Docket:
T-268-14
Citation:
2014 FC 1152
Ottawa, Ontario, December 1, 2014
PRESENT: The
Honourable Mr. Justice Boswell
BETWEEN:
|
PUBLIC SERVICE ALLIANCE OF CANADA
|
Applicant
|
and
|
ATTORNEY GENERAL OF CANADA
|
Respondent
|
JUDGMENT AND REASONS
I.
Background and Nature of the Proceeding
[1]
The Applicant represents employees working at
Veterans Affairs Canada [VAC] and the Veterans Review and Appeal Board. Among those
employees are client service agents [CSAs], who counsel veterans and their
families seeking benefits administered by VAC.
[2]
The CSAs’ responsibilities for the Veterans
Independence Program [VIP] and for Health-Related Travel [HRT] claims were
significantly reduced in 2012. The contract for service between Medavie Blue
Cross Inc. [Medavie] and Public Works and Government Services Canada [PWGSC]
was amended to include the payment of claims for housekeeping and grounds
maintenance under the VIP and the reimbursement of claims under the HRT
program. The prior system, whereby veterans would send in receipts and be
reimbursed under the VIP, was replaced with a grant system; changes were also
made in the processing of the annual form mailing to veterans.
[3]
As a result, the role of CSAs became less
proactive and more reactive, especially since VAC also transferred some of the
remaining responsibilities for administering the VIP and HRT to Medavie. About 50
CSA positions were eliminated and 37 CSAs were selected for lay-off. Most of
the laid-off CSAs found other positions, but 15 CSAs did not.
[4]
By letter dated August 2, 2012, the Applicant
filed a policy grievance pursuant to section 220 of the Public Service
Labour Relations Act, SC 2003, c 22, s 2 [the PSLRA] on behalf of its Union
of Veterans’ Affairs Employees component [the UVAE] . The grievance alleged
that, by virtue of the changes to the VIP and HRT and the consequent reduction
in the number of CSAs, VAC had violated clause 1.1.27 of Appendix D (Workforce
Adjustment) of the Program and Administrative Services collective agreement. That
clause provides as follows:
1.1.27 Departments
or organizations shall review the use of private temporary agency personnel,
consultants, contractors, employees appointed for a specified period (terms)
and all other non-indeterminate employees. Where practicable, departments or
organizations shall refrain from re-engaging such temporary agency personnel,
consultants or contractors or renewing the employment of such employees
referred to above where this will facilitate the appointment of surplus
employees or laid-off persons.
[5]
The grievance was referred to adjudication in
accordance with section 221 of the PSLRA. Following a hearing in October 2013,
the Applicant’s grievance was dismissed by an adjudicator of the Public Service
Labour Relations Board (see: 2013 PSLRB 165).
[6]
The Applicant now applies for judicial review of
the adjudicator’s decision under subsection 18.1(1) of the Federal Courts
Act, RSC 1985, c F-7, seeking an order to set aside that decision and remit
the matter to a different adjudicator. The Attorney General of Canada [the Respondent]
opposes this application, and both parties ask for their costs.
II.
The Adjudicator’s Decision
[7]
After comprehensively summarizing the evidence
and both parties’ arguments, the adjudicator observed that clause 1.1.27 would
not be engaged unless four requirements were met: (1) Medavie was a contractor;
(2) the amendment to the contract constituted a re‑engagement; (3) the
affected employees were “surplus employees” or “laid-off persons”; and (4) refraining from engaging
Medavie could have facilitated the appointment of the affected employees. Only
if those requirements were met would the onus then shift to the employer to show
that it would not have been practicable to refrain from engaging Medavie.
Ultimately, the adjudicator found against the Applicant on each of these
issues. .
[8]
First, the adjudicator was not convinced that Medavie
was a “contractor” within the meaning of clause
1.1.27. In making this determination, the adjudicator observed that
clause 1.1.27 was worded differently and quite distinct from a somewhat
similar clause 5.1.2 considered in Canada (AG) v Public Service Alliance of
Canada, [1993] 1 S.C.R. 941 at 947-948, 101 DLR (4th) 673 [PSAC (SCC)],
aff’g (1990), [1991] 1 FCR 428, 124 NR 379 (CA) [PSAC (FCA)], aff’g Public
Service Alliance of Canada v Treasury Board, [1990] CPSSRB No 51 (QL)
(PSLRB) [PSAC (Board)] (collectively, the PSAC decisions).
