Date: 20080121
Docket: T-1585-06
Citation: 2008 FC 73
Ottawa, Ontario, January 21,
2008
PRESENT: THE CHIEF JUSTICE
BETWEEN:
ATTORNEY
GENERAL OF CANADA
Applicant
and
MARK
McKINDSEY
Respondent
REASONS FOR JUDGMENT AND JUDGMENT
[1] The
respondent, Mark McKindsey, is employed as an oiler on Quest, an
auxillary vessel of the Canadian Forces.
[2] According to
paragraph 1(d) of Annex “B” Conventional Work System (paragraph 1(d)) of the
applicable collective agreement (the collective agreement), the respondent’s
“normal daily hours of work shall be between 06:00 hours and 18:00 hours and
employees shall be given forty-eight (48) hours notice of any change in
scheduled starting time” (at page 259 of the applicant’s record).
[3] On July 16,
2003, while the Quest was in dry dock in Halifax, the
respondent was directed to work from 16:00 hours to 24:00 hours for the next
two days, July 17 and 18.
[4] The
respondent complied with this direction to work outside the “normal daily hours
of work” even though the required 48-hour notice was not provided by the
employer.
[5] Although the
issue was contested before the adjudicator, the parties now agree that the
employer was required to provide the respondent with the 48-hour notice of the
change in the scheduled starting time (the notice requirement) and that the
employer failed to do so.
[6] In addition
to his principal finding that the employer failed to comply with the notice
requirement, the adjudicator also ordered that the respondent was “... entitled
to receive payment at the time and one-half (1-½) rate for all hours worked
after 18:00 hours on July 17 and 18, 2003” (the monetary remedy).
[7] The applicant
challenges the adjudicator’s monetary remedy. The applicant’s principal ground
is that the adjudicator, in the circumstances of this case, has no express
power to award damages as a consequence of the employer’s breach of the
collective agreement. He is limited to making a declaration of the breach.
From the applicant’s perspective, the declaration here is the remedy.
[8] The parties
acknowledge that the issue of a monetary remedy, in the range of $160 in this
case, was not fully argued before the adjudicator. Procedural fairness was not
raised in this proceeding to challenge the adjudicator’s decision.
The Relevant
Provisions of the Collective Agreement
[9] A proper
understanding of the adjudicator’s decision requires a review of the relevant
provisions of the collective agreement.
[10] The notice
requirement is set out in paragraph 1(d):
For employees who regularly
work five (5) consecutive days per week on “non-watchkeeping” vessels the hours
of work shall be consecutive, except for meal periods,
and
the normal daily hours of work
shall be between 06:00 hours and 18:00 hours.
and
employees shall be given
forty-eight (48) hours notice of any change in scheduled starting time.
[11] Paragraph
1(d) does not provide for a monetary remedy where there has been a breach of
the 48-hour notice requirement.
[12] In concluding
that the respondent should be indemnified time and one-half in compensation for
the employer’s breach of the notice requirement, the adjudicator referred to
paragraph 2.03 (c) of Appendix “G” Ships’ Crews Specific Provisions and Rates
of Pay (page 248 of the applicant’s record): “… an employee shall be entitled
to compensation at time and one-half (1½) for overtime worked by the employee”.
[13] Other provisions
of the collective agreement, not identical but similar to paragraph 1(d),
specify a remedy where the employer changed scheduled hours of work without
seven days prior notice. One example is found in paragraph 2.04(a) of Appendix
“B” General Labour & Trades Group (page 168 of the applicant’s record):
“An employee whose scheduled hours of work are changed without seven (7) days
prior notice: (a) shall be compensated at the rate of time and one-half
(1½) …”.
[14] Two other
provisions similar to paragraph 2.04(a) of Appendix “B” are found at pages 221
and 236 of the applicant’s record.
[15] In attacking
the adjudicator’s award of damages, the applicant relies principally on
subsection 96(2) of the Public Service Staff Relations Act, R.S.C. 1985,
c. P-35:
|
(2) No adjudicator shall, in respect of any grievance, render any
decision thereon the effect of which would be to require the amendment of a
collective agreement or an arbitral award.
|
(2)
En jugeant un grief, l’arbitre ne peut rendre une décision qui aurait pour
effet d’exiger la modification d’une convention collective ou d’une décision
arbitrale.
|
The parties agree that
this legislation, now repealed, was in force at all times relevant to this
proceeding.
