Supreme Court of Canada
Vermont Construction Inc. v. Beatson, [1977] 1 S.C.R.
758
Date: 1975-12-04
Vermont
Construction Inc. Appellant;
and
Gilbert R. Beatson Respondent.
1975: June 23; 1975: December 4.
Present: Laskin C.J. and Martland, Judson,
Pigeon and de Grandpré JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
QUEBEC
Contracts—Construction contract—Delay in
performing the work resulting from an error in the plans—Liability of the
architect—Contractual or delictual liability—Fault of the engineer consulted by
the architect—Civil Code, arts. 1053, 1688 and 1689.
Appellant, a contractor, built a recreational
centre under a lump sum contract for the City of Pointe-Claire which had
retained the services of respondent, an architect, to draw up the plans and
supervise the work. When the latter’s representative at the site realized that
the framing was not strong enough he advised respondent, who asked the
engineering firm which had calculated the stresses to ensure that they were
accurate. When the firm found no error, respondent asked to have the
calculations checked by a more experienced man. It was then found that an error
had been made and that in order to obtain walls strong enough, the framing
would have to be substantially reinforced. Respondent changed the plans and
instructed the contractor to make the necessary changes, as stipulated in the
contract. The contractor subsequently submitted its claim for the expenses
caused by the change, amounting to $15,521.80. Respondent recommended the City
of Pointe-Claire to pay the
contractor the sum of $4,159.32 for extra material and labour, and advised it
that it did not have to pay appellant’s claim for the delay resulting from
changes to the plans. Appellant contended that respondent was at fault and
claimed from him the amount unpaid by the City. The Superior Court and the
majority of the Court of Appeal dismissed the claim. Hence the appeal to this
Court.
Held (de
Grandpré J. dissenting): The appeal should be dismissed.
Per Laskin
C.J. and Martland, Judson and Pigeon JJ.: In the absence of any contractual
link between the contractor and the architect, appellant can rely only on
art. 1053 C.C. As the City compensated appellant for the cost of
necessary additional work to complete the
[Page 759]
construction, the remedy for loss caused by
the delay in the work can be based only on delictual or quasi-delictual
liability.
A contractor’s situation cannot be likened to
that of a consumer having purchased a manufactured product. While the architect
is not a party to the business contract, he is involved in it. Faults between
the contractor and the architect, such as that imputed to the latter, form part
of the performance of the contract and cannot be considered offences, unless
they are gross negligence.
Appellant seeks to recover from the agent
(the respondent architect), responsible for the damages suffered, the part of
the loss which it agreed it would not be entitled to recover from the person
with whom it made the contract. As a rule, contracts have effect only between the
parties thereto, but here the acts of the respondent on which appellant’s claim
is based are contemplated in the provisions of the contract and their
consequences are stipulated.
Consideration should also be given to the
fact that although, under the provisions of the contract or under arts. 1688
and 1689, respondent could not plead as a ground of defence that it was the
engineers he consulted who committed the wrongful act, the situation is not the
same in the case of delictual liability. In this case, the rule is that one is
liable only for his own wrongful acts save in certain exceptional cases, such
as committing a wrongful act for one’s servants or employees, and the engineers
consulted by respondent definitely cannot be considered as such in this case.
Per de
Grandpré J., dissenting: The Quebec courts have based themselves
primarily on common law authorities in refusing to recognize the
existence of a delictual remedy for appellant against respondent. There is
always a danger in using authorities from English law in a civil law matter. In
the case at bar, the parties cited no Quebec authority dealing specifically with this point and none is known.
One can therefore feel free to refer to French authorities who have recognized
the right of a third party to sue the contractor and the architect. As this
right seems clearly established, there is no reason why it should not also
extend to the contractor if the architect’s mistake caused him a harmful delay,
since there is no contractual link between the contractor and the architect.
The agreement between the City and appellant
does not change the situation between the contractor and the architect, who
remains liable for his fault. The stipulation in favour of the contractor
cannot benefit the
[Page 760]
architect, who is not a party to the
contract. Nor does anything in this agreement provide that the contractor must
completely abandon all remedy against the architect at fault. As such a waiver
is clearly an exception to the general rule of liability, it should be
expressed in clear terms, which is not the case.
The claim that the error was not a personal
error on the part of the architect cannot be accepted since the contract
clearly states that he is the only person responsible for the plans and
specifications. Further, this argument would apply to only a part of the
damages since, once the error was noted, respondent should have corrected the
plans without delay, but did not do so. Most of the delay can therefore be
attributed to the architect personally.
[Ross v. Dunstall (1921), 62 S.C.R. 393; J.G. Fitzpatrick Ltd. v. Brett et al., [1969]
C.S. 144, distinguished; Bank of Montreal v. Boston Ins. Co., [1963]
Que. Q.B. 487, aff’d [1964] S.C.R. v. Dominion Electric Protection
Co. Ltd. v. Alliance Ass’ce Co. Ltd. et al., [1967] Que. Q.B. 767, aff’d
[1970] S.C.R. 168; Felizat c. Henry, S. 1879.1.374; Donoghue v.
Stevenson, [1932] A.C. 562; Beaucamp-Wartel c. Léonardi de Galéa et
Tournier, Gaz. Pal. 1929.1.150; Nova Scotia Construction v. Quebec
Streams Commission, [1933] S.C.R. 220, [1933] 2 D.L.R. 593; Prévert
c. Lavigne, [1969] J.C.P. (Semaine juridique), No. 15937; Bilodeau
v. A. Bergeron & Fils Ltée and Dominion Ready Mix Inc., [1975] 2 S.C.R.
345; N.Z. Shipping v. Satterthwaite Ltd., [1975] A.C. 154; The London
& Lancashire Guarantee & Accident Co. of Canada v. La Compagnie F.X.
