Supreme Court of Canada
Faubert and Watts v. Temagami Mining Co. Ltd., [1960]
S.C.R. 235
Date: 1960-01-26
Faubert and Watts (Plaintiff)
Appellant;
and
Temagami Mining Co. Limited (Defendant)
Respondent.
1959: December 7, 8; 1960: January 26.
Present: Kerwin C.J. and Locke, Cartwright, Abbott and Judson
JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR ONTARIO.
Arbitration—Error of law upon face of award—Jurisdiction of
arbitrators—Distinction where question of law arises in course of arbitration
and where question of law specifically referred—Nature of order extending time
to apply to set aside award—Leave required of Supreme Court of Canada—The
Arbitration Act, R.S.O.1950, c. 20, s. 30—The Supreme Court Act, R.S.C. 1952,
c. 259, ss. 41, 44.
The contract between the plaintiff and the defendant, for the
construction by the plaintiff of a mining access road, provided for
arbitration. Disputes arose between the parties and the plaintiff commenced
arbitration proceedings. The defendant’s motion to set aside the arbitrators’
award on the grounds that it was bad on its face and that the arbitrators had
exceeded their jurisdiction, was dismissed after the time for bringing the
motion had been extended pursuant to s. 30 of The Arbitration Act. The
Court of Appeal set aside the award and dismissed the plaintiff’s cross-appeal
in which he had contended that the defendant had accepted a benefit under the
award and was thereby precluded from applying to have it set aside. The
plaintiff appealed to this Court.
Held: The appeal should be dismissed; but the order of
the trial judge extending the time to make the motion to set aside the award
should be restored.
The order of the Court of Appeal, affirming the order made by
the trial judge to extend under s. 30 of the Act the time for applying to set
aside the award was a discretionary order within s. 44 of the Supreme
Court Act. No appeal lay from that order unless leave be given by this
Court under s. 41, and under the circumstances of this case leave would not be
given.
There was no acceptance by the defendant of any benefit under
the award or acquiescence in it so as to preclude it from applying for an
extension of time, or from applying to set aside the award itself.
There was error of law appearing upon the face of the award.
The authorities make a clear distinction between a case where disputes are
referred to an arbitrator in the decision of which a question of law becomes
material from the case in which a specific question of law has been referred to
him for decision. In the first case, the Court can interfere if and when any
error of law appears on the face of the award but in the latter case no such
interference is possible upon the ground that it so appears that the decision
upon the question of law is an erroneous one. In the case at bar, the pleadings
indicate that no specific question of law was submitted to the arbitrators.
[Page 236]
APPEAL from a judgment of the Court of Appeal for Ontario,
setting aside an arbitration award. Appeal dismissed.
F.P. Varcoe, Q.C., for the plaintiff, appellant.
J.J. Robinette, Q.C., for the defendant, respondent.
The judgment of the Court was delivered by
THE CHIEF JUSTICE:—This is an appeal by Faubert and Watts against
the judgment of the Court of Appeal for Ontario1 allowing with costs
an appeal by Temagami Mining Co. Limited from an order of Landreville J.,
dismissing without costs Faubert and Watts’ cross-appeal, setting aside the
order appealed from and also an award of a Board of Arbitration, dated
April 1, 1958. The costs of the application to Landreville J. were also
directed to be paid by Faubert and Watts. The latter will be referred to as the
Contractor and Temagami Mining Co. Limited as the Company.
On October 9, 1956, these parties entered into a written
agreement (the construction contract) whereby the Contractor agreed to
(a) construct a mining access road (hereinafter
called the “road”), as hereinafter provided, from a point on Highway No. 11
approximately four (4) miles south of the Village of Temagami, westerly a
distance of approximately twelve (12) miles to Sulphide Point on Lake Temagami
along the route indicated on the plan hereto annexed as Schedule “A”, subject
to slight variation therefrom to secure better grades; and
(b) provide all the materials and complete the road
including all bridges and culverts as follows and as in this agreement
provided:—
(i) the road will be built to the specifications prescribed
for mining access roads which include a road bed of gravel twenty-eight feet
(28′) wide and at least one foot (1′) thick over base, of a grade
of not more than seven percent (7%) and curves of not more than ten degrees
(10°);
(ii) construction will be of the standard which may be
required by the District Engineer of the Department of Highways at North Bay;
(iii) construction to commence immediately and proceed
continuously, subject to weather conditions, and to be completed to the
satisfaction of the company’s engineers, Geophysical Engineering & Surveys
Limited.
[Page 237]
The Company agreed to:—
(a) pay the Contractor in lawful money of Canada for the
materials and services aforesaid at the rate of Ten Thousand Dollars
($10,000.00) per mile plus Two Dollars ($2) per cubic yard of necessary rock
cut and One Dollar ($1) per lineal foot of necessary corduroy, exclusive of
bridges and culverts for which payment will be made at cost of labour and
materials plus ten percent (10%) and
(b) make payments on account thereof upon the
certificate of the Engineers as set out.
