Supreme Court of Canada
Cargill Grain Ltd. v. Davie Shipbuilding Ltd., [1977] 1
S.C.R. 659
Date: 1975-12-04
Cargill Grain
Limited (Defendant) Appellant;
and
Davie Shipbuilding
Limited (Plaintiff) Respondent.
1975: June 20; 1975: December 4.
Present: Ritchie, Spence, Pigeon, Beetz and
de Grandpré JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
QUEBEC
Sale of
goods—Calculation of weight of steel—Erroneous interpretation of
contract—Inexact nature of draught displacement method—Inadmissibility of
hearsay evidence—Weights and Measures Act, R.S.C. 1970,c. W-7.
A number of contracts for the construction of
harbour facilities, providing inter alia for the supply of steel, were
awarded by appellant to respondent. The latter obtained judgment against
appellant in the Superior Court for $594,856.08, and the cross-demand was
dismissed. A majority of the Court of Appeal upheld this decision. The
dissenting judge would have deducted an amount of $120,800.61, that is to say
the greater part of an invoice of $130,754.61 for additional steel supplied
under contract No. 7. The point in dispute, on which Hyde J. in the Court of
Appeal based his dissent, concerns the manner of calculating the additional
steel delivered under contract No. 7, having regard to the relevant clauses. This
contract stipulated a lump sum price for a certain quantity of steel, but also
provided that “should the final shipping weight differ from the tonnage
stated”, this price would be decreased or increased at certain rates, depending
on the type of steel. In order to arrive at the sum of $130,754.61, respondent
calculated the amount of additional steel supplied by using the draught
displacement method. According to the trial judge, this method had been
stipulated by the parties for contract No. 7, and reference therefore had to be
made to it. The Court of Appeal held unanimously that this was a
misinterpretation on the part of the trial judge, but the majority held that
although this method had not been stipulated by the parties, it was the most
appropriate one in the circumstances, and they upheld the conclusions of the
Superior Court. Hence the appeal to this Court.
Held: The
appeal should be allowed.
Whereas other contracts between the parties
(contracts 6 and 12) stipulate a method for calculating the
[Page 660]
weight of the steel, the so-called C.I.C.S.
method, the contract which is the subject of the dispute is silent on the
matter. When the contract talks of shipping weight, it is not contemplating the
draught displacement method. The trial judge accepted the submission that this
method was the one intended by the parties, and therefore saw no need to
consider appellant’s evidence on the accuracy of the method.
On the other hand, once it is admitted that
the contract is silent on the manner of determining the weight of the steel
sold and delivered, the general rules governing commercial contracts must be
applied. Generally, when this type of contract speaks of the weight of
merchandise to be delivered, it means the weight determined by weighing the
object on scales that have been verified in accordance with the Weights and
Measures Act. Even though in the case at bar the seller, Davie, had no
scales on which to weigh the large pieces of steel shipped by water, it had the
onus of proving that the method used was normal under such circumstances and
that it was a commercially acceptable way of determining the weight of
structural steel.
The witnesses all recognized that the draught
displacement method was very inaccurate and that in practice it is never used
to calculate the weight of steel or other expensive merchandise. This method is
also incompatible with the clause in the contract providing for three,
different prices for the additional steel, depending on the category.
At the trial, plaintiff Davie’s sole basis for proof of its
calculations was a document prepared by one J.R. Josslyn, deceased. This was
thus hearsay evidence, inadmissible unless the document came under one of the
exceptions. The document did not contain facts but conclusions, and it is not possible
to ascertain and verify the calculations made in order to arrive at the result
recorded. This is not a situation where, owing to the sudden death of one of
its employees, a business firm would be totally unable to prove a claim, since
the structure erected for appellant is still there and there is nothing to
prevent respondent from establishing the weight by measuring the pieces, which
is the usual method in the case of structural steel.
Since the draught displacement method was not
stipulated for the calculation of the weight of steel delivered, and since
Josslyn’s conclusions were not admissible as evidence, there is no other
evidence as to weight than that present by the witness Armstrong on appellant’s
behalf. According to this witness the additional steel weight is some 21 tons,
and the claim under this heading should be reduced from $130,754.61 to
$5,447.60.