Drolet, [1944] S.C.R. 82, referred to]
APPEAL from a decision of the Court of Appeal
for Quebec, affirming a judgment of the Superior Court dismissing appellant’s
action. Appeal dismissed, de Grandpré J. dissenting.
Louis Vaillancourt, Q.C., for the
appellant.
Alain Létourneau, for the respondent.
The judgment of Laskin C.J. and Martland, Judson
and Pigeon JJ. was delivered by
PIGEON J.—The appeal is against a decision of
the Court of Appeal for Quebec
affirming the judgment of the Superior Court dismissing appellant’s action. The
reasons for the majority were stated by Rinfret and Montgomery JJ.A. Deschênes
J.A. dissented.
[Page 761]
Under a lump sum contract dated February 15,
1965, appellant undertook to build for the City of Pointe-Claire a recreational
centre for which respondent was the architect. One of the buildings was to
house a swimming pool. This building would have no side walls; a large A‑frame
roof was to rest directly on the foundation walls just above ground level. The
two end walls were to be curtain walls made of plywood sheathing nailed to both
sides of light studs. Due to the size of walls, the studs were to be spliced.
With the consent of the Montreal architect who supervised the work for the respondent, who lived in Calgary, appellant used braces instead of
splices believing stronger walls would be obtained in this way. However, it was
soon apparent that with studs of the specified size, the walls swayed
dangerously in the slightest wind. The Montreal architect immediately advised respondent that the curtain walls
would not be strong enough with studs as specified.
Stresses had been calculated for the respondent
by an engineering firm in Calgary. He told them what his representative had reported, but the
engineers replied that their calculations were accurate and that the walls
would be strong enough with dimensions as shown on the plans. Respondent
therefore ordered the construction completed without change.
However, at the site it was obvious that the
framing was not strong enough. The Montreal architect told respondent of this and the latter went back to the
engineers and insisted on having the calculations checked by a more experienced
man. It was then found that an error had been made and that in order to obtain
walls strong enough, the framing would have to be substantially reinforced.
Respondent thereupon prepared a change order involving the addition of 2 ins.
by 8 ins. and 2 ins. by 6 ins. studs with heavier plywood nailed and glued.
This was forwarded to appellant by the Montreal architect representing respondent, together with a letter dated June 21, 1965 instruct-
[Page 762]
ing it to make the changes. The letter concluded
as follows:
We have forwarded to you under separate
cover 3 copies of Drawing # 3154 SK-1 dated June 15, 1965. As discussed with
you on June 15 at the site we wish to have the extra done on a cost and
percentage basis as per Article 26D of the Agreement.
According to appellant’s estimate, the work
described in its contract with the City of Pointe‑Claire was to be completed on June 20, 1965. In fact, it was not
completed until October 15. However, appellant did not submit its claim to the
Montreal architect for the expenses caused by the change described in the
letter of June 21, 1965, until January 28, 1966. The total amount was
$15,521.80 and included $9,760 for the resulting delay. In a letter to the City
dated February 25, 1966, the architect advised it that the contractor was
entitled to $4,159.32 for the extra material and labour. Appellant protested
this decision but finally, on May 20, 1966, it took this amount under reserve,
signing the document prepared by the municipal officials in the following form:
CITY OF
POINTE-CLAIRE
ORDER FOR EXTRA WORK
|
Job
No. 600
|
Date: May 17,
1966
|
|
By-law
No. 1009
|
Change Order
No.: 46
|
TO:
Vermont Construction Inc.
You are hereby instructed to carry out the
following work:
To strengthen the end of the pool building
in accordance with the architect’s instructions and revised drawing.
Letter of quotation dated Feb. 1, 1966 from
Vermont Construction Inc.
For which payment will be made as follows:
|
Adjusted amount
|
$ 15,383.32
|
|
Less $9,760.00 plus 15% charge for delay in getting decision of
the changes
|
11,224.00
|
|
Amount to be paid
|
$ 4,159.32
|
[Page 763]
See
letter Chadwick, Pope & Edge,
Architects, dated Feb. 25/66
|
Authorized by:
|
J.P. Coombes
|
|
|
City Engineer
|
|
|
Date: May 18/66
|
Without prejudice to the balance of our
quotation revised to $15,383.32 of Feb. 1, 1966
Change order received and agreed to by:
P. Beetz
for
contractor
Date: 20-5-66
To complete this summary of the facts, I shall
quote the following provisions of the contract:
|
ARTICLE 25.
|
Changes in the
Work.
|
The Owner, or the Architect, without
invalidating the contract, may make changes by altering, adding to, or
deducting from the work, the contract sum being adjusted accordingly. All such
work shall be executed under the conditions of the original contract except
that any claim for extension or reduction of time caused thereby shall be
adjusted at the time of ordering such change. Except as provided in
Article 18, no change shall be made unless in pursuance of a written order
from the Architect and no claim for an addition to or deduction from the
contract sum shall be valid unless so ordered and at the same time valued or
agreed to be valued as provided in Article 26.
|
ARTICLE 26.
|
Valuation of
Changes.
|
The value of any change shall be determined
in one or more of the following ways:
(a) By estimate and acceptance in a lump
sum.
(b) By unit prices agreed upon.
(c) By cost and percentage or by cost and a
fixed fee.
(d) If none of the above methods be agreed
upon, such value shall be determined in the manner set out in Article 44
hereof…
If the Contractor is delayed in the
completion of the work by any act or neglect of the Owner, Architect or any
Other Contractor or any employee of any one of them or by changes ordered in
the work, then the time of completion shall be extended for such reasonable
time as the Architect may decide…
[Page 764]
It should now be added that respondent, heard as
a witness, admitted that in the initial plan, the building’s curtain walls were
not strong enough, that the engineers had made an error in their calculations,
and that he could have detected it if he had checked their work. The reason he
did not check it is that the accepted practice is to rely on the engineers
consulted, whom he considered more competent than himself in the area of stress
calculations.