“The General Conditions of the Contract” which were annexed to
the agreement and were to be read into and form part thereof contained Art. XII
the relevant parts of which provided:
In the case of any dispute between the Company, or the
Engineers on its behalf, and the Contractor during the progress of the work, or
afterwards, or after the determination or breach of the contract as to any
matter arising thereunder, either party hereto shall be entitled to give to the
other notice of such dispute and to demand arbitration thereof.
Such notice and demand being given, each party shall at once
appoint-an arbitrator and these shall jointly select the third. The decision of
any two of three arbitrators shall be final and binding upon the parties who
covenant that their disputes shall be so decided by arbitration alone and not
by recourse to any court by way of action at Law. However, if within a
reasonable time the two arbitrators appointed by the parties do not agree upon
a third or a party who has been notified of a dispute fails to appoint an
arbitrator, then a third arbitrator or an arbitrator to represent the party in
default or both such arbitrators may, upon simple petition of the party not in
default, be appointed by a Judge of the Supreme Court of the Province of
Ontario.
The original construction agreement was amended by another
between the same parties, dated June 4, 1957, clause (a) of which reads:
(a) Notwithstanding any other provision in the
Construction Contract to the contrary, from and after the 4th day of June,
1957, the Company will pay the Contractor in lawful money of Canada, Three
Dollars ($3) per cubic yard of necessary rock cut and Fifty-five Cents ($.55)
per cubic yard for gravel fill hauled to and used for the construction of said
road (exclusive of such material hauled for surfacing the mining access road to
a uniform depth of one foot). Payment for said fill shall be based on pit
measurements and the Contractor shall advise the Company, from time to time, of
its intention to remove gravel fill from a pit which it shall designate and
shall enable the employees or nominees of the Company to properly survey said
pit both before and after any such gravel is removed therefrom by the
Contractor. In the event the Contractor fails to enable the Company to perform
any such survey or surveys, the Company shall be under no obligation to pay for
gravel removed from the pit since the time a survey of
[Page 238]
the pit was last made by the Company. Notwithstanding any
other provision to the contrary, the Company shall not pay the Contractor for
hauling gravel fill which is used in the construction of any part of said road
from 0 + 0 to 264 + 00 on the grid laid out.
Prior to the agreement of October 9, 1956, the Contractor had
entered into one dated September 13, 1956, with Geophysical Engineering &
Surveys, Ltd., for the clearing of all trees, brush and other vegetation and
the removal of all merchantable timber, windfalls and other fallen timber,
fallen branches and other surface Utter, on a location corresponding to that of
the mining access road referred to in the agreement of October 9, 1956. As
appears from clause (b) (iii) of this last mentioned agreement set out
above, Geophysical Engineering & Surveys, Ltd. were the Company’s
engineers.
Disputes having arisen between the Contractor and the Company the
former commenced arbitration proceedings in pursuance of Art. XII of the
General Conditions. The procedure before the Board of Arbitration and what it
did will be referred to later but it is first necessary to dispose of two points
upon which we did not require to hear counsel for the respondent. The award
dated April 1, 1958, was, according to the Contractor’s factum, published and
delivered to the solicitors for each party on April 2, 1958. According to the same factum, on May 15, 1958, the solicitors for the Contractor served a
notice of motion asking for leave to enforce the said award, and on May 16,
1958, they were served with a notice of motion on behalf of the Company asking
for an order extending the time for bringing a motion to set aside the award
and for an order setting it aside on the grounds therein set forth. On May 20,
1958, the Company’s motion was adjourned by consent and it was that motion
which was heard by Landreville J. on June 16 and 17, 1958. That learned judge
extended the time for bringing the motion pursuant to s. 30 of The
Arbitration Act, R.S.O. 1950, c. 20:
30. (1) Unless by leave of the Court or a Judge, an
application to set aside an award, otherwise than by way of appeal, shall not
be made after six weeks from the publication of the award.
(2) Such leave may be granted before or after the expiration
of the six weeks.
[Page 239]
This was one of the matters as to which the Contractor
cross-appealed to the Court of Appeal without success.
Mr.Varcoe agreed that Laidlaw J.A., with whom the other members
of the Court of Appeal concurred, was correct in stating that he accepted the
statement of counsel for the Company that the latter had made a mistake as to
the date of publication of the award and the circumstances under which it
became necessary to ask for an extension of time to set aside the award, but
that Laidlaw J.A. was mistaken in stating that counsel for the Contractor
therefore confined the cross-appeal to the submission “that a person who has accepted
a benefit under an award is thereby precluded from applying to have it set
aside”. He did indeed make this latter submission before this Court but also
contended that the Court can exercise its judicial discretion to extend the
time for moving to set aside an award only if it can be shown that the
applicant held a bona fide intention to move while the right to do so
existed, that there were special circumstances which prevented him from so
doing and that justice requires that leave be given. So far as that point is
concerned we are all of opinion that no matter what the effect of the
authorities to which counsel referred may be, the order of the Court of Appeal,
affirming in that respect the order of the judge of first instance, was a
discretionary order within s. 44 of the Supreme Court Act and that,
therefore, no appeal lay unless leave be given by this Court under s. 41 and
that under the circumstances leave would not be given.