[Page 661]
The cross-demand raises only questions of
fact on which the Quebec courts
agreed; their conclusions should not be disturbed.
Royal
Victoria Hospital
et al. v. Mary Morrow, [1974] S.C.R. 501; Ares
v. Venner, [1970] S.C.R. 608, referred to.
APPEAL from a decision of the Court of Appeal
for Quebec upholding a judgment of the Superior Court ordering appellant to pay
respondent the sum of $594,856.08 and dismissing appellant’s cross-demand.
Appeal allowed and judgment of the Superior Court altered by reducing the
amount of the order by $125,307.
The judgment of the Court was delivered by
PIGEON J.—This is an appeal from a decision of
the Quebec Court of Appeal which upheld the judgment of the Superior Court
maintaining action by respondent Davie Shipbuilding Limited (“Davie”) for the
sum of $594,856.08, and dismissing the cross-demand of appellant (“Cargill”).
Hyde J.A., dissenting, would have deducted from the judgment, besides a small
sum of $984.66, an amount of $120,800.61, that is to say the greater part of an
invoice of $130,754.61 for additional steel.
In its factum and in its argument at the
hearing, Cargill limited its appeal to two points: (1) the amount of
$130,754.61; (2) the cross-demand.
With respect to the Cross-demand, which is based
on alleged defects, the Court has before it concurrent findings of fact in the
courts below which led to its dismissal. Cargill did not really raise any
question of law in this regard or show any manifest error which would justify
this Court’s intervention. There is therefore no need to dwell further on this
part of the appeal.
The same cannot be said for the amount that is
the subject of Hyde J.A.’s dissent. As the judges who heard the case in the
Court of Appeal are unanimous in acknowledging, the trial judge misunderstood
the meaning of the contract under
[Page 662]
which Davie claimed the amount of $130,754.61 in
question. Furthermore, in order to allow this amount he relied on the result of
observations and calculations made by a person who died before the trial, and
whose observations and calculations were not preserved. It is therefore
necessary to state the essential facts relating to this part of the case.
In the spring of 1959, Cargill decided to erect
harbour facilities for the purpose of receiving and delivering grain at Baie
Comeau. It awarded a number of contracts to Davie, inter alia one
designated as “contract No. 7” and dated April 3, 1959 for the construction of
warehouse No. 1. It stipulated a lump sum price but with provision for
additional payment should the total shipping weight of the steel exceed the
quantity anticipated. The two relevant clauses read as follows:
3. TONNAGES
The price tendered is based on the
following shipping weights, including erection bolts, etc…
(a) Supplied by
Contractor
|
1,247 tons
|
(b) Supplied by
Owner
|
1,207 tons
|
TOTAL
|
2,454 tons
|
4. UNIT PRICE ADJUSTMENTS
Should the final shipping weight differ
from the tonnage stated, it is agreed that the lump sum tendered will be
decreased, or increased at the following unit price rates.
Plate Steel
|
$264.00 per ton
|
Structural Steel
|
$237.00 per ton
|
Miscellaneous
Ironwork
|
$403.00 per ton
|
It is agreed that ton shall mean the short
ton of 2,000 pounds.
Contracts Nos. 6 and 12 were not drawn up in the
same way as contract No. 7. In the first there is, with respect to the
structural steel only and not to the hoppers and so forth for which a set price
is stipulated, the following provision:
ITEM 102—Extra or credit to Item 101 for Alterations Causing
Variation from the Total Weight of Steel Submitted in Item 101.
[Page 663]
The quantity used for payment under Item
102 shall be the difference between the total weight quoted under Item 101 and
the total weight actually supplied. Measurement for payment shall be as
stipulated in C.I.S.C. technical bulletin No. 12, Part 3—Calculation of weights
for pound-price bids.
There is a similar provision in contract No. 12
with respect to certain items. The so-called C.I.S.C. method of calculation
involves determining the weight of the pieces from their volume, based on the
density of steel fixed at 0.2833 lb per cubic inch. Volume is calculated
according to the theoretical dimensions of the pieces, without deductions for
trimming.
