Date: 20101112
Docket: T-1349-09
Citation: 2010 FC 1139
BETWEEN:
|
YELLOWKNIVES DENE FIRST NATION,
LUTSEL K’E DENE FIRST NATION,
CHIEF TED TSETTA and CHIEF EDWARD
SANGRIS on their own behalf and on behalf of all Members of the Yellowknives
Dene First Nation, and CHIEF STEVEN NITAH on his own behalf and on behalf of
all Members of the Lutsel K’e Dene First Nation
|
|
|
Applicants
|
And
|
|
THE ATTORNEY GENERAL OF CANADA
NORTH ARROW MINERALS INC.
|
|
|
Respondents
|
|
|
|
REASONS FOR JUDGMENT
PHELAN
J.
I. INTRODUCTION
[1]
The
Applicants are the Yellowknives Dene First Nation and the Lutsel K’e Dene (collectively
First Nations) who seek judicial review of a July 16, 2009 decision of the Mackenzie Valley Land and Water Board
(Board) to issue North Arrow Minerals Inc. (North Arrow) a land use permit
(Permit) to conduct mineral explorations. The principal issue raised is whether
the Applicants were properly consulted.
While there
are two Respondents, North Arrow did not participate in the case. The term
“Respondent” refers to the Attorney General of Canada.
[2]
The
Applicants request that this Court quash the Permit because the requirements
under the Mackenzie Valley Resource Management Act (Act) and related
regulations were not met. The Applicants further seek a variety of other
remedies including declaration for breach of procedural fairness and reasonable
apprehension of bias; a declaration of breach of the Crown’s duty to consult;
an order requiring the Crown to consult and accommodate the Applicants before a
permit may be issued; and an order requiring North Arrow to consult and
accommodate.
[3]
There
was a preliminary motion by the Respondents to strike several of the
Applicants’ affidavits either in whole or in part. This motion was heard at the
time of the judicial review and the Court reserved its decision so that the
full judicial review could be argued in the time allotted for the hearing at Yellowknife.
II. BACKGROUND
A. Parties
and Agreements
[4]
The
Applicant Yellowknives (consisting of two communities; the Dettah and the Ndilo)
and the Lutsel K’e are among the Akaitcho Dene First Nations (ADFN). There is
no issue that these are Aboriginal people within the meaning of s. 35 of the Constitution
Act, 1982.
[5]
On
July 25, 1900, the ADFN signed “Treaty 8” with the Crown and created
constitutionally protected treaty rights. However, each side has different
interpretations of that treaty and this has led to over 100 years of dispute
and negotiation in order to clarify the rights of the ADFN.
[6]
The
ADFN have since made a claim (the Akaitcho Claim) to various aboriginal and
treaty rights including rights of exclusive possession and control over the
land, rights of self government, cultural rights and rights to hunt, trap,
travel and gather on and over the land. In 1976 the Crown accepted the claim
for negotiation in the context of a larger Dene-Metis claim. In 1996
Akaitcho-specific negotiations began and are still in progress.
[7]
One
hundred years after signing the Treaty, the ADFN and the Crown signed a
“Framework Agreement” in order to clarify the negotiation process. The
Framework Agreement is a fairly basic and broad document which speaks almost
entirely to procedural aspects of negotiations, states some basic principles
and sets out some timelines, which have not been met. It is important to note
that this Framework Agreement does acknowledge the assertion of the ADFN of
traditional and current land use. Section 11 of the Framework Agreement,
however, specifically states that nothing in the Agreement is to be interpreted
as creating, recognizing or denying rights or obligations on the part of any of
the parties.
[8]
In
2001, the parties signed an “Interim Measures Agreement” (IMA) in which Canada
and the Government of the Northwest Territories acknowledged that the
Akaitcho DFN asserted their traditional territory as outlined in a map attached
to the IMA. The IMA covers a number of activities undertaken by the Governments
of Canada and of the Northwest Territories including federal land
use permits. The IMA essentially sets up a process whereby the ADFN can
“pre-screen” these types of decisions upon being given the earliest possible
notice of applications for various licences and the necessary information to
respond. A series of schedules are attached to the IMA setting out more
comprehensive means by which this brief pre-screening is to be done in relation
to various permits and other government decisions.
[9]
Schedule
C of the IMA guides the process as it relates to Land Use Permits. It requires
that the Akaitcho Screening Board be given notice of an application process as
early as possible. Once an application is received, the Board has five days to
notify the Akaitcho Screening Board and in the case of a “Type A permit” (such
as the one at issue in this proceeding), the affected First Nations have 21
days to respond. Schedule C was implemented by Ministerial Order on February
23, 2004. The Ministerial Order does not give directions as to how the Board is
to consider the First Nations’ submissions, merely that it must do so “fully
and impartially”.
[10]
The
Akaitcho Screening Board operates through the IMA implementation office. This
office is a support unit for First Nations, essentially a regional coordinating
body. It acts as a communication link between First Nations, governments and
“project proponents” (e.g. companies looking to undertake operations in the
area such as North Arrow).
The
Applicants submit that while the office exists to facilitate the process, it by
no means guarantees adequate consultation. It is argued that the office
essentially puts people in touch with each other and may act in an advisory
capacity as to how communications should occur.
It is the
Applicant’s position that this IMA is not a substitute for consultation.
B. MacKenzie Valley Land and
Water Board
[11]
The
Board is established pursuant to the Mackenzie Valley Resource Management
Act S.C., 1998, c. 25 and the associated regulations.
[12]
There
is dispute between the parties as to how the Board’s regime was developed. The Applicants
contend that the regime was established unilaterally by the Government of
Canada without the input of the ADFN. It is the position of the Respondents
that the regime arose, inter alia, from the requirements of the
Gwitch’in and Sathu Dene & Metis Comprehensive Land Claim Agreements.
[13]
Justice
Blanchard, in his decision Ka’a’Gee Tu First Nation v. Canada (Attorney
General),
2007 FC 763 (Ka’a’Gee #1), set forth the Act and Regulations and their
genesis in detail. He noted that the regime, including the Land and Water Board
and the Environmental Impact Review Board, was indeed a result of these land
claims. He further found that Bill C-6, which prescribed the legislation, took
five years to complete and included “considerable consultation with all affected
groups”. The position that this regime was imposed unilaterally and without
consultation simply is not in accord with Justice Blanchard’s reasons.
[14]
The
Act is not a model of brevity, simplicity or clarity. It describes land use
planning, water and land regulation and the composition of various boards
making specific provisions for the First Nations whose agreements gave rise to
the Act.
