Date: 20110629
Dockets: T-520-10
T-666-10
Citation: 2011
FC 791
Ottawa, Ontario,
June 29, 2011
PRESENT: The Honourable Madam Justice Heneghan
BETWEEN:
Docket: T-520-10
|
J.D. IRVING, LIMITED
|
|
|
Plaintiff
|
and
|
|
SIEMENS CANADA LIMITED, MARITIME MARINE
CONSULTANTS (2003) INC., SUPERPORT MARINE SERVICES LTD. AND NEW BRUNSWICK POWER NUCLEAR CORPORATION
|
|
|
Defendants
|
|
|
|
Docket: T-666-10
|
MARITIME MARINE CONSULTANTS (2003) INC.
|
|
|
Plaintiff
|
and
|
|
SIEMENS CANADA LIMITED, J.D. IRVING,
LIMITED, SUPERPORT MARINE SERVICES LTD., NEW BRUNSWICK POWER NUCLEAR
CORPORATION AND BMT MARINE AND OFFSHORE SURVEYS LTD.
|
|
|
Defendants
|
|
and
|
|
|
AXA CORPORATE SOLUTIONS
|
|
|
|
Third Party
|
REASONS FOR ORDER AND ORDER
Overview
[1]
Within 10
seconds in the forenoon of October 15, 2008, two steam turbine rotors that were
destined to the Point Lepreau Nuclear Generating Station in Point Lepreau, New
Brunswick, parted from the deck of cargo barge SPM 125 at Pier 3 of the harbour
in Saint John, New Brunswick, and came to rest in waters of the harbour (the “Incident”).
[2]
On or
about April 8, 2010, Siemens Canada Limited (“Siemens”), the suppliers of the
rotors, commenced an action in the Ontario Superior Court of Justice in cause
number CV-10-400645, against J.D. Irving Ltd. (“Irving”), BMT Marine and
Offshore Surveys Limited (“BMT”), Maritime Marine Consultants (2003) Inc.
(“MMC”) and Superport Marine Services Ltd. (“Superport”). In the Ontario action, Siemens advanced claims
for breach of contract, negligent misrepresentation, negligence and/or gross
negligence and failure to warn, and claimed damages of $40,000,000 together
with pre-judgment and post-judgment interest pursuant to the Courts of
Justice Act, R.S.O. 1990, c. 43, together with costs on a substantial
indemnity basis. The initial claim of $40,000,000 was later increased to
$45,000,000.
[3]
Furthermore,
Siemens claimed joint and several indemnification from Irving, MMC, BMT, and
Superport (“the defending parties”) in respect of “all claims, liabilities,
charges, or demands made against it by New Brunswick Power Nuclear Corporation
(“NBPNC”) including all claims made by NBPNC for liquidated damages under the
Agreement” between it and NBPNC. Siemens contracted to provide the rotors to
NBPNC.
[4]
By
Statement of Claim filed on April 7, 2010, Irving commenced an action in this
Court pursuant to the Marine Liability Act, S.C. 2001, c. 6 (the “MLA”
or the “Act”) seeking, among other things, a declaration that it is entitled to
limit its liability in relation to the Incident to $500,000 plus interest to
the date of the constitution of the limitation fund pursuant to subsections
29(6), 29.1 and 32(5) of the MLA. This action is cause number T-520-10.
[5]
Irving named Siemens, MMC, Superport
and NBPNC as Defendants (the “Defendants”).
[6]
By a
Statement of Claim filed on April 30, 2010, MMC commenced an action in this
Court seeking to limit its liability, pursuant to the MLA, in relation to the
Incident. MMC named Siemens, Irving, Superport, NBPNC and BMT as
Defendants in its action. This action is cause number T-666-10.
[7]
By Third
Party Notice filed on July 28, 2010, BMT claimed contribution and indemnity and
other relief, in relation to the Incident, against AXA Corporate Solutions (“AXA”),
a cargo insurer.
[8]
By letter
dated November 22, 2010, Counsel for Irving
advised that Siemens had commenced a second action in the Ontario Superior
Court of Justice relative to the Incident. In this action, being cause number
CV-10-412-348, Siemens claimed $45,000,000 in damages against twelve
individuals, including Mr. Don Bremner, a principal of MMC, and Atlantic Towing
Limited, a subsidiary of Irving.
[9]
This
action was begun on October 14, 2010 and Irving objected that Siemens had failed to
advise this Court about this second action when the several motions were argued
on October 19, 2010. Irving advised the relief sought in
its motion should apply to the second action. The parties were given the
opportunity to make further submissions in this regard and did so by filing
written arguments in January and February 2011.
Background
[10]
The
following facts are taken from the materials filed in the parties’ Motion
Records, including the pleadings that have been filed in both the Ontario
Superior Court of Justice and Federal Court actions.
[11]
Siemens
entered into a contract with Atomic Energy of Canada Limited, on or about
September 1, 2006, for certain work in refurbishing and upgrading the Point
Lepreau Nuclear Generating Station located at Point Lepreau, New Brunswick. The contract, subsequently assigned to
NBPNC, required the provision of three modules for incorporation into Point
Lepreau. The modules included turbine rotors. The modules were manufactured in
Germany and transported to Saint
John, New
Brunswick, for
further transport to Port Lepreau.
[12]
Siemens
entered into a contract with Irving by means of a purchase order
issued on or about January 11, 2007 for the carriage of the modules. The rotors
were to be moved from Saint
John harbour to
Point Lepreau Nuclear Generating Station by water.
[13]
Irving
engaged MMC, as marine architects, relative to the water carriage of the rotors
from Saint John to Point Lepreau. Irving retained MMC to approve the
stability of the SMP 125, determine the appropriate lashing and securing
arrangements and to calculate a ballasting plan for loading the rotors onto the
SMP 125. MMC prepared a plan entitled “Barge ‘SPM 125’ Stability Conditions
for Lepreau Rotor Move First Load”, dated October 8, 2010 and revised October
10, 2010.
[14]
By
bareboat charter-party dated October 9, 2008, Irving chartered from Superport the SPM 125, a
barge with a reported gross tonnage of 256.00 tonnes. The charter-party
agreement also gave Irving the use of the tug “Mary
Steele”.
[15]
Siemens
engaged BMT, on or about October 2, 2008, to provide marine surveying services
relating to the handling and transportation plan for the movement of the rotors
by the barge SPM 125.
[16]
As noted
above, in the course of the boarding of two rotors on to the barge SPM 125 on
the morning of October 15, 2008, the two rotors left the barge and went into
the waters of Saint
John harbour.
[17]
The rotors
were damaged as a result of their submersion. Siemens alleges that it is
responsible for the delivery, at its expense, of new modules to the Point
Lepreau station. The cost of manufacturing and delivering two new rotors is
estimated to cost approximately $20,000,000 and will require four years to
complete. In an effort to mitigate its losses, Siemens arranged for repair of
the damaged rotors. The costs of such repairs are estimated to be $10,000,000
plus additional transportation costs.
Procedural Steps
[18]
Siemens, Irving, BMT, Superport, and NBPNC
signed a tolling agreement on October 13, 2009 in which they agreed not to
commence litigation before April 13, 2010 without first giving two weeks’
notice of their intention to do so. Article 1 of the tolling agreement
suspended all applicable time periods for the duration of that agreement. Siemens
and Irving both provided two weeks notice to all the other parties to the
tolling agreement on March 24, 2010.
[19]
As noted
above, Siemens commenced litigation in the Ontario Superior Court of
Justice in April 2010 and the within actions were commenced at the same time.
Siemens initiated its second action in the Ontario Superior Court in October
2010.
[20]
The
present actions in the Federal Court address issues relative to limitation of
liability, including the establishment of a limitation fund. The
Statements of Claim issued in causes number T-520-10 and T-666-10 are
substantially the same, involving the same set of facts, the same key parties
and the same legal issues. Although there are slight differences in the
language of the two Statements of Claim, essentially the same relief is sought,
that is a declaration that the liability of Irving and MMC is limited to
$500,000 pursuant to the MLA and an order enjoining any proceedings beyond this
Court, that is the Federal Court.
Present Motions
i) T-520-10
[21]
On April
28, 2010, Siemens filed a Notice of Motion seeking a stay of this action
insofar as it relates to the constitution and distribution of a limitation fund
pursuant to section 33 of the MLA, as well as a permanent stay of the action
relative to Irving’s entitlement to limit its liability pursuant to section 28
and 29 of the Act.
[22]
By Notice
of Motion dated April 30, 2010, Irving
sought the following relief:
a)
giving
advice and directions as to the manner in which the Plaintiff’s action for a
declaration that its liability in respect of the incident of October 15, 2008,
as described in the Statement of Claim in this action, (the “Incident”) is
limited pursuant to the provisions of the Marine Liability Act, S.C.
