Supreme Court of
Canada
Modern
Construction Ltd. v. Maritime Rock Products Ltd., [1963] S.C.R. 347
Date:
1963-06-24
Modern Construction Limited (Plaintiff) Appellant;
and
Maritime Rock Products Limited (Defendant)
Respondent
1963: February
22; 1963: June 24.
Present: Cartwright, Fauteux, Martland, Judson and Ritchie
JJ.
ON APPEAL FROM THE SUPREME COURT OF NOVA SCOTIA
Mechanics' liens—Whether last work done under contract
performed within 45 days of filing of lien as required by statute—Interest in
lands—Mechanics' Lien Act, R.S.N.S. 1954, c. 171, s. 23.
The plaintiff, a general construction company, entered into a
contract whereby it agreed among other things to repair and extend a causeway
and convert a ship into a wharf at a certain property where the defendant was
carrying on the business of quarrying, selling and shipping stone. It was
provided that the work would be substantially completed by June 1 so that the
defendant would have its plant and wharf ready for the opening of the shipping
season, and a list of the drawings and specifications was set out in the
contract. By June 16 the wharf and causeway were temporarily operational. The
substantial amount of work that remained to be done in order to bring the
contract to completion was started on September 6 and completed on September
27. The plaintiff filed a mechanics' lien on October 17 and brought an action
to enforce its claim. At the close of the plaintiff's case, the trial judge
granted the defendant's motion for nonsuit on the ground that the last work
proved to have been done under the contract was completed on June 16, and therefore
not within 45 days of the filing of the lien, as required by s. 23 of the Mechanics'
Lien Act, R.S.N.S. 1954, c. 171. The trial judgment having been affirmed on
appeal, the plaintiff further appealed to this Court.
Held: The appeal should be allowed.
By the terms of the contract the plaintiff assumed an
obligation to do everything indicated in the specifications and drawings which
included sinking the ship complete with superstructure and extending the
causeway to the ship. This work was not completed by providing temporary
facilities which were not suitable to withstand the winter weather in the area.
The evidence in the case constituted prima facie proof of the fact that
the plaintiff had not done all that it promised to do under the contract until
about September 27, and that the last work done by it thereunder was
accordingly performed within 45 days of the registration of the lien. County
of Lambton v. Canadian Comstock Co. et al., [1960]
S.C.R. 86, followed.
As to the defendant's contention that no prima facie case
had been established to show that the defendant had any estate or interest in
the lands described in the statement of claim, there was evidence to the effect
that work was done and materials were supplied "in respect of" lands
as to which there was some evidence of the defendant's interest. The validity
of the lien was not destroyed by the fact that the descrip-
[Page 348]
tion in the statement of claim and claim for lien included
together with those lands, certain Crown lands to which no lien attached.
Practice—Judgment granting motion for nonsuit reversed
on appeal—Action referred back to trial judge.
The trial judge heard the defendant's motion for nonsuit in
accordance with the submission of its counsel that he could be prejudiced if he
was required to proceed before the Court decided on the issues raised. This
left the defendant's counsel in a position where he was entitled to assume that
he would be permitted to proceed if the motion were decided against him. In
view of these circumstances it would be unjust for the defendant to be
precluded from proceeding with its case, and it was therefore directed that the
action be referred back to the trial judge so that the trial might proceed in
the usual course. McKee v. Fisher (1929), 64 O.L.R. 634; Hayhurst v.
Innisfail Motors Ltd., [1935] 2 D.L.R. 272; Cudworth v. Eddy, [1927]
1 W.W.R. 583; Protopappas v. B.C. Electric Ry. and Knap, [1946] 1 W.W.R.
232; Yuill v. Yuill, [1945] P. 15, referred to.
APPEAL from a judgment of the Supreme Court of Nova
Scotia, in banco, affirming a judgment of McKinnon C.C.J., dismissing
appellant's claim in a mechanics' lien action. Appeal allowed.
A. L. Caldwell, for the plaintiff, appellant.
A. R. Moreira, for the defendant, respondent.
The judgment of the Court was delivered by
Ritchie J.:—This
is an appeal from a judgment of the Supreme Court of Nova Scotia in banco affirming
a judgment rendered at trial by His Honour Judge A. H. McKinnon whereby he
dismissed the appellant's claim for a lien under the Mechanics' Lien Act, R.S.N.S. 1954, c. 171, at the close of
the appellant's case on the ground that the evidence then adduced did not
establish a prima facie case to prove that the last work done under the
contract upon which the claim is based was performed within 45 days of the
filing of the lien on October 17, 1961, as required by the provisions of s. 23
of the said Act.
