Supreme Court of Canada
Wire Rope Industries of Canada (1966) Ltd. v. B.C. Marine Shipbuilders Ltd. et al.,
[1981] 1 S.C.R. 363
Date: 1981-03-19
Wire Rope
Industries of Canada (1966) Ltd. (Third Party) Appellant;
and
B.C. Marine
Shipbuilders Ltd. and Straits Towing Ltd. (Plaintiffs) Respondents;
and
F.M. Yorke &
Son Limited (Defendant) Respondent;
and
Wire Rope
Industries of Canada (1966) Ltd. (Defendant) Appellant;
and
B.C. Marine
Shipbuilders Ltd. and Straits Towing Ltd. (Plaintiffs) Respondents.
1980: March 11, 12, April 23, 24; 1981:
March 19.
Present: Martland, Ritchie, Dickson, Beetz,
Estey, McIntyre and Chouinard JJ.
ON APPEAL FROM THE FEDERAL COURT OF APPEAL
Courts—Jurisdiction—Federal Court of
Canada—Trial Division—Canadian maritime law—Third party proceedings, while
related to action in maritime law, based in tort and contract—Whether or not
jurisdiction to entertain third party proceeding—British North America Act,
s. 91.10—Federal Court Act, R.S.C. 1970 (2nd Supp.), c. 10, ss. 2, 22(1),
(2), 42—The Admiralty Act, 1891, 1891 (Can.), c. 29, ss. 3, 4—An Act to improve
the Practice and extend the Jurisdiction of the High Court of Admiralty of
England, 1840 (U.K.), c. 65, s. 6—The Admiralty Act, 1934, 1934 (Can.), c.
31—Colonial Courts of Admiralty Act, 1890, 1890 (U.K.), c. 27.
Maritime law—Barge lost at sea—Towline
socket failure—Socket resocketed under contract—Tug’s contract requiring
seaworthiness at outset of voyage—No liability of due diligence proved—Whether
or not tug owner liable—Whether or not third party liable to indemnify other
parties for loss of third party negligent in resocketing process.
[Page 364]
These appeals raised questions of liability
for loss at sea of a log barge, owned by the respondent B.C. Marine
Shipbuilders Ltd. and chartered to Straits Towing Ltd., while the barge was
being towed by the Lorne Yorke, a tug owned by F.M.Yorke & Son
Limited. Pursuant to the contract with the tug owner the ship had to be
seaworthy at the outset of the voyage, and if it were otherwise, the burden lay
on the tug owner to prove due diligence with respect to seaworthiness. The loss
occurred because of the failure of a manganese steel socket that formed part of
the towline between the tug and the barge. The socket had been resocketed—a
process by which a socket was reattached to the wire rope or cable—and because
the process had been performed by Wire Rope, that company was joined in the
action as a third party. Claims were made by the owner and the charterer of the
barge against the tug’s owner; claims for indemnity were made against Wire
Rope; as well, the jurisdiction of the Federal Court of Canada to deal with the
third party claim was in issue.
At trial, judgment was ordered against Yorke
in favour of Straits and B.C. Marine, and a reference directed. The actions
against Wire Rope were dismissed. The Court of Appeal allowed Yorke’s appeal
from the judgment in favour of B.C. Marine but dismissed its appeal from
judgment in favour of Straits. The third party claim by Yorke and the appeals
by B.C. Marine and Straits against Wire Rope succeeded, rendering Yorke
liable for the barge’s loss with right of indemnity against Wire Rope and
making Wire Rope liable to B.C. Marine and Straits for their losses. In this
Court, Wire Rope appealed and sought the restoration of the trial judgment.
B.C. Marine and Straits sought dismissal of the appeal made by Wire Rope and
Yorke, and B.C. Marine also sought a reversal of the Court of Appeal’s
dismissal of its action against Yorke. Yorke cross-appealed the judgment made
against it in favour of Straits, and alternatively, sought an order for
indemnification against Wire Rope for damages and costs for which it could be
held liable.
Held: The
appeals of Wire Rope against the judgments in favour of B.C. Marine, Straits
and Yorke should be allowed and the part of the trial judgment dismissing the
actions against Wire Rope restored; the cross-appeal by Yorke should be
allowed; the action by
[Page 365]
B.C. Marine and Straits against Yorke should
be dismissed; and the cross-appeal of B.C. Marine and Straits should be
dismissed.
The Federal Court had jurisdiction to deal
with the claims made against Wire Rope. Those claims alleged breach of contract
and negligence in the resocketing of the main towing cable which formed part of
the equipment of the Lorne Yorke. The claims made against Wire Rope were
encompassed within the meaning of “Canadian maritime law” as used in the Federal
Court Act. Jurisdiction broad enough to include these claims had been
granted the British High Court of Admiralty, and had been transmitted through a
succession of courts to the Federal Court. In addition, the substantive law
relating to the claims fell within federal legislative competence under
s. 91.10 of the British North America Act. There was therefore law
of Canada relating to the
issues upon which the Federal Court could operate. It was of no significance
that Yorke’s claim was one for indemnity. Claims for indemnity and third party
actions, generally, are not mere incidents to the principal action but are
independent, standing on their own feet.
The appeals against Wire Rope were dismissed
for it could not be shown that its work on the socket caused or contributed to
the socket’s failure leading to the loss of the barge. There was evidence to
support the conclusion that resocketing did not significantly embrittle the
socket and cause its failure. Any claim that the defect was caused by an
indefinite number of resocketings could not be sustained for no affirmative
evidence was adduced to establish more than one socketing and resocketing. As
the resocketing did not cause the socket’s failure, no liability could fall on
Wire Rope.
Yorke was not liable in the main action
brought by B.C. Marine and Straits for the loss of the barge. Any implied
warranty respecting the ability of the crew, tackle and equipment at the outset
of the voyage to meet the circumstances reasonably expected, was replaced by
the inclusion of specific provisions in the contract between Yorke and Straits.
Yorke was liable to B.C. Marine or Straits only if the Lorne Yorke, because
of a failure by Yorke to exercise due diligence, was not seaworthy when it put
out on the voyage that led to the accident, and if the loss was caused by lack
of seaworthiness. Yorke successfully met the burden of showing that the
socket’s failure was caused by a latent defect. The exercise of due diligence
would not have revealed the defect. Even if the socket had had no latent
defect, there was evidence that the manganese steel socket could be
[Page 366]
safely resocketed and that the practice of
re-using sockets after resocketing was regularly followed in the industry with
no apparent ill-effects. The state of the socket at the outset of the voyage
was not such as to make the vessel unseaworthy and so render Yorke liable
pursuant to the contract. There was no evidence of loss being caused by faulty
navigation or seamanship.
R. v. Thomas Fuller Construction Co.
(1958) Limited and Foundation Company of Canada Limited, [1980] 1 S.C.R. 695, distinguished; Tropwood A.G. and the Owners
of the Vessel Tropwood v. Sivaco Wire & Nail Company and Atlantic Lines
& Navigation Company, Inc., [1979] 2 S.C.R. 157; Quebec North Shore
Paper Company et al. v. Canadian Pacific Limited, et al., [1977] 2
S.C.R. 1054; McNamara Construction (Western) Limited et al. v. The
Queen, [1977] 2 S.C.R. 654; Bank of Montreal v. Royal Bank of Canada, [1933]
S.C.R. 311; Charles Goodfellow Lumber Sales Limited v. Borromée Verreault,
Captain Fernand Hovington and Verreault Navigation Inc., [1971] S.C.R. 522,
applied; Maxine Footwear Company Ltd. et al. v. Canadian Government Merchant
Marine Ltd., [1957] S.C.R. 801; Western Canada Steamship Company Limited
v. Canadian Commercial Corporation and Others, [1960] S.C.R. 632; Riverstone
Meat Co. Pty. Ltd. v. Lancashire Shipping Co. Ltd., (“Muncaster Castle”), [1961]
A.C. 807; Toronto Elevators Limited v. Colonial Steamship Limited, [1950]
Ex. C.R. 371; Robin Hood Flour Mills Limited v. N. M. Paterson & Sons
Limited, [1967] 1 Ex. C.R. 431, aff’d [1968] 1 Ex. C.R. 175, referred
to; Scottish Metropolitan Assurance Company, Limited v. Canada Steamship
Lines, Limited, [1930] S.C.R. 262; The “Dimitrios N. Rallias” (1922),
13 L1. L.R. 363, considered.
APPEALS AND CROSS-APPEALS from decisions of
the Federal Court of Appeal,
allowing the appeals from and varying the judgments of Gibson J. Appeals by
Wire Rope against the judgments in favour of B.C. Marine, Straits, and Yorke
allowed, and that part of the judgment at trial dismissing the actions against
Wire Rope restored; cross-appeal by Yorke allowed; the action by B.C. Marine
and Straits against Yorke dismissed; and the cross‑appeal of B.C. Marine
and
[Page 367]
Straits dismissed.