2001 c. 6 (the “MLA”) to $500,000 plus interest from October 15, 2008 to the
date on which the statutory limitation fund is constituted, and for the
constitution of a limitation fund (the “Limitation Fund”), may be heard and
determined;
b)
for
service of notice of this action on potential claimants by advertising in two
weekend editions of the New Brunswick Telegraph Journal or by such other
forms of advertising as this Court deems just and appropriate;
c)
authorizing
the Plaintiff, J.D. Irving, Limited (“JDI”), to file a guarantee bond (the
“Guarantee Bond”) in an amount to be fixed by the Court, being $500,000 plus
interest from October 15, 2008 to the date of the institution of the Limitation
Fund, and that the filing of the Guarantee Bond shall constitute the Limitation
Fund in respect of the Incident;
d)
setting
the time limit within which the Defendants and other potential claimants must
file their defences or claims against the Limitation Fund;
e)
directing
that any claim against the Limitation Fund not filed within the time specified
by the Court shall be barred from participation in the distribution of the
Limitation Fund;
f)
enjoining
the Defendants, and any other person, from commencing or continuing proceedings
before any court other than this Court against the Plaintiff in respect of the
Incident;
g)
declaring
that the Limitation Fund be rateably distributed amongst the persons whom the
Court decides are entitled to claim against the Limitation Fund; and,
h)
such
further and other relief as counsel advise and this Court deems just and
appropriate.
ii) T-666-10
[23]
By Notice
of Motion dated June 4, 2010, Siemens sought the following relief:
1.An order staying this action (the
“Action”) as it relates to the constitution and distribution of a fund pursuant
to section 33 of the Marine Liability Act;
2. An order permanently staying the
Action as it relates to the entitlement of Maritime Marine Consultants (2003)
Inc. (“MMC”) to limit is [sic] liability pursuant to sections 28 and 29
of the Marine Liability Act;
3. Such further and other relief as
counsel may advise and this Honourable Court deem just.
[24]
By Notice
of Motion dated July 23, 2010, MMC sought the following relief:
1. An order giving the parties advice and
direction as to the manner in which the Plaintiff’s action for a declaration
that its liability in respect of an incident which occurred on October 15,
2008, and as further described in the Statement of Claim (“the incident”) is
limited pursuant to the provisions of the Marine Liability Act, S.C.
2001, c. 6;
2. An order for service of the notice of
this action on potential claimants by advertising in two weekend editions of
the New Brunswick Telegraph Journal or by such other forms of advertising as
this Court deems just and appropriate, which advertising shall take place
jointly with the advertising in connection with an action brought by J.D.
Irving Limited bearing Court File No. T-520-10 (“the Irving action”);
3. An order setting the time limit within
which the Defendants and other potential claimants must file their defences or
claims in connection with this action;
4. An order directing that any claim not
filed within the time specified by the Court shall be barred from participation
in the distribution of any limitation fund which may be established in
connection with this action or the Irving action;
5. An order enjoining the Defendants, and
any other person, from commencing or continuing proceedings before any other
Court, other than the Federal Court of Canada, against the Plaintiff in respect
of the incident;
6. Such further and other relief as
counsel may advise and this Honourable Court deems just and proper.
[25]
Finally,
by Notice of Motion dated August 4, 2010, BMT sought the following relief:
1. directing the Defendants herein,
including Siemens Canada Limited and any other person or party having knowledge
of the said Order, from commencing or continuing proceedings in any Court,
tribunal or authority other than the Federal Court of Canada, being the
Admiralty Court as defined by the Marine Liability Act, S.C. 2001, c. 6,
as amended, with respect to any claim of any nature whatsoever arising from or
relating to the capsizing of the barge “SPM 125” at Saint John, New Brunswick
on or about 15 October 2008;
2. directing that those claims filed by
way of legal proceedings in the Ontario Superior Court of Justice in Toronto
(docket number CV-10-400645), including any and all related counter and/or
cross-claims, be asserted by way of counter-claims or cross-claims herein and
directing further that the plaintiffs therein refrain from continuing the said
proceedings;
3. such other and further relief as
counsel advise and this Honourable Court deems just and appropriate;
4. The whole with costs.
The Evidence
[26]
Affidavit
and documentary evidence in these matters was filed both by Irving and Siemens.
In support of its motion in T-520-10, Irving
filed the affidavit of Mr. Wayne Power, a Vice-President with Irving.
[27]
In his
affidavit, Mr. Power provided background information concerning the
relationship between Irving and Siemens, arrangements for the transportation of
the rotors from Saint John to Point Lepreau, the engagement of MMC to advise
Irving in that regard, references to the accident of October 15, 2008 and a
subsequent investigation by Transport Canada in that regard. He also referred
to the commencement of the execution of a tolling agreement among the parties
to this litigation and the commencement of litigation by Siemens in the Ontario
Superior Court.
[28]
Various
documents are attached as exhibits to Mr. Power’s affidavit, including Irving’s
quote dated April 28, 2006 for the movement of the rotors, a copy of the
purchase order dated January 11, 2007 that was issued by Siemens, a copy of the
charter-party between Irving and Superport, a copy of certain stability
calculations that were prepared by MMC relative to the transportation of the
rotors on the SPM 125 and a copy of the investigation report prepared by
Transport Canada Marine Safety Division.
[29]
Irving
also filed three affidavits of Ms. Jean Campbell, a litigation law clerk
employed by the solicitors for Irving in this matter. In her first
affidavit, sworn to on April 30, 2010, Ms. Campbell attached, as exhibits,
copies of certain documents prepared by Canada Revenue Agency relating to
interest payable on overpayments of income tax for the financial quarter during
which the Incident took place, and the two following financial quarters. Ms.
Campbell also attached, as an exhibit, a table showing the interest, compounded
daily, that had accrued from the date of the Incident as of June 15, 2010. The
amount of interest was calculated as $29,217.96.
[30]
In her
second affidavit, sworn to on September 27, 2010, Ms. Campbell attached, as
exhibits, copies of certain correspondence between Counsel for Irving and
Counsel for Superport; copies of certain emails exchanged between Counsel for
Irving and Counsel for Siemens; and a copy of a letter from Counsel for Irving
providing replies to undertakings and questions taken under advisement on the
cross-examination of Mr. Power, which cross-examination was conducted on June
21, 2010.
[31]
The third
affidavit from Ms. Campbell is dated October 13, 2010. Attached as an exhibit
to that affidavit was a copy of a Notice of Arbitration between Superport and Irving, dated October 13, 2010, sent
by email from Counsel for Superport to Counsel for Irving. The Notice of Arbitration was given
pursuant to the charter-party between Irving and Superport and gave notice that
Superport intended to seek a determination by arbitration as to “whether and to
what extent” Irving is liable to Superport for
loss and damage as a result of the occurrence of October 15, 2008.
[32]
Siemens
filed four affidavits sworn to by Ms. Jennifer Robinson, a law clerk with
Counsel for Siemens. In her first affidavit, sworn on April 14, 2010, Ms.
Robinson referred to the event giving rise to this litigation, and related
litigation, and attached various documents as exhibits, including a copy of the
tolling agreement and a copy of the Statement of Claim relating to the action
commenced by Siemens in the Ontario Superior Court.
[33]
In her
second affidavit, sworn to on June 4, 2010, Ms. Robinson referred to the
commencement of the limitation proceedings by MMC in the Federal Court and
attached, as exhibits, copies of the Statement of Claim in that regard, as well
as a copy of the Defence filed by MMC to the limitation proceedings commenced
by Irving in the Federal Court.
[34]
In the
third affidavit, sworn to on June 18, 2010, Ms. Robinson attached copies of
certain correspondence sent by Counsel for Siemens to three of the defending
parties in the Ontario proceedings, wherein Counsel
for Siemens requested defences on behalf of MMC, BMT and Superport in respect
of the Ontario proceedings. This affidavit
also included, as an exhibit, a copy of an expert report prepared on behalf of
Siemens by Design Research Engineering. This report is dated June 10, 2010.
Finally, this affidavit included a copy of a jury notice that has been filed by
Siemens in relation to the Ontario proceedings.
[35]
In her
fourth affidavit, sworn to on September 1, 2010, Ms. Robinson attached copies
of various documents relating to the Ontario
proceedings and the action commenced by MMC in the Federal Court, cause number
T-666-10. She also attached a copy of a supplementary expert report, dated
August 2, 2010, prepared by Design Research Engineering. Siemens had
commissioned this report to be used in connection with the Ontario proceedings. Finally, she
attached a copy of a letter dated September 1, 2010 from Counsel for Siemens to
Counsel for Irving, advising that Siemens did not require the creation of a
limitation fund and advising, as well, that NBPNC waiving the creation of a
limitation fund.
[36]
In
addition to these affidavits of Ms. Robinson, together with the attached
exhibits, Siemens filed a compendium of documents consisting primarily of
copies of the pleadings to date in the Ontario and Federal Court actions. Siemens also
filed an Exhibit Book consisting of documents concerning efforts made by Irving to obtain a barge for the
carriage of the rotors, documents relating to communications between Irving and
MMC as to the suitability of the barge and stability calculations,
communications concerning the timing of the transportation, and related emails.
The Exhibit Book also contains copies of a series of photographs and an extract
from a web page for Irving Equipment.
[37]
No
affidavit evidence in respect of these motions was filed by MMC, BMT or AXA.
