Docket: A-85-17
Citation:
2017 FCA 247
|
CORAM:
|
DAWSON J.A.
STRATAS J.A.
RENNIE J.A.
|
|
BETWEEN:
|
|
MUHAMMAD FARID,
ABDUR RASHID,
|
|
A PARTNERSHIP
DOING BUSINESS AS KAAFTRONICS
|
|
Appellants
|
|
and
|
|
HER MAJESTY THE
QUEEN
|
|
Respondent
|
REASONS FOR JUDGMENT OF THE COURT
(Delivered from the Bench at Toronto, Ontario, on
December 13, 2017).
STRATAS J.A.
[1]
The appellants appeal from the judgment dated
February 7, 2017 of the Federal Court (per St-Louis J.): 2017 FC 143.
The Federal Court dismissed the appellants’ action with costs.
[2]
In the Federal Court the appellants claimed
compensatory, exemplary and punitive damages against Canada arising from its
conduct during a procurement process. They alleged several causes of action. The
Federal Court found that the appellants had not made out any of them.
[3]
In order for this Court to set aside the Federal
Court’s judgment, the appellants must persuade us that the Federal Court erred
in law or on an extricable question of principle or that the Federal Court
committed palpable and overriding error in its findings of fact or in its factually
suffused findings of mixed law and fact: Housen v. Nikolaisen, 2002 SCC
33, [2002] 2 S.C.R. 235; H.L. v. Canada (Attorney
General), 2005 SCC 25, [2005] 1 S.C.R. 401.
Palpable and overriding error is a highly deferential
standard of review: Benhaim v. St. Germain, 2016
SCC 48, [2016] 2 S.C.R. 352 at para. 38; Canada v. South Yukon Forest
Corporation, 2012 FCA 165, 431 N.R. 286 at para. 46;
Mahjoub v. Canada (Citizenship and Immigration), 2017 FCA 157 at
paras. 56-74. For the following reasons, we
have not been persuaded.
[4]
The appellants’ action challenges two
solicitations for bids conducted by the Department of Public Works and
Government Services.
[5]
In the first, the appellants’ central submission
is that their bid was the only one submitted and, thus, was the lowest bid and
so, as a matter of contractual interpretation, Public Works had to accept their
bid and enter into a purchase agreement with them. But Public Works did not.
It rejected the appellants’ bid on the ground it was too high. It exceeded the
limit in Public Works’ budget, a limit that was not disclosed to the appellants
in the bidding process.
[6]
The appellants’ advanced their central submission
in the Federal Court. The Federal Court did not accept it, finding that, as a
matter of contractual interpretation, Public Works was not obligated to accept
the appellants’ bid in these circumstances. In reaching this finding, the
Federal Court specifically considered contractual language stating that a “responsive bid will be recommended for award of the
contract”—language that the appellants say required Public Works to
award the contract to them—and found that other contractual language gave
Public Works the clear right to “reject any or all bids
received,” even a “recommended” bid, to “cancel the bid solicitation at any time,” and to “reissue the bid solicitation.” The appellants’ submitted
that this contractual language is ambiguous and should be interpreted in
accordance with an entire agreement clause. The Federal Court did not accept
this. It saw no ambiguity in the terms and interpreted them in a manner
consistent with the entire agreement clause.
[7]
In the Federal Court, the appellants advanced
other submissions and the Federal Court rejected them all. It did not find any
improper, undisclosed criteria relied upon by Public Works in rejecting the
appellants’ bid. It held on the evidence before it that Public Works’ decision
not to accept the appellants’ bid was done in good faith and for legally
acceptable reasons. It also did not accept that there were deficiencies in the way
Public Works established its budget, nor did it accept that the bidding process
offended the North American Free Trade Agreement Between the Government of
Canada, the Government of Mexico and the Government of the United States,
17 December 1992, Can. T.S. 1994 No. 2, 32 I.L.M. 289.
[8]
On all these points, we are not persuaded that
the Federal Court committed any error of law, error in extricable legal
principle, or palpable and overriding error.
[9]
The appellants also submit that the Federal
Court erred in finding that Public Works was under a legal duty to disclose the
budget under which it was operating in the tendering process. We disagree.
Given the tendering documents and the circumstances of this case, such a duty
did not arise as a matter of law: see Martel Building Ltd. v. The Queen,
2000 SCC 60, [2000] 2 S.C.R. 860 at para. 67; Defence Construction (1951)
Ltd. v. Zenix Engineering Ltd., 2008 FCA 109, 377 N.R. 47; GDC Gatineau
Development Corp. v. Canada (Minister of Public Works and Government Services),
2009 FC 1275, 360 F.T.R. 294. We are not persuaded that these authorities can
be distinguished on the facts of this case.
[10]
After rejecting the appellants’ bid, Public
Works conducted a second solicitation for bids. The appellants did not respond
to it. Nevertheless, in their action they impugned the solicitation, Public
Works’ later conduct of the bidding process, and the contract that eventuated.
The Federal Court found that the appellants did not respond to the second
solicitation. In our view, because of that, the appellants had no standing to raise
these issues.
[11]
Therefore, despite Mr. Farid’s thorough and
well-organized submissions, we shall dismiss the appellants’ appeal with costs.
"David Stratas"