The Adjudicator’s
Decision
[16] The adjudicator understood that paragraph 1(d) of the collective
agreement, unlike his experience with other collective agreements, did not
explicitly provide for a penalty in the form of overtime compensation:
¶50 The employer and bargaining agent
have not specified in the collective agreement a consequence where the employer
fails to provide the required 48 hours notice under paragraph 1(d). This is
not, for example, a situation where the collective agreement explicitly imposes
a penalty in the form of overtime compensation, as is the case under some
collective agreements where the employer fails to provide the required advance
notice of a change in an employee’s shift schedule. …
[17] The adjudicator also acknowledged that the respondent’s
scheduled hours of work did not meet the definition of “overtime” at paragraph
2.01(q) of the collective agreement (see paragraph 52 of his decision and page
114 of the applicant’s record):
¶58 … I find, however, that the arguments
made by [the respondent] are not sufficient to overcome a plain reading of the
language used in the collective agreement. The definition of “overtime” in
the collective agreement clearly states that the hours worked must be “in
excess of” the employee’s scheduled hours of work. …
¶59 Taken within the context of paragraph
1(a) of Annex “B” which establishes a daily work requirement of eight hours, it
follows from the foregoing analysis that the [respondent’s] scheduled hours of
work must have exceeded eight hours in order to meet the definition of
overtime. The facts are that they did not. Barring this condition precedent,
the entitlement to premium pay pursuant to clause 2.03 of Appendix “G” is
not triggered. (emphasis added)
[18] However, the adjudicator concluded that “corrective action”
for the employer’s breach of the collective agreement was necessary to prevent
the employer from enjoying “… free license to ignore the advance notice
provision at will, …”:
¶61 … Is there corrective action
available beyond declaring the breach of the collective agreement? If the
answer to this question were in the negative, the employer could, in effect,
enjoy free license to ignore the advance notice provision at will, leaving this
aspect of paragraph 1(d) devoid of any practical significance. The parties
presumably included the notice requirement in paragraph 1(d) for good reason. I
feel bound, as a result, to determine whether I can give it substantial meaning
beyond declaring a breach of the collective agreement.
The adjudicator’s
concern that he give paragraph 1(d) “…substantial meaning beyond declaring a
breach” suggests that he was searching for a monetary remedy which may have not
been envisaged by the parties to the collective agreement.
[19] The adjudicator understood that paragraph 1(d)
provided no remedy for the breach of the notice requirement. Yet, he crafted a
monetary remedy on his view that the rescheduled hours of work were analogous
to overtime:
¶64 … The normal consequence under the
collective agreement where work does not form part of scheduled hours is the
payment of premium compensation, principally in the form of overtime. I,
therefore, believe that it is reasonable in the circumstances of this case, and
in the absence of explicit guidance in the collective agreement as to the
consequences of the employer’s failure to respect the 48 hours notice
requirement, to consider the time worked by grievor McKindsey after 18:00 hours
as equivalent to “work in excess of the employee’s scheduled hours of work”
within the meaning of paragraph 2.01(d) [sic] definition of “overtime”.
As such, they should attract compensation at the premium rate of time and
one-half (1-½) in accordance with paragraph 2.03(c) of Appendix “G” … (emphasis
added)
[20] The adjudicator’s monetary remedy was, in his words,
to compensate “… hours which are not within an employee’s proper schedule”. He
also explained that he was not amending the collective agreement:
¶65 In reaching this conclusion, I do not
believe that I am amending or compromising the existing framework of the
collective agreement. … the corrective action is congruent with the overall
system of the collective agreement put in place by the parties.
The Standard of Review
[21] The principal issue identified by the parties is whether the
adjudicator erred in awarding the respondent overtime compensation as a result
of the employer’s failure to comply with the notice requirement. Put
differently, could the adjudicator order corrective action, absent any specific
provision to that effect in the collective agreement, in view of subsection
96(2) of the Public Service Staff Relations Act?
