the provisions of the CEAA, the Government of Canada,
the minister of Environment, the Canadian Environmental Assessment Agency (the
Agency), and all bodies subject to the provisions of this Act, including
federal authorities and responsible authorities (RAs), shall exercise their
powers in a manner that protects the environment and human health and applies
the precautionary principle.
[52]
In
this regard, a RA shall not exercise any power or perform any duty or function
referred to in section 5 of the CEAA in relation to a project unless it takes a
“course of action” pursuant to paragraph 20(1)(a) or 37(1)(a) of the CEAA
(subsection 11(2) of the CEAA). The CEAA is binding on Her Majesty in right of Canada or a
province (section 3 of the CEAA).
[53]
Where
there are two or more RAs in relation to a project, as in the case at bar, they
must together determine the manner in which to perform their duties and
functions and follow the procedures set out in the Regulations Respecting
the Coordination by Federal Authorities of Environmental Assessment Procedures
and Requirements, SOR/97-181 (subsection 12(1) and paragraph 59(a) of the
CEAA).
[54]
A
federal environmental assessment coordinator will coordinate the participation
of federal authorities in the environmental assessment process for a project
where a screening or comprehensive study is or might be required and to
facilitate communication and cooperation among them and with provinces (section
12.1 of the CEAA). In the case at bar, the federal environmental assessment
coordinator for the Project was the Agency (sections 12.4 and 61of the CEAA).
[55]
Every
federal authority that is in possession of specialist or expert information
with respect to a project shall, on request, make available information or
knowledge to the RA (subsection 12(3) of the CEAA). In this case at bar,
Environment Canada and Health Canada, as expert federal authorities, provided
expert advice to the RAs. More particularly, advice was received from
Environment Canada on water quality, hydrology, wildlife, climate, air quality
and potential malfunctions and accidents. Expert advice was received on health
matters from Health Canada.
[56]
Some
clarification must be made with respect to the content of Schedule 2 of the
MMER and the role of the federal authorities involved in the EA of the Project.
In this case, prior to any action by the Governor in Council under the MMER,
the RAs shall consider the applicable reports and comments referred to in
sections 20 and 32 of the CEAA, and make their recommendations to the Cabinet
accordingly.
[57]
That
being said, where a screening or comprehensive study of a project is to be
conducted and a jurisdiction, such as a government of a province, has a
responsibility or an authority to conduct an assessment of the environmental
effects of the project or any part thereof, the RA may cooperate with that
jurisdiction respecting the environmental assessment of the project (subsection
12(4) of the CEAA).
[58]
In
this regard, the “Canada-British Columbia Agreement for Environmental
Assessment Cooperation (2004)” (the Agreement), provides that where Canada and
British Columbia have an environmental assessment responsibility for a proposed
project, such as the Project, a cooperative environmental assessment will be
administered under the Agreement, to generate the type, level, and quality of
information to meet the environmental assessment requirements of each
government, while maintaining the existing roles and responsibilities of
each level of government (see sections 11 and 20 of the Agreement) [emphasis
added].
[59]
Indeed,
the contacts and the authorities required to ensure that an EA of the project
is conducted in accordance with the CEAA or its regulations must develop, as
early as practicable in the cooperative environmental assessment process, a
project-specific work plan of a cooperative EA that may include the scope of
the project to be assessed and the factors and scope of the factors to be
considered (section 14 of the agreement).
IV – FACTUAL BACKGROUND
A. PROVINCIAL
ASSESSMENT
[60]
On
October 2, 1995, American Bullion Minerals, the previous owner of the Project, submitted
an application (the Original Application) to the BCEAO for a project approval certificate
for the Project under the Environmental Assessment Act, R.S.B.C. 1996,
c.119 (the Former Provincial Act).
[61]
The
final project report specifications for the Project were issued by the BCEAO on
June 18, 1996, and an assessment of the Project under the Former
Provincial Act was in progress when the Provincial Act came into effect on
December 30, 2002. A transition order issued under the Provincial Act required
the submission of the information in the project report specifications to be
submitted by June 18, 2003, or the current EA would be terminated.
[62]
On
June 17, 2003, RCDC formally withdrew from the environmental assessment process
with the intention of re-entering the process by submitting a new project description
at a future date.
[63]
On
October 27, 2003, a new project description based on a nominal mill production
rate of 25,000 tonnes per day for a period of 18 years was submitted to BCEAO
by RCDC. The new project description also described the Project and the
proposed scope of studies for the EA of the Project.
1) Preliminary
decision
[64]
On
November 19, 2003, BCEAO issued an order pursuant to paragraph 10(1)(c) of the Provincial
Act stating that the Project was reviewable and that an environmental
assessment certificate would be required prior to the Project proceeding. BCEAO
set up an interagency committee (the Working Group) to provide advice to RCDC
and to assist in the review of the terms of reference and other documentation
provided by RCDC. First Nations and provincial and federal government agencies
were represented in the Working Group.
2) Terms
of reference
[65]
The
provincial environmental process does not require public consultation on the
“terms of reference”, which set the scope of the Project. On March 25, 2004,
RCDC submitted “draft terms of reference” for the application to the BCEAO (the
Draft Terms of Reference), which were made available for comment to provincial
and federal agencies, local government and the Tahltan and Iskut First Nations,
but not the public. In its foreword, the following explanation was provided by
RCDC:
These Terms of Reference have been
developed by RCDC in accordance with the BCEAA in order to define the
information requirements necessary for inclusion in an Application for an
Environmental Assessment Certificate (“AEAC”) in order to allow for a
determination of the significance of potential environmental, heritage, social,
economic and health effects of the Project and the adequacy of measures
proposed to prevent or mitigate such effects.
In anticipation that the Project will
also be subject to review under the Canadian Environmental Assessment Act
(“CEAA”),
these Terms of Reference also include the information requirements necessary to
meet the requirements of CEAA. In such case, it is expected that the
cooperative environmental assessment process will be undertaken as provided for
in the Canada-British Columbia Agreement for Environmental Assessment
Cooperation. [emphasis added]
[66]
On
June 18, 2004, BCEAO approved final terms of reference for the Project (the ATOR).
The passage contained in the foreword of the Draft Terms of Reference remained
unchanged despite the fact that an EA under the CEAA had commenced in the
meantime, that is on May 19, 2004 (see next subsection of the present reasons
of order, Federal Assessment).
[67]
On
June 30, 2004, RCDC wrote BCEAO to advise that the Project was revised to a
production mill capacity of 27,500 tonnes per day for a period of 18 years.
3) Section
11 order
[68]
On
August 4, 2004, BCEAO issued an order under section 11 of the Provincial Act stipulating
the scope of the Project, the scope of assessment, and the procedures and
methods for the review of the application and application supplement would be
submitted by the Proponent to the Project Director within three years (the
Section 11 Order).
[69]
In
particular, the Section 11 Order scoped the Project as follows:
1.
Open
pit mine
2.
27,
500 tonne per day mill
3.
Tailings
management facility
4.
Waste
Rock Storage Facility
5.
Low
Grade
Ore Stockpile
6.
Mine
camp and associated works
7.
New
access/haul roads and related infrastructure
8.
Upgrade
of existing access roads and associated infrastructure
9.
Water
supply and associated works
10.
Use
of existing roads by concentrate trucks
11.
Power
supply and related infrastructure
12.
Maintenance
shop
13.
Explosives
storage and/or manufacturing facility
14.
Any
on or off-site compensation or mitigation works, as required
15.
Ancillary
facilities
16.
Activities
included in construction, operating, maintaining, and dismantling and
abandoning the above facilities
17.
Any
other physical works or activities which, in the view of the Project Director,
form an integral part of the project.
[70]
Moreover,
the Section 11 Order provided that the assessment of the Project would include
consideration of the potential for environmental, social, economic, health and
heritage effects, and the potential for effects on the interests of First
Nations groups and would take into account practical means to prevent or reduce
any potential adverse effects of the Project to an acceptable level.
[71]
The
Section 11 Order also established parameters and a time-frame with respect to the
environmental assessment process, including the requirement for public
consultation:
(a)
The
“pre-application stage” would focus on identifying Project-related issues to be
addressed, based on consultations conducted by RCDC and/or the BCEAO with
interested and potentially affected parties, including the public, First
Nations, federal and provincial government agencies and local governments;
(b)
The
“application review stage” would focus on review of the application itself to
determine whether or not identified concerns had been satisfactorily addressed,
and would conclude with a decision made by responsible provincial ministers on
the application, in this case the minister of Sustainable Resource Management,
the minister of Water, Land and Air Protection and/or the minister of Energy
and Mines (collectively the Provincial Ministers).
[72]
The
application review stage would be 180 days and was to commence after the
Project Director had notified RCDC that the application had been accepted for
review (section 3 of the Prescribed Time Limits Regulations, B.C. Reg. 372/2002).
Prior to a final decision being made by the Provincial Ministers, the Project
Director would hold a formal public comment period of 65 days in this case (section
7 of the Public Consultation Policy Regulation, B.C. Reg. 373/02). There
would also be a First Nations consultation program.
[73]
Following
the expiry of the consultation process, the Project Director would then prepare
an assessment report, outlining the issues raised during the review of the application,
as well as any identified practical means to avoid or reduce impacts to an
acceptable level. The Project Director would provide relevant government
agencies, local governments and First Nations with an opportunity to review and
comment on the draft assessment report.
[74]
The
assessment report would next be referred for action to the Provincial Ministers.
While it was expected that their decision would be rendered within 180 days of
the date on which the Project Director had notified RCDC that the application
had been accepted for review, prior to submitting the assessment report to the
Provincial Ministers, the Project Director could, nevertheless, suspend for any
valid reason the 180 day time limit for completing the review of the
application.
4) The
Application and the Application Supplement
[75]
On
September 24, 2004, RCDC submitted its formal “Application for an Environmental
Assessment Certificate” (the Application) for review under the Provincial Act. The
Application was screened by BCEAO, federal agencies, First Nations groups and
some provincial agencies to ensure that it met the ATOR.
[76]
On
October 20, 2004, the Project Director accepted the Application with changes
required to the Application. By letter dated October 28, 2004, RCDC submitted a
revised version of the Application, incorporating the necessary changes. The
multi-volume Application was then distributed to federal and provincial
agencies, local governments, First Nations groups and to the public.
[77]
Copies
of the revised Application were received by BCEAO on November 2, 2004 and
distributed to federal and provincial agencies, local government and the First
Nations in the Working Group. The 180 day application review period began on
November 2, 2004.
[78]
A
two-volume supplement (the Application Supplement) was submitted to BCEAO by
RCDC on November 12, 2004 and was accepted for review on November 30, 2004. The
Application Supplement was also distributed to federal and provincial agencies,
local governments, First Nations groups and to the public. The Application Supplement
contains the results of studies and field work conducted during the summer
field season of 2004.
[79]
RCDC,
in a letter dated December 21, 2004 to BCEAO, amended certain features of the
Application based on the results of a feasibility study. However, it was not
expected by RCDC that these changes would have a significant effect on the
overall scope of the Project as presented in the Application, other than
extending the planned mine life from 18 to 25 years and bringing the daily mill
throughput from 27 500 to 30 000 tonnes per day.
5) Public
consultation
[80]
Apart
from the consultations undertaken by RCDC and BCEAO prior to the submission of
the Application and Application Supplement, a formal 65 day public comment
period was advertised on the BCEAO’s website and in local papers (the
Provincial Notice).
[81]
The
Provincial Notice gave a brief description of the Project and indicated that,
for the purposes of the EA review, the Project included the on-site and
off-site physical works and activities associated with the construction,
operation, maintenance on the weeks listed in same. The works listed are the
same as the ones mentioned in the Section 11 Order. The Provincial Notice
mentioned that RCDC had submitted an application for an environmental assessment
certificate (the EA application) under the EAA as well as applications for a
permit under the MA, a special use permit under the FPC, and a licence to cut
under the FA for the development of the Project (the concurrent permit
applications). The Provincial Notice invited comments on the EA Application and
concurrent permit applications and indicated that the purpose of the public
comment period which began on November 17, 2004 and ended on January 21, 2005,
was “to document specific issues as they relate to the technical review of the
EA application.” However, there is no reference whatsoever in the Provincial
Notice to the environmental assessment process launched under the CEAA or to any
application made to the federal authorities by RCDC under subsection 35(2) of
the Fisheries Act or under paragraph 7(1)(a) of the Explosives Act, or that an
amendment by the Governor in Council of Schedule 2 of the MMER will be required
in order to include the headwaters of Trail Creek as a TIA.
[82]
A
total of ten public comments were submitted to BCEAO during this public comment
period. These public comments raised concerns on the following aspects of the
Project: environmental protection, wildlife and fisheries habitat, the local
recreational tourism industry, as well as social and community concerns. There were
no comments submitted by the Applicant.
[83]
Some
federal agencies responded as well. NRCan submitted extensive comments to BCEAO
regarding not only the explosives facility but also with respect to other major
components of the Project: mine waste management; protection surface and
groundwater quality; acid drainage, seismic hazard issues; geological
engineering, slope stability and related hazards for the open pit, waste rock
dumps and tailings storage facilities; and hydrogeology and hydrology aspects.
Comments were also submitted by Health Canada on water
quality, fish as a food source, noise and socio-economic aspects of the
Project. DFO did not make written comments to BCEAO.
[84]
Sometime
in February 2005, RCDC submitted its response to the various comments received
by BCEAO, including those made by NRCan and participants. NRCan submitted
additional comments to RCDC’s responses in March and April 2005.
6) Consultations
with First Nations
[85]
On
April 11, 2005, at the specific request of RCDC, the 180 day review period was
temporarily suspended so that RCDC could address concerns that had been raised
by the Iskut and Tahltan First Nations Group. The 180 day review period
recommenced on June 30, 2005, after further consultation efforts were
undertaken by RCDC, including meetings with First Nations groups on April 5,
April 26, May 4 and May 20, 2005, and after RCDC had provided further reports
and information to BCEAO, as requested by BCEAO.
7) Assessment
report
[86]
The
results of BCEAO’s EA are contained in its July 22, 2005 assessment report (the
BCEAO Report), in which BCEAO concluded that the Project is not likely to cause
significant adverse environmental, heritage, social, economic, or health
effects. In addition, the BCEAO Report provides further information concerning
the review process, the scope of review, the issues considered, and the means
adopted to prevent or reduce any potentially significant adverse effect of the
Project.
[87]
The
BCEAO report dealt with all provincial and federal aspects of the
Project, including: the potential effects to existing drainage patterns and the
quality of water resulting from mine site discharges to receiving waters, as
well as from TIA discharges; the potential impacts to fish and fish habitat and
the necessity of a compensation plan for the loss of fish habitat due to the
TIA; the potential impacts on wildlife including certain species at risk red or
blue-listed provincially, or of a “special concern” federally (such as the
Western Toad). The concerns identified both by the provincial or federal
authorities, as well as by the public and by the Tahltan and Iskut people are
mentioned in the BCEAO report.
[88]
The
Project was initially considered to be a comprehensive study review
under the CEAA and then changed to a CEAA screening level review, as
discussed below at paragraphs 93 to 97 and paragraphs 108 to 111. That being
said, factors related to a comprehensive study were also included in the BCEAO
report. As the case may be, they included:
·
the
effects of the environment on the Project;
·
the
environmental impacts of accidents and malfunctions;
·
alternatives;
·
cumulative
environmental effects of the Project over a regional scale; and
·
follow-up
monitoring programs.
[89]
In
particular, the BCEAO report noted that a cumulative effects assessment (CEA)
had been conducted by RCDC. The following projects were considered in the CEA:
Galore Creek project; Forrest Kerr hydroelectric project; Tom McKay Lake waste rock
and tailings project; Kemess North and South Project; Sustut Cooper project;
Strousay lead/zinc project; and mineral exploration activity in the region. The
BCEAO report stated:
Based on this information, EAO is
satisfied there are no significant cumulative environmental effects associated
with the construction, operation and decommissioning of the Project. However,
as a CEAA requirement, the federal RAs will make their own separate
determination of cumulative environmental effects associated with the
construction, operation and decommissioning of the Project in a CEAA screening
report.
[90]
In
its general review conclusions, the BCEAO report stated, in part:
Based on the information provided by the
Proponent,
the Project is not likely to cause significant adverse environmental, heritage,
social, economic, or health effects, taking into account the implementation of
mitigation measures committed to by the Proponent.
Federal Responsible Authorities are
preparing a separate CEAA Project screening report based on sections of this
report. Federal RAs have stated that they expect to conclude that the
Project is not likely to cause significant adverse environmental effects,
assuming the implementation of proposed mitigation measures and monitoring
programs. [emphasis added]
8) Environment
assessment certificate
[91]
On
July 25, 2005, BCEAO’s Executive Director recommended that an environment
assessment certificate be granted and on August 24, 2005, an assessment certificate
was issued by the Provincial Ministers.
B. FEDERAL
ASSESSMENT
[92]
The
federal environment assessment process was formally triggered when, on or about
May 3, 2004, bcMetals (on behalf of RCDC) submitted to DFO two
applications under subsection 35(2) of the Fisheries Act to cover the
contemplated construction of the starter dams for the tailings impoundment
proposed for upper Trail Creek, as well as for the stream crossing of White
Rock Canyon Creek and Coyote Creek for the proposed preferred and alternative
access road alignments. Prior to May 2004, federal departments’ actual
involvement in the EA of the Project was limited to their participation to
various meetings of the Working Group.
1) Preliminary
decision
[93]
On
or about May 19, 2004, based on the information provided by RCDC both to BCEAO
(in October 2003 and February 2004) and to DFO (May 2004), DFO concluded that an
EA of the Project was required under section 5 of the CEAA. This preliminary
decision was supported by the following findings and analysis of the scope of
the Project:
Fisheries and Oceans Canada (DFO)
received your application for Authorization under Section 35(2) of the federal Fisheries
Act dated May 3, 2004, concerning components related to the proposed Red
Chris Porphyry Copper-Gold Mine Project. To expedite future correspondence or
inquiries, please refer to your referral title and file numbers when you
contact us.
HRTS Referral File No.: 03-HPAC-PA1-000-000116
Habitat File No.: PRHQ-5300-10-083
Referral Title: Red
Chris Porphyry Cooper-Gold Mine Project
It is our understanding that the proposed
mine development consists of:
-
Open pit
mine
-
25,000
tonne per day mill
-
Tailings
Impoundment Area
-
Waste rock
storage facility(ies)
-
Mine camp
and associated works
-
Water
supply
-
Ancillary
facilities
-
Explosives
storage and/or manufacturing facility
-
Maintenance
shop
-
New
access/haul roads and related infrastructure
-
Upgrade of
existing access roads and related infrastructure
-
Use of
existing Highway 37 & 37A by concentrate haul trucks
-
Power
supply and associated works
-
Any
off-site or on-site compensation or mitigation works, as required
-
Any other
physical works or activities which form an integral part of the project.
as outlined in the following submitted
information:
-
Red Chris
Porphyry Copper-Gold Mine Project Description. Prepared by Red Chris
Development Company Ltd. October, 2003
-
Red Chris
Mine Access Review. Prepared by Allnorth Consultants Ltd. February 2004
-
Application
for Works or Undertakings Affecting Fish Habitat: Red Chris copper-gold mine
development Project dated May 3, 2004.
If the above information has changed
since the time of your submission, you should consult with us to determine if
the information in this letter still applies.
Based on the information provided, DFO
has concluded that your proposal is likely to result in the harmful alteration,
disruption or destruction of fish habitat. The harmful alteration, disruption or
destruction of fish habitat is prohibited unless authorized by DFO pursuant to
subsection 35(2) of the Fisheries Act. In reviewing your proposal, we
will consider the Department’s Policy for the Management of Fish Habitat, which
provides that no authorizations be issued unless acceptable measures for any
habitat loss are developed and implemented by the proponent.
Please be advised that subsection 35(2)
of the Fisheries Act has been included in the list of laws that trigger
the Canadian Environmental Assessment Act (CEAA). This means that
Fisheries and Oceans Canada is required to conduct an environmental assessment
of your project, as prescribed by the CEAA, before deciding to issue an
authorization. Your project information will be circulated to other federal
government departments for their review and comments. If, as a result of this
review, we are satisfied that the project, after taking into account the
implementation of any mitigation measures, is not likely to cause significant
adverse environmental effects, an authorization under the Fisheries Act
may be issued. [emphasis added]
2) Notice
of Commencement
[94]
On
or about May 21, 2004, a “Notice of Commencement of an environmental
assessment” (the Notice of Commencement) was posted on the Registry announcing
that DFO would conduct a comprehensive study commencing on May 19, 2004,
and describing the Project as an:
OPEN PIT MINE WITH ASSOCIATED
INFRASTRUCTURE INCLUDING TAILINGS IMPOUNDMENT AREA, ACCESS ROADS, WATER INTAKE,
TRANSMISSION LINES AND ACCESSORY BUILDINGS (E.G. MAINTENANCE, CAMPSITE) The
scope of the project will be added when available.
[95]
The
Notice of Commencement further made reference to the fact that an EA under
section 5 of the CEAA was required for “this project” because DFO may issue a
permit or licence under subsection 35(2) of the Fisheries Act. The Notice of
Commencement also indicated that the Project was being assessed by the
Government of British Columbia and that the Agency would act as the Federal
Environmental Assessment Coordinator for this EA.
3) Initial
tracking decision
[96]
It
may not have been entirely clear on what legal basis it was initially
determined by DFO in mid-May 2004, that the proper track to follow in the EA of
the Project was that of a comprehensive study and not a screening. However,
this issue is clarified for the benefit of other federal departments in a
letter prepared by DFO dated May 31, 2004, where it is clearly stated that “DFO
has determined that the proposed project will require a Comprehensive Study
level review based on a proposed ore production capacity of up to 50 000
tonnes/day which exceeds the threshold of 600 tonnes/day threshold under
Section 16(c) of CEAA’s Comprehensive Study List Regulations”. [emphasis added]
[97]
Moreover,
other federal departments were informed at the same time, by the letter of May 31,
2004, that the Project as scoped by DFO encompassed the proposed mine and mill as
well as certain accessory physical works:
A preliminary scope of the project under
CEAA will include:
(i)
Principal
project
Construction and operation of an open pit
gold-copper mine and mill with an ore production rate of up to 50 000 tonnes
per day.
(ii)
Accessory
physical works
Under the CEAA linkage principal:
tailings impoundment area, low grade stockpiles, waste rocks storage
facility(ies), mine camp and associated works, water supply, ancillary
facilities, explosives storage and/or manufacturing facility, maintenance shop,
new access/haul roads and related infrastructure, upgrade of existing access
roads and related infrastructure, use of Highway 37 & 37A by concentrate
haul trucks, power supply and associated works, any off-site or on-site
compensation and mitigation works as required, and any other physical works or activities
which form an integral part of the project.
