Date: 20100602
Docket: A-361-09
Citation: 2010 FCA 147
CORAM: NADON
J.A.
SHARLOW
J.A.
LAYDEN-STEVENSON
J.A.
BETWEEN:
CANADIAN
NATIONAL RAILWAY COMPANY
Appellant
and
NORTHGATE TERMINALS LTD.,
WESTRAN PORTSIDE TERMINAL LIMITED and
CANADIAN TRANSPORTATION AGENCY
Respondents
REASONS FOR JUDGMENT
SHARLOW J.A.
[1]
Northgate
Terminals Ltd. (“Northgate”) operates an export terminal in North
Vancouver,
British Columbia. The terminal is serviced by Canadian National Railway Company
(“CN”). In 2008, Northgate complained to the Canadian Transportation Agency (the
“Agency”) pursuant to subsection 116(1) of the Canada Transportation Act,
S.C. 1996, c. 10 (the “CTA”), that CN was in breach of its service
obligations. In Decision No. 166-R-2009, the Agency concluded that Northgate’s complaint
was well founded and ordered a remedy. CN sought and obtained leave to appeal
that decision. For the reasons that follow, I would dismiss the appeal with
costs.
Facts
[2]
Northgate's
customers are producers of forest products in northern British Columbia. They contract
with CN for the transportation of pulp, paper, lumber, and panel to Northgate’s
terminal, and they are responsible for the payment of applicable rail freight
tariffs and demurrage charges. CN delivers the products to the unloading track
at the Northgate terminal, where they are transloaded to trucks for delivery to
various export docks in the Vancouver area. Under normal conditions,
Northgate is capable of receiving 12 rail cars at its unloading track at any
one time. During exceptionally good weather conditions, Northgate may receive 14
rail cars at one time because an uncovered ramp accommodates two additional
rail cars.
[3]
Northgate
normally operates only on weekdays, unloading approximately 20 rail cars per
weekday, based on a delivery of 12 to 14 cars in the morning, and 6
to 10 rail cars in the afternoon. Using traffic data produced by CN, the Agency
verified the consistency of these traffic distribution patterns and determined
that during the period 2004-2008, 49 percent of the first daily deliveries
account for 12 or more rail cars while
83 percent of the second daily deliveries are composed of six rail cars or more.
[4]
CN
is the only provider of rail service to the Northgate terminal. Northgate
competes with a number of other terminals in the Vancouver area,
including a terminal operated by CN.
[5]
In
2008, CN reduced its level of service to terminal operators in the Greater
Vancouver area, including Northgate, from two deliveries (switches) per day
Monday through Friday to one delivery per day, but indicated that it would
provide additional service upon payment of the tariff under Item 13200 of CN
Tariff 9000, Optional Special Switch and Special Train Services. That service
reduction is the subject of Northgate’s complaint to the Agency. The complaint
was supported by an intervener, Westran Portside Terminal Limited, which
operates another terminal that it said was captive to CN.
[6]
CN
submitted to the Agency that some terminal operators affected by the service
reduction expanded their in-plant trackage or increased their operations from 5
to 7 days per week to accommodate the change. Northgate provided evidence that:
(1) it had examined
the possibility of expanding trackage at its facility but concluded that it
would not be physically possible or economically feasible; (2) if it increased
its operations from 5 to 7 days per week, its labour costs would increase significantly
but Northgate would realize no benefit because the docks and trucking companies
with which it dealt did not operate on weekends; and (3) if CN’s level of
service as reduced in 2009 were to remain in place and Northgate were required
to pay the amount required by Item 13200 of Tariff 9000 for the additional services
that Northgate would require, the increased cost to Northgate would exceed $450,000
per year.
[7]
The
Agency concluded that CN was in breach of its service obligations and ordered
CN to continue to provide Northgate with a second switch each weekday (Monday
through Friday) when requested. The Agency also ordered that the second switch
performed in a day resulting from an order placed by Northgate for no fewer
than 6 cars would be exempt from the application of Item 13200 of Tariff 9000. CN
and Northgate were ordered to work together to determine an appropriate time
schedule for the delivery of the cars.
Relevant provisions of
the Canada Transportation Act
[8]
Section
5 of the CTA states its objectives. It reads as follows:
5. It is declared that a competitive, economic and
efficient national transportation system that meets the highest practicable
safety and security standards and contributes to a sustainable environment
and makes the best use of all modes of transportation at the lowest total
cost is essential to serve the needs of its users, advance the well-being of
Canadians and enable competitiveness and economic growth in both urban and
rural areas throughout Canada. Those objectives are most likely to be
achieved when
(a) competition and market forces, both within and
among the various modes of transportation, are the prime agents in providing
viable and effective transportation services;
(b) regulation and
strategic public intervention are used to achieve economic, safety, security,
environmental or social outcomes that cannot be achieved satisfactorily by
competition and market forces and do not unduly favour, or reduce the
inherent advantages of, any particular mode of transportation;
(c) rates and conditions
do not constitute an undue obstacle to the movement of traffic within Canada or to the
export of goods from Canada;
(d) the transportation
system is accessible without undue obstacle to the mobility of persons,
including persons with disabilities; and
(e) governments and the
private sector work together for an integrated transportation system.
|
5. Il est déclaré qu’un système de transport national
compétitif et rentable qui respecte les plus hautes normes possibles de
sûreté et de sécurité, qui favorise un environnement durable et qui utilise
tous les modes de transport au mieux et au coût le plus bas possible est
essentiel à la satisfaction des besoins de ses usagers et au bien-être des
Canadiens et favorise la compétitivité et la croissance économique dans les
régions rurales et urbaines partout au Canada. Ces objectifs sont plus
susceptibles d’être atteints si :
a) la concurrence et les
forces du marché, au sein des divers modes de transport et entre eux, sont
les principaux facteurs en jeu dans la prestation de services de transport
viables et efficaces;
b) la réglementation et
les mesures publiques stratégiques sont utilisées pour l’obtention de
résultats de nature économique, environnementale ou sociale ou de résultats
dans le domaine de la sûreté et de la sécurité que la concurrence et les
forces du marché ne permettent pas d’atteindre de manière satisfaisante, sans
pour autant favoriser indûment un mode de transport donné ou en réduire les
avantages inhérents;
c) les prix et modalités
ne constituent pas un obstacle abusif au trafic à l’intérieur du Canada ou à
l’exportation des marchandises du Canada;
d) le système de
transport est accessible sans obstacle abusif à la circulation des personnes,
y compris les personnes ayant une déficience;
e) les secteurs public
et privé travaillent ensemble pour le maintien d’un système de transport
intégré.
|
[9]
Sections
113 to 115 of the CTA set out the service obligations of a railway
company. Only section 113 is relevant to this appeal. It reads as follows:
113. (1) A railway company shall, according to its powers,
in respect of a railway owned or operated by it,
(a) furnish, at the point
of origin, at the point of junction of the railway with another railway, and
at all points of stopping established for that purpose, adequate and suitable
accommodation for the receiving and loading of all traffic offered for
carriage on the railway;
(b) furnish adequate and
suitable accommodation for the carriage, unloading and delivering of the
traffic;
(c) without delay, and
with due care and diligence, receive, carry and deliver the traffic;
(d) furnish and use all
proper appliances, accommodation and means necessary for receiving, loading,
carrying, unloading and delivering the traffic; and
(e) furnish any other
service incidental to transportation that is customary or usual in connection
with the business of a railway company.
(2) Traffic must be taken, carried to and from, and
delivered at the points referred to in paragraph (1)(a) on the payment of the
lawfully payable rate.
(3) Where a shipper provides rolling stock for the
carriage by the railway company of the shipper’s traffic, the company shall,
at the request of the shipper, establish specific reasonable compensation to
the shipper in a tariff for the provision of the rolling stock.
