Supreme Court of Canada
Bouge Electric of Canada Ltd. v. Crothers
Manufacturing Ltd., [1961] S.C.R. 108
Date: 1960-12-19
Bogue Electric of
Canada Limited (Plaintiff) Appellant;
and
Crothers
Manufacturing Limited (Defendant) Respondent.
1960: November 16; 1960: December 19.
Present: Kerwin C.J. and Locke, Cartwright,
Martland and Judson JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
ONTARIO.
Contract—Time of
essence—Non-delivery—Extension of time—Further delay—Cancellation—Notice of
termination.
The respondent C entered into a contract with
a Crown corporation to supply motor‑driven generator sets, and sub-let to
the appellant B the contract for the supply of the generators. Very little
effort was made to commence production of the generators, and as a result of the
appellant’s inability to begin deliveries at the time promised, the three
interested parties agreed to a revised delivery schedule. B failed to adhere to
the new schedule and C cancelled the sub-contract, having previously notified B
of its intention so to do, if delivery was not made as promised. B sued for
damages arising from cancellation of the contract. The action was dismissed by
the trial judge, and this judgment was affirmed by a majority in the Court of
Appeal. B then appealed to this Court.
Held: The
appeal should be dismissed.
Time was of the essence of both the head
contract and the sub-contract. The importance of delivery according to schedule
had been emphasized, and punctual performance by B went to the whole
consideration of the sale.
Time remained of the essence notwithstanding
the substitution of new delivery elates. The appellant’s two-fold submission
that when notice was given time was not of the essence, and that the notice was
not a reasonable one was rejected.
The provision for cancellation on 15 days’
notice in the general conditions was in conflict with the condition in the
agreement between C and B authorizing an immediate right of cancellation
without further liability “if delivery is not made within the time promised or
specified”. Consequently the general conditions, even if assumed to be
applicable to the sub‑contract, must give way in accordance with clause
1(2) of the interpretation section of the said conditions.
APPEAL from a judgment of the Court of Appeal
for Ontario, affirming a
judgment of Gale J. Appeal dismissed.
A.S. Pattillo, Q.C., and D.J. Wright, for
the plaintiff, appellant.
P.B.C. Pepper, Q.C., Miss Janet Scott and
W. Herridge, for the defendant, respondent.
[Page 109]
The judgment of the Court was delivered by
JUDSON J.:—Bogue Electric of Canada Limited, the
appellant, sued the respondent, Crothers Manufacturing Limited, for damages
arising from the cancellation of a contract for the supply of 249 electrical
generators which Bogue was to manufacture for Crothers. The judgment at trial
was that Crothers was justified in cancelling the contract for non-delivery at
the stated time. This judgment was affirmed on appeal and Bogue now appeals to
this Court.
On October 18, 1956, Crothers entered into a
contract with Canadian Commercial Corporation, a Crown corporation, for the
supply of a large number of motor-driven generator sets for rural
electrification in India.
Crothers were suppliers of diesel motors and they sub-let to Bogue the contract
for the supply of the generators. On October 19, Crothers wired to Bogue to
book the order for the generators. There had been previous discussions between
the two companies. Bogue knew that Crothers was tendering for the contract with
Canadian Commercial Corporation and that if the tender was successful, it would
be asked to supply these generators. Bogue had stated that shipment could begin
16 to 18 weeks from the date of receipt of a firm order. On October 30, 1957,
Bogue and Crothers entered into their formal contract, which provided for end
of the month deliveries of 40 generators from February to June 1957 and the
balance in July and August. The need for regular deliveries was known to both
parties. Crothers had first to connect the generators to the diesel units
before it could meet its own schedule of deliveries under the head contract
commencing in March 1957, and its ability to do this depended upon prompt
performance by Bogue.
