[ENGLISH TRANSLATION]
REASONS FOR JUDGMENT
Tardif J.
[1]
This is an appeal from a case regarding the
insurability of work performed by the Appellant for the account and benefit of
the Intervener during the period from January 9, 2009, to
December 16, 2009.
[2]
From the outset, the Intervener and the
Respondent argued that the work at issue was performed under an enterprise
contract as a subcontractor and, consequently, was not insurable.
[3]
However, the Appellant argues that the work was
performed under a contract of service and was insurable under the Employment
Insurance Act.
[4]
After the Appellant had testified regarding the
relevant facts supporting his arguments, the Respondent told the Court that it
had no evidence to submit and because of that it intended to consent to
judgment in favour of the Appellant.
[5]
The Intervener told the Court that it was in
total disagreement with the Respondent's assessment of the case. It then told
the Court that it intended to prove that its intervention had merit.
[6]
After having testified, noting the particularity
of the situation, it asked the Court for a postponement so that it could hire a
lawyer; the Appellant objected to this.
[7]
The Court granted the postponement request on
the condition that the Intervener cover only the cost of transcripts and copies
for the parties and the Court.
[8]
The proceedings resumed on January 14,
2016. There was not enough time to continue with the Intervener's case; the
proceedings continued in Montréal on June 1, 2016.
Facts
[9]
The Appellant argued that he received the job at
issue in this case through a newspaper advertisement. He stated that he signed
no written contract, but entered into a verbal agreement with the Intervener on
the nature of the work to be performed.
[10]
The Appellant argued that the verbal agreement
set out conditions in terms of hours worked, how to calculate them, the
remuneration involved, and the location of the work; he maintained that he
required net pay of $1000 per week.
[11]
The Appellant argued that the Intervener had
agreed to the $1000 amount that was to have been, and was, deposited directly
into his bank account. Copies of statements were produced and they confirmed
the payments and the regularity. With a few minor exceptions, the Appellant
received the dollar amounts at issue on a regular basis and continued to do so
throughout the period at issue.
[12]
The Intervener provided the necessary tools to
perform the agreed-upon work: an office, a computer, rulers, and so on.
[13]
As part of his work, the Appellant also acted as
a key person to train Martin Cayer, who worked in the same office in a
building that the Intervener rented; Mr. Cayer was the brother-in-law of
one of the two shareholders.
[14]
The Appellant was the first to show up on the
premises, arriving very early. He opened the office and his brother-in-law,
Martin Cayer, generally showed up a bit later. The Appellant always filled
out a timesheet that he submitted to Mr. Cayer.
[15]
His work included obtaining plans and
specifications for construction projects that were in progress or likely to
begin. From the plan, the Appellant determined how many materials were required
to carry out the projected subcontract; this involved assessing the materials
required to divide the surfaces. These materials included plywood or drywall
for the walls, ceilings, and so on; in other words, the Appellant made a
detailed determination of the material required to do the ceilings and divide
the various surfaces.
[16]
Once the exact quantities were established and
determined, he submitted everything to his bosses, who then calculated the
related prices to submit a bid to the recipient of the contract for the entire
project; the Intervener would still act as a subcontractor.
[17]
When he wanted time off, he had to ask for it.
Vacations fell under the rules governing the construction sector. He was paid
the agreed-upon amount ($1000/week) through direct deposits into his bank
account.
[18]
Lastly, the Appellant explained the
circumstances surrounding his layoff. Upon noting that part of the agreed-upon
payment had not been deposited into his bank account, and being very surprised
with the situation, which had never happened before, he contacted the
Intervener's representative and was told that his services were no longer
required.
[19]
He then requested a record of employment that he
could use to file an Employment Insurance claim. The Intervener refused on the
pretext that he had always worked as a self-employed person and was not
employed under a contract of service.
[20]
He therefore took various steps to request and
obtain the possible compensation set out in various regulations, namely with
the Commission des normes, which referred him to the Employment Insurance
Commission. Those are the main facts submitted by the Appellant to support his
appeal.
[21]
The Intervener's representative,
Michel Desmarais, also testified. He argued that the work performed by the
Appellant had been done under an enterprise contract. He explained that the
Appellant's services were not exclusive; he gave an example where the Appellant
allegedly performed work for someone else without giving any details, leaving
even this aspect of the case rather vague and ambiguous.
[22]
Mr. Desmarais said that the Appellant had carte
blanche to perform the work. The Intervener said that the Appellant had no
restrictions to comply with except delivering the work within the required time
frame to formalize a bid within the deadlines imposed by the general
contractor.
[23]
It also referred to and formally insisted on
account statements and a contract signed by the Appellant. The content of this
contract refers to an enterprise contract, not a contract of service as the
Appellant contends.
[24]
It also explained that the Appellant had the
experience and knowledge to differentiate the nuances and tell the difference
between an enterprise contract and a contract of service.