D. Brander Smith and N. Daugulis, for the
appellant.
W. O’M. Forbes, for the respondents B.C.
Marine Shipbuilders Ltd. and Straits Towing Ltd.
J.R. Cunningham, for the respondent F.M.
Yorke & Son Limited.
The judgment of the Court was delivered by
MCINTYRE J.—These appeals raise questions of
liability for the loss at sea of a log barge owned by the respondent B.C.
Marine Shipbuilders Ltd. Claims were made by the owners and charterers of the
lost barge against the owners of the tug engaged to tow it; claims for
indemnity were also made against a company which had performed certain services
for the tug; as well the jurisdiction of the Federal Court of Canada to deal
with the third party claim for indemnity was in issue.
The respondents B.C. Marine Shipbuilders Ltd.
(B.C. Marine) and Straits Towing Ltd. (Straits) commenced these proceedings in
the Federal Court against F.M. Yorke & Son Limited (Yorke) claiming damages
for breach of a contract of towage and for negligence resulting in the loss of
their barge, the Westport Straits. The breach alleged was that Yorke had
failed to furnish a seaworthy tug. By the order of Mr. Justice Sheppard,
dated January 7, 1970, Yorke issued a third party notice directed to Wire Rope
Industries of Canada (1966) Ltd. (Wire Rope) and later filed a statement of
claim for indemnity for any damages for which it might become liable to the
respondents. Yorke alleged negligence on the part of Wire Rope in the
resocketing of a cable used in towing the Westport Straits, a process I
will describe later, and breach of an implied warranty of fitness of its work.
On January 5, 1973 Collier J. gave leave to B.C. Marine and Straits to add Wire
Rope as a defendant, and in their amended statement of claim they claimed
negligence in the
[Page 368]
resocketing process and resultant damages
against Wire Rope.
Yorke denied negligence and denied breach of any
implied term of seaworthiness of the tug and its towing gear. It asserted that
it had exercised due diligence in furnishing a seaworthy vessel. In its
statement of defence and counterclaim, Yorke said that if any negligence was
involved in connection with the towing and loss of the Westport Straits it
was attributable to the negligence of one Tobiasen, the mate of the tug, who
was an employee of Straits and who had been placed as mate upon the tug by
agreement with Yorke. Wire Rope denied negligence in the resocketing and also
denied any implied or express warranty as to the quality of its work.
The plaintiff B.C. Marine owned the Westport
Straits. By demise charter it chartered the barge to its co-plaintiff
Straits. It was to be used to haul logs between Vancouver and a port, or ports, on the westerly coast of Vancouver Island. Straits, in turn, had
chartered the tug Lorne Yorke from Yorke. It then engaged Yorke to tow
the Westport Straits from Vancouver to a port on Kyuquot Sound on the west
coast of Vancouver Island and there to pick up a load of logs and return them
to Vancouver. Yorke picked up the barge at Vancouver and commenced to tow it to its destination.
The voyage involved passing through the Straits
of Juan de Fuca and proceeding along the west coast of Vancouver Island to the
entry to Kyuquot Channel where it was necessary to turn to starboard and pass
into the channel and proceed to the destination which was known as Fair Harbour
farther up the channel. The weather conditions were bad and on the night of
January 31, 1968, while en route to Fair Harbour, the tug had been forced by
weather to turn back from the westerly end of the Straits of Juan de Fuca and
remain in the shelter of the straits for several hours. By the morning of
February 1, the master of the Lorne Yorke elected to proceed with the
voyage. He
[Page 369]
continued along the west coast of Vancouver
Island towards Kyuquot Sound. At midnight on February 1 he turned over the watch to the mate Tobiasen, and
went to bed. At about 0200 hours on February 2 Tobiasen reduced speed to cut
down the ‘surging’ effect of the movement of tug and barge on the towline. This
had the effect of allowing the towline to sink to the bottom and drag. At about
0245 hours while entering Kyuquot Channel the tug encountered a squall with
sleet and snow and strong gusting winds from east-south-east. At this time the
towline had been extended to about 2,000 feet. Tobiasen found that the tug was
being moved to port, toward the northerly shore of the channel and, as he
ordered a change of course to starboard, the towline became snagged on the
bottom and the tug would no longer answer to its helm. In these conditions of
weather and sea both tug and tow were placed in extreme hazard. The master was called
after speed had been reduced to reduce pressure on the towline. The master came
to the wheelhouse at once. He ordered the dropping of the towing pins—devices
used to guide the towlines straight over the stern of the tug—for the purpose
of making it possible to drive the tug hard to starboard, which he did, while
at the same time going to full power in an attempt to jerk the towline free.
The towline parted and, as a result, the barge Westport Straits was
driven ashore and became a total loss.
The towline in use was in three connected
sections. The principal section described as the main towline extended
from the tug about 1,300 feet where it joined the second section or
pennant which was some 350 to 400 feet in length and it, in turn, joined the
third section which was of similar length and attached to the barge. The
connections between the main towline and the first pennant, and between the two
pennants, were effected by the use of sockets at the end of each
section of cable, joined by links to the opposite sides of a steel tag
plate. The sockets were made of steel. They were provided with an eye through
which the link of the tag plate passed and were attached to the end of the
towline by a process called socketing. Drawings illustrating the triple towing
gear involved in this appeal appear below. Figure ‘A’ illustrates the linkage
involved where three barges
[Page 370]
are towed at once. Figure ‘B’ illustrates the
method of towing employed by Yorke on the date of the loss of the barge and, as
well, gives an idea of the relative positions of tug, tow, and towline at the
time the line failed. Figure ‘C’ shows the method of linkage from pennant to
pennant, and figure ‘D’ provides a rough sketch showing the broken socket. It
was the socketing of the main towline which brought Wire Rope into this action.

When the broken towline, or what remained of it,
was taken aboard the Lorne Yorke it was observed that the break in the
line had occurred at the main towline socket. The socket itself had broken and
allowed the link to the adjoining pennant to escape. The line itself remained
intact. Marks about fifty feet from the socket indicated where the towline had
apparently been caught on the rocks. It was alleged against Wire Rope that the
socket failed because it had been damaged and weakened by the negligence of
Wire Rope in resocketing the towline. Wire Rope had performed this service for
Yorke on October 13, 1967. Much
[Page 371]
of the evidence at trial was concerned with this
issue. The process of socketing must be understood.
The sockets in use by Yorke at the time of the
accident were made of manganese steel. This steel is particularly suited for
this function, being very strong, ductile, and having great tensile strength.
During the manufacturing process of manganese steel sockets the steel is heated
to a temperature of some 1,950° F. and then quenched, or cooled very quickly,
in cold water. The sudden cooling prevents the precipitation in the steel of
undesirable carbides which, if present, would have the effect of making or
tending to make the steel brittle, and thus subject to failure and unsuitable
for use in this type of socket. After manufacture if it is necessary for any
reason to heat the steel beyond 500° F. or 600° F. there is a danger that some
embrittlement may result, depending upon the temperature reached and the time
it is maintained, particularly if the heating is repeated frequently. To avoid
this danger the steel should be reheated to 1,950° F. and quenched suddenly in
cold water as above.
The type of socket in use in this case is used
upon cable, commonly called wire rope. When put in use the socket is attached
to the towline by running the end of the towline into the bottom of the socket
so that it is enclosed by a collar or cylinder forming the base of the socket
and called a basket. The wires of the cable end are loosened to give what is
termed a ‘brushing’ effect and then molten zinc is poured into the base of the
socket. When the zinc cools and hardens the end of the cable is securely retained
in the socket.
From time to time for various reasons, including
wear on the cable which frequently appears in the vicinity of the socket, it is
necessary to remove the socket and to cut out any worn part of the line. If the
socket is considered to be sound it can be resocketed and returned to use. The
evidence indicated that re-use of sockets involving a consequent resocketing
was common practice with York and other towing companies on the Pacific coast.
