Supreme Court of Canada
Garceau
v. Ouellette, [1960] S.C.R. 668
Date: 1960-06-24
Charles Garceau Appellant;
and
Maurice R. Ouellette Respondent;
and
Louis H. Sideleau
Mis-En-Cause.
1960: June 2, 3; 1960: June 24.
Present: Taschereau, Fauteux, Abbott, Judson and Ritchie JJ.
ON APPEAL FROM THE COURT OP QUEEN'S BENCH, APPEAL SIDE, PROVINCE OF QUEBEC.
Contracts—Building contract—Extension to building—Final
cost—Whether contract at fixed price—Whether settlement of all claims—Action to
enforce builder's privilege—Civil Code, art. 1690.
By a contract between the appellant and L, the latter
undertook to build an extension or addition to the hotel owned by the
appellant. L was furnished with a sketch and rough plan and specification. The
contract stipulated the payment of $16,000 in instalments. L was to be paid 10
percent as his fee, but agreed, in the event that the contract was to run in
excess of the $16,000, to waive this percentage charge on the excess, on
condition that the appellant pay the installments as before. The eventual cost
far exceeded the amount of $16,000. The appellant-paid the contract price and
give two promissory notes to L for $3,000 each, paying both at maturity. He
refused to pay the excess, and took the position that the contract was a contract
at a fixed price within art. 1690 of the Civil Code, and furthermore
that L had accepted the second promissory note in full and final settlement of
all his claims.
The respondent, as trustee of the estate of L, a bankrupt,
took an action to enforce a builder's privilege. The appellant took an action
to have the registration of such privilege declared null and void. The
respondent's action was allowed and the appellant's dismissed by the trial
judge. These judgments were reversed by the Court of Appeal.
Held: Both appeals should be dismissed.
There was no evidence to support the contention that the
second note was accepted by L in final settlement of all his claims. Moreover,
no fee for L's services was included in the total payments made by the appellant.
[Page 669]
The sketch and plan furnished by the appellant could do no
more than give a general idea of the extent and character of the work to be
done, and it was obvious that the parties had contemplated that there would be
changes and alterations and that the estimated cost would be exceeded. The
contract was not undertaken at a fixed price and art. 1690 had therefore no
application.
APPEALS from two judgments of the Court of Queen's Bench,
Appeal Side, Province of Quebec, reversing two judgments of Cliche J.
Appeals dismissed.
R. Bouchard, Q.C., and G. Normandin, Q.C., for
the appellant.
A. Forget, for the respondent.
The judgment of the Court was delivered by
Abbott J.:—These
appeals are from judgments of the Court of Queen's Bench,
unanimously reversing two judgments of the Superior Court, the judgments in the
Court below in the one case allowing respondent's action to enforce a builder's
privilege in the amount of $10,121.21, and in the other dismissing appellant's
action asking that the registration of such privilege be declared null and
void. Respondent is the trustee of the estate of one Raoul Lamont, a bankrupt,
who in April 1953 had entered into a contract with appellant to construct an
extension or addition to a hotel owned by the latter at Coaticook, Quebec. The
facts are fully set out in the judgment of Mr. Justice Taschereau in the Court
below and I need refer to them only briefly.
The contract to which I have referred is dated April 18,
1953, and it reads as follows:
18 avril 1953.
Contrat entre Mr. Charles Garceau de
Coaticook, Que. pour une annexe à l'Hotel "Child"
de 40' x 80' d'une étage de 14',
fini tel que plans et devis que j'ai en mains et avec la
coopération de Bernard Poitras et le Propriétaire. Ceci avec un pourcentage de 10% sur un montant de $16,000.00.
S'il y a un excédent, je me charge de continuer le contrat
sans aucune charge de pourcentage à condition que M. Charles Garceau,
propriétaire de l'Hotel Child se charge de payer la différence de ce montant de
$16,000.00 avec condition de $500.00 par mois jusqu'au règlement de la dette
finale.
[Page 670]
Condition
de règlement pour la première
somme
de $16,000.00
Premier paiement de $5,000.00
le 30 avril 1953
Deuxième paiement de $5,000.00
le 30 Mai 1953
Troisième paiement de $5,000.00
le 30 Juin 1953.
Balance de $1,000.00 sur règlement au mois de $500.00 par mois et au même condition s'il y a excédent du montant du contrat.
(signé) C. GARCEAU
(signé) RAOUL
LAMONT
Concurrently with the execution of this agreement appellant
furnished Lamont with a coloured sketch and rough plan and specification of the
proposed extension. This sketch and plan were both filed as exhibits and it is
clear that the details of construction of the proposed building, contained in
the said plan, are very meagre indeed.
Lamont started work on April 20, 1953, and the whole project
was completed on July 17, 1953. It is common ground that the cost of the work
substantially exceeded the amount of $16,000 mentioned in the written contract.