[9]
Clause 5.1.2 provided that departments had to “ … review … their use of contracted services and should
terminate them” where such action would facilitate the redeployment of
affected or surplus employees or laid-off persons. In contrast, the adjudicator
found that clause 1.1.27 was narrower in scope than the clause 5.1.2
considered in the PSAC decisions, in that clause 1.127 did not refer to “contracted services” but rather used the word “contractors”, a word whose otherwise broad definition
was narrowed by the other terms with which it was grouped: i.e., “private temporary agency personnel”, “consultants”, “employees
appointed for a specified period (terms)”, and “all
other non-indeterminate employees”. Since each such term refers to
individuals in the workplace, the adjudicator reasoned that “contractors” should likewise be limited to those in the
workplace. Furthermore, clause 1.1.28 of Appendix D confirmed this
interpretation in the adjudicator’s mind, since that clause gives priority to
surplus and laid-off persons for short-term work opportunities. The adjudicator
concluded that Medavie was not such a contractor.
[10]
Second, the adjudicator found that Medavie had
not been “re-engaged” even if it was a contractor.
The work transferred to Medavie was entirely consistent with the claims
processing work Medavie had been doing for PWGSC and, to some extent, for VAC
for many years. This transfer of work amounted to an amendment to an existing
contract and, thus, was not a re‑engagement or a rehiring of Medavie within
the meaning of clause 1.1.27.
[11]
Third, the adjudicator rejected the Applicant’s
argument that clause 1.1.27 should be construed so as to prohibit the employer
from rehiring or re-engaging a contractor if it would result in the creation of
surplus employees or laid-off persons. This argument, the adjudicator noted,
would be to interpret and apply clause 1.1.27 in a manner that would have the
effect of amending the collective agreement contrary to section 229 of the
PSLRA. The adjudicator determined that clause 1.1.27 was directed to a
consideration of surplus employees or laid-off persons
in existence at the time of contracting out the VIP work to Medavie. The
adjudicator thus reasoned that the existence of “surplus
employees or laid-off persons” at the time the Medavie contract was
amended was necessary before clause 1.1.27 would be engaged. Since the uncontradicted
evidence of all witnesses was that there were no such employees, clause 1.1.27
had not been violated.
[12]
Fourth, the adjudicator concluded that there was
no evidence led by either party that the work contracted out to Medavie was
work that the CSAs could have done. Unlike the situation in PSAC (SCC),
where the government set out to terminate indeterminate employees and simply
contracted out their identical jobs, here the jobs of CSAs were fundamentally
changed by the strategic shift to a grant system and the new regime for
processing annual questionnaires.
[13]
Lastly, the adjudicator found that even if
clause 1.1.27 had been engaged, the employer had provided evidence that it was
not practicable to refrain from contracting out the work to Medavie and also that
VAC had saved a lot of money.
[14]
The adjudicator therefore dismissed the
grievance.
III.
Issues
[15]
The Applicant states that there are only two
issues:
1.
What is the standard of review?
2.
Was the Adjudicator’s interpretation of Clause
1.1.27 reasonable?
[16]
The Respondent divides the second issue above
into four issues which can be rephrased, along with the Applicant’s argument
that the adjudicator failed to consider the purpose or objectives of clause
1.1.27, as follows:
1.
What is the standard of review?
2.
Did the adjudicator fail to consider the purpose
of clause 1.1.27?
3.
Did the adjudicator err in her interpretation of
“contractors”?
4.
Did the adjudicator err in her interpretation of
“re-engaging”?
5.
Did the adjudicator err by requiring
pre-existing “surplus employees or laid-off persons”?
6.
Did the adjudicator err by finding that it was
impracticable not to contract with Medavie?
IV.