(4) A shipper and a
railway company may, by means of a confidential contract or other written
agreement, agree on the manner in which the obligations under this section
are to be fulfilled by the company.
|
113. (1) Chaque compagnie de chemin de fer, dans le cadre
de ses attributions, relativement au chemin de fer qui lui appartient ou
qu’elle exploite :
a) fournit, au point
d’origine de son chemin de fer et au point de raccordement avec d’autres, et
à tous les points d’arrêt établis à cette fin, des installations convenables
pour la réception et le chargement des marchandises à transporter par chemin
de fer;
b) fournit les
installations convenables pour le transport, le déchargement et la livraison
des marchandises;
c) reçoit, transporte et
livre ces marchandises sans délai et avec le soin et la diligence voulus;
d) fournit et utilise
tous les appareils, toutes les installations et tous les moyens nécessaires à
la réception, au chargement, au transport, au déchargement et à la livraison de
ces marchandises;
e) fournit les autres
services normalement liés à l’exploitation d’un service de transport par une
compagnie de chemin de fer.
(2) Les marchandises sont reçues, transportées et livrées
aux points visés à l’alinéa (1)a) sur paiement du prix licitement exigible
pour ces services.
(3) Dans les cas où l’expéditeur fournit du matériel
roulant pour le transport des marchandises par la compagnie, celle-ci prévoit
dans un tarif, sur demande de l’expéditeur, une compensation spécifique
raisonnable en faveur de celui-ci pour la fourniture de ce matériel.
(4) Un expéditeur et une compagnie
peuvent s’entendre, par contrat confidentiel ou autre accord écrit, sur les
moyens à prendre par la compagnie pour s’acquitter de ses obligations.
|
[10]
Section
116 of the CTA sets out two separate consequences of a railway company’s
failure to meet its service obligations. First, a complaint may be made to the Agency under
subsection 116(1). If the Agency’s investigation of the complaint discloses
that the complaint is warranted, the Agency may make a remedial order pursuant
to subsection 116(4). Second, subsection 116(5) creates a cause of action for
“every person aggrieved” by a railway company’s neglect or refusal to meet its
service obligations. Subsections 116(1), (4) and (5) read as follows:
116. (1) On receipt
of a complaint made by any person that a railway company is not fulfilling
any of its service obligations, the Agency shall
(a) conduct,
as expeditiously as possible, an investigation of the complaint that, in its
opinion, is warranted; and
(b) within one
hundred and twenty days after receipt of the complaint, determine whether the
company is fulfilling that obligation.
…
(4) If the Agency
determines that a company is not fulfilling any of its service obligations,
the Agency may
(a) order
that
(i) specific works be constructed or
carried out,
(ii) property be acquired,
(iii) cars, motive power or other
equipment be allotted, distributed, used or moved as specified by the Agency,
or
(iv) any specified steps, systems or
methods be taken or followed by the company;
(b) specify
in the order the maximum charges that may be made by the company in respect
of the matter so ordered;
(c)
order the company to fulfil that obligation in any manner and within any time
or during any period that the Agency deems expedient, having regard to all
proper interests, and specify the particulars of the obligation to be fulfilled;
(d) if the
service obligation is in respect of a grain-dependent branch line listed in
Schedule I, order the company to add to the plan it is required to prepare
under subsection 141(1) an indication that it intends to take steps to
discontinue operating the line; or
(e) if the
service obligation is in respect of a grain-dependent branch line listed in
Schedule I, order the company, on the terms and conditions that the Agency
considers appropriate, to grant to another railway company the right
(i) to run and operate its trains over
and on any portion of the line, and
(ii) in so far as necessary to provide
service to the line, to run and operate its trains over and on any portion of
any other portion of the railway of the company against which the order is
made but not to solicit traffic on that railway, to take possession of, use
or occupy any land belonging to that company and to use the whole or any
portion of that company’s right-of-way, tracks, terminals, stations or
station grounds.
(5) Every person
aggrieved by any neglect or refusal of a company to fulfil its service
obligations has, subject to this Act, an action for the neglect or refusal
against the company.
|
116. (1) Sur
réception d’une plainte selon laquelle une compagnie de chemin de fer ne
s’acquitte pas de ses obligations prévues par les articles 113 ou 114,
l’Office mène, aussi rapidement que possible, l’enquête qu’il estime indiquée
et décide, dans les cent vingt jours suivant la réception de la plainte, si
la compagnie s’acquitte de ses obligations.
[…]
(4) L’Office,
ayant décidé qu’une compagnie ne s’acquitte pas de ses obligations prévues par
les articles 113 ou 114, peut :
a) ordonner la
prise de l’une ou l’autre des mesures suivantes :
(i) la construction ou l’exécution
d’ouvrages spécifiques,
(ii) l’acquisition de biens,
(iii) l’attribution, la distribution,
l’usage ou le déplacement de wagons, de moteurs ou d’autre matériel selon ses
instructions,
(iv) la prise de mesures ou
l’application de systèmes ou de méthodes par la compagnie;
b) préciser le
prix maximal que la compagnie peut exiger pour mettre en oeuvre les mesures
qu’il impose;
c) ordonner à
la compagnie de remplir ses obligations selon les modalités de forme et de
temps qu’il estime indiquées, eu égard aux intérêts légitimes, et préciser
les détails de l’obligation à respecter;
d) en cas de
manquement à une obligation de service relative à un embranchement tributaire
du transport du grain mentionné à l’annexe I, ordonner à la compagnie
d’ajouter l’embranchement au plan visé au paragraphe 141(1) à titre de ligne
dont elle entend cesser l’exploitation;
e) en cas de
manquement à une obligation de service relative à un embranchement tributaire
du transport du grain mentionné à l’annexe I, ordonner à la compagnie, selon
les modalités qu’il estime indiquées, d’autoriser une autre compagnie :
(i) à faire circuler et à exploiter ses
trains sur toute partie de l’embranchement,
(ii) dans la mesure
nécessaire pour assurer le service sur l’embranchement, à faire circuler et à
exploiter ses trains sur toute autre partie du chemin de fer de la compagnie,
sans toutefois lui permettre d’offrir des services de transport sur cette
partie du chemin de fer, de même qu’à utiliser ou à occuper des terres lui
appartenant, ou à prendre possession de telles terres, ou à utiliser tout ou
partie de l’emprise, des rails, des têtes de lignes, des gares ou des terrains
lui appartenant.
(5) Quiconque
souffre préjudice de la négligence ou du refus d’une compagnie de s’acquitter
de ses obligations prévues par les articles 113 ou 114 possède, sous réserve
de la présente loi, un droit d’action contre la compagnie.
|
Standard of
review
[11]
CN
has raised five grounds of appeal. It is convenient to deal with the applicable
standard of review for each ground of appeal separately. At this stage it is
sufficient to refer to recent jurisprudence on the issue of the standard of
review in an appeal from a decision of the Agency.
[12]
Generally,
the standard of review on an appeal from a decision of the Agency is
reasonableness, even on a question of the interpretation of the Agency’s home
statute, the CTA: see Council of Canadians with Disabilities v. VIA
Rail Canada, [2007] 1 S.C.R. 650, 2007 SCC 15 (“VIA Rail”). A
decision is reasonable if it falls within a range of possible, acceptable
outcomes that are defensible in respect of the facts and law: see Dunsmuir
v. New
Brunswick, [2008] 1 S.C.R. 190, 2008 SCC 9, at paragraph 47
(“Dunsmuir”).
[13]
Following
VIA Rail, this Court has applied the reasonableness standard in a number
of appeals involving the interpretation of the CTA. See, for example, Canadian
Pacific Railway Co. v. Canada (Canadian Transportation Agency), [2009] 2
F.C.R. 253, 2008 FCA 42 (F.C.A.) (interpretation of “railway line”); Canadian
National Railway Co. v. Canada (Canadian Transportation Agency), 2008
FCA 363 (implementation of new statutory provisions relating to western grain
freight rates); Canadian
National Railway Co. v. Canada (Canadian Transportation Agency), 2010
FCA 65 (determination of revenue cap).
[14]
However,
the standard of correctness was applied in Canadian National Railway Co. v.