[15]
While
Part 3 outlines the duties and powers of the boards more generally, Part 4
specifically sets out the Mackenzie Valley Land and Water
Board’s composition and authority. Moreover, this Part 4 incorporates Part 3 by
reference pursuant to s. 102(1):
102. (1) The Board has
jurisdiction in respect of all uses of land or waters or deposits of waste in
the Mackenzie Valley for which a permit is required under Part 3 or a licence
is required under the Northwest Territories Waters Act, and for that
purpose the Board has the powers and duties of a board established under Part
3, other than powers under sections 78, 79 and 79.2 to 80.1, as if a
reference in that Part to a management area were a reference to the Mackenzie
Valley, except that, with regard to subsection 61(2), the reference to
management area continues to be a reference to Wekeezhii.
|
102. (1) L’Office a
compétence en ce qui touche toute forme d’utilisation des terres ou des eaux
ou de dépôt de déchets réalisée dans la vallée du Mackenzie pour laquelle un
permis est nécessaire sous le régime de la partie 3 ou aux termes de la Loi
sur les eaux des Territoires du Nord-Ouest. Il exerce à cet égard les
attributions conférées aux offices constitués en vertu de cette partie,
exception faite toutefois de celles prévues aux articles 78, 79 et 79.2 à
80.1, la mention de la zone de gestion dans les dispositions pertinentes de
cette partie valant mention de la vallée du Mackenzie, sauf au paragraphe
61(2) où cette mention continue de viser le Wekeezhii.
|
Therefore, the considerations and requirements of
Part 3 are relevant to the Board and to this litigation.
[16]
The
most relevant provisions of Part 3 affecting this judicial review are parts
60.1 – 65 (relevant provisions shown below):
60.1
In exercising its powers, a board shall consider
(a) the importance
of conservation to the well-being and way of life of the aboriginal peoples
of Canada to whom section 35 of the Constitution Act, 1982 applies and
who use an area of the Mackenzie Valley; and
(b) any traditional
knowledge and scientific information that is made available to it.
2005, c. 1, s. 35.
62.
A board may not issue a licence, permit or authorization
for the carrying out of a proposed development within the meaning of Part 5
unless the requirements of that Part have been complied with, and every
licence, permit or authorization so issued shall include any conditions that
are required to be included in it pursuant to a decision made under that
Part.
63.
(1) A board shall provide a copy of each application made
to the board for a licence or permit to the owner of any land to which the
application relates and to appropriate departments and agencies of the
federal and territorial governments.
(2) A
board shall notify affected communities and first nations of an application
made to the board for a licence, permit or authorization and allow a
reasonable period of time for them to make representations to the board with
respect to the application.
64.
(1) A board shall seek and consider the advice of any
affected first nation and, in the case of the Wekeezhii Land and Water Board,
the Tlicho Government and any appropriate department or agency of the federal
or territorial government respecting the presence of heritage resources that
might be affected by a use of land or waters or a deposit of waste proposed
in an application for a licence or permit.
(2) A
board shall seek and consider the advice of the renewable resources board
established by the land claim agreement applicable in its management area
respecting the presence of wildlife and wildlife habitat that might be
affected by a use of land or waters or a deposit of waste proposed in an
application for a licence or permit.
65.
Subject to the regulations, a board may establish
guidelines and policies respecting licences, permits and authorizations,
including their issuance under this Part.
|
60.1
Dans l’exercice de ses pouvoirs, l’office tient compte,
d’une part, de l’importance de préserver les ressources pour le bien-être et
le mode de vie des peuples autochtones du Canada visés par l’article 35 de la
Loi constitutionnelle de 1982 et qui utilisent les ressources d’une région
de la vallée du Mackenzie et, d’autre part, des connaissances traditionnelles
et des renseignements scientifiques mis à sa disposition.
62.
L’office ne peut délivrer de permis ou d’autorisation
visant à permettre la réalisation d’un projet de développement au sens de la
partie 5 avant que n’aient été remplies les conditions prévues par celle-ci.
Il est en outre tenu d’assortir le permis ou l’autorisation des conditions
qui sont imposées par les décisions rendues sous le régime de cette partie.
63.
(1) L’office adresse une copie de toute demande de permis
dont il est saisi aux ministères et organismes compétents des gouvernements
fédéral et territorial, ainsi qu’au propriétaire des terres visées.
(2) Il
avise la collectivité et la première nation concernées de toute demande de
permis ou d’autorisation dont il est saisi et leur accorde un délai suffisant
pour lui présenter des observations à cet égard.
64.
(1) L’office doit demander et étudier l’avis de toute
première nation concernée, des ministères et organismes compétents des
gouvernements fédéral et territorial et, s’agissant de l’Office des terres et
des eaux du Wekeezhii, du gouvernement tlicho au sujet des ressources
patrimoniales susceptibles d’être touchées par l’activité visée par la demande
de permis dont il est saisi.
(2) Il
doit de plus demander et étudier l’avis de l’office des ressources
renouvelables constitué par l’accord de revendication au sujet des ressources
fauniques et de leur habitat susceptibles d’être touchés par l’activité visée
par la demande de permis.
65.
L’office peut, sous réserve des règlements, établir des
principes directeurs et des directives concernant les permis et
autorisations, notamment en ce qui touche leur délivrance sous le régime de
la présente partie.
|
[17]
In
addition, in Part 5 dealing with the Mackenzie Valley Environmental Impact
Review Board (Review Board), s. 118(1) specifically states that no permit
required for carrying out development can be issued unless the requirements of
Part 5 have been complied with in relation to development.
[18]
The
separate aspects of the process are described in greater detail in Part 5 and
the steps required are set forth in s. 124(1)(a) and (b) and s.
125(1)(a) and (b):
124.
(1) Where, pursuant to any federal or territorial law
specified in the regulations made under paragraph 143(1)(b), an
application is made to a regulatory authority or designated regulatory agency
for a licence, permit or other authorization required for the carrying out of
a development, the authority or agency shall notify the Review Board in
writing of the application and conduct a preliminary screening of the
proposal for the development, unless the development is exempted from
preliminary screening because
(a) its impact on
the environment is declared to be insignificant by regulations made under
paragraph 143(1)(c); or
(b) an examination
of the proposal is declared to be inappropriate for reasons of national
security by those regulations.
…
125.
(1) Except as provided by subsection (2), a body that
conducts a preliminary screening of a proposal shall
(a) determine and
report to the Review Board whether, in its opinion, the development might
have a significant adverse impact on the environment or might be a cause of
public concern; and
(b) where it so
determines in the affirmative, refer the proposal to the Review Board for an
environmental assessment.
|
124.