The Court below found that the cost of the work done and materials furnished by
Lamont (aside from any compensation for his own services) amounted to
$32,340.98. There was ample evidence to support that finding and, in fact, the
appellant made no attempt to challenge its accuracy.
Appellant paid $16,000 in the manner specified in the
contract and subsequent to the completion of the work he also paid suppliers of
material to the extent of $1,478.77 and gave Lamont two promissory notes for
$3,000 each, dated July 17, 1953, and July 24, 1953, respectively, both of
which were paid at maturity. Total payments made by appellant therefore
amounted to $23,478.77.
As I have said, appellant made no attempt to establish that
the cost of the work done and materials supplied was not in excess of $30,000.
Moreover, a report of Jean Julien Perrault, an architect who was appointed as
an expert by the learned trial judge, established that the work done and
materials furnished by Lamont had given an added value to the appellant's
property of $30,900.
In his defence and at the trial appellant took the position
(1) that the contract of April 18, 1953, was a contract at a fixed price within
the meaning of art. 1690 of the Civil
[Page 671]
Code, that he had authorized and paid for additions
and alterations to a total amount of $7,478.70 only, and was liable for no
further amount and (2) that in taking the promissory note for $3,000 dated July
24, 1953, to which I have referred, Lamont had accepted it in full and final
settlement of all his claims.
As to appellant's second ground of defence, I am satisfied
that there is no evidence to support his contention that the note for $3,000
dated July 24, 1953, was accepted by Lamont in final settlement of all his
claims. Lamont denied that this note was in full and final payment of his
claim, his evidence on this point being as follows:
Q. Maintenant, je vous
repose la même question parce
qu'il y a un fait nouveau: Lorsque ce billet du vingt-quatre (24) juillet "cinquantetrois" ('53), PG-6, a été donné, est-ce qu'il a été
question que c'était en paiement final, qu'il ne vous devait plus rien?
R. Non. Moi, j'ai demandé ça pour qu'il me
donne une chance pour passer ça à ma banque pour que je paye d'autres
créanciers.
Q. Pour éviter la faillite?
R. Pour éviter la faillite, justement.
Moreover, it is to be observed that no fee for Lamont's
services was included in the total payments of $23,478.70 made by appellant.
Appellant obtained no final receipt from Lamont and the note for $3,000 dated
July 24, 1953, bears no indication that it was given by appellant and accepted
by Lamont in full and final settlement.
The question as to whether the contract in issue here comes
within the provisions of art. 1690 of the Civil Code depends, of course,
upon the interpretation and effect to be given to the agreement of April 17,
1953. In the Court below Mr. Justice Taschereau speaking for the Court held
that it was not a contract at a fixed price under the terms of art. 1960 C.C. I
share that view and there is little I can usefully add to what he has said in
this respect.
Article 1690 C.C. contains an exception to the general rules
as to proof and, as such, it must be strictly interpreted. Commenting
on this article, Faribault in his "Traité du Droit Civil du Québec", vol. XII, page 450, says:
On distingue le marché
à forfait absolu ou pur et simple, et le marché à forfait relatif. Il est
absolu lorsque le propriétaire ne s'est pas réservé le droit ou le privilège de
modifier les plans et devis durant le cours des travaux. Il n'est que relatif dans
le cas contraire. L'article 1690 n'a
d'application que si le contrat à forfait est absolu: lorsque ce contrat est
relatif, on doit appliquer les règles ordinaires de la preuve.
[Page 672]
Comme l'article 1690 est une exception à la règle générale de la preuve, il doit être
interprété restrictivement. Il n'a d'application que s'il existe un marché à
forfait pur et simple, accompagné de plans et devis. Il ne peut s'appliquer si
le contrat prévoit une possibilité de modifications dans les plans et devis, ou
si ces derniers font entièrement défaut.
As I have stated, the details contained in the sketch and
plan furnished to Lamont when the contract was entered into are very meagre
indeed. It is obvious that such a sketch and plan could do no more than give a
general idea of the extent and character of the work to be done, and it is
equally obvious, in my opinion, that both parties contemplated there would be
changes and alterations and that the cost would exceed $16,000. The only
feature of the contract which is clear and precise is that the contractor
Lamont would be paid for his services an amount limited to $1,600, being 10 per
cent of $16,000.
The contract in issue here, even if undertaken upon a plan
and specifications within the meaning of those terms as used in art. 1690
C.C.—as to which I have some doubt— was not, in my opinion, undertaken at a
fixed price, and art. 1690 has therefore no application.
For the foregoing reasons and for those of Mr. Justice
Taschereau in the Court below, with which I am in agreement, both appeals
should be dismissed with costs.
Appeals dismissed with costs.
Attorney for the appellant: R. Bouchard,
Coaticook.
Attorneys for the respondent: Tremblay, Monk,
Forget, Bruneau & Boivin, Montreal.