In this regard the trial judge, before quoting
the contract provisions, observed:
[TRANSLATION] The adjustment of the lump
sum prices stipulated in the three contracts is to be made on two different
bases. Under contracts Nos. 6 and 12, the calculation is to be made from the
drawings, by finding the volume of the steel or iron used, and establishing its
weight according to the so-called C.I.S.C. method, described in the contract
and found in C.I.S.C. bulletin No. 12, Part 3. It is quite simple for experts
to establish the weight of steel entering into any construction by using this
method.
A different method was adopted in
contract No. 7 for calculating the weight of steel which entered into the
construction. There, the parties stipulated the draught displacement method for
the vessels carrying the steel. This method
involves reading the draught marks before and after loading the steel. By using
this method one can determine how much lower the ship is in the water. Knowing
the size of the ship and the weight of various objects on board which are not
part of the shipment of steel, and which accordingly must not figure in the
calculations, experts can establish the weight of steel carried in this
fashion.
There is no need to discuss whether or
not these methods are exact. Since the parties stipulated in the contracts that
these methods were to apply, it is to these methods that reference must be
made. (My italics and my underlining.)
Then, having quoted the contract provisions and
rules on the claim under contracts Nos. 6 and 12 which is no longer in dispute,
the trial judge added:
[Page 664]
[TRANSLATION] However, the situation is
different for contract No. 7. As in the other contracts, a lump sum
price was stipulated on the basis of an approximate estimate. The contract then
goes on to state that the total weight of the steel used in the performance of
this contract shall be established by the draught displacement method. The
method works as follows. On the side of the vessel there is a graduated scale
showing the settling of the vessel in the water. The heavier the load, the
greater the settling. The scale is read before and after loading. It is a
simple matter for experts to determine the weight of the load; they take into
account the size of the vessel, the depth to which it has settled and the
weight of the various objects placed on the vessel that were not part of the
load, as for example trucks, mechanical cranes and various pieces of equipment.
(My italics.)
The Court of Appeal held unanimously that this
was a misinterpretation. Deschênes J.A. stated:
[TRANSLATION] At the outset, I must agree
with Appellant that the trial judge misinterpreted contract No. 7 when he
wrote:
(text of the two italicized passages in the
above quotations).
With all due respect, as my brother Rinfret
J.A. has emphasized, it should rather be said that the contract is silent as to
the method of calculation to be used, while the other contracts stipulated a
specific method. It was accordingly respondent’s duty to use the method most
appropriate to the circumstances: given the great size of several pieces
required by the contract it was decided, and rightly so, to resort to the
draught displacement method. Should the Court and the parties lose the benefit
of this because architect Josslyn died between the relevant events and the
trial?
In my opinion, the trial judge correctly
held that they should not, and I adopt his reasoning and the authorities
referred to in support of it.
As may be seen, while acknowledging the
fundamental error of the trial judge, the majority on appeal still upheld his
conclusions. In my opinion Hyde J.A. dissenting, correctly held to the
contrary:
Contract No. 7, however, is silent on the
method and we have only the term “final shipping weight” as used in clause 4,
above quoted, to go by. Of the total 2960 tons which Davie claims were
delivered under this contract all but some 80 tons were shipped by boat from
its yards
[Page 665]
at Lauzon to the erection site at Baie Comeau
(see Ex. P-257 and supporting invoices filed en liasse as Ex. P-78).
Undoubtedly the most exact weights would
have been determined by the use of scales, public or otherwise, but Davie
claims that the size and shape of a number of pieces made this impractical and
furthermore, strange as it may seem, Davie had no scales at its works (Veliotis
5-868). Accordingly it relied on ship draught displacement calculations.
Veliotis (Davie’s Vice-President) describes the procedure followed (5-800):
From each shipment we had a shipping weight
as taken by the method I described—by the additional displacement of the
vessel. This all added up to a total weight, from which we deducted the weights
of amounts of steel, which are invoiced separately, less an allowance for
dunnage and blocking and other items that were not a part of the contract. We
arrived at a weight, a net weight, of some 5,920,000 pounds, I believe.
which he said is “in accordance with the
contract”. It may have been this comment which led the trial judge astray into
stating, quite erroneously, that the parties had stipulated that the weights
would be determined by “la méthode de tirant d’eau”.