Canada (Canadian Transportation Agency), [2009] 1 F.C.R. 287, 2008 FCA 199,
in which the appellant challenged the decision of the Agency that it has the
implied authority to extend a certain statutory limitation period. That was
held to be a “true question of jurisdiction or vires” as explained in
paragraph 59 of Dunsmuir, which reads as follows:
¶59 …"Jurisdiction"
is intended in the narrow sense of whether or not the tribunal had the
authority to make the inquiry. In other words, true jurisdiction
questions arise where the tribunal must explicitly determine whether its
statutory grant of power gives it the authority to decide a particular matter. The
tribunal must interpret the grant of authority correctly or its action will
be found to be ultra vires or to constitute a
wrongful decline of jurisdiction ….
|
[15]
The
standard of correctness was also applied in Canadian National Railway Co. v.
Canada (Canadian
Transportation Agency), 2008 FCA 123. In that case the issue was
whether the Agency had properly understood and applied a point of statutory
interpretation that had been settled in a prior case, Canadian Pacific
Railway Co. v. Canada (Canadian Transportation Agency), [2003] 4 F.C. 558,
2003 FCA 271 (F.C.A.).
First issue:
Was Northgate entitled to complain?
[16]
The
first ground of appeal challenges the Agency’s conclusion that subsection
116(1) of the CTA, properly interpreted, gives the Agency the statutory
authority to investigate a complaint made by the operator of a terminal that is
directly affected by the decision of a railway company to reduce the level of
service to the terminal. That seems to me to be a question of vires as
explained in paragraph 59 of Dunsmuir, quoted above, reviewable on the
standard of correctness.
[17]
CN
argued before the Agency, and in this Court, that the Agency had no legal
authority under subsection 116(1) to investigate Northgate’s complaint because
Northgate was not the shipper of the traffic in issue or a party to the
contract of carriage. The
Agency rejected that argument because Northgate, as the operator of a terminal
designated by the shipper to receive the goods in issue, was directly
impacted by the decision of CN to reduce the level of service to the terminal. The
Agency explained this conclusion as follows in paragraphs 44 to 51 of its decision:
¶44. CN questions Northgate's
standing to file the present complaint on the ground that in the vast
majority of cases, Northgate is neither the shipper nor the consignee of the
traffic at issue. It is with the shipper that CN contracts for the provision
of transportation services and it is from the shipper that CN receives the
shipping instructions.
¶45. CN argues that in accordance
with the Agency's decision in the Scotia Terminals Ltd. v. CN case
(Decision No. 715-R-2000), the complaint of Northgate is not well founded
and, on this basis alone, should be dismissed as the facts of that case are
similar and equally applicable to the Northgate situation. According to CN,
its service obligations pursuant to the CTA do not extend to Northgate, a
terminal operator which exercises no control over the movement of the traffic
and with whom CN has no service contract.
¶46. Although the Agency
acknowledges that the facts of Scotia Terminals case are very similar to
those of the present complaint, namely that both applicants are terminal
operators, have no contractual arrangements with CN and exercise no control
over the subject traffic, there is a major distinction between the two cases
that is of primary importance. In the Scotia Terminals case, the terminal
operator complained in respect of traffic moved by CN and routed through
competitor terminals in the Port of Halifax. Scotia Terminals was in no way
part of the logistics chain of the subject traffic. There was no traffic
being shipped to Scotia Terminals. In the present complaint, although
Northgate has no contractual arrangement with CN for the transportation of
the traffic, it does receive the traffic moved on behalf of the shippers and,
as a receiver of traffic, is directly impacted by the level of service
provided by CN.
¶47. The Agency notes that the
Supreme Court of British Columbia has considered the level of service
obligations of a railway company in the context of a dispute in respect of
the appropriateness of charging demurrage to a party that is not a shipper in
Canadian National Railway Company v. Neptune Bulk Terminals (Canada) Ltd.
2006 BCSC 1073 (Neptune Terminals decision). In her Reasons for Judgment,
Madam Justice Wedge asserts that the level of service obligations of railway
companies, as set out in section 113 of the CTA, are only owed to parties
with whom the railway company has a contract for the carriage of goods. The
Agency is of the opinion that her reasoning is restricted to consideration of
obligations related to the transit of traffic, or the movement of goods, such
that, under subsection 113(2), a railway company is required to accept
traffic and move goods once the lawfully payable rate has been paid.
¶48. However, the obligations set
out in subsection 113(1) are broader and include the general obligation to
provide "adequate and suitable accommodation" for, among other
things, the delivery of traffic. The fact that the traffic is being delivered
to a facility owned by a person who is not a party to the contract for the
carriage of traffic does not relieve the railway company of its various
obligations under subsection 113(1) to provide accommodation for
traffic. Furthermore, the legislation specifically provides a statutory right
of complaint to "any person" and is not limited to "shippers",
or parties with whom the railway company has a contract for the carriage of
goods. This permits another party in the logistics chain, such as a
transloader, to complain that the railway company is not fulfilling its level
of service obligations with respect to the rail transportation of the traffic
of a shipper that is ultimately delivered to that transloader.
¶49. Subsection 113(1) may be
usefully contrasted with subsections 113(3) and (4) which explicitly provide
for specific level of service obligations owed by the railway company to
shippers. Furthermore, section 116 of the CTA provides for a complaint
made by any person regarding a railway company that is not fulfilling
any of its service obligations. Contrary to the broad language of subsection
116(1), other rail provisions in the CTA are limited by their terms to
provide relief to particular categories of persons. For example, subsection
120.1 specifically provides for complaints to be filed by shippers.
Similarly, subsection 152.1(1) specifically provides for applications by
public passenger service providers.
¶50. Clearly, Northgate falls
within the category of "any person" and, as such, has standing
under section 116 of the CTA to file a level of service complaint against CN.
Further, the use of "any person" in subsection 116(1) can be
contrasted with subsections 116(2) and (3), which specifically acknowledge
the possible existence of contracts between a shipper and the railway company
that may affect the outcome of an investigation into such a complaint.
¶51. Accordingly,
the Agency concludes that it has jurisdiction to consider Northgate's
complaint under section 116 of the CTA and will therefore determine
whether CN has failed to fulfill its common carrier obligations.
|
[18]
In
my view, the Agency’s interpretation is consistent with the language and
statutory context of subsection 116(1). CN does not argue that there is any
provision of the CTA that compels a different interpretation. Rather, CN
argues that there is jurisprudence binding on the Agency compelling it to adopt
the narrower interpretation of subsection 116(1) advocated by CN. That
jurisprudence consists of three cases: Scotia
Terminals Ltd. v. CN
(Decision No. 715-R-2000, Canadian Transportation Agency) (“Scotia Terminals”),
Canadian National Railway Company v. Neptune Bulk Terminals (Canada) Ltd., 2006 BCSC 1073 (“Neptune Bulk
Terminals”), and Kiist v. Canadian Pacific Railway Co., [1982] 1
F.C. 361 (F.C.A.) (“Kiist”)
[19]
Only
Scotia Terminals and Neptune Bulk Terminals were cited to the
Agency. The Agency did not consider either case to compel the conclusion that the right
to make a complaint under subsection 116(1) is limited to a shipper or a party to
a contract of carriage. I agree, essentially for the reasons given by the
Agency as quoted above.
[20]
It
remains only to consider Kiist, a case that CN did not cite to the Agency
or in its memorandum of fact and law in this appeal. CN referred to this case
for the first time in oral argument. I note however that the Agency was aware
of Kiist because that case is cited in the Agency’s memorandum of fact
and law, albeit on a different point.
[21]
Kiist
was
an appeal of a judgment of the Federal Court (then the Trial Division of the
Federal Court of Canada) striking out a statement of claim and dismissing an
action in damages against CN and Canadian Pacific Railway Company (“CP”). The
Federal Court had concluded that the statement of claim did not disclose a
reasonable cause of action and that in any event the Federal Court was without
jurisdiction to entertain the claim ([1980] 2 FC. 650).