Discussion
(i) Jurisdiction
[38]
As noted
at the beginning of these Reasons, there are five motions before the Court in
these two proceedings. Siemens has filed a motion in both cause number T-520-10
and cause number T-666-10 seeking a stay of the two respective actions insofar
as the relief sought by Irving and MMC, respectively, is principally the
constitution and distribution of a limitation fund pursuant to the MLA. As
well, in both actions, Siemens seeks a permanent stay of the actions on the
basis that neither Irving nor MMC is entitled to limit liability pursuant to
the MLA.
[39]
Insofar as
it seeks to stay the two limitation proceedings in the Federal Court, Siemens challenges
the jurisdiction of this Court over the subject matter of its claim,
that is the claim for damages in the actions that it commenced in the Ontario
Superior Court of Justice. Siemens argues that its claim does not fall within the jurisdiction of this
Court because it is not a matter of maritime law, and in any event, if there is
doubt on that issue, this Court should decline to exercise its jurisdiction
pursuant to section 33 of the MLA.
[40]
It submits that its
claim for damages does not arise in connection with the operation of a ship,
that the damage did not occur on board the ship, and that its claim for damages
does not arise from the delay in the carriage of the goods. Rather, its claim
for damages relates to repair and replacement costs. It further submits that
the scope of the proceedings before the Ontario Superior Court is broader and
without doubt as to the jurisdiction of that Court over all the defending
parties. It argues that the purpose of the Ontario
proceedings is much different from the purposes of the limitation proceedings
commenced in the Federal Court.
[41]
It argues
that the heart of its claim is a contract with Irving, pursuant to a purchase
order that was issued on January 11, 2007 for the transportation of the
rotors from Saint
John to Port
Lepreau. It submits that this purchase order is a standard contract for
transportation of goods and not a contract for the carriage of goods by sea. It
argues that the essential character of its claim is unrelated to navigation,
seamanship or shipping and that these elements are irrelevant to its loss.
[42]
Siemens relies on the
decision in Ontario (Attorney General) v. Pembina
Exploration Canada Ltd.,
[1989] 1 S.C.R. 206, to argue that a claim can have a “local or private”
aspect, as well as maritime aspects, and accordingly, can be adjudicated by a
provincial court.
[43]
Irving,
MMC and BMT resist and repudiate Siemens’ characterization of the claim and
submit that the claim is clearly a matter of maritime law falling within the
jurisdiction of this Court.
[44]
The first
question, then is whether this Court has jurisdiction over Siemens’ claim for
the recovery of damages.
[45]
Siemens
characterizes its claim for the recovery of damages as a matter of contract and
common law negligence. In the further submissions, Siemens and AXA refer to and
rely upon the recent decisions of the Supreme Court of Canada in Canada
(Attorney General) v. TeleZone Inc., [2010] 3 S.C.R. 585, arguing that this
Court should consider the cause of action as it was characterized in the Ontario
Superior Court of Justice, in deciding whether this Court has jurisdiction. It
submits that the matter at issue does not fall within the jurisdiction of the
Federal Court because its claim is not, essentially, one of maritime law.
[46]
In this
regard, it relies upon the decisions in Dreifelds v. Burton (1998), 38
O.R. (3d) 393 (O.N.C.A.), and Isen v. Simms, [2006] 2 S.C.R. 349, among
others, to argue that the mere presence of water and a ship is insufficient to
establish a claim within the jurisdiction of this Court.
[47]
Irving and
BMT submit that TeleZone has no application to the present case because
that decision involves the availability of certain remedies, that is an
application for judicial review as opposed to an action against the federal
Crown.
[48]
I agree
with the general argument made by Siemens that the mere proximity of water,
together with a water borne craft, is insufficient, per se, to grant
jurisdiction in this Court. The test for finding jurisdiction in matters of
navigation and shipping was set out by the Supreme Court of Canada in its
decision in ITO-Int'l Terminal Operators v. Miida Electronics, [1986] 1
S.C.R. 752 at 766, as follows:
The question of the Federal Court's
jurisdiction arises in this case in the context of Miida's claim against ITO, a
claim involving the negligence of a stevedore-terminal operator in the
post-discharge storage of the consignee's goods. The general extent of the
jurisdiction of the Federal Court has been the subject of much judicial
consideration in recent years. In Quebec North Shore Paper Co. v. Canadian Pacific Ltd., [1977] 2 S.C.R. 1054, and
in McNamara Construction (Western) Ltd. v. The Queen, [1977] 2 S.C.R.
654, the essential requirements to support a finding of jurisdiction in the
Federal Court were established. They are:
1. There must be a statutory grant of
jurisdiction by the federal Parliament.
2. There must be an existing body of
federal law which is essential to the disposition of the case and which
nourishes the statutory grant of jurisdiction.
3. The law on which the case is based
must be “a law of Canada” as the phrase is used in s.
101 of the Constitution Act, 1867.
[49]
Section 22
of the Federal Courts Act, R.S.C. 1985, c. F-7 fulfills the first step
of the ITO test by describing the admiralty jurisdiction of this
Court. Subsection 22(1) is a statement of general jurisdiction and provides as
follows:
Navigation
and shipping
22.
(1) The Federal Court has concurrent original jurisdiction, between subject
and subject as well as otherwise, in all cases in which a claim for relief is
made or a remedy is sought under or by virtue of Canadian maritime law or any
other law of Canada relating to any matter coming within the class of subject
of navigation and shipping, except to the extent that jurisdiction has been
otherwise specially assigned.
|
Navigation
et marine marchande
22.
(1) La Cour fédérale a compétence concurrente, en première instance, dans les
cas — opposant notamment des administrés — où une demande de réparation ou un
recours est présenté en vertu du droit maritime canadien ou d’une loi
fédérale concernant la navigation ou la marine marchande, sauf attribution
expresse contraire de cette compétence.
|
[50]
Subsection 22(2)
identifies a number of specific instances where this Court possesses maritime
jurisdiction. Paragraphs 22(2) (e), (h) and (i) are relevant and provide as
follows:
Maritime
jurisdiction
(2) Without
limiting the generality of subsection (1), for greater certainty, the Federal
Court has jurisdiction with respect to all of the following:
…
(e) any claim
for damage sustained by, or for loss of, a ship including, without
restricting the generality of the foregoing, damage to or loss of the cargo
or equipment of, or any property in or on or being loaded on or off, a ship;
…
(h) any claim
for loss of or damage to goods carried in or on a ship including, without
restricting the generality of the foregoing, loss of or damage to passengers’
baggage or personal effects;
(i) any claim
arising out of any agreement relating to the carriage of goods in or on a
ship or to the use or hire of a ship whether by charter party or otherwise;
…
|
Compétence
maritime
(2)
Il demeure entendu que, sans préjudice de la portée générale du paragraphe
(1), elle a compétence dans les cas suivants :
…
e)
une demande d’indemnisation pour l’avarie ou la perte d’un navire, notamment
de sa cargaison ou de son équipement ou de tout bien à son bord ou en cours
de transbordement;
…
h)
une demande d’indemnisation pour la perte ou l’avarie de marchandises
transportées à bord d’un navire, notamment dans le cas des bagages ou effets
personnels des passagers;
i)
une demande fondée sur une convention relative au transport de marchandises à
bord d’un navire, à l’usage ou au louage d’un navire, notamment par
charte-partie;
…
|
[51]
This statutory grant
of jurisdiction over Canadian maritime law is nourished by a number of statutes
applicable to this case, including the MLA, which incorporates the Convention
on Limitation of Liability for Maritime Claims, 1976 (the
“Convention”) pursuant to subsection 26(1) of that Act, and the Canada
Shipping Act, 2001, S.C. 2001, c. 26.
[52]
In Radil Bros.
Fishing Co. v. Canada (Department of Fisheries and Oceans,
Pacific Region), [2002]
2 F.C. 219 (C.A.) at para. 60, the Federal Court of Appeal identified some of
the factors that will distinguish a simple claim in contract from one where the
“true essence of the contract relied upon is maritime”. At para. 60 the Court
said the following:
60
None of these cases is helpful to the appellant. Quite to the contrary, they
tend to show that the Court will not assert its admiralty jurisdiction in
agency claims unless the true essence of the contract relied upon is maritime.
This is not the case here, where the sole factor possibly connected to maritime
law is the fact that the licence with respect to which the agency contract was
entered into happens to be issued in relation to an activity occurring at sea.
There is no contract for carriage of goods by sea. There is no marine
insurance. There are no goods at issue. Nothing has happened at sea. There is
no issue as to the seaworthiness of the ships. The ships are not party to the
action. There are no in rem proceedings. There are no shipping agents. There
are no admiralty laws or principles or practices applicable. The claim, at best
and incidentally, may be said to relate to the ability of a ship to perform
certain fishing activities in accordance with requirements that have nothing to
do with navigation and shipping and everything to do with fisheries.
[53]
Siemens is adopting a
highly restrictive view of the legal context surrounding its claim for damages.
On the basis of the evidence submitted and the arguments advanced by the
parties in connection with the present motions, it is clear that many of the indicia
of maritime jurisdiction that were identified in Radil Bros. are
present. In my opinion, it is clear that the nature of Siemens’ claim is
essentially maritime law.