Should another RA be identified or new
information relevant to the scope of project be forthcoming, the final scope of
the project may include accommodating adjustments to the above. The final scope
of document will be reflected in a separate “Scoping Document” under
development by DFO pursuant to Section 21(1) of the CEAA. DFO will be
initiating the Sec 21 public consultation exercise on scoping soon and will be consulting
other RAs on the content of the scoping document. [emphasis added]
4) Departments’ responses
[98]
Transport
Canada (TC) promptly responded in writing to DFO. Its response states that “[t]he
scoping appears to be correct based on the information received to date” but advises
that TC may have a paragraph 5(1)(d) trigger, namely section 5(1) of the Navigable
Waters Protection Act, R.S.C. 1985, c. N-22, for bridges crossing navigable
waterways. At a later date, however, upon further examination of Project
information for the access road, TC determined that it would not require an
approval under this Act and it was, thus, no longer an RA.
[99]
On
June 2, 2004, NRCan responded in writing to advise that NRCan was likely to be
an RA, as there was a paragraph 5(1)(d) trigger, namely section 7 of the Explosives
Act.
[100] On June 10,
2004, Indian and Northern Affairs Canada responded in writing to DFO in
accordance with section 12(3) of the CEAA. It advised that it had no section 5
triggers but that it would respond as required by subsection 12(3) of the CEAA.
[101] On June 18,
2004, Health Canada responded in
writing to DFO to advise that it had no section 5 triggers, but that it would
provide specialist or expert knowledge as required pursuant to subsection 12(3)
of the CEAA.
5) Minister
of Environment
[102] In July 2004,
the Agency submitted a lengthy briefing document regarding many aspects of the CEAA,
including ongoing CEAA assessments, to the incoming minister of the Environment,
the Honourable Stéphane Dion (the Briefing Book). At page 1, it was explained
that:
As a result of recent revisions to the Canadian
Environmental Assessment Act (the Act) proclaimed though Bill C-9, the
responsible authority (RA) must consult the public on its proposed approach,
report on this consultation to the Minister of Environment, and recommend to
the Minister whether the environmental assessment (EA) be continued by means of
a comprehensive study, or the project be referred to a mediator or review
panel. The Minister’s decision is known as the EA track decision.
[103] The Agency also
advised the minister of the Environment that the Project would receive
comprehensive study under the Bill C-9 revised Act:
DFO is the RA, but had not yet formally
identified the scope of the project for the purposes of the comprehensive
study. The review will be conducted in a single, cooperative review with British Columbia. The RA is expected to
initiate a 30-day public consultation period on the draft scope of the project
in August. A recommendation to the Minister of the EA track decision is
expected in September.
6) Work plan
[104] On July 28,
2004, in accordance with section 14 of the Agreement, a draft work plan was
prepared by the Agency for the cooperative EA of the Project (the Draft Work
Plan). It mentioned that the Project exceeded both the threshold of 3,000
tonnes per day of ore production and the threshold of 600 tonnes per day in ore
production capacity for gold listed respectively under paragraphs 16(a) and (c)
of the Comprehensive Study List (CSL). The plan set out a tentative Project
review schedule, including the public consultation for a CEAA comprehensive
study and the preparation of same within the provincial legislated timelines,
based on the assumption that RCDC’s application would have been accepted for
formal detailed review by September 14, 2004.
[105] On October
18, 2004, the Draft Work Plan was revised by the Agency and new dates were
inscribed, this time based on the assumption that RCDC’s application would have
been accepted for formal detailed review by October 27, 2004 (and not September
14, 2004). The Project was still to be assessed by the RAs by way of a
comprehensive study and the public was to be invited to make comments to the
RAs with respect to the proposed scope of the Project, the factors proposed to
be considered in the EA, the proposed study of the factors and the ability of
the comprehensive study to address issues relating to this project.
[106] In this regard,
it was mentioned in the Draft Work Plan:
- The Agency will set out a
public comment period for the comprehensive study report (CSR) and publish a
notice setting out the date on which the report will be available, the location
where the report is available and the deadline for filing comments on the
conclusions and recommendations of the report.
- The Agency will work with RAs
making reasonable efforts to complete the public comment period on the
comprehensive study report so as to allow the timing of the environmental
assessment decisions of both levels of government to be coordinated.
- The goal is to produce a
comprehensive study report which is, to the extent possible, based on the
assessment report that accurately reflects the assessment findings under both
CEAA and BCEAA, and which is completed within the provincial legislated
timelines.
[107] As already
mentioned in the previous subsection of these reasons for order (Provincial Assessment),
by October 18, 2004, RCDC’s application had already been submitted and by
October 20, 2004, the Project Director had accepted the Application with
changes required to the Application. However, the steps described in the Draft
Work Plan to complete, within the provincial 180 days time limit, a joint
cooperative EA, leading to the production of a comprehensive study, were not
followed or respected by the RAs.
7) Subsequent
tracking decision
[108] On or about
December 9, 2004, Mr. Richard Wex of DFO wrote a letter (the Wex letter) to
Mr. Steve Burgess of the Agency, stating the following:
In early May 2004, DFO, NRCan and
Transport Canada (TC), which at the time advised that it was a RA, jointly initiated
an EA for the Red Chris Proposal. At the onset, from the DFO perspective, there
was little fisheries data available and DFO was therefore not in a position to
clearly identify all aspects of the proposal that would require authorization.
At the proposed minesite there were a number of components of the proposed
project which had the potential to affect fish habitat. As a result and
consistent with DFO’s policy on early triggering which took effect this past
summer, DFO tentatively contemplated with NRCan and TC to include the TIA, the
mill, the mine pit, the waste rock pile, the low grade stock pile and access
roads in the scope of the project. With little detailed information on CEAA
triggers and respective regulatory responsibilities and pressure to get a
harmonized federal-provincial EA process started, the approach of all RAs
seemed to have been to take the proponent’s developmental proposal at its face
value. With the proposed capacity of the mill exceeding the threshold for a
comprehensive study pursuant to s.16(a) of the Comprehensive Study Regulations,
a comprehensive study was initiated.
Since that initial scoping exercise, which continued into the
fall under the guidance of the CEA Agency, a number of events occurred to cause
DFO to re-evaluate our proposed scope of project. DFO had asked the
proponent to overlay project components over fish habitat. The proponent
gathered additional fisheries data, and presented the overlay to DFO in early
November. DFO has recently completed its review of the new information and
determined that the mill, mine pit, waste rock pile, low grade stock pile and
access roads would in fact not likely result in impacts to fish habitat that
would require authorization under the Fisheries Act.
…
During this time, the Federal Court
handed down its decision in the True North case. This decision, consistent with
previous decisions of the court, underlines the importance of considering the
nature of CEAA triggers and the RAs regulatory responsibilities in the process
of exercising the RAs project scoping discretion.
As a result of the new fisheries
information, and consistent with the direction provided by the courts including
the most recent decision in True North, DFO has reviewed its approach to
scoping the Red Chris mine proposal by focussing, among other things, on its
CEAA triggers and regulatory responsibilities, and determined a new proposed
scope of project. As a result, there will no longer be a requirement for a
comprehensive study since the mill will not be included in our scope of
project. Accordingly, a Screening Report will be prepared.
We will now proceed to work with NRCan
with the next steps to conduct an EA under the CEAA in relation to the Red
Chris mine proposal. To this end DFO has agreed with NRCan to assume the “lead”
RA role. [emphasis added]
[109] Despite the
reference made in the Wex letter to the “overlay to DFO” in early November 2004
of “additional fisheries data”, the Court was unable to find in the record any
documentary evidence supporting the statement made “that the mill, mine pit,
waste rock pile, low grade stock pile and access roads would in fact not likely
result in impacts to fish habitat that would require authorization under the
Fisheries Act”. Quite the contrary, the documentary evidence on record shows that
the Trail Creek system provides an important spawning and rearing system for
the only inlet-spawning rainbow trout stock of Kluea Lake, and also
that rainbow trout and bull trout also spawn in reaches of Quarry Creek and
North East Arm Creek of the extent of the proposed TIA. Baseline Studies have
also showed that there are rainbow trout present within the lower reaches of
Trail Creek, up to and including the proposed location of the South Dam of the
TIA and in Kluea
Lake downstream
of Trail Creek. According to the documentary evidence, the proposed TIA will therefore
adversely affect some fish habitat, watercourses and aquatic resources by
flooding and infilling the upper reaches of Trail Creek and diverting its flows
to Quarry Creek during operations and to North East Arm Creek after mine
closure. Indeed, a fisheries compensation plan has been submitted by RCDC.
[110] The Wex letter
also refers to the decision rendered by this Court on September 16, 2004 in Prairie
Acid Rain Coalition v. Canada (Minister of Fisheries and Oceans), 2004 FC
1265 (the TrueNorth decision - first instance). The Court notes at this point
that Justice Russell’s decision in TrueNorth confirms the broad power under
section 15 of the CEAA to scope a project. The latter was subsequently upheld
by the Federal Court of Appeal on January 27, 2006, Prairie Acid Rain
Coalition v. Canada (Minister of Fisheries and Oceans), 2006 FCA 31 (the
TrueNorth decision - appeal). Leave for appeal to the Supreme Court of Canada
was dismissed without reasons on July 20, 2006. Counsel for the parties in
the present case do not agree on the scope and application of the TrueNorth
decisions. These decisions, which are based on the provisions of the CEAA as
they read before the coming into force of the Bill C-9 amendments, will be further
discussed in the subsequent section where the Court analyzes the merits of the present
application.
[111] On December
14, 2004, the online Notice of Commencement was retroactively amended to
indicate that DFO would conduct a screening commencing on May 19, 2004 (the First
Amended Notice of Commencement). There is no explicit reference to the fact
that a comprehensive study had been previously announced in May 2004. Moreover,
the First Amended Notice of Commencement continued to describe the Project as
follows:
OPEN PIT MINE WITH ASSOCIATED
INFRASTRUCTURE INCLUDING TAILINGS IMPOUNDMENT AREA, ACCESS ROADS, WATER INTAKE,
TRANSMISSION LINES AND ACCESSORY BUILDINGS (E.G. MAINTENANCE, CAMPSITE) The
scope of the project will be added when available.
The references to the fact that the Project
was being also being assessed by the government of British Columbia and that the
Agency would act as the Federal Environmental Assessment Coordinator are still
mentioned. While the 65 day public consultation process in British
Columbia
had already started in November 2004 and was due to expire on January 21, 2005,
there is no formal invitation made to the public in the Notice of Commencement to
submit their comments with respect to the Project through the former environmental
assessment process.
8) Unresolved
issue respecting the amount of water
[112] The last
meeting of the Working Group, established by BCEAO in November 2003 to provide
advice and support on the Project, was held on January 11, 2005. The potential effects
of the Project on fisheries habitat, as well as various mitigation and
compensation options were specifically discussed on that occasion. It appears
that there were still a number of important issues left unanswered, one being
the amount of water that would be transferred between watersheds as a result of
the operation of the TIA:
Federal agencies need to know the amount
of the operation of the TIA. The comprehensive study threshold which
determines the EA track is 10 million m3 per year or greater.
The precise amount can be determined by calculations. The proponent responded
that it is anticipated that a total of 6 to 7 million m3 of water
per year would be discharged to quarry creek, beginning in approximately 2 or 3
mine operation. The proponent will provide a letter stating the amount of water
to be diverted. [emphasis added]
[113] On February
25, 2005, in a letter addressed by DFO to the Agency, DFO confirmed that they intended
to await resolution or clarification of the outstanding issues prior to
completing their review of the Project. The precise amount of water to be
diverted continued to remain a concern: “At the January 11, 2005 meeting in
Smithers, RCDC was informed by the CEA Agency of the CEAA Comprehensive Study
Regulation (sic) threshold for the “…diversion of 10M m3/a or more of water
from a natural water body into another material water body …” (Part III, Item
9). RCDC committed to calculating the amount of water proposed to be diverted
from the Trail Creek to the Quarry Creek watershed. To date, this information
has still not been provided.”
9) The
Scoping Decision of March 2005
[114] In a letter
dated March 11, 2005, DFO informed BCEAO that the RAs had “determined the scope
of project for the purposes of an environmental assessment under the CEAA in
relation to the Red Chris Project” (the Scoping Decision of March 2005).
Specifically, the letter stated:
In accordance with subsection 15(1) of
the CEAA, the responsible authorities have determined that the scope of the
project for the purposes of the environmental assessment under the CEAA will
be the construction, operation, modification and decommissioning of the
following physical works:
·
Tailings
Impoundment Area including barriers and seepage dams in the headwaters of
Trail, Quarry and NE Arm creeks.
·
Water
diversion system in the headwaters of Trail, Quarry, and NE Arm creeks.
·
Ancillary
Facilities supporting the above mentioned (i.e. process water supply pipeline
intake) on the Klappan River.
·
Explosives
storage and/or manufacturing facility on the mine property.
The environmental assessment under the
CEAA of the project as scoped above will be conducted in accordance with the
requirements of s. 18(1) of the CEAA at the level of screening. [emphasis
added]
[115] On March 15,
2005, the online Notice of Commencement was amended retroactively for a second
time, stating that both DFO and NRCan would conduct a screening of the Project commencing
May 19, 2004 (the Second Amended Notice of Commencement). This was the first
time that NRCan’s involvement as a RA was mentioned. Accordingly, the Notice of
Commencement was amended to also state that an environmental assessment was required
under section 5 of the CEAA pursuant to paragraph 7(1)(a) of the
Explosives Act. Furthermore, the Notice of Commencement continued to state that
the scope of the project would be added when available.
[116] On March 24,
2005, the online Notice of Commencement was amended a third and final time (the
Third Amended Notice of Commencement) in order to specify that an EA was
required because: 1) NRCan was contemplating the issuance of a license pursuant
to paragraph 7(1)(a) of the Explosives Act for construction of the explosives
storage and/or manufacturing facility on the mine property; 2) DFO was
contemplating the issuance of authorisations under section 25 of the Fisheries
Act for the harmful alteration, disruption of fish habitat; and 3) Regulations
to be made by the Governor in Council were being contemplated to list the
headwaters of Trail Creek as a TIA on Schedule 2 of the MMER pursuant to
paragraphs 36(5)(a) to (e) of the Fisheries Act.
[117] Furthermore, the
Third Amended Notice of Commencement stated that, in accordance with subsection
15(1) of the CEAA, the RAs had determined that the scope of the Project for the
purposes of environmental assessment under the CEAA would be:
[…] the construction, operation,
modification and decommissioning of the following physical works: Tailings
Impoundment Area including barriers and seepage dams in the headwaters of Trial,
Quarry and NE Arm creeks. Water diversion system in the headwaters of Trail,
Quarry, and NE Arm creeks. Ancillary Facilities supporting the above mentioned
(i.e. process water supply pipeline intake) on the Klappan River. Explosives storage and/or manufacturing
facility on the mine property. [emphasis added]
[118] It appears
from the documentary evidence on record that as of March 2005, when the
“scoping decision” which appears on the Third Amended Notice of Commencement was
made, the RAs were still struggling to obtain key information from RCDC. The
exact scope of the Project remained a matter of concern. In a letter dated
March 30, 2005, addressed by NRCan to BCEAO in the context of its first draft
report , NRCan stressed that “[i]t would be difficult for us to complete the
EA before understanding potential impacts and whether or not they can be
mitigated” [emphasis added]. Key outstanding issues needed to be clarified or
resolved by RCDC including “[s]pecification of planned discharged locations
from and the TMF, post closure”; “[d]ilution in the TMF to manage water quality
for various metals”; “the management of low-grade material if it cannot be
processed”; “[t]iming of discharges”; “the volume of till available in the
immediate vicinity of the project”; “geological and geotechnical complexity of
the open pit site and the potential for slope instabilities on the south walls
of the open pit”; “[t]errain Hazards Along Access Roads”; “the availability of
larger borrow pits for material to be used as cover material fro the waste rock
dump”; “bedrock contact depth” (with respect to the tailing storage
facilities); the nature of certain “modification to the mine plan and how this
is going to affect the mine facilities”; and finally: “we need the total
volume of water that will be diverted from one water body to another and we
need to resolve the issue regarding the SARA species of the Western Toad” [emphasis
added].
[119] It must be
remembered that the Project “as scoped” by the RAs in March 2005 included the
water diversion system and that item 9 of the CSL had been identified by the
Agency at the January 11, 2005 meeting as a threshold that could be
potentially exceeded. If this was the case, even “as scoped” by the RAs, the EA
of the Project would have needed to be conducted by way of a comprehensive
study and not a screening.
[120] On April 1,
2005, DFO advised the Agency that it was unable to provide significant comments
with respect to the draft assessment report prepared by BCEAO. Moreover,
further clarification was needed from RCDC with respect to the habitat
compensation plan: “To date, no further information has been received from RCDC
to allow DFO to initiate the MMER process with Environment Canada”. In
addition, DFO advised the Agency that it had received no response from RCDC
about water diversion while “[i]tem 9 of the CEAA Comprehensive Study
Regulations … was identified by the Agency at the January 11, 2005 meeting in
Smithers as a threshold that may be potentially exceeded.”
10) Provincial
assessment
[121] As aforementioned
in the previous subsection (Provincial Assessment), the BCEAO report was
released on or around July 22, 2005. It concluded that based on the
information provided by RCDC, the Project was not likely to cause significant
adverse environmental effects taking account the implementation of mitigation
measures committed to by RCDC.
[122] Again, it is
useful to be reminded here that the BCEAO report further stated in its review
conclusions:
Federal RAs are preparing a separate CEAA
Project screening report based on sections of this report. Federal RAs have
stated that they expect to conclude that the Project is not likely to cause
significant adverse environmental effects, assuming the implementation of
proposed mitigation measures and monitoring programs. [emphasis added]
[123] That being
said, it took several months for the RAs to complete the EA of the Project.
11) Consultations
with the First Nations
[124] In keeping
with the intent of the RAs to consult First Nations in the review of the
Project, on January 10, 2006, the Tahltan band council and the Iskut First
Nation were specifically invited to make comments by February 10, 2006
respecting a draft of a screening report the RAs had agreed to disclose prior
to finalizing the screening report. No prior disclosure of such draft report
was made on the Internet site and no such solicitation to receive comments from
the general public was made by the RAs in the case at bar.
12) Screening
Report
[125] The RAs completed
their EA and produced a screening report on or about April 16, 2006, under the
purported authority of section 18 of the CEAA (the Screening Report).
[126] The Screening
Report stated that it was “based on information collected through the
cooperative federal/provincial EA process …” (section 7 of the Screening Report).
The RAs concluded that “taking into account the implementation of the
mitigation measures, the Project is not likely to cause significant adverse
environmental effects”. The scope of the Project, as described at page 10 of
the Screening Report, was larger than that described in the Third Amended
Notice of Commencement and contained the following three additions:
- The deposit of a deleterious
substance (tailings) into a Tailing Impoundment Area (TIA);
- Any works or undertakings
required as mitigation and compensation for the harmful alteration, disruption
or destruction (HADD) of fish habitat associated with construction of the TIA
that may require an authorization under the Fisheries Act; and
- Any works or undertakings
required as compensation fro the deposit of tailings into the TIA that may
require an authorization under the Fisheries Act.
[127] With regards
to the subject of consultation, the Screening Report read as follows:
The BCEAO led consultations with the
Proponent, local governments, First Nations, federal and provincial agencies,
and other communities of interest (with emphasis in Stewart, Iskut, Dease Lake,
and Telegraph Creek) to provide opportunities to review the proposed
development and to ensure their input into the EA process. The RAs have used
the information collected from these consultations to inform their screening
decision. A summary of consultation efforts with First Nations can be found in
Sections 3 and 5.4, and Appendices E and F of the BCEAO report. A summary of
community consultation efforts undertaken by the Proponent and BCEAO are
presented in Section 3.2 of the BCEAO report.
The RAs are satisfied that this effort
towards public consultation provided sufficient and satisfactory opportunities
for public input into the Red Chris EA process. Based on the extent of
consultation that has been conducted by the Government of BC and the Proponent,
and the information that the RAs received from this consultation, the RAs are
of the opinion that public participation in the screening of the Project under
CEAA 18(3) is not appropriate under these circumstances. [emphasis added]
13) The
Course of Action Decision
[128] On May 2,
2006, the RAs took a course of action under the purported authority of
paragraph 20(1)(a) of the CEAA (the Course of Action Decision). More
particularly, the RAs determined that the Project “as scoped” by them was not
likely to cause “significant adverse environmental effects”.
[129] The Course of
Action Decision was posted on the Registry on May 10, 2006. At this time, the general
public was able to consult the Screening Report.
[130] Under the
Course of Action Decision, RCDC and related contractors could proceed with the
process of applying for a license as issued by NRCan pursuant to paragraph
7(1)(a) of the Explosives Act. DFO could also proceed as appropriate
with a subsection 35(2) Fisheries Act authorization for the HADD of fish
habitat. Furthermore, DFO was required to consider the Screening Report in
relation to determining whether to recommend to the Governor in Council the
designation of the headwaters of Trail Creek as a TIA on Schedule 2 of the MMER
pursuant to paragraphs 36(5) (a) to (e) of the Fisheries Act. As of the date this
application for judicial review was heard, specifically in June 2007, no
authorization or license had yet been delivered or issued and no action had yet
been taken by the Cabinet.
V – THE PRESENT
APPLICATION
[131] A notice of
application for the present judicial review was filed by the Applicant on June
9, 2006. Essentially, the Court is asked to determine whether the RAs have been
under the legal duty, since the EA was announced on the Registry in May 2004,
to conduct a comprehensive study and to consult the public prior to taking a
course of action decision in respect of the Project.
[132] At issue in this
case, is the right of the RAs to make the Course of Action Decision under the
purported authority of paragraph 20(1)(a) of the CEAA. The Applicant claims
that section 20 of the CEAA does not apply to the EA of the Project. The
Applicant states that pursuant to section 13 of the CEAA, any course of action
decision taken in this case must be made under section 37 of the CEAA before
the Project is allowed to proceed and before authorizations or licences are given
or issued by the RAs in accordance with the Fisheries Act and the Explosives
Act respectively. Finally, the applicant contends that the Governor in Council
ought to amend Schedule 2 of the MMER.
[133] The Applicant
has abandoned its earlier request for a declaration that the Project falls
under item 9 of the CSL, as it exceeds the water diversion volume threshold of
10 million m3 per year. However, the Applicant maintains its request
that the Project be declared a “project” for which a comprehensive study is
required as it exceeds the ore production capacities provided in items 16(a)
and/or 16(c) of the CSL. It also seeks an order in the form of a declaration
declaring, inter alia, that the RAs were under a legal duty pursuant to
subsection 21(1) of the CEAA to ensure public consultation with respect to the
proposed scope of the Project, the proposed factors to be considered in its
assessment, the proposed scope of those factors and the ability of the
comprehensive study to address issues relating to the Project. The Applicant
further seek an order declaring that the RAs erred in law or acted without
jurisdiction in failing to perform their legal duty pursuant to subsection
21(1) of the CEAA.
[134] Furthermore,
the Applicant requests an order in the nature of certiorari quashing and
setting aside the Course of Action Decision. It also seeks an order
prohibiting the exercise of any powers under paragraph 5(1)(d) or subsection
5(2) of the CEAA that would permit the Project to be carried out in whole or in
part. Alternatively, it seeks an order in the nature of a mandamus
compelling the RAs, the Minister of Fisheries and Oceans, the Minister of
Natural Resources and the Governor in Council, as represented by the Attorney
General, to refrain from exercising any power, duty or function that would
permit the Project to be carried out in whole or in part until a course of
action has been taken in relation to the Project in accordance with paragraph
37(1)(a) of the CEAA, in performance of their duty to conduct an EA under
section 13 of the CEAA.