Applicant’s Position
[17]
The Applicant accepts that the standard of
review is reasonableness, but submits that the range of acceptable outcomes is
narrow because of the legal nature of the questions at issue and the language
of the collective agreement (citing Canada (AG) v Abraham, 2012 FCA 266
at paras 42-43, 45, 440 NR 201 [Abraham]; First Nations Child and
Family Caring Society of Canada v Canada (AG), 2013 FCA 75 at paras 13-15,
444 NR 120 [First Nations]).
[18]
The Applicant argues that the purpose of
Appendix D is to shield indeterminate employees from the consequences of major
changes to the federal public service. At the hearing of this matter, the Applicant’s
counsel called this Appendix and, in particular, clause 1.1.27 “a lifeline” for job security protection. The same type
of clause was in issue in PSAC (Board) at 10, 13-14, i.e., clause 5.1.2,
and the board there held that such a clause exists so that employees,
particularly those who are indeterminate, can rely on the termination of
contracts to protect their jobs. The Applicant submits that the purpose of
clause 1.1.27 is the same as the former clause 5.1.2, and that the adjudicator
in the present case unreasonably failed to interpret clause 1.1.27 in a manner consistent
with that purpose. The Applicant asserts that the adjudicator stripped away any
meaningful protection for the job security of indeterminate employees in
contracting out cases.
[19]
The Applicant argues that this error tainted
every part of the adjudicator’s analysis, including her unreasonable definition
of the term “contractors”. The term “contractors”, the Applicant submits, is not general or
ambiguous, so there is no reason to restrict it to the same class of persons as
the surrounding words (National Bank of Greece (Canada) v Katsikonouris,
[1990] 2 S.C.R. 1029 at 1040, 74 DLR (4th) 197). Moreover, the Applicant argues
that limiting “contractors” to those in the
workplace fails to give effect to the plain and ordinary meaning of that word.
[20]
The Applicant further contends that the
adjudicator’s interpretation of “re-engaging” or “renewing” was unreasonable, in that the adjudicator
considered only the method by which the Medavie contract was changed and not
the substantive effect of the changes.
[21]
The Applicant also states that the adjudicator’s
interpretation of clause 1.1.27 imposes a requirement for there to be
pre-existing surplus employees or laid-off persons. The Applicant argues that such
a requirement defeats the purpose of clause 1.1.27 since it would allow a
department to unilaterally avoid the application of the clause simply by
controlling the timing of surplus and lay-off decisions so that they happen
after contracting-out has been completed.
[22]
Moreover, the Applicant submitted that the
adjudicator erred in determining that it was not practicable to refrain from
contracting out in this case. According to the Applicant, the adjudicator’s
finding that the mere fact the work was contracted out is proof enough that it
would have been impracticable to have kept the work in-house, is an
inappropriate, subjective standard. As well, the Applicant says that the adjudicator
erred by accepting the employer’s evidence of savings without proof that the
employer had considered other ways to realize those savings.
V.
Respondent’s Position
[23]
The Respondent agrees that the standard of
review is reasonableness and emphasizes the high degree of deference typically
accorded to a labour arbitrator’s interpretation of a collective agreement because
it is the “heartland” of their jurisdiction. In
particular, the Respondent argues that: adjudicators are not strictly bound by
the common law and equitable doctrines of the courts (Nor-Man Regional
Health Authority Inc v Manitoba Association of Health Care Professionals,
2011 SCC 59 at paras 42, 45-51, 60, [2011] 3 S.C.R. 616 [Nor-Man]); adjudicators
need not consider or discuss every issue raised by the parties (Construction
Labour Relations Inc v Driver Iron Inc, 2012 SCC 65 at para 3, [2012] 3 SCR
405); and an adjudicator’s decision cannot be unreasonable for failing to
consider an issue that was not argued (Alberta (Information and Privacy
Commissioner) v Alberta Teachers’ Association, 2011 SCC 61 at paras 22-28,
[2011] 3 S.C.R. 654 [Alberta Teachers]).
[24]
In the present case, the Respondent states that
each of the adjudicator’s primary findings in respect of the first part of
clause 1.1.27 was dispositive of the grievance, so the onus is upon the
Applicant to show that each of those findings was unreasonable. In the
Respondent’s view, the Applicant has not done that. The adjudicator summarized
all of the evidence and arguments in her decision and justified each of her
conclusions transparently and intelligibly. Furthermore, the Respondent states,
the outcome also falls within the acceptable range of outcomes and the
adjudicator’s reasons for dismissing the grievance are reasonable.