[Page 372]
To remove the socket it is necessary to heat the
zinc in the socket to its melting point which was, according to the evidence,
between 700° F. and 800° F. The molten zinc is then allowed to escape and the
cable may be removed. The remaining zinc may then be cleaned out of the socket
and after worn portions of the cable are removed the socket may be replaced as
described above. It should, however, be noted that the process of heating to
1,950° F. followed by a rapid quenching in cold water is done in the foundry
where the socket is cast and could not be carried out, and was not carried out,
in the circumstances of the resocketing in this case, which will be described
later.
The trial judge found that the mate of the Lorne
Yorke, although an employee of Straits, was at all relevant times under the
control and direction of Captain McLean, the master of the Lorne Yorke. He
therefore considered that, being in the actual control and employment of Yorke,
his negligence, if found to exist, would be attributable to Yorke. In this I
agree with him and this point was not argued later. It may be observed here
that in view of the position taken in this Court on the question of negligence
in seamanship and navigation by B.C. Marine and Straits it ceased to be of
significance.
He went on to refer to the scientific evidence
called by the parties regarding the treatment of the socket and its effect, and
expressed his findings in these words:
Having carefully considered all this
evidence, I am of the view, using the usual test of more probable than not, in
respect to both the expert and lay evidence, what Chapman and Babey of Wire
Rope Industries of Canada (1966) Ltd., did at the material time in re‑socketing,
because of the manner in which they did it and the time involved, did not
result in the subject socket (Exhibit 3) becoming embrittled to any significant
extent.
Whatever embrittlement there was in this
subject socket, in my view, was caused by the indefinite number of re-socketing
operations which were done to it prior to the occasion when Chapman and Babey
did their work.
In addition, at the material time when the
subject socket broke, it was not subject to just a straight linear pull.
Instead, it was subject to a large number of stresses
[Page 373]
in various directions at the moment when it
broke. As a consequence, it is difficult to say precisely how much strength and
ductility it had lost.
Regarding the position in this matter of Yorke,
he went on to say:
In coming to the conclusion I do, I am of
the view, firstly either the Defendant, F.M. Yorke & Son Limited through
its servants which includes in law the mate Tobiasen, may have caused the tug
through improper seamanship to have got itself in the position it reached near
the rocks at the southwesterly end of Kyuquot Channel so that even with proper
seamanship, the tug could not have been extricated from its difficulty without
breaking the towline; or second, it may be that the situation in which the
Defendant, F.M. Yorke & Son Limited through its servants, got the tug
into at the material time was a situation which it was not unreasonable under
the circumstances of time and sea, to have got the tug into and that following
that, the actions taken by Captain McLean were the correct actions and that the
towline at the socket should not have broken and it broke only because it was a
faulty socket which the Defendant, F.M. Yorke & Son Limited, knew or should
have known was likely to occur or by contract impliedly warranted would not
happen. (cf McKenzie Barge & Derrick Co. Ltd. v. Rivtow Marine Ltd. (1968),
2 D.L.R. 505.)
In either event, the Defendant, F.M. Yorke
& Son Limited is liable to the Plaintiffs for the damages that resulted.
He held Wire Rope not liable in the matter and
ordered judgment against Yorke in favour of Straits and B.C. Marine and
directed a reference as to damages. The plaintiffs were given costs against
Yorke and the actions against Wire Rope were dismissed with costs.
In the Court of Appeal, Pratte, Ryan and Smith
JJ.A., Ryan J.A. speaking for the Court, allowed the appeal of Yorke against
the judgment in favour of B.C. Marine and dismissed Yorke’s appeal against the
judgment in favour of Straits. It also ordered that Yorke should succeed in its
third party claim against Wire Rope and allowed the appeal by B.C. Marine and
Straits against Wire Rope. The effect of this judgment was to render Yorke
liable to the plaintiff Straits for the loss of the barge and give Yorke
a right of indemnity
[Page 374]
against Wire Rope. It also gave judgment against
Wire Rope for the loss to the plaintiffs B.C. Marine and Straits.
These appeals were taken by leave granted on
June 29, 1978. The appellant Wire Rope asks that both of its appeals be allowed
with costs and that the judgment at trial be restored. B.C. Marine and
Straits seek the dismissal of the appeals of Wire Rope and Yorke against the
Federal Court of Appeal’s judgment in their favour. B.C. Marine, as owner of
the lost barge, also seeks a reversal of the Court of Appeal’s dismissal of the
action against Yorke. Yorke asks that its cross-appeal from the judgment
against it in favour of Straits be allowed and that the action be dismissed.
Alternatively, if the cross-appeal is not allowed Yorke seeks an order for
indemnification against Wire Rope for any damages and costs for which it may be
held liable.
The hearing of the appeals commenced in this
Court on March 11, 1980. On March 12 during argument the Court raised the
question of jurisdiction of the Federal Court Trial Division to entertain
Yorke’s action for indemnity against Wire Rope. This point had not been raised
before. Counsel were referred to the judgment of this Court in R. v. Thomas
Fuller Construction Co. (1958) Limited and Foundation Company of Canada Limited. The hearing was adjourned to give
time for counsel to consider the position in the light of the Fuller case
and to submit new factums on the question of jurisdiction so that it could be
argued in full. On April 23, 1980, counsel having filed new factums, argument
resumed. The hearing was completed and judgment reserved. I will deal firstly
with jurisdiction.
The question of jurisdiction of the Federal
Court has been raised and considered in several recent cases, of which the most
significant for our purpose is Tropwood A.G. and the Owners of the
[Page 375]
Vessel Tropwood v. Sivaco Wire & Nail
Company and Atlantic Lines & Navigation Company, Inc.
At no time in these proceedings has it been contended that the Federal Court
did not have jurisdiction to deal with the claims made by the plaintiffs B.C.
Marine & Straits against Yorke. It is clear that these claims, arising out
of a marine accident concerning rights and liabilities under a barge charter
and a contract of towage and the exercise of due diligence in connection
therewith, come within the ambit of Canadian maritime law as described in s. 2
of the Federal Court Act. The jurisdictional question arises, however,
because of the claims against Wire Rope which allege a breach of contract and
negligence in the resocketing of the main towing cable. The issue then is, do
such claims fall within the jurisdiction of the Federal Court, or are they
governed by provincial law and therefore come within the jurisdiction of the
Supreme Court of British Columbia?
In Tropwood it was held, following
earlier decisions in this Court in Quebec North Shore Paper Company et al. v.
Canadian Pacific Limited, et al. and
McNamara Construction (Western) Limited et al. v. The Queen, that to give the Federal Court
jurisdiction there must be a body of applicable federal law upon which that
jurisdiction might operate. Such was not the case in Quebec North Shore, nor
in McNamara, and accordingly jurisdiction in respect of the issues
arising in those cases rested not in the Federal Court but in the Superior
Courts of the provinces. However, in Tropwood, it was held that there
exists a body of federal law described as Canadian maritime law in the Federal
Court Act over which the Federal Court has jurisdiction, that it was within
Parliament’s legislative competence under s. 91.10 of the British North
America Act, and that certain of the paragraphs of s. 22(2) of the Federal
Court Act gave specific jurisdiction to the Federal Court. Laskin C.J.C.,
speaking for the Court, said at p. 163:
[Page 376]
I come, therefore, to the Federal Court
Act. I have already quoted s. 22(1) and I refer to the words “Canadian
maritime law” therein, words which are defined in s. 2 of the Act as
follows:
“Canadian maritime law” means the law that
was administered by the Exchequer Court of Canada on its Admiralty side by
virtue of the Admiralty Act or any other statute, or that would have
been so administered if that Court had had, on its Admiralty side, unlimited
jurisdiction in relation to maritime and admiralty matters, as that law has
been altered by this or any other Act of the Parliament of Canada;
This definition is supplemented by
s. 42 of the Federal Court Act, reading as follows:
Canadian maritime law as it was immediately
before the first day of June, 1971 continues subject to such changes therein as
may be made by this or any other Act.
This definition of Canadian maritime law in
s. 2 refers to the law that was administered by the Exchequer Court “by
virtue of the Admiralty Act or any other statute”. The. reference to the
Admiralty Act is undoubtedly to the Act of 1934, but the Admiralty
Act of 1891, although it was repealed, may certainly be considered as “any
other statute” by virtue of which law was administered by the Exchequer
Court on its admiralty side. If therefore there was a deficient incorporation
of admiralty law by the Act of 1934, the same cannot be said of the Act of
1891.