The claim is for work and labour done, services rendered and
materials supplied by the appellant, which is a company engaged in the general
construction business, under a contract dated April 20, 1961, whereby it agreed
among other things to repair and extend a causeway and convert a ship into a
wharf at a property situate at Malignant Cove, in the County of Antigonish,
where the respondent was carrying on the business of quarrying, selling and
shipping stone.
[Page 349]
The making of this contract appears to have been first
discussed at a meeting of the directors of the respondent company on April 16,
1961, at which representatives of the appellant were present. At this meeting
it was disclosed that the respondent company, which has since become bankrupt,
was in serious financial difficulties and that it was necessary for it to have
its plant and wharf put in operational condition by the opening of the summer
shipping season in June. It was reported also that the Nova Scotia Government
had not yet made any final decision on the company's application for a loan of
$100,000 "to take care of building a new wharf and to put the plant at
Malignant Cove into operation", and it was pointed out that this decision
might not be made until the middle of May whereas the work had to be done
immediately. Some discussion followed concerning an offer by the appellant
company to undertake the work forthwith, the upshot of which is perhaps best
described in a letter written to the appellant by the respondent on April 20
which reads in part as follows:
At a meeting of the Directors on April 15, 1961, it was
proposed that Modern Construction Limited, Moncton, be granted a contract in
the sum of $75,000 to carry out the construction of a wharf and certain repairs
as per instructions which you already have, to the tunnel and conveyor of the
Company's premises at Malignant Cove, construction operations to commence
immediately and Modern Construction to wait until such time as Maritime Rock
Products have completed proper financial arrangements for payment of this
contract. It was further decided that if Modern Construction Limited would
immediately commence operations and be prepared to await payment at a future
date, then in consideration of this valuable service, Maritime Rock Products
Limited would cause to be issued to Modern Construction Limited as a bonus,
78,948 shares of common capital stock of the Company at the purchase price of 5
cents per share.
The appellant having replied accepting this offer, a
contract was prepared and executed by the parties on April 20 which included
the following provisions:
ARTICLE I. The Contractor will:
(a) provide all the materials and perform all the
work shown on the Drawings and described in the Specifications … which have
been signed in duplicate by both parties …
(b) do and fulfill everything indicated by this
Agreement, the General Conditions of the Contract, the Specifications, and the
Drawings, and
(c) complete substantially as certified by the
architect, all the work by the 1st day of June.
[Page 350]
ARTICLE II. The following is an exact list of the drawings
and specifications referred to in Article I:
(a) carry out repairs to existing causeway and to
extend causeway to ship,
(b) preparing ship for sinking, towing ship to site
and sinking ship complete with superstructure.
(a) and (b) to be carried out as
detailed on attached blueprints designated Schedules "A",
"B" and "C".
* * *
It is understood that Maritime Rock Products Limited will
supply all materials presently on site cost free to Modern Construction
Limited, and it is further understood that Modern Construction Limited will
supply all materials not otherwise located on the site.
ARTICLE III. The owner will:
(a) pay the contractor in lawful money of Canada for
the materials and services aforesaid Seventy-five Thousand dollars ($75,000)
subject to additions and deductions as provided in the General Conditions of
the Contract.
No architect was engaged under the contract and the
only provision with respect to the method of payment was that it would be made
on receipt of funds from Nova Scotia Government loan or the
making of other satisfactory arrangements.
Work was commenced at the end of April or early in May 1961
and the evidence discloses that by June 16 the wharf and causeway were
temporarily operational so that ships were able to come alongside and load the
respondent's rock for the opening of the shipping season. It does not, however,
appear that any further work was done during the summer months and the
appellant's comptroller, the respondent's general manager, and the foreman on
the job all testified that the substantial amount of work remaining to be done
in order to bring the contract to completion was not started until September 6
and only completed on or about September 27.
None of this evidence is contradicted as the respondent's
motion for nonsuit was granted at the close of the appellant's case on the
ground that the last work proved to have been done under the contract was
completed by June 16.