[22] Counsel for the respondent, in particular, has reminded the
Court that the decision of an adjudicator acting within the scope of the
collective agreement should attract the highest curial deference: for example, Canada (Attorney General) v.
Séguin,
[1995] F.C.J. No. 1178 (QL)(T.D.); Barry v. Canada (Treasury Board),
[1997] F.C.J. No. 1404 (QL)(C.A.); Currie v. Canada (Customs and Revenue
Agency), 2006 FCA 194 at paragraphs 20-22. Counsel also noted the
jurisprudential trend from the Supreme Court of Canada signaling a broader
approach to the remedial powers of an adjudicator: Public Service Alliance
of Canada v. Nav Canada, [2002] O.J. No. 1435 (QL)(C.A.) at paragraphs 27-42.
[23] The applicant characterized the issue as jurisdictional or one
of statutory interpretation. In either event, I am satisfied, as conceded by
the applicant at the hearing, that the adjudicator’s expertise in the
circumstances of this proceeding invites a standard of review other than
correctness: Dynamex Canada Inc. v. Mamona, 2003 FCA 248 at paragraph
26. The applicant now urges the standard of reasonableness to review the
outcome of this case.
[24] During the hearing, the respondent also modified his written
submissions concerning the standard of review. He framed the issue as twofold.
The respondent conceded that the question as to whether the adjudicator can award
damages in the absence of an express provision in the collective agreement
should be subject to a reasonableness test. According to the respondent, the
second issue as to whether the adjudicator should have awarded damages
in this case attracts a patently reasonableness standard.
[25] The relevant inquiry in this proceeding is whether
the collective agreement envisaged the adjudicator making the monetary remedy,
even keeping in mind his broad remedial powers. If not, the adjudicator may be
said to have provided a remedy that is outside the ambit of the collective
agreement.
[26] Until 1992, the former Public Service Staff Relations Act
contained a privative clause which Parliament then repealed in the Public Service
Reform Act, S.C. 1992, c. 54, section 73. Thereafter, the legislation was
silent on the standard of review. The parties acknowledge that no privative
clause in the collective agreement applies to this case. The one at pages 32-33
of the applicant’s record is for a different adjudication process.
[27] The purpose of adjudication is to facilitate the timely
resolution of disputes between the employer and the union. The relative
expertise of adjudicators in these matters is not in issue.
[28] The question of the monetary remedy coming within the scope
of the adjudicator’s role pursuant to the terms of the collective agreement is
one of mixed fact and law. Also, the decision of a statutory labour board,
such as the Public Service Staff Relations Board, may attract greater curial
deference than that of an adjudicator: Public Service Alliance of Canada v. Canada (Canadian Food
Inspection Agency),
2005 FCA 366 at paragraph 21. Whether the adjudicator is named in the
collective agreement, chosen by the parties or appointed by the Board pursuant
to section 95 of the Act should not affect the degree of curial deference. In
this case, the Court has not been told who appointed the adjudicator.
[29] Balancing these factors, I am satisfied that the appropriate
standard as to whether the adjudicator could make the monetary remedy is
reasonableness.
[30] Whether the adjudicator should have made the monetary
remedy is to be scrutinized against the patent unreasonableness standard.
However, the decision must be supportable on the evidence that was presented to
him: Reibin v. Canada (Treasury Board), [1996] F.C.J. No.
794(QL) (T.D.) at paragraph 15; Canada (Attorney General) v. Wiseman, [1995] F.C.J. No. 692
(QL) (T.D.) at paragraph 17.
Analysis
[31] The applicant’s position is straightforward. The
adjudicator’s mandate was to determine if the employer breached the notice
requirement. The respondent’s remedy was the adjudicator’s declaration that
there was a breach. In making such a finding, the adjudicator made the parties
“whole” in the absence of any evidence that the breach caused any financial
loss. The monetary award in this case was not contemplated by the parties to
the collective agreement. The adjudicator’s corrective action is a remedy in
the nature of punitive damages. This remedy was contrary to the collective
agreement and to the terms of subsection 96(2) of the Public Service Staff
Relations Act.