He went on to pose two further questions in
these terms:
Two questions, therefore, remain. The first
is whether a claim of the kind made here was within the scope of admiralty law
as it was incorporated into the law of Canada in 1891. If so, the second
question is whether such a claim fell within the scope of federal power in
relation to navigation and shipping.
He held that the claim made in Tropwood, “damage
to incoming cargo”, had been brought into the admiralty jurisdiction of the
Exchequer Court of Canada by The Admiralty Act, 1891, 1891 (Can.), c.
29, and that as a result such a claim, pursuant to s. 2 of the Federal
Court Act, would be subject to Canadian maritime law under the jurisdiction
of the Federal Court of Canada pursuant to s. 22(1) and certain paragraphs
of s. 22(2) of the said Act. He held as well that the claim
[Page 377]
would also fall under federal legislative
competence under s. 91.10 of the British North America Act.
Turning to the case at bar, the claim against
Wire Rope by Yorke alleges negligence in the resocketing of the main towing
cable pursuant to a contract made regarding such work, and claims an indemnity
for loss caused by a breach of that contract. The claim by B.C. Marine and Straits
involves negligence in the resocketing operation which resulted in their loss.
It will be observed that the root of both claims lies in the work done by Wire
Rope in resocketing the cable and that the cable was part of the equipment of
the tug Lorne Yorke, a seagoing vessel which was involved in the marine
accident that gave rise to this action. That such a claim formed part of
admiralty law which was incorporated into Canadian law by the Canadian Admiralty
Act of 1891 seems clear. That Act constituted the Exchequer Court of Canada
a Colonial Court of Admiralty, conferring on it all the jurisdiction given in
that Act pursuant to the British Colonial Courts of Admiralty Act, 1890, 1890
(U.K.), c. 27. The jurisdiction of the British High Court of Admiralty was
therefore vested in the Exchequer Court of Canada. That jurisdiction was
formed, in part, by another English Act, An Act to improve the Practice and
extend the Jurisdiction of the High Court of Admiralty of England, 1840
(U.K.), c. 65. Section 6 of that last-named Act provided:
VI. And be it enacted, That the High Court
of Admiralty shall have Jurisdiction to decide all Claims and Demands
whatsoever in the Nature of Salvage for Services rendered to or Damage received
by any Ship or Sea-going Vessel, or in the Nature of Towage, or for Necessaries
supplied to any Foreign Ship or Sea-going Vessel, and to enforce the Payment
thereof, whether such Ship or Vessel may have been within the Body of a County,
or upon the High Seas, at the Time when the Services were rendered or Damage
received, or Necessaries furnished, in respect of which such Claim is made.
[Page 378]
It is my opinion that this section is
sufficiently broad to comprehend the claims made against Wire Rope in the case
at bar.
The Canadian Admiralty Act of 1891
provided in sections 3 and 4:
3. In
pursuance of the powers given by “The Colonial Courts of Admiralty Act, 1890”,
aforesaid, or otherwise in any manner vested in the Parliament of Canada, it is
enacted and declared that the Exchequer Court of Canada is and shall be, within
Canada, a Colonial Court of Admiralty, and as a Court of Admiralty shall,
within Canada, have and exercise all the jurisdiction, powers and authority
conferred by the said Act and by this Act.
4. Such
jurisdiction, powers and authority shall be exercisable and exercised by the
Exchequer Court throughout Canada, and the waters thereof, whether tidal or
non-tidal, or naturally navigable or artificially made so, and all persons
shall, as well in such parts of Canada as have heretofore been beyond the reach
of the process of any Vice‑Admiralty court, as elsewhere therein, have
all rights and remedies in all matters, (including cases of contract and tort
and proceedings in rem and in personam), arising out of or
connected with navigation, shipping, trade or commerce, which may be had or
enforced in any Colonial Court of Admiralty under “The Colonial Courts of
Admiralty Act, 1890.”
This jurisdiction was carried forward by The
Admiralty Act, 1934, 1934 (Can.), c. 31, and passed into the purview of the
Federal Court by the Federal Court Act in its definition of maritime law
in s. 2 and by the terms of s. 42 of that Act.
42. Canadian
maritime law as it was immediately before the 1st day of June 1971 continues
subject to such changes therein as may be made by this or any other Act.
Section 22(1) gives a general statement of
jurisdiction, and s. 22(2)(m) and (n) reproduced hereunder
are apt to cover the claims in question here and in part are a restatement of
the jurisdiction of the British Admiralty Courts contained in s. 6 of the
1840 Statute cited above:
(m) any claim in respect of
goods, materials or services wherever supplied to a ship for her operation or
maintenance including, without restricting the gener-
[Page 379]
ality of the foregoing, claims in respect
of stevedoring and lighterage;
(n) any claim arising out of
a contract relating to the construction, repair or equipping of a ship;
I am therefore of the view that the claims made
against Wire Rope come within Canadian maritime law as defined in the Federal
Court Act. There can be no doubt in my mind that the substantive law
relating to these claims falls within federal legislative competence under
s. 91.10 of the British North America Act, being in relation to
navigation and shipping. There is therefore law of Canada relating to the
issues arising in this case upon which the jurisdiction of the Federal Court
may operate. In my opinion, it is of no significance that the claim made by
Yorke is a claim for indemnity. Claims for indemnity and third party actions,
generally, are not mere incidents to the principal action. They are independent
actions which stand upon their own feet. On this point I refer to the Fuller
case, supra, where Pigeon J. referred to Bank of Montreal v.
Royal Bank of Canada, at
pp. 315-6, where Duff C.J.C. said:
… The Supreme Court of Ontario has
jurisdiction, by virtue of the statutes and rules by which it is governed, to
entertain and dispose of claims in what are known as third party proceedings.
Claims for indemnity, for example, from a third party, by a defendant in
respect of the claim in the principal action against him, can be preferred and
dealt with in the principal action. But there can be no doubt that the
proceeding against the third party is a substantive proceeding and not a mere
incident of the principal action.
The Fuller case, in my view, is
distinguishable. In that case Foundation Company of Canada, Ltd., a building
contractor, brought action against the Crown for a breach of contract relating
to damage caused by blasting operations which had been performed by another
contractor, Thomas Fuller Construction Co. (1958) Limited. There was no doubt
that the Crown had been properly impleaded in the Federal Court which had full
jurisdiction to hear the plaintiff’s claim against the
[Page 380]
Crown. The Crown then issued a third party
notice claiming indemnity against the Fuller company. In so doing, it relied
specifically upon the law of Ontario to support a claim based on negligence.
This Court held, as did the Federal Court of Appeal and the Trial Division,
that there was no law of Canada to support the jurisdiction of the Court in
respect of that particular third party claim. In this respect, the case differs
from the case at bar, lacking the essential element of a law of Canada to feed
the jurisdiction of the Federal Court. I am satisfied that the Federal Court
had jurisdiction to entertain not only the claims made by B.C. Marine and
Straits against Yorke, but also the third party claims made by Yorke against
Wire Rope and the direct claims made by B.C. Marine and Straits.
I now turn to the question of the liability of
Wire Rope in this matter. It will be seen at once that the only connection Wire
Rope had with the matters raised in these proceedings resulted from the
resocketing which was done for Yorke on October 13, 1967. Whether the claims
against Wire Rope sound in contract or tort, and whether they are for direct
relief or indemnity, the basis for any liability upon Wire Rope must remain the
same. For success against Wire Rope it must be shown that its work on the
socket caused or contributed to its failure, leading to the loss of the barge.
For this reason the socketing operation must be examined.
On October 13, 1967 two workmen employed by Wire
Rope came to the premises of Yorke to do some resocketing at the request of
Yorke. Mr. J. C. Yahemech, marine superintendent for Yorke, gave them
three or four socketed towlines, the precise number is not clear, and
instructed them to remove the sockets and resocket the lines using the same
sockets which were then on the lines. One of the lines involved was the line
which failed in this accident. Mr. Yahemech left them to their task. He
returned some hours later when the job was nearly completed. The whole operation
took six hours. The cost to Yorke was in the neighbourhood
[Page 381]
of ninety dollars. When it was completed the
cables, including the one used to tow the Westport Straits on the
occasion of its loss, were left in the possession of Yorke and Wire Rope had no
further part in the matter.
It was alleged that Wire Rope, for a period of
something in excess of three years, had done all the resocketing for Yorke.