[25]
It submitted several documents containing the
Appellant's signature. These documents consist of a contract stating that it
was essentially an enterprise contract, on the one hand, and of several
invoices, on the other.
[26]
Essentially, the evidence presented by the
Intervener's representative, Mr. Desmarais, maintained that the contract
that bound the Intervener to the Appellant was an enterprise contract for the
following reasons:
−
Willingness clearly stated by the parties;
−
Flexibility;
−
Non-exclusivity of the work;
−
No relationship of subordination;
−
No control;
−
No supervision;
−
Plurality of very relevant documents signed by
the Appellant.
[27]
The issue became very tense when the question of
the Appellant's signature on the documents (contract and invoices) came up.
Categorically denying having signed the documents at issue, the Appellant told
the Court that he filed a criminal complaint alleging that the documents were
forged; he then hired an expert to prove that it was not his signature on the
documents.
[28]
The expert at issue testified. She corroborated
another expert's findings that the signatures were forged and did not belong to
the Appellant; however, this expert was not present to testify.
[29]
Subsequently, the Intervener's representative,
Mr. Desmarais, reacted as if the Appellant were accusing him of forging
his signature. The Appellant never directly or indirectly accused
Mr. Desmarais of having forged his signature; essentially, he vehemently
argued that it was not his signature.
[30]
To refute the Appellant's arguments, the
Intervener hired two experts: a handwriting expert and a polygraph operation
expert.
[31]
The first expert firmly held that the documents
at issue had indeed been signed by the Appellant.
[32]
The second held that Mr. Desmarais took a
lie detector test and it was determined that he was not the originator of the
signatures and that if they were forgeries, he did not know who was
responsible; in other words, the signatures and documents were forged and
Mr. Desmarais was in no way involved.
[33]
The Intervener also asked and vehemently
insisted that the Appellant also take a lie detector test; he agreed on the
condition that his brother and brother-in-law also take one. In the end, he
simply refused.
[34]
To support its evidence, the Intervener called
one of its co-shareholders, Mario Desmarais, and Martin Cayer, the
Appellant's brother-in-law.
[35]
The testimony contradicted part of the evidence
submitted by the Appellant, namely with regard to when he was on the premises
and the date of a meeting.
[36]
Overall, the testimony at issue was vague,
unclear, and full of hostility. As a significant example of the evidence being
questionable, Mr. Desmarais strongly contradicted the Appellant to the
effect that there was no meeting on December 28. To validate his argument,
he produced evidence of a reservation for several days in the North during the
2009 holiday season, which, needless to say, included December 28.
[37]
This evidence is in no way decisive because
Mr. Desmarais could have decided to cut his trip short so that he could
attend the meeting with Mr. Perras. The documents mention several people
without stating their names. Yet it is clear that this does not prove that
Mr. Desmarais was there and if he were, he could very well have cut his
trip short and gone to the office for December 28.
[38]
In addition, when cross-examined again about the
December 28 meeting, the Appellant again confirmed it, even adding having
reached Mr. Desmarais by telephone, and that he told him that he was in
the North but that he would be at the office on December 28 to meet with
him.
[39]
So this supposedly decisive argument just fell
apart, at least in terms of its probative value. Several times, the Intervener
gave explanations and reasons that seemed relevant at first glance, but whose
credibility crumbled after cross-examination; the trip to the North, the letter
to a car dealership, when the Appellant showed up for work, and the
non-exclusivity of the Appellant's work are telling facts.
[40]
The Intervener's submissions in no way proved
its inability to attend a meeting with the Appellant. Moreover, he did not
insist on having one.
[41]
Martin Cayer argued with hesitation and
discomfort that the Appellant was rarely at the office very early in the
morning.
[42]
On the issue of when the Appellant showed up for
work, the owner of the premises rented by the Intervener where the Appellant
worked, totally uninterested in the case, unequivocally upheld and confirmed
the Appellant's testimony regarding when he showed up on the premises in the
morning.
[43]
The testimony given by the Desmarais brothers
and the brother-in-law of one of them all have the same characteristics: vague
and unclear. A lot of implications and answers that varied with regard to the
insistence of the questions in a context of arrogance can be explained by the
complaint filed against the Intervener by the Appellant.
[44]
Did Mr. Desmarais or anyone else forge the
Appellant's signature? That is a question whose answer does not fall under this
Court's jurisdiction. In addition, yes-or-no answers add absolutely nothing to
the relevant evidence available to me. I therefore have no reason to doubt
Mr. Desmarais when he says that he did not forge the Appellant's
signature. The signatures at issue could have been forged by anyone.
[45]
Although the Appellant did indeed sign the
documents at issue, this factor in and of itself would not have been enough to
dismiss the appeal. Case law makes several mentions of the relative importance
of written and signed contracts.