(1) L’autorité administrative ou l’organisme
administratif désigné saisi, en vertu d’une règle de droit fédérale ou
territoriale mentionnée dans les règlements pris en vertu de l’alinéa 143(1)b),
d’une demande de permis ou d’autre autorisation relativement à un projet de
développement est tenu d’en informer l’Office par écrit et d’effectuer un
examen préalable du projet, sauf si celui-ci y est soustrait parce que, aux
termes des règlements pris en vertu de l’alinéa 143(1)c) :
a)
soit ses répercussions environnementales ne sont pas importantes;
b)
soit l’examen ne serait pas indiqué pour des motifs de sécurité nationale.
…
125. (1) Sauf dans les
cas visés au paragraphe (2), l’organe chargé de l’examen préalable indique,
dans un rapport d’examen adressé à l’Office, si, à son avis, le projet est
susceptible soit d’avoir des répercussions négatives importantes sur
l’environnement, soit d’être la cause de préoccupations pour le public. Dans
l’affirmative, il renvoie l’affaire à l’Office pour qu’il procède à une
évaluation environnementale.
|
[19]
Guiding
principles and purposes for the whole process are set out in ss. 114-115 as
follows:
114.
The purpose of this Part is to establish a process
comprising a preliminary screening, an environmental assessment and an
environmental impact review in relation to proposals for developments, and
(a) to establish the
Review Board as the main instrument in the Mackenzie Valley for the
environmental assessment and environmental impact review of developments;
(b) to ensure that
the impact on the environment of proposed developments receives careful
consideration before actions are taken in connection with them; and
(c) to ensure that
the concerns of aboriginal people and the general public are taken into
account in that process.
115.
The process established by this Part shall be carried out
in a timely and expeditious manner and shall have regard to
(a) the protection
of the environment from the significant adverse impacts of proposed
developments;
(b) the protection
of the social, cultural and economic well-being of residents and communities
in the Mackenzie Valley;
and
(c) the importance
of conservation to the well-being and way of life of the aboriginal peoples
of Canada to whom section 35 of the Constitution Act, 1982 applies and
who use an area of the Mackenzie Valley.
|
114.
La présente partie a pour objet d’instaurer un processus
comprenant un examen préalable, une évaluation environnementale et une étude
d’impact relativement aux projets de développement et, ce faisant :
a)
de faire de l’Office l’outil primordial, dans la vallée du Mackenzie, en ce
qui concerne l’évaluation environnementale et l’étude d’impact de ces
projets;
b)
de veiller à ce que la prise de mesures à l’égard de tout projet de
développement découle d’un jugement éclairé quant à ses répercussions
environnementales;
c)
de veiller à ce qu’il soit tenu compte, dans le cadre du processus, des
préoccupations des autochtones et du public en général.
115.
Le processus mis en place par la présente partie est
suivi avec célérité, compte tenu des points suivants :
a)
la protection de l’environnement contre les répercussions négatives importantes
du projet de développement;
b)
le maintien du bien-être social, culturel et économique des habitants et des
collectivités de la vallée du Mackenzie;
c)
l’importance de préserver les ressources pour le bien-être et le mode de vie
des peuples autochtones du Canada visés par l’article 35 de la Loi
constitutionnelle de 1982 et qui utilisent les ressources d’une région de
la vallée du Mackenzie.
|
[20]
Consultation
is set forth in s. 123.1 and applies only to the Review Board or a review
panel.
123.1
In conducting a review or examination of the impact on
the environment of a development, a review panel of the Review Board or a
review panel, or a joint panel, established jointly by the Review Board and
any other person or body,
(a) shall carry out
any consultations that are required by any of the land claim agreements; and
(b) may carry out
other consultations with any persons who use an area where the development
might have an impact on the environment.
|
123.1 Au cours de l’étude
d’impact ou de l’examen des répercussions environnementales d’un projet de
développement, la formation de l’Office ou la formation conjointe ou la
commission conjointe établie par l’Office et une autre autorité procède aux
consultations exigées par les accords de revendication et, en outre, elle
peut consulter toute personne qui utilise les ressources de la région où le
projet peut avoir des répercussions sur l’environnement.
|
[21]
The
Regulations set out in greater detail the process for the application for a
permit. An applicant for such a permit must set out particular details of the
land use in a preliminary plan. Particular quantitative and qualitative details
must be given where known and an inspector may make an inspection and report
back to the Board on his findings. The Board’s options are found at s. 22
of the Regulations:
22.
(1) The Board shall, within 10 days after receipt of an application for a
Type A permit,
(a) where the
application was not made in accordance with these Regulations, return the
application to the applicant and advise the applicant in writing of the
reasons for its return; or
(b)
notify the applicant in writing of the date of receipt of the application and
of the fact that the Board will take, subject to sections 23.1 and 24, one of
the measures referred to in subsection (2) within 42 days after its receipt.
(2) Subject to sections
23.1 and 24, if the Board does not return an application under paragraph (1)(a),
it shall, within 42 days after receipt of the application,
(a) issue a Type A
permit, subject to any conditions included pursuant to subsection 26(1);
(b)
conduct a hearing under section 24 of the Act or require that further studies
or investigations be made respecting the lands proposed to be used in the
land-use operation and notify the applicant in writing of the reasons for the
hearing, studies or investigations;
(c) refer the
application to the Mackenzie Valley Environmental Impact Review Board under
subsection 125(1) or paragraph 126(2)(a) of the Act for an
environmental assessment and notify the applicant in writing of its referral
and of the reasons for the referral; or
(d) if a requirement
set out in section 61 or 61.1 of the Act has not been met, refuse to issue a
permit and notify the applicant in writing of its refusal and of the reasons
for the refusal.
|
22.
(1) Dans les 10 jours suivant la réception de la demande d’un permis de type
A, l’office :
a)
dans le cas où la demande n’est pas conforme au présent règlement, la
retourne au demandeur et l’informe par écrit des motifs du rejet;
b)
dans tout autre cas, donne au demandeur un avis écrit indiquant la date de
réception de la demande et précisant qu’il prendra, sous réserve des articles
23.1 et 24, l’une des mesures visées au paragraphe (2) dans les 42 jours
suivant la réception de la demande.
(2) Sous réserve des
articles 23.1 et 24, lorsque l’office ne retourne pas la demande aux termes
de l’alinéa (1)a), il prend l’une des mesures ci-après dans les 42
jours qui suivent la réception de la demande :
a)
il délivre un permis de type A assorti de toute condition prévue au
paragraphe 26(1);
b)
il effectue une enquête en vertu de l’article 24 de la Loi ou exige la
réalisation d’études ou d’investigations supplémentaires au sujet des terres
visées par le projet et en communique les raisons par écrit au demandeur;
c)
il renvoie, aux termes du paragraphe 125(1) ou de l’alinéa 126(2)a) de
la Loi, la demande à l’Office d’examen des répercussions environnementales de
la vallée du Mackenzie afin que celui-ci procède à une évaluation environnementale,
et il en communique les raisons par écrit au demandeur;
d)
dans le cas où les exigences des articles 61 ou 61.1 de la Loi ne sont pas
respectées, il refuse de délivrer le permis et en communique les raisons par
écrit au demandeur.