That this is an error of some consequence
may be appreciated by the judge’s statement following his description of this
method of weighing:
[TRANSLATION] There is no need to discuss
whether or not these methods are exact. Since the parties stipulated in the
contracts that these methods were to apply, it is to these methods that
reference must be made.
The passage quoted shows that the trial judge
simply refused to consider the evidence presented by Cargill on the inexact
nature of the draught displacement method. He accepted Davie’s submission that
this was the method stipulated in the contract. It is now agreed that this was
wrong. The contract did not state how the quantity of steel delivered was to be
measured. It referred only to the “shipping weight”.
Generally, when a commercial contract speaks of
the weight of merchandise to be delivered, it means the weight determined by
weighing the object on scales that have been verified in accord-
[Page 666]
ance with the Weights and Measures Act. (R.S.C.c. W-7).
Therefore, even in the case of merchandise worth only a few dollars per ton,
such as sand or crushed rock, the seller always provides the buyer with a
certificate of weight for each delivery. In this case, however, Davie had no
scales to weigh the large pieces that it shipped by water from Lauzon to Baie
Comeau. Under such conditions, Davie assumed that it could determine the weight
of the merchandise shipped by the method known as draught displacement. It
seems clear to me that, since Davie was the plaintiff in the action, it had the
onus of proving that this was a normal method under such circumstances. This it
did not do. It adopted the mistaken attitude that such were the provisions of
the contract and the trial judge erroneously accepted this submission.
On appeal the error was unanimously
acknowledged, but the majority, as we have seen, still adopted the conclusion
of the trial judge. Essentially the reasoning of Rinfret J.A. on the point is
as follows:
[TRANSLATION] Pieces of large dimensions
were involved, which it proved impossible to weigh after assembly, and which
had to be transported by boat: this was obviously the most practical and
economical means of transport for both the shipper Davie and the consignee at
Baie Comeau, since both had excellent harbour facilities. Furthermore, there
was nothing in the contract to exclude water transport.
Under such circumstances, it seemed simpler
and more practical to weigh the steel shipments using the method known as
draught displacement.
I find no fault with the explanation given
by the trial judge:
(passage following the italicized part of
the second quotation above).
In its simplest form, the method involved
measuring the weight of the cargo using the difference between the weight of
the boat when empty and its weight once loaded.
On the question of the validity of the
draught displacement method, defendant-appellant called four witnesses, Messrs
Kuscher, Armstrong, Simard and Perry.
Some dismissed it out of hand as completely
ineffective; others, less adamant, admitted that under certain conditions, as
for example in the case of relatively
[Page 667]
inexpensive bulk freight, it could be used
in weighing within close to one per cent of the exact weight.
Like the trial judge, I am surprised that a
distinction was made between freight having a greater or less value; if the
weight is accurate within one per cent in one case why would it be different in
the other? The financial value is not a consideration here.
With respect, such reasoning seems faulty to me.
The trial judge dismissed the question of value, because he believed that the
contract stipulated the draught displacement method. However, once it is
admitted that the contract did not stipulate this, then it becomes clear that
the value of the merchandise is an important factor in determining whether a
particular method of measurement is accurate enough to be acceptable. Davie
made no attempt to prove that the draught displacement method was accepted
business practice in determining the weight of structural steel.
The witness who stated that the draught
displacement method is sometimes stipulated for bulk merchandise was Captain
Kuscher, who has considerable expertise in the field. He produced the form
which he uses to determine with acceptable accuracy the weight of bulk freight
by the draught displacement method. This form completely fills a legal-size
page and requires another sheet for stores and ballast. When he was shown the
exhibits that Davie purportedly used to determine the weight of the steel
delivered to Cargill, he stated categorically that, under such conditions, it
would be totally impossible to reach an acceptable degree of accuracy. In his
opinion, the margin of error for certain cargoes was greater than the weight
calculated for contract No. 7.
The witness Armstrong gave the following
answers:
Q. Now, wouldn’t shipping draughts be
another way of determining the shipping weight of steel?
A. To my mind, it would be quite impossible
to arrive at even a vaguely accurate weight. There are so many variables.