It is not disputed that under the provisions of s. 23 of the
Mechanics' Lien Act the lien here in question was required to be
registered within 45 days after the completion or abandonment of the contract
but as has been indicated it is the appellant's contention that the work done
in September
[Page 351]
1961 was done pursuant to the contract and that registration
of the lien on October 17 was therefore in conformity with the statutory
requirements. The respondent, on the other hand, contends, as the Courts below
have found, that the appellant's contractual obligation was completely
fulfilled by having the shipping facilities available for transport and that
this was done in the month of June and therefore more than 45 days before the
registration of the lien.
In the course of his reasons for judgment, Judge McKinnon
refers at length to the evidence of Mr. Ingalls, the appellant's comptroller,
in which that witness agrees that the two principal items discussed at the
directors' meeting of April 15 were that the respondent's wharf be made
suitable for accommodating vessels and that the plant had to be made ready for
the summer season. The learned trial judge quotes the following excerpts from
the cross-examination of Mr. Ingalls regarding these two items:
Q. Isn't it true that those were substantially done by the
19th of June of that year?
A. The answer to that has to be a little indirect in
that there was such a tremendous rush to get, the plant into operation and take advantage to
the shipping contract.
Q. But those two necessary items we just discussed—they were
completed June 19th.
A. It was possible. I visited the site by that time and.
enough had been done that temporarily it was possible
to operate the plant for shipping material. It would be shown the shipping date
was very quickly achieved.df
Q. (by the Court): What is the answer to that question. The work contemplated by the agreement was
completed by June?
A. It was possible to begin shipping quickly on a basis that
was almost temporary. The company had entered into the contract with Mussens of
Canada whereby if the shipping was not moving there would be heavy penalties.
It was possible to achieve shipping by that date.
The interpretation placed on the contract by Judge McKinnon
appears to be based in large measure upon this evidence, as to which he states:
It would appear to me that this evidence indicates the full
purpose and extent of the contract. It was necessary to get the plant in
operation and shipping facilities available for transport at some date in June,
or the company would be subject to heavy penalties.
[Page 352]
That it was this concept which controlled the conclusion
reached by the learned trial judge is shown by the following two paragraphs
from his decision:
It appears that the contract called for substantial
compliance with the terms of the contract by June 1st and it would seem from
the evidence herein that all the work contemplated by the contract was performed
by the plaintiff by the early part of that month, and a careful review of the
testimony of Mr. Ingalls, Mr. Chapman, as well as an examination of Schedules
"A", "B" and "C" under the contract.
In September, after the conclusion of the shipping season,
the plaintiff proceeded to do further work on the causeway and boat although he
must have been fully aware that he had no prospect of payment from the proceeds
of a Nova Scotia Government loan as provided in the contract or, as it may be
fairly assumed, from any other source. In view of this, it can well be that the
defendant has some cause to contend that the plaintiff was simply securing the
ship and causeway against the heavy winter weather to be expected in this area
and this work had no connection with the purpose for which the contract was
entered into.
With the greatest respect, it appears to me from a
consideration of the terms of the contract itself that the appellant had
thereby assumed an obligation to do everything indicated in the specifications
and drawings which included sinking the ship complete with superstructure and
extending the causeway to the ship and that this work was not completed by
providing temporary facilities which were not suitable to withstand the winter
weather in the area. It was no doubt recognized by all concerned with the
project that it was necessary for the respondent to have its wharf and causeway
in operational condition by the opening of the summer shipping season and it
could be inferred from the evidence that the appellant had agreed to bring this
about but this does not, in my opinion, justify the further inference that no
more work was to be done under the contract or that the wharf and causeway were
intended to be temporary structures only.
Mr. Chapman, to whose evidence the learned trial judge
refers, was the respondent's general manager and one of the signatories to the
contract on its behalf. In the course of his evidence this witness was
specifically directed to the contract specifications and the attached drawings,
and after referring to them he stated that in the month of September
"approximately 35–45% of the rock was yet to be placed in and around the
boat and causeway and 15–20% piling had to be completed around the back of the
boat" in order to complete
[Page 353]
the work indicated by those documents. In my view, this
evidence was admissible and constituted prima facie proof of work having
been done under the contract in September 1961.
In affirming the decision of the learned trial judge, Mr.