[54]
The Incident occurred
on the water. Preparations for the transportation of the rotors involved
marine surveyors, that is MMC and BMT, and a cargo insurer, that is AXA. The
rotors were on board a ship, that is the SPM 125. The Incident was investigated
in accordance with the Transport Canada Marine Safety Policy for investigating
maritime occurrences under the authority of section 219 of the Canada Shipping Act, 2001.
[55]
The
misrepresentations alleged by Siemens relate to the preparation for loading the
barge, raising an issue of seaworthiness. That issue is subject to
applicable admiralty laws, principles and practices.
[56]
The alleged breach of
contract and negligence relate to an agreement for the carriage of goods by
sea. Siemens argues that the purchase order, which is a contract, is not a
matter subject to Canadian maritime law. Nevertheless, the object of that
contract is the transportation of the rotors from the harbour in Saint John to the nuclear plant at Point Lepreau. The obligation of a
carrier, in respect of a contract of carriage of goods, is to safely load and
deliver the goods; see The “Muncaster Castle”, [1961] 1 Lloyd’s Rep. 57
(H.L.).
[57]
MMC, marine surveyors,
were engaged by Irving to provide marine
architectural services. Irving’s responsibility for the actions,
neglect or default of MMC can be assessed pursuant to paragraph 4 of Article 1
of the Convention.
[58]
The right of BMT to
limit its liability will be an issue for determination in the limitation
proceedings. It was engaged by Siemens to “provide marine surveying services
with respect to that aspect of the handling and transportation plan”. Marine
surveying services are related to navigation and shipping.
[59]
It is incorrect to
say that Siemens’ claim for damages is beyond the jurisdiction of this Court
because its final adjudication may involve the application of common law principles
of tort. In Chartwell Shipping Limited v. Q.N.S. Paper Co. Ltd. (1989),
101 N.R. 1 (S.C.C.), the Supreme Court of Canada said that Canadian maritime
law encompasses the common law principles of tort, contract, bailment and
agency.
[60]
Siemens’ argument
that the nature of its claim has nothing to do with shipping is directly
contradicted by the jurisprudence of the Supreme Court of Canada. In Isen,
at para. 22, the Supreme Court of Canada said the following:
Commercial
shipping was traditionally viewed as within the scope of Parliament's
jurisdiction over navigation and shipping. Shipping contracts involve not only
the safe carriage of goods over the sea, but also the movement of goods on and
off a ship.
[61]
The decisions in Dreifelds
and Isen, referred to above, can be distinguished. In Dreifelds,
the Ontario Court of Appeal held that the pleadings in that case concerned the
preparation for and conduct of a scuba diving trip. The plaintiff did not plead
any negligence on the part of the charter boat involved, that is anything
related to navigation or shipping.
[62]
In Isen, the
accident occurred on land when a bungee cord being attached to a tarpaulin, on
a pleasure craft in the course of preparing for transport of that craft on a
provincial highway, snapped, causing injury to the plaintiff. The Supreme Court
of Canada determined that the injury was caused by a negligent act which had
nothing to do with navigation or shipping. The negligent act was subject to
provincial law, not federal maritime law.
[63]
Siemens also argues
that this Court does not have jurisdiction over its claim because neither MMC
nor BMT are entitled to limit their liability under the Act as they do not fall
within the relevant statutory definitions, and in any event, are barred by
Article 4 of the Convention from limiting their liability.
[64]
Regardless of the
merit of Siemens’ submissions regarding the entitlement of Irving, MMC and BMT
to limit their liability, it is clear that the ultimate findings on these issues
will be made with reference to the provisions of the MLA and the Convention.
Put another way, Canadian maritime law will apply to the issues Siemens raises
regarding the limitation of liability of Irving, MMC, and BMT.
[65]
I agree with the
arguments of Irving and BMT that the decision in TeleZone is not relevant
to the issue of this Court’s jurisdiction over the claim arising in relation to
the Incident. Even as pleaded in the Ontario proceedings, it is clear that Siemens’
claim is a maritime claim.
[66]
There is concurrent
jurisdiction in both the Federal Court and in the Ontario Superior Court of
Justice over both the issues of liability and of limitation of liability. The
jurisdiction of the Ontario Superior Court of Justice is not challenged by any
of the Defendants.
(ii)
Stay Motions
[67]
Siemens, supported by
AXA, seeks to stay the two limitation proceedings, both on an interlocutory and
permanent basis. It wants the interlocutory stay in order to allow the Ontario
Superior Court of Justice proceedings to continue through trial and adjudication.
It wants a permanent stay on the grounds that limitation of liability is not
available to Irving and MMC, having regard to Article 4 of the Convention.
[68]
Irving, MMC and BMT,
for their part, oppose this motion and seek to enjoin proceedings in any other
Court, including the Ontario Superior Court of Justice, arguing that all issues
relating to the Incident should be addressed in the Federal Court.
[69]
The authority to stay
proceedings in this Court flows from subsection 50(1) of the Federal Courts
Act which provides as follows:
Stay of
proceedings authorized
50. (1) The
Federal Court of Appeal or the Federal Court may, in its discretion, stay
proceedings in any cause or matter
(a) on the
ground that the claim is being proceeded with in another court or
jurisdiction; or
(b) where for
any other reason it is in the interest of justice that the proceedings be
stayed.
|
Suspension
d’instance
50.
(1) La Cour d’appel fédérale et la Cour fédérale ont le pouvoir
discrétionnaire de suspendre les procédures dans toute affaire :
a)
au motif que la demande est en instance devant un autre tribunal;
b)
lorsque, pour quelque autre raison, l’intérêt de la justice l’exige.
|
[70]
Siemens argues that
both the circumstances identified in subsection 50(1) apply in this case, that
a stay should be granted because a claim is being adjudicated in another court
or jurisdiction and that a stay of the limitation proceedings is required in
the interest of justice.
[71]
Siemens points out
that it is the only party who has suffered a loss. No other party is making a
claim against Siemens and that the proceedings which it has instituted in the
Ontario Superior Court of Justice is broader in scope than the limitation
proceedings in the Federal Court. It further notes that with proceedings in
both the Ontario Superior Court of Justice and this Court, there is a risk of
inconsistent findings. It relies upon the decision in Jazz Air LP v. Ontario
Port Authority (2009), 343 F.T.R. 165 (F.C.) at paras. 13, 31 and 32 to
support its argument in this regard.
[72]
Irving, MMC and BMT
oppose Siemens’ motion for a stay. Among other things, they note that a stay
pursuant to subsection 50(1) is a discretionary order. They argue that the
interests of justice will be best served, with less inconvenience and expense
to all parties, if the proceedings in this Court are allowed to proceed and
proceedings in any other Court, including the current proceedings in the
Ontario Superior Court of Justice, are enjoined.
[73]
Irving, MMC and BMT
are of one voice in arguing against Siemens’ stay motion, each of them
referring to the broad powers conferred upon the Federal Court, as the Admiralty Court for the purposes of the Act, with
respect to establishing the procedure in relation to the constitution and
distribution of a limitation fund. These powers are described, not exclusively,
in subsection 33(1) of the MLA which provides as follows:
Powers of Admiralty Court
33. (1) Where
a claim is made or apprehended against a person in respect of liability that
is limited by section 28 or 29 of this Act or paragraph 1 of Article 6 or 7
of the Convention, the Admiralty Court, on application by that person or any
other interested person, including a person who is a party to proceedings in
relation to the same subject-matter before another court, tribunal or
authority, may take any steps it considers appropriate, including
(a)
determining the amount of the liability and providing for the constitution
and distribution of a fund under Articles 11 and 12 of the Convention;
(b) joining interested
persons as parties to the proceedings, excluding any claimants who do not
make a claim within a certain time, requiring security from the person
claiming limitation of liability or from any other interested person and
requiring the payment of any costs; and
(c) enjoining
any person from commencing or continuing proceedings in any court, tribunal
or authority other than the Admiralty
Court in relation to the
same subject-matter.
|
Pouvoirs
de la Cour d’amirauté
33.
(1) Lorsque la responsabilité d’une personne est limitée aux termes des
articles 28 ou 29 de la présente loi ou du paragraphe 1 des articles 6 ou 7
de la Convention, relativement à une créance — réelle ou appréhendée — , la
Cour d’amirauté peut, à la demande de cette personne ou de tout autre
intéressé — y compris une partie à une procédure relative à la même affaire
devant tout autre tribunal ou autorité — , prendre toute mesure qu’elle juge
indiquée, notamment :
a)
déterminer le montant de la responsabilité et faire le nécessaire pour la
constitution et la répartition du fonds de limitation correspondant,
conformément aux articles 11 et 12 de la Convention;
b)
joindre tout intéressé comme partie à la procédure, exclure tout créancier
forclos, exiger une garantie des parties invoquant la limitation de
responsabilité ou de tout autre intéressé et exiger le paiement des frais;
c)
empêcher toute personne d’intenter ou de continuer quelque procédure relative
à la même affaire devant tout autre tribunal ou autorité.
|
[74]
Paragraph 33(1)(c) specifically
allows the Federal Court to enjoin the commencement or continued prosecution of
proceedings in any Court “other than the Admiralty
Court in relation to the
same subject-matter”.