[Page 668]
Q. In your long experience did you have
occasion to meet cases where the weight of steel was determined by the draught
of a ship?
A. No.
The witness Simard saw the last steel cargo for
contract No. 7 shipped by Davie to Baie Comeau. He said he had never used the
draught displacement method, and added that at the time of the last shipment,
there were no marks on the ship that could have been used for this purpose
because it was navigating through ice. The bill of lading shows 42.6 tons,
while the tabulation used as the basis of the claim shows 69 tons.
Finally, the witness Perry stated:
…for billing it is unthinkable frankly for
structural steel. I can’t imagine using the draught of a ship except for a full
bulk cargo of a basically cheap material.
It must therefore be said that there is
absolutely no evidence that the draught displacement method is commercially
acceptable for establishing the weight of structural steel shipped by water.
With respect, I find a clear error in the statement that, since some witnesses
admit that the method is sometimes used for inexpensive merchandise, it must be
considered acceptable for expensive merchandise. The witnesses are unanimous in
saying exactly the opposite.
Moreover, it appears to me that the contract
implicitly excluded any use of the draught displacement method when it
stipulated not just one price for the additional quantity of steel, but three
different prices, depending on whether plate steel, structural steel or other
ironwork was involved. Through the stipulation of three different prices it was
obviously intended that the additional price be determined according to the
additional weight for each of the three categories. In the draught displacement
method, no such distinctions are possible: it provides a total figure for the
weight of the cargo. Because this method was used, it was impossible to make the
calculation in the manner provided in the contract and an average had to be
taken. In this regard, Rinfret J.A. said:
[Page 669]
[TRANSLATION] Appellant objects to the rate
charged being an average rate of $258.18 per additional ton and submits that the
lowest rate of $237.00 should be adopted.
I see no merit in this submission: the
figure of $258.18 appears to be the result of a calculation based on the
proportion of each type of steel transported: “stepped siding, 34%; loose
structural steel, 17% and arch pipes, 49% of the total weight”.
With respect, this appears illogical. How were
the proportions of types of steel transported determined if not by calculating
the weight from the quantities and dimensions, as was done, moreover, for the
steel used in contracts Nos. 6 and 12. In actual fact, Davie did not make up
its invoice according to the draught displacement method. It only resorted to
that method in order to establish the total weight. To determine the price in
terms of the various categories stipulated in the contract, it was obliged to
use another method.
Furthermore, the greater part of the steel
pieces supplied in accordance with contracts Nos. 6 and 12 was shipped by water
in loads which also contained pieces pertaining to contract No. 7. Since the
draught displacement method only gives a total weight, it was necessary to
substract the weight of the pieces pertaining to the other contracts in order
to arrive at a figure for those pertaining to contract No. 7. The weight of
these other pieces was established using the stipulated method, namely by
multiplying the volume by the density of the steel. The use of this procedure
meant that, in actual fact, the weight of the whole was determined by the
draught displacement method. It is true that invoices for two contracts were
established according to the calculation based on the volume of the pieces, but
because the rest was charged to contract No. 7, in the end the amount claimed
for everything delivered by water was based on the weight as established by the
draught displacement method.
It should be emphasized that the bills of lading
for shipments by water only give a total figure for
[Page 670]
the steel pieces. The attached lists do not
indicate which contract they refer to. This may possibly be deduced from the
number assigned to the pieces, but there is nothing to indicate this or to
establish the connection. In any event, the position taken by Cargill at the
trial was that the bills of lading were not the basis of its claim. Cargill’s
sole basis for everything shipped by water was a document entitled “Tabulated
shipments to Baie Comeau up to date as of 31st December 1959”, prepared by one
J.R. Josslyn, a naval architect in its employ at the time. This document
indicates in tons the quantity of steel that was shipped on each voyage and
billed to each of the three contracts. It does not show how this result was
reached. At the trial, Davie stated that it was unable to supply the data used
or the calculations made in order to arrive at these figures. These
calculations are obviously complex. One only has to have to look at the
document produced by the witness Kuscher to realize this. Notwithstanding this
fact, the trial judge and the majority on appeal accepted the evidence based on
this document.