[46]
To determine the nature of a working contract,
having them in writing is certainly important, but they must essentially
validate the facts in terms of how the work will be performed and under what
conditions and circumstances.
[47]
Only the facts inherent to its performance,
context and terms have decisive importance for differentiating an enterprise
contract from a contract of service.
[48]
The intent written and signed by the parties to
a contract is helpful and may be considered as an addition in situations that
are very difficult to assess. However, it will always be essential for written
contracts to be validated by facts; otherwise, these contracts will be removed
from the analysis.
[49]
In other words, the conditions, terms, and
methods are factors that must reflect the terms of the written contracts;
otherwise, the Court will conduct its analysis based on the facts and will not
take the written contracts into consideration.
[50]
In this case, the preponderance of evidence is
to the effect that the facts related to how the work was performed are in no
way consistent with the content of the written contracts.
[51]
The Intervener's representative,
Mr. Desmarais, argues that he told the truth and that everything is
confirmed by the two expert assessments: from the handwriting expert and the
polygraph expert. He adds that the Appellant who refused to take the same test
is lying on all fronts.
[52]
Yet the testimony given by Mr. Perras (the
Appellant) was clear and accurate and the explanations were reasonable, logical
and credible. The answers never varied despite the insistence and repetition of
the questions.
[53]
With regard to evidence, the number of witnesses
and testimonies is in no way decisive. Only quality and credibility have a
relevant impact.
[54]
With regard to the three expert assessments in
the record, I will limit myself to the following comments: the record gives a
rather clear account of the issue of experts in a case. Generally, expert
assessments produce plausible, reasonable, probative, but never irrefutable,
findings. The findings generally confirm the position put forward by whoever
receives the fees for preparing the assessment.
[55]
The direct effect of such a reality is that the
findings retained are generally consistent with the expectations of the agent
or agents. Moreover, it is still possible not to use the findings in an
assessment that allegedly did not meet their expectations.
[56]
In this case, the Court listened very carefully
to the expert testimony.
[57]
However, contradictory findings arise from a
serious, thorough and professional analysis.
[58]
Consequently, I essentially trust the facts and
elements highlighted by the evidence with regard to the work at issue
concerning the circumstances and terms of its performance during the period at
issue.
[59]
Mr. Perras' testimony was clear, accurate
and very detailed. The explanations submitted were reasonable and very
credible. In the two very important meetings, I refer to that where he was
informed that his services were no longer required and to that where he met
with the person responsible for his Employment Insurance file.
[60]
On each occasion, the Appellant reacted
spontaneously and forcefully and clearly expressed his disappointment, but
especially his very firm intention to contest the facts before him (namely,
that he had worked as a self-employed person).
[61]
To sum up, I noted certain elements that
unequivocally confirm or uphold the presence of an actual contract of service.
The facts include:
•
The Appellant opened the office and had the
access code;
•
The Appellant completed an activities report and
filled out timesheets every week;
•
Remuneration was always the same and was deposited
directly into his bank account continuously and without interruption;
•
The Appellant had business cards that were
provided to him and paid for by the payer of the weekly remuneration;.
•
The Appellant's duties were defined, specific
and repetitive;
•
All tools, including pencils, paper, a computer,
rulers, an office and a telephone were provided to him by the payer of the
remuneration;
•
Fixed working hours (7 a.m. to 4 p.m.
every business day);
•
Needed permission to change or modify his
regular work schedule, including to prepare for his wedding;
•
Very special circumstances when he was laid off,
when the Appellant spontaneously asked for a record of employment for
Employment Insurance purposes. At his request, he was told that he would be
declared a self-employed person and that he will have to get GST and QST
registration numbers;
•
Correspondence from the Intervener regarding the
Appellant's actual status with the authorities;
•
No application for a GST or QST registration
number from the Intervener upon hiring.
[62]
To begin with, counsel for the Respondent had
told the Court that he would consent to judgment immediately after the
Appellant presented his evidence on the first day of the hearing.
[63]
Later, he reserved his right to slightly modify
his final position.
[64]
Counsel for the Respondent was very diligent
throughout the case. When the Appellant and the Intervener rested their cases,
the Court asked the Respondent to clearly state his position.
[65]
To this effect, counsel for the Respondent
upheld and confirmed his initial assessment of the case and told the Court that
the Appellant had established the merit of his appeal by retaining a few
elements also held by the Court regarding the existence of an actual contract
of service.
[66]
The arguments and submissions put forth by the
Intervener are not upheld and are therefore overruled.
[67]
The appeal is allowed and the Minister's
decision is set aside in that the work performed by the Appellant during the
period at issue for the account and benefit of the Intervener was a contract of
service and therefore insurable.
Signed at
Ottawa, Canada, this 27th day of October 2016.
“Alain Tardif”