[22]
The
appellants were grain producers who had commenced an action on their own behalf
and on behalf of all grain producers who, like themselves, sold their grain to
Canadian Wheat Board (the “CWB”) and had a statutory right to receive a share
of the surplus realized by CWB on the resale of the grain, net of expenses.
They alleged that for two specified crop years CN and CP had breached their
service obligations to the CWB in a number of respects, thereby causing financial
loss to the CWB and reducing the surplus entitlements of the appellants, for
which they sought compensation. The appellants also alleged that the failure of
CN and CP to fulfil their service obligations resulted in lost future sales and
goodwill, for which they sought additional compensation. They claimed damages
totalling almost $700 million.
[23]
The
appellants’ claim was based primarily on subsection 262(7) of the Railway
Act, R.S.C. 1970, c. R-2, the predecessor to subsection 116(5) of the CTA.
The two provisions read as follows (my emphasis):
Canada Transportation Act
|
Loi sur les
transports au Canada
|
116.
(5)
Every person aggrieved by any neglect or refusal of a company to fulfil
its service obligations has, subject to this Act, an action for the
neglect or refusal against the company.
|
116.
(5)
Quiconque souffre préjudice de la négligence ou du refus d’une compagnie
de s’acquitter de ses obligations prévues par les articles 113 ou 114
possède, sous réserve de la présente loi, un droit d’action contre la
compagnie.
|
Railway Act
|
Loi sur les
chemins de fer
|
262. (7) Every person aggrieved by
any neglect or refusal of the company to comply with the requirements of this
section has, subject to this Act, an action therefor against the company,
from which action the company is not relieved by any notice, condition or
declaration, if the damage arises from any negligence or omission of the
company or its servant.
|
262. (7) Quiconque
a été lésé par le négligence ou le refus da la compagnie de se conformer aux
exigences du présent article, a, sous réserve de la présente loi, le
droit d’intenter une poursuite contre la compagnie ; et la compagnie ne peut
se mettre à l’abri de cette poursuite en invoquant un avis, une condition ou
une déclaration, si le tort résulte d’une négligence ou d’une omission de la
compagnie ou de ses employés.
|
(The portion of subsection 262(7) of the Railway
Act that precludes a railway company from relying on a notice, condition or
declaration to relieve it of liability for negligence or an omission is the
statutory predecessor of subsection 116(6) of the CTA, which is not
relevant to this appeal.)
[24]
The
service obligations of a railway company under the Railway Act are set
out in subsection 262(1), the statutory predecessor to subsection 113(1) of the
CTA. Paragraph 262(1)(b) of the Railway Act is similar to
paragraph 113(1)(b) of the CTA. Those two provisions read as
follows:
Canada Transportation Act
|
Loi sur les
transports au Canada
|
113. (1) A railway company shall, according
to its powers, in respect of a railway owned or operated by it,
…
(b) furnish adequate and
suitable accommodation for the carriage, unloading and delivering of the
traffic
….
|
113. (1) Chaque compagnie
de chemin de fer, dans le cadre de ses attributions, relativement au chemin de
fer qui lui appartient ou qu’elle exploite :
[…]
b) fournit les
installations convenables pour le transport, le déchargement et la livraison
des marchandises […].
|
Railway Act
|
Loi sur les
chemins de fer
|
262. (1) The company shall, according
to its powers,
…
(b) furnish adequate and
suitable accommodation for the carrying, unloading and delivering of all such
traffic ….
|
262. (1) La companie doit,
selon ses pouvoirs,
[…]
b) fournir
des installations suffisantes et convenables pour le transport, le déchargement
et la livraison de ces marchandises et effets […].
|
[25]
Justice
Le Dain, writing for the Court, concluded that the Federal Court was the
appropriate forum for a claim for damages under subsection 262(7) of the Railway
Act, rejecting the argument of CN and CP that the Canadian Transport
Commission (the predecessor of the Agency) had the exclusive jurisdiction to
entertain such a claim. However, he also concluded that the Commission had the
sole jurisdiction to determine whether CN and CP had failed to fulfil their
service obligations, and that in the absence of such a determination by the
Commission, the Federal Court was without jurisdiction to entertain the claim
for damages.
[26]
In
case that conclusion was wrong, Justice Le Dain went on to say that the statement
of claim did not disclose a reasonable cause of action because the appellants
were not “persons aggrieved” within the meaning of that phrase in subsection
262(7) of the Railway Act. Justice Le Dain explained the scope of that
duty as follows (at page 383):
It
has been said on several occasions that the liability of a railway under the
provisions of the Railway Act is essentially that of a common carrier:
Canadian National Railway Co. v. Harris, [1946] S.C.R. 352 at page
376. While the specific duty that is found in section 262 to furnish adequate
and suitable accommodation may be said to be the creation of statute, it
could not have been contemplated that it should be owed to persons outside
the scope of a common carrier's liability because they do not have
contractual relations with the carrier and are not the owners of the goods
offered for carriage.
|
The grain producers were not the owners of
the wheat because they had sold it to the CWB, and they were not parties to the
contract of carriage. Therefore, they were not “persons aggrieved” within the
meaning of subsection 262(7) of the Railway Act.
[27]
Kiist may well be authority
for the proposition that the phrase “every person aggrieved” (or the
French phrase « quiconque souffre préjudice ») in subsection 262(7)
of the Railway Act (and therefore presumably subsection 116(5) of the CTA)
includes only the owner or shipper of the traffic in issue or a person who has a
contractual relationship with the railway company in relation to that traffic. However,
it does not necessarily follow that a similar limitation must apply in
determining the class of persons who are entitled to have the Agency
investigate a complaint under subsection 116(1) that a railway company is not
fulfilling its service obligations.
[28]
The
Railway Act does not contain a predecessor to subsection 116(1) of the CTA,
but it does contain a statutory predecessor to subsection 116(4) of the CTA,
the provision that authorizes a remedial order for a breach of a service
obligation. That statutory predecessor is subsection 262(3) of the Railway
Act, which reads as follows:
262. (3) If in any case such
accommodation is not, in the opinion of the Commission, furnished by the
company, the Commission may order the company to furnish the same within such
time or during such period as the Commission deems expedient, having regard
to all proper interests; or may prohibit or limit the use, either generally
or upon any specified railway or part thereof, of any engines, locomotives,
cars, rolling stock, apparatus, machinery, or devices, or any class or kind
thereof, not equipped as required by this Act, or by any orders or
regulations of the Commission made within its jurisdiction under the
provisions of this Act.
|
262. (3) S’il arrive que,
de l’avis de la Commission, la compagnie ne fournit pas les installations et
les commodités nécessaires, la Commission peut ordonner à la compagnie de les
fournir dans un délai ou durant une période qu’elle juge convenable en tenant
compte de tous les intérêts légitimes; ou elle peut interdire ou restreindre
l’emploi, sur tous les chemins de fer généralement, sur un chemin de fer
déterminé ou sur un tronçon de ce chemin de fer, de machines, locomotives,
wagons, matériel roulant, appareils, machineries ou dispositifs, ou d’une espèce
ou catégorie quelconque, non équipés selon les prescriptions de la présente
loi ou des ordonnances rendues ou des règlements établis par la Commission
dans les limites de ses attributions en vertu des dispositions de la présente
loi.
|
The phrase “such accommodation” in
subsection 262(3) of the Railway Act refers to the accommodation that a railway
company is required to provide pursuant to subsection 262(1), including
paragraph 262(1)(b), the statutory predecessor to paragraph 113(1)(b)
of the CTA (both provisions are quoted above).
[29]
The Railway Act
did not require a complaint to be made as a precondition to the Commission’s
authority to make a remedial order under subsection 262(3) of the Railway
Act. Therefore, it seems that the Commission’s remedial powers were
exercisable on the Commission’s own motion, which necessarily implies that the
Commission could act in response to information received from anyone. Further, the
Commission was required, in exercising the authority to make a remedial order
under subsection 262(3), to have regard to “all proper interests” (in French « tous les intérêts
légitimes
»),
suggesting that the class of persons whose interests the Commission was
required to consider in relation to a controversy about a railway company’s level
of service was broader than the class of persons (“persons aggrieved”) who were
entitled to make a claim for damages under subsection 262(7) (as interpreted by
this Court in Kiist).