[Emphasis added]
|
Section 22(2)(b) has been described as a “pause”
option where once a study is done, a new 42-day timeline begins.
[22]
The
importance of all these provisions lie in part in the Applicants’ reliance on
its understanding that if a First Nations send a letter expressing concerns
over consultation, s. 22(2)(b) of the Regulations will be triggered and
Indian and Northern Affairs Canada (INAC) will be alerted to these “assertion
letters” and thereby open the door to consultation.
[23]
In
addition to the Act and Regulations, the Board has established guidelines in
relation to permits and licence applications as an aid to those seeking a
permit. There are more general Public Involvement Guidelines for Permit and
Licence Applicants to the Mackenzie Valley Land
and Water Board as well as specific guidelines in relation to the Akaitcho Dene
First Nations. It is these guidelines and not the statutory scheme that explicitly
outline consultation with the affected First Nations at the preliminary stage.
For instance, the ADFN guidelines state that “it is important that proponents
meet face to face with ADFN prior to submission of an application”.
[24]
These
guidelines, although they do not have the force of law, are important in that
the government has indicated that it will look to the consultation engaged in
by proponents for permits to determine whether adequate consultation has
occurred.
[25]
In
addition to the Board’s policies regarding consultation, the Akaitcho have
developed their own guidelines (Akaitcho Exploration Guidelines) and a template
Exploration Agreement. The template agreement sets up a regular and ongoing
consultation process, requires employment and business opportunities (where
possible, the conduct of archaeological studies and monitoring (including site
visits)) and some mitigation measures. The costs of these measures are to be
borne by the proponent for the permit. In return, the First Nation offers their
support.
C. North Arrow
Inc. and the Phoenix Project
[26]
North
Arrow, a named Respondent but non-participant in this judicial review, is a
relatively small Vancouver-based exploration company with a technical office in
Yellowknife. Its business is the
acquisition of additional North American lithium exploration “opportunities”.
[27]
The
Phoenix project is located 340 kilometres northeast of Yellowknife in a remote area and on
Crown land. Previous research and prospecting had indicated the presence of
lithium.
[28]
North
Arrow wished to undertake more serious exploration and therefore was looking
for a permit to allow prospecting, mapping, ground geophysics and diamond
drilling of potential lithium targets on the property.
[29]
North
Arrow approached the Board in December 2008 about submitting an application for
a Type A land use permit for mineral exploration. The company official, a Mr.
Clarke, was advised to consult the affected First Nations.
[30]
In
early January 2009, an Akaitcho Treaty #8 screening officer at the IMA
Implementation Office received information from North Arrow in the form of a
lithium fact sheet and draft application for a permit. The screening officer
advised the screening board of the application later that month.
[31]
On
January 21, 2009, Mr. Clarke met with an official of the Yellowknives Land
& Environmental Office where he provided essentially the same information
he had earlier given to the screening officer.
[32]
Mr.
Slack of the Yellowknives Land & Environmental Office presented the
information in the application later in the month of February to the Chief and
Councils of the Yellowknives who decided that based on the information given,
the project could potentially impact the community. He decided to work towards
an agreement with North Arrow in order to identify and mitigate possible
impacts.
[33]
Mr.
Slack subsequently informed Mr. Clarke of a proposed exploration agreement
underlining the Band’s understanding of a junior company’s financial
limitations and indicating the willingness to negotiate. The e-mail indicated
that the Yellowknives had no significant concerns with the project so long as
the exploration agreement was entered into.
[34]
North
Arrow clearly wished to deal with only one point of contact with the Aboriginal
people rather than dealing with both Bands but that was not possible.
[35]
Upon
Mr. Clarke reviewing the proposed exploration agreement, he indicated that
while he was agreeable to certain aspects of notification of activity and
project updates, those aspects of the agreement requiring archaeological study,
environmental monitoring, jobs training and business opportunities were not
acceptable because they had no fixed costs and could not be borne by the
company. He also objected to the company being required to pay for the Chief,
Council and Senate Elders to attend a meeting between the corporation and the
Band.
[36]
North
Arrow filed its permit application with the Board on April 14, 2009, the same
day as Mr. Clarke’s letter indicating to the Yellowknives that the proposed
agreement was unacceptable. North Arrow advised the Board on that same date
that consultation with the Band was complete.
[37]
A day
later, Mr. Slack attempted to deal with Mr. Clarke’s concerns, underlined that
the agreement was in draft and that the Band was prepared to be flexible enough
to deal with both large and small companies. He further indicated that certain
areas were open to negotiation but concluded that in the absence of an
exploration agreement, the Yellowknives could not support the proposed project.
Mr. Clarke never responded to that letter.
[38]
North
Arrow was also in contact with Lutsel K’e but in an even less regular and
structured way. A Mr. Ellis sent Mr. Clarke an e-mail explaining the overlap in
territory between the two First Nations and the need to deal with both Bands. A
week later Mr. Clarke e-mailed to ask about a meeting with the First Nations.
[39]
While
Lutsel K’e had some notice of the project, the formal contact did not begin
until late February. At that time North Arrow e-mailed an information package
to Lutsel K’e’s Wildlife, Lands and Environment Department. Again, North Arrow
rejected proposals because the costs were too high but before Lutsel K’e could
respond with a more modest budget, the permit application was filed.
[40]
The
evidence is that there was no actual consultation or face-to-face meetings with
community members concerning the project beyond contact with Mr. Slack.
[41]
Upon
receiving the permit application, the Board notified the two First Nations,
among others, and invited written comments by May 6, 2009. The Board sought the
advice of the Screening Board and on May 4 and 6 respectively, the Yellowknives
and Lutsel K’e submitted letters to the Board being “assertion letters”
outlining the s. 35 rights and indicating that the applications would infringe
upon those rights.
[42]
The
Lutsel K’e in particular expressed concern that they were not consulted. They
generally outlined the traditional uses of the area particularly for hunting
and their belief that there were a number of historical and burial sites in the
area. The Lutsel K’e also outlined their view that the consultations were not
to be “token” as they had been in this instance. They rejected the suggestion
that they would not facilitate the relationship with small scale companies and
contended that North Arrow simply dismissed their proposals as unreasonable and
did not indicate that the company had heard the people’s concerns.
[43]
The
Yellowknives’ letter was similar in nature and content. The most striking
difference is the assertion of the need for an exploration agreement in these
terms: “Without a signed Exploration Agreement, the company and INAC must
ensure due consultation and accommodation in some other legally sufficient
manner. Otherwise, the YKDFN are left with no choice but to indicate that their
rights will be infringed”.
