Supreme Court of Canada
Perini Pacific Ltd. v. Greater Vancouver Sewerage and
Drainage District, [1967] S.C.R. 189
Date: 1967-01-24
Perini Pacific
Limited (Plaintiff) Appellant;
and
Greater Vancouver
Sewerage and Drainage District (Defendant) Respondent.
1966: December 5, 6; 1967: January 24.
Present: Abbott, Martland, Judson, Ritchie
and Spence JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
BRITISH COLUMBIA
Contracts—Building contract—Action for
damages brought by contractor—Loss by way of overhead alleged to have been
sustained because contract completion date extended by delays on part of
owner—Claim prevented by clause in contract.
Under a contract between the appellant and
the respondent the appellant agreed to construct a sewage disposal plant within
six hundred days next ensuing from the date of receiving notice from the
respondent to proceed with the work. Pursuant to the provisions of the
contract, the completion date, initially November 25, 1962, was extended to
January 10, 1963. Various delays occurred in the course of the work, and the
project was not completed before March 4, 1963.
In an action brought by the appellant against
the respondent for damages the former alleged that it had been delayed in the
construction by various breaches of the agreement by the respondent. The
respondent counter-claimed for $53,000, the contract having stipulated for
payment by the appellant of the sum of $1,000 per day for each day by which the
putting into operation of the plant was delayed beyond the completion date.
The action was dismissed at trial and
judgment was given in favour of the respondent on the counterclaim for the
amount of $8,000. On appeal,
[Page 190]
the appellant’s appeal was dismissed, save as
to the counterclaim, the counterclaim being dismissed by the Court of Appeal.
On appeal to this Court, the counterclaim was not in issue.
Held: The
appeal should be dismissed.
What the appellant was seeking, in the way of
damages, was compensation for loss which it claimed to have sustained, by way
of overhead, because the contract completion date had been extended by reason
of breaches of the contract by the respondent. This argument could not succeed
by reason of a clause in the contract which read in part: “…the Contractor
shall have no claim or right of action against the Corporation for damages,
costs, expenses, loss of profits or otherwise…by reason of any delay in the
fulfilment of the contract within the time limited therefor occasioned by any
cause or event within or without the Contractor’s control, and whether or not
such delay may have resulted from anything done or not done by the Corporation
under this contract.”
The appellant was seeking compensation for
loss which it claimed to have sustained by reason of delay in the fulfilment of
the contract within the time limited, and it was exactly that kind of loss
which the above clause said could not be claimed even if it resulted from
anything done or not done by the respondent under the contract.
The appellant also appealed from the decision
of both Courts below in respect of a second action brought by the appellant
against the respondent for holdback moneys alleged to be due under the
contract. This action was consolidated with the first one. The Court agreed
with the reasons given by Davey J.A. for holding that this claim failed.
APPEAL from a judgment of the Court of Appeal for British
Columbia, dismissing an appeal from a judgment of Collins J. Appeal dismissed.
J.S. Maguire, Q.C., and K.S. Fawcus, for
the plaintiff, appellant.
R.M. Hayman and B.W.F. Fodchuk, for the
defendant, respondent.
The judgment of the Court was delivered by
MARTLAND J.:—This action was brought by the
appellant against the respondent for damages in respect of various alleged
breaches by the respondent of a contract between them in which the appellant
agreed to construct for the respondent a sewage disposal plant on Iona Island
in the Fraser River. The appellant agreed to construct the plant within six
hundred days next ensuing from the date of receiving notice from the respondent
to proceed with the work. Pursuant to the provisions of the contract, the
completion date, initially November 25, 1962, was extended to January 10, 1963.
Various delays occurred in the course of
[Page 191]
the work, and it was common ground that the work
was not completed before March 4, 1963.
The appellant alleged that it had been delayed
in the construction by various breaches of the agreement by the respondent. The
respondent counterclaimed for $53,000, the contract having stipulated for
payment by the appellant of the sum of $1,000 per day for each day by which the
putting into operation of the plant was delayed beyond the completion date.
The action was dismissed at trial and judgment
was given in favour of the respondent on the counterclaim for the amount of
$8,000. On appeal, the appellant’s appeal was dismissed, save as to the
counterclaim, the counterclaim being dismissed by the Court of Appeal. The
counterclaim was not in issue before this Court.