It became apparent on February 13, 1957, as a result of a visit by an
official of Crothers to the Bogue plant in Ottawa, that Bogue had made very little effort to begin to produce the
generators and that delivery could not begin by the end of February as
promised. This was nearly four months after the placing of the order. The
evidence coming from the internal memorandum of the Bogue Company, dated
February 22, 1957, makes it clear that the delay was entirely the fault of the
Bogue Company, which appears
[Page 110]
to have been making little or no effort to
complete its contract. The reason was that while the contracting party was
Bogue Electric of Canada Limited, the decisions necessary to carry out the
contract had to be made at the head office of the parent company in the United States and these decisions were not
being made. As a result of the obvious inability of Bogue to begin its
deliveries on February 28, 1957,
the three interested parties, the Government, Crothers and Bogue, agreed, on
March 12, 1957, to accept a new delivery schedule to begin on May 15, 1957. On March 13, 1957, the Canadian
company emphasized to its parent company the urgency of preparing to meet this
new delivery schedule.
After this had been arranged, Crothers, with the
approval of the Government, revised its own delivery schedule of the completed
units to begin on June 30, 1957,
instead of March, as previously agreed. On March 29, 1957, Bogue assured
Crothers that “delivery was progressing satisfactorily according to the revised
schedule.” This assurance was given notwithstanding the fact that on March 22,
1957, a Government inspector who had visited the Bogue plant in Ottawa had made
a report which showed that little was being done to fill the order and that
there was little likelihood of the delivery of 40 generators by May 15, 1957.
Crothers complained to the Government about this but was informed on April 18
that it would be held to its own revised delivery schedule under the head
contract. After receiving this information, Crothers made another visit to the
Bogue plant and found that conditions were as bad as had been reported by the
Government inspector one month before. In spite of the assurances of Bogue that
the delivery schedule would be met, Crothers was satisfied that this was
impossible because of the inactivity in the plant. Crothers then began to make
plans for an alternative source of supply of generators.
On May 6, 1957, Crothers notified Bogue that if deliveries were not made on May 15
as promised, it would cancel the sub-contract. Bogue, on May 7, 1957, stated
that it was exerting its best efforts to meet its commitments under the
contract. Crothers made tentative arrangements to obtain generators from an
alternative supplier if Bogue
[Page 111]
generators should not be delivered on May 15.
Bogue did not deliver on May 15 and Crothers cancelled the subcontract on May
16.
At the trial no attempt was made to explain
Bogue’s lack of preparedness and dilatory conduct. The learned trial judge said
that there was no evidence to lead to any conclusion about the date when Bogue
might have delivered its first 40 units had it been allowed to do so. The
generators called for under the contract were uncomplicated, run-of-the-mill
units. At no time did Bogue have a first-production unit available for
inspection as required by the contract. It failed to take on labour. It was late
in ordering supplies. By May 15, 1957, it had been supposedly working on this sub-contract from October
19, 1956, a period of 7 months. Both the trial judge and the majority opinion
in the Court of Appeal held that Crothers was justified in terminating the
contract in these circumstances. The only point of the dissent in the Court of
Appeal was that certain general conditions, which Laidlaw J.A. said formed part
of the sub-contract, required the giving of 15 days’ notice of termination on
default by Bogue.
The sub-contract between Crothers and Bogue
contained the following condition:
The purchaser reserves the right to cancel
all or any part of this order if delivery is not made within the time promised
or specified, without any liability whatsoever.
This was the condition under which Crothers
exercised its right of cancellation. The learned trial judge’s finding was that
time was of the essence of the head contract between the Government and
Crothers. He was also of the same opinion concerning the sub-contract between
Crothers and Bogue. In the circumstances of this case no other conclusion is
possible. This was a mercantile contract. The importance of delivery according
to schedule is emphasized by the whole of this record. Crothers was depending
upon Bogue to make and deliver a component part of a complete unit. After
delivery of the generator, Crothers had to connect it with its motive power and
meet a delivery schedule of its own. The supply of these complete units was
part of a wider Government plan which was recognized to be
[Page 112]
an urgent one. It was part of a chain of
transactions, and punctual performance by Bogue went to the whole consideration
of the sale. (22 Hals., 2nd ed., 57)
The next question is whether time ceased to be
of the essence because of the alteration of the delivery dates by mutual
consent. The dates of all the deliveries were precisely stated in both the
original and the amended schedule. No other change was made in the
sub-contract. All that happened was that one schedule of deliveries was
substituted for another. Bogue’s new delivery schedule was acted upon by
Crothers in re-scheduling its own deliveries despite the problem of storage
space, and at no time between March 1957 and May 15, 1957, did Crothers do anything to
indicate to Bogue that May 15 was not the deadline. As late as April 25 Bogue
was insisting that it could make delivery on May 15 although it is quite
apparent from the evidence that there was no basis of fact for this insistence.