This was not denied and both the trial judge and the Court of Appeal accepted
this fact and spoke of an indefinite number of resocketings. It may be observed
at this point that the only negligent resocketing alleged against Wire Rope was
that of October 13, 1967 and, whatever the evidence of previous resocketings
may have been in general terms, there was no evidence of any indefinite number
of resocketings of this particular socket. The significance of this fact will
be dealt with later.
A review of the evidence of certain of the
expert metallurgists who were called by the various parties must now be made.
Mr. Ian Heslop, a consulting engineer called by B.C. Marine and Straits,
who has specialized in metallurgical engineering, served as a senior
metallurgical engineer in industry, and has been called as an expert witness on
metallurgical matters in many courts, gave evidence of having examined the
socket. He found it to have numerous casting defects (shrinkage cavities and
blow-holes); a brittle microstructure, whereas properly treated material would
be tough and ductile; and considerable wear. He gave his opinion that the
brittleness was the most significant cause of the failure, making the socket
likely to fail under “shock, impact or bending loads of relatively small
magnitude”. He felt that the socket had been heated above 650° F. and that this
had rendered the metal weak and brittle and that this was the result of
resocketing. He said that this particular metal should stretch before failing
and it had not done so in this accident because of its brittleness. In his
view, properly treated material would have a higher breaking point and
cumulative damage would result from continued reheatings without proper reheat
and quenching treatment.
Another expert, called by Wire Rope, James
Pearce McCulloch, a professional engineer with
[Page 382]
high qualifications in metallurgical engineering
and with broad experience in that field, gave evidence of various tests which
he had made and experiments he had performed on manganese steel in an effort to
determine the cause of the failure of the socket in question.
In one experiment Mr. McCulloch fractured a
manganese steel socket which had been resocketed numerous times and found a
smoother fracture, with only minor porosity, than that found in the failed
socket. He then heated the test socket to 900° F. and maintained it at that
temperature for one and one-half hours. He had already performed tests from
which he concluded that a resocketing operation would take about sixteen
minutes—other evidence put the time at twenty to twenty-five minutes. The time
and temperature exposure of the socket in this test was therefore substantially
greater than in a resocketing. He found again a smoother fracture than that
found in the failed socket and concluded that even severe heating would not
produce the rough, porous, surface found in the failed socket which, he
considered, had been the cause of the failure.
In yet a further test, he heated a manganese
steel socket to 1,950° F. for one-half hour with water quenching, leading to
the production of a sample of manganese steel of as high a quality as
commercially possible. He heated one sample of this steel to 800° F. for an
hour, another to 900° F. for one and one-half hours, and another to 1,000° F.
for one and one-half hours. He then took micro-photographs of each. He found
the more severe the heating the more carbide precipitation appeared, but it was
of a different type than that found in the failed socket. Finally, he took
another sample of steel and heated it to 1,550° F. for two hours. This
temperature was too low for proper heat treating in the production of manganese
steel. This steel, on cooling, produced a micro-structure similar to that in
the failed socket. From this and other tests, Mr. McCulloch concluded that
the embrittlement found in the failed socket was the result not of resocketing
but of improper heat treatment at the time of manufacture. Other expert
witnesses were called, among them one T.
[Page 383]
H. Williams who generally reached conclusions
similar to that of McCulloch. The most helpful evidence, in my view, was that
of Heslop and McCulloch.
Upon this and other evidence the trial judge
seems to have concluded that the socket had become embrittled and that the
embrittlement caused it to fail. He concluded as well that the socketing
operation of October 13, 1967 had not caused the defect. His words on this
point have been reproduced above.
In the Court of Appeal Ryan J., speaking for the
Court and holding that Wire Rope was liable, said:
I am satisfied that the loss of the barge
was caused by the breaking of the defective socket, and that the break was
caused by the brittleness of the socket. I also accept the trial judge’s
finding that the brittleness, to the extent there was brittleness, was caused
by the various re-socketings to which the socket had been subjected. He also
found that there had been an indefinite number of resocketings.
and later:
I am of opinion that Wire Rope was in
breach of its contract with F.M. Yorke. The trial judge found, and I, of
course, accept his finding, that Wire Rope, through its servants, did not, by
the re-socketing on October 13, 1967, cause the socket to become embrittled to
any significant extent.
As is evident from a review of the expert
evidence very briefly summarized above, there was evidence upon which the trial
judge could find, as he did, that the resocketing on October 13, 1967 did not
significantly embrittle the socket and cause its failure. The Court of Appeal
accepted this finding and I am of the opinion that it should remain
undisturbed. Both the trial judge and the Court of Appeal, however, seem to
have been of the opinion that the socket failed because it had been rendered
defective as a result of an indefinite number of past resocketings. Leaving
aside the fact that the only occasion of resocketing pleaded against Wire Rope
was that of October 13, 1967, I am of the opinion that any finding of fact that
the defect in the socket was the result of an indefinite number of past
resocketings cannot be sustained
[Page 384]
for the reason that there was no evidence adduced
of any such “indefinite number of past resocketings” relating to this socket. A
trial judge’s finding based on evidence should not be rejected by an appellate
court unless he has applied some incorrect principle, or made a palpable error.
A finding made without evidence, however, cannot be sustained. Yahemech, who
gave the instructions for the resocketing, produced such records as he had and
said a new socket had been put on the line on September 20, 1966. He said that
‘new’ could mean new from the factory or a used socket from the company’s
stock. He did not know which. If the socket had been new from the factory on
September 20, 1966, then it had been socketed on that occasion and resocketed
on October 13, 1967. There was no evidence of any intervening resocketing and
the records produced by Mr. Yahemech, while sparse, indicated that no more
had occurred. If it were new only in the sense that it came from the stock of
used sockets belonging to the company, then it would have been socketed on
September 20, 1966 and resocketed on October 13, 1967. Doubtless—if it had been
used before—it would have been socketed at least on one previous occasion.
Yorke bore the burden of proof on this issue. Put at its highest, and accepting
the evidence of Yahemech, the socket was socketed once and resocketed once. It
may have been socketed once and resocketed twice; and it may, as well, have
been resocketed more often. The only affirmative evidence, however, discloses
no more than one socketing and one resocketing. All other possible operations
remain in the realm of pure speculation and provide no evidence to support such
a significant finding. It should also be observed that the expert evidence
indicated that damage of the sort alleged here would be cumulative as a result of
repeated heating and cooling and would require more of such operations than are
revealed in the evidence. The totality of the evidence on this point came from
Yahemech and extracts from his evidence at trial appear below:
[Page 385]
THE COURT: Let’s confine it to Exhibit 13
because that is what is relevant. Can you tell from that where the sockets came
from?
A. No, I can’t tell.
MR. MERRITT: Q. You can’t say, however,
that you didn’t supply the sockets on every occasion?
A. No, I can’t.
THE COURT: Just on this point, does that
indicate how many times this particular socket, Exhibit 3, had been resocketed?
A. No, your honour.
Q. Well, it says resocketing on two or
three occasions but maybe I am not reading it correctly. It says resocketed
October the 19th, ‘65, resocketed 1st June of 1966. Resocketed September 26th,
‘67. Inspection tags, is that it—September the 1st, ‘67. Resocketed October the
13th, ‘67. What do all those notations mean in that?
A. They would be times that that particular
socket would have been taken off and reinstalled. There was no way of knowing
whether that socket after it had been cut off that portion of the line would
have been put directly on that portion of the line. If they cut three sockets
out and cleaned them out and then went to put them back they wouldn’t
necessarily go back on—I have no way of knowing that they went back on—
THE COURT: This was referring to a socket,
a particular socket on Exhibit 13, is it not?
A. It refers that that is the location of
the socket but whether the socketing crew cut the socket off of say the one
next to the towline and then reinstalled it on the end of the pennant, I would
have no way of knowing. They were done as a group.
THE COURT: What good is a record if it
isn’t referring to a particular socket. Isn’t that the purpose of that?
A. The record was basically referring to
the resocketing, that it had been resocketed on the line in that location.
Q. But there is no record of whether,
Exhibit 3, let’s talk about it, was resocketed three or four—four times during
the period October the 19th to the 13th of October, 1967?
A. No, the sockets as such were not—
Q. Is there any way you can tell on any of
your records whether Exhibit 3 was resocketed before?
[Page 386]
A. No, there is no way I can tell for certain.
Q. Do you know how many times it had been
resocketed?
A. No, I do not.
Q. Do you know how old it is?
A. No, I do not.
Q. Does it look old to you?
A. It looks the way all sockets look when
they are placed in use for a short time.