VI – STANDARD OF REVIEW
[135] The Federal
Court of Appeal has already addressed the issue of the standard of review in Bow
Valley Naturalists
Society v. Canada (Minister of Canadian Heritage), [2001] F.C.J. No. 18
(Bow
Valley). At para.
55, Justice Linden noted in this regard:
The leading case dealing with sections 15
and 16 of the Act is a decision of this Court in Friends of the West Country
Assn. v. Canada (Minister of Fisheries and Oceans) [citation omitted].
Writing for the unanimous Court, Rothstein J.A. concluded that the interpretation
of the Act, a statute of general application, is a question of law reviewable
on a correctness standard [citation omitted]. Consequently, this
standard of review of statutory interpretation issues will be employed in this
case. However, in that case, this Court did not rule on the appropriate
standard of review for discretionary decisions of substance pursuant to the
authority granted in the Act. The Trial Judge in that case has held that the
standard of review for such cases should be reasonableness. Applying the Pushpanathan
factors, this would be appropriate in this case particularly because there is
no privative clause, and because the level of expertise in administering the
Act is minimal in this and most, if not all, other responsible authorities. The
Court determines that the standard of review applicable to the issues of jurisdiction
and applicability of the impugned legislative and regulatory provisions to the
Project raised by the Applicant is that of correctness. In coming to this conclusion,
all four contextual factors mentioned in Dr. Q v. College of Physicians and
Surgeons of British Columbia, 2003 S.C.C. 19 (presence or absence of a
privative clause or statutory right of appeal; expertise of the tribunal
relative to that of the reviewing court on the issue in question; purposes of
the legislation and of the provision in particular; and, nature of the
question) have been considered by the Court.
[136] The Court
must determine whether, as alleged by the Applicant, the Project falls under items
16(a) and/or 16(c) of the CSL and whether the RAs are required by section 21 of
the CEAA to consult the public on the scope of the Project and the scope of the
assessment prior to making any scoping or course of action decisions with
respect to the Project. The Respondents submit on the contrary that section 21
does not apply since the Project “as scoped” under section 15 by the RAs is not
mentioned on the CSL; therefore, the impugned decisions or actions made by the
RAs were authorized by section 18 of the CEAA.
[137] As can be
seen, the Court must interpret and determine the scope of sections 15 and 21 of
the CEAA. The nature of the questions of law and of law and fact involved in
this case is determinative. Accordingly, the statutory interpretation issues
raised in this case will be decided on a correctness standard.
VII – PRELIMINARY
ISSUES RAISED BY THE RESPONDENTS
[138]
For the reasons indicated below (section VIII –
Merits of the case), I find that DFO correctly determined in May of 2004
that the Project is included in the CSL. The wording of section 21 of the CEAA,
as amended in 2003, made public consultation mandatory. This is a clear and
straightforward requirement, the significance of which appears not to have been
lost on the RAs who subsequently re-tracked the Project under the aegis
of a scoping decision thereby avoiding the rigors of the requisite public
consultation process. I have accordingly decided to grant the present judicial
review application. However, the Court must deal with two preliminary
issues raised by the Respondents. First, the Proponent and the Attorney General
contend that the Applicant did not file its application in a timely manner.
Second, the Proponent challenges the Applicant’s standing in the matter.
[146] The affiant who
submitted an affidavit on behalf of the Crown was directly involved in the
Project when the Scoping Decision of March 2005 was made. This affiant
acknowledges that the Project as scoped only included the construction,
operation, modification and decommissioning of four physical works,
specifically the TIA; the water diversion system in the headwaters of Trail
Creek and Northeast Arm Creeks; ancillary facilities supporting the
aforementioned; and the explosive storage and manufacturing facility. To this
extent, until February 8, 2007, the time of the cross-examination on his
affidavit, the affiant was apparently unaware that three additional components
had been added to the Project following the Scoping Decision of March 2005.
Upon questioning by counsel for the Applicant, the affiant stated that he was
unable to explain how the changes had happened. He further acknowledged that
he was unaware of any notice ever being given to the public regarding this
addition to the scope of the Project.
[…] unless there are special
circumstances there should not be any appeal or immediate judicial review of an
interlocutory judgement. Similarly, there will not be any basis for judicial
review, especially immediate review, when at the end of the proceedings some
other appropriate remedy exists. These rules have been applied in several Court
decisions specifically in order to avoid breaking up cases and the resulting
delays and expenses, which interfere with the sound administration of justice
and ultimately bring it into disrepute.
[…] I would associate myself
with the view that appeals from rulings on preliminary enquiries ought to be
discouraged. While the law must afford a remedy where one is needed, the remedy
should, in general, be accorded within the normal procedural context in which
an issue arises, namely the trial. Such restraint will prevent a plethora of
interlocutory appeals and the delays which inevitably flow from them. It will
also permit a fuller view of the issue by the reviewing courts, which will have
the benefit of a more complete picture of the evidence and the case.
With respect, I am not persuaded that judicial review
is premature in regard to a decision, by the responsible authority, determining
the scope of the project which will be assessed, and which assessment that
authority will later approve or disapprove. That decision is not merely a
recommendation; rather it meets a statutory requirement and provides the basis
for the process of the assessment from that point on and, as a consequence, in
my opinion it is a decision subject to judicial review.
[156] In Alberta
Wilderness Assn. v. Canada (Minister of Fisheries and Oceans), [1998]
F.C.J. No. 1746 (C.A.), the Alberta Wilderness Association, the Canadian Nature
Federation, the Canadian Parks and Wilderness Society, the Jasper Environmental
Association, and the Pembina Institute for Appropriate Development
(collectively the appellants), were seeking an order of prohibition against the
minister of Fisheries and Oceans from issuing authorizations under the
Fisheries Act on the basis that the EA conducted by the Joint Review Panel, did
not comply with the statutory requirements stipulated in the CEAA. In this
case, the report prepared by the panel consisted of an EA of a proposal of the
Cardinal River Coals Ltd. to build and operate a 20 km open pit coal mine three
kilometres east of Jasper National Park in Alberta.
[157] The
Application Judge had dismissed the application on the preliminary basis that
the federal response issued by the minister of Fisheries and Oceans had not
been challenged previously by the appellants and therefore served as a barrier
to the appellants’ claim. Consequently, the merits of the appellants’ arguments
were not addressed. The decision of the Application Judge was set aside by the
Federal Court of Appeal and the matter referred back to the Court for
determination on the merits.
[158] In Alberta
Wilderness Assn., Justice Sexton noted at paras. 15-18:
In
a preliminary motion prior to this appeal, the respondents sought to strike out
the appellants' original application on the basis that it was time-barred.
Hugessen J., starting at paragraph 3, made the following comments:
Rather I think the Report should be seen
as an essential statutory preliminary step required by the Canadian
Environmental Assessment Act prior to a decision by the Minister to issue an
authorization under section 35 of the Fisheries Act.
That decision has not been made and I
think it is a fair reading of the Applicants' Originating Notice of Motion that
it seeks primarily to prohibit the Minister from making it on the grounds that
the Panel Report is fatally defective.
Prohibition (like mandamus and quo
warranto) is a remedy specifically envisaged in section 18 of the Federal Court
Act and like them it does not require that there be a decision or order
actually in existence as a prerequisite to its exercise.
I
agree with the view presented in this passage, which was adopted by Gibson J.
in Friends of the West Country Association v. Canada (Ministry of Fisheries
and Oceans), [1998] F.C.J. No. 976 (T.D.) [Q.L.] at page 7.
I agree with the decisions of Bowen v.
Canada, [1997] F.C.J. No. 1526 (T.D.) [Q.L.], Friends of West Country,
supra, and Union of Nova Scotia Indians v. Canada (Attorney General) (1996),
22 C.E.L.R. (N.S.) 293 (F.C.T.D.) which hold that an environmental
assessment carried out in accordance with the Act is required before a decision
such as the Minister's authorization in the present case can be issued.
This view is reinforced by the decision in Friends of the Oldman River
Society v. Canada (Minister of Transport) (1992), 88 D.L.R. (4th) 1
(S.C.C.) which confirmed that the guidelines that were a pre-cursor to CEAA
(the Environmental Assessment and Review Process Guidelines Order SOR/84-467)
were mandatory rather than directory in nature and, thus, failure to comply
with them would deny the responsible authority the jurisdiction to proceed.
[160] With respect
to standing, the Proponent contends that the Applicant has not raised a serious
issue, that it does not have a genuine interest in the subject matter and that
there are other directly affected parties who chose not to come forth with an
application for judicial review.
[161] The Proponent
submits in this regard that the Applicant has not challenged the substantive
outcome of the Course of Action Decision and that the issues raised by the Applicant
have already been decided by this Court and the Federal Court of Appeal in the
TrueNorth case, above. The Proponent notes that the Applicant is an advocacy
group headquartered in Ottawa who does not represent any group of local
citizens or interest groups directly affected by the Project. First Nations
groups who are directly affected by the Project have not made an application
for judicial review. Moreover, the Proponent stresses that the Applicant has
chosen not to participate in the cooperative environment assessment process. Indeed,
the Applicant has not made any submissions on the merits of the Project to BCEAO,
the RAs or RCDC.
[162] The
jurisprudence of the Supreme Court of Canada establishes that standing will be
granted to a public interest group who wishes to challenge the exercise of
administrative authority, as well as legislation, where the following tri-part
test is met: a serious issue is raised; the Applicant shows a genuine interest;
and there is no other reasonable and effective manner in which the issue may be
brought to the Court (Thorson v. Attorney General of Canada et al, [1975]
15 S.C.R. 138; Minister of Justice of Canada v. Borowski, [1986] 2
S.C.R. 607 at pages 339-340; Canadian Council of Churches v. Canada,
[1992] 1 S.C.R. 236, at para. 33 and following).
[163] In applying this
tri-part test, this Court has consistently rejected the proposition that the
words “directly affected” used in subsection 18.1(1) of the FCA should be given
a restricted meaning. Indeed, it has been decided in the past that an applicant
who satisfies the requirements of discretionary public interest standing may
seek relief under subsection 18.1(1) of the FCA even though not “directly
affected”, when the Court is otherwise convinced that the particular
circumstances of the case and the type of interest which the applicant hold
justify status being granted (see Friends of the Island v. Canada (Minister
of Public Works), [1993] 2 F.C. 229 (T.D.) at paras. 75 to 80; Sunshine
Village Corp. v. Canada (Minister of Canadian Heritage), [1996] F.C.J. No.
1118, at paras. 65 to 72; Citizens’ Mining, above, at paras. 30
to 33; Sierra Club of Canada v. Canada (Minister of Finance), [1999] 2
F.C. 211, at paras. 27 to 34).
[164] I accept the
arguments submitted in writing and orally at the hearing on behalf of the
Applicant. In the exercise of my discretion, I have considered all three
factors of the tri-part test, as well as the purpose of the CEAA and the
particular circumstances of this case.
[165] The
fundamental purpose of the CEAA is to ensure that projects requiring an EA are
considered in a careful and precautionary manner before federal authorities
take action in connection with them, in order to ensure that such projects do
not cause “significant adverse environmental effects” (paragraph 4(a) of the
CEAA). Another underlying purpose is to ensure that there are opportunities for
timely and meaningful public participation throughout the
environmental assessment process (paragraph 4(d) of the CEAA) [emphasis added].
Therefore, operational provisions found in the CEAA and its regulations must be
interpreted and applied in a manner consistent with these purposes.
[166] For the
purpose of facilitating public access to records related to environmental
assessments and providing notice in a timely manner of the assessments, there
is a registry called the Canadian Environmental Assessment Registry (the
Registry), consisting of an Internet Site and projects files (subsection 55(1)
of the CEAA). Within fourteen days after the commencement of an EA under the
CEAA, notice of its commencement must be posted on the Agency’s Internet site
(paragraph 55.1(2)(a) of the CEAA). The notice shall include a description of
the scope of the project in relation to which an EA is to be conducted, as
determined under section 15 of the CEAA (see paragraph 55.1(2)(c) of the CEAA).
In the preceding section (see IV – Factual Background, particularly subsection
B. Federal Assessment), I have examined the measures taken by the RAs and/or
the Agency to inform the general public.
[167] In addition
to any requirement to notify the public or opportunities for public
participation flowing from the provisions of the CEAA, an obligation on the
Crown (though not on private companies or individuals) to consult First Nations
exists where aboriginal rights may be affected by a project (see Taku River
Tlingit First Nation v. British Columbia (Project Assessment Director),
[2004] S.C.J. No. 69; Haida Nation v. British Columbia (Minister of Forests),
[2004] S.C.J. No. 70). Indeed in Taku River Tlingit First Nation, above,
the Supreme Court of Canada held that the process engaged in by the Province of British
Columbia
in respect of the EA of a mining project contemplated in the traditional
territory of the Taku River Tlingit First Nation fulfilled the requirements of
its duty to consult and accommodate. However, it is not necessary in this case
to determine whether or not the particular requirement to consult and
accommodate the members of the Tahltan and Iskut nations has been satisfied by
the provincial and federal authorities involved in the EA of the Project.
[168] A serious
issue is raised by the Applicant with respect to the legality of the Course of
Action Decision which is a final decision for the purpose of the present
judicial review. In this instance, the Applicant is contesting that the
impugned decision represents a departure from a positive duty to consult the
public. To this effect, the issue of public participation is of import, not
just in this case, but for future projects across Canada.
Comprehensive studies as stated, mandate public consultation.
[169] Section 21 of
the CEAA which the Applicant alleges to be applicable in the case at bar, has
been amended substantially in 2003. The current and enhanced version of this
provision was introduced by section 12 of the Act to amend the Canadian
Environmental Assessment Act, S.C. 2003, c.9 (the Bill C-9 amendments). The
former text of section 21 of the CEAA is also reproduced at the end of the
present reasons for order (see Appendix “A”). The Bill C-9 amendments came into
effect on October 30, 2003 and apply to the Project.
[170] The TrueNorth
decisions invoked by the Respondents to sustain the legality of the impugned
actions or decisions are based on the law as it read prior to the Bill C-9
amendments.
[171] Section 21 of
the CEAA now makes public consultation mandatory when conducting an EA
by means of a comprehensive study. Specifically, the new provision provides
that “[w]here a project is described in the comprehensive study list,
the RA shall ensure public consultation with respect to the proposed scope
of the project for the purposes of the environmental assessment, the
factors proposed to be considered in its assessment, the proposed scope of
those factors and the ability of the comprehensive study to address issues
relating to the project” [emphasis added].
[172] Moreover, the
new section 21 of the CEAA provides that when making an EA by means of a
comprehensive study, the RA must also report to the minister of the
Environment after the public consultation regarding: the scope of the
project, the factors to be considered in its assessment and the scope of
those factors; the public concerns in relation to the project; the
potential of the project to cause adverse environmental effects; and the
ability of the comprehensive study to address issues relating to the project.
The RA must also recommend to the minister of the Environment to continue with
the EA by means of a comprehensive study or to refer the project to a
mediator or review panel (subsection 21(2) of the CEAA). Again, such
requirements do not exist where a screening is conducted by the RA. [emphasis
added]
[173] A duty to
consult the public at an early stage on key aspects of the environment
assessment process is, therefore, one fundamental aspect introduced by the Bill
C-9 amendments. Another one is participant funding. Previous subsection 58(1.1)
required the Minister to establish a participant funding program to facilitate
the public’s participation in mediations and assessment by a review panel. The
Bill C-9 amendments expand this program by extending participant funding to
comprehensive studies and also clarifies that the participant funding program
applies to joint assessment by a review panel as well. The program is
administered by the Agency.
[174] The Notice of
Commencement which was posted on the Registry on May 23, 2004, announced that
DFO would conduct a comprehensive study commencing on May 19, 2004. It
can seriously be argued by the Applicant that this created a legitimate
expectation that the general public would be consulted in accordance with
section 21 of the CEAA. Moreover, at the time that the RAs changed “track” and
chose to proceed by way of a screening, the documentation on file shows that
the public consultation process under the provincial EA was well underway.
Indeed, it was completed prior to the announcement made on the Registry of the
Scoping Decision of March 2005.
[175] In the end
result, there was no public consultation with respect to the screening report
prepared in 2006 under the purported authority of section 18 of the CEAA. This
contrasts sharply with the evidence on file that the public has been consulted by
the RAs with respect to the comprehensive study prepared in the case of the
Galore Creek Gold – Silver – Copper mine, which is also located in the area
where the Red Chris property is situated.
[176] Relevant
documentary evidence produced by the Applicant (the affidavit of Ms. Kuyek),
which I find admissible and accept to consider in this proceeding, shows that
on January 25, 2005, the DFO, NRCan and TC decided to conduct a comprehensive
study commencing on January 11, 2005 of the Galore Creek Gold – Silver –
Copper mine in British Columbia and that the general public, including the
Applicant, had the opportunity to be consulted by the RAs on the scope of the
project and factors to be considered despite the fact that a joint cooperative
EA was also in progress.
[177] Therefore, other
mines are currently being scoped by RAs with differing results. This brings a
state of uncertainty with respect to the correct interpretation and application
of section 21 of the CEAA which is mandatory.
[178] I defer to
the reasoning of Justice Cory in Canadian Council of Churches v. Canada,
[1992] 1 S.C.R. 236, at para. 38 wherein it was elucidated that the
issues of standing and of whether there is a reasonable cause of action are
closely related and indeed tend to merge. In the case
at bar, compliance with the CEAA raises a serious and justiciable question of
law.
[179] The Applicant
also shows a genuine interest in the issues raised in this application for
judicial review. More than a mere bona fide interest and concern about
social and environmental issues is necessary to obtain public interest
standing. In Citizens’ Mining, above, at para. 30, this Court
determined that an applicant seeking public interest standing must demonstrate:
“… a longstanding reputation and it must do significant work on the
subject-matter of the challenge, and its interest must be greater than that
possessed by a member of the general public.”
[180] Based on the
evidence before me, MiningWatch clearly satisfies this requirement. It is a
federally-registered non-profit society that functions as a coalition of
environmental, social justice, aboriginal and labour organizations from across Canada. By
focusing on federal aspects of mining development, the Applicant enjoys the
highest possible reputation and has demonstrated a real and continuing interest
in the problems associated mine development. Indeed, MiningWatch has made
submissions before the House Committee on Bill C-19, the predecessor of the
2003 amendments to the CEAA, and has published studies critical of failed
mitigation plans in relation to mine development.
VIII – MERITS OF THE
CASE
2) The
Respondents
[194] For their
part, the Respondents contend that “scoping” determines the “tracking” of a
project.
[195] The Proponent
submits the Applicant’s arguments were already dealt with in the TrueNorth
decisions. Even where the entire proposal contains some components that are
included on the CSL, a RA may scope the project down to focus on those
components that require a federal permit, licence or approval. Furthermore, in
TrueNorth, the Federal Court of Appeal confirmed that the scoping decision
under section 15 of the CEAA is made prior to the decisions to proceed by means
of either screening or comprehensive study. The Proponent submits that Bill C-9
amendments did not change that order and points out that no amendments were
made to section 15.
[196] The Crown
submits that section 21 of the CEAA is only triggered if a component of the
proposed scope of the project, as determined by the RA under section 15,
appears on the CSL. The Crown further argues that a RA may amend the scope of
the project at any time after section 21 is engaged. If the scope is amended so
that none of the components of the project appear on the CSL, section 21 ceases
to apply. It submits that in the TrueNorth decision, the Federal Court of
Appeal confirmed that “project” for purposes of assessment is not the proposal,
but is determined by the RA pursuant to the exercise of its discretion under
section 15 of the CEAA. The Crown submits that the Federal Court of Appeal in
TrueNorth has decided that “project” for the purposes of the CEAA must be read
as “project as scoped” under section 15 of the CEAA. According to the Crown,
the term “project” must therefore be read throughout the CEAA as “project as
scoped”, including at section 21.
[197] While the
Crown’s written submissions also focused on the constitutional aspect of
TrueNorth, at the hearing, counsel for the Crown clarified that he did not
believe that their position differed from that of the Proponent. In any event,
counsel for the Crown submits that this issue does not have to be determined in
the case at bar.
[198] In Bow Valley,
above, the Federal Court of Appeal, at para. 19, affirmed that the basic
framework for an environmental assessment was as follows:
The basic framework for an environmental
assessment is as follows. First, the responsible authority must decide
whether the Act applies to the project and if it does, which type of
environmental assessment applies. The next step is the conduct of the
assessment itself. Following the assessment, the responsible authority
makes a decision as to whether or not to allow the project to proceed. The
final step is the post-decision activity which includes ensuring that
mitigation measures are being implemented and giving public notice concerning
the responsible authority's course of action. [emphasis added]
[199]
It is not necessary to come back to the particular
elements which have triggered the need to conduct an EA under section 5 of the
CEAA in the case of the Project. In this regard, I will refer only to what has
already been mentioned in section III – Requirement of an Environmental
Assessment (EA), above. That being said, I will now examine two particular legal
aspects that need clarification: 1) the types of environmental assessment
(tracks) and 2) the nature of scoping.
[200] Section 14 of
the CEAA provides that there are four types of environmental assessments:
screening, comprehensive study, mediation and assessment by a review panel.
These types of assessments are also commonly referred to as “tracks”. Where
applicable, the EA also includes the design and implementation of a follow-up
program.
[201] The majority
of projects requiring an EA under section 5 of the CEAA will undergo a
self-directed EA, which can involve either a screening or a comprehensive study.
[202] Pursuant to
section 13 of the CEAA, where a project is described in the CSL or is referred
to a mediator or a review panel, notwithstanding any other Act of Parliament,
no power, duty or function confirmed by or under the Act and any regulation made
thereunder shall be exercised or performed that would permit the project to be
carried out in whole or in part unless an EA of the project has been completed
and a course of action has been taken in relation to the project in accordance
with paragraph 37(1)(a) of the CEAA.
[203] Section 18 of
the CEAA, which the Respondents allege to be applicable in the case at bar,
provides that where a project is not described in the CSL or the EL, the RA
shall ensure that a screening of the project is conducted and that a screening
report is prepared.
[204] Under
subsection 16(1) of the CEAA, the screening will include a consideration of the
following factors: the environmental effects of the project, the significance
of the environmental effects, comments from the public received in accordance
with the CEAA and the regulations, measures that are technically and
economically feasible and that would mitigate any significant adverse
environmental effects of the project, and any other matter relevant to the
screening that the RA may require.
[205] In the
context of a screening, public consultation is not necessarily mandatory. Where
it is not required by regulations, the latter will only occur if the RA is of
the opinion that public participation in the screening of a project is
appropriate in the circumstances (subsection 18(3) of the CEAA). In such cases,
the RA will include, on the Internet site, a description of the scope of the
project, the factors to be taken into consideration in the screening and the
scope of those factors or an indication of how such a description may be
obtained (paragraph 18(3)(a) of the CEAA).
