Supreme Court of Canada
Giffels v. Eastern Construction, [1978] 2 S.C.R. 1346
Date: 1978-02-07
Giffels Associates
Limited (Defendant) Appellant;
and
Eastern
Construction Company Limited (Defendant) Respondent;
and
Dominion Chain
Company Limited (Plaintiff);
and
Roof Engineering
and Inspection Co. Limited (Defendant).
1977: October 19, 20; 1978: February 7.
Present: Laskin C.J. and Martland, Ritchie,
Spence, Pigeon, Dickson and Beetz JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
ONTARIO.
Negligence—Contribution—Building
contract—Contribution as between general contractor and engineer as
joint-tortfeasors—Guarantee period of general contractor—The Negligence Act,
R.S.O. 1970, c. 296, s. 2(1).
The issues before the Supreme Court arose
from an action by the plaintiff Dominion against Giffels and Eastern for
damages for a defective roof on a new plant constructed by Eastern as general
contractor. Giffels was the engineer for the project under a contract with the
plaintiff to prepare specifications and to supervise the construction. A
separate contract was entered into between the plaintiff and Eastern as the
general contractor. The trial judge found that because of certain construction
practices by Eastern in the winter of 1964-65 which involved keeping the
building as closed in as possible and using artificial heat, high humidity and
the resulting condensation adversely affected the roof which blistered or
buckled in 1970. He also found that responsibility for this lay with both
Giffels and Eastern. Giffels had approved the roof as satisfactory on November
3, 1965, and Eastern’s one-year guarantee had expired on September 30, 1966. As to Eastern however he
found that the plaintiff had not brought itself within the terms of the
contract and that the action against it would have to be dismissed but for The
Negligence Act. This reservation by the trial judge concerned the liability
of Eastern not to the plaintiff but to Giffels for contribution and in the
result Eastern, although not directly
[Page 1347]
liable to the plaintiff was to bear 75 per
cent of the damages awarded to the plaintiff against Giffels. The Court of
Appeal dismissed Giffels’ appeal but allowed by a majority that of Eastern, the
majority reasons holding that it was a precondition of Giffels’ right to contribution
that Eastern be found liable to the plaintiff and that s. 2(1) of the Act
applied only as between tortfeasors and that in this case Giffels and Eastern
were under a duty of care in a tort sense apart from their liability in
contract. On further appeal Giffels contended that (1) the plaintiff could
properly pursue a remedy in tort for negligence, despite the existence of
contracts with Giffels and Eastern out of which the plaintiff’s relationship
with them arose; (2) this made s. 2(1) of The Negligence Act clearly
applicable but, in any event, that provision was wide enough to embrace breach
of contractual duty to exercise reasonable care as well as breach of duty in
tort of negligence; and (3) it was not a precondition of the right to invoke s.
2(1) for contribution that there be a finding of liability on Eastern’s part to
the plaintiff.
Held: The
appeal should be dismissed.
It is not necessary to come to a final
determination on whether s. 2(1) is broad enough to embrace contractual
liability when other provisions like ss. 3 and 9 clearly do not. It is however
difficult to read a contract basis for contribution into one provision of a
statute which has interrelated provisions dominated by a reference to
tortfeasors. But, even assuming that a tort claim in negligence was open to the
plaintiff, two considerations are preclusive against Giffels’ right to
contribution, namely, the giving of the final certificate in terms of Eastern’s
contract, and the finding at trial that the guarantee period fixed by that
contract had run in Eastern’s favour. A contractor protected by a valid
contractual limitation of liability cannot in these circumstances be said to
have contributed to any actionable loss by the plaintiff, a result which must
follow whether the claim for contribution is based on a liability in tort for
negligence or on contract.
APPEAL from a judgment of the Court of Appeal
for Ontario allowing an appeal
from a judgment of Lerner J. at trial. Appeal dismissed.
W.H.O. Mueller and F.A. Platt, for the
appellant.
D.K. Laidlaw, Q.C., for the respondent.