Q. From your experience would you say it
had been resocketed a number of times prior to the 13th of October 1967?
A. I could only guess, I would assume it
had.
Q. Well, from your experience, you are not
an amateur like the rest of us.
A. I couldn’t say, my lord, how many times
it had been resocketed.
Q. But it was done more than once?
A. I would say yes, more than once.
Q. You have no record to tell you how many
times?
A. No.
MR. MERRITT: My lord, may I just follow up
on that a bit.
Q. So that Exhibit 13 indicates when an operation
of resocketing or inspection was done but it gives no indication at all as to
the history of any particular socket, right?
A. Yes.
Q. The answer is it gives no such
indication?
A. Yes.
Q. Now, in fact in answer to his lordship
you said you thought that it had been resocketed before but I think you don’t
hold yourself out as an expert in that field, do you?
A. Resocketing, no.
Q. Or in identifying the results of
resocketing?
A. No.
Q. It may only have been resocketed once
before for all you know.
A. Yes.
and later:
THE COURT: I thought you said before you
didn’t know whether that had been done by you, been
[Page 387]
done by Wire Rope before or at all,
resocketed before by Wire Rope or at all. I think Mr. Merritt finally
asked you a question, you weren’t sure whether it had been done once or more
than once or at all.
A. I thought I had said that it looked as
though it had been done more than once. I couldn’t say for certain.
THE COURT: Or by whom? What is the correct
answer anyway? Do you know whether Exhibit 3 first of all had been resocketed
before the 13th of October 1967?
A. I can’t say for a certainty.
Q. And it follows that you don’t know
whether Wire Rope socketed it, that is the end of the answer.
MR. FORBES: Well, in fact though didn’t
Wire Rope, that is Wire Rope Industries of Canada (1966) Ltd. do all your
resocketing of the towlines while you were there?
A. Yes.
THE COURT: Well, the answer he had given
just a minute ago was that Wire Rope had resocketed these same sockets before.
Now he says “I don’t know whether this Exhibit 3 had been resocketed before, at
all or not.” Now, two answers can’t hang together, can they?
MR. FORBES: He is not my witness, my lord.
THE COURT: NO, I know. I just want to know
what the correct answer is, or do you know? The correct answer is you don’t
know whether it has been resocketed before or not?
A. There is no identifying marks on it, my
lord, so I can’t say for certainty.
THE COURT: The only thing you know is that
at the time Wire Rope did your resocketing work in the main, is that a fair
statement?
A. Yes. Perhaps I could clarify to the
court some of the procedure involved. The reason I am uncertain is that we
would take a socket to Wire Rope Industries and say, when we order a new line,
would you put this socket on the towline. I would not be present when the
towline was resocketed. I would assume that they would have taken the same
socket. I would have no way of knowing whether they had used the socket we had
actually given them or not.
[Page 388]
Q. Well, let’s just confine it to Exhibit
3. The answer is you don’t know whether that has been resocket-ed before or
not?
A. No.
Accepting, as I have done, that the resocketing
operation of October 13, 1967 did not cause the failure of the socket and that
no indefinite number of past resocketings has been shown, the question arises:
What then did cause the failure? While it is not necessary to consider this
question in order to dispose of the issue of Wire Rope’s liability, an answer
is required in considering the position of Yorke vis-à-vis B.C. Marine and
Straits in order to determine whether or not Yorke exercised due diligence in
furnishing a seaworthy tug in accordance with its contract of towage.
The conclusion that the socket was defective is,
in my opinion, inescapable. The mere failure in use would not necessarily
establish that fact, but it must be observed here that a sound manganese steel
socket is the strongest part of a towline of this nature and therefore should
not be the first part to fail. The line itself, when subjected to excessive
strain, is expected to fail before the socket. It may well be that in this case
unusual and heavy strains were imposed on the socket, but it failed before the
line, which remained intact. Such failure is strong evidence of a defect,
particularly when the evidence also indicated that it was not the socket itself
which was snagged on the bottom, but a part of the line in the vicinity of the
socket.
A review of the evidence of Mr. McCulloch
indicates that the socket was defective because of improper heating and cooling
in its original manufacture. This evidence received some support in the
evidence of Mr. Heslop, who found and described casting defects in the
socket which would also be attributable to its original manufacture. Mr. Heslop
mentioned that on examination the socket showed signs of substantial wear, but
he did not consider that such wear was a significant factor in its failure. I
am of the opinion that this socket failed in use because it was defective from
the time of its manufacture due to improper treatment in
[Page 389]
the manufacturing process. In this, I am
accepting the evidence of Mr. McCulloch supported to some extent by
Mr. Heslop. In my view, the fair conclusion on the evidence is that the
most probable cause of porosity and embrittlement which caused the failure was
improper heat treating in manufacture. The appeals of Wire Rope, therefore,
must be allowed.
It now falls to consider the liability of Yorke
in the main action brought by B.C. Marine and Straits. Yorke had entered into a
contract of towage with Straits. This contract was evidenced in writing in the
form of a letter from Yorke to Straits, which provided:
January
24th, 1968.
Mr. Nick Malysh,
Straits Towing Limited,
2215 Commissioner Street,
Vancouver 6, B.C.
Dear Nick:
Confirming our recent telephone
conversation we are pleased to charter you our “Lone Yorke” for barge towing
under the following conditions:
1. The rate to be $684.00 per day.
2. Your firm to supply, employ, and pay for
the Mate on the vessel.
3. That Yorke be held harmless by Straits
in connection with any claim or damage arising out of any advice or
instructions received from your Mate.
4. The Standard Towing Conditions of the
B.C. Tugboat Owners’ Association to apply.
5. The Home Trade Class III certificate
shall govern her area of charter.
6. Charges by crew personnel because of
performing Duties other than an Officer or Unlicensed Personnel are for the
account of Straits.
7. Navigation overtime is for the account
of Yorke unless such amount is excessive and inevitable on the type of towing
that is being performed.
[Page 390]
Yours
very truly,
F.M.YORKE
& SON LIMITED
“Walter Nezil”
Walter
Nezil
Chief Despatcher
The standard towing conditions of the B.C.
Tugboat Owners’ Association made applicable to this contract by paragraph 4 of
the contractual letter were contained in Exhibit 23, a rate book of the
Association. For the purposes of this case the significant term is expressed in
these words:
It is a term of all towing contracts, written
or verbal, that (providing the tugboat owner uses due diligence to make and
keep the tugboat seaworthy) the towboat owner, its servants or agents are not
to be liable for loss or damage to the tow or its contents, howsoever caused.
Yorke will be liable then to B.C. Marine or
Straits only if the Lorne Yorke, because of a failure by Yorke to
exercise due diligence, was not seaworthy when it set out upon the voyage which
led to the accident and if the loss was caused by the lack of seaworthiness.
This proposition was accepted by B.C. Marine and
Straits as the following extract from their factum in this Court shows.
Paragraph 1 on page 18 of the factum provides:
1. The Federal Court of Appeal and the
learned Trial Judge did not err in finding that the Appellant F.M. Yorke &
Son Limited was liable to the Respondent Straits Towing Ltd. for breach of its
contract with the Respondent Straits, by failing to exercise due diligence to
make and keep the tug “LORNE YORKE” seaworthy.
and on page 19, in paragraph 3, the following
appears:
3. The liability of F.M. Yorke & Son
Limited to Straits Towing Ltd. for breach of its contractual obligations with
respect to the seaworthiness of the tug “LORNE YORKE” and its towing gear is
for damages in the amount of the value of the lost barge “WESTPORT STRAITS”,
and any supposed ambiguity in the judgments below on this point should be
resolved.
[Page 391]
It should also be noted that before this Court
counsel for B.C. Marine and Straits disclaimed any assertion of negligence in seamanship
and navigation and placed its whole case against Yorke on an alleged failure to
use due diligence in providing a seaworthy tug.
The failure alleged against Yorke is that it
suffered Wire Rope to mistreat the manganese steel socket in the resocketing
procedure on October 13, 1967. This, it is said, weakened the socket and
rendered the tug unseaworthy and finally caused the loss. The burden of proving
due diligence rested upon Yorke. This burden could not be discharged by merely
showing that it contracted out certain necessary work to an independent
contractor, however reliable and skilled it may have been. Yorke, it was
argued, instructed or permitted Wire Rope, on October 13, 1967 when the
resocketing was done, to put back upon the towline a used socket. In doing so,
it knew or ought to have known that the socket had been used and was worn, that
it had been resocketed in the past, and that because of alleged repeated
heating the socket had become, or might well have become, damaged. The exercise
of due diligence would have required more in this matter, including the use of
a new socket which, according to the evidence, would have cost sixteen dollars.