[206] Again, if the
RA is of the opinion that public participation in the screening of a project is
appropriate, before taking a course of action under section 20 of the CEAA, the
RA will give the public an opportunity to examine and comment on the screening
report and on any record relating to the project that has been included in the
Registry and will give adequate notice of that opportunity (paragraph 18(3)(b)
of the CEAA). After taking into consideration the screening report and any
comments filed pursuant to subsection 18(3) of the CEAA), the RA can then take
one of the courses of action described at section 20 of the CEAA.
[207] As it was
explained earlier, the Course of Action Decision made by the RAs on May 2, 2006
is based on paragraph 20(1)(a) of the CEAA, which reads as follows:
20.
(1) The responsible authority shall take one of the following courses of
action in respect of a project after taking into consideration the screening
report and any comments filed pursuant to subsection 18(3):
(a)
subject to subparagraph (c)(iii), where, taking into account the
implementation of any mitigation measures that the responsible authority
considers appropriate, the project is not likely to cause significant adverse
environmental effects, the responsible authority may exercise any power or
perform any duty or function that would permit the project to be carried out
in whole or in part;
|
20.
(1) L’autorité responsable prend l’une des mesures suivantes, après avoir
pris en compte le rapport d’examen préalable et les observations reçues
aux termes du paragraphe 18(3) :
a)
sous réserve du sous-alinéa c)(iii), si la réalisation du projet n’est pas
susceptible, compte tenu de l’application des mesures d’atténuation qu’elle
estime indiquées, d’entraîner des effets environnementaux négatifs
importants, exercer ses attributions afin de permettre la mise en œuvre
totale ou partielle du projet;
|
[emphasis
added]
[208] Indeed, the
RAs took the Course of Action Decision without any input from the public in the
EA process under the CEAA on the grounds that public consultation in the
provincial EA process “provided sufficient and satisfactory opportunities for
public input into the Red Chris EA process”. In this regard, the RAs noted: “Based
on the extent of consultation that has been conducted by the Government of BC
and the Proponent, and the information that the RAs received from this
consultation, the RAs are of the opinion that public participation in the
screening of the Project under CEAA 18(3) is not appropriate under these
circumstances”.
[209] Section 21
provides that a comprehensive study must be conducted in the case of a project
mentioned on the CSL. Section 21 has been substantially amended in 2003. The
amendments introduced by Bill C-9 will be discussed later.
[210] A
comprehensive study constitutes a more thorough environmental assessment than a
screening. Indeed, where a comprehensive study is required, in addition to the
factors considered under subsection 16(1) of the CEAA, the following factors
will also be considered: the purpose of the project; alternative means of
carrying out the project that are technically and economically feasible and the
environmental effects of any such alternative means; the need for, and the
requirements of, any follow-up program in respect of the project; and the
capacity of renewable resources that are likely to be significantly affected by
the project to meet the needs of the present and those of the future
(subsection 16(2) of the CEAA).
[211] The CSL
referred to in section 21 of the CEAA, which the Applicant alleges to be
applicable to the Project, categorizes projects or classes of projects for
which a comprehensive study is required where the Governor in Council is
satisfied that the project or any project within the class is likely to have
significant adverse environmental effects. The CSL is appended as a schedule of
the CSL Regulations.
[212] In a manner
similar to the EL and the IL already mentioned above (see Section III –
Requirement of an EA), the CSL is divided into parts reflecting its general
areas of application, including: national parks and protected areas; electrical
generating stations and transmission lines; water projects; oil and gas
projects; minerals and mineral processing; nuclear and related facilities;
industrial facilities; defence; transportation; and water management.
[213] Pursuant to
section 3 of the CSL Regulations, the proposed construction, decommissioning or
abandonment of a metal mine, other than a gold mine with an ore production
capacity of 3 000 tonnes per day or more, or a gold mine other than a placer
mine, with an ore production capacity of 600 tonnes per day or more are
prescribed projects and classes of projects for which a comprehensive study is
required (see items 16(a) and (c) of Part 5 - Minerals and Mineral Processing
of the Schedule to the CSL Regulations).
[214] Moreover, a
comprehensive study is required in the case of the proposed construction,
decommissioning or abandonment of a structure for the diversion of 10 million m3
or more of water from a natural water body into an other natural body water or
an expansion of such structure that would result in an increase in the
diversion capacity of more than 35 percent (Item 9 of Part III – Water Projects
of the CSL). However, in view of the fact that the Applicant has abandoned its
request that a declaration be made in this regard, it is not necessary to
determine whether or not the Project also falls under item 9 of the CSL, as it
may exceed the water diversion volume threshold of 10 million m3 per
year in the post-closure period of the mine (see the estimates mentioned at
section II - The Project).
[215] The Bill C-9
amendments also added sections 21.1 and 21.2 to the CEAA.
[216] Section 21.1
of the CEAA provides that after the public consultation, the minister of the
Environment must take into account the RA’s report and its recommendation, and
then either refer the project to the RA so that it may continue the
comprehensive study and ensure that a comprehensive study report is prepared
and provided to the minister of the Environment and to the Agency or refer the
project to a mediator or review panel. If the minister of the Environment
refers the project to the RA, this decision is final; the project may not be
later referred to a mediator or review panel (subsection 21.1(2) of the CEAA).
[217] Furthermore,
pursuant to the new section 21.2 of the CEAA, the RA must then ensure that the
public is provided with an opportunity in addition to those provided
under subsection 21(1) and section 22 of the CEAA, to participate in the
comprehensive study, subject to a decision with respect to the timing of the
participation made by the federal environmental assessment coordinator under
paragraph 12.3(c) of the CEAA.
[218] Section 22 of
the CEAA, which also deals with comprehensive studies, has not been amended.
After receiving a comprehensive study report in respect of a project, the
Agency publishes a notice setting out, inter alia, the address for
filing comments on the conclusions and recommendations of the report and any
person may file comments with the Agency relating to the conclusions and
recommendations and any other aspect of the comprehensive study report. Prior
to the deadline set out in the notice published by the Agency, any person may
file comments with the Agency relating to the conclusions and recommendations
and any other aspects of the comprehensive study report.
[219] Pursuant to
subsection 23(1) of the CEAA, after taking into consideration the comprehensive
study report and any comments filed, the minister of the Environment may refer
the project to the RA for action under section 37 of the CEAA and issue an
environmental assessment decision statement that sets out the minister of the
Environment’s opinion as to whether, taking into account the implementation of
any mitigation measures that the minister of the Environment considers
appropriate, the project is or is not likely to cause significant adverse
environmental effects and sets out any mitigation measures or follow-up program
that the minister of the Environment considers appropriate, after having taken
into account the views of the RAs and other federal authorities concerning the
measures and program.
c) Review
panel or mediator
2) The
nature of scoping
[223] Establishing the scope
of a project to be assessed is a very fact-specific endeavor, one which
requires a careful examination of the works that are being carried out in
relation to the project in question.
[224] For example, in Québec
(Attorney General) v. Canada (National Energy Board), [1994] 1 S.C.R. 159,
the Supreme Court of Canada considered the question of the scope of the project
for the purposes of assessment under the National Energy Board Act, R.S.C.
1985, c. N-7. Hydro-Québec had applied for licenses to export electricity to
the United
States.
The National Energy Board (the Board) approved the licenses subject to two
environmental conditions related to the proposed electricity generating
facilities. One condition required that, prior to their construction, the
electricity generating facilities undergo an environmental assessment.
[225] The Supreme Court ruled
that, in assessing the scope of the assessment, the proper question to ask was
whether the construction of the new facilities "is required to serve,
among other needs, the demands of the export contract." The Supreme Court
further held that the Board was not limited in its scope of inquiry to the
"environmental ramifications of the transmission of power by a line of
wire." Thus, the environmental effects of the electricity generating
facilities were related to the Board's power to grant an export license and
came within the scope of the assessment.
[229] While not
binding, the guidelines explain how the Agency envisions the operation of the
EA process, which is a complex one. Indeed, courts have relied on the Agency’s
publications in order to describe the EA process: Friends of the West
Country Assn. v. Canada (Minister of Fisheries
& Oceans), [2000] 2 F.C. 263 (C.A.), Citizens’ Mining, above; Manitoba’s
Future Forest Alliance v. Canada
(Minister of the Environment) (1999), 170 F.T.R.161 (T.D.), Bow Valley, above.
[230] The RAs must
first determine whether the CEAA applies. To answer this question, the RA must
determine if:
1) there
is a “project” as defined by the CEAA;
2) the
project is not excluded by the CEAA or one of its regulations;
3) the
project involves a “federal authority”; and/or
4) the
project involves an action that triggers the need for an EA under the CEAA.
[231] Second, the
RA determines which EA track to follow. In this regard, the Guide to the
preparation of a comprehensive study for proponents and responsible authorities
mentions:
The majority of federal projects
requiring an environmental assessment will undergo a self-directed EA, which
can involve either a screening or a comprehensive study. Both are considered
self-directed environmental assessments because the responsible authority:
·
determines
the scope of the environmental assessment;
·
ascertains
the factors to be considered;
·
directly
manages the environmental assessment process; and
·
ensures
that an environmental assessment report is drawn up.
Although the majority of self-directed
EAs will involve screenings, some will require a comprehensive study, which
involves a more intensive and rigorous assessment of a proposed project’s
environmental effects.
A project will undergo a comprehensive
study when it:
·
is
prescribed within the Comprehensive Study List Regulations;
·
Has not
been referred directly by the RA to the Minister for mediation or panel review;
and
·
Takes
place inside of Canada.
The RA must review the Comprehensive
Study List Regulations to determine if the project, for which it is proposing
to exercise a power, is described on the list. Where it is unclear whether a
project is on the list, the RA should seek advice from the Agency.
[232] In this
regard, the Guide to the preparation of a comprehensive study mentions:
It is up to the responsible authorities
to determine the scope of the project (s.15), and the scope of the factors to
be taken into consideration during the comprehensive study (ss. 16(1), ss.
16(2) and ss (3)). The Federal Coordination Regulations require that the
RAs and expert departments together determine the scope of the project, the
factors to be considered and the scope of the factors. The best practice is for
federal authorities to agree on one scope that satisfies all their EA responsibilities.
However, this is not a legal requirement.
It is highly recommended that the scoping
exercise be undertaken in consultation with the proponent, stakeholders groups,
expert departments and the Agency. Scoping sessions should be held as early as
possible in the process. The success of the environmental assessment process
will often depend on how well this step is undertaken. The scoping exercise
sets the parameters for the comprehensive study and provides a rationale for
the design of the studies which may be required. [emphasis added]
[233] As noted by
Justice Linden in Bow Valley, above, at paras. 25-27:
The Act does not define the process of
scoping of the project. Neither does it define the term "scope." Nor
does it provide any direction to the responsible authority in determining which
physical works should be included within the scope of the project. The
Responsible Authority's Guide, however, suggests the use of the principal
project/accessory test to ensure consistency in scope of the project determinations.
According to the principal project/accessory test, the principal project,
i.e., either the undertaking with respect to a physical work or the physical
activity, must always be included in the scope of the project. The scope should
also include other physical works or physical activities which are accessory to
the principal project.
The Responsible Authority's Guide
suggests two criteria be used in determining what constitutes an accessory to
the principal project: interdependence and linkage. If the principal project
cannot proceed without the undertaking of another physical work or activity,
then that other physical work or activity may be considered as a component of
the scoped project. Furthermore, if the decision to undertake the principal project
makes the decision to undertake another physical work or activity inevitable,
then that other physical work or activity may also be considered as a component
of the scoped project.
The Operational Policy Statement issued
by the Agency entitled "Establishing the Scope of the Environmental
Assessment" provides that "scoping establishes the boundaries of an
environmental assessment (what elements of the project to consider and include
and what environmental components are likely to be affected and how far removed
those components are from the project)." The Statement recommends the
following, among other things, be considered when determining the scope of the
project: the description of the project (what is the project and is it the
principal project?) and justification for the project (what is the purpose of
project and why is it proposed?), and other physical works which are inevitable
or physically linked to or are inseparable from the proposed projects; whether
the proposed project is or has been the subject of an assessment of
environmental effects by others, such as other environmental assessments,
forest management plans, or resource management plans, regional land use plans;
whether other review processes have occurred or are occurring and their results.
[emphasis added]
[234] As can be
seen, the process of scoping involves several issues, namely the scope of the
project itself, the scope of the environmental assessment, the scope of the
factors to be considered, and scoping “interested parties” (see the definition
in section 2 of the CEAA). I will now examine the relevant case law with
respect to the interpretation of the powers granted to the RAs in this regard.
[235] In the case at bar, it
is not contemplated that the Project will be completed in several phases
(however the two projected open pits would eventually merge into one) or that
RCDC will not construct the projected mine and mill which have been excluded by
the RAs in the Scoping Decision of March 2005. Neither is it a case where the
RAs have decided to include in the scoping exercise components of a project
which had for instance, been excluded by a proponent in its description of the
contemplated project. As it was previously explained, it was initially
determined by DFO in May 2004 that a comprehensive study, preceded by a public
consultation with respect to the scope of the Project and factors to be
considered in the EA of the Project, would be prepared by the RAs. However, the
RAs later determined that the Project “as scoped” by them was no longer
included in the CSL.
[236] The interpretation of
section 15 has been the subject of significant judicial consideration.
1) Bowen
[237] In Bowen
v. Canada (Attorney General), [1997] F.C.J. No. 1526 (T.D.), the applicants
contested a decision of the minister of Canadian Heritage to close the
airstrips in Banff and Jasper National
Parks. More specifically, the applicants alleged the screening process, which
the Department of Heritage undertook to determine the environmental effects of
decommissioning the airstrips, was in violation of the requirements under the
CEAA to complete a comprehensive study. In this decision, the Court assessed
the scheme under the former version of the CEAA. The Court then evaluated
whether the decision of the Governor in Council was “in relation to a physical
work.” Having identified the project as the decommissioning of airstrips, the
Court next considered whether the project was on the comprehensive study list.
Justice Campbell noted in this regard:
Under
s. 1 of the Comprehensive Study List, since each decommissioning is in relation
to a physical work in a national park, a comprehensive study is required, but
only if the decommissioning is contrary to the management plan for the park
concerned.
[238] Finding that
the decommissioning of airstrips was contrary to the management plan for the
parks concerned, the Court determined the project was on the CSL. Justice
Campbell further noted:
Therefore,
I find that a comprehensive study is required respecting any decision to
decommission either the Banff or Jasper airstrips. I also find that
the fact that screening assessments have already been done is an irrelevant
consideration as far as the law is concerned, although undoubtedly, the results
will be of practical assistance in the development of the required
comprehensive studies.
[239] In light of
this finding, the Court concluded, therefore, a comprehensive study was
required and that the screening was ultra vires.
2) Manitoba's Future Forest Alliance
[240] The case of Manitoba's
Future Forest Alliance v. Canada (Minister of the
Environment)
(1999), 170 F.T.R.161 (T.D.) involved the construction of a bridge and an
environmental assessment undertaken by the Canada Coast Guard. The proponent of
the project was also undertaking the conversion and expansion of an existing
pulp mill, the construction of a new pulp mill, the construction of hundreds of
kilometres of logging roads and other related forestry activities. The approval
was challenged on the basis of the narrow scoping of the project. Justice Nadon
found that, when determining the scope of the project under subsection 15(1) of
the CEAA, the responsible authority was required under subsection 15(3) to
assess not just those undertakings proposed by the proponent but also those
which were likely to be carried out in relation to the bridge.
[241] Justice Nadon at para.
53, imported the following passage from the respondent’s memorandum into his
judgment:
The
effect of s. 15(3)... is that the scope of the assessment of a physical work
project may be increased beyond what is proposed in the project itself, in
order to take into account the environmental effects of the undertakings the
responsible authority believes are likely to be carried out to carry the
project through its life cycle. [emphasis added]
[243] In Friends of the West
Country Assn.,
above, the breadth of subsections 15(1) and (3) of the CEAA was reviewed by
this Court and the Federal Court of Appeal. In first instance, the Court found
no reviewable error in the manner in which the Coast Guard exercised its
discretion in defining the projects subject to environmental assessment review.
In particular, the Court found no error in the Coast Guard, not including the
main line road and the proposed Sunpine forestry operations within the scope of
the bridge projects. However, the Court went on to consider subsection 15(3).
In this regard, my colleague Justice Gibson concluded that the RA was obliged
to include within “the scope of the environmental assessment” (as opposed to
the “projects”) the road and perhaps the forestry operations because they were
“in relation to” the bridges.
[244] The appeal was dismissed
and it was ordered that the matter be redetermined in the accordance with the
reasons of Justice Gibson as modified by the reasons of the Federal Court of
Appeal. In this regard, Justice Rothstein who wrote the reasons of the Court of
Appeal stated that while the scope of the project is to be determined by the
RA, it may include more than just the physical work that triggered CEAA review,
where there are other physical activities in relation to a particular work. However,
subsection 15(3), is “subsidiary” to subsection 15(1), and as stated by Justice
Rothstein in the latter case “… the words in subsection 15(3) do not have the
effect of re-scoping a project to something wider than that was determined
under subsection 15(1)”.
[245] That being said, Justice
Rothstein opined at paras. 34 and 39:
Under paragraph 16(1)(a), the responsible
authority is not limited to considering environmental effects solely within the
scope of a project as defined in subsection 15(1). Nor is it restricted to considering
only environmental effects emanating from sources within federal jurisdiction. Indeed,
the nature of a cumulative effects assessment under paragraph 16(1)(a) would
appear to expressly broaden the considerations beyond the project as scoped.
…
[…] It is not illogical to think that the
accumulation of a series of insignificant effects might at some point result in
significant effects. I do not say that is the case here. I only observe that a
finding of insignificant effects of the scoped projects is sufficient to open
the possibility of cumulative significant environmental effects when other
projects are taken into account. For this reason, I do not think the
insignificant effects finding precludes the application of the cumulative
effects portion of paragraph 16(1)(a) or subsection 16(3) in this case.
[emphasis
added]
[246] Accordingly, the Federal
Court of Appeal determined that the Coast Guard had erred in declining to
exercise the discretion conferred on it in its cumulative effects analysis
under paragraph 16(1)(a) by excluding consideration of effects from other
projects or activities because they were outside the scoped projects or were
outside federal jurisdiction.
4) Canadian Parks and Wilderness
Society
[247] The courts have
recognized that the need to establish the scope of a project to be assessed is
particularly important when looking at a project that may involve different
phases or developments over the course of several years. For example, in Canadian
Parks and Wilderness Society v. the Minister of Canadian Heritage, [2001]
F.C.J. No. 1543, 2001 FCT 1123 (T.D.); affd [2003] F.C.J. No. 703, 2003 FCA
197, the minister of Canadian Heritage treated an EA of a winter road as one
project and determined that any future proposal to build an all-season road
would be a new project. The EA was challenged, based in part on the scope of
the assessment. The challenge was not successful and it was determined that the
minister of Canadian Heritage had acted within the scope of her jurisdiction by
considering the winter road and possible all-season road as two separate
projects.
5) TrueNorth
[248] I will now
analyze the two TrueNorth decisions rendered by this Court in 2004 and the
Federal Court of Appeal in 2006. The relevant facts of that case, as set out by
my colleague Justice Russell in TrueNorth – first instance, are explained
below. Like the cases mentioned above, the TrueNorth decisions are also based
on the provisions of the CEAA as they read prior to the Bill C-9 amendments.
However, the text of section 15 has remained the same.
a) Factual
background
[249] In August
2000, TrueNorth Energy Corporation announced its plans to develop an oil sands
extraction mine near Fort McMurray, Alberta, which
required the removal of oil-laden soil. The development necessitated the
destruction of Fort Creek, a fish-bearing stream that ran through the area of
the proposed mine. Consequently, an authorization to destroy fish and fish
habitat (HADD) was required by section 35 of the Fisheries Act. DFO, the
responsible authority in that case, received a formal application for
authorization in April 2001, which triggered an environmental assessment
pursuant to paragraph 5(d) of the CEAA.
[250] The Province of Alberta
was also conducting a review of TrueNorth’s proposal. In July 2001, DFO
obtained TrueNorth’s environmental impact assessment (EIA), which had been
required by the Province of Alberta for the purpose of its
review of the TrueNorth’s proposal. The EIA identified fish tainting as a
potential issue of high significance. Fish tainting, a long-term declining quality
of fish, is caused either by natural seepage or by the deposit of a deleterious
substance into waters frequented by fish. In this regard, the EIA contemplated
the possibility of the deposit coming from the operations of TrueNorth’s mine.
The Court noted in obiter at para. 9, that although “[t]he deposit of a
deleterious substance into waters frequented by fish is prohibited by s. 36(3)
of the Fisheries Act, [it] was not subject to an authorization under subsection
35(a) of the Fisheries Act [sic]”. It is worthwhile to reiterate that
TrueNorth’s proposal, unlike in the case at bar, did not include a TIA.
[251] Almost one
year later, in May 2002, TrueNorth provided DFO with a consultant’s report that
reduced the potential fish tainting effects to the level of negligible. In July
2002, Environment Canada provided its expert advice and urged that further
studies be conducted, although it did not necessarily dispute TrueNorth’s
assessment that the fish tainting effects would be negligible.
[252] In July 2002,
DFO participated as an intervener in the hearings conducted by the province
through the Alberta Energy and Utilities Board (AEUB) in relation to the
TrueNorth mining proposal.
[253] The following
month, in August 2002, DFO circulated a preliminary scoping decision in a
letter, identifying the scope of the project in relation to which an
environmental assessment was to be conducted as being the destruction of the
bed and channel of Fort Creek and other associated activities:
1. The
destruction of the bed and channel of Fort Creek
2. The
construction of temporary or permanent diversions of Fort Creek
3. The
construction of site de-watering and drainage works
4. The
construction and operation of associated sediment and erosion control works
5. The
construction of any Fort Creek crossings and associated approaches
6. The
construction and operation of any fish habitat compensation works as required
by DFO
7. The
construction of camps and storage areas associated with (1) through (7)
8. Site clearing
and removal of riparian vegetation associated with (1) through (8)
[254] In September
2002, the Government of Canada served its submissions on the AEUB and the
participants in the provincial hearings.
[255] DFO consulted
with other federal authorities before determining the scope of the project,
pursuant to section 8 of the Regulations Respecting the Coordination by
Federal Authorities of Environmental Assessment Procedures and Requirements,
SOR/97-181. Responses were received from Health Canada, Parks
Canada, NRCan and Environment Canada. Of all of these federal authorities, only
Environment Canada recommended that the scope of the project be expanded beyond
that proposed in DFO’s letter. Specifically, it recommended that the scope of
the project be expanded “to include the entire project as defined by TrueNorth
Energy Ltd. in its combined application to the Alberta Energy Utilities Board
and Alberta Environment”. Furthermore, in October 2002, three non-profit
organizations also submitted a letter through their counsel arguing that the
proposed scoping was too narrow and that a comprehensive study was required.
[256] In December
2002, DFO issued its final scoping decision with scoping unchanged from its
August 2002 preliminary decision. With regards to this decision, Justice
Russell writes:
In arriving at the final scoping
Decision, Ms. Majewski [Area Chief, Habitat with the DFO] was guided by the
principles that the determination must be reasonable and made on a case-by case
basis. Ms. Majewski determined the scope of the project to be that which
includes the undertakings and activities that require authorization under s.