[30]
The
apparent breadth of subsection 262(3) of the Railway Act, compared to
subsection 262(7), is consistent with the position of the Agency that subsection
116(1) of the CTA creates a class of potential complainants that is broader
than the class of “persons aggrieved” referred to in subsection 116(5). In that
regard, the Agency correctly noted that the English version of subsection
116(1) permits a complaint to be made by “any person”, a phrase that is more
general than “persons aggrieved” and necessarily includes a larger class of
persons. The French version does not expressly limit the class of complainants
at all, but simply states that the Agency must act « sur réception d’une
plainte
».
[31]
For
these reasons, I agree with the conclusion of the Agency that it had the
authority under subsection 116(1) of the CTA to investigate Northgate’s
complaint, and I would reject CN’s first ground of appeal.
Second issue: Did the
Agency apply the proper principles in finding a breach?
[32]
CN
argues that the Agency failed to apply properly, or at all, the principles
stated in A.L. Patchett & Sons Ltd. v. Pacific Great Eastern
Railway Company, [1959] S.C.R. 271 (“Patchett”). This ground of
appeal goes to the merits of the Agency’s decision, which must be reviewed on the
standard of reasonableness.
[33]
This
argument is based largely on CN’s characterization of the Agency’s decision,
which Northgate disputes. CN says that the Agency ordered CN to provide an
increased level of service to Northgate free of charge. However, Northgate says
that the Agency required CN to restore a long standing level of service to
Northgate, a level of service that CN had reduced and offered to restore only
upon receiving payment of a tariff. Northgate’s description is more accurate.
[34]
Patchett is generally
recognized as the leading case on the determination of the adequacy of the
service provided by a railway company. CN argues that Patchett established
three principles of law that were not applied properly, or at all, by the Agency.
CN asserts that the three principles are: (1) a railway company is not bound to
furnish cars at all times sufficient to meet all demands, (2) the obligation to
give transportation is subject to reasonable charges, and (3) on the duty of a
railway company to furnish services there is a correlative obligation on the
customer to furnish reasonable means of access.
[35]
Patchett stands for
the general proposition that the duty of a railway company to fulfil its
service obligations is “permeated with reasonableness in all aspects of what is
undertaken” (except in relation to its special responsibility as an insurer of
goods, which is not in issue in this case). As I read Patchett, the
three propositions to which CN refers in its argument are not free-standing
principles of law. They are guidelines that must inform any determination by the
Agency of a service complaint, but they do not necessarily compel a particular
outcome. That is because the determination of a service complaint requires the
Agency to balance the interests of the railway company with those of the
complainant in the context of the particular facts of the case.
[36]
A
fair reading of the decision of the Agency discloses that it was well aware of
its obligation to strike a reasonable balance between the interests of CN and
the interests of Northgate in the factual context of the Northgate complaint. Contrary
to the submissions of CN, the Agency did not require CN to furnish cars at all
times sufficient to meet all of Northgate’s demands. The Agency did not deprive
CN of the right to make a reasonable charge for its services or to require an
extra payment for services requested in excess of the minimum level prescribed
by the Agency. Nor did the Agency require CN to provide Northgate with service
in circumstances where CN had no reasonable means of access. In my view, the
Agency’s decision strikes a reasonable balance that is consisted with Patchett.
I would reject CN’s second ground of appeal.
Third issue:
Was the Agency entitled to relieve Northgate of a tariff obligation?
[37]
CN
argues that the Agency did not have the legal authority to relieve Northgate of
the obligation to pay the tariff charge for the second daily switch pursuant to
Item 13200 Tariff 9000. In my view, this ground of appeal could be interpreted
either as a challenge to the Agency’s interpretation of the scope of its legal
authority to make a remedial order, which is reviewable on the standard of
correctness, or a challenge to the merits of the Agency’s decision, which is
reviewable on the standard of reasonableness. I do not consider it necessary to
determine the standard of review on this point because, in my view, there is no
merit to this ground of appeal on any standard.
[38]
As
I read subsection 116(4), it clearly permits the Agency to do exactly what it
did, which was to order CN to take specific steps to restore a reasonable level
of service to Northgate and to specify the maximum charge that CN could make in
respect of those steps. I would reject CN’s third ground of appeal.
Fourth issue: Should Northgate have been
obliged to provide further information about the possibility of expanding its
facility?
[39]
CN
argues that the Agency breached the rules of natural justice when it refused to
permit CN to obtain information from Northgate concerning the possibility of
constructing additional trackage at the site operated by Northgate and then
concluded that there was no room for additional trackage. This relates to CN’s
argument on the third Patchett proposition referred to above, which was
that Northgate bore some responsibility for ensuring the adequacy of its
facilities.
[40]
The
Agency has adopted procedures in relation to a subsection 116(1) investigation
that permit opposing parties to obtain information from one another. However, the
Agency as the master of its own procedure has the discretion to supervise the
disclosure process. That includes the discretion to limit the disclosure
process on a particular point if the Agency concludes, reasonably, that it has
the information it requires on the point, the information requested is not
relevant, or the burden of producing the information is disproportionate to its
probable usefulness.
[41]
CN
was seeking extensive and detailed information from Northgate about the basis
for its submission that it was not feasible to expand its site and Northgate
objected to providing that additional information. The Agency sustained the
objection because it considered that it had sufficient information about the
Northgate facility and its limited prospects for expansion and that additional
information would not be necessary or relevant. In my view, the Agency’s disposition
of the Northgate objection was not a breach of the rules of natural justice but
a reasonable exercise of the Agency’s discretion to limit the disclosure
process. I would reject CN’s fourth ground of appeal.
Fifth issue: Was CN
unfairly deprived of the right to be heard in relation to certain evidence?
[42]
CN
argues that the Agency breached the rules of natural justice when it asked CN
to file a large amount of data in respect of the volume of traffic delivered to
Northgate’s facility between 2004 and 2008 and then interpreted the data
without providing CN the opportunity to comment on it, despite CN having
“cautioned” the Agency that the data could be misinterpreted.
[43]
The
data that the Agency requested from CN is well within the core of the Agency’s
expertise. CN does not allege that the Agency misinterpreted the data, or that
the Agency’s understanding of the data could have been enhanced by a further
submission from CN. Rather, CN is arguing that, having provided the Agency with
the requested information with a “caution” against possible misinterpretation,
the Agency was obliged to refrain from concluding its factual analysis without
inviting further submissions from CN.
[44]
As
I understand the record, CN cannot claim that it had no opportunity to explain
the data it provided to the Agency. In fact, CN provided the Agency with a
three-page explanation of the data when it was submitted. Nothing precluded CN
from providing a more detailed explanation or any submission it wished to make on
the interpretation of the data. Indeed, nothing precluded CN from asking expressly
for the right to make an additional submission, but it did not do so. Certainly
no such request is implicit in the “caution” to which CN refers, which was
simply a statement that some of the data “may not be easily interpreted”,
followed by three reasons why that might be so. In my view, in these
circumstances the Agency’s duty of fairness did not preclude it from analyzing
the CN data without inviting further submissions. I would reject CN’s fifth
ground of appeal.
Conclusion
[45]
I
would dismiss this appeal with costs payable by CN to Northgate.
“K. Sharlow”
“I
agree
Carolyn
Layden-Stevenson”
NADON
J.A. (Dissenting)
[46]
I have
read, in draft, the Reasons of Sharlow J.A. For the reasons that follow, I
cannot agree with her that the appeal should be dismissed.
[47]
More
particularly, I do not agree that Northgate was entitled to complain under
subsection 116(1) of the CTA that CN was not fulfilling its service
obligations under paragraph 113(1)(b) of the CTA. This is the
only conclusion of Sharlow J.A. with which I disagree.