[Page 1348]
The judgment of the Court was delivered by
THE CHIEF JUSTICE—By an order dated June 1,
1976, the Ontario Court of Appeal gave leave to the appellant Giffels to appeal
its judgment dated April 23, 1976 to this Court on six questions, stated to be questions of law,
formulated as follows:
(a) whether the ‘contribution’ provision of
Section 2(1) of The Negligence Act is applicable because both Giffels and
Eastern have been ‘found to be at fault or negligent’, even though Eastern has
not been found ‘liable’ to the plaintiff by reason of a special defence held to
be available to Eastern as against the plaintiff alone;
(b) whether either or both Articles 17 and
28 of the construction contract, being standard terms within such contracts, is
or are sufficient to exempt Eastern from liability for negligent construction,
subsequent to and consequent upon the giving of Giffels’ ‘final certificate’ as
to completion of construction;
(c) whether Giffels’ ‘final certificate’
may be disregarded, for the purpose of eliminating it as a bar to the bringing
of an action for damages for negligent construction, in the event of it being
shown that Eastern which is seeking to shield itself from liability by virtue
of such certificate, concealed from Giffels material evidence that would have
influenced the decision of Giffels in releasing such certificate;
(d) whether the contribution and indemnity
provision of Section 2(1) of the Negligence Act is applicable in respect of
contract claims by the plaintiff against both Giffels and Eastern based upon
their negligent failure to exercise reasonable care in carrying out their
contractual duties requiring simply that reasonable care be exercised;
(e) alternatively, whether actions against
either or both of Giffels as engineers and Eastern as building contractors may
be alternatively asserted either in contract or in tort;
(f) whether Giffels has status to appeal a
finding that its co-defendant Eastern is not ‘liable’ to the plaintiff in order
to maintain a right to contribution and indemnity from Eastern (in the event
that ‘liability’ of Eastern is a precondition to contribution).
[Page 1349]
There is one peculiarity about the order For
leave on which I must comment. Question (f) raises an issue which was not
canvassed by the Ontario Court of Appeal, being, indeed, one which was not
originally raised in the appellant’s notice of appeal to that Court. After the
Ontario Court of Appeal gave judgment in the appeal on April 23, 1976, the appellant
Giffels moved to amend its notice of appeal to that Court to raise the point
taken in question (f). Leave to do so was given nunc pro tunc by an
order of May 21, 1976 but the Ontario Court of Appeal then refused to rehear
the appeal in respect of that point. Instead, it has purported to allow the
appellant to argue the point here. I do not think that this was either a
regular or a proper thing to do. It is for this Court alone to determine
whether it will give leave to argue here a point not taken or argued or
considered by the Court appealed from. If the Ontario Court of Appeal was not
prepared to rehear the appellant, there was no reason for allowing an amendment
to the notice of appeal after judgment was delivered, and less reason to add
the point of the amendment to the questions to be argued in this Court.
In my opinion, question (f) of the order for
leave to come to this Court is not open for consideration here. Moreover, the
point taken in the question goes beyond mere status to challenge the dismissal
of the plaintiff’s action against Eastern and involves a claim to argue the
propriety of the trial judge’s dismissal of the plaintiff’s action against the
respondent Eastern. This Court would necessarily be caught up in a reassessment
or review of questions of fact, and I would be unwilling to undertake this in
the present case.
The issues brought to this Court by the
appellant Giffels arise out of an action instituted by the plaintiff Dominion
Chain Company Limited against Giffels and Eastern to recover damages for a
defective roof on a new plant constructed for the plaintiff by Eastern, the
general contractor for the building. The roof was constructed by a
sub-contractor but nothing turns on this in this case. Giffels was the engineer
for the project under a contract with the plaintiff to prepare the specifica-
[Page 1350]
tions and to supervise the construction. A
separate contract was entered into between the plaintiff and Eastern as the
general contractor for the building. The trial judge, Lerner J., found that
because of certain construction practices by Eastern in the winter of
1964-1965, which involved keeping the building as closed-in as possible and
using artificial heat, high humidity with resulting condensation adversely
affected the roof which blistered or buckled in 1970, five years after its
construction. He also found that responsibility for the substantial injury to
the roof lay with both Giffels and Eastern.
The contract between the plaintiff and Eastern,
which was prepared by Giffels, contained, inter alia, the following
provisions:
Article 10. Engineer and Contractor. The
Engineer is, in the first instance, the interpreter of the Contract and the
judge of its performance; he shall use his powers under the Contract to enforce
its faithful performance by both parties hereto. The Contractor shall however
have complete control, subject to Article 12, of his organization.
Article 11. The Engineer’s Decisions. The
Engineer shall decide on questions arising under the contract documents, whether
as to the performance of the work or the interpretation of the specifications
and drawings; but should the Contractor hold such decisions to be at variance
with the contract documents, or to involve changes in work already built,
fixed, ordered or in hand in excess of the contract, or to be given in error,
he shall notify the Engineer before proceeding to carry them out. The Engineer
has authority to stop the work whenever such stoppage may be necessary to
ensure the proper execution of the Contract.
…
Article 17. Correction after Final Payment.
Neither the final certificate nor payment thereunder, nor any provision in the
contract documents shall relieve the Contractor from responsibility for faulty
materials or workmanship, which appear within a period of one year from the
date of substantial completion of the work, and he shall remedy any defects due
thereto and pay for any damage to other work resulting therefrom which appear
within such period of one year. The Owner shall give notice of observed defects
promptly. Questions arising under this Article shall be decided as provided in
Article 11. Notwithstanding the provisions of this Article, if any section of
the Quebec Civil Code in the case of work
[Page 1351]
performed in the Province
of Quebec, creates a more
extended liability for faulty materials or workmanship, then that section of
the Civil Code shall apply.