35(2) of the Fisheries Act and give rise to the application of CEAA and
the ancillary works and activities. Accordingly, she scoped in the destruction
of the bed channel of Fort Creek because it entails physical activities
prescribed to be a "project" for the purpose of CEAA pursuant to Part
VII of the Schedule of the Inclusion List Regulations. The remaining elements
of her scoping Decision entail the ancillary works and activities, including a
Fort Creek diversion channel.
Had the water flows of Fort Creek into a
diversion channel exceeded limits shown in s. 9 of the Comprehensive Study
List Regulations, a comprehensive study would have been required. Since
this was not the case, Ms. Majewski concluded that the environmental assessment
under CEAA should be conducted at a screening level.
In reaching her final Decision on scoping
Ms. Majewski took into consideration all comments, including those made by the
Applicants' counsel, as well as the findings of the provincial hearing.
b) Judicial
review application
[257] The
non-profit organizations who had earlier made representations to DFO applied to
this Court for judicial review of DFO’s December 2002 scoping decision. They
submitted that DFO had wrongly limited the scope of the project to the
destruction of the Fort Creek and should instead have scoped the entire oil
sands undertaking. They argued that DFO had erred in its interpretation of the
scope of the federal assessment power under the CEAA and of the definition of
“project”, and had unreasonably exercised its discretion in determining the
scope of the project to be assessed. Specifically, the applicants submitted
that the destruction of Fort Creek was an impact of the project and not a
separate project in and of itself. Because the oil sands project exceeded two
separate thresholds set out in Part IV of the CSL, a comprehensive study of the
project was required.
[258] The
applicants stressed that Ms. Majewski had wrongly assumed that where an EA
was triggered, “the scope of the project should be limited to those elements
over which the federal government can validly assert authority, either directly
or indirectly. The EA scope of project should correspond to the federally
regulated undertaking involved in the application”. The applicants argued that
this demonstrated that DFO mistakenly believed that a federal authority could
only look at what it could validly regulate. However, according to the
applicants, in Friends of Oldman River Society, above, the Supreme Court
of Canada had established that the scope of assessment was not confined to the
particular head of power under which the federal authority had decision-making
responsibility and once the initiating department had been given authority to
embark on the assessment, its review must consider the environmental effect on
all areas of federal jurisdiction.
c) Decision
in first instance
[259] On September
16, 2004, Justice Russell dismissed the application. In coming to his
conclusion, he noted, at para. 234:
In my view, then, the Oldman River case,
although directing that assessment, once appropriately initiated, can consider
the impact of a project on all areas of federal jurisdiction, does not
suggest that the scope of an assessment does not have to be connected to
the relevant head of federal power that is engaged by an application. In fact,
I am of the view that there was behind the judgment of LaForest J. in Oldman River an assumption that the
exercise of legislative power can only give a mandate to examine matters that
are related to the heads of federal responsibility affected.
In any event, I am of the view that the
scoping mandate of DFO is to be found in CEAA itself and not by reference
to a decision such as that in Oldman River, that dealt specifically with the
constitutionality of a particular Guidelines Order. [emphasis added]
[260] Justice
Russell further observed, at para. 243:
I agree with the Applicants that, once
CEAA has been triggered, there is nothing in s. 15 or any provision related
to the scope of an assessment which specifically limits a scoping decision
to the relevant head of federal jurisdiction occupied by the responsible
authority. But, in my view, no such words of limitation are necessary because
it could not have been Parliament's intent to authorize a Responsible Authority
to environmentally assess aspects of a project unrelated to those heads of
federal jurisdiction called into play by the project in question. [emphasis
added]
[261] Moreover,
Justice Russell held that nothing in the definition of “project” in the CEAA
prevented the destruction of Fort Creek from being a project in its own right.
[262] Although former
section 21 of the CEAA was mentioned in Justice Russell’s summary of the
parties’ submissions, it was not explicitly mentioned in his analysis. That
being said, it is clear that Justice Russell’s comments above are directed
exclusively to the “scope of an assessment” under section 5 of the CEAA, which
in this case “specifically limits a scoping decision to the relevant head of
federal jurisdiction occupied by the responsible authority”.
d) Decision
in appeal
[263] The
applicants appealed the decision rendered by the Court. On January 27, 2006,
the Federal Court of Appeal dismissed the appeal.
[264] First, with
regards to the applicants’ argument that the words “in whole or in part” in
paragraph 5(1)(d) implied that a project must consist of an entire physical
work or physical activity, Justice Rothstein who wrote the reasons of the
Federal Court of Appeal stated:
The appellants have misconstrued paragraph
5(1)(d). The project referred to in paragraph 5(1)(d) is the project as
scoped by the responsible authority under subsection 15(1). The words
"in whole or in part" recognize that within a project as scoped by a
responsible authority, the power to be exercised by a federal authority under
subsection 5(1)(d) may relate only to a part of that project. In this case,
TrueNorth requires authorization from the Minister of Fisheries and Oceans of
Canada under subsection 35(2) of the Fisheries Act for the destruction of the
Fort Creek fish habitat. However, the project, as scoped, involves more
than the destruction of Fort Creek: for example, construction of camps and
storage areas required to carry out the destruction of Fort Creek. Although the
construction camps and storage areas are scoped as part of the destruction of
the Fort Creek project, TrueNorth will not require permits under paragraph
5(1)(d) for them. [emphasis added]
[265] It is
interesting to note that in these passages, no direct mention is made by
Justice Rothstein to former section 21. Justice Rothstein’s reasoning in
TrueNorth suggests that the word “project” which is broadly defined at section
2 of the CEAA must have a more restrictive meaning when it is used in paragraph
5(1)(d) of the CEAA: “[t]he project referred to in paragraph 5(1)(d) is
the project as scoped by the responsible authority under subsection
15(1)” [emphasis added]. However, this leaves the question whether the word
“project” used elsewhere in other provisions of the Act should be read as the
project scoped by the RA or as the project proposed by the proponent. In other
words, does the scope of the project proposed by the proponent or determined by
the RA have an effect on the level of assessment itself?
[266] Without
directly answering this question, Justice Rothstein rejected the applicants’
argument that projects listed in the CSL must be subject to an EA under the
CEAA, stating at para. 23 and 24:
The appellants' next argument is based on
the Comprehensive Study List Regulations, SOR/94-438. Many of the
projects listed in these Regulations are under provincial jurisdiction with a
limited federal role. Nonetheless, they argue that projects listed in these
Regulations must be subject to an environmental assessment under the CEAA.
The purpose of the Regulations appears to
be that when a listed project is scoped under subsection 15(1), a comprehensive
study, rather than a screening, will be required in respect of that project.
But it does not purport to impose on a responsible authority exercising its
discretion under subsection 15(1) of the CEAA the requirement to scope a work
or activity as a project merely because it is listed in the Regulations. In this case, the oil sands
undertaking is subject to provincial jurisdiction. The Comprehensive Study List
Regulations do not purport to sweep under a federal environmental assessment
undertakings that are not subject to federal jurisdiction. Nor are the
Regulations engaged because of some narrow ground of federal jurisdiction, in
this case, subsection 35(2) of the Fisheries Act. See Friends of the Oldman River Society v. Canada (Minister of Transport), [1992] 1 S.C.R. 3 at pages
71-72.
…
The appellants may not be satisfied with
a province conducting an environmental assessment, but the subject of the
environment is not one within the exclusive legislative authority of the
Parliament of Canada. Constitutional limitations must be respected and that is
what has occurred in this case. [emphasis added]
[267] Indeed, in
TrueNorth, Justice Rothstein stated:
In this case the Alberta provincial authorities were conducting
an environmental assessment. It would be inefficient for two assessments to be
performed. It was both legally appropriate and efficient from a policy
perspective for the DFO to rely on Alberta's
performance of an environmental assessment.
[268] I read these
passages to mean that the mere fact that a particular undertaking appears to be
covered by the CSL, does not mean that an EA must be conducted under section 5
of the CEAA. There must always be a federal trigger present. However, I am not
sure that Justice Rothstein meant by this that a RA could use section 15 to
discard the application of former section 21 where it has already been decided
that a joint assessment of the project proposed by a proponent, as in this
case, would be conducted by the provincial and federal authorities. In the case
at bar, it was initially announced by the RA in spring 2004 and subsequently recognized
by the BCEAO that the Project would be jointly assessed at the level of a
comprehensive study, and in this regard, a draft working plan was jointly developed
during the autumn of 2004 in accordance with the Agreement (see paragraph 58
above).
[269] Leave for appeal to the Supreme Court of Canada of the judgment of
the Court of Appeal in TrueNorth was dismissed without reasons on July 20,
2006.
D. COURSE
OF ACTION DECISION REVIEWABLE
[270] In May 2004,
based on the information provided by RCDC, the Notice of Commencement posted on
the Registry announced that a comprehensive study commencing on May 19,
2004 would be conducted with respect to the Project. It is apparent in the
correspondence and various documents emanating from DFO and the Agency that
while DFO, “had not yet formally identified the scope of the project for the
purposes of the comprehensive study”, the RAs would consult the public on the
proposed scope of the project and other aspects mentioned at section 21 of the
CEAA (see DFO’s Notice to Federal Authorities, the Briefing Book and the Draft
Work Plan).
[271] As stated in
the Briefing Book addressed to the minister of the Environment in July 2004,
the tracking decision taken by DFO in May 2004 was consistent both with the
scheme of the CEAA and Bill C-9 amendments which now oblige the RAs to consult
the public on their proposed approach, report on this consultation to the
minister of the Environment, and recommend to the latter whether the EA be
continued by means of a comprehensive study, or the project be referred to a
mediator or a review panel.
[272] The decision taken in December
2004 to suddenly re-track the Project appears to have been based on inexistent “new”
fisheries data. This contrasts sharply with the decision made in January 2005
to conduct a comprehensive study commencing on January 22, 2005, of the
Galore-Creek Gold-Silver-Copper mine, where the Agency has established a
$50,000 participant funding program to assist groups and/or individuals to take
part in the federal EA of the proposed project, which exceeds threshold
production listed under paragraphs 16(a), (b) and (c) of the CSL. Indeed, the
general public was subsequently invited to comment on the scope of the project
and on the scope of the factors contained in the document entitled
“Comprehensive Study Scoping Document for the NovaGold Canada Inc. Proposed Galore-Creek
Gold-Silver-Copper Mine Project in North-Western British Columbia” dated
November 30, 2005.
[273] What is
really at issue in this case is whether the RAs may legally refuse to conduct a
comprehensive study on the grounds that the Project as re-scoped by them does
not include a mine and milling facility anymore.
[274] Overall, sections
2, 5, 13, 14, 15, 16 and 18 and the new section 21 of the CEAA, as I read them
together, and having in mind the purpose of the CEAA and the intention of
Parliament, support the Applicant’s principal proposition that where a project is
described in the CSL, the RA must now ensure public consultation with respect
to the proposed scope of the project for the purposes of the EA, the factors
proposed to be considered in its assessment, the proposed scope of those
factors are the ability of the comprehensive study to address issues relating
to the project.
[275] Subsection
21(1) of the CEAA is of particular importance for this case. It reads as
follows:
21.
(1) Where a project is described in the comprehensive study list, the
responsible authority shall ensure public consultation with respect to the
proposed scope of the project for the purposes of the environmental
assessment, the factors proposed to be considered in its assessment, the
proposed scope of those factors and the ability of the comprehensive study to
address issues relating to the project.
|
21.
(1) Dans le cas où le projet est visé dans la liste d’étude approfondie,
l’autorité responsable veille à la tenue d’une consultation publique sur les
propositions relatives à la portée du projet en matière d’évaluation
environnementale, aux éléments à prendre en compte dans le cadre de
l’évaluation et à la portée de ces éléments ainsi que sur la question de
savoir si l’étude approfondie permet l’examen des questions soulevées par le
projet.
|
[emphasis
added]
[276] In
comparison, the former version of section 21, which has been repealed by Bill
C-9, read as follows:
21.
Where a project is described in the comprehensive study list, the responsible
authority shall
(a)
ensure that a comprehensive study is conducted, and a comprehensive study
report is prepared and provided to the Minister and the Agency; or
(b)
refer the project to the Minister for a referral to a mediator or a review panel
in accordance with section 29.
|
21.
Dans le cas où le projet est visé dans la liste d'étude approfondie,
l'autorité responsable a le choix:
a)
de veiller à ce que soit effectuée une étude approfondie et à ce que soit
présenté au ministre et à l'Agence un rapport de cette étude;
b)
de s'adresser au ministre afin qu'il fasse effectuer, aux termes de l'article
29, une médiation ou un examen par une commission.
|
[emphasis
added]
[277] While I do
not need to resort on the guidelines, I am comforted by the fact that my
interpretation is in accord with same. I note that according to the guidelines,
large-scale projects with potentially significant environmental effects
identified on the CSL, such as marine terminals; highways; airstrips;
electrical generating stations; dams and reservoirs; artificial islands for oil
and gas production; oil sands processing plants and mines; oil refineries; oil
and gas pipelines; metal and uranium mines; pulp and paper mills; and certain
military constructions will usually undergo the rigorous assessment of a
“comprehensive study”.
[278] While these
guidelines are not legally binding – what counts are the actual applicable
legislative and regulatory provisions – they provide a strong indication that
the present project is one of these large-scale projects which Cabinet wanted
to undergo the rigorous assessment of a comprehensive study. I doubt very much
that Cabinet’s intention in adding to the CSL mining projects exceeding any of the
thresholds mentioned at items 16, 17 and 18 of the CSL, was to restrain the
scope of an assessment by way of a comprehensive study to mines located on
Crown lands or operated by a federal authority.
[279] According to
the original wording of paragraph 59(d) of the CEAA, which section came into
force on January 19, 1995, Parliament wholly reserved to Cabinet the discretion
to decide what projects to describe in the CSL. It must be assumed that this
was not meant to be the project “as scoped” by the RA, otherwise the exercise
of Cabinet’s plenary discretion would be futile and useless. Cabinet has
exercised the discretion by promulgating and amending the CSL Regulations from
time to time. As I read the CSL, the EL and the IL, projects mentioned in these
regulations, refer to the project described by a proponent.
[280] Moreover,
since the amendments brought by Bill C-9 in October 2003, the power to add a
project in the CSL has been transferred by Parliament from Cabinet to the
minister of Environment (the Bill C-9 Amendments, above, at s.29 (2.1)).
Section 58(1)(i) of the amended CEAA, (the version, it bears re-iterating, that
is applicable to the case at bar), now provides that the minister of the
Environment may “make regulations prescribing any project or class of projects
for which a comprehensive study is required where the Minister is satisfied
that the project or any project within that class is likely to have significant
adverse environmental effects.”
[281] The corollary
to this is also true: if the minister does not wish to have mining projects,
such as the present Project, to be “tracked” for the purpose of an EA as one
requiring a comprehensive study, the minister may simply suppress the same from
the current CSL. In my opinion, this legislative amendment is significant
since, in the event that the government determines projects have been either
omitted from or wrongly included in the CSL, it makes for an even easier
process to rectify such an oversight.
[282] As stated in
the preamble of the CEAA, an EA is a tool used to help achieve the goal of
sustainable development by providing “an effective means of integrating
environmental factors into planning and decision-making processes.”
[283] I am not persuaded that
once public consultation is required under section 21 of the CEAA, it is
possible to avoid the entire public consultation process by narrowing the scope
of the project in order to reduce it to the level of a screening. Once a
project has been included in the CSL, section 21.1 grants the minister of
the Environment
the discretion to either continue with the comprehensive study or to refer the
project to a mediator or review panel in accordance with section 29. The
legislative scheme, thus, only allows the minister of the
Environment
to maintain a comprehensive study or to upgrade it to a more in-depth process.
No provision in the CEAA empowers the minister of the Environment to downgrade a
comprehensive study to a screening. Likewise and more significantly to the
case at bar, no provision in the CEAA empowers a responsible authority to
downgrade a comprehensive study to a screening.
[284] Once a tracking decision had
been made requiring the project to undergo a comprehensive study, it is my view
that the RAs did not have the discretion to re-scope the project in such a
manner as to avoid the public consultation implications of section 21. To
allow them to do so would violate not only the plain meaning of the legislation
in question, but also the spirit of the entire legislative scheme, as amended,
which is designed to foster public participation for projects with significant
potential environmental repercussions.
[285] Counsel for
the Proponent asserts that the current case is virtually on all fours with
TrueNorth in that:
·
TrueNorth
proposed to develop an oil sands extraction mine;
·
The
entire mining project was the subject of a full provincial environmental
assessment;
·
Viewed
as a whole, the mine included a processing facility with a capacity of 30 000 m3/d
and a mine with a capacity of 15 000 m3/d, which meant that it was
described on the comprehensive study list;
·
The
only federal authorization for the project was the Fisheries Act authorization
for harm to the fish habitat; and
·
The
RA (DFO) determined pursuant to section 15(1) of the CEAA that the scope of the
project that was to be subject to a federal environmental assessment was the
destruction of Fort Creek and ancillary works and activities.
[286] First, it is
trite law that this Court is bound by the judgment of the Federal Court of
Appeal in TrueNorth. While I agree with the Proponent that there are some
similarities between the two cases, the Proponent fails to note a few factual
differences which, in my opinion, limit its applicability to this case:
·
In
TrueNorth, the applicants were seeking the judicial review of a scoping
decision made pursuant to section 15 of the CEAA. In this case, the Applicant
alleges an ongoing breach of the duty to ensure public consultation in
accordance with section 21 of the CEAA, which breach culminated in the
communication of the Course of Action Decision Report, and whose legality must
be examined in light of the factual context of the case.
·
There
is no evidence in TrueNorth to indicate the responsible authorities originally
decided the project ought to be tracked as a comprehensive study, only to
modify the decision at a later date. Indeed, in TrueNorth, the evidence
before this Court and the Federal Court of Appeal was that the project was
always intended to undergo a screening and not a comprehensive study. Again, this suggests to
me that the TrueNorth decision should be applied cautiously and only to the
extent that the facts of this case are directly on point with the facts in that
case.
·
There
was no TIA to be constructed by the proponent in TrueNorth.
·
There
was no explosives factory and magazine involved in TrueNorth. Not only does
a federal licence under the Explosives Act needs to be issued by the minister
of Natural Resources, but the explosives factory and magazine will be
constructed on the mine site. Indeed, the facilities are to be located
approximately 400-450 m apart and 450-500 m north of the ultimate toe of the
waste rock storage area.
·
Physical
activities in relation to the carrying of the Project go beyond the harmful
alteration, disruption, or destruction of fish habitat (HADD) but contemplates
the deposit of a deleterious substance (tailings) into a TIA which is also
included in the Project “as scoped” by the RAs.
·
The
tailings in question are produced by physical activities carried on the mine
site. The metals will come from milling operations and from precipitation runoff
and ground water draining through the north waste dump and across and through
the exposed rock in the open pit walls.
[287] Second, given
that the vast majority of the analysis of the Federal Court of Appeal in
TrueNorth focused on section 15 of the CEAA, I find that it is of limited
applicability to a case, such as this one, where an analysis of section 21 as
it now reads since the coming into force of Bill C-9 amendments, is of central
importance to the resolution of the issues raised by the Applicant. Upon a
careful reading of the Federal Court of Appeal decision, I note that it does
not once reference the former section 21 expressly in its reasons, although at
paragraphs 23 and 24 of the same cited above, it dismisses the argument made by
the appellants that the projects listed on the CSL must be subject to an EA
under section 5 of the CEAA.
[288] Third, and
perhaps most significantly, although the TrueNorth decision was rendered by
this Court in September, 2004, it was issued in consideration of the former
section 21, which did not refer to the “proposed scope” of a project. As
aforementioned, the CEAA was amended in October, 2003. All parties agree and I
support their view that only the new version of the CEAA applies in this
situation. Even in the decision of this Court in TrueNorth, I do not find
that former section 21 is rigorously scrutinized. Indeed, former section 21
seems to refer to the project as “listed” on the CSL and not to the project as
“scoped” under section 15. I, therefore, do not believe I am bound by the
TrueNorth decision to the extent that it was deciding issues outside the
particular context of sections 5 and 15.
[289] It is
worthwhile to briefly highlight a few of the differences between the former and
the amended versions of section 21 in order to emphasize why I am of the view
that the TrueNorth decision is of limited applicability to the case at bar.
Firstly, while the former section 21 of the CEAA did not make public
consultation mandatory, the current version does. Furthermore, it is clear that
the language of “proposed scope”, as added to the new section 21, mandates that
public consultation must take place prior to the actual scoping decision.
Finally, under the new CEAA, once a “project” that has been proposed is set out
in the CSL, the environmental assessment must be carried out by means of a
comprehensive study.
[290] Accordingly, I am of the opinion that
the TrueNorth decision of the Federal Court of Appeal remains the law with
respect to a scoping decision made pursuant section 15, if such an EA were
commenced prior to October, 2003. However, I am not of the view that it applies
to assessments commenced after October 2003 pursuant to section 21 of the CEAA.
[291] Therefore, I do not view
the discretion to scope a project under section 15 of the CEAA as the
"full discretion" alleged by the Respondents. Instead, the RAs are
bound procedurally by the requirements of new section 21 of the CEAA,
such that if the project proposed by a proponent is on the comprehensive study
list, there is a duty to consult the public, assuming that there is a section 5
trigger. After public consultations, the scoping exercise shall set the
parameters for the comprehensive study and provide a rationale for the design
of the studies which may be required, on a case-by-case basis.
[292] It is not entirely clear to
the Court why, once it had been determined the Project, as described by the
RCDC, was included in the CSL, the decision was subsequently made to downgrade
the extent of the assessment required to that of a screening. To this effect,
the only affiant to submit an affidavit on behalf of the Crown was an
individual who was employed by DFO as the acting manager of the Major Projects
Review Unit for the Pacific Region from February to August 2005.
[293] This affiant was only
involved in the Project for approximately six months out of an approximately
twenty-four month environmental assessment, and interestingly, was not involved
in the Project during the time in question when the re-tracking decision of
December 2004 was made. Nevertheless, according to the cross-examination of the
affiant on his affidavit, he was aware the Project would no longer be addressed
as a comprehensive study within the initial weeks of his tenure as acting
manager.
[294] The Project
is currently based on the mill production rate of 30 000 tonnes of ore per day
for sale to the export market, over a projected mine life of 25 years. I do not
need to rest my decision on the fact that the re-scoping of the Project has all
the characteristics of a capricious and arbitrary decision which was taken for
an improper purpose. It is sufficient to declare that DFO correctly determined
in the initial tracking decision of May 2004 that the Project would require a
comprehensive study level review based on a proposed ore production capacity of
up to 50 000 tonnes/day which exceeds the threshold of 600 tonnes/day threshold
under item 16(c) of the CSL. In view of this conclusion, I do not need to
determine whether the proposed construction, decommissioning or abandonment of
the Red Chris porphyry copper-gold mine also falls under item 16(a) of the CSL
as it is a metal mine, other than a gold mine, with an ore production capacity
of 3 000 tonnes or more per day.