After stating the facts, the trial judge said:
[TRANSLATION] In performing his duties as
an architect, defendant was acting only as the mandatory of the City of
Pointe-Claire, and there was no contractual relationship between him and the
plaintiff. In other words, any claim plaintiff may make as a result of damages
sustained in the course of performing its contract must be made against the
City of Pointe-Claire, the contracting party, and not against its mandatory.
Moreover, the evidence shows that all the
decisions and actions taken were carried out in accordance with the terms of
the contract concluded between the City of Pointe-Claire and the plaintiff
through change orders and orders for extra work.
In addition, the contract concluded between
the owner and the architect confers no rights upon plaintiff.
Plaintiff claims that it has a delictual
remedy against defendant.
Having examined the arguments submitted by
counsel for the parties on this delictual remedy, and having studied the case
law cited below, the Court finds that in the case at bar plaintiff has no
delictual remedy against defendant.
On appeal, counsel for the appellant criticized
the trial judge for citing only judgments based on the common law in the case
on which he relied. Rinfret and Montgomery JJ.A. did not consider this an error
in the case at bar, because they saw no basic difference between the civil law
and the common law on the point. Deschênes J.A., dissenting, dealt with the
case at the greatest length. After citing several cases on the danger of
applying precedents based on a different legal system, he summarized two recent
cases in which, relying
[Page 765]
on Ross v. Dunstall, the theoretical possibility of the
co-existence of a delictual and a contractual remedy was recognized: Bank of
Montreal v. Boston Insurance Company,
Dominion Electric Protection Company Limited v. Alliance Assurance Company
Limited et al. He then
considered the case in the light of arts. 1688 and 1689 C.C., which read
as follows:
Art. 1688. If a building perish in whole or
in part within five years, from a defect in construction, or even from the
unfavourable nature of the ground, the architect superintending the work, and
the builder are jointly and severally liable for the loss.
Art. 1689. If, in the case stated in the
last preceding article, the architect does not superintend the work, he is
liable for the loss only which is occasioned by defect or error in the plan
furnished by him.
On this point, Deschênes J.A. concluded as
follows:
[TRANSLATION] It is therefore clear in my
view, that despite the absence of any strictly contractual link between the
contractor and the architect, the contractor has an extra‑contractual
remedy against the architect if the latter’s fault in the performance of his
contractual obligation to the owner meant that the contractor had to undertake
additional work, in order to complete the job in accordance with its own
contract with the owner: arts. 1688, 1118 and 1120 C.C.
However, this remedy is restricted to the
amount of the loss, as indicated in art. 1688, that is, generally
speaking, to the cost of rebuilding or of doing the additional work required in
order to complete the project in accordance with accepted standards. This was
not the object of the action brought by Vermont.
On the contrary, it was required to carry
out additional corrective work and claimed payment for this from the City,
which, far from holding Vermont strictly to its undertaking, complied with its
request and reimbursed it for the cost of labour and material required for the
extra work.
Thus the effect of art. 1688 between
Beatson and Vermont was exhausted…
He then went on to consider the remedy based on
the general principles of delictual or quasi-
[Page 766]
delictual liability, art. 1053 C.C. He
said, inter alia:
[TRANSLATION] One must also be realistic
and must not ignore the true facts. The contractor was expected to build in
accordance with the plans of the architect hired by the City and it was
justified in relying on the competence of the architect. Moreover, the latter
was not working on a merely theoretical project. He knew that the plans he was
required to prepare were to be used for a specific purpose and that a
contractor would be responsible for the transition from a conception to an
actual structure.
It is thus a sophism to consider
exclusively the contractual link between Beatson and the City. Beatson supplied
the plans to a contractor so that, after examination they would be the basis of
a proposal, and then be used faithfully in performing the work. To fail to
recognize Beatson’s resulting obligation towards the contractor at common law
is to deny obvious facts and to refuse to recognize a relationship between two
persons that was essential to the realization of the project.
Thus, if in addition to the increased cost
of the work, the architect’s negligence resulted in a delay in the work which
caused the contractor to sustain damages for which it cannot possibly hold the
owner liable, I see no valid reason to prevent the contractor from asserting
this specific claim against the architect.
The law required Beatson to provide Vermont
with plans that were in accordance with professional standards; it also allows
Vermont to hold Beatson liable for failing to fulfill his legal duty. This is a
case of “fault… by …want of skill” within the meaning of art. 1053 C.C.
After referring again to Ross v. Dunstall, Deschênes
J.A. concluded that appellant’s claim was well founded in law, but, in view of
the conclusion of the majority, he did not go on to consider whether the
damages claimed were proven.
On appeal and in this Court, appellant referred
to the judgment of Mayrand J. in J.G. Fitzpatrick Ltd. v. Brett. There are many analogies between
that case and the case at bar. Plaintiff was also a contractor and during the
construction of a building had to do extra work in order to make a part of
[Page 767]
the structure stronger. As in the case at bar,
this was the result of an error in calculations made by the engineers whom the
architect had consulted. Since the owner refused to make any additional
payment, an action was brought against it and against the architect and the
engineers. The contractor withdrew his action against the owner, and proceeded
only against the engineers. The contractor won its case. The Court held that it
was subrogated to the architect’s remedy against the engineers and expressed
the view that the action was justified by the combined force of arts. 1053 and
1688 C.C.
I do not think that the case is of any help to
the appellant. As Deschênes J.A. pointed out, it has received from the City
everything it would be entitled to under arts. 1688 and 1689. Mayrand J. does
not appear to have awarded more than that, and nothing in his judgment
indicates that he relied on art. 1053 to support a claim for damages not
contemplated in those articles. Assuming they apply not only to the perishing
of the building after completion of the work, but also to additional work
required during construction to avoid it, I do not see how this could support
appellant’s claim. On the contrary, where these articles do apply, should it
not be said that the remedy is restricted to what they provide for? However, I
doubt that they apply in such a case. Is this not rather a case concerning
exclusively a lump sum contractor’s obligation to deliver the building whereby
“the loss of the thing, in any manner whatsoever, before delivery, falls upon
himself…” (art. 1684 C.C.).