On the argument before this Court, the number of
breaches of contract which the appellant alleged to have occurred had been
reduced to three. In each instance it was claimed that the appellant’s work had
been delayed, and the periods of delay claimed were 3½ days, 14 days and 69
days respectively. In respect of the first item, the majority of the Court of
Appeal held that delay had not been proven. With regard to the second, it was
held unanimously that delay had not been proven. The Court found that the
respondent had caused delay for a period of 12 days in respect of the third
matter, but also held, in respect of this claim, that the appellant had not
proved the resulting damage.
The damages in each case claimed by the
appellant were for increased overhead costs resulting from the delays. The
proof of its loss consisted in determining the average daily overhead costs for
the entire period of the work, from commencement to conclusion. The loss for
each period of delay was then said to consist of the number of days’ delay
multiplied by that average daily figure.
This was rejected by the trial judge and by all
the members of the Court of Appeal. The position of the Courts below may be
summarized in the following passage from the reasons of Bull J.A., in the Court
of Appeal:
The quantum of these items claimed
was arrived at by translating the respondent’s fault into the number of days’
delay caused thereby and multiplying the result by a daily average “overhead”
(including indirect
[Page 192]
costs) over the lifetime of the whole
construction period, such daily average being calculated by taking the total of
those items of overhead and indirect costs incurred from the beginning of the
work to its completion and dividing same by the number of the days in that
period. Obviously, as found by the learned trial Judge, the overhead referred
to continued for other works bearing no relevance to that in respect to which
the delays occurred, and the appellant made no effort at all to establish that
such overhead (whether in gross or daily average) was increased in any respect by,
or had included therein, any amount that could be said to have been sustained
either directly or indirectly by the breaches of contract of the respondent.
This difficulty was brought to the attention of the appellant by the learned
trial Judge during the trial, when he indicated that such daily average
overhead claimed was no proof of any amount of loss sustained by the appellant
through the delays caused by the respondent, and that he required some evidence
of increases in overhead resulting therefrom. This evidence was not
forthcoming, and in fact one witness for the appellant said it was not possible
to break down the overhead and indirect cost figures to show what was
allocatable to the respondent’s breaches of contract. This same difficulty was
raised by this Court on the appeal before us, and again we were not directed to
any evidence to show any such attributable damage, the appellant maintaining
throughout that it was entitled to damages on the basis of the daily average
overhead for each day’s delay caused by the respondent.
With deference, I am in agreement with what
the learned trial Judge in effect held that an average daily overhead amount
calculated on the total overhead over the whole construction period divided by
the number of days of construction, was not in the circumstances of this case,
a proper measure of damages.
The appellant’s submission to this Court, in
answer to these reasons, was stated in its factum, as follows:
The Appellant submits that once it has
proved that the contract completion date has been extended by reason of a
breach of contract by the Respondent, it is entitled to damages calculated on
the basis advanced by the Appellant at the trial. The method adopted at the
trial by the Appellant was to show the amount of all the items of expenses or
costs for the whole construction period that were extended by the passage of
time. To find the cost per day, the Appellant divided this total by the number
of days in the construction period. The cost per day was found to be $738.47.
The Appellant submits that such a method is
the only reasonable method of calculating the cost of the delay because the
effect on cost of the breach of contract extends beyond the period in which the
breach occurs. In any event, it is submitted that the method of calculation by
the Appellant would have been acceptable to the learned Justices in the Courts
below if they had appreciated that the result of the Respondent’s breaches of
contract caused delay in the overall completion of the contract, or in other words,
increased the number of days required by the Appellant to complete the
contract.
This contention makes it clear that what the
appellant is seeking, in the way of damages, is compensation for loss which it
claims to have sustained, by way of overhead,
[Page 193]
because the contract completion date had been
extended by reason of breaches of the contract by the respondent.