[32] The respondent’s position is equally succinct. The core
principle of the grievance process is to make the employee “whole”, in the
absence of any specific remedial provision to the contrary. The case law
affords adjudicators broad remedial jurisdiction to fashion a remedy
appropriate to the circumstances. In the absence of “explicit guidance”
concerning a monetary remedy in the collective agreement, it was open to the
adjudicator to apply the overtime provisions. The adjudicator’s remedy was
consistent with the collective agreement and the broad remedial jurisdiction of
labour adjudicators.
[33] Support for the applicant’s position that the monetary remedy
was beyond the scope of the collective agreement can be found in the
adjudicator’s own words:
·
“[t]he
employer and bargaining agent have not specified in the collective agreement a
consequence where the employer fails to provide the required 48 hours notice
under paragraph 1(d)”: paragraph 50
·
“[t]he
plain wording of the collective agreement definition of overtime does not
support the grievors’ claim for overtime compensation”: paragraph 56
·
“the
arguments made by [the respondent] are not sufficient to overcome a plain
reading of the language used in the collective agreement. The definition of
“overtime” in the collective agreement clearly states that the hours worked must
be “in excess of” the employee’s scheduled hours of work. …” (emphasis
added): paragraph 58
·
“… it
follows from the foregoing analysis that the [respondent’s] scheduled hours of
work must have exceeded eight hours in order to meet the definition of
overtime. The facts are that they did not. Barring the condition precedent, the
entitlement to premium pay pursuant to clause 2.03 of Appendix “G” is not
triggered.” (emphasis added): paragraph 59
·
“[w]hether
it is fair or appropriate for the employer to be able to reschedule work in
this fashion without a requirement to pay overtime or otherwise compensate [the
respondent] beyond [his] regular pay is a question that must be left to the
employer and the bargaining agent” (emphasis added): paragraph 60
These statements again
indicate the adjudicator’s concern, if not his understanding, that a monetary
remedy for the breach of the notice requirement was not envisaged by the
parties to the collective agreement.
[34] There are other passages from the adjudicator’s decision
which indicate his awareness that he may have been acting outside the scope of
the collective agreement, perhaps even to sanction the employer for its breach
of the notice requirement or, at least, to serve as a deterrent:
·
“[a]m
I left, therefore, with no corrective action for grievor McKindsey other than
to declare the breach of the collective agreement?”: paragraph 50
·
“[i]f
the answer to this question were in the negative, the employer could, in
effect, enjoy free licence to ignore the advance notice provision at will,
leaving this aspect of paragraph 1(d) devoid of any practical significance”:
paragraph 61
·
“I,
therefore, believe that it is reasonable in the circumstances of this case, and
in the absence of explicit guidance in the collective agreement … to consider
the time worked by grievor McKindsey after 18:00 hours as equivalent to “work
in excess of the employee’s scheduled hours of work” within the meaning of
paragraph 2.01(d) [sic] definition of “overtime””: paragraph 64
·
“[i]n
reaching this conclusion, I do not believe that I am amending or compromising
the existing framework of the collective agreement: paragraph 65
[35] In this case, the respondent acknowledges that the employer
was acting in good faith. The breach of the notice requirement resulted from
the employer’s honestly-held but mistaken view of the collective agreement. In
these circumstances, the need for “corrective action” or a deterrent is not
adequately explained by the adjudicator.
[36] The adjudicator, furthermore, compared the collective
agreement in this case with others which explicitly provided for a monetary
remedy (at paragraph 50):
This is not, for example, a situation
where the collective agreement explicitly imposes a penalty in the form of
overtime compensation, as is the case under some collective agreements
where the employer fails to provide the required advance notice of a change in
an employee’s shift schedule. (emphasis added)
[37] In drawing this distinction with other collective
agreements, the adjudicator makes no mention of three other clauses, in the
collective agreement he was interpreting, which specified time and one-half
compensation where scheduled hours of work were changed without seven days
prior notice (at pages 168, 221 and 236 of the applicant’s record). Had he
referred to these clauses, his interpretation of the collective agreement and
his ability to make the monetary remedy pursuant to paragraph 1(d) might have
been different. The collective agreement must be interpreted as a whole and not
in the abstract: Richmond v. Canada (Attorney General), [1996] 2 F.C. 305
(T.D.) at paragraph 5.