[75]
In Canadian
Pacific Railway Co. v. Sheena M (The), [2000] 4 F.C. 159 (F.C.T.D.), the
late Prothonotary Hargrave at para. 17, discussed the difference between
staying and enjoining as follows:
To
complete this line of reasoning, there is a difference between enjoining and
staying. The former, is defined in the revised 4th edition of Black's Law
Dictionary in terms of an injunctive direction to perform or to abstain from
some act…
In
contrast a stay, or a stay of proceedings as it is correctly called, is an
order by which a court suspends its own proceedings, either temporarily, until
something is done, or permanently, where it is improper to proceed….
The
test for a stay, in the interests of justice, is generally acknowledged to be
the three-part test set out in RJR--MacDonald Inc. v. Canada (Attorney
General), [1994] 1 S.C.R. 311, being the three-part American Cyanamid test
[American Cyanamid Co. v. Ethicon Ltd., [1975] A.C. 396 (H.L.)] although
in this instance the appropriate test for a stay of proceedings is a two-part
test set out in Mon-Oil Ltd. v. Canada (1989), 26 C.P.R. (3d) 379
(F.C.T.D.), a point that I shall touch on again in due course. The test for a
stay is very different concept and test from that of an enjoinment of a
proceeding in another court under the Canada Shipping Act. Indeed, this
is to be expected for in one statute the draftsman has used the term enjoin and
in the other the reference is to a stay…
[76]
At para. 32,
Prothonotary Hargrave, having reviewed two lines of cases addressing the onus
and test for a stay stated the following conclusion:
In
summary, that the two-part test is appropriate where a stay of the Court's own
proceeding is at issue, while the three-part RJR--MacDonald test is
appropriate where the stay is that of proceedings before some tribunal or an
order of the Court pending an appeal…
[77]
In my opinion, the
same approach applies here. The two part test of Mon-Oil Ltd. v. Canada (1989), 26 C.P.R. (3d) 379 (F.C.T.D.), should be
considered in respect of Siemens’ motion for a stay. That test requires the
Court to consider two questions, that is will the continuation of the action
cause prejudice to the defendant, in this case Siemens, and will the stay cause
an injustice to the plaintiffs, that is Irving and MMC.
[78]
As noted by Chief
Justice Thurlow in Nisshin Kisen Kaisha Ltd. v. CNR, [1982] 1 F.C. 530
(C.A.), a limitation action is “incidental” to any action for determination of
liability. It is an action for the establishment and distribution of a fund,
and its apportionment after findings of liability. In my opinion, Siemens has
not demonstrated that these actions, which have been commenced in a timely
basis, will prejudice it. In the exercise of my discretion, I decline to grant
an interlocutory stay of the limitation action.
[79]
I will now address
Siemens’ request for a permanent stay of these two actions.
[80]
Underlying Siemens’
request for a permanent stay of the Federal Court proceedings is its position
that the right to limit liability is unavailable to Irving, MMC and BMT
pursuant to the application of Article 4 of the Convention, which provides as
follows:
Conduct
barring limitation
A person
liable shall not be entitled to limit his liability if it is proved that the
loss resulted from his personal act or omission, committed with the intent to
cause such loss, or recklessly and with knowledge that such loss would
probably result.
|
Conduite
supprimant la limitation
Une
personne responsable n’est pas en droit de limiter sa responsabilité s’il est
prouvé que le dommage résulte de son fait ou de son omission personnels,
commis avec l’intention de provoquer un tel dommage, ou commis témérairement
et avec conscience qu’un tel dommage en résulterait probablement.
|
[81]
Siemens relies upon
the expert opinion which it obtained for use in the Ontario proceedings, that is the two reports prepared by Design
Research Engineering. These two reports challenge in particular the stability
calculations that were prepared in connection with the loading and carriage of
the rotors in October 2008. Mr. Robert K. Taylor, the author of the two
reports, expressed the following opinion in his supplementary report of August
2, 2010:
Barring
the presence of such an analysis, it remains my opinion that the failure to
consider the overall transverse stability of the entire system is dangerous and
from an engineering standpoint, reckless.
Relying
on this opinion, Siemens argues that the conduct of Irving was reckless and accordingly, that it has no right to limit
liability having regard to Article 4 of the Convention.
[82]
However, in my
opinion, this argument is premature. There is an insufficient evidentiary
foundation before the Court at this time to find that Irving, MMC or BMT are
not entitled to limit their liability, if any, to Siemens. Denial of the right
to limit liability cannot be made in the absence of a proper evidentiary record
and that evidentiary record will be available after a trial.
[83]
I am not persuaded
that Siemens has presented evidence to show that it would be prejudiced by the
continuation of the limitation proceedings. It has proceeded on the premise that
the Defendants will not be able to limit liability, due to their conduct,
relying on the application of Article 4 of the Convention. However, this is
only an argument. The application of Article 4 will require evidence; see Société
Telus Communications v. Peracomo Inc., 2011 FC 494.
[84]
Regardless of the ultimate
characterization of the Defendants’ conduct, Siemens’ current arguments do not
demonstrate prejudice and in any event, legal arguments are no substitution for
evidence.
[85]
Siemens also argues,
based on Jazz Air LP, that the limitation action should be permanently
stayed in order to avoid duplication of proceedings and inconsistent findings.
[86]
I agree that
duplicate proceedings and inconsistent findings should be avoided. However, as Prothonotary
Milczynski held in Jazz Air LP at para. 32, “accepting that duplication
must be avoided does not answer the question of which court should be
preferred...”.
[87]
As discussed, the
Federal Court has full jurisdiction over Siemens’ claim. Siemens can fully
pursue its claim in this Court. In my opinion, Siemens’ submissions that
duplication and inconsistency should be avoided, without more, do not
demonstrate that it will be prejudiced if the stay of proceedings in this Court
is denied.
[88]
On the other hand, a
stay of the limitation action would work an injustice to Irving, MMC and BMT.
There is a presumptive right to limit liability. Section 33 of the MLA allows a
party seeking to limit liability to bring its own action in this Court, and to apply
for directions. The very purpose of the limitation regime is to avoid multiple
proceedings; see Bayside Towing Ltd. v. Canadian Pacific Railway Co.,
[2001] 2 F.C. 258 (F.C.T.D.) at para. 30.
[89]
Staying these
proceedings would restrict Irving, MMC and BMT in advancing their limitation actions.
Although Irving, MMC and BMT could raise limitation as a defence in the Ontario action, they can only address the constitution of the
limitation fund in the within proceedings before this Court. If the right to
limit is not broken and liability is limited, the limitation fund will be
distributed. These aspects of a limitation action, that is the constitution and
distribution of a fund, are exclusively within the jurisdiction of this Court.
[90]
I refer again to the
decision in Jazz Air LP, where Prothonotary Milczynski at para. 35, said
that “stays are to be granted only in the clearest of cases”. Having considered
the submissions of all parties, I am not persuaded that the limitation actions
should be stayed either on an interlocutory or permanent basis.
(iii) Limitation Fund
[91]
In its present motion
before this Court, Irving seeks advice and directions as to the
manner in which its limitation action in this Court may be heard and
determined, as well as advice and directions concerning the constitution of a
limitation fund. In their motions, MMC and BMT likewise seek directions
as to the manner in which its limitation action should proceed.
[92]
Insofar as Siemens
and AXA dispute the right to limit, they will have that opportunity in the
context of the limitation action.
[93]
The first matter to
be addressed is whether a limitation fund should be established.
[94]
There is a
presumption in favour of limitation of liability relative to a maritime claim,
as provided by the Convention which forms part of Canadian maritime law
pursuant to its incorporation in the MLA.
[95]
Part 3 of the MLA is
entitled “Limitation of Liability for Maritime Claims”. Section 24 contains
definitions that are relevant to the present proceedings, specifically
“convention” and “maritime claim” which are defined as follows:
“Convention”
“Convention”
means the Convention on Limitation of Liability for Maritime Claims, 1976,
concluded at London on November 19, 1976, as amended by the Protocol,
Articles 1 to 15 of which Convention are set out in Part 1 of Schedule 1 and
Article 18 of which is set out in Part 2 of that Schedule.
“maritime
claim”
“maritime
claim” means a claim described in Article 2 of the Convention for which a
person referred to in Article 1 of the Convention is entitled to limitation
of liability.
|
«
Convention »
«
Convention » La Convention de 1976 sur la limitation de la responsabilité en
matière de créances maritimes conclue à Londres le 19 novembre 1976 — dans sa
version modifiée par le Protocole — dont les articles 1 à 15 figurent à la
partie 1 de l’annexe 1 et l’article 18 figure à la partie 2 de cette annexe.
«
créance maritime »
«
créance maritime » Créance maritime visée à l’article 2 de la Convention
contre toute personne visée à l’article 1 de la Convention.
|
[96]
Section 25 of the Act
is also relevant and provides as follows:
25.