Justice MacQuarrie who delivered the reasons for judgment of the Supreme Court in
banco had occasion to say that "the circumstances disclosed by the
evidence in this case indicate the value and importance of the learned trial
judge having seen and heard the witnesses. This Court considering all the
circumstances should attach great weight to this opinion".
The value and importance of seeing and hearing the witnesses
which is enjoyed by the trial judge and denied to an appellate court should
never be underestimated, but in the present case as the evidence for the
appellant is entirely uncontradicted and as I do not read the learned trial
judge's reasons and conclusion as being inconsistent with his having believed
this evidence I do not, with respect, feel that this Court is under the same
disadvantage as is the case where there is some conflict of evidence or some
indication that the demeanour of the witnesses has affected the result. As I
interpret the decision of the trial judge, it is based upon his construction of
the contract and the fact that he differs in this regard from some of the
witnesses does not, in my opinion, indicate that he was influenced by their
demeanour.
In holding that "the September work does not confer or
revive any lien", Mr. Justice MacQuarrie made reference to the case of County
of Lambton v. Canadian Comstock Company Ltd. et al. In
that case, Judson J., speaking on behalf of this Court, with respect to s.
21(1) of the Ontario Mechanics' Lien Act, said at pp. 93–4:
The fact that a contractor, who has substantially completed
his work, may sue for the contract price, subject to deductions for minor
defects or omissions, if there are any, does not and cannot determine when time
begins to run against him under The Mechanics' Lien Act. Completion
means what it says. I do not think that time begins to run under s. 21(1) until
it can be said that the contractor or sub-contractor has done all that he
promised to do and is entitled to maintain his account for the full amount.
[Page 354]
In my opinion, this language applies with equal force to s.
23 of the Nova Scotia Mechanics' Lien Act and as I have indicated, the
evidence in the present case appears to me to constitute prima facie proof
of the fact that the appellant had not done "all that it promised to
do" under the contract here in question until about September 27, 1961,
and that the last work done by it thereunder was accordingly performed within
45 days of the registration of the lien on October 17.
This does not, however, dispose of this appeal as the
respondent's motion for nonsuit was also based on the ground that no prima
facie case had been established to show that the respondent had any estate
or interest in the lands described in the statement of claim, or that the
appellant had contracted to do any work on those lands, or that the amount
claimed was owed with respect to work performed thereon.
The lands described in the statement of claim are said to be
situate "at or near Malignant Cove, in the County of Antigonish, and to
border on the highway leading from Georgeville to Malignant Cove". This
description includes "a certain causeway", "the conveyor to the
causeway", and "the hull of a sunken ship", and while denying
that it is "the registered owner of the lands" the respondent
pleaded, by para. 4(f) of its defence:
In the further alternative, that the bankrupt is not the
owner of the lands and premises referred to … but is entitled only to the
equity of redemption in certain portions thereof, the same (in so far as the
bankrupt has any interest therein) being subject to a mortgage the holder
whereof is the owner of the legal estate and fee simple in the said lands and
premises.
In the course of his evidence, Mr. Chapman was asked where
the causeway on which the work was done was located, and he replied "off
the causeway and wharf adjacent to the plant and situate at Georgeville,
Malignant Cove, Antigonish area". It will be remembered also that in its
letter of April 20 the respondent described the work to be done as "to
carry out the construction of a wharf and certain repairs … to the tunnel and
conveyor to the company's premises at Malignant Cove …".
[Page 355]
The attitude adopted by the appellant is made plain in its
factum, where it is said:
The estate or interest of the defendant in the lands
described in the statement of claim is of two kinds:
(1) actual possession of the causeway and ship located on
lands of the Crown, and
(2) the holder of the equity of redemption in the remaining
lands described in the statement of claim and claim for lien.
As to the lands other than the Crown lands, although the
proof is slim indeed I do not think that it can be said that there is no
evidence of the respondent having an estate or interest therein capable of
being the subject of a mechanics' lien.
The respondent, which held itself out to be the owner of
these lands when the contract was made and accepted the work and labour on that
basis, is at a grave disadvantage when, having called no evidence to disprove
its estate or interest in such lands, it seeks to have the action dismissed on
the ground that no such estate or interest has been shown to exist. Under such
circumstances, the Court is, in my opinion, entitled to resolve any doubts as
to the respondent’s interest in the lands in favour of the lien claimant.
