The Road Ahead
Progress Against the 2000-2001 Road Ahead
| Targeted Areas for Improvement* | Targeted Completion Date* | Status | On track? | Roll Forward into Road Ahead 2002? |
|---|---|---|---|---|
| Implementing the Customs Action Plan initiatives
|
2001-2005
|
Partial implementation of commercial AMPS.
|
|
Yes
See item 1 below
|
| Implementation of CSA including driver registration, carrier and importer pre-approval, and passage processing for low-risk shipments.
|
|
Yes
See item 1 below
|
||
| Completed evaluation of NEXUS Highway Pilot. Working towards expansion to B.C. and Southern Ontario locations by summer of 2002.
|
|
Yes
See item 1 below
|
||
| Finalized detailed program requirements for the Expedited Passenger Processing System (EPPS)—now referred to as NEXUS-AIR. Delay in rolling out the system compared to commitment made in the Corporate Business Plan.
|
|
Yes
See item 1 below
|
||
| Continued implementation of the Integrated Primary Inspection Line at all major airports and bus offices.
|
|
No
|
||
| Increased stability and availability of Accelerated Commercial Release Operations System (ACROSS).
|
|
No
|
||
| ACROSS interface with the Department of Foreign Affairs and International Trade (DFAIT) Import Processing System implemented in June 2001.
|
|
No
|
||
| Systems design and development continued on the Integrated Customs System in support of Advanced Passenger Information and Passenger Name Record.
|
|
Yes
See item 1 below
|
||
| Implementing Compliance Improvement Plan
|
2001-2005
|
Some advances were made with respect to process and training plans; however, overall progress did not meet expectations.
|
|
Yes
See item 2 below
|
| Implement the CCRA's performance measurement framework
|
2001-2004
|
In step with the broader implementation of the Balanced Scorecard (BSC), work progressed on the development of BSC measures and indicators. However, at a corporate level, the Agency did not progress as expected, falling short in the overall phased-in implementation of the BSC. We are now back on track in 2002-2003.
|
|
Yes
See item 4 below
|
*Source: Prior year Annual Report to Parliament (2000-2001)
Attachment 1: Logic Model
This following logic model offers a roadmap showing the links between our inputs, activities and outputs that are essential to achieving our anticipated results in support of our expected outcome. It also shows how these fit into the Agency's overall strategic outcomes. This logic model is the foundation of our performance report card which summarizes our performance against each anticipated result.
Attachment 2: Service Standards in Customs
|
|
Met or exceeded target
|
|
Target mostly met (at least 95%)
|
|
Target not met
|
|
New or modified service standard
|
Explanatory notes
Standard 1: The percentage given is for releases processed on the ACROSS Worklist Platform within 45 minutes.
Standard 2: The monitoring of the five-minute processing standard for machine release is currently under development.
Standard 3: Sample for RMD paper releases was 6,419 out of a total population of 1,974,058. The sample was conducted over four days in June and November 2001.
Standard 4: The percentage given is for releases processed on the ACROSS Worklist Platform within 45 minutes. The current timing reports generated from the ACROSS system only monitor the ACROSS Worklist/Processing time for a transaction. As the service standard for PARS-EDI includes the client transmission time, data reflecting the standard is incomplete at this time.
Standard 5: The sample for PARS paper releases was 2,176, out of a total population of 1,231,403. The sample was conducted over four days in June and November 2001.
Standard 6: Information is an estimate based on samples collected for the period of April 1, 2001, to September 1, 2001. Data collection was suspended due to the events of September 11, 2001.
Standard 7: Studies of wait times for the payment of duties and taxes have not been considered necessary, due to dramatic declines in small collections in recent years.
New Service Standards for 2002-2003
| New standards and related targets | ||
|---|---|---|
| Customs Services
|
First Tier Automated Customs Information Systems (ACIS)
|
under development
|
Improvements to Existing Service Standards for 2002-2003
| Improvements to existing standards in 2002-2003 | |
|---|---|
| Customs Services
|
Improved monitoring to support reporting on existing service standards
|