The second point in the cross-appeal by the Contractor which was
decided adversely to it by the Court of Appeal is as to the alleged approbation
of the award. As to that we agree with Laidlaw J.A., speaking for the Court of
Appeal, that while certain saleable timber left on the site of the work after
the termination of the construction contract was found by the Board to be the
property of the Company and while the Company transferred its right in the
timber to one Roy Pacey in return for his clearing it from the right of way,
there was a separate contract between the Contractor and the engineers for the
clearing of the right of way. Any question as to the ownership of this timber
arose under this separate contract and was in no way connected
[Page 240]
with or dependent upon the terms of the construction contract,
and there was no acceptance by the Company of any benefit under the award or
acquiescence in it so as to preclude it from applying for an extension of time,
or from applying to set aside the award itself.
The members of the Board of Arbitration were duly chosen; what might
be called pleadings were then delivered,—”points of claim” by the Contractor,
“points of defence and counter‑claim” by the Company and “points of reply
and defence to counter-claim” by the Contractor. In view of the award made by
the Board it is important to note that after referring to the construction
contract of October 9, 1956, para. 7 of the claim alleged that at the request
of one Davidson, for and on behalf of the Company, the Contractor agreed to
construct a road substantially different from that contemplated by the
contract, the benefit of which had been accepted by the Company, and that “It
was an implied term of the said agreement that the Defendant Company would pay
to the Plaintiffs a reasonable remuneration on a quantum meruit basis
for the construction of the said road. The said term is to be implied from the
said request and the said acceptance by the Defendant Company. The Plaintiffs
say that a reasonable remuneration for the construction of the said road would
be the cost of construction incurred by the Plaintiffs plus ten per cent
profit”. These allegations were denied by para. 8 of the defence including a
specific denial that there were implied terms of any agreement between the
parties. Denial was also made that the Company had accepted as substantially
complete the work done by the Contractor under the original construction
contract and the Company maintained that the amending agreement of June 4,
1957, was entered into at the request of the Contractor for its financial
benefit. Claims were also advanced by the Contractor as set out in the reasons
of Laidlaw J.A. for damages under various heads.
The Board made this finding:—“We further find that the only means
to settle the deeply involved dispute is to pay the Contractor the cost of the
work, plus a percentage for profit”, and then awarded the contractor the cost
of the work plus ten per cent. “applied to the total cost of the
[Page 241]
work after deducting therefrom the amount of equipment rentals”.
The Board also found that the contract was wrongfully terminated by the Company
and therefore in addition to the cost of the work, plus ten per cent., awarded
the Contractor $10,100 “as liquidated damages”.
I find it unnecessary to refer to any of the other findings of
the Board of Arbitration. It appears to me to be quite clear that there is
error of law appearing upon the face of the award. The Board did not proceed to
arbitrate the matters that were in dispute under the construction contracts but
imposed their own view of what should be done and gave what they considered was
a proper sum on a quantum meruit basis and furthermore allowed a large
sum by way of “liquidated damages”. The authorities are all mentioned in the
16th ed. of Russell on Arbitration but reference might be made particularly to
the judgment of the House of Lords in Absalom Ltd. v. Great Western (London)
Garden Village Society Ltd.[2]
Lord Russell with the concurrence of Lord Buckmaster and Lord Tomlin, at p.
607, points out that the authorities make a clear distinction between a case
where disputes are referred to an arbitrator in the decision of which a
question of law becomes material from the case in which a specific question of
law has been referred to him for decision. In the first, the Court can
interfere if and when any error of law appears on the face of the award but in
the latter case no such interference is possible upon the ground that it so
appears that the decision upon the question of law is an erroneous one. Lord Warrington
of Clyffe and Lord Wright came to a like conclusion for similar reasons. I read
the relevant parts of the pleadings as indicating that no specific question of
law was submitted by the parties to the Board and therefore I do not
investigate the problem that would arise if this were not so as did LeBel J.A.
with the concurrence of McGillivray J.A.
The appeal should be dismissed with costs. The formal judgment of
the Court of Appeal set aside the order of Landreville J., but, as the latter
extended the time within which the motion to set aside the award might be made,
it
[Page 242]
would appear to be preferable if the affirmance of that part of
the order of the judge of first instance were made clear in the judgment of
this Court to be issued.
Appeal dismissed with costs.
Solicitors for the plaintiff, appellant: Varcoe, Duncan
& Associates, Toronto.
Solicitors for the defendant, respondent: Lang, Michener
& Cranston, Toronto.