In the case at bar, the damage for which
appellant is claiming compensation consists essentially in that, as a result of
a defect in the plans supplied by respondent, the performance of the
construction contract proved less profitable (or more disadvantageous) because
the duration of the work was thereby increased. The appellant did receive the
compensation specified in the contract for the change, but it maintains that
this is no compensation for the loss caused by the delay in the work.
[Page 768]
The fault imputed to the architect is therefore
said to consist in having supplied to the City defective plans which necessitated
a change during construction, when it became obvious that otherwise the
building would not withstand the wind.
Appellant would have this situation likened to
the marketing of a product with a concealed danger, which was held to be a
wrongful act in Ross v. Dunstall. It was no doubt recognized in that
case that, independently of any question of contractual liability, a person who
markets a dangerous product without giving sufficient warning of a concealed
danger may incur delictual liability. In so holding, this Court relied in
particular on a decision of the Cour de Cassation, Félizat c. Henry. It also expressed the view that the
conclusion would have been the same at common law more than ten years before
this view was adopted by the House of Lords in Donoghue v. Stevensen.
However, in the case at bar, this Court does not
have to consider an architect’s liability to a person injured in the collapse
of a badly constructed building. What we do have to consider are the legal
relations between the contractor and the architect of a building. Can the fact
that the architect supplied plans that did not provide for adequate framing be
regarded as a fault giving rise to liability? Even though the architect is not
a party to the building contract, he is not a stranger to it. He is an agent of
the owner, and his duties are defined in the contract. In addition, arts. 1688
and 1689 C.C. make the contractor and the architect jointly and
severally liable for defective construction. Towards the owner, the contractor
is the guarantor of defects in the plans as well as in his own work, saving his
remedy against the architect, just as the latter is the guarantor of defects in
the work, saving his remedy against the contractor: Beaucamps-Wartel
c. Léonardi de Galéa et Tournier.
[Page 769]
Thus a contractor’s situation cannot be likened
to that of a consumer having purchased a manufactured product. By law, a
contractor assumes responsibility for defects in the plan. While he does have a
remedy against the architect, as noted, this remedy is limited in scope and
does not cover the appellant’s claim in this case. By the contract it agreed
that it would have no claim against the owner. How then could it be able to
make a claim against the architect? If some work is badly done and, as a result
the architect supervising the construction for a set fee or percentage, is
required to spend more time than usual performing his supervisory duties
because of the work that has to be redone, can he claim additional payment from
the contractor as damages caused by the fault of the latter’s workmen? In my
view, faults of this kind, as between the contractor and the architect, form
part of the performance of the contract and cannot be considered offences,
unless perhaps they are what is called in France “fautes caractérisées” that
is, gross negligence. In Nova Scotia Construction v. Quebec Streams
Commission, at
pp. 601-2, Cannon J. cited English legal theory and case law to the effect that
the architect does not guarantee to the contractor the accuracy of his
calculations. It is true that the action was against the owner, not the
engineer who had prepared the plans for the dam. However, in holding that, with
respect to the additional work required which was not provided for in the
initial plans, the contractor could recover only the contractual compensation
rather than all the expenses incurred, the Court undoubtedly applied the
contractual rule.
The Cour de Cassation recently admitted
the application of the rules of delictual liability to an action against a
contractor and an architect for a defect in construction (using timber that had
not been treated with the specific insecticide). It affirmed the judgment
allowing the action in warranty by the contractor against the architect on the
basis of inadequate supervision: Prévert c. Lavigne. This conclusion is in direct
conflict with this Court’s unanimous judgment in Bilodeau v.
[Page 770]
Bergeron et Fils Ltée and Dominion Ready Mix
Inc., in which it was held that a supplier of defective materials
had no remedy against the inspector who had approved them, although the latter
was liable for his negligence to the contractor who had retained his services.
In a certain sense, the case at bar involves a
restricted liability clause, as in the Bank of Montreal and Dominion
Electric Protection cases. Appellant seeks to recover from the agent
responsible for the damages suffered, the part of the loss which it agreed that
it would not be entitled to recover from the person with whom it made the
contract. It is no doubt true that, as a rule, contracts have effect only
between the parties thereto. But here, the acts of the respondent on which
appellant’s claim is based are contemplated in the provisions of the contract
and their consequences are stipulated. Even though such acts may fail to meet
professional standards, they are not unlawful or fraudulent and, in my opinion,
they cannot be dealt with as if done apart from any contract, because the
contract provides for their possibility and settles their consequences
beforehand. At common law, where a stipulation for the benefit of third parties
is not admitted as it is in civil law, the effectiveness of a clause in a bill
of lading, limiting the liability of stevedores, has recently been recognized, N.Z.
Shipping v. Satterthwaite Ltd. A
fortiori must this be true in civil law.
Finally, consideration should also, I think, be
given to the fact that it was not the respondent, but the engineers whom he
consulted, who made the error that caused the damage. It is true that this
cannot be a ground of defence under the provisions of the contract or under
arts. 1688 and 1689. However, in the case at bar the claim is not based on
those sources but rather on the general principles of delictual or
quasi-delictual liability, where it is an established rule that a party
“charged with negligence can clear his feet, if he shows that he has acted in
accord with general and approved practice”: London & Lancashire
Guarantee & Accident Co. of Canada v. La Compagnie
[Page 771]
F.X. Drolet. It is the
practice for architects to rely on engineers to make stress calculations for
the structures for which they prepare plans. The engineers consulted by the
respondent were apparently competent. In my view, it has not been shown that he
committed a wrongful act by trusting them and not checking their calculations,
even though he could have done so. This would not clear him of the liability
contemplated in arts. 1688 and 1689, which is imposed by law and does not allow
of such an exception, but with respect to delictual or quasi-delictual
responsibility, the situation is not the same. The rule is that one is liable
only for his own wrongful acts save in certain exceptional cases. In this case,
the engineers consulted by the respondent definitely cannot be considered as
his employees or servants.