[44]
On
receiving these two letters, the Board invoked s. 22(2)(b) of the Regulations
to undertake “further study”. That further study appears to have been nothing
more than consulting INAC in order to determine whether adequate consultation
had occurred.
[45]
In
early June Mr. Clarke, on behalf of North Arrow, wrote to the Board’s staff
asking whether the duty to consult was the only thing standing in the way of
their application. The response was “the Board does not determine if Crown
consultation has occurred, INAC does. If INAC tells the Board that consultation
is complete, the Board will continue the process of issuing a land use permit”.
[46]
The
overwhelming evidence in this case from all native affiants confirms that the
Bands were never contacted by either the Board or INAC at any point
before the Permit was issued. To underscore, the affiants stated that they were
never contacted by any government department.
[47]
The
first contact from government, and in particular INAC, was August 2009 when a
Stephanie Poole was contacted by INAC asking whether she was aware of INAC’s
letter to the Board and how the Band might respond to a decision they did not
like.
[48]
In
fact, on June 29 INAC faxed to the Board a letter dated June 18 containing
their answers to the confirmation request concerning the duty to consult. It
was INAC’s position that “the legal duty to consult in this situation had
been met”.
[49]
The
details of the letter give an indication of how INAC could have reached this
conclusion that the duty to consult had been met:
·
The terms and
conditions recommended by other departments – so long as they are met or
exceeded – will mitigate any adverse effects on wildlife and the environment.
The First Nations raised issues of some adverse impacts as to cultural sites
but no specifics were given. INAC will assist in accommodating this concern by working
with the First Nations to identify them with the understanding the company
should adapt its work program to mitigate impact on these sites.
·
INAC points to the
Aboriginal involvement in the regulatory process and the fact that they take
into account procedural aspects of consultation which occurred in it. They
note the ADFN requests that North Arrow enter into an agreement and that their
response on the company’s refusal was “that they would not engage in such
consultative processes until an exploration agreement was signed”. The letter
goes on to say that it is INAC’s expectation that aboriginal groups “will not
frustrate reasonable attempts by companies to provide information about and
discuss potential resource exploration…” and that “accommodation will be
proportionate to the potential adverse impacts on their…rights”.
·
INAC also outlines
the other processes designed to ensure input (e.g. the IMA and its related
processes) and their expectation that aboriginal groups will use them.
[50]
On
July 16, 2009, the Board issued North Arrow the requested Type A Land Use
Permit for mineral explorations at Aylmer Lake. The Permit was for five years expiring July
15, 2014.
[51]
Attached
to the Permit was a list of conditions, five pages in length, issued pursuant to
the Regulations. Included in those conditions are specifications related to the
protection of historical, archaeological and burial sites (namely, that a
vehicle cannot be operated near one and that the Board must be notified on the
discovery of such a site) as well as general control of refuse, fuel storage
and restoration of lands. There is nothing specific listed pursuant to the
wildlife and fish habitat provisions of the Regulations.
[52]
It
is now obvious that in August 2009 when INAC contacted Stephanie Poole, the Akaitcho
Treaty #8 screening officer, the Permit had already been issued, indeed
drilling had already commenced.
III. ISSUES
[53]
The
Applicants raise a broad range of issues stemming from the Board’s decision but
their concerns are essentially the nature of the Board’s duties and the
delegation to INAC, the Board’s failure to comply with the Act and whether the
Crown breached its duty to consult.
[54]
While
the following issues are somewhat intertwined, they can be broken down as
follows:
1. What is the
nature of the Board’s jurisdiction in regard to consultation?
(a) Is
the Board required to determine whether the Crown’s duty to accommodate has
been met; did it err in delegating that determination to INAC?
(b) Did
the Board’s delegation to INAC result in a procedurally unfair decision (including
a reasonable apprehension of bias)?
2. Did
the Board fail to comply with the provisions of the Act, and in particular s.
62, by allegedly failing to comply with Part 5 and s. 60.1?
3. Was
the Crown’s duty to consult discharged (included in that issue is the nature
and scope of that duty to consult).
IV. ANALYSIS
A. Respondent’s
Motion to Strike
[55]
The
Respondent filed a motion to strike several of the Applicants’ affidavits in
whole or in part. Nine of the twenty-six affidavits filed are at issue.
The principal concern is
that the affidavits contain information that was not before the Board.
[56]
Five
of the affidavits sought to be struck in their entirety are from experts which
speak to the impact of the mining on the Akaitcho Dene First Nations or on
First Nations people generally.
The other affidavits,
where only parts are to be struck, are statements from members of the community
as to the importance of the land, the potential impacts and their own
experiences.
[57]
There
are parts of some of the affidavits which address legal issues and express
legal opinions; the Court is quite able to ignore these offending paragraphs.
However, some of the affidavits address relevant issues including the interests
that the First Nations have in the area, what constitutes consultation in their
terms, and the impacts of the project. They address in part whether the duty to
consult exists and why, as well as what adequate consultation might entail.
[58]
The
affidavits address the grounds of this application - the failure to consult and
the Board’s failure to properly exercise its jurisdiction. Given the facts of
this case and how consultation was allegedly conducted, it was not possible to
have this evidence before the Board because the Applicants were never given
that opportunity.
[59]
The
Notice of Application specifically raised procedural fairness, both in respect
of consultation and in respect of reasonable apprehension of bias. In such
instances it is expected that additional evidence will be introduced on
judicial review to support the arguments. The evidence is not received to
support the merits of the Permit itself or to allow the Court to expand or
contract the Permit per se but to show the nature of the rights and
interests at issue; the real importance of the procedural rights and their
scope.
[60]
This
Court, in Liidlii Kue First Nation v. Canada (Attorney General), [2000] 4 C.N.L.R. 123,
dealt with a similar case of a drilling permit and its impact on First Nations
groups in the Territory. The affidavits at issue in that case were virtually
the same as those in this case and in permitting them to be part of the record,
the Court set forth the following rationale:
31 The
requirement that a decision must only be reviewed on the basis of the material
before the decision-maker, applies when a decision is challenged on the ground
that it is based on an erroneous finding of fact made in a perverse or
capricious manner or without regard to the material before the decision-maker.
The challenge to the decision in this case is not based on those grounds. It is
based on the allegation that there was an obligation to adequately consult the
applicant, which consultation it is alleged did not occur and is not
contemplated.
32 Challenges to
decisions on the ground that procedural fairness has not occurred, because the
affected party has not been given adequate opportunity to present its case, are
likely to involve the adducing of information that was not before the
decision-maker. In the present case, evidence relating to the status of an
applicant, and whether a duty to consult exists, and the scope of that duty, is
relevant, even though it may not have been before the decision-maker. To the
extent that the new evidence relates to those issues, it is properly a part of
the application records.