[25]
The Respondent emphasizes that adjudicators must
respect provisions that are clear, even if they might seem unfair (Chafe v
Treasury Board (Department of Fisheries and Oceans), 2010 PSLRB 112 at
paras 50-51, [2010] CPSLRB No 116 (QL)). The adjudicator in this case observed
that the terms with which “contractors” were
grouped all referred to individuals used by an employer to meet short-term
non-recurring requirements, and the Respondent argues that it was reasonable to
narrow the term “contractors” to that class in a
manner consistent with the limited class rule. In addition, the adjudicator’s
reference to clause 1.1.28 in interpreting the meaning of clause 1.1.27 was
reasonable since it confirms that surplus employees and laid-off persons should
have priority even for short-term work opportunities.
[26]
Furthermore, it was reasonable, the Respondent
contends, for the adjudicator to depart from the meaning ascribed to clause
5.1.2 in the PSAC decisions since clause 1.1.27 was subsequently negotiated
to employ different language. In any event, the Respondent submits, some
clauses can bear more than one reasonable interpretation and adjudicators do
not necessarily act unreasonably by choosing an interpretation different from
one that has received prior judicial approval (Alberta Health Services v
Alberta Union of Provincial Employees, 2013 ABCA 243 at para 17, 556 AR
102).
[27]
The Respondent also points out that because the
words “review”, “re-engaging”,
and “renewing” all share the prefix “re”, which
means to do again, this confirms that it was reasonable for the adjudicator to
find that the obligation created by clause 1.1.27 does not preclude a
department or organization from engaging a new contract or expanding the scope
of an existing one. Had the parties intended to do that, the Respondent states,
the parties would have used words like “engaging”
and “appointing” instead of “re-engaging”
and “renewing the employment of”.
[28]
The Respondent defends the adjudicator’s finding
that clause 1.1.27 cannot be triggered and cannot be violated unless the “surplus employees” or “laid-off
persons” already exist. Both of these terms are defined in the past
tense in Appendix D and, according to the Respondent, Appendix D is about
securing new employment for such individuals. Had prospective obligations been
intended by the parties, the Respondent states that prospective language would
have been used in clause 1.1.27.
[29]
Although the adjudicator may not have explicitly
identified the specific purpose of clause 1.1.27, the Respondent argues
that she did not have to do so. The adjudicator acknowledged the Applicant’s
argument about the objectives of clause 1.1.27, but she disagreed, and the
Respondent says that the adjudicator’s interpretation of clause 1.1.27 was
consistent with the purpose she assigned to Appendix D.
[30]
Finally, the Respondent contends that the
adjudicator reasonably construed “practicable” to
mean economically practical. The adjudicator had before her uncontradicted
evidence that the VIP was changed to better serve veterans and that the costs
of administering it were substantially reduced, and the Respondent submits that
the adjudicator’s assessment of that evidence should not be disturbed by this
Court (Hughes v Canada (Department of Human Resources and Skills
Development), 2014 FCA 43 at paras 11-12 (available on CanLII)).
VI.
Analysis
1.
What is the standard of review?
[31]
Both parties acknowledged that the standard of
review is reasonableness, since every issue “turn[s] on
the interpretation and application of the collective agreement, an exercise
with which adjudicators have particular familiarity” (Nitschmann v
Canada (Treasury Board), 2009 FCA 263 at para 8, 394 NR 126; see also: Communications,
Energy and Paperworkers Union of Canada, Local 30 v Irving Pulp & Paper,
Ltd, 2013 SCC 34 at para 16, [2013] 2 S.C.R. 458; Dunsmuir v New Brunswick,
2008 SCC 9 at para 68, [2008] 1 S.C.R. 190 [Dunsmuir]).
[32]
Applying this standard to the decision under
review means that this Court should not disturb the adjudicator’s decision if “the reasons allow the reviewing court to understand why the
tribunal made its decision and permit it to determine whether the conclusion is
within the range of acceptable outcomes” (Newfoundland and Labrador
Nurses’ Union v Newfoundland and Labrador (Treasury Board), 2011 SCC 62 at
para 16, [2011] 3 S.C.R. 708 [Newfoundland Nurses]).
[33]
There may be some cases where the acceptable
outcomes are few, especially when the issues are tightly governed by the law (First
Nations at paras 13-15; McLean v British Columbia (Securities Commission),
2013 SCC 67 at para 38, [2013] 3 S.C.R. 895 [McLean]). However, this case
is not one of them. The thrust of the Applicant’s submission that the range of
acceptable outcomes in this case is narrow and constrained is premised on what
the Applicant asserts is “the undisputed purpose of [the]
contracting out provisions” within Appendix D. That purpose, however, is
anything but undisputed, if only because the parties now find themselves before
this Court.