[48]
In my
view, on a fair reading of the provisions at issue, CN owed no obligation or
duty to Northgate under section 113 of the CTA. Hence, Northgate had no
standing to complain under subsection 116(1). This interpretation of the
provisions finds support in three decisions, namely, the Agency’s decision in Scotia
Terminals, the British Columbia Supreme Court’s decision in Neptune Bulk
Terminals, and this Court’s decision in Kiist.
[49]
I need not
summarize the relevant facts as they are correctly summarized in Sharlow J.A.’s
Reasons. I would only state that the dispute between Northgate and CN concerns
the schedule of delivery of CN’s rail cars to Northgate’s terminal. Specifically,
the dispute arises because of CN’s decision to modify the schedule of delivery
to terminal operators in the Greater Vancouver Area from two deliveries per
day, Monday through Friday, to one delivery per day, seven days a week.
[50]
Paragraph 113(1)(b) of
the CTA requires a railway company to “furnish adequate and suitable
accommodation for the carriage, unloading and delivering of the traffic;…”.The
word
traffic”, as is easily apparent from the French version of
the paragraph, means the goods or the merchandise carried by the railway
company, in regard to which subsection 113(2) provides that the railway
company’s obligation to receive, carry and deliver from the point of origin to
destination is premised on the payment of a “lawfully payable rate” to the
railway company.
[51]
Of
relevance is subsection 113(4), which makes it clear that shippers and railway
companies can, by way of a confidential contract or other written agreement,
determine the precise obligations pursuant to which the railway company will fulfill
its service obligations under subsection 113(1).
[52]
Subsection
116(1) of the CTA provides that upon receipt of a complaint “made by any
person” that a railway company is not fulfilling all or part of its service
obligations, the Agency shall investigate the complaint and make a
determination within 120 days after receipt of the complaint as to whether the
railway company is fulfilling its service obligations.
[53]
I am
satisfied that the words “on receipt of a complaint by any person”, found in
subsection 116(1), do not mean that anyone can file a complaint against a
railway company with regard to the company’s service obligations under
subsection 113(1). Rather, the provision can only mean that any person to whom
a railway company is obligated to furnish those services set out at subsection
113(1) may file a complaint in regard to the company’s failure to provide
adequate service. In other words, if, in this case, CN was bound to provide to
Northgate the service set out at paragraph 113(1)(b) of the CTA,
then Northgate was entitled to file a complaint under subsection 116(1).
However, I am of the view that CN had no duty to provide Northgate with the
service described at paragraph 113(1)(b).
[54]
In my
view, the services set out at subsection 113(1) of the CTA are services
which a railway company is bound to provide or furnish only to those persons
who have required it to provide the services and have paid or undertaken to pay
the “lawfully payable rate” in regard to those services. I cannot see how the
provision can otherwise be understood.
[55]
The fact
that a party, such as Northgate in the present instance, might be affected by
CN’s decision to reduce or modify the level of service to its terminal does
not, in my respectful view, bring Northgate within the class of persons to whom
CN is bound to provide services under subsection 113(1). It should not be
forgotten that CN’s services were retained by a shipper who required it to take
its traffic from the point of origin and deliver it to Northgate’s terminal.
Nor should it be forgotten that Northgate’s services were retained by the same
client who retained CN’s services. Thus, both Northgate and CN are dealing with
the same entity, but providing different services to it.
[56]
It is also
relevant to point out that there is no evidence that CN’s client has either
taken objection to or filed any complaint in regard to the fact that CN
proposes to modify the schedule of delivery of its rail cars to Northgate.
[57]
The
Agency’s rationale for concluding as it did is found at paragraphs 44 to 51 of
its Reasons, which Sharlow J.A. has reproduced in her Reasons. At paragraphs 44
to 47 of its Reasons, the Agency sets out CN’s arguments and proceeds to
distinguish the two cases relied upon by CN, namely, Scotia Terminals, and
Neptune Bulk Terminals. Then, at paragraphs 48 to 51 which, for ease of
reference, I also reproduce, the Agency sets out its rationale for concluding
that Northgate was entitled to file a complaint under subsection 116(1) of the CTA:
[48] However,
the obligations set out in subsection 113(1) are broader and include the
general obligation to provide "adequate and suitable accommodation"
for, among other things, the delivery of traffic. The fact that the traffic is
being delivered to a facility owned by a person who is not a party to the
contract for the carriage of traffic does not relieve the railway company of
its various obligations under subsection 113(1) to provide accommodation for
traffic. Furthermore, the legislation specifically provides a statutory right
of complaint to "any person" and is not limited to
"shippers", or parties with whom the railway company has a contract
for the carriage of goods. This permits another party in the logistics chain,
such as a transloader, to complain that the railway company is not fulfilling
its level of service obligations with respect to the rail transportation of the
traffic of a shipper that is ultimately delivered to that transloader.
[49]
Subsection 113(1) may be usefully contrasted with subsections 113(3) and (4)
which explicitly provide for specific level of service obligations owed by the
railway company to shippers. Furthermore, section 116 of the CTA provides for a
complaint made by any person regarding a railway company that is not fulfilling
any of its service obligations. Contrary to the broad language of subsection
116(1), other rail provisions in the CTA are limited by their terms to provide
relief to particular categories of persons. For example, subsection 120.1
specifically provides for complaints to be filed by shippers. Similarly,
subsection 152.1(1) specifically provides for applications by public passenger
service providers.
[50] Clearly,
Northgate falls within the category of "any person" and, as such, has
standing under section 116 of the CTA to file a level of service complaint
against CN. Further, the use of "any person" in subsection 116(1) can
be contrasted with subsections 116(2) and (3), which specifically acknowledge
the possible existence of contracts between a shipper and the railway company
that may affect the outcome of an investigation into such a complaint.
[51]
Accordingly, the Agency concludes that it has jurisdiction to consider
Northgate's complaint under section 116 of the CTA and will therefore determine
whether CN has failed to fulfill its common carrier obligations.
[58]
I will
shortly examine Scotia Terminals, Neptune Bulk Terminals, and this Court’s decision in Kiist.
However, before doing so, I wish to make the following remarks in regard to the
Agency’s rationale for concluding as it did.
[59]
Instead of
determining whether Northgate is a person to whom a duty is owed by CN under
subsection 113(1), the Agency deems this to be the case because of its
interpretation of subsection 116(1) that “any person” can complain.
Consequently, in the Agency’s view, as the right to complain is not limited to
“shippers”, those in the logistics chain, such as Northgate, can file a
complaint in regard to a railway company’s failure to fulfill its service
obligations. In my view, that reasoning finds no support in the legislation.
[60]
The
Agency’s rationale cannot be reconciled with subsection 113(4), which allows
shippers and railway companies to determine, if they so wish, “the manner in
which the obligations under this section are to be fulfilled by the company”. In
other words, the parties may agree to determine the precise nature of the
services which the railway company will render to the shipper and the manner in
which the services will be rendered. To the extent that the railway company
meets the level of services provided in the written agreement, the shipper may
not successfully bring a complaint under subsection 116(1).
[61]
The
Agency, at paragraph 49 of its Reasons, indicates that “[S]ubsection 113(1) may
be usefully contrasted with subsections 113(3) and (4) which explicitly provide
for specific level of service obligations owed by the railway company to
shippers”. That assertion, in my view, misses the point, which is that the
obligations owed by the railway company under subsection 113(1) are obligations
owed to its contracting party, the shipper, or possibly to the consignee of the
goods where the shipper’s rights have been transferred to the consignee.
[62]
In any
event, the answer to the question at issue does not depend on the words “any
person” found in subsection 116(1). As I have already indicated, those who may
complain under the subsection are those who are entitled to receive services
from the railway company under subsection 113(1). It is worthwhile pointing out
that the French version of subsection 116(1) simply provides that the Agency
must investigate and make a determination in regard to a complaint made against
a railway company that it is not fulfilling its service obligations under
sections 113 or 114. There is no equivalent in the French version to the words
“made by any person” found in the English version. This supports my view of the
section that it does not apply to persons other than those who are entitled to
the railway company’s services under subsection 113(1).