[295] Therefore, in
sidestepping statutory requisites mentioned in section 21 of the CEAA as
amended in 2003, in the guise of a decision to re-scope the Project, the RAs
acted beyond the ambit of their statutory powers. Thus, in my opinion the
RAs committed a reviewable error, which error culminated in the communication
of the Course of Action Decision, by deciding to forego the public consultation
process that the Project was statutorily mandated to undergo under section 13
of the CEAA. This is not to suggest that the RAs do not have the discretion to
amend the scope of projects. To the contrary, such a ruling would be absurd,
given the language of section 15(1) which clearly imparts discretion to the
responsible authority. Further, such a ruling would violate the case law (see section
C. Case law, above) which emphasizes that section 15 of the CEAA grants RAs wide
latitude to scope projects in the manner they deem appropriate on a
case-by-case basis.
[296] The consequences of
downgrading the Project from a comprehensive study to a screening were known
and understood by the RAs at all relevant times. According to the evidence on
record, the RAs were well aware that environmental groups, including the
Applicant, would be unhappy with the re-tracking decision. Likewise, the RAs
understood that the minister of the Environment would no longer have any
decision-making power with respect to the Project and that, as a consequence of
the decision to re-track the Project, the general public would not have the
opportunity to submit comments with respect to the proposed scope of the
Project, the factors proposed to be considered in its assessment, the proposed
scope of those factors and the ability of a comprehensive study to address
issues relating to the Project.
[297] Setting aside
the Course of Action Decision will therefore endorse a fundamental purpose of
the CEAA, which premises that public participation is meant to improve the
quality and influence the outcome of an EA. Public consultation on the
parameters mentioned in section 21 of the CEAA as it now reads since the Bill
C-9 amendments, undoubtedly improves the EA and decision-making process.
[298] I must take
into account the fact that there was no public consultation whatsoever by the
RAs prior to the taking of the Course of Action Decision with respect to the
draft screening report. While I recognize that the public was invited to make
comments in the 65 day period mentioned in the Provincial Notice, this
concerned exclusively the provincial EA process. Again, considering the
particular and very unusual circumstances of this case which have been set out
in great detail above (IV – Factual Background), I find that judicial
intervention is necessary and in the public interest.
[299] In Friends
of Oldman River Society, above, by the time the application was heard, the
dam at issue was 40% completed. By the time the appeal got to the Supreme
Court, the dam was almost entirely completed. Despite these facts, the Supreme
Court rejected the respondents’ arguments that granting prerogative relief
would be futile.
[300] The facts in
the case at bar are more favourable to relief, as construction has not started
on the Project. A comprehensive study will involve public participation,
additional section 16 considerations, and mandatory follow-up, and thus cannot
be said to be futile.
IX – CONCLUSION
[301] Having
considered the particular circumstances of this case, the conduct of the
parties and the representations made by counsel, I am satisfied that relief
should be granted in the exercise of the Court’s remedial powers under section
18 and 18.1 of the FCA.
[302] Accordingly,
the present application shall be allowed and an order be made by the Court:
a) declaring
that DFO correctly determined in the initial tracking decision of May 2004 that
the Project would require a comprehensive study level review based on a
proposed ore production capacity of up to 50 000 tonnes/day which exceeds the
threshold of 600 tonnes/day threshold under item 16(c) of the CSL. Therefore,
in sidestepping statutory requisites mentioned in section 21 of the CEAA as
amended in 2003, in the guise of a decision to re-scope the Project, the RAs
acted beyond the ambit of their statutory powers;
b) quashing
and setting aside the Course of Action Decision;
c) declaring
that the RAs are under a legal duty pursuant to subsection 21(1) of the CEAA as
amended in 2003, to ensure public consultation with respect to the proposed
scope of the Project, the factors proposed to be considered in its assessment,
the proposed scope of those factors and the ability of a comprehensive study to
address issues relating to the Project;
d) prohibiting
the exercise of any powers under paragraph 5(1)(d) or subsection 5(2) of the
CEAA that would permit the Project to be carried out in whole or in part until
a course of action has been taken by the RAs in accordance with section 37 of
the CEAA, in performance of their duty to conduct an EA of the Project under
section 13 of the CEAA;
e) reserving
the Court’s full discretionary power over the amount and allocation of costs
and the determination of by whom they are to be paid, pending receipt and
consideration of parties’ submissions with respect to costs.
[303] Moreover, unless
the Court directs otherwise, submissions with respect to costs shall be made in
writing and addressed to the registrar of the Court within the following
timeframe:
a) Applicant’s
submissions: October 9, 2007;
b) Respondent’s
submissions: October 23, 2007; and
c) Applicant’s
reply: October 30, 2007.
ORDER
THIS COURT ORDERS AND
DECLARES that
1. the present
application is allowed;
2. DFO
correctly determined in the initial tracking decision of May 2004 that the Project
would require a comprehensive study level review based on a proposed ore
production capacity of up to 50 000 tonnes/day which exceeds the threshold of
600 tonnes/day threshold under item 16(c) of the CSL. Therefore, in sidestepping
statutory requisites mentioned in section 21 of the CEAA as amended in 2003, in
the guise of a decision to re-scope the Project, the RAs acted beyond the ambit
of their statutory powers;;
3. the
Course of Action Decision is quashed and set aside;
4. the
RAs are under a legal duty pursuant to subsection 21(1) of the CEAA as amended
in 2003, to ensure public consultation with respect to the proposed scope of
the Project, the factors proposed to be considered in its assessment, the
proposed scope of those factors and the ability of a comprehensive study to
address issues relating to the Project;
5. the
exercise of any powers under paragraph 5(1)(d) or subsection 5(2) of the CEAA
that would permit the Project to be carried out in whole or in part is
prohibited until a course of action has been taken by the RAs in accordance
with section 37 of the CEAA, in performance of their duty to conduct an EA of
the Project under section 13 of the CEAA;
6. the
Court is reserving full discretionary power over the amount and allocation of
costs and the determination of by whom they are to be paid, pending receipt and
consideration of parties’ submissions with respect to costs.
7. Unless
the Court directs otherwise, submissions with respect to costs shall be made in
writing and addressed to the registrar of the Court within the following
timeframe:
a) Applicant’s
submissions: October 9, 2007;
b) Respondent’s
submissions: October 23, 2007; and
c) Applicant’s
reply: October 30, 2007.
“Luc Martineau”
APPENDIX “A”
Canadian Environmental
Assessment Act,
S.C. 1992, c. 32, as amended
Definitions
2. (1) In this Act,
[…]
"comprehensive study" means
an environmental assessment that is conducted pursuant to sections 21 and
21.1, and that includes a consideration of the factors required to be
considered pursuant to subsections 16(1) and (2); ;
"comprehensive study list"
means a list of all projects or classes of projects that have been prescribed
pursuant to regulations made under paragraph 59(d);
[…]
"exclusion list" means a list
of projects or classes of projects that have been exempted from the
requirement to conduct an assessment by regulations made under paragraph
59(c) or ( c.1);
"federal authority" means
(a) a Minister of the Crown in right of
Canada,
(b) an agency of the Government of
Canada, a parent Crown corporation, as defined in subsection 83(1) of the
Financial Administration Act, or any other body established by or pursuant to
an Act of Parliament that is ultimately accountable through a Minister of the
Crown in right of Canada to Parliament for the conduct of its affairs,
(c) any department or departmental
corporation set out in Schedule I or II to the Financial Administration Act,
and
(d) any other body that is prescribed
pursuant to regulations made under paragraph 59(e),
but does not include the Executive
Council of — or a minister, department, agency or body of the government of —
Yukon, the Northwest Territories or Nunavut, a council of the band within the
meaning of the Indian Act, Export Development Canada, the Canada Pension Plan
Investment Board, a Crown corporation that is a wholly-owned subsidiary, as
defined in subsection 83(1) of the Financial Administration Act, The Hamilton
Harbour Commissioners as constituted pursuant to The Hamilton Harbour
Commissioners’ Act, a harbour commission established pursuant to the Harbour
Commissions Act, a not-for-profit corporation that enters into an agreement
under subsection 80(5) of the Canada Marine Act or a port authority established
under that Act;
[…]
"interested party" means, in
respect of an environmental assessment, any person or body having an interest
in the outcome of the environmental assessment for a purpose that is neither
frivolous nor vexatious;
[…]
"project" means
(a) in relation to a physical work, any
proposed construction, operation, modification, decommissioning, abandonment
or other undertaking in relation to that physical work, or
(b) any proposed physical activity not
relating to a physical work that is prescribed or is within a class of
physical activities that is prescribed pursuant to regulations made under
paragraph 59(b);
"responsible authority" , in
relation to a project, means a federal authority that is required pursuant to
subsection 11(1) to ensure that an environmental assessment of the project is
conducted;
[…]
"responsible authority"
«autorité responsable »
"responsible authority" , in
relation to a project, means a federal authority that is required pursuant to
subsection 11(1) to ensure that an environmental assessment of the project is
conducted;
"screening" means an
environmental assessment that is conducted pursuant to section 18 and that
includes a consideration of the factors set out in subsection 16(1);
"screening report" means a
report that summarizes the results of a screening;
[…]
Purposes
4. (1) The purposes of this Act are
( a) to ensure that projects are
considered in a careful and precautionary manner before federal authorities
take action in connection with them, in order to ensure that such projects do
not cause significant adverse environmental effects;
( b) to encourage responsible
authorities to take actions that promote sustainable development and thereby
achieve or maintain a healthy environment and a healthy economy;
( b.1) to ensure that responsible
authorities carry out their responsibilities in a coordinated manner with a
view to eliminating unnecessary duplication in the environmental assessment
process;
( b.2) to promote cooperation and
coordinated action between federal and provincial governments with respect to
environmental assessment processes for projects;
( b.3) to promote communication and
cooperation between responsible authorities and Aboriginal peoples with
respect to environmental assessment;
( c) to ensure that projects that are
to be carried out in Canada or on federal lands do not cause significant
adverse environmental effects outside the jurisdictions in which the projects
are carried out; and
( d) to ensure that there be opportunities
for timely and meaningful public participation throughout the environmental
assessment process.
Projects requiring environmental
assessment
5. (1) An environmental assessment of a
project is required before a federal authority exercises one of the following
powers or performs one of the following duties or functions in respect of a
project, namely, where a federal authority
(a) is the proponent of the project and
does any act or thing that commits the federal authority to carrying out the
project in whole or in part;
(b) makes or authorizes payments or
provides a guarantee for a loan or any other form of financial assistance to
the proponent for the purpose of enabling the project to be carried out in
whole or in part, except where the financial assistance is in the form of any
reduction, avoidance, deferral, removal, refund, remission or other form of
relief from the payment of any tax, duty or impost imposed under any Act of
Parliament, unless that financial assistance is provided for the purpose of
enabling an individual project specifically named in the Act, regulation or
order that provides the relief to be carried out;
(c) has the administration of federal
lands and sells, leases or otherwise disposes of those lands or any interests
in those lands, or transfers the administration and control of those lands or
interests to Her Majesty in right of a province, for the purpose of enabling
the project to be carried out in whole or in part; or
(d) under a provision prescribed
pursuant to paragraph 59(f), issues a permit or licence, grants an approval
or takes any other action for the purpose of enabling the project to be
carried out in whole or in part.
Projects requiring approval of Governor
in Council
(2) Notwithstanding any other provision
of this Act,
(a) an environmental assessment of a
project is required before the Governor in Council, under a provision
prescribed pursuant to regulations made under paragraph 59(g), issues a
permit or licence, grants an approval or takes any other action for the
purpose of enabling the project to be carried out in whole or in part; and
(b) the federal authority that,
directly or through a Minister of the Crown in right of Canada, recommends
that the Governor in Council take an action referred to in paragraph (a) in
relation to that project
(i) shall ensure that an environmental
assessment of the project is conducted as early as is practicable in the
planning stages of the project and before irrevocable decisions are made,
(ii) is, for the purposes of this Act
and the regulations, except subsection 11(2) and sections 20 and 37, the
responsible authority in relation to the project,
(iii) shall consider the applicable
reports and comments referred to in sections 20 and 37, and
(iv) where applicable, shall perform
the duties of the responsible authority in relation to the project under
section 38 as if it were the responsible authority in relation to the project
for the purposes of paragraphs 20(1)(a) and 37(1)(a).
[…]
Action suspended
13. Where a project is described in the
comprehensive study list or is referred to a mediator or a review panel,
notwithstanding any other Act of Parliament, no power, duty or function
conferred by or under that Act or any regulation made thereunder shall be
exercised or performed that would permit the project to be carried out in
whole or in part unless an environmental assessment of the project has been
completed and a course of action has been taken in relation to the project in
accordance with paragraph 37(1)(a).
Environmental assessment process
14. The environmental assessment
process includes, where applicable,
(a) a screening or comprehensive study
and the preparation of a screening report or a comprehensive study report;
(b) a mediation or assessment by a
review panel as provided in section 29 and the preparation of a report; and
(c) the design and implementation of a
follow-up program.
Scope of project
15. (1) The scope of the project in
relation to which an environmental assessment is to be conducted shall be
determined by
(a) the responsible authority; or
(b) where the project is referred to a
mediator or a review panel, the Minister, after consulting with the
responsible authority.
Same assessment for related projects
(2) For the purposes of conducting an
environmental assessment in respect of two or more projects,
(a) the responsible authority, or
(b) where at least one of the projects
is referred to a mediator or a review panel, the Minister, after consulting
with the responsible authority,
may determine that the projects are so
closely related that they can be considered to form a single project.
All proposed undertakings to be
considered
(3) Where a project is in relation to a
physical work, an environmental assessment shall be conducted in respect of
every construction, operation, modification, decommissioning, abandonment or
other undertaking in relation to that physical work that is proposed by the
proponent or that is, in the opinion of
(a) the responsible authority, or
(b) where the project is referred to a
mediator or a review panel, the Minister, after consulting with the
responsible authority,
likely to be carried out in relation to
that physical work.
Factors to be considered
16. (1) Every screening or
comprehensive study of a project and every mediation or assessment by a
review panel shall include a consideration of the following factors:
(a) the environmental effects of the
project, including the environmental effects of malfunctions or accidents
that may occur in connection with the project and any cumulative
environmental effects that are likely to result from the project in
combination with other projects or activities that have been or will be
carried out;
(b) the significance of the effects
referred to in paragraph (a);
(c) comments from the public that are
received in accordance with this Act and the regulations;
(d) measures that are technically and
economically feasible and that would mitigate any significant adverse
environmental effects of the project; and
(e) any other matter relevant to the
screening, comprehensive study, mediation or assessment by a review panel,
such as the need for the project and alternatives to the project, that the
responsible authority or, except in the case of a screening, the Minister after
consulting with the responsible authority, may require to be considered.
Additional factors
(2) In addition to the factors set out
in subsection (1), every comprehensive study of a project and every mediation
or assessment by a review panel shall include a consideration of the
following factors:
(a) the purpose of the project;
(b) alternative means of carrying out
the project that are technically and economically feasible and the
environmental effects of any such alternative means;
(c) the need for, and the requirements
of, any follow-up program in respect of the project; and
(d) the capacity of renewable resources
that are likely to be significantly affected by the project to meet the needs
of the present and those of the future.
Determination of factors
(3) The scope of the factors to be
taken into consideration pursuant to paragraphs (1)(a), (b) and (d) and
(2)(b), (c) and (d) shall be determined
(a) by the responsible authority; or
(b) where a project is referred to a
mediator or a review panel, by the Minister, after consulting the responsible
authority, when fixing the terms of reference of the mediation or review
panel.
Factors not included
(4) An environmental assessment of a
project is not required to include a consideration of the environmental
effects that could result from carrying out the project in response to a
national emergency for which special temporary measures are taken under the
Emergencies Act.
Community knowledge and aboriginal
traditional knowledge
16.1 Community knowledge and aboriginal
traditional knowledge may be considered in conducting an environmental
assessment.
Regional studies
16.2 The results of a study of the
environmental effects of possible future projects in a region, in which a
federal authority participates, outside the scope of this Act, with other
jurisdictions referred to in paragraph 12(5)(a), (c) or (d), may be taken
into account in conducting an environmental assessment of a project in the
region, particularly in considering any cumulative environmental effects that
are likely to result from the project in combination with other projects or
activities that have been or will be carried out.
Publication of determinations
16.3 The responsible authority shall
document and make available to the public, pursuant to subsection 55(1), its
determinations pursuant to section 20.
[…]
Screening
18. (1) Where a project is not
described in the comprehensive study list or the exclusion list made under
paragraph 59( c), the responsible authority shall ensure that
( a) a screening of the project is
conducted; and
( b) a screening report is prepared.
Source of information
(2) Any available information may be
used in conducting the screening of a project, but where a responsible
authority is of the opinion that the information available is not adequate to
enable it to take a course of action pursuant to subsection 20(1), it shall
ensure that any studies and information that it considers necessary for that
purpose are undertaken or collected.
Public participation
(3) Where the responsible authority is
of the opinion that public participation in the screening of a project is
appropriate in the circumstances — or where required by regulation — the
responsible authority
( a) shall, before providing the public
with an opportunity to examine and comment on the screening report, include
in the Internet site a description of the scope of the project, the factors
to be taken into consideration in the screening and the scope of those
factors or an indication of how such a description may be obtained;
( b) shall give the public an
opportunity to examine and comment on the screening report and on any record
relating to the project that has been included in the Registry before taking
a course of action under section 20 and shall give adequate notice of that
opportunity; and
( c) may, at any stage of the screening
that it determines, give the public any other opportunity to participate.
Timing of public participation
(4) The responsible authority’s
discretion under subsection (3) with respect to the timing of public
participation is subject to a decision made by the federal environmental
assessment coordinator under paragraph 12.3( c).
[…]
Decision of responsible authority
following a screening
20. (1) The responsible authority shall
take one of the following courses of action in respect of a project after
taking into consideration the screening report and any comments filed
pursuant to subsection 18(3):
(a) subject to subparagraph (c)(iii),
where, taking into account the implementation of any mitigation measures that
the responsible authority considers appropriate, the project is not likely to
cause significant adverse environmental effects, the responsible authority
may exercise any power or perform any duty or function that would permit the
project to be carried out in whole or in part;
(b) where, taking into account the
implementation of any mitigation measures that the responsible authority
considers appropriate, the project is likely to cause significant adverse
environmental effects that cannot be justified in the circumstances, the
responsible authority shall not exercise any power or perform any duty or
function conferred on it by or under any Act of Parliament that would permit
the project to be carried out in whole or in part; or
(c) where
(i) it is uncertain whether the
project, taking into account the implementation of any mitigation measures
that the responsible authority considers appropriate, is likely to cause
significant adverse environmental effects,
(ii) the project, taking into account
the implementation of any mitigation measures that the responsible authority
considers appropriate, is likely to cause significant adverse environmental
effects and paragraph (b) does not apply, or
(iii) public concerns warrant a
reference to a mediator or a review panel,
the responsible authority shall refer
the project to the Minister for a referral to a mediator or a review panel in
accordance with section 29.
Mitigation measures — extent of authority
(1.1) Mitigation measures that may be
taken into account under subsection (1) by a responsible authority are not
limited to measures within the legislative authority of Parliament and
include
(a) any mitigation measures whose
implementation the responsible authority can ensure; and
(b) any other mitigation measures that
it is satisfied will be implemented by another person or body.
Responsible authority to ensure
implementation of mitigation measures
(2) When a responsible authority takes
a course of action referred to in paragraph (1)(a), it shall, with respect to
any mitigation measures it has taken into account and that are described in
paragraph (1.1)(a), ensure their implementation in any manner that it
considers necessary and, in doing so, it is not limited to its duties or
powers under any other Act of Parliament.
Assistance of other federal authority
(2.1) A federal authority shall provide
any assistance requested by a responsible authority in ensuring the
implementation of a mitigation measure on which the federal authority and the
responsible authority have agreed.
Prohibition of actions in furtherance
of project
(3) Where the responsible authority
takes a course of action pursuant to paragraph (1)(b) in relation to a
project, the responsible authority shall publish a notice of that course of
action in the Registry and, notwithstanding any other Act of Parliament, no
power, duty or function conferred by or under that Act or any regulation made
under it shall be exercised or performed that would permit that project to be
carried out in whole or in part.
Time for decision
(4) A responsible authority shall not
take any course of action under subsection (1) before the 15th day after the
inclusion on the Internet site of
(a) notice of the commencement of the
environmental assessment;
(b) a description of the scope of the
project; and
(c) where the responsible authority, in
accordance with subsection 18(3), gives the public an opportunity to
participate in the screening of a project, a description of the factors to be
taken into consideration in the environmental assessment and of the scope of
those factors or an indication of how such a description may be obtained.
Public consultation
21. (1) Where a project is described in
the comprehensive study list, the responsible authority shall ensure public
consultation with respect to the proposed scope of the project for the
purposes of the environmental assessment, the factors proposed to be
considered in its assessment, the proposed scope of those factors and the
ability of the comprehensive study to address issues relating to the project.
Report and recommendation
(2) After the public consultation, as
soon as it is of the opinion that it has sufficient information to do so, the
responsible authority shall
(a) report to the Minister regarding
(i) the scope of the project, the
factors to be considered in its assessment and the scope of those factors,
(ii) public concerns in relation to the
project,
(iii) the potential of the project to
cause adverse environmental effects, and
(iv) the ability of the comprehensive
study to address issues relating to the project; and
(b) recommend to the Minister to
continue with the environmental assessment by means of a comprehensive study,
or to refer the project to a mediator or review panel in accordance with
section 29.
Minister’s decision
21.1 (1) The Minister, taking into
account the things with regard to which the responsible authority must report
under paragraph 21(2)(a) and the recommendation of the responsible authority
under paragraph 21(2)(b), shall, as the Minister considers appropriate,
(a) refer the project to the
responsible authority so that it may continue the comprehensive study and
ensure that a comprehensive study report is prepared and provided to the
Minister and to the Agency; or
(b) refer the project to a mediator or
review panel in accordance with section 29.
Decision final
(2) Despite any other provision of this
Act, if the Minister refers the project to a responsible authority under
paragraph (1)(a), it may not be referred to a mediator or review panel in
accordance with section 29.
Public participation
21.2 Where a project has been referred
to a responsible authority under paragraph 21.1(1)(a), the responsible authority
shall ensure that the public is provided with an opportunity, in addition to
those provided under subsection 21(1) and section 22, to participate in the
comprehensive study, subject to a decision with respect to the timing of the
participation made by the federal environmental assessment coordinator under
paragraph 12.3(c).
[…]
Referral by Minister
28. (1) Where at any time the Minister
is of the opinion that
(a) a project for which an
environmental assessment may be required under section 5, taking into account
the implementation of any appropriate mitigation measures, may cause
significant adverse environmental effects, or
(b) public concerns warrant a reference
to a mediator or a review panel,
the Minister may, after offering to
consult with the jurisdiction, within the meaning of subsection 12(5), where
the project is to be carried out and after consulting with the responsible
authority or, where there is no responsible authority in relation to the
project, the appropriate federal authority, refer the project to a mediator
or a review panel in accordance with section 29.