On the whole I would dismiss the appeal with
costs.
DE GRANDPRE J. (dissenting)—The principal
question raised by this appeal is the following. When the plans and
specifications of an architect are erroneous and such an error delays
performance of the work, can the contractor, after receiving payment from the
owner for the additional work required to make the necessary corrections, take
legal action under art. 1053 C.C. against the architect at fault
and claim the damages caused by the delay?
The existence of the initial error, which was
corrected only with a great deal of effort, emerges from the findings of fact
contained in the judgment of the Superior Court and accepted by the Court of
Appeal:
[TRANSLATION] The structure that was to
house the pool was covered with a self‑supporting A-shaped roof, with its
base supported on the ground on either side by a plate resting on a concrete
wall.
Two walls were to be put up at each end of
the structure, to close the structure and not to support the roof. According to
the plans and specifications these walls were to be composed of studs
reinforced by splices, with plywood panelling to be attached on both sides of
the studs.
[Page 772]
Plaintiff began to put up the wall on May
11, 1965, and noticed at the start that the structure, as shown in the plans
and specifications, would not be sturdy enough. In fact, after the plans and
specifications had been followed up to a height of sixteen feet, it was found
that the wall swayed.
In accordance with the plans and
specifications, the vertical studs were attached to one another by splices, as
shown in sketch No 27A6/A6, circled on the drawing produced as Exhibit P-18 D,
and in Exhibit P-10.
After consulting with Mr. Whiteside,
representing the defendant, plaintiff decided to change the arrangement of the
studs and adopt the girt method (horizontal members between the studs) instead
of the method called for in the plans and specifications.
On May 25, 1965 Mr. R.W. Chadwick stopped
construction of the walls at the end of the structure, and contacted defendant
on that day or the following day to inform him that, in his opinion, the plans
were faulty, and that the walls as erected by plaintiff would not be strong
enough and solid enough to withstand wind pressure—no more so than if they had
been erected according to the plans and specifications mentioned above.
The problem raised by Mr. R.W.
Chadwick was not related to the manner in which the studs had been arranged,
but rather to the inadequacy of the information supplied by the architect in
the plans and specifications relating to the “stressed skin” process required
in clause XII-27 of specification P-15, that is, the arrangement and fastening
of the plywood panels that form the structural skin of the walls to resist the
force of the wind.
Mr. Chadwick’s opinion is shared by
Mr. Jean Damphousse, an architect heard as an expert witness, and by the
engineers to whom defendant had initially referred to have plans and
specifications prepared for the erection and construction of these walls, and
lastly by the defendant himself.
The above-mentioned engineers, after making
new calculations, proposed a new, revised plan and specifications (P-2), which
was finally submitted to plaintiff on June 22, 1965.
Defendant not only admitted that the
original plans and specifications for the erection and construction of the said
walls were incomplete and incorrect, but even stated that if he had examined
and studied them, he would have been able to realize whether or not the
information contained in them was adequate.
[Page 773]
Notwithstanding this error, the Quebec courts,
with Deschênes J. dissenting, refused to recognize the existence of a delictual
remedy for plaintiff-appellant against the architect‑respondent. In so
doing they based themselves, entirely in the case of the Superior Court and
partially in the case of the Court of Appeal, on common law authorities, and
held, citing Lord Denning’s preface to J.P. Eddy’s Professional Negligence, that
the architect’s liability “rests in contract and not in tort; and it avails
only the party to the contract and no one else”.
I will not dwell on the assertion that there is
no fundamental difference between the two legal systems. The sequence of these
reasons attempts to establish that while common law is well expressed in the
authorities cited by the Quebec courts, there are major differences between the
two. It is nonetheless pertinent to repeat here the caution found in the
reasons of Deschênes J. regarding the danger of using authorities from English
law in a civil law matter.
Does the common law really say what the Superior
Court and Court of Appeal make it say? It is not necessary for me to decide
this. I may be permitted, however, to express a doubt based, inter alia, on
the decision of this Court in Canadian General Electric Company Limited v.
Pickford & Black Limited, at
p. 43, and on the decision of the House of Lords in Hedley Byrne &
Co., Ltd. v. Heller & Partners, Ltd.,
the latter decision lending weight to the dissenting opinion of Lord Denning in
Candler v. Crane Christmas & Co.
It is certainly permissible to ask: does not an architect, whose profession is
to draw up plans, have, in English law, the duty to prepare them correctly, not
only with respect to the owner but to all who, to his certain knowledge, will
of necessity be using them? This undoubtedly includes the contractor who is to
carry out the work.
[Page 774]
I now come to the heart of the question. What
does the civil law have to say, apart from any particular stipulation? The
parties have referred us to no authority dealing specifically with this point
and I know of none. I therefore feel free to refer to French authorities in the
following analysis.
There seems to me to be no doubt that in
undertaking to prepare the plans and specifications, the architect had a duty
to take reasonable care in his work. The owner was not the only beneficiary of
this duty. In carrying out his work, respondent should have seen appellant as a
person directly affected by his acts. Our case law contains numerous examples
of liability imposed on a defendant whose relation to the damage has its source
in a contract to which the victim was not a party.