[34]
In this case, the adjudicator was interpreting a
collective agreement, something which is clearly a matter of contractual
interpretation. The view that contractual interpretation is a pure question of
law has recently been abandoned by the Supreme Court of Canada in Sattva
Capital Corp v Creston Moly Corp, 2014 SCC 53 at para 50, 373 DLR (4th) 393
[Sattva]. Mr. Justice Rothstein observed at paragraph 50 that
contractual interpretation “involves issues of mixed fact
and law as it is an exercise in which the principles of contractual
interpretation are applied to the words of the written contract, considered in
light of the factual matrix”.
[35]
I therefore reject the Applicant’s submission
that the range of acceptable outcomes is narrow and constrained given the legal
nature of the questions before the adjudicator. The essential question before
the arbitrator was one of contractual interpretation, and not one of statutory
interpretation as was the case in First Nations and also in McLean.
[36]
In any event, reasonableness review is a
contextual inquiry (Catalyst Paper Corp v North Cowichan (District),
2012 SCC 2 at para 18, [2012] 1 S.C.R. 5). It is generally more useful to ask only
whether the actual outcome is defensible in respect of the facts and the law
and not, as the Applicant contends, place a limit on how many possible outcomes
there could have been.
2.
Did the adjudicator fail to consider the purpose
of clause 1.1.27?
[37]
The Applicant’s main argument rests primarily on
the interpretation given to a provision similar to clause 1.1.27 over two
decades ago. In PSAC (Board), the purpose of the Workforce Adjustment
Policy [the WAP] considered in that decision was determined to be to “protect, to the extent of the Policy, indeterminate employees
from the consequences of major changes to the structure of the federal public
service” (PSAC (Board) at 13). The specific clause in question in
the PSAC decisions was intended to ensure that “indeterminate
employees can rely on the termination of contracting out in order to protect
their jobs” (PSAC (Board) at 14). The Supreme Court agreed with the
Board’s conclusion in this regard and emphasized that it “certainly
cannot be said that the Board’s interpretation was patently unreasonable”
(PSAC (SCC) at 972).
[38]
The adjudicator in this case did not construe
the purpose of Appendix D (Workforce Adjustment) as broadly as the WAP in the PSAC
decisions. On the contrary, the adjudicator stated at paragraph 76 of her
decision that the purpose of the policy in Appendix D was only to assist
indeterminate employees who have lost their jobs by ensuring that alternative
employment opportunities were provided to such employees. The adjudicator
clearly considered the PSAC decisions, yet she distinguished them from
the present case since the wording in clause 1.1.27 was narrower in scope
than that in clause 5.1.2. Furthermore, the language used to state the purpose
of the WAP in the PSAC decisions and that used in Appendix D is
different:
PSAC (SCC)
|
Current
|
1.3 The purpose of this policy is to
minimize the impact of WORK FORCE ADJUSTMENT situations on indeterminate
employees and to ensure that, wherever possible, alternate employment
opportunities are provided TO AFFECTED EMPLOYEES.
(see: PSAC
(SCC) at 970)
|
Objectives
It is the policy of
the Employer to maximize employment opportunities for indeterminate employees
affected by workforce adjustment situations, primarily through ensuring that,
wherever possible, alternative employment opportunities are provided to them.
This should not be construed as the continuation of a specific position or
job but rather as continued employment.
|
[39]
These differences are substantial. Rather than
minimizing the impact of work force adjustments generally, the policy that
applies to the present dispute is about maximizing the employment opportunities
for employees affected by a workforce adjustment. In my view, the adjudicator
did not act unreasonably by assigning significance to the new language by which
the policy in Appendix D is stated.