[…]
Decision of responsible authority
37. (1) Subject to subsections (1.1) to
(1.3), the responsible authority shall take one of the following courses of
action in respect of a project after taking into consideration the report
submitted by a mediator or a review panel or, in the case of a project
referred back to the responsible authority pursuant to subsection 23(1), the
comprehensive study report:
( a) where, taking into account the
implementation of any mitigation measures that the responsible authority
considers appropriate,
(i) the project is not likely to cause
significant adverse environmental effects, or
(ii) the project is likely to cause
significant adverse environmental effects that can be justified in the
circumstances,
the responsible authority may exercise
any power or perform any duty or function that would permit the project to be
carried out in whole or in part; or
( b) where, taking into account the
implementation of any mitigation measures that the responsible authority
considers appropriate, the project is likely to cause significant adverse
environmental effects that cannot be justified in the circumstances, the
responsible authority shall not exercise any power or perform any duty or
function conferred on it by or under any Act of Parliament that would permit
the project to be carried out in whole or in part.
[…]
Powers to facilitate environmental
assessments
58. (1) For the purposes of this Act,
the Minister may
[…]
(i) make regulations prescribing any
project or class of projects for which a comprehensive study is required
where the Minister is satisfied that the project or any project within that
class is likely to have significant adverse environmental effects.
Regulations
59. The Governor in Council may make
regulations
(a) respecting the procedures and
requirements of, and the time periods relating to, environmental assessment
and follow-up programs, including the conduct of assessments by review panels
established pursuant to section 40 and the timing of taking a course of
action pursuant to section 20 or 37 where two or more federal authorities are
likely to exercise a power or perform a duty or function referred to in
section 5 with respect to the same project;
[…]
( b) prescribing, for the purpose of
the definition “project” in subsection 2(1), any physical activity or class
of physical activities;
(c) exempting any projects or classes
of projects from the requirement to conduct an assessment under this Act that
(i) in the opinion of the Governor in
Council, ought not to be assessed for reasons of national security,
(ii) in the case of projects in
relation to physical works, in the opinion of the Governor in Council, have insignificant
environmental effects, or
(iii) have a total cost below a
prescribed amount and meet prescribed environmental conditions;
[…]
(f)
prescribing, for the purposes of paragraph 5(1)(d), the provisions of any Act
of Parliament or any instrument made under an Act of Parliament;
(
g) prescribing the provisions of any Act of Parliament or any regulation made
pursuant to any such Act that confer powers, duties or functions on the
Governor in Council, the exercise or performance of which require an
environmental assessment under subsection 5(2);
|
Définitions
2. (1) Les définitions qui suivent
s’appliquent à la présente loi.
[…]
«étude
approfondie » Évaluation environnementale d’un projet effectuée aux termes
des articles 21 et 21.1 et qui comprend la prise en compte des éléments
énumérés aux paragraphes 16(1) et (2).
«liste
d’étude approfondie » Liste des projets ou catégories de projets désignés par
règlement aux termes de l’alinéa 59 d).
[…]
«liste d’exclusion »
«liste
d’exclusion » Liste des projets ou catégories de projets soustraits à
l’évaluation par règlement pris en vertu des alinéas 59c) ou c.1).
«autorité
fédérale »
a)
Ministre fédéral;
b)
agence fédérale, société d’État mère au sens du paragraphe 83(1) de la Loi
sur la gestion des finances publiques ou autre organisme constitué sous le
régime d’une loi fédérale et tenu de rendre compte au Parlement de ses
activités par l’intermédiaire d’un ministre fédéral;
c)
ministère ou établissement public mentionnés aux annexes I et II de la Loi
sur la gestion des finances publiques;
d)
tout autre organisme désigné par les règlements d’application de l’alinéa
59e).
Sont
exclus le conseil exécutif et les ministres du Yukon, des Territoires du
Nord-Ouest et du Nunavut, ainsi que les ministères et les organismes de
l’administration publique de ces territoires, tout conseil de bande au sens
donné à « conseil de la bande » dans la Loi sur les Indiens, Exportation et
développement Canada, l’Office d’investissement du régime de pensions du
Canada, les sociétés d’État qui sont des filiales à cent pour cent au sens du
paragraphe 83(1) de la Loi sur la gestion des finances publiques, les
commissions portuaires constituées par la Loi sur les commissions portuaires,
les commissaires nommés en vertu de la Loi des commissaires du havre de
Hamilton, la société sans but lucratif qui a conclu une entente en vertu du
paragraphe 80(5) de la Loi maritime du Canada et les administrations
portuaires constituées sous le régime de cette loi.
[…]
«partie
intéressée » Toute personne ou tout organisme pour qui le résultat de
l’évaluation environnementale revêt un intérêt qui ne soit ni frivole ni
vexatoire.
[…]
«projet
» Réalisation — y compris l’exploitation, la modification, la désaffectation
ou la fermeture — d’un ouvrage ou proposition d’exercice d’une activité
concrète, non liée à un ouvrage, désignée par règlement ou faisant partie
d’une catégorie d’activités concrètes désignée par règlement aux termes de
l’alinéa 59 b).
[…]
«autorité responsable »
"responsible authority"
«autorité responsable » L’autorité
fédérale qui, en conformité avec le paragraphe 11(1), est tenue de veiller à
ce qu’il soit procédé à l’évaluation environnementale d’un projet.
«examen préalable » Évaluation environnementale
qui, à la fois :
a) est effectuée de la façon prévue à
l’article 18;
b) prend en compte les éléments
énumérés au paragraphe 16(1).
«rapport d’examen préalable » Rapport
des résultats d’un examen préalable.
[…]
Objet
4. (1) La présente loi a pour objet :
a) de veiller à ce que les projets
soient étudiés avec soin et prudence avant que les autorités fédérales
prennent des mesures à leur égard, afin qu’ils n’entraînent pas d’effets
environnementaux négatifs importants;
b) d’inciter ces autorités à favoriser
un développement durable propice à la salubrité de l’environnement et à la
santé de l’économie;
b.1) de faire en sorte que les
autorités responsables s’acquittent de leurs obligations afin d’éviter tout
double emploi dans le processus d’évaluation environnementale;
b.2) de promouvoir la collaboration des
gouvernements fédéral et provinciaux, et la coordination de leurs activités,
dans le cadre du processus d’évaluation environnementale de projets;
b.3) de promouvoir la communication et
la collaboration entre les autorités responsables et les peuples autochtones
en matière d’évaluation environnementale;
c) de faire en sorte que les éventuels
effets environnementaux négatifs importants des projets devant être réalisés
dans les limites du Canada ou du territoire domanial ne débordent pas ces
limites;
d) de veiller à ce que le public ait la
possibilité de participer de façon significative et en temps opportun au
processus de l’évaluation environnementale.
Projets visés
5. (1) L’évaluation environnementale
d’un projet est effectuée avant l’exercice d’une des attributions suivantes :
a) une autorité fédérale en est le
promoteur et le met en oeuvre en tout ou en partie;
b) une autorité fédérale accorde à un
promoteur en vue de l’aider à mettre en oeuvre le projet en tout ou en partie
un financement, une garantie d’emprunt ou toute autre aide financière, sauf
si l’aide financière est accordée sous forme d’allègement — notamment
réduction, évitement, report, remboursement, annulation ou remise — d’une
taxe ou d’un impôt qui est prévu sous le régime d’une loi fédérale, à moins
que cette aide soit accordée en vue de permettre la mise en oeuvre d’un
projet particulier spécifié nommément dans la loi, le règlement ou le décret
prévoyant l’allègement;
c) une autorité fédérale administre le
territoire domanial et en autorise la cession, notamment par vente ou cession
à bail, ou celle de tout droit foncier relatif à celui-ci ou en transfère à
Sa Majesté du chef d’une province l’administration et le contrôle, en vue de
la mise en oeuvre du projet en tout ou en partie;
d) une autorité fédérale, aux termes
d’une disposition prévue par règlement pris en vertu de l’alinéa 59f),
délivre un permis ou une licence, donne toute autorisation ou prend toute
mesure en vue de permettre la mise en oeuvre du projet en tout ou en partie.
Projets nécessitant l’approbation du
gouverneur en conseil
(2) Par dérogation à toute autre
disposition de la présente loi :
a) l’évaluation environnementale d’un
projet est obligatoire, avant que le gouverneur en conseil, en vertu d’une
disposition désignée par règlement aux termes de l’alinéa 59g), prenne une
mesure, notamment délivre un permis ou une licence ou accorde une
approbation, autorisant la réalisation du projet en tout ou en partie;
b) l’autorité fédérale qui, directement
ou par l’intermédiaire d’un ministre fédéral, recommande au gouverneur en
conseil la prise d’une mesure visée à l’alinéa a) à l’égard du projet :
(i) est tenue de veiller à ce que
l’évaluation environnementale du projet soit effectuée le plus tôt possible
au stade de la planification de celui-ci, avant la prise d’une décision
irrévocable,
(ii) est l’autorité responsable à
l’égard du projet pour l’application de la présente loi — à l’exception du
paragraphe 11(2) et des articles 20 et 37 — et de ses règlements,
(iii) est tenue de prendre en compte
les rapports et observations pertinents visés aux articles 20 et 37,
(iv) le cas échéant, est tenue
d’exercer à l’égard du projet les attributions de l’autorité responsable
prévues à l’article 38 comme si celle-ci était l’autorité responsable à
l’égard du projet pour l’application des alinéas 20(1)a) et 37(1)a).
[…]
Suspension de la prise de décision
13. Dans le cas où un projet appartient
à une catégorie visée dans la liste d’étude approfondie, ou si un examen par
une commission ou un médiateur doit être effectué, malgré toute autre loi
fédérale, l’exercice d’une attribution qui est prévu par cette loi ou ses
règlements pour mettre en oeuvre le projet en tout ou en partie est
subordonné à l’achèvement de l’évaluation environnementale de celui-ci et à
la prise d’une décision à son égard aux termes de l’alinéa 37(1)a).
Processus d’évaluation environnementale
14. Le processus d’évaluation environnementale
d’un projet comporte, selon le cas :
a) un examen préalable ou une étude
approfondie et l’établissement d’un rapport d’examen préalable ou d’un
rapport d’étude approfondie;
b) une médiation ou un examen par une
commission prévu à l’article 29 et l’établissement d’un rapport;
c) l’élaboration et l’application d’un
programme de suivi.
Détermination de la portée du projet
15. (1) L’autorité responsable ou, dans
le cas où le projet est renvoyé à la médiation ou à l’examen par une
commission, le ministre, après consultation de l’autorité responsable,
détermine la portée du projet à l’égard duquel l’évaluation environnementale
doit être effectuée.
Pluralité de projets
(2) Dans le cadre d’une évaluation
environnementale de deux ou plusieurs projets, l’autorité responsable ou, au
moins un des projets est renvoyé à la médiation ou à l’examen par une
commission, le ministre, après consultation de l’autorité responsable, peut
décider que deux projets sont liés assez étroitement pour être considérés
comme un seul projet.
Projet lié à un ouvrage
(3) Est effectuée, dans l’un ou l’autre
des cas suivants, l’évaluation environnementale de toute opération —
construction, exploitation, modification, désaffectation, fermeture ou autre
— constituant un projet lié à un ouvrage :
a) l’opération est proposée par le
promoteur;
b) l’autorité responsable ou, dans le
cadre d’une médiation ou de l’examen par une commission et après consultation
de cette autorité, le ministre estime l’opération susceptible d’être réalisée
en liaison avec l’ouvrage.
Éléments à examiner
16. (1) L’examen préalable, l’étude
approfondie, la médiation ou l’examen par une commission d’un projet portent
notamment sur les éléments suivants :
a) les effets environnementaux du projet,
y compris ceux causés par les accidents ou défaillances pouvant en résulter,
et les effets cumulatifs que sa réalisation, combinée à l’existence d’autres
ouvrages ou à la réalisation d’autres projets ou activités, est susceptible
de causer à l’environnement;
b) l’importance des effets visés à
l’alinéa a);
c) les observations du public à cet
égard, reçues conformément à la présente loi et aux règlements;
d) les mesures d’atténuation
réalisables, sur les plans technique et économique, des effets environnementaux
importants du projet;
e) tout autre élément utile à l’examen
préalable, à l’étude approfondie, à la médiation ou à l’examen par une
commission, notamment la nécessité du projet et ses solutions de rechange, —
dont l’autorité responsable ou, sauf dans le cas d’un examen préalable, le
ministre, après consultation de celle-ci, peut exiger la prise en compte.
Éléments supplémentaires
(2) L’étude approfondie d’un projet et
l’évaluation environnementale qui fait l’objet d’une médiation ou d’un examen
par une commission portent également sur les éléments suivants :
a) les raisons d’être du projet;
b) les solutions de rechange
réalisables sur les plans technique et économique, et leurs effets
environnementaux;
c) la nécessité d’un programme de suivi
du projet, ainsi que ses modalités;
d) la capacité des ressources
renouvelables, risquant d’être touchées de façon importante par le projet, de
répondre aux besoins du présent et à ceux des générations futures.
Obligations
(3) L’évaluation de la portée des
éléments visés aux alinéas (1)a), b) et d) et (2)b), c) et d) incombe :
a) à l’autorité responsable;
b) au ministre, après consultation de
l’autorité responsable, lors de la détermination du mandat du médiateur ou de
la commission d’examen.
Situations de crise nationale
(4) L’évaluation environnementale d’un
projet n’a pas à porter sur les effets environnementaux que sa réalisation
peut entraîner en réaction à des situations de crise nationale pour
lesquelles des mesures d’intervention sont prises aux termes de la Loi sur
les mesures d’urgence.
Connaissances des collectivités et
connaissances traditionnelles autochtones
16.1 Les connaissances des
collectivités et les connaissances traditionnelles autochtones peuvent être
prises en compte pour l’évaluation environnementale d’un projet.
Études régionales
16.2 Les résultats d’une étude des
effets environnementaux de projets éventuels dans une région, faite hors du
champ d’application de la présente loi et à laquelle une autorité fédérale a
collaboré avec des instances, au sens des alinéas 12(5)a), c) ou d), peuvent
être pris en compte dans l’évaluation environnementale d’un projet à réaliser
dans cette région, notamment dans l’évaluation des effets cumulatifs que la
réalisation du projet, combinée à celle d’autres projets ou activités déjà
complétés ou à venir, est susceptible de produire sur l’environnement.
Publication des décisions
16.3 L’autorité responsable consigne et
rend accessibles au public, conformément au paragraphe 55(1), les décisions
qu’elle prend aux termes de l’article 20.
[…]
Examen préalable
18. (1) Dans le cas où le projet n’est
pas visé dans la liste d’étude approfondie ou dans la liste d’exclusion
établie par règlement pris en vertu de l’alinéa 59c), l’autorité responsable
veille :
a) à ce qu’en soit effectué l’examen
préalable;
b) à ce que soit établi un rapport
d’examen préalable.
Information
(2) Dans le cadre de l’examen préalable
qu’elle effectue, l’autorité responsable peut utiliser tous les renseignements
disponibles; toutefois, si elle est d’avis qu’il n’existe pas suffisamment de
renseignements pour lui permettre de prendre une décision en vertu du
paragraphe 20(1), elle fait procéder aux études et à la collecte de
renseignements nécessaires à cette fin.
Participation du public
(3) Dans les cas où elle estime que la
participation du public à l’examen préalable est indiquée ou dans les cas
prévus par règlement, l’autorité responsable :
a) verse au site Internet, avant de
donner au public la possibilité d’examiner le rapport d’examen préalable et
de faire des observations à son égard, une description de la portée du
projet, des éléments à prendre en compte dans le cadre de l’examen préalable
et de la portée de ceux-ci ou une indication de la façon d’obtenir copie de
cette description;
b) avant de prendre sa décision aux
termes de l’article 20, donne au public la possibilité d’examiner le rapport
d’examen préalable et tout document relatif au projet et de faire ses
observations à leur égard et un avis suffisant de cette possibilité;
c) peut donner au public la possibilité
de prendre part à toute étape de l’examen préalable qu’elle choisit.
Moment de la participation
(4) L’exercice du pouvoir
discrétionnaire dont dispose l’autorité responsable, dans le cadre du
paragraphe (3), de déterminer à quel moment peut se faire la participation du
public est assujetti à toute décision pouvant être prise par le coordonnateur
fédéral de l’évaluation environnementale en vertu de l’alinéa 12.3c).
[…]
Décision de l’autorité responsable
20. (1) L’autorité responsable prend
l’une des mesures suivantes, après avoir pris en compte le rapport d’examen
préalable et les observations reçues aux termes du paragraphe 18(3) :
a) sous réserve du sous-alinéa c)(iii),
si la réalisation du projet n’est pas susceptible, compte tenu de
l’application des mesures d’atténuation qu’elle estime indiquées, d’entraîner
des effets environnementaux négatifs importants, exercer ses attributions
afin de permettre la mise en œuvre totale ou partielle du projet;
b) si, compte tenu de l’application des
mesures d’atténuation qu’elle estime indiquées, la réalisation du projet est
susceptible d’entraîner des effets environnementaux négatifs importants qui
ne peuvent être justifiés dans les circonstances, ne pas exercer les
attributions qui lui sont conférées sous le régime d’une loi fédérale et qui
pourraient lui permettre la mise en oeuvre du projet en tout ou en partie;
c) s’adresser au ministre pour une
médiation ou un examen par une commission prévu à l’article 29 :
(i) s’il n’est pas clair, compte tenu
de l’application des mesures d’atténuation qu’elle estime indiquées, que la
réalisation du projet soit susceptible d’entraîner des effets
environnementaux négatifs importants,
(ii) si la réalisation du projet,
compte tenu de l’application de mesures d’atténuation qu’elle estime
indiquées, est susceptible d’entraîner des effets environnementaux négatifs
importants et si l’alinéa b) ne s’applique pas,
(iii) si les préoccupations du public
le justifient.
Mesures d’atténuation — étendue des
pouvoirs
(1.1) Les mesures d’atténuation que
l’autorité responsable peut prendre en compte dans le cadre du paragraphe (1)
ne se limitent pas à celles qui relèvent de la compétence législative du
Parlement; elles comprennent :
a) les mesures d’atténuation dont elle
peut assurer l’application;
b) toute autre mesure d’atténuation
dont elle est convaincue qu’elle sera appliquée par une autre personne ou un
autre organisme.
Application des mesures d’atténuation
(2) Si elle prend une décision dans le
cadre de l’alinéa (1)a), l’autorité responsable veille à l’application des
mesures d’atténuation qu’elle a prises en compte et qui sont visées à
l’alinéa (1.1)a) de la façon qu’elle estime nécessaire, même si aucune autre
loi fédérale ne lui confère de tels pouvoirs d’application.
Appui à l’autorité responsable
(2.1) Il incombe à l’autorité fédérale
qui convient avec l’autorité responsable de mesures d’atténuation d’appuyer
celle-ci, sur demande, dans l’application de ces mesures.
Interdiction de mise en œuvre
(3) L’autorité responsable qui prend la
décision visée à l’alinéa (1)b) à l’égard d’un projet est tenue de publier un
avis de cette décision dans le registre, et aucune attribution conférée sous
le régime de toute autre loi fédérale ou de ses règlements ne peut être
exercée de façon à permettre la mise en œuvre, en tout ou en partie, du
projet.
Versement préalable de documents
(4) L’autorité responsable ne peut
prendre une décision dans le cadre du paragraphe (1) avant le quinzième jour
suivant le versement au site Internet des documents suivants :
a) l’avis du début de l’évaluation
environnementale;
b) la description de la portée du
projet;
c) dans le cas où l’autorité responsable
donne, au titre du paragraphe 18(3), la possibilité au public de participer à
l’examen préalable, la description des éléments à prendre en compte dans le
cadre de l’évaluation environnementale et de la portée de ceux-ci ou une
indication de la façon d’obtenir copie de cette description.
Consultation
21. (1) Dans le cas où le projet est
visé dans la liste d’étude approfondie, l’autorité responsable veille à la
tenue d’une consultation publique sur les propositions relatives à la portée
du projet en matière d’évaluation environnementale, aux éléments à prendre en
compte dans le cadre de l’évaluation et à la portée de ces éléments ainsi que
sur la question de savoir si l’étude approfondie permet l’examen des
questions soulevées par le projet.
Rapport et recommandation
(2) L’autorité responsable, dès qu’elle
estime disposer de suffisamment de renseignements et après avoir tenu la
consultation publique :
a) fait rapport au ministre de la
portée du projet, des éléments à prendre en compte dans le cadre de
l’évaluation, de la portée de ceux-ci, des préoccupations du public, de la
possibilité d’effets environnementaux négatifs et de la question de savoir si
l’étude approfondie permet l’examen des questions soulevées par le projet;
b) lui recommande de poursuivre
l’évaluation environnementale par étude approfondie ou de la renvoyer à un
médiateur ou à une commission conformément à l’article 29.
Décision du ministre
21.1 (1) Le ministre, prenant en compte
tous les éléments qui doivent lui être signalés dans le cadre de l’alinéa
21(2)a) et les recommandations de l’autorité responsable et selon ce qu’il
estime indiqué dans les circonstances :
a) renvoie le projet à l’autorité
responsable pour qu’elle poursuive l’étude approfondie et qu’elle veille à ce
qu’un rapport de cette étude lui soit présenté, de même qu’à l’Agence;
b) renvoie le projet à la médiation ou
à l’examen par une commission conformément à l’article 29.
Caractère définitif de la décision
(2) Malgré toute autre disposition de
la présente loi, le projet que le ministre renvoie à l’autorité responsable
au titre de l’alinéa (1)a) ne peut faire l’objet d’une médiation ou d’un
examen par une commission conformément à l’article 29.
Participation du public à l’étude
approfondie
21.2 En plus des consultations
publiques prévues au paragraphe 21(1) et à l’article 22, l’autorité
responsable à laquelle le projet est renvoyé en vertu de l’alinéa 21.1(1)a)
est tenue de veiller à ce que le public ait la possibilité de prendre part à
l’étude approfondie. Elle est toutefois assujettie à toute décision
éventuellement prise par le coordonnateur fédéral de l’évaluation
environnementale en vertu de l’alinéa 12.3c) quant au moment de la
participation.
[…]
Idem
28. (1) À tout moment, le ministre,
après avoir offert de consulter l’instance, au sens du paragraphe 12(5),
responsable du lieu où le projet doit être réalisé et après consultation de
l’autorité responsable, ou, à défaut, de toute autorité fédérale compétente,
s’il estime soit qu’un projet assujetti à l’évaluation environnementale aux
termes de l’article 5 peut, compte tenu de l’application des mesures
d’atténuation indiquées, entraîner des effets environnementaux négatifs
importants, soit que les préoccupations du public le justifient, peut faire procéder
à une médiation ou à un examen par une commission conformément à l’article
29.