(1) For the purposes of this Part and Articles 1 to 15 of the Convention,
(a)
“ship” means any vessel or craft designed, used or capable of being used
solely or partly for navigation, without regard to method or lack of
propulsion, and includes
(i)
a ship in the process of construction from the time that it is capable of
floating, and
(ii)
a ship that has been stranded, wrecked or sunk and any part of a ship that
has broken up,
but
does not include an air cushion vehicle or a floating platform constructed
for the purpose of exploring or exploiting the natural resources or the
subsoil of the sea-bed;
(b)
the definition “shipowner” in paragraph 2 of Article 1 of the Convention
shall be read without reference to the word “seagoing” and as including any
person who has an interest in or possession of a ship from and including its
launching;
…
(2)
In the event of any inconsistency between sections 28 to 34 of this Act and
Articles 1 to 15 of the Convention, those sections prevail to the extent of
the inconsistency.
|
25. (1) Pour l’application de la
présente partie et des articles 1 à 15 de la Convention :
a) « navire » s’entend d’un bâtiment ou
d’une embarcation conçus, utilisés ou utilisables, exclusivement ou non, pour
la navigation, indépendamment de leur mode de propulsion ou de l’absence de
propulsion, à l’exclusion des aéroglisseurs et des plates-formes flottantes
destinées à l’exploration ou à l’exploitation des ressources naturelles du
fond ou du sous-sol marin; y sont assimilés les navires en construction à
partir du moment où ils peuvent flotter, les navires échoués ou coulés ainsi
que les épaves et toute partie d’un navire qui s’est brisé;
b) la définition de
« propriétaire de navire», au
paragraphe 2 de l’article premier de la Convention, vise notamment la
personne ayant un intérêt dans un navire ou la possession d’un navire, à
compter de son lancement, et s’interprète sans égard au terme « de mer »;
…
(2) Les articles 28 à 34 de la présente
loi l’emportent sur les dispositions incompatibles des articles 1 à 15 de la
Convention.
|
[97]
Paragraph 2 of
Article 1 of the Convention defines “shipowner” as follows:
2. The term
“shipowner” shall mean the owner, charterer, manager and operator of a
seagoing ship.
|
2.
L’expression « propriétaire de navire », désigne le propriétaire,
l’affréteur, l’armateur et l’armateur-gérant d’un navire de mer.
|
[98]
The definition of
“maritime claim” in section 24 of the MLA is cross-referenced to paragraph (1)
and (2) of Article 2 of the Convention as follows:
Article 2
Claims subject
to limitation
1. Subject to
Articles 3 and 4 the following claims, whatever the basis of liability may
be, shall be subject to limitation of liability:
(a) claims in
respect of loss of life or personal injury or loss of or damage to property
(including damage to harbour works, basins and waterways and aids to
navigation), occurring on board or in direct connexion with the operation of
the ship or with salvage operations, and consequential loss resulting
therefrom;
(b) claims in
respect of loss resulting from delay in the carriage by sea of cargo,
passengers or their luggage;
|
Article
2
Créances
soumises à la limitation
1.
Sous réserves des articles 3 et 4, les créances suivantes, quel que soit le
fondement de la responsabilité, sont soumises à la limitation de la
responsabilité:
a)
créances pour mort, pour lésions corporelles, pour pertes et pour dommages à
tous biens (y compris les dommages causés aux ouvrages d’art des ports,
bassins, voies navigables et aides à la navigation) survenus à bord du navire
ou en relation directe avec l’exploitation de celui-ci ou avec des opérations
d’assistance ou de sauvetage, ainsi que pour tout autre préjudice en
résultant;
b)
créances pour tout préjudice résultant d’un retard dans le transport par mer
de la cargaison, des passagers ou de leurs bagages;
|
2. Claims set
out in paragraph 1 shall be subject to limitation of liability even if
brought by way of recourse or for indemnity under a contract or otherwise.
However, claims set out under paragraph 1(d), (e) and (f) shall not be
subject to limitation of liability to the extent that they relate to
remuneration under a contract with the person liable.
|
2.
Les créances visées au paragraphe 1 sont soumises à la limitation de la
responsabilité même si elles font l’objet d’une action, contractuelle ou non,
récursoire ou en garantie. Toutefois, les créances produites aux termes des
alinéas d), e) et f) du paragraphe 1 ne sont pas soumises à la limitation de
responsabilité dans la mesure où elles sont relatives à la rémunération en
application d’un contrat conclu avec la personne responsable.
|
[99]
There is
no dispute that the barge SPM 125 is a ship as defined in paragraph 25(1)(a) of
the Act nor that Irving is a “shipowner” as defined both in paragraph 25(1)(b)
of the MLA and in paragraph 2, Article 1 of the Convention.
[100]
There is
no dispute that the barge SPM 125 weighs less than 300 tonnes and accordingly,
the limitation of that amount set out in subsection 29(b) of the Act applies.
Subsection 29(b) provides as follows:
29.
The maximum liability for maritime claims that arise on any distinct occasion
involving a ship of less than 300 gross tonnage, other than claims referred
to in section 28, is
…
(b)
$500,000 in respect of any other claims.
|
29.
La limite de responsabilité pour les créances maritimes — autres que celles
mentionnées à l’article 28 — nées d’un même événement impliquant un navire
d’une jauge brute inférieure à 300 est fixée à :
…
b)
500 000 $ pour les autres
créances.
|
[101]
Article 11 of the
Convention allows for the creation of a limitation fund and provides as
follows:
Article 11
Constitution
of the fund
1. Any person
alleged to be liable may constitute a fund with the Court or other competent
authority in any State Party in which legal proceedings are instituted in
respect of claims subject to limitation. The fund shall be constituted in the
sum of such of the amounts set out in Articles 6 and 7 as are applicable to
claims for which that person may be liable, together with interest thereon
from the date of the occurrence giving rise to the liability until the date
of the constitution of the fund. Any fund thus constituted shall be available
only for the payment of claims in respect of which limitation of liability
can be invoked.
2. A fund may
be constituted, either by depositing the sum, or by producing a guarantee
acceptable under the legislation of the State Party where the fund is
constituted and considered to be adequate by the Court or other competent
authority.
3. A fund
constituted by one of the persons mentioned in paragraph 1(a), (b) or (c) or
paragraph 2 of Article 9 or his insurer shall be deemed constituted by all
persons mentioned in paragraph 1(a), (b) or (c) or paragraph 2, respectively.
|
Article
11
Constitution
du fonds
1.
Toute personne dont la responsabilité peut être mise en cause peut constituer
un fonds auprès du tribunal ou de toute autre autorité compétente de tout
État Partie dans lequel une action est engagée pour des créances soumises à
limitation. Le fonds est constitué à concurrence du montant tel qu’il est
calculé selon les dispositions des articles 6 et 7 applicables aux créances
dont cette personne peut être responsable, augmenté des intérêts courus depuis
la date de l’événement donnant naissance à la responsabilité jusqu’à celle de
la constitution du fonds. Tout fonds ainsi constitué n’est disponible que
pour régler les créances à l’égard desquelles la limitation de la
responsabilité peut être invoquée.
2.
Un fonds peut être constitué, soit en consignant la somme, soit en
fournissant une garantie acceptable en vertu de la législation de l’État
Partie dans lequel le fonds est constitué, et considérée comme adéquate par
le tribunal ou par toute autre autorité compétente.
3.
Un fonds constitué par l’une des personnes mentionnées aux alinéas a), b) ou
c) du paragraphe 1 ou au paragraphe 2 de l’article 9, ou par son assureur,
est réputé constitué par toutes les personnes visées aux alinéas a), b) ou c)
du paragraphe 1 ou au paragraphe 2 respectivement.
|
[102]
Section 32 of the MLA
sets out the procedure to be followed with respect to the establishment of a
limitation fund under Articles 11 to 13 of the Convention and provides as
follows:
Jurisdiction
of Admiralty Court
32. (1) The
Admiralty Court has exclusive jurisdiction with respect to any matter
relating to the constitution and distribution of a limitation fund under
Articles 11 to 13 of the Convention.
Right to
assert limitation defence
(2) Where a
claim is made or apprehended against a person in respect of liability that is
limited by section 28, 29 or 30 of this Act or paragraph 1 of Article 6 or 7
of the Convention, that person may assert the right to limitation of
liability in a defence filed, or by way of action or counterclaim for
declaratory relief, in any court of competent jurisdiction in Canada.
|
Compétence
exclusive de la Cour d’amirauté
32.
(1) La Cour d’amirauté a compétence exclusive pour trancher toute question
relative à la constitution et à la répartition du fonds de limitation aux
termes des articles 11 à 13 de la Convention.
Droit
d’invoquer la limite de responsabilité
(2)
Lorsque la responsabilité d’une personne est limitée aux termes des articles
28, 29 ou 30 de la présente loi ou du paragraphe 1 des articles 6 ou 7 de la
Convention, relativement à une créance — réelle ou appréhendée — , cette
personne peut se prévaloir de ces dispositions en défense, ou dans le cadre
d’une action ou demande reconventionnelle pour obtenir un jugement déclaratoire,
devant tout tribunal compétent au Canada.
|
[103]
“Admiralty Court” is defined in section 2 of the Act as
meaning the Federal Court.