[61]
Justice
Rothstein in Shubenacadie Indian Band v. Canada (Human Rights Commission),
[1998] 2 F.C. 198, spoke of both the “jurisdictional issues exception” and the
impossible position a party is in where there was an inadequate opportunity to
be heard yet a suggestion that their evidence and argument cannot be before
this Court because it was not before the tribunal who had precluded its
receipt.
40 … Given that a decision of an
administrative tribunal in excess of its jurisdiction "is not a decision
at all", it seems paradoxical that the same "decision" would be
immunized from review where jurisdiction is never raised and the tribunal's
jurisdiction and/or the constitutionality of its enabling legislation is assumed.
This is tantamount to saying that parties to an administrative proceeding may,
by waiver or acquiesence, confer jurisdiction on a tribunal that was not, or
could not be, conferred by Parliament, and that this conferral of authority by
the parties is unreviewable once the decision is made. Indeed, it is not
difficult to imagine a Tribunal falling into jurisdictional error simply
because it did not hear arguments on that issue.
[62]
In
the present case, the Applicants could not have been expected to adduce this
evidence to the Board regarding the failure to consult as the Applicants were
never afforded that opportunity.
[63]
There
is no evidence of prejudice to the Respondent. It knew that the issue before
the Court was the failure to consult and the existence and scope of that duty.
It had an opportunity to address those issues by evidence and argument well
before the hearing of this judicial review.
[64]
Therefore,
the evidence is allowed in for the purposes described above. Any offending
paragraphs such as those dealing with legal issues can be easily ignored (and
were) by this Court.
B. Standard
of Review
[65]
The
issue of the Board’s jurisdiction – whether it could and should have determined
the Crown’s duty to consult – is a question of law and should be judged on the
standard of correctness, as required by Dunsmuir v. New Brunswick, 2008 SCC 9 at
paragraph 59.
[66]
There
is no issue as to the existence of a duty to consult. The real issue is the
scope of the duty and whether that duty had been discharged.
[67]
With
respect to the standard of review governing the scope of the duty, in this case
there were no factual findings or analysis by the Board on this issue. INAC’s
letter to the Board deals with processes available to the Applicants and
whether the duty had been discharged. The issue of scope of the duty is
severable from that of discharge of that duty and is a question of law to which
the correctness standard is applicable.
[68]
As
to whether that duty to consult has been discharged, the analysis requires a
factual context determinable by the Board. This Court in Dene Tha’ First
Nation v. Canada (Minister of
Environment),
2006 FC 1354 at paragraph 93 and in Ka’a’Gee # 1, above, at paragraphs
91-93, concluded that reasonableness is the appropriate standard of review.
[69]
Although
the question of whether to issue a permit engages the Board’s expertise, the
question of whether the duty exists, its shape and in this case whether the
duty was fulfilled does not. In the present circumstances, the Board had
delegated to INAC the responsibility to determine the duty to consult
requirement.
[70]
Whether
the Act requires the Board to consider consultation is a restatement of the
jurisdiction issue earlier described. In Ka’a’Gee Tu First Nation v. Canada
(Minister of Indian and Northern Affairs), 2007 FC 764 (Ka’a’Gee #2),
the Court concluded that whether failure to consult leads to the conclusion
that the requirements of Part 5 of this Act have not been met is a question of
law reviewable on a correctness standard.
[71]
Therefore,
the question of whether the Act should be interpreted to include a duty to
consult is a question of correctness and is subsumed in the jurisdictional
issue. Whether the requirements of the Act were in fact carried out is one of
reasonableness.
C. Issue 1 –
The Extent of the Board’s Duties under the Act – Duty to Consult
[72]
The
issue to determine is whether the Board was required to determine that the duty
to consult existed and had been met.
[73]
The
Respondent’s position is that the Board is required to take the Aboriginal peoples’
concerns into account but it does not share the Crown’s duty to consult. The
Crown, it is argued, bears the duty and while it can take regulatory processes
into account in deciding whether the duty is met, it is the Crown which remains
responsible for meeting that duty. Therefore, the Board can proceed separately
from the Crown’s duty to consult.
[74]
The
Respondent concedes that if the Court determines that the Board had to decide
whether the Crown fulfilled its duty to consult, it delegated it away to INAC
and did not have authority to do so. It, however, argues that the duty was
discharged and that the decision should stand.
[75]
The
parties have made this issue and this litigation more complex than need be. The
Court will not make general pronouncements on the process as a whole but will
limit itself to those matters which are truly necessary to resolve the issue of
the validity of the Board’s decision to issue a permit to North Arrow.
[76]
The
real question is the scope of the Board’s responsibilities pursuant to the
statutory scheme and that issue is fairly easily resolved by considering the
language of the Act and the decision of Justice Blanchard in the two Ka’a’Gee
decisions. I adopt his reasoning both as a matter of judicial comity and as a
result of my concurrence with the rationale.
[77]
While
Ka’a’Gee #1 is relevant on the Crown’s duty to consult, Ka’a’Gee #2
is on point with respect to the Board’s responsibilities. That decision concerned
the Mackenzie Valley Land and Water Board’s
decision to issue an amended land use permit. The issue was whether the Crown’s
failure to consult resulted in a failure to meet the requirements of Part 5 of
the Act. Justice Blanchard concluded that it did:
66 Section
114 of the Act sets out the purpose of Part 5 which is "to establish a
process comprising a preliminary screening, an environmental assessment and an
environmental impact review in relation to proposals for development,..."
to, among other objectives, "ensure that the concerns of the Aboriginal
people and the general public are taken into account in that process." The
requirements of Part 5 are not directed to a Board or to the Ministers. Rather,
they are aimed at the process itself that must ensure the concerns of the
Aboriginal people are taken into account.
68 Inherent
in the Crown's duty to consult is the obligation to ensure that the concerns of
the Aboriginal people are taken into account. In my view this is the central
purpose of the obligation. By failing to meet its duty to consult and
accommodate in the circumstances of this case, the Crown cannot, therefore, be
said to have taken into account the concerns of the Aboriginal people, as
required by section 114 of the Act, before making its decision to approve the
Extension Project. Any other conclusion would not be consistent with my earlier
finding. Whether the duty to consult is characterized as constitutional or not
is immaterial in these circumstances, since the obligation need not be read in.
Section 114 of the Act expressly provides that the process must ensure that the
concerns of the Aboriginal people be taken into account. It follows that this
central requirement of Part 5 of the Act cannot be said to have been complied
with.
[78]
Section
114 and the duty to consult applies to the process as a whole. The preliminary
screening is part of the process. There is no basis, as argued by the
Respondent, to conclude that in some fashion s. 62 and s. 114 do not apply to
this part of the process.