[…]
Autorité responsable
37. (1) Sous réserve des paragraphes
(1.1) à (1.3), l’autorité responsable, après avoir pris en compte le rapport
du médiateur ou de la commission ou, si le projet lui est renvoyé aux termes
du paragraphe 23(1), le rapport d’étude approfondie, prend l’une des
décisions suivantes :
a) si, compte tenu de l’application des
mesures d’atténuation qu’elle estime indiquées, la réalisation du projet
n’est pas susceptible d’entraîner des effets environnementaux négatifs
importants ou est susceptible d’en entraîner qui sont justifiables dans les
circonstances, exercer ses attributions afin de permettre la mise en œuvre
totale ou partielle du projet;
b) si, compte tenu de l’application des
mesures d’atténuation qu’elle estime indiquées, la réalisation du projet est
susceptible d’entraîner des effets environnementaux qui ne sont pas
justifiables dans les circonstances, ne pas exercer les attributions qui lui
sont conférées sous le régime d’une loi fédérale et qui pourraient permettre
la mise en oeuvre du projet en tout ou en partie.
[…]
Évaluation
environnementale
58.
(1) Pour l’application de la présente loi, le ministre peut :
[…]
i)
prendre des règlements désignant des projets ou des catégories de projets
pour lesquels une étude approfondie est obligatoire, s’il est convaincu que
ceux-ci sont susceptibles d’entraîner des effets environnementaux négatifs
importants.
Règlements
59. Le gouverneur en conseil peut, par
règlement :
a) régir les procédures, les délais
applicables et les exigences relatives à l’évaluation environnementale et au
programme de suivi, notamment le moment de la prise de mesures au titre des
articles 20 ou 37 quand plusieurs autorités fédérales sont susceptibles
d’exercer les attributions visées à l’article 5, ainsi que les évaluations
effectuées par une commission aux termes de l’article 40;
[…]
b) désigner une activité concrète ou
une catégorie d’activités concrètes pour l’application de la définition de «
projet » au paragraphe 2(1);
c) soustraire à l’évaluation exigée par
la présente loi des projets ou des catégories de projets :
(i) dont, à son avis, l’évaluation ne
serait pas indiquée pour des raisons de sécurité nationale,
(ii) qui sont liés à un ouvrage et
dont, à son avis, les effets environnementaux ne sont pas importants,
(iii) qui remplissent les conditions de
nature environnementale prévues par règlement et dont le coût total est
en-deçà du seuil réglementaire
[…]
f) déterminer, pour l’application de
l’alinéa 5(1)d), des dispositions de toute loi fédérale ou de textes pris
sous son régime;
g) désigner les dispositions
législatives ou réglementaires fédérales conférant des attributions au
gouverneur en conseil pour l’exercice desquelles le paragraphe 5(2) exige une
évaluation environnementale;
|
Section 21 of the Canadian Environmental
Assessment Act, S.C. 1992, c. 32 before it was amended in 2003
[…]
Comprehensive study
21. Where a project is described in the
comprehensive study list, the responsible authority shall
(a) ensure that a comprehensive study
is conducted, and a comprehensive study report is prepared and provided to
the Minister and the Agency; or
(b) refer the project to the Minister
for a referral to a mediator or a review panel in accordance with section 29.
[…]
|
[…]
Étude approfondie
21. Dans le cas où le projet est visé
dans la liste d'étude approfondie, l'autorité responsable a le choix:
a) de veiller à ce que soit effectuée
une étude approfondie et à ce que soit présenté au ministre et à l'Agence un
rapport de cette étude;
b) de s'adresser au ministre afin qu'il
fasse effectuer, aux termes de l'article 29, une médiation ou un examen par
une commission.
[…]
|
Explosives Act, R.S.C. 1985, c. E-17, as
amended
[…]
Licences and permits
7.
(1) The Minister may issue
(a)
licences for factories and magazines;
[…]
|
[…]
Délivrance
7. (1) Le ministre peut délivrer :
a) des licences pour des fabriques et poudrières;
[…]
|
Fisheries Act, R.S.C. 1985, c.F-14, as
amended
[…]
Harmful alteration, etc., of fish habitat
35.
(1) No person shall carry on any work or undertaking that results in the
harmful alteration, disruption or destruction of fish habitat.
Alteration, etc., authorized
(2)
No person contravenes subsection (1) by causing the alteration, disruption or
destruction of fish habitat by any means or under any conditions authorized
by the Minister or under regulations made by the Governor in Council under
this Act.
Deposit of deleterious substance prohibited
36.
(3) Subject to subsection (4), no person shall deposit or permit the deposit
of a deleterious substance of any type in water frequented by fish or in any
place under any conditions where the deleterious substance or any other
deleterious substance that results from the deposit of the deleterious
substance may enter any such water.
[…]
|
[…]
Détérioration de l’habitat du poisson,
etc.
35. (1) Il est interdit d’exploiter des
ouvrages ou entreprises entraînant la détérioration, la destruction ou la
perturbation de l’habitat du poisson.
Exception
(2) Le paragraphe (1) ne s’applique pas
aux personnes qui détériorent, détruisent ou perturbent l’habitat du poisson
avec des moyens ou dans des circonstances autorisés par le ministre ou
conformes aux règlements pris par le gouverneur en conseil en application de
la présente loi.
Dépôt de substances nocives prohibé
36. (3) Sous réserve du paragraphe (4),
il est interdit d’immerger ou de rejeter une substance nocive — ou d’en
permettre l’immersion ou le rejet — dans des eaux où vivent des poissons, ou
en quelque autre lieu si le risque existe que la substance ou toute autre
substance nocive provenant de son immersion ou rejet pénètre dans ces eaux.
[…]
|
Species at Risk Act, S.C. 2002, c. 29, as amended
[…]
Notification of Minister
79.
(1) Every person who is required by or under an Act of Parliament to ensure
that an assessment of the environmental effects of a project is conducted must,
without delay, notify the competent minister or ministers in writing of the
project if it is likely to affect a listed wildlife species or its critical
habitat.
[…]
Definitions
79.
(3) The definitions in this subsection apply in this section.
[…]
"project"
«projet
»
"project"
means a project as defined in subsection 2(1) of the Canadian Environmental
Assessment Act.
[…]
|
[…]
Notification du ministre
79. (1) Toute personne tenue, sous le
régime d’une loi fédérale, de veiller à ce qu’il soit procédé à l’évaluation
des effets environnementaux d’un projet notifie sans tarder à tout ministre
compétent tout projet susceptible de toucher une espèce sauvage inscrite ou
son habitat essentiel.
[…]
Définitions
79. (3) Les définitions qui suivent s’appliquent
au présent article.
[…]
«projet »
"project"
«projet » S’entend au sens du
paragraphe 2(1) de la Loi canadienne sur l’évaluation environnementale.
[…]
|
REGULATIONS
Comprehensive Study List Regulations,
SOR/94-638, as amended
[…]
General
3.
The projects and classes of projects that are set out in the schedule are
prescribed projects and classes of projects for which a comprehensive study
is required.
[…]
SCHEDULE
(Section 3)
[…]
PART V
MINERALS AND MINERAL PROCESSING
16.
The proposed construction, decommissioning or abandonment of
(a)
a metal mine, other than a gold mine, with an ore production capacity of 3
000 t/d or more;
(b)
a metal mill with an ore input capacity of 4 000 t/d or more;
(c)
a gold mine, other than a placer mine, with an ore production capacity of 600
t/d or more;
(d)
a coal mine with a coal production capacity of 3 000 t/d or more; or
(e)
a potash mine with a potassium chloride production capacity of 1 000 000 t/a
or more.
|
[…]
Dispositions Générales
3. Les projets et les catégories de
projets figurant à l’annexe sont ceux pour lesquels une étude approfondie est
obligatoire.
[…]
ANNEXE
(article 3)
[…]
PARTIE V
MINERAIS ET TRAITEMENT DES MINERAIS
16. Projet de construction, de désaffectation
ou de fermeture :
a) d’une mine métallifère, autre qu’une
mine d’or, d’une capacité de production de minerai de 3 000 t/d ou plus;
b) d’une usine métallurgique d’une
capacité d’admission de minerai de 4 000 t/d ou plus;
c) d’une mine d’or, autre qu’un placer,
d’une capacité de production de minerai de 600 t/d ou plus;
d) d’une mine de charbon d’une capacité
de production de charbon de 3 000 t/d ou plus;
e) d’une mine de potasse d’une capacité
de production de chlorure de potassium de 1 000 000 t/a ou plus.
|
Inclusion List Regulations, SOR/94-637, as amended
[…]
SCHEDULE
(Section 3)
[…]
PART VII
FISHERIES
42.
The destruction of fish by any means other than fishing, where the
destruction requires the authorization of the Minister of Fisheries and
Oceans under section 32 of the Fisheries Act or authorization under
regulations made by the Governor in Council under that Act.
43.
The harmful alteration, disruption or destruction of fish habitat by means of
physical activities carried out in a water body, including dredge or fill
operations, that require the authorization of the Minister of Fisheries and
Oceans under subsection 35(2) of the Fisheries Act or authorization under
regulations made by the Governor in Council under that Act.
44.
The harmful alteration, disruption or destruction of fish habitat by means of
draining or altering the water levels of a water body that require the
authorization of the Minister of Fisheries and Oceans under subsection 35(2)
of the Fisheries Act or authorization under regulations made by the Governor
in Council under that Act.
45.
The harmful alteration, disruption or destruction of fish habitat by means of
erosion control measures adjacent to a water body that require the
authorization of the Minister of Fisheries and Oceans under subsection 35(2)
of the Fisheries Act or authorization under regulations made by the Governor
in Council under that Act.
46.
The harmful alteration, disruption or destruction of fish habitat by means of
the removal of vegetation in or adjacent to a water body that requires the
authorization of the Minister of Fisheries and Oceans under subsection 35(2)
of the Fisheries Act or authorization under regulations made by the Governor
in Council under that Act.
46.1
The harmful alteration, disruption or destruction of fish habitat by means of
physical activities intended to establish or modify more than 500 m of
continuous natural shoreline and that require the authorization of the
Minister of Fisheries and Oceans under subsection 35(2) of the Fisheries Act
or authorization under regulations made by the Governor in Council under that
Act.
47.
The deposit of a deleterious substance that requires authorization under
regulations made by the Governor in Council pursuant to subsection 36(5) of
the Fisheries Act.
[…]
|
[…]
ANNEXE
(article 3)
[…]
PARTIE VII
PÊCHES
42. La destruction de poissons par
d’autres moyens que la pêche, qui nécessite l’autorisation émanant du
ministre des Pêches et des Océans prévue à l’article 32 de la Loi sur les
pêches ou l’autorisation prévue dans tout règlement pris par le gouverneur en
conseil en application de cette loi.
43. La détérioration, la destruction ou
la perturbation de l’habitat du poisson par des activités concrètes exercées
dans un plan d’eau, notamment des opérations de dragage ou de remblayage, qui
nécessitent l’autorisation du ministre des Pêches et des Océans prévue au
paragraphe 35(2) de la Loi sur les pêches ou l’autorisation prévue dans tout
règlement pris par le gouverneur en conseil en application de cette loi.
44. La détérioration, la destruction ou
la perturbation de l’habitat du poisson par le vidage d’un plan d’eau ou la
modification de son niveau d’eau, qui nécessitent l’autorisation du ministre
des Pêches et des Océans prévue au paragraphe 35(2) de la Loi sur les pêches
ou l’autorisation prévue dans tout règlement pris par le gouverneur en
conseil en application de cette loi.
45. La détérioration, la destruction ou
la perturbation de l’habitat du poisson par des mesures de contrôle de
l’érosion le long d’un plan d’eau, qui nécessitent l’autorisation du ministre
des Pêches et des Océans prévue au paragraphe 35(2) de la Loi sur les pêches
ou l’autorisation prévue dans tout règlement pris par le gouverneur en
conseil en application de cette loi.
46. La détérioration, la destruction ou
la perturbation de l’habitat du poisson par l’enlèvement de la végétation
dans un plan d’eau ou le long de celui-ci, qui nécessitent l’autorisation du
ministre des Pêches et des Océans prévue au paragraphe 35(2) de la Loi sur
les pêches ou l’autorisation prévue dans tout règlement pris par le
gouverneur en conseil en application de cette loi.
46.1 La détérioration, la perturbation
ou la destruction de l’habitat du poisson par suite d’activités concrètes
visant à mettre en valeur ou à modifier plus de 500 m d’un rivage naturel
continu, qui nécessitent l’autorisation du ministre des Pêches et des Océans
prévue au paragraphe 35(2) de la Loi sur les pêches ou l’autorisation prévue dans
tout règlement pris par le gouverneur en conseil en application de cette loi.
47. L’immersion ou le rejet d’une
substance nocive qui nécessitent l’autorisation prévue dans tout règlement
pris par le gouverneur en conseil en application du paragraphe 36(5) de la
Loi sur les pêches.
[…]
|
Metal Mining Effluent Regulations, SOR/2002-222, as amended
Interpretation
1.
(1) The following definitions apply in these Regulations.
"Act"
means the Fisheries Act. ( Loi )
[…]
"deleterious
substance" means a substance prescribed under section 3 except as
otherwise prescribed by these Regulations. ( substance nocive )
"effluent"
means an effluent — mine water effluent, milling facility effluent, tailings
impoundment area effluent, treatment pond effluent, treatment facility
effluent other than effluent from a sewage treatment facility, seepage and
surface drainage — that contains a deleterious substance. ( effluent )
[…]
Application
2.
(1) These Regulations apply in respect of mines and recognized closed mines
that
(a)
at any time after these Regulations are registered, exceed an effluent flow
rate of 50 m3 per day, based on effluent deposited from all the final
discharge points of the mine; and
(b)
deposit a deleterious substance in any water or place referred to in
subsection 36(3) of the Act.
[…]
Authority to Deposit
4.
(1) Subject to subsection (2), the owner or operator of a mine may deposit,
or permit the deposit of, an effluent that contains a deleterious substance
in any water or place referred to in subsection 36(3) of the Act if a
transitional authorization permits the deposit or if
(a)
the concentration of the deleterious substance in the effluent does not
exceed the authorized limits set out in Schedule 4;
(b)
the pH of the effluent is equal to or greater than 6.0 but is not greater
than 9.5; and
(c)
the deleterious substance is not an acutely lethal effluent.
(2)
The authority in subsection (1) is conditional
(a)
in the case of a transitional authorization that permits the deposit, on the
owner or operator complying with section 36; and
(b)
in the other case, on the owner or operator complying with sections 6 to 27.
Authority to Deposit in Tailings Impoundment Areas
5.
(1) Despite section 4, the owner or operator of a mine may deposit or permit
the deposit of waste rock or an effluent that contains any concentration of a
deleterious substance and that is of any pH into a tailings impoundment area
that is either
(a)
a water or place set out in Schedule 2; or
(b)
a disposal area that is confined by anthropogenic or natural structures or by
both, other than a disposal area that is, or is part of, a natural water body
that is frequented by fish.
(2)
The authority in subsection (1) is conditional on the owner or operator
complying with sections 7 to 28.
(SOR/2006-239,
s. 2.)
Prohibition on Diluting Effluent
6.
The owner or operator of a mine shall not combine effluent with water or any
other effluent for the purpose of diluting effluent before it is deposited.
[…]
Compensation Plan
27.1
(1) The owner or operator of a mine shall submit to the Minister for approval
a compensation plan and obtain the Minister’s approval of that plan before
depositing a deleterious substance into a tailings impoundment area that is
added to Schedule 2 after the coming into force of this section.
(2)
The purpose of the compensation plan is to offset for the loss of fish
habitat resulting from the deposit of a deleterious substance into the
tailings impoundment area.
(3)
The compensation plan shall contain the following elements:
(a)
a description of the location of the tailings impoundment area and the fish
habitat affected by the deposit;
(b)
a quantitative impact assessment of the deposit on the fish habitat;
(c)
a description of the measures to be taken to offset the loss of fish habitat
caused by the deposit;
(d)
a description of the measures to be taken during the planning and
implementation of the compensation plan to mitigate any potential adverse effect
on the fish habitat that could result from the plan’s implementation;
(e)
a description of measures to be taken to monitor the plan’s implementation;
(f)
a description of the measures to be taken to verify the extent to which the
plan’s purpose has been achieved;
(g)
a description of the time schedule for the plan’s implementation, which time
schedule shall provide for achievement of the plan’s purpose within a
reasonable time; and
(h)
an estimate of the cost of implementing each element of the plan.
(4)
The owner or operator shall submit with the compensation plan an irrevocable
letter of credit to cover the plan’s implementation costs, which letter of
credit shall be payable upon demand on the declining balance of the
implementation costs.
(5)
The Minister shall approve the compensation plan if it meets the requirements
of subsections (2) and (3) and the owner or operator has complied with
subsection (4).
(6)
The owner or operator shall ensure that the compensation plan approved by the
Minister is implemented.
(7)
If the measures referred to in paragraph (3)(f) reveal that the compensation
plan’s purpose is not being achieved, the owner or operator shall inform the
Minister and, as soon as possible in the circumstances, identify and implement
all necessary remedial measures. (SOR/2006-239, s. 14.)
Deposits from Tailings Impoundment Areas
28.
(1) The owner or operator of a mine shall deposit effluent from a tailings
impoundment area only through a final discharge point that is monitored and
reported on in accordance with the requirements of these Regulations.
(2)
The owner or operator of a mine shall comply with section 6 and the
conditions prescribed in paragraphs 4(1)(a) to (c) for all effluent that
exits a tailing impoundment area.
|
Définitions et interprétation
1. (1) Les définitions qui suivent
s’appliquent au présent règlement.
«Loi» La Loi sur
les pêches. ( Act )
[…]
«substance nocive» Toute substance
désignée aux termes de l’article 3, sauf disposition contraire du présent
règlement. ( deleterious substance )
«effluent» Effluent — effluent d’eau de mine,
effluent d’installations de préparation du minerai, effluent de dépôts de
résidus miniers, effluent de bassins de traitement, effluent d’installations
de traitement, à l’exclusion de l’effluent d’installations de traitement
d’eaux résiduaires, eaux d’exfiltration et eaux de drainage superficiel — qui
contient une substance nocive. ( effluent )
[…]
Champ d’application
2. (1) Le présent règlement s’applique
aux mines et aux mines fermées reconnues qui présentent les caractéristiques
suivantes :
a) après l’enregistrement du présent
règlement, elles ont, à un moment quelconque, un débit d’effluent supérieur à
50 m3 par jour, déterminé d’après les rejets d’effluent à partir de tous
leurs points de rejet final;
b) elles rejettent une substance nocive
dans les eaux ou les lieux visés au paragraphe 36(3) de la Loi.
[…]
Rejet autorisé
4. (1) Sous réserve du paragraphe (2),
le propriétaire ou l’exploitant d’une mine peut rejeter — ou permettre que
soit rejeté — un effluent contenant des substances nocives dans les eaux ou
les lieux visés au paragraphe 36(3) de la Loi si une autorisation transitoire
le permet ou si les conditions suivantes sont réunies :
a) la concentration des substances
nocives dans l’effluent ne dépasse pas les limites permises prévues à
l’annexe 4;
b) le pH de l’effluent est égal ou
supérieur à 6,0 mais ne dépasse pas 9,5;
c) la substance nocive n’est pas un
effluent à létalité aiguë.
(2) Le propriétaire ou l’exploitant ne
peut se prévaloir du droit que lui confère le paragraphe (1) que s’il
satisfait aux exigences prévues :
a) à l’article 36, dans le cas où une
autorisation transitoire permet le rejet;
b) aux articles 6 à 27, dans l’autre
cas.
Autorisation de rejeter dans un dépôt
de résidus miniers
5. (1) Malgré l’article 4, le
propriétaire ou l’exploitant d’une mine peut rejeter — ou permettre que
soient rejetés — des stériles ou un effluent, quel que soit le pH de
l’effluent ou sa concentration en substances nocives, dans l’un ou l’autre
des dépôts de résidus miniers suivants :
a) les eaux et lieux mentionnés à
l’annexe 2;
b) toute aire de décharge circonscrite
par une formation naturelle ou un ouvrage artificiel, ou les deux, à
l’exclusion d’une aire de décharge qui est un plan d’eau naturel où vivent
des poissons ou qui en fait partie.
(2) Le propriétaire ou l’exploitant ne
peut se prévaloir du droit que lui confère le paragraphe (1) que s’il
satisfait aux exigences prévues aux articles 7 à 28.
(DORS/2006-239, art. 2.)
Interdiction de diluer
6. Il est interdit au propriétaire ou à
l’exploitant d’une mine de combiner un effluent avec de l’eau ou avec tout
autre effluent dans le but de le diluer avant son rejet.
[…]
Plan compensatoire
27.1 (1) Le propriétaire ou
l’exploitant d’une mine présente au ministre un plan compensatoire pour
approbation et doit obtenir celle-ci avant de rejeter des substances nocives
dans tout dépôt de résidus miniers qui est ajouté à l’annexe 2 après l’entrée
en vigueur du présent article.
(2) Le plan compensatoire a pour
objectif de contrebalancer la perte d’habitat du poisson consécutive au rejet
de substances nocives dans le dépôt de résidus miniers.
(3) Le plan compensatoire comporte des
dispositions portant sur les éléments suivants:
a) une description de l’emplacement du
dépôt de résidus miniers et de l’habitat du poisson atteint par le rejet de
substances nocives;
b) l’analyse quantitative de
l’incidence du rejet sur l’habitat du poisson;
c) les mesures visant à contrebalancer
la perte d’habitat du poisson;
d) les mesures envisagées durant la
planification et la mise en oeuvre du plan pour atténuer les effets
défavorables sur l’habitat du poisson qui pourraient résulter de la mise en
oeuvre du plan;
e) les mesures de surveillance de la
mise en oeuvre du plan;
f) les mécanismes visant à établir dans
quelle mesure les objectifs du plan ont été atteints;
g) le délai pour la mise en oeuvre du
plan, lequel délai permet l’atteinte des objectifs prévus dans un délai
raisonnable;
h) l’estimation du coût de mise en
oeuvre de chacun des éléments du plan.
(4) Le propriétaire ou l’exploitant
présente, avec le plan compensatoire, une lettre de crédit irrévocable
couvrant les coûts de mise en oeuvre du plan et payable sur demande à l’égard
du coût des éléments du plan qui n’ont pas été mis en oeuvre.
(5) Le ministre approuve le plan
compensatoire si les exigences des paragraphes (2) et (3) ont été remplies et
si le propriétaire ou l’exploitant s’est conformé aux exigences du paragraphe
(4).
(6) Le propriétaire ou l’exploitant
veille à ce que le plan compensatoire soit mis en oeuvre.
(7) Si les mécanismes visés à l’alinéa
(3)f) révèlent que les objectifs n’ont pas été atteints, le propriétaire ou
l’exploitant en informe le ministre et, le plus tôt possible dans les
circonstances, détermine et prend les mesures correctives nécessaires à
l’atteinte des objectifs. (DORS/2006-239, art. 14.)
Rejets à partir de dépôts de résidus
miniers
28. (1) Le propriétaire ou l’exploitant
d’une mine ne rejette l’effluent provenant d’un dépôt de résidus miniers qu’à
un point de rejet final faisant l’objet d’un suivi et de rapports
conformément aux exigences du présent règlement.
(2) Il remplit les conditions prévues
aux alinéas 4(1)a) à c) et se conforme à l’article 6 lorsqu’il rejette un tel
effluent.
|