[104]
It is clear from the
language of section 32 of the Act that only the Federal Court has jurisdiction
with respect to “any matter relating to the constitution and distribution of a
limitation fund” under the applicable Articles of the Convention.
[105]
Paragraph 1 of
Article 9 of the Convention is also relevant to the within proceedings and
provides as follows:
Aggregation of
claims
1. The limits
of liability determined in accordance with Article 6 shall apply to the
aggregate of all claims which arise on any distinct occasion:
(a) against
the person or persons mentioned in paragraph 2 of Article 1 and any person
for whose act, neglect or default he or they are responsible; or
(b) against
the shipowner of a ship rendering salvage services from that ship and the
salvor or salvors operating from such ship and any person for whose act,
neglect or default he or they are responsible; or
(c) against
the salvor or salvors who are not operating from a ship or who are operating
solely on the ship to or in respect of which the salvage services are
rendered and any person for whose act, neglect or default he or they are
responsible.
|
Concours
de créances
1.
Les limites de la responsabilité déterminée selon l’article 6 s’appliquent à
l’ensemble de toutes les créances nées d’un même événement :
a)
à l’égard de la personne ou des personnes visées au paragraphe 2 de l’article
premier et de toute personne dont les faits, négligences ou fautes entraînent
la responsabilité de celle-ci ou de celles-ci; ou
b)
à l’égard du propriétaire d’un navire qui fournit des services d’assistance
ou de sauvetage à partir de ce navire et à l’égard de l’assistant ou des
assistants agissant à partir dudit navire et de toute personne dont les
faits, négligences ou fautes entraînent la responsabilité de celui-ci ou de
ceux-ci;
c)
à l’égard de l’assistant ou des assistants n’agissant pas à partir d’un
navire ou agissant uniquement à bord du navire auquel ou à l’égard duquel des
services d’assistance ou de sauvetage sont fournis et de toute personne dont
les faits, négligences ou fautes entraînent la responsabilité de celui-ci ou
de ceux-ci.
|
[106]
The combined effect
of Articles 9 and 11 of the Convention, which forms part of the Act, is that
only one fund is established to answer the “aggregate of all claims which arise
on any distinct occasion”.
[107]
On the basis of the
evidence presently submitted, the “distinct occasion” in the present
circumstance is the loss of the rotors in the harbour of Saint
John on October 15, 2008.
[108]
In its supplementary
submissions, Siemens argues that there is no need for a limitation fund,
because the need for such fund arises only when the loss is international in
nature and property has been arrested.
[109]
This argument is
without merit. The MLA, incorporating the Convention, is domestic legislation. There
is nothing in the Act to suggest that limitation proceedings are not available
for maritime claims occurring in Canada. The Incident occurred in Canada.
[110]
The limitation fund
is available for the benefit of the shipowner, as determined in the limitation
proceedings and for “any person for whose act, neglect or default” it is
responsible: see Article 9, paragraph 1(a).
[111]
As discussed, the Act
provides for different limits in different circumstances. In the circumstances
of this Incident, a “distinct occasion involving a ship of less than 300 gross
tons”, the maximum liability for all claims arising is $500,000 pursuant to
subsection 29(b) of the Act. As described by Chief Justice Thurlow in Nisshin
Kisen Kaisha Ltd. at 237, limitation funds are constituted “for the purpose
of apportioning the limitation fund among the claimants”.
[112]
Irving, MMC and BMT
seek various directions relative to the limitation actions, including
directions as to the manner in which those actions should proceed, the giving
of notice of the actions to potential claimants, the constitution of a
limitation fund by the filing of a guarantee bond, the filing of claims against
the limitation fund and the distribution of the fund following the hearing of
the action in cause number T-520-10.
[113]
In my opinion, a
limitation fund should be established in this case. Irving has proposed that a guarantee bond be filed in an amount to
be set by the Court, that is $500,000 plus interest pursuant to subsection
33(5). The Court can determine the form of the guarantee pursuant to paragraph
33(4)(b) of the Act.
[114]
I am not satisfied
that sufficient detail has been provided by the parties for me to issue further
directions at this time. The parties have not made submissions as to
acceptability of a guarantee bond, or its form, as constituting the limitation
fund, nor have there been submissions as to the circumstances of publication of
notice of these actions. These matters, among others, should be discussed
between the parties.
[115]
The matter of setting
time limits within which the Defendants and other potential claimants must file
their defences or claims against the limitation fund is a matter that can be
addressed by the Case Management Judge who was appointed by Order made on June
10, 2010, pursuant to the Federal Courts Rules, SOR/98-106 (the “Rules”),
in respect of both Irving and MMC.
[116]
The Case Management
Judge can also deal with setting other time limits as may be required in the
prosecution of the two limitation actions to trial.
[117]
However, there is a
time period that will be set by the Court, in reference to paragraph (e) of Irving’s prayer for relief as follows:
directing
that any claim against the Limitation Fund not filed within the time specified
by the Court shall be barred from participation in the distribution of the
Limitation Fund;
[118]
This time limit will
be set by the Court upon review of submissions from the parties as to an
appropriate timeframe.
(iv) Motion to Enjoin
[119]
As noted above,
Irving, MMC and BMT seek an order enjoining the continued prosecution of the
proceedings in the Ontario Superior Court, as well as against the commencement
of proceedings before any other court or tribunal. Their motions are brought
pursuant to section 33 of the MLA.
[120]
Siemens argues that
this Court should not enjoin the Ontario proceedings unless it is satisfied
that Federal Court actions and the Ontario actions arise “in relation to the same
subject matter”. It submits that this is not the case.
[121]
Siemens further
argues that its right to choose its forum should not be lightly interfered
with, that the Ontario Rules of Practice and Procedure allow a broader range of
discovery, that the Ontario Court possesses jurisdiction over all parties and
all claims, that it would be forced to begin another action against Irving,
MMC, BMT and Superport and the parties would be required to take third party
claims for contribution and indemnity. As well, it submits that the Federal
Court is not the most efficient forum to determine all these issues.
[122]
The first question is
the test to be applied in exercising the power to enjoin, pursuant to section
33 of the MLA.
[123]
In the Sheena M,
Prothonotary Hargrave suggested that the tri-partite test in RJR-MacDonald Inc.
v. Canada (Attorney General), [1995] 3 S.C.R. 199, would apply
to a motion to enjoin proceedings before another court or tribunal. However, he
did not decide the point in that case and in my opinion, his remarks in that
regard are to be taken as obiter.
[124]
The language of
section 33 of the Act is very broad. Subsection 33(1) says that the “Admiralty Court… may take any steps it considers
appropriate”, including the extraordinary remedy identified in paragraph
33(1)(c) of enjoining proceedings before any other court, tribunal or
authority. The availability of this remedy indicates the value attached to the
importance of adjudicating all issues relevant to the constitution and
distribution of a limitation fund, in one forum. Proceeding in one Court
contributes to the expeditious disposition of issues relating to limitation of
liability.
[125]
The concept of
“appropriate”, includes the element of suitability. In this regard, I refer to
the decision in Levitt v. Carr et al. (1992), 23 W.A.C. 27 at para. 53.
[126]
I refer as well to
the decision in R. v. McIvor (2006), 210 C.C.C. (3d) 161 (B.C.C.A.) where
the British Columbia Court of Appeal, in the context of a criminal proceeding,
said the following at para. 30:
…in
its ordinary meaning, the word “appropriate” connotes suitability for a
particular purpose, something that is fit and proper in the circumstances.
[127]
In my opinion, having
regard to the facts alleged in the evidence submitted in the present case, it
is appropriate that proceedings outside the Federal Court be enjoined, to allow
adjudication in this Court of all issues relating to the Incident, including the
issues of liability which are the subject of the current proceedings before the
Ontario Superior Court of Justice.
[128]
I disagree with
Siemens’ argument that its Ontario actions are not “in relation to the same
subject matter” as these proceedings. I prefer the arguments advanced by Irving
and BMT on this point. In my opinion, the “subject matter” of both the Ontario and Federal Court proceedings is the Incident, that is the
damage to the rotors, liability for that damage and any limitation of that
liability.
[129]
In its Ontario actions, Siemens claims that Irving, BMT, MMC and others
are liable for its loss. The within proceedings raise a claim for
limitation of liability. The Convention, which forms part of the MLA, clearly
shows that there is a presumptive right to limit liability and a heavy burden,
pursuant to Article 4 of the Convention, on the part of any person seeking to
break that limit.
[130]
In their
pleadings in the within proceedings, Irving, MMC and BMT assert a right to
limit their liability, if any, relative to Siemens.
[131]
In cause
number T-520-10, MMC as a Defendant, seeks contribution and indemnity from Irving and says that this specific claim
is not subject to limitation. In its Reply, Irving pleads that the claim for contribution
and indemnity is subject to limitation pursuant to the Act and the Convention.
[132]
In cause
number T-666-10, BMT as a Defendant, claims contribution and indemnity from MMC
and advances a claim in negligence against AXA, by way of a Third Party Claim.
[133]
MMC, in
its Defence to Counterclaim, pleads that the claim for contribution and
indemnity is subject to limitation. Irving,
in its Defence to the MMC action, pleads that MMC is entitled to limit its
liability as long as Irving is able to do so.