[79]
It
is evident that the Board was also of the view that Crown consultation was a
necessary consideration in determining whether a permit should be issued. The
Board’s decision was premised on the assurance from INAC.
[80]
The
argument that the Board had no jurisdiction to consider whether the duty to
consult had been met, because there is no such statutory requirement, is
unsound. A similar argument was dismissed in Ka’a’Gee #2 as irrelevant
because what mattered was whether the concerns of Aboriginal people were taken
into account in the process.
69 As
noted earlier, the Respondents argue that as the Ministers have final
decision-making authority the Board has no authority to review ministerial
decision-making. While this may be so, the argument cannot serve to cure a
fundamental flaw in the process. The Crown's efforts in respect to the duty to
consult pursuant to the process under the Act were found to be inconsistent
with the honour of the Crown. It matters not, therefore, whether the Board had
the authority to question the process followed by the Responsible Ministers.
What matters is that the duty was breached and the concerns of the Aboriginal
people were not taken into account.
[81]
The
Respondent’s reliance on the decision in Standing Buffalo Dakota First Nation v
Enbridge Pipelines Inc., 2009 FCA 308, is misplaced. The decision also does not
support the Applicants’ position that the Board could presume to evaluate the
Crown’s duty to consult.
[82]
Standing
Buffalo
was concerned with whether the National Energy Board (NEB) had to undertake a
“Haida” type analysis of consultation in making its final determination. The
Court’s finding was that the NEB
was exercising its powers with respect to s. 35 of the Constitution Act, 1982.
The Board determined that it did not need to know whether the Crown had
discharged its duty to consult in order to render its decision.
[83]
In
the present case, the Board seemingly operates in compliance with both its
enabling legislation and s. 35 as its decision depends on whether the Crown’s
duty to consult is being discharged. Ka’a’Gee #2 indicates that this
type of determination is legally necessary. There is no suggestion that the
Board would dictate to the Crown that it was required to consult but it is
evident that the Board might have decided differently or conducted its own
process differently had it known the facts surrounding consultation.
[84]
In
light of Standing Buffalo and the two Ka’a’Gee cases which
suggest that questions of adequate consultation are for the courts to
determine, the issues of the Board’s alleged delegation to INAC or reasonable
apprehension of bias are not germane to this case.
[85]
The
Board was justified in inquiring of INAC whether consultation had taken place.
The substantive issue is whether the Board relied on proper information as its
decision was dependent on the response to that question of whether the duty had
been discharged. The Board’s failure to hear from the Applicants undermines the
Board’s information base as well as being procedurally infirmed.
D. Issue 2 –
Crown Duty to Consult and its Discharge
[86]
The
law as to what engages the duty to consult and its scope has been addressed in
numerous cases. At its core the duty to consult and accommodate is based upon
the honour of the Crown which requires honourable participation in processes of
negotiation with a view to reconciliation between the Crown and Aboriginal
people with respect to the interests at stake (Mikisew Cree First Nation v.
Canada (Minister of Canadian Heritage), 2005 SCC 69).
[87]
For
the duty to be engaged, there must be (i) an existing or potentially existing Aboriginal
right on title that may be affected by Crown contemplated conduct; and (ii) the
Crown must have knowledge (actual or implied) of these rights or title and that
they may be adversely affected.
[88]
As
held in Haida Nation v. British Columbia (Minister of Forests), 2004 SCC 73, the
content of the duty varies. It depends on the strength of the claim and the
impact of the proposed activity on the claimed right. This has given rise to
the concept of the “spectrum” from weak claim and negligible impact to strong
claim and severe adverse impact. Even at the lowest end, the Crown is required
to discuss issues raised without any assurance of remedy.
[89]
The
Respondent does not seriously argue that the duty to consult was not engaged.
The assertion letters clearly point to significant interests including burial
sites, trails, caribou hunting and other uses of the land. The exploration
could have impact on those rights. The fact that conditions were imposed in the
Permit to mitigate impacts is, at the very minimum, suggestive of some impact.
[90]
This
is not a case like Brokenhead Ojibway Nation v. Canada (Attorney General), 2009 FC 484, where the
rights at issue were “peripheral”. (In that case, the potential development was
on private land already used for such development purposes – not traditional
use.) In this case, the land is Crown land on which there are accepted
assertions of traditional use. Further, there remains live debate as to the
nature of the 1900 Treaty, the rights attached to the land and the control over
it.
[91]
At
this stage (and the Applicants’ comments that more study and consultation would
show more impacts), the impacts are in the mid-range. They certainly give rise
to the right to be consulted as to ways by which impacts are to be mitigated,
how the people will continue to be informed of the developments in the project
and how existing and new concerns will be accommodated.
[92]
The
Supreme Court’s comments in Mikisew, above, where the duty was at the
low end of the spectrum (whereas here it is further along the spectrum) are
apt:
64 The
duty here has both informational and response components. In this case, given
that the Crown is proposing to build a fairly minor winter road on surrendered
lands where the Mikisew hunting, fishing and trapping rights are expressly
subject to the "taking up" limitation, I believe the Crown's duty
lies at the lower end of the spectrum. The Crown was required to provide notice
to the Mikisew and to engage directly with them (and not, as seems to have been
the case here, as an afterthought to a general public consultation with Park
users). This engagement ought to have included the provision of information
about the project addressing what the Crown knew to be Mikisew interests and
what the Crown anticipated might be the potential adverse impact on those
interests. The Crown was required to solicit and to listen carefully to the
Mikisew concerns, and to attempt to minimize adverse impacts on the Mikisew
hunting, fishing and trapping rights. The Crown did not discharge this obligation
when it unilaterally declared the road realignment would be shifted from the
reserve itself to a track along its boundary. I agree on this point with what
Finch J.A. (now C.J.B.C.) said in Halfway River First Nation at paras.
159-60.
The fact that adequate notice of an intended decision may have
been given does not mean that the requirement for adequate consultation has
also been met.
The Crown's duty to consult
imposes on it a positive obligation to reasonably ensure that aboriginal
peoples are provided with all necessary information in a timely way so that
they have an opportunity to express their interests and concerns, and to ensure that their representations are seriously
considered and, wherever possible, demonstrably integrated into the proposed
plan of action. [Emphasis added.]
[93]
The
Respondent correctly argues that the Crown can rely on the actions of others in
assessing whether the duty to consult had been discharged. It can delegate
responsibility to take certain consultative steps to third parties such as
North Arrow but the underlying duty remains that of the Crown. The third
parties are akin to a limited purpose agent for the Crown but not its delegate.
It is the final responsibility of the Crown, not the Board or North Arrow.