As I have already indicated, the case against
Wire Rope has failed, Yorke not having shown that Wire Rope rendered the socket
defective in the resocketing operation. This fact, however, is not decisive in
favour of Yorke in its defence against the claims of B.C. Marine and Straits.
Against Wire Rope, Yorke bore the burden of proving negligence. This it failed
to do. As against B.C. Marine and Straits, however, it must show due diligence
in making the tugboat seaworthy and the fact that Wire Rope has been exonerated
does not by itself relieve Yorke, for the evidence shows that whatever may have
been the cause the socket was defective and, in the circumstances of this case,
its use rendered the Lorne Yorke unseaworthy.
[Page 392]
The Carriage of Goods by Water Act, R.S.C.
1970, c. C-15, and the Hague Rules do not apply to this case. However,
the principles enunciated in the many cases decided under the Act and the Rules
dealing with the obligation of a shipowner to exercise due diligence to make
his vessel seaworthy and the consequences of a failure to do so are clearly
applicable to the case at bar because of the contractual provision referred to
above. The similarity in the obligations assumed by Yorke and those set out in
the Carriage of Goods by Water Act and the Hague Rules may be
shown by a reference to Article III of the Schedule to the Act, which is virtually
identical to the provisions of the Hague Rules:
Article III
Responsibilities
and Liabilities
1. The carrier shall be bound, before and
at the beginning of the voyage, to exercise due diligence to,
(a) make the ship seaworthy;
Generally, the obligation of a tugboat owner
upon entering into a contract of towage is expressed in Halsbury’s Laws of
England, 3rd ed., vol. 35, at p. 589, para. 869:
In an ordinary contract of towage the owner
of the tug contracts that the tug shall be efficient for the purpose for which
she is employed, and that her crew, tackle and equipment shall be equal to the
work to be accomplished, in the weather and under the circumstances reasonably
to be expected. There is a warranty implied in such a contract that at the
outset the crew, tackle and equipment are equal to the work to be accomplished
in circumstances reasonably to be expected, and there is an implied obligation
that thereafter competence skill and best endeavours shall be used in doing the
work.
In the case at bar, however, the inclusion in
the towage contract of the provisions excerpted above replaced any implied
warranty in this respect and protects Yorke from failures in this regard and
from liability for damage, however caused, where
[Page 393]
it can show that it has exercised due diligence
to make the tugboat seaworthy.
The concepts of due diligence and seaworthiness
have been discussed in many cases. The leading case on the subject in this
Court is Charles Good-fellow Lumber Sales Limited v. Borromée Verreault, Captain
Fernand Hovington and Verreault Navigation Inc. While this was a case in which the Carriage
of Goods by Water Act applied, the reasoning employed by Ritchie J., who
wrote the judgment of the Court, is applicable to the construction of the
contractual provision in issue here. At pp. 535-6, he said:
In this regard the first question to be
determined is whether or not the evidence discloses that the Claudette V was
unseaworthy.
The test of seaworthiness most frequently
adopted is to be found in the judgment of Lord Herschell in Gilroy Sons
& Co. v. Price & Co., where he said:
That the ship should be in a condition to
encounter whatever perils of the sea a ship of that kind, and laden in that
way, may be fairly expected to encounter in crossing the Atlantic, or in
performing whatever is the voyage to be performed.
He found the ship in that case was unseaworthy
and then went on to consider, at pp. 540-1, the question of due diligence. He
said:
Where the ship is found to have been
unseaworthy the ship owner is seized with the burden of proving that he
exercised due diligence to make her so, if he is to escape liability. When the Maxine
Footwear case, supra, was heard in this Court, a dissenting judgment
was delivered by Mr. Justice Cartwright (as he then was). The dissenting
reasons for judgment were affirmed in the Privy Council and in the course of
them Mr. Justice Cartwright adopted the following definition of the due
diligence required by art. III, Rule 1:
‘Due diligence’ seems to be equivalent to
reasonable diligence, having regard to the circumstances known, or fairly to be
expected, and to the nature of the voyage, and the cargo to be carried. It will
suffice to satisfy the condition if such diligence has been exercised down to
the sailing from the loading port. But
[Page 394]
the fitness of the ship at that time must
be considered with reference to the cargo, and to the intended course of the
voyage, and the burden is upon the shipowner to establish that there has been
diligence to make her fit.
It is not enough to satisfy the condition
that the shipowner has been personally diligent, as by employing competent men
to do the work. The condition requires that diligence to make her fit shall, in
fact, have been exercised, by the shipowner himself, or by those whom he
employs for the purpose. The shipowner ‘is responsible for any shortcoming of
his agents or subordinates in making the steamer seaworthy at commencement of
the voyage for the transportation of the particular cargo.’ (Per Brown
Dist. J. in The Frey (1899), 92 F. 667).
‘The obligation to make a ship seaworthy is
personal to the owners, whether or not they entrust the performance of that
obligation to experts, servants or agents.’ (Per Lord Wright in Northumbrian
Shipping Company Limited v. E. Timm and Son, Limited, [1939] A.C. 397 at
403, [1939] 2 All E.R. 648). If such experts, servants or agents fail to
exercise due diligence to make her seaworthy the owners are liable under Art.
III, r. 1 of the Rules.
The burden of proving the exercise of due diligence
which is placed upon the carrier under the provisions of art. IV(1) can
only be discharged by affirmative proof that due diligence was exercised to
make the ship seaworthy.
The Goodfellow case and the authorities
cited in it conveniently state the law upon this question and, in addition,
several other cases of high authority have declared and illustrated the
principles involved. They include Maxine Footwear Company Ltd. et al. v.
Canadian Government Merchant Marine Ltd.,
in which see particularly dissenting reasons of Cartwright J. later affirmed in
the Privy Council; Western Canada Steamship Company Limited v. Canadian
Commercial Corporation and Others,
Riverstone Meat Co. Pty. Ltd. v. Lancashire Shipping Co. Ltd., (“Muncaster
[Page 395]
Castle”); Toronto
Elevators Limited v. Colonial Steamship Limited; Robin Hood Flour Mills Limited v. N.M.
Paterson & Sons Limited.
The rules which may be derived from these and
other cases dealing with this point may be summarized in this manner in so far
as they relate to the case at bar. Yorke, as the tugboat owner, was bound both
at common law and by the terms of the contract to put the tugboat in seaworthy
condition at the commencement of the voyage. In the event of damage being
caused to the tow or its contents during the voyage by reason of the
unseaworthiness of the tug, Yorke could escape liability only by proving that
it had exercised due diligence to make the tug seaworthy. In the facts of this
case the exercise of due diligence could not be proved by reference to the fact
that Yorke had contracted out work, in connection with the towing line which
failed, to a reputable and experienced contractor. The burden upon Yorke in the
case at bar would extend to showing in the facts of this case that the failure
of the socket was caused by a latent defect, that is a defect which would not
be discernible upon reasonable examination.
As Ritchie J. said in the first passage from the
Goodfellow case quoted above, the first question to be resolved is
whether on the occasion in question the Lorne Yorke was unseaworthy. Was
she in a condition to encounter whatever perils of the sea a tugboat with a tow
such as she had could be fairly expected to encounter in the voyage that she
had embarked upon? It would appear from the totality of the evidence that on
the disastrous voyage the Lorne Yorke did not encounter in the waters on
the outer coast of Vancouver Island any perils or hazards which were beyond
normal and reasonable expectation. Bad weather is common, particularly at that
time of the year, and the weather on the occasion of the accident, while bad,
was not abnormally so and evidence was given of safe passages
[Page 396]
being made without loss in like conditions
through the entrance to Kyuquot Channel. The dragging of towlines, intentional
or accidental, is not a rare occurrence in these waters and the snagging of
towlines on obstructions on the bottom is a hazard which must be expected and
encountered in Kyuquot Channel. Despite these facts the socket failed, and as a
direct consequence the Westport Straits was lost. There was evidence
that in such a situation the socket would be subjected to a variety of stresses
and strains but no evidence as to their actual nature, force, or effect. There
was no evidence of the maximum strain which the socket could have resisted, or
should have been capable of resisting, save for the unquestioned evidence that
the normal expectation when a towline is put under excessive strain is that the
line itself will fail before the socket. In this case then the failure of the
socket while the line remained intact would lead to the conclusion that the
socket was the weaker part of the gear, rather than the stronger as it ought to
have been. There was evidence that the tugboat master in his efforts to free
the line imposed the strain of full power on the line, and evidence that could
be said to provide some suggestion of negligence in the manner of entry by the
tug into the mouth of the channel. This evidence however, in my view, could not
indicate that faulty navigation or seamanship was causative of the loss. It is
impossible for us to speculate as to what might have occurred if the socket had
not failed and the line had been freed. What did occur was the failure of the
socket when it ought to have withstood the strain, as did the other parts of
the cable, enabling the cable to be freed and the voyage continued. In my view,
the failure of the socket in these circumstances was due to a fault or defect.