[40]
As well, in interpreting clause 1.1.27, the
adjudicator was not obliged to adopt the same purpose that had been assigned to
clause 5.1.2 in PSAC (SCC). Those clauses are also quite different:
5.1 Departments shall:
[…]
5.1.2 review their use of employees appointed for specified periods
(term employees) and their use of contracted services and should terminate
them where such action would facilitate the REDEPLOYMENT of AFFECTED
EMPLOYEES, SURPLUS EMPLOYEES, OR LAID-OFF PERSONS;
|
1.1.27 Departments or organizations
shall review the use of private temporary agency personnel, consultants,
contractors, employees appointed for a specified period (terms) and all other
non-indeterminate employees. Where practicable, departments or organizations
shall refrain from re-engaging such temporary agency personnel, consultants
or contractors or renewing the employment of such employees referred to above
where this will facilitate the appointment of surplus employees or laid-off
persons
1.1.28 Nothing in the foregoing shall restrict the Employer’s right to
engage or appoint persons to meet short-term, non-recurring requirements.
Surplus and laid-off persons shall be given priority even for these
short-term work opportunities.
|
[41]
The Applicant criticizes the adjudicator for not
expressly and precisely identifying the purpose of clause 1.1.27, but this does
not mean that she never considered such purpose. Indeed, the adjudicator was
clearly aware of the Applicant’s arguments in this regard, in that she
summarized them at paragraphs 29-30 and 42-45 of her decision.
[42]
As stated in Newfoundland Nurses at para
16: “[a] decision-maker is not required to make an
explicit finding on each constituent element, however subordinate, leading to
its final conclusion”. For the reasons stated below, the failure to
ascribe an explicit or precise purpose to clause 1.1.27 does not make the
adjudicator’s decision unreasonable or impossible to understand. It is at least
implicit in the adjudicator’s decision that the purpose of clause 1.1.27 was to
create employment opportunities for persons already affected by workforce
adjustments, not to prevent legitimate workforce adjustments from happening.
3.
Did the adjudicator err in her interpretation of
“contractors”?
[43]
At paragraph 72 of her decision, the adjudicator
decided that the term “contractors”, as referred
to in clause 1.1.27, “should be read to mean contractors
in the workplace”. During the hearing of this matter, the Applicant said
that that was nonsense and that the adjudicator failed to give effect to the
plain and ordinary meaning of the word “contractors”.
The Applicant also argued that it was inappropriate to apply the limited class
rule to the interpretation of the term “contractors”
since the word is neither general nor vague in a labour relations context. For
its part, the Respondent noted that the adjudicator observed that each of the
terms with which “contractors” was grouped were individuals employed to meet
short-term non-recurring requirements and, so the Respondent argued, it was
reasonable to narrow the term to that class in a manner consistent with the
limited class rule.
[44]
An adjudicator’s interpretation of a term in a
collective agreement can be reasonable even if the Court does not agree with
it. As noted in Nor-Man at para 45, arbitrators are not necessarily
bound by legal rules, and they can “adapt the legal and
equitable doctrines they find relevant within the contained sphere of arbitral
creativity”. Whether the adjudicator did or did not correctly apply the
limited class rule as it exists at common law does not make the decision under
review unreasonable provided the Court is able to understand the adjudicator’s
reasons (Newfoundland Nurses at para 16). In any event, the limited class
rule is more flexible in labour arbitration than it is at common law, and it
provides simply that “all the items included in a list
are presumed to have some common features and to be part of the same class”
(Michael Bendel, “Interpretation of the Collective Agreement” in Ronald M.
Snyder, ed, Collective Agreement Arbitration in Canada, 5th
ed (Markham, ON: LexisNexis, 2013) at para 2.25).
[45]
In my view, the adjudicator’s interpretation of “contractors” in the context of clause 1.1.27 was
reasonable. The previous PSAC decisions involved the same parties and
were about a situation where “the contract employees did
the same work, on the same equipment, in the same premises as had the union
employees” (see: PSAC (SCC) at 969; PSAC (Board) at 11).
That is the type of situation that would likely have been in the minds of the
parties when clause 1.1.27 was negotiated to employ different language,
notably, “contractors” in lieu of “contracted services”.
4.
Did the adjudicator err in her interpretation of
“re-engaging”?
[46]
At paragraph 74 of her decision, the adjudicator
found that Medavie was not re-engaged because the duties transferred to it “were consistent with those already contracted for and in my
opinion amounted to an amendment to an existing contract”
(emphasis added). The adjudicator’s use of the words “amounted
to” suggests that she viewed the changes effected by the amendment to
the Medavie contract in substance as well as in form, and that the changes
merely supplemented the duties Medavie already performed. Indeed, the
adjudicator observed at paragraph 80 of her decision that “[t]here was no evidence led by either party that the work
contracted out to Medavie was work that the CSAs could have done”.