[94]
The
problem is not that the Crown and Board looked to the “consultation” undertaken
by North Arrow; the problem is that they wrongly considered it to be adequate.
[95]
The
Crown (INAC) and the Board effectively relied on the word of one party to the
“consultations” – it accepted North Arrow’s assertion that consultation was
complete and that the First Nations had frustrated the process. The evidence is
quite to the opposite effect. Even the Yellowknives’ last reply e-mail
indicated an openness to negotiation.
[96]
On
the other hand, North Arrow cut off negotiations at the first offer and failed
to follow the Board’s guidelines on consultation. This North Arrow may do with
legal impunity for it is so constitutionally obligated to the First Nations.
However, the Crown cannot shelter behind North Arrow or absolve itself of its
obligations by having a third party undertake negotiations. The Crown and thus
the Board are impacted on North Arrow’s petard.
[97]
In
negotiations, the parties may engage in hard bargaining. First Nations run the
risk of demands being rejected and third parties walking away from the table.
But so long as a third party is still seeking to conduct activities on First
Nations’ land or in a way that impacts their interests, the Crown remains
obligated to at least consult and accommodate.
[98]
In
this case, no federal department or Board discussed either the project with the
Applicants, or the mitigating measures, nor did they confirm with the
Applicants the statements of North Arrow.
[99]
The
Respondent’s reliance on the regulatory process to cure the lack of contact
with the Applicants is on weak ground. While adequate regulatory consultation
may discharge the duty to consult, that does not relieve the Crown of the
responsibility to assess whether the duty has been discharged.
121 It is
not enough to rely on the process provided for in the Act. From the outset,
representatives of the Crown defended the process under the Act as sufficient
to discharge its duty to consult, essentially because it was provided for in
the Act. I agree with the Applicants that the Crown's duty to consult cannot be
boxed in by legislation. That is not to say that engaging in a statutory
process may never discharge the duty to consult. In Taku, at paragraph
22, the Supreme Court found that the process engaged in by the Province of British Columbia under
the Environmental Protection Act of that jurisdiction fulfilled the
requirements of the Crown's duty to consult. The circumstances here are
different. The powers granted to the Ministers under the Act must be exercised
in a manner that fulfills the honour of the Crown. The manner in which the
consult to modify process was implemented in this case, for reasons expressed
herein, failed to fulfill the Crown's duty to consult and was inconsistent with
the honour of the Crown.
Ka’a’Gee
#1, above, at para. 121
[100] Ka’a’Gee #1 only goes so far in its
endorsement of the regulatory scheme as assuring the discharge of the duty to
consult. The facts in that case covered all three stages of the process where
there were significant consultations, discussions and means by which the First
Nations had input. The legislation provides for different types of consultation
depending on the stage of the process.
[101] The Crown through INAC failed
to evaluate whether, on the facts of this particular case, the regulatory
process fulfilled its consultative duties. The scarcity of any provisions
regarding consultation where the preliminary assessment is concerned is
telling. There are no provisions similar to those in the Ka’a’Gee cases.
[102] It is only the
guidelines which give specifics on consultation and even those were not
followed. It is not sufficient, even if it occurred in this case, to have a
process, framework or some other system to facilitate negotiation. It is still
necessary to evaluate the actual implementation and processes specific to the
case. It is not sufficient to set up some form of elaborate system and then put
it on auto-pilot and hope for success.
[103] The Respondent argues
that the First Nations’ concern was not specific enough but they were
sufficient enough to engage the duty to consult. Had that duty been met, either
the specifics would have been developed or their inadequacy exposed or any
problems settled; but without real consultation, none of these results could be
obtained.
[104] The Respondent has the
difficult task of arguing that on the one hand, the Board cannot evaluate
whether the duty to consult has been met, and on the other, that the process
which the Board follows is such that the Crown need not actually consult – because
the duty is fulfilled.
[105] In this case, no one
took responsibility for ensuring meaningful consultation. The duty was not met.
The Applicants were not necessarily entitled to all that they would like but
they were entitled to some substantial actual consultation.
E. Issue 3 –
The Board’s Compliance with the Act’s Requirements
[106] Having concluded that
all parts of the process are subject to the Part 5 requirements that the
concerns of the Aboriginal people be taken into account, which includes whether
the Crown’s duty has been discharged, this issue is then dependent on the
determination of Issue 2.
If the Crown did not
discharge its duty, then in granting the Permit, the Board failed to comply
with the requirements of the Act.
[107] Independent of Issue 1,
if the Board did not take the concerns of the Aboriginal people into account or
failed to act fairly, the decision is subject to being quashed for those
reasons.
[108] As held in Standing
Buffalo, a federal board must act in accordance with s. 35. This is
confirmed in the Board’s legislation and in its own guidelines.
[109] Taking the Aboriginal
people’s concerns into account entails at least serious consideration of those
concerns. However, in the present case, the Applicants had no chance to comment
on any of the proposed conditions. Indeed they were never given notice of them.
[110] The Board never gave the
Applicants an opportunity to express their concerns – nor did any federal
government department.
[111] Aside from not affording
the Applicants an opportunity to address their concerns, the Board acted on
North Arrow’s statement as to consultation, as did INAC, without ever hearing
from these First Nations in response. They never inquired into the existence,
nature or manner of the so-called consultations.
[112] The Board compounded the
problem by simply accepting INAC’s assurances.
[113] The facts are that North
Arrow did not act in accordance with the Board’s guidelines on consultation.
There were no face-to-face meetings with chiefs on issues; no real meetings
with the communities and no attempt to address any of the communities’ or
leaders’ ideas into North Arrow’s proposal. North Arrow simply refused to
negotiate.
[114] INAC did nothing more
than accept North Arrow’s assurances and advise the Board that consultation had
occurred. There was no independent inquiry by either body much less an “opportunity
to be heard” for the Applicants. These actions (or lack thereof) were contrary
to the Board’s obligations and to the principles of fairness.
[115] Therefore, the Permit
cannot stand.
V. COSTS
[116] The parties were
requested to either arrive at agreed costs including a lump sum amount or the
method of calculating costs or otherwise make submissions to the Court. The
parties were unable to agree.
[117] The Applicants proposed
a lump sum amount of $80,000 covering fees and disbursements for the motion to
strike affidavits or portions thereof, and the application for judicial review
inclusive of both Applicants.
The Respondent’s
position is that each party bear its own costs.
[118] Given the result and the
absence of anything to suggest that the Applicants’ proposal is unreasonable,
and taking account of the nature of the proceeding and its difficulties, the
Applicants’ lump sum proposal is reasonable.
[119] Therefore, the
Applicants shall have costs as a lump sum of $80,000 inclusive of fees and
disbursements.
“Michael
L. Phelan”
Ottawa,
Ontario
November
12, 2010