This accords with the finding, both in the Trial Court and the Court of Appeal,
and leads to the conclusion that the towing gear, and hence the tugboat, at the
commencement of the voyage were not seaworthy. I part company with the judges
at trial and appeal only as to the cause of the defect.
[Page 397]
It follows from the foregoing that Yorke, as
owner of the tug, would be liable for the damage suffered by the owners of the Westport
Straits unless it is shown, the burden of proof being upon Yorke, that it
exercised due diligence to make the Lorne Yorke seaworthy at the
commencement of the voyage. The question then is—can it be shown that the
exercise of due diligence would not have revealed the defect in the socket
which caused the loss?
It was clear from the evidence of the experts
that the defect, however caused, was not apparent on ordinary visual
examination. To discover the defect the expert witnesses required complicated
testing and photographic procedures beyond the capacity of those ordinarily
concerned with the use of such equipment. By the standard of even careful
visual examination then the defect was latent. While as a general rule it may
be said that a latent defect is one not ascertainable on adequate examination,
it is not in every case that a defect, which is not apparent, will be considered
latent. Cases differ and there may be circumstances from time to time which
would dictate more than mere superficial investigation before one would be
enabled to set up the plea of latent defect. Such a case was Scottish
Metropolitan Assurance Company, Limited v. Canada Steamship Lines, Limited, where Anglin C.J.C., speaking for
the majority of the Court, dealt with a case where a threaded iron bolt which
had been in a bent condition, to the knowledge of the shipowner’s servants and
employees for several months, broke and caused damage. He said, at pp. 277-8:
There is a mass of testimony not, it is
true, uncontradicted, but in our view of great weight and cogency, that the
presence of the bend or curve in the bolt afforded a distinct and obvious
warning of its weakened condition, which should not have been neglected. We,
therefore, find it impossible to assent to the conclusion that the defendant’s
employees “exercised due diligence” to make the Hamilton seaworthy.
Either their inspection of the steering gear was of such a casual and
perfunctory character that they failed to discover the bend or curve, or,
having noticed it, they failed to
[Page 398]
discharge the plain duty of either
replacing the defective bolt or of making it fit for use, if that were possible.
That the bolt broke is only what must sooner or later have occurred, and what
should have been expected. The power of resistance of the metal having been
much reduced was eventually overcome, it may be by having some slight
additional stress or strain put upon it. To speak of such a defect as “latent”
seems to involve a misuse of that term. We do not find it necessary for the
present further to define “latent defect”. “Not discernible by adequate
inspection” seems not an inapt paraphrase.
In somewhat similar vein are the words of Atkin
L.J. in The “Dimitrios N. Rallias”
at pp. 366‑7 where excessive rusting had cracked rivets in a ship’s
hull thereby admitting water which damaged a cargo:
Under these circumstances it appears to me
perfectly impossible to say that the defect was a latent defect. The Judge has
so found; and it is necessary to inquire shortly what is the meaning of a
latent defect. I suppose normally speaking it means some defect that lies hid
as opposed to a defect that lies open. But it is suggested that it is not every
defect that cannot be perceived by touch or sight or hearing exercised with the
most minute examination or observation that is latent; and I can believe that
when the word is used with reference to. defects in a ship’s hull and machinery
it may not be capable of the very extreme meaning that they cannot be perceived
by the most accurate and refined perception. It was suggested to us that the
definition contained in a work of authority, Carver, gathered from American decisions,
is a better statement of what is meant by latent defect. That definition is:—
A defect which could not be discovered by a
person of competent skill and using ordinary care.
In this case I do not think it necessary to
say whether that is the true and precise definition of latent defect which
would meet every case. But I am prepared to say this, that a defect which does
not comply at any rate with these words could not be a latent defect; and I
think it is important in bearing in mind the effect of these words, to remember
that the phrase is, “which could not be discovered,” not which would not be
discovered or which might not be discovered. If these words were used it would
appear that there would be no difference between the test of what was a latent
defect
[Page 399]
and the test of whether the persons
responsible had been negligent or not; and I am quite clear that negligence is
not a test of latency.
In this case it is impossible to say this
defect could not have been discovered by persons of ordinary skill. One has
only to visualise what is meant by a degree of rust of 5-16 in. existing by the
side of the opening between the flange of the frame and the side plate, an
interstice into which a man could place his finger, to make it impossible to
suggest that this defect was a latent defect. It seems to me to have been a
latent defect to anyone looking out for rust.
In the case at bar, at least to a stranger, the
defect causing the failure was clearly ‘latent’. It is argued, however, that
Yorke was not a stranger in these matters. Yorke was a company which used
sockets regularly and according to the evidence knew, or ought to have known,
through their marine superintendent, Yahemech, his predecessor, and from
literature in their possession, that there was a potential for danger in the
resocketing of manganese steel sockets. Further, it was said, that a failure to
heed that danger by continuing the re-use of sockets was not consistent with
the exercise of due diligence, and the knowledge so possessed by Yorke should
have served to warn that the practice of resocketing used sockets ought to have
been abandoned. Yahemech admitted that he did not know if the socket was new or
used when put on the cable on September 20, 1966. Can it be said that, armed
with knowledge of the potential dangers involved in resocketing manganese steel
sockets, such apparent indifference, both in selecting a socket and keeping
records regarding its use, amounted to the exercise of due diligence? Can it be
said that this defect was latent, or is this a case where the knowledge
attributable to Yorke of the properties of manganese steel played the role of
the ‘bent bolt’ in the Scottish Metropolitan Assurance Company case, or
the role of the ‘deposits of rust’ in the case of The “Dimitrios N.
Rallias”, indicating a problem and robbing the defect of its latent
character?
In my opinion, after considering all the
evidence I conclude that the claim by Yorke that the defect was latent is
well-founded. There was evidence that manganese steel sockets could be safely
[Page 400]
resocketed and the practice of the re-use of
sockets after resocketing had been followed regularly by Yorke and other towing
companies with no apparent ill effects. Furthermore, the weight of the
evidence, as I have indicated, is that the failure did not occur because of any
recent resocketing, but as a result of a defect existing in the socket from its
manufacture, and there is no affirmative evidence to indicate that anything
Yorke did or authorized in connection with the socket and its resocketing
operation caused or contributed to that defect. In my view, bearing in mind the
words of Anglin, C.J.C. and Atkin L.J. quoted above and approaching the
question with the considerations they expressed in mind, the defect was a latent
defect and no amount of diligence on the part of Yorke could have detected it.
The evidence demonstrates, in my view, that the failure and the resulting loss
of the Westport Straits were not caused by any failure on the part of
Yorke to exercise due diligence in furnishing the tug in a seaworthy condition.
In the final result I would order that the
appeals of Wire Rope against the judgments in favour of B.C. Marine, Straits,
and Yorke be allowed, and that part of the judgment at trial dismissing the actions
against Wire Rope be restored with costs throughout; that the cross-appeal by
Yorke be allowed; and the action by B.C. Marine and Straits, against Yorke be
dismissed with costs throughout; and that the cross-appeal of B.C. Marine and
Straits be dismissed with costs.
Appeals by Wire Rope against judgments in favour of
B.C. Marine, Straits, and Yorke allowed, and that part of the judgments at
trial dismissing the actions against Wire Rope restored, with costs;
cross-appeal by Yorke allowed; the action by B.C. Marine and Straits against
Yorke dismissed with costs; and the cross-appeal of B.C. Marine and Straits
dismissed with costs.
Solicitors for the (third party)
appellant: Bull, Housser & Tupper, Vancouver.
Solicitors for the (plaintiffs)
respondents: Owen, Bird, Vancouver.
Solicitors for the (defendant)
respondent: MacRae, Montgomery, Spring & Cunningham, Vancouver.