As to the ship and causeway, I am not prepared to hold that
mere possession without any claim or colour of right coupled with an admission
that the lands in question belong to the Crown can give rise to an estate or
interest in lands capable of being the subject of a mechanics' lien. In this
regard, reference may usefully be had to the reasons for judgment rendered by
Laidlaw J.A. on behalf of the Court of Appeal of Ontario in Pankka v.
Butchart et al.
It is, however, to be remembered that a lien attaches to
"any estate or interest in the land upon or in respect of which the
work or service is done or materials are placed or furnished …" (s. 1(d)
and s. 5) and I am of opinion that there is some evidence to the effect
that the work done and materials supplied to the wharf and causeway were done
and supplied "in respect of" the remaining lands as to which there is
some evidence of the respondent's interest, and I do not think that the
validity of the lien is destroyed by the fact that the description in the
statement of claim
[Page 356]
and claim for lien includes together with those lands,
certain Crown lands to which no lien attaches.
In conclusion, I should add that it appears to me that there
was also some evidence that the amount claimed in the statement of claim was
owed pursuant to work done under the contract hereinbefore referred to.
In view of all the above, I would allow this appeal and set
aside the judgment of the Supreme Court in banco and of the learned
trial judge.
In his factum, the appellant's counsel asks that judgment be
entered for the relief claimed in the statement of claim but we did not hear
argument on this phase of the matter and we were referred to no reported case,
nor have I been able to find one, establishing the practice in Nova Scotia when
a judgment granting a motion for nonsuit is reversed on appeal.
The practice under such circumstances appears to be well
established in Ontario (see McKee v. Fisher), Alberta (see Hayhurst
v. Innisfail Motors Ltd.),
and in British Columbia (see Cudworth v. Eddy, and Protopappas v.
B.C. Electric Ry. and Knap),
and is well described by Harvey C.J. in the Hayhurst case, supra,
where he said at p. 277:
… we see no reason why we should not apply the same rule of
practice as that of Ontario. It is to be understood therefore that for the
future when a defendant applies for a dismissal at the close of the plaintiff's
case he does so at the risk of not having the right to give any evidence on his
own behalf for if the trial Judge grants his application and the Appellate
Court comes to the conclusion that it was wrong, it will feel itself at liberty
to finally dispose of the case on the evidence already given and will do so unless
in its discretion it considers that in the interests of justice some other
course should be taken.
The English practice in this regard is discussed by Lord
Greene in Yuill v. Yuill,
where, after referring to Laurie v. Raglan Building Co. Ltd., he goes on to say:
The practice which has been laid down amounts to no more
than a direction to the judge to put counsel who desires to make a submission
of
[Page 357]
no case to his election, and to refuse to rule unless
counsel elects to call no evidence. Where counsel has so elected he is, of
course, bound: but if for any reason, be it through oversight or (as here)
through a misapprehension as to the nature of counsel's argument, the judge
does not put counsel to his election, and no election in fact takes place,
counsel is entitled to call his evidence just as if he had never made the
submission.
In the present case, the learned trial judge explained his
reasons for entertaining the respondent's motion for nonsuit on the following
basis:
It was further contended by the defendant that as none of
these essentials were properly and sufficiently established, the case for the
defendant could be prejudiced if he was required to proceed before the Court
decided on the issues raised. Accordingly, decision was reserved and the trial
adjourned until today …
It appears to me that the learned trial judge heard the
respondent's motion in accordance with the submission of its counsel that he
could "be prejudiced if he was required to proceed before the Court
decided on the issues raised". In my view, this left the respondent's
counsel in a position where he was entitled to assume that he would be permitted
to proceed if the motion were decided against him.
In view of these circumstances, I am of opinion that it
would be unjust for the respondent to be precluded from proceeding with its
case and I would therefore direct that the action be referred back to the
learned trial judge so that the trial may proceed in the usual course.
The appellant should have the costs of this appeal and of
the appeal to the Supreme Court of Nova Scotia in banco. The costs of
the trial, however, should abide the result thereof.
Appeal allowed with costs.
Solicitor for the plaintiff, appellant: A. L.
Caldwell, Halifax.
Solicitor for the defendant, respondent: L. F.
Daley, Halifax.