In Royal Victoria Hospital and Estate of the
late Ewen Cameron v. Mary Morrow, this
Court held that, as a rule, hearsay evidence is inadmissible in Quebec. The
document in question, as well as those based on data it contained, could
accordingly only be admitted under an exception. As Hyde J.A. pointed out, the
case at bar is not of the same kind as the one dealt with by this Court in Ares
v. Venner, a
British Columbia case. In the latter, the documents held admissible were
records in which facts observed by an employee in the performance of his duties
were recorded immediately. Here, however, we have no document in which the
facts noted by Josslyn—namely, the draught at the beginning and end of each
loading and other data necessary for calculating the weight of the steel when
loaded—were recorded. By the same token, the calculations made in order to
arrive at the result recorded in the document
[Page 671]
produced were not filed. We are therefore
dealing here, not with facts, but with conclusions. In short, if the document
prepared by Josslyn is admitted, it means that Davie’s employee has settled the
point at issue by calculating the quantity of steel shipped, without it being
possible to verify such quantity.
In any event, I do not think that the contract
in the case at bar allowed Davie to claim a weight established by the draught
displacement method. It is not enough that a representative of the firm of
consulting engineers responsible for supervising the performance of the
contract on Cargill’s behalf did not object to the draught displacement method
when it was first mentioned to him. The fact is that this firm never agreed to
approve invoices made up on that basis. It has been said that they were given
ample documentation, but it does not appear that they were ever given the
detailed data and calculations from which Josslyn made up the claim. The Court
was told that there were a great many documents, and that a large commercial
undertaking cannot keep everything for an indefinite period. In my view, this
argument cannot be sustained. In the case at bar, it was well known that
litigation would ensue, since the consulting engineers refused to approve the
invoice when it was presented to them, and persisted in their refusal.
This case cannot be viewed as a situation where,
owing to the sudden death of one of its employees, a business firm would be
totally unable to prove a claim. The structure erected for Cargill is still
there, as are the plans and shop drawings. There was nothing to prevent Davie
from establishing the weight by measuring the pieces, which is the usual method
when dealing with structural steel. Davie did not do this. Even if Josslyn’s
documents were complete, the question would arise whether they would have been
admissible as evidence, in view of the existence of this other simple,
practical method. In such case, the question would require further
consideration. Since the draught displacement method was not stipulated for the
calculation at the weight of steel delivered, and since Josslyn’s conclusions
were not admissible as evidence, there
[Page 672]
is no other evidence as to weight than that
presented by the witness Armstrong on Cargill’s behalf. The latter did not
follow the C.I.S.C. method exactly. Owing to the shipping weight stipulation,
he believed that he should deduct the trimmings in calculating the volume of
the pieces in order to come as close as possible to the weight that would have
been indicated by scales.
Under such circumstances, I believe that Hyde
J.A. was right in maintaining that the weight calculated in this manner should
be taken. However, he erred in holding that the price must be set at the lowest
figure provided by the agreement, namely $237 per ton. Once the procedure for
determining the weight by measuring the pieces is held to be acceptable, the
average of $258.18 established by Davie on that same basis, should be accepted.
In fact, this average is not an arithmetical average but a weighted average
established according to the proportion of each category of steel in the structure
as a whole. On the other hand, the additional weight as established by
Car-gill’s expert is not 42 tons, but 42,209 lbs. or 21.1 tons, or, at $258.18
per ton, $5,447.60. I must accordingly conclude that the sum of $130,754.61
awarded to Davie for additional steel weight on contract No. 7 should be
reduced to the above amount; this means a reduction of $125,307.
Everything considered, it does not appear to me
that costs should be awarded on appeal or in this Court.
For these reasons, I am of the opinion that the
appeal should be allowed, the judgment of the Court of Appeal set aside and the
judgment of the Superior Court varied by reducing the amount of the judgment by
$125,307, without costs in this Court or in the Court of Appeal.
Appeal allowed.
Solicitors for the appellant: Ahern, de
Brabant, Nuss & Drymer, Montreal and P. Casgrain, Montreal.
Solicitors for the respondent: Langlois,
Drouin & Laflamme, Quebec, and H. Hansard, Montreal.