[134]
Irving and
MMC, in their pleadings filed in these two limitation actions, claim that the
aggregate of all claims made against them, jointly, is limited to the sum of
$500,000.
[135]
The sum of
$500,000, as the limit of liability, derives from the combined effect of
subsection 29(b) and Article 9 of the Convention.
[136]
Presumptively,
the fund available to answer Siemens’ claim for damages is $500,000. The damage
claim arises in relation to the Incident. Regardless of the number of actions
started and cross-claims advanced, if the right to limit is not defeated by
evidence of recklessness pursuant to Article 4 of the Convention, the only
amount available to meet Siemens’ claim will be $500,000, together with
interest.
[137]
The fact
that Siemens’ claim is in the millions is not a principled reason to postpone
adjudication of the issues in the limitation proceedings, foremost whether
limitation of liability is available. Indeed, in my opinion the discrepancy
between the amount claimed and the prima facie amount of the
limitation fund is a factor weighing heavily in favour of proceeding with the
limitation actions and enjoining the liability action. This is a practical
consideration which the Court acknowledges. There will be significant costs
saved for all parties and persons by proceeding in this manner.
[138]
While it is clear
that Irving meets the definition of “shipowner” set
out in Article 1 of the Convention, it is also clear from the arguments made
that the status of MMC and BMT, as “shipowners”, will be robustly debated.
Arguably, MMC will rely on paragraph 4 of Article 1 to claim the right to
limit.
[139]
Insofar as BMT claims
the right to limit, there is an issue as to whether Siemens meets the
definition of “shipowner”, a status that may arise from its contractual
relationship with Irving.
[140]
I refer, as well, to
the individuals who were named as defendants in the second action commenced by
Siemens in the Ontario Superior Court of Justice. At first blush, they would
appear to benefit from paragraph 4, Article 1 of the Convention as being
persons “for whose act, neglect or default the shipowner” is responsible.
[141]
All of these issues
will be subject to argument, both for and against, upon the basis of whatever
evidence is submitted.
[142]
Siemens will resist
the invocation of the right to limit. It has already shown, by the commencement
of the two Ontario actions, that it is casting a broad net
in terms of potential defendants.
[143]
This wide range of
litigation is another factor in favour of proceeding with the limitation action
first, or at least at the same time, as the liability action and to deal with
the issues of the entitlement to limit, both in terms of who can limit and
whether there is conduct barring limitation.
[144]
I note, as well, that
the class of potential plaintiffs or claimants against the limitation fund is
not yet known. Siemens, to date, is the only Plaintiff but there may be others.
In these circumstances, it becomes important to enjoin suits and actions in
other courts or tribunals and upon giving notice, allow potential claimants to
file their claim against the limitation fund.
[145]
Siemens has made it
clear that it will also contest the right of Irving
and others to invoke limitation of liability, having regard to Article 4 of the
Convention. In order to show that the right to limit is unavailable, it will
have to lead evidence to establish that the conduct of Irving and others in relation
to the Incident was reckless. In my opinion, there will inevitably be an
overlap between this evidence with the evidence required to prove liability
against the defending parties in the Ontario actions. As Siemens argues, duplicity of
proceedings with the risk of inconsistent findings should be avoided.
[146]
As discussed, the
determination of liability, and limitation thereof, for the Incident can be
determined in the Federal Court, as well as in the Ontario Superior Court of
Justice.
[147]
The present motions
for directions, with respect to section 33 of the Act, are interlocutory in
nature. An order dealing with the limit of liability and its ultimate
availability would be made only after a full trial of the issues.
[148]
I do not accept the
submissions made by Siemens, endorsed by AXA, that the liability trial should
proceed before the Ontario Superior Court of Justice, on the basis that certain
steps have been taken in the prosecution of the existing action, including the
retention of an expert in preparation of an expert report, and the serving of a
jury notice. Siemens points out that section 49 of the Federal Courts Act prohibits
jury trials.
[149]
I also do not accept
that Siemens’ choice of forum militates in favour of the Ontario proceedings. As discussed, the MLA provides Irving, BMT and
MMC with their own cause of action to limit liability, a proceeding which is
meant to be expeditious. Those parties, too, have a choice of forum in which to
bring their actions, and that choice must be balanced with the choice made by
Siemens.
[150]
While the Ontario
Rules of Practice and Procedure allow a broader range of discovery, a case
management judge of this Court can also allow for broader discovery, if
warranted.
[151]
The question of the
availability of a jury trial is an appropriate factor to consider, but is not
determinative. In my opinion, depriving Siemens of the option to have its claim
considered by a jury is outweighed by the inconvenience and repetition that
would be required to have the issue of limitation considered in this Court, and
the issue of liability determined in the Ontario Superior Court of Justice.
[152]
Siemens also argues
that the Ontario Court possesses jurisdiction over all parties and all claims,
and again submits that this Court does not have that jurisdiction.
[153]
On the other hand,
BMT submits that it is not clear that the Ontario Superior Court of Justice has
jurisdiction over all the defendants Siemens has named in the Ontario actions, particularly the individuals in its second action.
The Incident did not occur in Ontario, and Siemens has not demonstrated that
those individuals have attorned to the Ontario action, that they have business assets
in that Province, or that there is a contractual nexus between those individual
defendants and the Ontario Superior Court of Justice.
[154]
The Federal Court has
jurisdiction over all claims relating to the Incident, which is clearly
maritime in nature. The issue of liability as between Siemens and the
Defendants can be addressed in the context of the limitation actions.
[155]
It will not be
necessary for Siemens to begin another action in the Federal Court, with
resulting counterclaims and cross-claims by the other parties, although it can
do so if it likes. Siemens, itself, can proceed by way of counterclaim or
cross-claims against the Defendants in the two limitation actions, pursuant to
paragraph 33(4)(a) of the MLA. If it is determined in the limitation actions
that any party is not entitled to limit its liability pursuant to the
Convention, Siemens can pursue its claims in the Ontario
proceedings.
[156]
Contrary to Siemens’
submissions, the Federal Court is the most efficient forum to determine all the
issues relative to the Incident. It is beyond doubt that the Federal Court has
jurisdiction over the issue of liability. Only the Federal Court has
jurisdiction over the constitution and distribution of a limitation fund. While
such a fund may be incidental to the determinations of liability and
limitation, having the entirety of the proceedings considered in one Court
would be the most efficient. The issue of entitlement to limit can be
determined in the limitation actions.
[157]
In the
result, the motions of Irving, MMC and BMT to enjoin all parties and any
persons from continuing with or commencing any proceedings before any court or
tribunal, including an arbitration panel, other than this Court, in respect of
the Incident are allowed.
Conclusion
[158]
For the reasons
above, Siemens’ motions to stay are dismissed and the limitation actions will
proceed in accordance with these Reasons.
[159]
The motions of
Irving, MMC and BMT to enjoin any other proceedings before any court or
tribunal in respect of the Incident is granted.
[160]
If the
parties cannot agree on costs, that issue may be addressed in submissions to be
served and filed on or before July 14, 2011.
[161]
These
Reasons for Order and Order will be filed in both cause number T-520-10 and
cause number T-666-10.
ORDER
THIS COURT ORDERS that:
1. The motions to stay these
proceedings are dismissed.
2. The Defendants and any other person
are enjoined from commencing or continuing proceedings before any other Court
or tribunal than the Federal Court against Irving, the Plaintiff in T-520-10
and MMC, the Plaintiff in T-666-10, in respect of the Incident.
3. Any claim in respect of the
Incident which may be subject to limitation of liability shall be asserted
either by way of a counterclaim or cross-claim in these actions, or by way of a
separate action before this Court.
4. The issues determined and the
procedure established by this Order do not preclude any of the Defendants or
claimants from alleging that:
(a) Irving and MMC, as Plaintiffs,
and any other party, are not entitled to limit liability as contemplated by the
MLA; and
(b) One or more of the parties do
not fall within the category of those entitled to invoke pursuant to he MLA,
the right to limit liability.
5. The parties herein are
directed to consult and to submit a draft order to give effect to the Reasons
for Order, concerning the establishment of a limitation fund in the amount of
$500,000 plus interest from October 15, 2008 to the date on which the statutory
limitation fund is constituted, pursuant to subsection 33(5) of the Act. The
parties shall specifically address the relief sought in paragraphs (a), (b),
(c), (d), (e), (g) and (h) of Irving’s Notice of Motion. The draft order will
be submitted to the Court on or before July 14, 2011.
6. The establishment of a
limitation fund, in accordance with the MLA, in the amount of $500,000 and
interest, shall not preclude any party or person from denying liability or
legal responsibility and contesting the quantum of any claim.
7. These actions are specially managed
proceedings and following constitution of the limitation fund, any party shall
be at liberty to seek orders and directions from the Case Management Judge
concerning the completion of pre-trial steps, the consolidation of the actions,
the fixing of a single or separate hearing and any other relevant matter
mentioned in the MLA or the Rules.
8. If the parties cannot agree on
costs, that issue may be addressed in submissions to be served and filed on or
before July 14, 2011.
“E.
Heneghan”