The relevant principles were stated in Alliance
Assurance Company Limited v. Dominion Electric Protection Company Limited. At p. 173 it is stated:
The duty it (Dominion Electric Protection)
is blamed for not performing and by reason of which it is alleged to have
committed a fault involving liability is not one which falls on everybody; on
the contrary, it is solely a contractual obligation.
It is true that the existence of
contractual relations does in no way exclude the possibility of a delictual or
quasi-delictual obligation arising out of the same fact. However, it is
necessary for this that all the elements required to give rise to such
responsibility should be found. Obviously, a fault is the first of these
elements. For a fault to exist, it is essential, as appears from the wording of
Art. 1053 C.C., that there be either a positive damaging and non-justifiable
act or the omission to perform a duty towards the injured party.
And at p. 174:
Many cases were cited respecting the
responsibility of the manufacturer of a dangerous product towards persons who
did not contract with him. In such cases, the source of the responsibility is
the breach of the duty lying upon the manufacturer not to put such things on
the market and this duty is independent of his contractual obligation, as
vendor: Ross v. Dunstall (1921), 62
[Page 775]
S.C.R. 393. The same observation applies to
the owner of a leased building towards persons admitted to the premises by the
lessee. The responsibility for damages resulting from a defective condition
rests with him as owner and exists independently of his contractual obligations
as lessor. Examples could be multiplied and in every case where quasi-delictual
responsibility has been held to exist, it will be found that its basis is the
existence of a duty other than one deriving solely from a contractual
obligation.
The case of the manufacturer and the vendor is
well known and I will not dwell on it, except to cite two passages from the
leading case, Ross v. Dunstall. First,
Duff J. as he then was (at p. 396):
Is the appellant responsible? I can see no
reason for holding that such responsibility does not arise from the very terms
of Art. 1053 C.C. unless it can be successfully contended that the
responsibility in such circumstances is limited to that arising from the
contract of sale. I see no reason for such a limitation of the effect of the
article mentioned. I cannot understand why a delictual responsibility towards
those with whom the negligent manufacturer has no contractual relation may not
co-exist with contractual responsibility towards those with whom he has.
Then Anglin J., as he then was (at p. 399):
The failure of the appellant to take any
reasonable steps to insure that warning of the latent danger of the misplaced
bolt—whether it did or did not amount to a defect in design—should be given
purchasers in the ordinary course of the sporting rifles which he put on the
market in my opinion renders him liable to the plaintiffs in these actions. His
omission to do so was a failure to take a precaution which human prudence
should have dictated and which it was his duty to have taken and as such
constituted a fault which, when injury resulted from it to a person of a class
who the manufacturer must have contemplated should become users of the rifle,
gave rise to a cause of action against him.
In Modern Motor Sales Limited v. Masoud et
al.,
Taschereau J., as he then was, wrote (at p. 157):
[Page 776]
[TRANSLATION] The vendor of an object which
causes damage will be liable not only to the purchaser, but also to the users
of that object, even though there is no contractual relationship. The fault is
delictual…
See also Cohen v. Coca-Cola Limited. If the manufacturer or vendor are
responsible for the product that leaves their hands and causes damage to a
third party, it seems to me that the architect has an equivalent responsibility
for the product which he puts on the market, namely drawings and
specifications.
In the specific case of building contracts, the
French courts have recognized the right of a third party to sue the contractor
and the architect. This right has been recognized, inter alia, in the
case of tenants (Cass. civ. I, Oct. 24, 1967: Bull. civ. 1, No. 309,
p. 232) and in the case of a victim in the collapse of a balcony (Caen,
April 16, 1947: J.C.P. 47, II, ed. G., 3667).
For its part, French legal theory recognizes the
right of the third party to take legal action the contractor and the architect.
Thus Mazeaud’s Traité théorique et pratique de la responsabilité civile
délictuelle et contractuelle, 6th ed., vol. 1, at p. 178 states:
[TRANSLATION] 144-3. Action for delictual
liability brought by a third party and based on the contact.—Once it is
admitted that a contracting party cannot be held contractually liable toward a
third party, another question arises: can third parties bring a delictual
action against the contracting party when, to win their action, they are
compelled to rely on the contract? In so doing, are they not running counter to
the rule of res inter alias acta…?
The solution lies in a distinction. It is
permissible for third parties to take advantage of the existence and
non-performance of a contract to which they were not parties, provided they do
not thereby attempt to extend to their benefit an obligation that was made only
between the contracting parties. To take advantage of the fact that a person
has concluded a contract, and even that he has failed to perform it, is merely
to take advantage of a fact which exists as such before everyone. To claim to
be the beneficiary of a commitment made between the parties is to extend the
scope of the con-
[Page 777]
tract, to rely on the contract as a legal
instrument, a source of obligations, which is impossible.
It is also interesting to read what the same
author has to say at p. 58 of vol. 2, and in particular, at p. 121 of
vol. 2, where he deals with remedies between builders.
It therefore seems to me that the right of a
third party not involved in the design and construction of the building to
proceed against the architect, if an error in the plans has caused him damage,
is clearly established. Accordingly, why would this right not also extend to
the contractor if the architect’s mistake caused him a harmful delay? There is
no contract between the contractor and the architect and it seems to me that
one is “another”, in relation to the other, within the meaning of
art. 1053 of the Civil Code.
The Cour de Cassation has held on several
occasions that the architect and the contractor are third parties in their
personal relations. It is true that none of these cases corresponds exactly to
the case at bar, or examines the situation of personal damages suffered by a
contractor because of a delay resulting from an architect’s error.
Nevertheless, as a whole the decisions of the Cour de Cassation are
enlightening. In order not to encumber these reasons I refer to Jurisprudence
française, 1807-1967, verbo Architecte et Entrepreneur, vol. 1, at
pp. 423 and 424, and I would cite here No. 349:
[TRANSLATION] The architect and the
contractor, bound by contract to the owner by separate agreements, are third
parties in their personal relations and can be liable to each other in
quasi-delict, even if the wrongful act giving rise to such liability
constitutes at the same time a breach of a contractual obligation toward the
owner (Cass. civ. 1, Oct. 14, 1958: J.C.P. 58, IV, ed. G., 162; Bull. civ. I,
No. 429, p. 345).