[47]
The Applicant’s proposed interpretation of
clause 1.1.27 ignores the prefix “re-” in both “re-engage”
and “renew”. A decision to create a new function
with the implementation of the grant system and contract that work out is not
re-engaging a contractor; it is engaging a contractor, either by a new contract
or by expanding the scope of an existing one. The parties must have negotiated
the “re-engaging” and “renewing”
language for a reason, and it is consistent with the adjudicator’s
interpretation of the purpose of Appendix D. The adjudicator’s conclusion that
Medavie was not re-engaged or rehired contrary to clause 1.1.27 was not only reasonable
but also was understandable in view of her reasoning.
5.
Did the adjudicator err by requiring
pre-existing “surplus employees or laid-off persons”?
[48]
The WAP at issue in PSAC (FCA) provided
that departments “should terminate” their use of “contracted services” if that
would facilitate the redeployment of affected employees. At page 442, Mr.
Justice Mahoney said the following for the majority of the Federal Court of
Appeal:
The entire thrust of the Workforce Adjustment
Policy is that, in a workforce adjustment situation, indeterminate employees
whose services would no longer be required would, as far as practicable, be
redeployed and, if necessary, retrained. The Policy does not prohibit
contracting out but it does contemplate that, to facilitate redeployment of “affected”,
“surplus” or “laid-off” personnel, the employer will, inter alia, review
and terminate its use of contracted services. That requirement is utterly
inconsistent with an intention to permit the creation of “affected”, “surplus”
or “laid-off” personnel by contracting out the very jobs that they have been
doing.
The Supreme Court of
Canada endorsed the foregoing passage in PSAC (SCC) at 975.
[49]
The adjudicator was not bound by the
interpretation the Supreme Court or the Federal Court of Appeal assigned to the
WAP in the PSAC decisions. Unlike clause 5.1.2, clause 1.1.27 does not
apply to “affected” personnel. Rather, clause
1.1.27 applies only to “surplus employees” and “laid-off persons”, both of which terms are defined in
the past tense:
Laid-off person (personne mise en disponibilité)—is
a person who has been laid-off pursuant to subsection 64(1) of the PSEA
and who still retains an appointment priority under subsection 41(4) and
section 64 of PSEA.
[…]
Surplus employee (employé-e excédentaire)—is an
indeterminate employee who has been formally declared surplus, in
writing, by his or her deputy head.
[Emphasis added]
[50]
It was reasonable for the adjudicator to consider the use of the
past tense in these definitions as being significant, especially since she did
not assign to Appendix D the same purpose that the Supreme Court did with
respect to the WAP in 1993. On the contrary, the adjudicator stated at
paragraph 76 of her decision that the purpose of the workforce adjustment
directive in Appendix D was “to assist
indeterminate employees ‘whose services are no longer required because of a
workforce adjustment situation’ and to ensure, ‘wherever possible, alternative
employment opportunities are provided to them’. The objectives go on to say
that this should not be construed as the continuation of a specific position or
job”.
[51]
Under the arbitrator’s view, clause 1.1.27
exists to generate further employment opportunities for surplus employees or
laid-off persons by requiring the employer to review the use and work of
temporary or contracted personnel and consider whether such work could be done
by the indeterminate employees instead. It is understandable why the
adjudicator found that there is no need to review the employer’s existing
contractual engagements unless and until there are such surplus employees or
laid-off persons in existence. Although this interpretation of clause 1.1.27
may not produce as favourable a result to the Applicant as clause 5.1.2 did in
the PSAC decisions, it is nonetheless a reasonable one to which this
Court should defer.
[52]
It deserves note that, in PSAC (FCA), Mr.
Justice Mahoney also said the following at page 442:
By definition, a “Work Force Adjustment” occurs
when management decides that one or more indeterminate employees will no longer
be required because of “lack of work” or “a discontinuance of a function”. It
cannot, in my view, be said that the services of an employee whose job has been
contracted out are not required because of lack of work or the discontinuance
of a function. That employee is not required only because the job has been
contracted out.