[63]
Having
stated my view of the provisions at issue, I now turn to the two decisions
relied on by CN before the Agency.
[64]
I begin
with Scotia Terminals. Scotia Terminals operated as an intermediary: it
transferred nickel sulphide from ships onto trains for inland transportation.
The two shipping lines that served Scotia Terminals then signed an Agreement
whereby Scotia Terminals would handle all of their cargo, not just nickel
sulphide. CN refused to provide direct rail service for this additional
containerized cargo and stated that it would only provide direct service for
the nickel sulphide shipments. Scotia Terminals complained to the Agency that
by refusing service, CN violated its level of service obligations and caused it
significant economic loss. The Agency dismissed the complaint, ruling that it
was “not well founded”. Specifically, it found that Scotia Terminals did not
have a contract with CN and exercised no control over the routing of the
traffic beyond the port.
[65]
The
Agency’s analysis appears at pages 4 and following of its Reasons. More
particularly, at pages 4 and 5, the Agency explains why it cannot entertain
Scotia Terminals’ complaint under subsection 116(1). In my view, the Agency’s
reasoning in Scotia Terminals is correct and is entirely in line with
the interpretation that I am proposing:
Sections 113
to 115 of the CTA set out the statutory service obligations of
federally-regulated railway companies and include the services that a railway
company must provide to accommodate traffic. Section 113 of the CTA deals
with what is generally referred to as the common carrier obligations. Under
this provision, a railway company must provide, according to its powers,
adequate and suitable accommodation for the receiving, loading, carrying,
unloading and delivering of all traffic offered for carriage on its railway.
To determine
whether CN has breached its statutory service obligations, it is important to
examine the characteristics of the traffic subject to the present complaint,
focussing primarily on the selection of the terminal operator to be used for
transloading the cargo at the port, the involvement of the terminal operator in
the routing of traffic, and the contractual relationship between the rail
carrier and the terminal operator.
A review of
the evidence and information provided by the parties revealed that, in general
terms, both the rail carrier and the terminal operator act as contracted
service providers to the same client, either the cargo owner or the shipping
line. The terminal operator is the contractor responsible to provide
terminal services such as cargo handling to and from the vessel and to and from
the inland carriers, either by rail or truck. Similarly, the rail carrier is
also a contractor hired by the shipping line or the cargo owner to transport
the cargo inland. The service contracts for the rail transportation portion of
the movement are negotiated directly with the rail carrier involved, and these
contracts are negotiated separately from those governing the marine terminal
services performed by the terminal operator. Terminal operators do not
contract for rail transportation services.
…
With respect
to the selection of the terminal operator, it is either the shipping line or
the owner of the cargo who determines which terminal operator is going to be used
to transload the cargo; the shipping lines or the cargo owners will negotiate
directly with the terminal operators at a given port seeking the most
competitive terms and conditions. In the case of the traffic moving on the
account of Sherritt, Sherritt is responsible for the cost associated with the
discharge of the cargo and, consequently, it determines where the traffic will
be handled. In the case of containers where the shipping line is essentially
the principal, the shipping line would determine which terminal operator will
be used for the transloading of the cargo.
An
examination of the evidence and information provided by the parties
demonstrates clearly that it is the shipping line or the cargo owner,
depending mainly on the type of traffic involved, that determines the routing
of the traffic and negotiates contracts separately with the rail carrier and
the terminal operator involved. As a result, the relationship between the rail
carrier and the terminal operator is mainly for operational purposes. CN
indicated that there is no formal agreement between CN and terminal operators,
but rather a letter of understanding concerning the operational requirements. Scotia
Terminals confirmed that the relationship between a rail carrier and a marine
terminal operator is that of a cooperative effort, the goals of both of those
service providers being to meet the needs of the client.
Furthermore,
the evidence adduced reveals that Scotia Terminals does not enter into
contractual arrangements with CN for rail transportation service and it does
not exercise any degree of control over the routing of that traffic. Scotia
Terminals admitted that the decision to divert the container traffic from Pier
9A to Halterm Limited's container terminal was a decision made by the shipping
line.
Having
determined that Scotia Terminals does not
exercise any degree of control over the routing of the traffic, the Agency must
conclude that the present complaint is not well founded. Only the parties who
do control the routing of the traffic, either the shipping lines or the cargo
owners, depending on the type of traffic, and who do enter into contractual
arrangements with CN for the rail transportation of the traffic may
legitimately request the Agency to undertake an investigation of the service
offered by CN at Pier 9A. In that context, the Agency has determined that it
would be inappropriate to investigate further the issues raised in the
complaint of Scotia Terminals.
The Agency
would like to stress, however, that should a complaint be filed by the proper
parties,
the Agency would be receptive to reconsider the issues underlying the present
complaint and
to make a determination on whether or not CN has failed to fulfil its common
carrier obligations to provide adequate service at Pier 9A at the port of
Halifax.
[Emphasis added]
[66]
I see no
basis whatsoever to distinguish the present case from Scotia Terminals.
Northgate claims that this case is different because traffic actually passed
through its yard. However, I believe that this is a distinction without
substance. The essence of the complaint in Scotia Terminals was that the
terminal had lost business to other transloaders because CN would not provide
adequate service. The Agency ruled that Scotia Terminals did not have a valid
complaint because railways only owe level of service obligations to parties
bound by contract or who have control over the destination of the cargo. In the
present matter, the only distinguishing factor is that instead of being unable
to attract business, which was the case in Scotia Terminals, Northgate
is losing business it already has. This difference is insubstantial and
entirely unrelated to the ratio decidendi of the case.
[67]
I would
conclude regarding Scotia Terminals by simply saying that the Agency correctly
pointed out in its analysis that section 113 of the CTA sets out the
obligations which are generally referred to as the common carrier obligations.
Under such provisions, as the Agency explained, a railway company must provide
adequate and suitable accommodation with respect to the receiving, loading,
carrying, unloading and delivering of the traffic offered to it for carriage on
its railway. Clearly, under such provisions, a railway owes a duty to the
persons who retain its services.
[68]
I now turn
to Neptune Bulk Terminals. In distinguishing that decision, the Agency
stated at paragraph 47 of its Reasons:
[47] … In
her Reasons for Judgment, Madam Justice Wedge asserts that the level of service
obligations of railway companies, as set out in section 113 of the CTA, are
only owed to parties with whom the railway company has a contract for the
carriage of goods. The Agency is of the opinion that her reasoning is
restricted to consideration of obligations related to the transit of traffic,
or the movement of goods, such that, under subsection 113(2), a railway company
is required to accept traffic and move goods once the lawfully payable rate has
been paid.
[69]
Again, in
my view, the distinction which the Agency seeks to make is without substance.
The reasons given by Madam Justice Wedge for concluding as she did cannot, in
my respectful view, be dismissed offhand in the way the Agency does. The Agency
attempts to make a distinction based on subsection 113(2), but that distinction
is clearly without any foundation. Subsection 113(2) cannot be disassociated
from subsection 113(1). As the Agency itself indicated in Scotia Terminals,
the obligations found in subsection 113(1) are generally referred to as the
common carrier obligations. Subsection 113(2) clearly states the obvious:
unless payment is made or undertaken to be made to the railway, it has no
obligations under subsection 113(1).
[70]
The issue
before Madam Justice Wedge was whether CN could demand the payment of demurrage
from Neptune, a terminal operator. The facts were that CN, as in the present
matter, did not have a contract for the carriage of goods or any other contract
with the terminal operator.
[71]
At
paragraph 92 of her Reasons, Madam Justice Wedge states that the CTA
“continues to impose on railway companies such as CN certain duties often
referred to as ‘common carrier obligations’ and to which CN refers to as ‘level
of service’ obligations”. She then states that those obligations are those
found in section 113 of the CTA and, in particular, in paragraph 113(1)(a),
which requires a railway company to furnish “adequate and suitable
accommodation for the receiving and loading of all traffic offered for carriage
on the railway” and for “the carriage, unloading and delivering of the
traffic”. She then makes the following remarks at paragraph 93:
[93]
Nevertheless, a railway’s relationship with its customer is a contractual one.