…
Article 28. Certificates and Payments. If
and so often as the Contractor has made application for payment by submitting
to the Engineer the invoice provided for in Article III of the Agreement, the
Engineer shall, within Ten (10) days of receipt of the application, approve the
account for payment or advise the Contractor promptly in writing why the
account is amended or disapproved. Such approval may provide for holdbacks
sufficient to protect the Owner against all liens and may be withheld if the
Engineer has not received information that payments due to sub‑contractors
have not been made.
No payment made to the Contractor and no
partial or entire use or occupancy of the work by the Owner shall be construed
as an acceptance of any work or material not in accordance with this contract.
The issuance of the final certificate shall constitute a waiver of all claims
by the Owner otherwise than under Articles 17 and 29 [dealing with liens] of
these conditions and the acceptance of such final certificate by the Contractor
shall constitute a waiver by him of all claims except those previously made and
still unsettled if any. Should the Owner fail to pay the sum named in any
certificate of the Engineer upon demand when due, the Contractor shall receive,
in addition to the sum named in the certificate, interest thereon at the rate
of 6%.
I need not dwell on the evidence or findings of
the trial judge that Giffels, in the words of the trial judge, “failed in its
contractual obligations or duties and was negligent in the performance of its
professional skills” in respect of the damage to the roof. Giffels had approved
the roof as satisfactory on November 3, 1965, and Eastern’s one year guarantee
expired on September 30, 1966, this being accepted (according to the trial
judge) by all parties at trial as a fact. As to Eastern, although the failure
of the roof was the result of its faulty construction procedures, the findings
of the trial judge were that the plaintiff had not brought itself within
article 17 of the contract, and that since Giffels itself had delivered to
Eastern on April 15, 1967 the final certificate contemplated by article 28 of
the contract, the action against it would have to be dismissed “but for The
Negligence Act”. This reservation by the trial judge concerned the
liability of Eastern not to the plaintiff but to
[Page 1352]
Giffels for contribution. The trial judge found
that The Negligence Act, R.S.O. 1970, c. 296, provided a basis for
apportioning liability between Giffels and Eastern inter se, and that
Eastern, although not itself liable to the plaintiff, must bear 75 per cent of
the damages awarded to the plaintiff against Giffels.
Lerner J. arrived at this conclusion by holding,
first, that The Negligence Act could be invoked only as between
tortfeasors; second, by finding that both Giffels and Eastern were negligent in
a tort sense in the carrying out of their respective obligations, apart from
breach of contract; and, third, that it was not necessary under s. 2(1) of The
Negligence Act, as it was under s. 3, that each tortfeasor be found liable
to the plaintiff as a precondition of liability to make contribution to the
other.
Both Giffels and Eastern appealed to the Court
of Appeal, the former from the judgment of Lerner J. holding it liable to the
plaintiff and the latter from the judgment against it for contribution in
favour of Giffels. The Court of Appeal disposed of Giffels’ appeal adversely to
it in oral reasons and reserved judgment on Eastern’s appeal. This appeal was
allowed but the Court was not unanimous in its reasons. The majority reasons of
Jessup J.A., Zuber J.A. concurring, proceeded on the ground that it was a
precondition of Giffels’ right to contribution that Eastern be found liable to
the plaintiff, but in the course of arriving at this conclusion, the learned
judge also held that s. 2(1) of The Negligence Act applied only as
between tortfeasors and that in the present case Giffels and Eastern were under
a duty of care in a tort sense, apart from their liability in contract. Madame
Justice Wilson was of the opinion that any liabilities of Giffels and Eastern
arose only in contract and that no separate cause of action lay through the
tort of negligence.
In its appeal to this Court, Giffels through its
counsel, in a wide ranging argument, contended that (1) the plaintiff could
properly pursue a
[Page 1353]
remedy in tort for negligence, despite the
existence of contracts with Giffels and Eastern out of which the plaintiff’s
relationship with them arose; (2) this made s. 2(1) of The Negligence Act clearly
applicable but, in any event, that provision was wide enough to embrace breach
of contractual duty to exercise reasonable care as well as breach of duty in
tort for negligence; and (3) it was not a precondition of the right to invoke
s. 2(1) for contribution that there be a finding of liability on Eastern’s part
to the plaintiff.
Sections 2(1) and 3 of The Negligence Act read
as follows:
2.(1) Where damages have been caused or
contributed to by the fault or neglect of two or more persons, the court shall
determine the degree in which each of such persons is at fault or negligent,
and, except as provided by subsections 2, 3 and 4, where two or more persons
are found at fault or negligent, they are jointly and severally liable to the
person suffering loss or damage for such fault or negligence, but as between
themselves, in the absence of any contract express or implied, each is liable
to make contribution and indemnify each other in the degree in which they are
respectively found to be at fault or negligent.