[53]
Significantly, the adjudicator decided that the
present case was dissimilar, stating at paragraph 82 of her decision as
follows:
This is not a situation such as that in PSAC v. Canada, where the employer set out to
reduce the number of indeterminate employees and contracted out the identical
jobs being performed by the employees in order to do so. (PSAC v. Canada, FCA, at page 7; The Attorney General of Canada v. PSAC, [1993]
1 SCR 941 at para 67). This is a situation where a strategic decision was made
to move to a system that utilized grants rather than claims authorization that
changed the very nature of the work done by the employees (the CSAs) in the VIP
program and also resulted in a reduction of the work to be done.
In my view, it was
reasonable for the adjudicator to find that clause 1.1.27 does not, in and of
itself, prevent the government from making workforce adjustments.
6.
Did the adjudicator err by finding that it was
impracticable not to contract with Medavie?
[54]
The adjudicator stated the following at
paragraphs 80-81 of her decision:
80 There was no
evidence led by either party that the work contracted out to Medavie was work
that the CSAs could have done. The grievor [Applicant] argues that there is a
direct relationship between the work transferred and the reduction of CSA
positions and that refraining from amending the contract with Medavie would
have allowed the CSA employees to keep their jobs. This submission misses the
important strategic change that had taken place. Why then was it contracted out
to a third-party service provider? It was done because it was no longer
practicable in the employer's mind to continue to have the work performed
in-house. The fact of the matter is that the jobs of the CSAs were changed due
to the transformation to a grant system and due as well to the changes to how
annual questionnaires were mailed out, received and processed. This meant that
the CSAs would be engaged in follow up that might be flagged after canvassing
whether there was a change in circumstances. As Ms. Burdett testified, the CSAs
role was significantly reduced because, rather than determine veterans' needs,
there [sic] role focussed more on any follow up concerning the grant
payment and changes to the payment. It is also important to note that the role
of canvassing, which had been part of the role in claims processing in the
past, had also changed even before the 2012 Budget. The limitation in this case
was whether it was practicable for the employer to refrain from contracting out
these services in favour of maintaining the number of CSAs in its employ. The
UVAE did not provide any proof of whether it would have been practicable,
relying instead on a shifting of the burden of proof to the employer to prove
that it was not practicable to do so. Given my findings above, I do not find
that the employer was limited from contracting out these services. However,
even if there was a limitation, I find that the employer provided evidence that
demonstrated that it was not practicable to refrain from contracting out. The
employer led evidence that following the Deficit Reduction Action Plan and the
budget, Parliament ordered the amendment of the VIP to better serve veterans.
The employer also established the considerable savings the VAC realized as a
result of the contracting out. The employer argued that that established that
it was not practicable to continue with the CSAs performing the work.
81 Practicable does
not mean possible. (See Brannick, at 8). What is practicable must be
construed to mean practical, business-wise or economically practical, as well
as physically practical. (See The Council of Postal Unions, at 25).
Clearly, in the current economic climate the Government of Canada has
determined that spending in the public service must be reduced and that steps
must be taken to ensure the overall reduction of costs. The overall savings
realized by the employer as a result of the contracting out to Medavie was
economically practical as well as business-wise, albeit with unfortunate
results.
[55]
In my view it was not reasonable or, for that
matter, even necessary for the adjudicator to address or interpret what the
words “where practicable” mean in clause 1.1.27. That aspect of the clause, as
the Respondent argues, was not “triggered” in view of the adjudicator’s
determination that there were no contractors, no rehiring or re-engagement of a
contractor, and no surplus employees or laid-off persons at the time the
Medavie contract was amended. The adjudicator’s comments as quoted above were,
to say the least, superfluous. Such comments do not, however, render the other
aspects of her decision unreasonable or make the decision as a whole one which
is not understandable or not reasonable.
VII.
Conclusion
[56]
In the result, I find the adjudicator’s reasons for
dismissing the policy grievance justifiable and understandable and,
notwithstanding her comments concerning the words “where practicable” in the
context of clause 1.1.27, reasonable. The adjudicator was alive to the issues
before her and her decision is within the range of acceptable outcomes,
especially given an adjudicator’s particular familiarity with the interpretation
and application of collective agreements.
[57]
The Applicant’s application for judicial review is
dismissed.
[58]
The Respondent has requested its costs and, as the
parties agreed at the hearing of this matter, I see no reason to depart from
the general practice that costs will follow the result. Accordingly, the
Respondent shall have its costs of this application as assessed in accordance
with column III of the table to Tariff B.