It therefore seems to me to be established, and
I say this at the risk of repetition, that the architect’s responsibility is
not limited to the owner. If the structure, owing to an error in the plans,
causes damage to a third party, a passer-by for example, this third party has
the right to bring an action against the architect, since the latter has
neglected to ensure that his structure was solid
[Page 778]
when he knew that passers-by could be affected
by it. He thus neglected to fulfil a duty toward the injured party. Why should
this duty of the architect be limited, as a general principle, to “another” in
no way connected with the design and execution of the undertaking? In the case
at bar the trial judge found the architect at fault but imputed no blame to the
contractor. I fail to see why this contractor, who had to carry out additional
work to prevent an accident from occurring, could not recover from the
architect the damage caused it by the delay resulting from the error in the
plans.
The existence of art. 1688 C.C. in
no way modifies this rule, to which it is totally unrelated. This article
establishes in favour of the owner absolute liability even in the absence of
any fault on the part of the architect and contractor. However, nothing in this
text rules out a possible recourse by the latter if the architect has been
negligent.
From the foregoing, I conclude that at civil law
the following rule applies in a case such as that before the Court:
(1) the contractor and the architect are third
parties in relation to each other;
(2) the contractor may bring an action against
the architect for delictual damages if the latter has committed a fault, and
vice versa.
Nova Scotia Construction Company Limited v.
Quebec Streams Commission, does not contradict this rule. It deals with another
matter, the right of a contractor to supplementary compensation from the owner
because the solid rock on which it was to build a dam was at a greater depth than
expected. Since art. 37 of the contract stipulated that the contractor was
relying solely on the information received from a source other than the
respondent Commission, and the contractor was advised by the owner that its
tender was too low (much lower than those of its competitors), it is easy to
understand why Cannon J. could write (at p. 601):
[Page 779]
All the tenderers, except the appellant,
evidently took this uncertain element into account when preparing their tender
and reached a unit price after allowing themselves a margin of safety. This
appellant neglected to do because it considered, as it alleges at least, that
the indications on the plans of the base elevations were positive, certain and
constituted an implied warranty on which they were entitled to rely. There is
no express warranty in the contract; and, in law, there exist no implied
warranty as to the practicability of plans, nor as to accuracy of quantities.
Was the rule modified in the case at bar by the
agreement between the City of Pointe-Claire and appellant? I think not. There
is no general statement in this agreement that under no circumstances can the
contractor bring an action against the architect if the latter is at fault. The
only relevant stipulations are arts. 25, 35 and 39:
Article 25. Changes in the Work.
The Owner, or the Architect, without
invalidating the contract, may make changes by altering, adding to, or
deducting from the work, the contract sum being adjusted accordingly. All such
work shall be executed under the conditions of the original contract except
that any claim for extension or reduction of time caused thereby shall be
adjusted at the time of ordering such change. Except as provided in
Article 18, no change shall be made unless in pursuance of a written order
from the Architect and no claim for an addition to or deduction from the
contract sum shall be valid unless so ordered and at the same time valued or
agreed to be valued as provided in Article 26.
Article 35. Delays.
If the Contractor is delayed in the
completion of the work by any act or neglect of the Owner, Architect or any
Other Contractor or any employee of any one of them or by changes ordered in
the work, then the time of completion shall be extended for such reasonable
time as the Architect may decide.
Then follow two sentences dealing with the
contractor’s liability when the delay is the result of causes not attributable
to it, and with its liability when the delay is due to a cause under its
control. The procedure is then set out in two paragraphs that do not concern us
and the article continues:
[Page 780]
The Architect shall not, except by written
notice to the Contractor, stop or delay any part of the main contract work
pending decisions or proposed changes either by himself or by the Owner.
Article 39. Damages and Mutual
Responsibilities.
If either party to this contract should
suffer damage in any manner because of any wrongful act or neglect of the other
party or of anyone employed by him then he shall be reimbursed by the other
party for such damage. Claims under this paragraph shall be made in writing to
the party liable within a reasonable time after the first observance of such
damage and not later than the time of final payment, except as expressly
stipulated otherwise in the case of faulty work or materials, and shall be
adjusted by agreement or in the manner set out in Article 44 hereof, and
the party reimbursing the other party as aforesaid shall thereupon be
subrogated to the rights of the other party in respect of such wrongful act or
neglect if it be that of a third party. Should the Contractor cause damage to
any Other Contractor on the work, the Contractor agrees upon due notice to
settle with such Other Contractor by agreement or arbitration, if he will so
settle. If such Other Contractor sues the Owner on account of any damage
alleged to have been so sustained the Owner shall notify the Contractor who
shall defend such proceedings at the Owner’s expense and if any final order or
judgment against the Owner arises therefrom the Contractor shall pay or satisfy
it and pay all costs incurred by the Owner. Provided that if the Contractor
becomes liable to pay or satisfy any final order or judgment against the Owner
then the Contractor shall have the right, upon undertaking to indemnify the
Owner against any and all liability for costs, to appeal in the name of the
Owner such final order or judgment to any and all courts of competent
jurisdiction.
I find it impossible to accept respondent’s
claims that these articles are a full reply to the claim.
Article 25 does not provide that the
contractor must completely abandon all remedy against the architect at fault.
Such a waiver is clearly an exception to the general rule of liability and as
such must be expressed in very clear terms, which is certainly not the case (Canada
Steamship Lines
[Page 781]
v. The King.) The changes provided for in this
clause are modifications to the plans and specifications, which may be dictated
by various considerations but certainly not by the architect’s fault. If that
was the aim intended, it ought to have been spelled out in full.