…
3. A tort feasor may recover contribution
or indemnity from any other tort feasor who is, or would if sued have been, liable
in respect of the damage to any person suffering damage as a result of a tort
by settling with the person suffering such damage, and thereafter commencing or
continuing action against such other tort feasor, in which event the tort
feasor settling the damage shall satisfy the court that the amount of the
settlement was reasonable, and in the event that the court finds the amount of
the settlement was excessive it may fix the amount at which the claim should
have been settled.
The history of the Act, of the changes and
additions to it since its original enactment as a simple contributory
negligence statute in 1924 (see 1924 (Ont.) c. 32) were fully canvassed by the
appellant’s counsel and as well by respondent’s counsel. The former laid
particular stress on the substitution in 1935 of the words in the opening lines
of s. 2(1), “except as provided by subsection 2, where two or more persons are
found at fault or negligent”, for the words “where two or more persons
[Page 1354]
are found liable”. For him, this change
fortified his contention that a finding of liability or proof that liability
could have been found was not an essential basis for a claim of contribution.
Respondent’s counsel urged on his part that an appraisal of the Act as a whole
in the light of its history made it abundantly clear that the Act was concerned
with tort liability and not with contractual liability.
In my opinion, it is not necessary in this case
to come to a final determination on whether s. 2(1) of The Negligence
Act is broad enough to embrace contractual liability when other provisions
of the Act, like ss. 3 and 9, clearly do not. I incline, however, to the view
advanced by counsel for the respondent in this respect. I think it difficult to
see how a contract basis for contribution can be read into one provision of a
statute which has interrelated provisions dominated by a reference to
tortfeasors. Similarly, I am of the view that it is a precondition of the right
to resort to contribution that there be liability to the plaintiff. I am unable
to appreciate how a claim for contribution can be made under s. 2(1) by one
person against another in respect of loss resulting to a third person unless
each of the former two came under a liability to the third person to answer for
his loss. Hence, even assuming that a tort claim in negligence was open to the
plaintiff against Giffels and Eastern in the present case—and I need not come
to a determination on this issue here—there are two considerations which are
preclusive against Giffels’ right to contribution under s. 2(1). They are,
first, the giving of the final certificate under article 28 of Eastern’s
contract and, second, the finding by the trial judge that the guarantee period
fixed by article 17 of that contract has run in Eastern’s favour.
I do not think that any comfort is available to
Giffels from the “exculpatory clause” cases which hold that, unless negligence
is expressly mentioned, exculpation from liability will not cover liability for
negligent conduct if there is subject matter for the clause without reference
to negligence. Faulty material or wokmanship is expressly
[Page 1355]
covered in article 17 and article 28 must be
read to exclude all claims under or in respect of the performance of the
contract, and hence it is immaterial whether they arise in contract or in tort.
In the present case, it was the same negligence, whether regarded as a breach
of contract or as a basis for an independent tort claim, which lay at the base
of any claim by the plaintiff against Eastern for damages.
Moreover, whether Giffels bases its claim for
contribution on s. 2(1) or outside of that provision, the same result adverse
to Giffels must follow. I am prepared to assume, for the purposes of this case,
that where there are two contractors, each of which has a separate contract
with a plaintiff who suffers the same damage from concurrent breaches of those
contracts, it would be inequitable that one of the contractors bear the entire
brunt of the plaintiff’s loss, even where the plaintiff chooses to sue only
that one and not both as in this case. It is, however, open to any contractor
(unless precluded by law) to protect itself from liability under its contract
by a term thereof, and it does not then lie in the mouth of the other to claim
contribution in such a case. The contractor which has so protected itself
cannot be said to have contributed to any actionable loss by the plaintiff.
This result must follow whether the claim for contribution is based on a
liability to the plaintiff in tort for negligence or on contractual liability.
In either case there is a contractual shield which forecloses the plaintiff
against the protected contractor, and the other contractor cannot assert a
right to go behind it to compel the former to share the burden of compensating
the plaintiff for its loss.
What we have here is a case where the immunity
of Eastern from liability did not arise from some independent transaction or
settlement made after an actionable breach of contract or duty, but rather it
arose under the very instrument by which Eastern’s relationship with the
plaintiff was established. Giffels had no cross-contractual relationship with
Eastern upon which to base a claim for
[Page 1356]
contribution; and once it was clear, as it was
here, that Eastern could not be held accountable to the plaintiff for the
latter’s loss, any ground upon which Giffels could seek to burden Eastern with
a share of that loss disappeared.
I would dismiss the appeal with costs.
Appeal dismissed with costs.
Solicitors for the appellant:
Outerbridge, Manning & Mueller, Toronto.
Solicitors for the respondent: McCarthy
& McCarthy, Toronto.