Both the learned trial judge and the Court of
Appeal, without any dissent on this point, have held that time remained of the
essence of the contract notwithstanding the substitution of new delivery dates,
and in my opinion this is clearly correct. The principle is stated in 8 Hals.,
3rd ed., 165:
Where time is of the essence of the
contract, and is extended by agreement between the parties, the extension does
not operate as an entire waiver of the condition, but merely has the effect of
substituting the extended time for that originally fixed.
Even if this were not so, there is also a
unanimous finding of the learned trial judge and the whole Court of Appeal that
the notice given by Crothers to Bogue on May 6th requiring Bogue to deliver on
the date promised was reasonable. These are concurrent findings on a question
of fact, fully supported by the evidence and obviously correct. I have
therefore no difficulty in rejecting the appellant’s twofold submission that on
May 6, the date of the notice, time was not of the essence and that the notice
given was not a reasonable one.
This leaves only the appellant’s submission that
there was no right of cancellation until 15 days following May 15, 1957. This
proposition is the sole foundation for the dissenting opinion of Laidlaw J.A.
in the Court of Appeal.
[Page 113]
In order to succeed the appellant must show that
General Conditions CCC 50 form part of the contract and that the provision for
15 days’ notice of cancellation contained in clause 22 of these Conditions
overrides the specific provision for cancellation contained in the contract
itself which I have already quoted.
The learned trial judge dealt with this aspect
of the case on the assumption that these general conditions did form part of
the sub-contract. They expressly form part of the head contract and they were
drawn to be of general application to contracts between the Crown and a
contractor. There are many clauses which can have no possible application to a
contract to which the Government is not a party. The sub-contract between Crothers
and Bogue states that it is understood that General Conditions, Form CCC 50,
will apply for the duration of the contract, which could be interpreted to mean
that Bogue was contracting on the understanding that Crothers was subject to
these conditions. It is not, however, necessary to decide this point. I will
proceed on the same assumption as the trial judge. Clause 22 of these general
conditions provides:
If the Contractor is in default for a
period of fifteen days in carrying out the terms of the contract as a result of
events or occurrences for which it is responsible or which are within its
control… the Corporation may at his option, upon giving notice in writing to
the Contractor, (i) terminate the contract as to work not theretofore completed
or (ii) take the work out of the Contractor’s hands and employ such means as
the Corporation may see fit to complete the work in whole or in part.
But along with this, one must read Clause 1(2)
of the interpretation section of these general conditions. It reads:
In the event of any inconsistencies, the
provisions of the agreement and/or of these general conditions shall prevail
over the specifications (if any) and the provisions of the agreement and of the
supplemental conditions (if any) shall prevail over these general conditions.
I agree entirely with the finding of the learned
trial judge that the provision for cancellation on 15 days’ notice in the
general conditions is in conflict with the condition in the agreement between
Crothers and Bogue authorizing an immediate right of cancellation without
further liability “if delivery is not made within the time promised or
specified”, and that consequently, the general conditions, even if assumed to
be applicable, must give way.
[Page 114]
I would dismiss the appeal with costs.
Appeal dismissed with costs.
Solicitors for the plaintiff, appellant:
Mcllraith and Mcllraith, Ottawa.
Solicitors for the defendant, respondent:
McMillan, Binch, Stuart, Berry, Dunn, Corrigan & Howland, Toronto.