Furthermore, art. 35 does not dispose of
the case either. It is true that the delay mentioned therein may be the result
of an “act or neglect of the Owner, Architect”, and that at first glance this
text may include fault. However, that is not the meaning of the words used
since, in speaking of “act or neglect”, the parties used the adjectives
“wrongful” and “faulty” in art. 39, when they wished to refer to fault and
negligence. One should not read more into art. 35 than is expressed
therein, and find in it a stipulation regarding negligence. Moreover, even if
art. 35 dealt with wrongful acts, it would not dispose of the case at bar.
This article is clearly a stipulation in favour of the contractor, in that the
owner cannot in the circumstances it mentions force the contractor to complete
the work within the time periods stipulated in the contract. This article in no
way deals with the rights which the contractor may have in relation to a third
party, including the architect, as the result of a delay imposed on it through
the fault of this third party.
That leaves art. 39, which is the only one
that mentions wrongful acts and neglect. Nothing in it supports the conclusion
that the contractor has waived its recourse against the architect in advance.
This clause is limited to dealing with cases in which the parties to the
contract, namely the owner and the contractor, have committed a wrongful act:
nothing more.
In view of this situation, I conclude that the
general rule has not been altered by the agreement and that it applies to the
case at bar. I would add, although this is not the basis of my conclusion, that
Chadwick, the architect selected by respondent to supervise the work, would apparently
have recommended payment of the damages, or at least part of them, if he had
not wrongfully denied the existence of the architect’s fault. In his letter to
[Page 782]
the municipality dated February 25, 1966,
Chadwick certified that the contractor was entitled to the sum of $4,159.32,
the cost of the additional work resulting from the change in the plans and
specifications, but he refused to acknowledge the validity of the claim for
delay:
The contractor is not entitled to be paid
an amount for delay in the general progress of the work because any delay which
may have occurred was the consequence of the contractor’s own act in not
following the Architect’s plans.
After the contractor-appellant indicated that
this definitely was not the case, Chadwick maintained his position in a letter
dated March 28, 1966. However, we know that the cause of the delay was
something else altogether and that it must be found in the architect’s error.
If, as I believe, the relevant general rule
favours the contractor and it has not been changed by the agreement, should the
claim be set aside anyway because the error in the plans was not a personal
error on the part of the architect, but an error of the engineer consulted by
the architect? I cannot accept this claim of respondent. The contract between
the City of Pointe‑Claire and appellant states that the work undertaken
by the latter must conform to the plans and specifications of the architect
Beatson, and that the latter has all the rights and powers attributed to the architect
in the standard form contract existing at the time. As a matter of fact,
although the contract was evidently concluded only between the municipality and
plaintiff, reference is made to the architect in almost every article, and the
architect is the only third party identified by name and address. Under the
circumstances, it seems to me that appellant was perfectly justified in
assuming that the architect was the only person responsible for the plans and
specifications, and that the delegation made by the latter to other persons
could not be pleaded against the contractor. Further, even if this argument
were accepted, it would apply to only a small part of the damage. On or about
May 11, 1965 the architect’s representative, Whiteside, noted along with the
contractor that the plans and specifications were defective. On May 25,
Chadwick stopped the work. The engineer’s error was therefore obvious and the
architect, who was respon-
[Page 783]
sible for the plans and specifications, had a
duty to correct it without delay. As the trial judge points out, however,
nothing was done before mid-June, despite repeated communications by Chadwick
and Whiteside with the respondent. Finally, on June 22, the contractor received
the necessary documents enabling it to resume work. Accordingly, even if it
were possible, as respondent contends, to conclude that the initial error
cannot be attributed to the architect, the latter should bear the consequences
of his failure to make the correction without delay.
There remains the question of prescription,
which I will not dwell on. Respondent contends that since the suit was filed on
March 28, 1967 and the plans date back to the fall of 1964, delictual action is
prescribed by virtue of art. 2261 of the Civil Code. I cannot accept
this argument. The starting point of the prescription can only be May 1965, the
date on which appellant began to use the part of the plans and specifications
at issue in the case.
Since I am of the opinion that the architect is
liable for the damage sustained by the contractor, I must deal with the
question of damages. Since the action was dismissed in both the Superior Court
and the Court of Appeal, the damages were not assessed there. However, the
trial judge did make the following observation:
[TRANSLATION] The evidence establishes that
construction of these walls took fifty‑eight working days instead of ten
working days—forty-eight more working days than anticipated.
What is the monetary value of these forty-eight
days? Appellant maintains that the delay caused it to lose $312.52 per day, and
bases itself on the testimony of its secretary-treasurer and a consulting
architect, Damphousse. Then, principally through Chadwick’s testimony,
respondent claims that there are no damages. In my opinion, however, the value
of Chadwick’s testimony is considerably lessened by his letters of February 25
and March 28, 1966, to which 1 have already referred. If at that time he really
did not believe in the existence of damages resulting from the delay, why did
he refuse to recognize them, giving as his sole reason that these damages had
been caused
[Page 784]
through the fault of the contractor himself?
After studying the body of evidence on this point, I have come to the
conclusion that the amount of $11,224 mentioned by appellant in his claim of
February 1, 1966 is a resonable assessment of the damages.
I would accordingly allow the appeal and,
setting aside the judgment a quo, I would uphold the action and order
respondent to pay appellant the sum of $11,224 with interest since the date of
service, the whole with costs in all courts.
Appeal dismissed with costs, DE
GRANDPRÉ J. dissenting.
Solicitors for the appellant: Cousineau,
Vaillancourt &. Cadieux, Verdun, Que.
Solicitors for the respondent:
Létourneau, Forest, Raymond, Létourneau & Roy, Montréal.