[38] The respondent argues that the parties’ failure to provide
for any additional remuneration in paragraph 1(d) allowed the adjudicator to
establish a monetary remedy at any amount he deemed appropriate. I do not
consider this submission to be a reasonable interpretation of the bargain made
by the employer and the union in the collective agreement.
[39] In summary, the adjudicator’s conclusion that he
could award a monetary remedy cannot withstand “a somewhat probing examination”
as a reasonable interpretation of the collective agreement. The adjudicator’s
monetary remedy was not contemplated in the collective agreement. The
adjudicator himself conceded that “the plain language” of the collective
agreement did not specify that the respondent’s new hours of work constituted
“overtime”. The parties acknowledge that the employer’s breach of the notice
requirement was made in good faith. Nonetheless, the adjudicator concluded that
without “corrective action” the employer could “… enjoy free license to ignore
the advance notice provision at will”. This view is speculative. In the absence
of any language providing for additional compensation as a consequence of a
breach of paragraph 1(d), the adjudicator erred in creating his monetary remedy:
Canada (Attorney General) v. Hester, [1997] 2 F.C. 706 (T.D.) at
paragraph 18; Canada (Attorney General) v. Lussier, [1993] F.C.J. No. 64
(C.A.) per Justice Létourneau.
[40] The adjudicator did not take into consideration, in
my view, all of the relevant provisions of the collective agreement. Had he
done so, he should have concluded that the collective agreement envisaged no
monetary remedy as a result of the breach of the notice requirement in
paragraph 1(d) with respect to employees on “non-watchkeeping” vessels.
[41] If I am wrong in concluding that the adjudicator’s
determination as to whether he could make a monetary remedy was subject
to the reasonableness standard or if I have erred in finding that the
adjudicator’s interpretation of the collective agreement was unreasonable, I
would still set aside his decision as being patently unreasonable.
[42] First, the respondent did not seek a monetary remedy
in presenting his grievance. In paragraph 4 of his decision, the adjudicator
quoted the corrective action sought by the respondent:
McKindsey:
I would like a clear description of the conventional work system as to how it
applies to “Quest” i.e., for hrs worked 16-24 hrs at applicable rate. An
explanation as to why Management disregarded QHM Standing Orders, Master
Standing Orders and our collective agreement with regard to work hrs.
[Sic
throughout]
[43] Second, there is no evidence of any financial loss in
the record
placed before the Court. This is consistent with the parties’ acknowledgment
that the respondent presented no evidence of damages before the adjudicator. As
another adjudicator has noted, damages must be certain and not speculative: Chénier
v. Treasury Board (Solicitor General Canada – Correctional Service), 2003 PSSRB 27. In Chénier,
no aggravated damages were awarded, although the adjudicator was of the view
that his broad remedial powers allowed him to do so in the circumstance of that
case.
[44] Third, the monetary remedy of some $160 is, at the very
least, more than the respondent’s stated purpose of the adjudicative process to
make him “whole”. Rather, it has the appearance of being a penalty, or at least
a deterrent so that the employer would not have “free license” to repeat the
breach. On the basis of his own reasoning, the adjudicator appears to have
imposed a remedy which was other than being compensatory. In the words of
Justice Létourneau in Lussier, above, “… in view of the absence of any
evidence of damage, the fact that the adjudicator awarded compensation for the
error made is … [not] genuine compensation for damage actually suffered.”
[45] Put simply, even keeping in mind the highest
deference owed to decisions of adjudicators, the monetary remedy in this case
was not supportable on the evidence presented to the adjudicator. His decision
must be set aside.
[46] I have concluded that no monetary remedy could
reasonably have been made. Also, the respondent neither sought compensation nor
presented evidence of financial loss. Accordingly, the matter will not be
referred for redetermination.
JUDGMENT
THIS COURT ORDERS AND
ADJUDGES that:
1.
This
application for judicial review is granted and the decision of the adjudicator
dated August 2, 2006 is set aside.
2.
The
undersigned remains seized of this proceeding to adjudicate the issue of costs,
if necessary.
“Allan
Lutfy”