Railway companies such as CN have level of service obligations described in s.
113 to provide “adequate and suitable accommodation”, but only with respect
to those with whom it contracts. That is made clear by s. 113(2) which
requires the railway carrier to take, carry and deliver traffic “on the payment
of the lawfully payable rate.” CN sets the rate for the movement of the traffic,
and once the customer has agreed to pay the rate, CN must deliver the cars to
the destination specified in the contract.
[Emphasis
added]
[72]
Then, at
paragraphs 101 to 103, Madam Justice Wedge deals with the Agency’s decision in Scotia
Terminals. After citing relevant extracts from that decision, Madame
Justice Wedge states unequivocally at paragraph 103:
[103]
Neptune’s circumstances resemble those of Scotia Terminals as described by the
Agency in the above decision. It does not contract with CN for the carriage of
goods. It does not pay freight on its own behalf or on behalf of the party
whose commodities it unloads. It does not issue or receive bills of lading. It
takes rail traffic delivered by CN, but only pursuant to the contracts of carriage
CN holds with its customers, who are the shippers or cargo owners. The
terminal authorization and five-day notice procedures are administrative
processes which assist both CN and Neptune to meet the needs of the same
client, which is the cargo owner or the shipper.
[Emphasis
added]
[73]
In my
respectful view, both Scotia Terminals and Neptune Bulk Terminals
clearly support the proposition that CN owed no duty to Northgate under
subsection 113(1) of the CTA.
[74]
It now
remains for me to address this Court’s decision in Kiist. I need not
repeat the salient facts of that decision, as they are clearly set out at
paragraphs 21 and following of Sharlow J.A.’s Reasons. However, I do not agree
with my colleague’s understanding of that decision. Contrary to her, I believe
that Kiist clearly supports the interpretation that I am proposing.
[75]
After
concluding that it fell within the jurisdiction of the Canadian Transport
Commission to determine whether the respondent railways had furnished adequate
and suitable accommodation for the carriage of grain during the crop years at
issue, Le Dain J.A., writing for the Court, proceeded to determine, should he
be wrong with regard to the question of jurisdiction, whether the statement of
claim disclosed a reasonable cause of action. At paragraph 40 of his Reasons,
he stated that issue in the following terms:
40. The
issue as to whether the statement of claim discloses a reasonable cause of
action is whether, assuming the truth of the allegations of fact in the
statement of claim, the appellants are persons aggrieved within the meaning of
subsection 262(7) of the Railway Act. Since the action is based on
alleged failure to perform the statutory duty to provide adequate and suitable
accommodation the question is whether the duty is one that was owed by the
respondent railways to the appellants. In my opinion, it was not.
[76]
Thus, in
order to determine whether the appellants were “persons aggrieved” within the
meaning of subsection 262(7) of the Railway Act, a determination of
whether the respondent railways had breached their statutory duty to provide
adequate and suitable accommodation for the carrying, unloading and delivering
of the appellants’ traffic had to be made by the Court. More particularly, Le
Dain J.A. indicated that the Court had to determine whether the respondent
railways owed a duty to the appellants.
[77]
I should
point out that there is no material difference between paragraph 262(1)(a)
of the Railway Act and paragraph 113(1)(b) of the CTA.
[78]
In
concluding that the respondent railways owed no duty to the appellants with
regard to the furnishing of adequate and suitable accommodation for the
carrying, unloading and delivering of their traffic, Le Dain J.A. gave the
following reasons at paragraphs 41 and 42:
41 The
duty is, as indicated in paragraph 262(1)(a), to furnish adequate and suitable
accommodation "for the receiving and loading of all traffic offered for
carriage upon the railway". It is, therefore, a duty owed to one who
offers goods for carriage. It is clear from the allegations of the
statement of claim and the applicable provisions of the Canadian Wheat Board
Act, to which reference has been made, that the additional or excess grain (to
use the expression employed by the Trial Judge) which the Board could have sold
and would have authorized producers to deliver, but for the alleged failure of
the respondent railways to furnish adequate accommodation, was not, and could
not have been, offered for carriage by the appellants to the respondent
railways. The allegations of the statement of claim and the provisions of the
Act make it clear that producers do not make the necessary arrangements with
the railways for the transportation of grain that is marketed through the
Board. Grain is sold and delivered by individual producers to the Board at
primary elevators or railway cars where ownership of it passes by operation of
the statute to the Board and it becomes mixed with other grain. It is the Board
that makes the necessary arrangements with the railways for transportation of
the grain sold by it. It does so for its own account as owner of the grain and
not as agent of the producers. As alleged by the statement of claim, the Board
participated in the necessary planning with the railways through the Transport
Committee for the carriage of grain during the crop years in question and
received a confirmation or commitment from the railways that they would provide
the necessary capacity to carry the grain sold by the Board. Paragraph 9 of the
statement of claim reads:
9. At all
material times The Canadian Wheat Board arranged with the Defendant railway
companies for the carriage of grain through the device of the Transportation
Committee for forecasting long-range requirements and through a Block Shipping
System for allocating rolling stock and related facilities on a six-week
shipping cycle. The Defendant railway company participated in the decisions so
made and confirmed their capacity to carry the grain in question.
It must be
remembered, moreover, that the Board has the authority to allocate available
railway cars, and that it necessarily participated with the railways in the
joint decisions as to the disposition of available rolling stock. The railways
do not deal with individual producers at all in respect of specific quantities
of grain sold and delivered by them to the Board and later carried for the
Board by the railways. The consequence for an individual producer of a
particular failure in the entire system to provide adequate accommodation could
not be foreseen by the railways.
42 It
has been said on several occasions that the liability of a railway under the
provisions of the Railway Act is essentially that of a common carrier:
Canadian National Railway Co. v. Harris [1946] S.C.R. 352 at page 376. While
the specific duty that is found in section 262 to furnish adequate and suitable
accommodation may be said to be the creation of statute, it could not have been
contemplated that it should be owed to persons outside the scope of a common
carrier's liability because they do not have contractual relations with the
carrier and are not the owners of the goods offered for carriage.
[Emphasis
added]
[79]
Le Dain
J.A.’s reasons for concluding as he did do not rest on the meaning of the words
“persons aggrieved” found in subsection 262(7) of the Railway Act.
Rather, he concludes that the appellants in Kiist cannot succeed because
they are not persons to whom a duty was owed by the respondent railways under
subsection 262(1) of the Railway Act. More particularly, because the appellants
did not enter into any contract with the respondent railways and because they
were not the owners of the goods offered to the railways for carriage, the
railways had no obligation to furnish adequate and suitable accommodation to
the appellants. Thus, as no duty was owed to the appellants, they did not
constitute “persons aggrieved” under subsection 262(7) of the Railway Act.
Consequently, no right of action lay in their favour.
[80]
Le Dain
J.A.’s reasoning is, for all intents and purposes, the reasoning that I am
proposing in the present matter. Consequently, as CN owed Northgate no duty
under subsection 113(1) of the CTA, it cannot be found to have failed to
furnish Northgate with adequate and suitable accommodation for the carrying,
unloading and delivering of the traffic. Thus, no complaint was receivable
under subsection 116(1).
[81]
At
paragraph 30 of her Reasons, Sharlow J.A. indicates that the Agency correctly
observed that the words “any person” found in subsection 116(1) of the CTA
were broader or more general than the words “persons aggrieved” found in
subsection 262(7) of the Railway Act and, thus, “necessarily includes a
larger class of persons”. In my respectful view, that distinction does not
allow us to distinguish Kiist from the present matter.
[82]
For these
reasons, I would allow the appeal with costs, I would set aside the Agency’s
decision and I would dismiss Northgate’s complaint.
“M.
Nadon”