In my opinion this argument cannot succeed in
view of the provisions of clause 6-04 of the general conditions of the
contract. This clause is one of a group of clauses headed “PROSECUTION OF WORK”
and it reads as follows:
6-04. No Claim against Corporation
Unless otherwise particularly provided in
the contract, the Contractor shall have no claim or right of action against the
Corporation for damages, costs, expenses, loss of profits or otherwise
howsoever because or by reason of any delay in the fulfilment of the contract
within the time limited therefor occasioned by any cause or event within or
without the Contractor’s control, and whether or not such delay may have
resulted from anything done or not done by the Corporation under this contract.
The opening words of the portion of the argument
above quoted—“once it has proved that the contract completion date has been
extended by reason of a breach of contract by the Respondent”—make it clear
that what the appellant is seeking is compensation for loss which it claims to
have sustained by reason of delay in the fulfilment of the contract within the
time limited, and it is exactly that kind of loss which clause 6-04 says cannot
be claimed even if it results from anything done or not done by the respondent
under the contract.
The claim in respect of the last item of delay
was in respect of the failure by the respondent promptly to furnish, and set on
the foundations constructed under the contract, six engine generator units,
which it was required to furnish under clause 7-05(2) of the specifications.
These generators were supplied by a supplier, under contract with the
respondent, and proved to be defective. This resulted in delay of the
appellant’s work while the necessary repairs were being made.
The specifications did not provide any specific
date for furnishing them. It must be implied that they should be furnished
within a reasonable time so as to permit the appellant to proceed with its work
within the contract period. The respondent would, in my opinion, only be
legally responsible for such delay in: performing this obligation as would
prevent the appellant from completing its work within the stipulated period.
But for loss occasioned by
[Page 194]
that kind of delay there can be no claim because
of clause 6-04 of the general conditions.
Clause 6-04 was referred to in the reasons for
judgment of the learned trial judge, but with no specific expression of opinion
as to whether it was applicable. In the Court of Appeal, the majority held that
it was not applicable, while Davey J.A. did not find it necessary to deal with
it. Bull J.A. discusses its application in the following passage in his
reasons:
As I have indicated earlier, it is not too
clear from the learned trial Judge’s reasons for judgment as to what importance
he placed on the relieving provisions of article 6-04 of the General Conditions
of the contract in dismissing the claims being discussed. As it is my view that
the claim was properly dismissed on the grounds set out above, the question of
whether it was barred by the provisions of the article need not be considered.
However, should I be wrong in my conclusions, or a higher court should consider
that nominal damages should have been awarded or a new assessment of damages
had, I consider that it might be useful to express my views as to the proper
construction of that article. Accordingly I have come to the conclusion that
the respondent could not with respect to this particular claim, rely on these
provisions. The relief to the respondent is only against damages (inter alia)
“because of or by reason of any delay in the fulfilment of the contract
within the time limited therefor,” notwithstanding that such delay may be the
sole fault of the respondent. The claim for damages for the delay being
considered has nothing to do with the revised contract completion date of
January 10, 1963. It is damages for breach of contract and it is immaterial to
that claim whether the contract was completed before, at or after the time
limited for completion thereof. The relief given by the article does not
purport to cover damages for any delay other than one involving the time limit
for completion. Although of no relevance in this appeal, it would appear that
the article was designed to and would protect the owner from any claim or
set-off by a contractor for liquidated damages or penalties payable by it under
an unrelieved completion clause when breach thereof was caused by the owner’s
actionable breach of contract; such situations have not been unusual.
In view of the position taken by the appellant
before us, to which I have already referred, I am not able to agree that:
The claim for damages for the delay being
considered has nothing to do with the revised contract completion date of
January 10, 1963. It is damages for breach of contract and it is immaterial to
that claim whether the contract was completed before, at or after the time
limited for completion thereof.
As already indicated, my understanding of the
appellant’s position in respect of the claims urged before us is that, because
the delays caused by the respondent extended the work period beyond the
contract completion date, full overhead can be recovered for the number of
days’ delay which
[Page 195]
led to that result. I interpret clause 6-04 as
preventing the making of that kind of claim. I understand this clause to mean
that if the appellant complains that, because of causes or events outside its
control, it has not been able to complete the contract within the contract
period and has thereby incurred expense, it shall not be entitled to recover
such expense from the respondent, even though the respondent had caused such
delay.
The appellant also appealed from the decision of
both Courts below in respect of a second action brought by the appellant
against the respondent for payment of the holdback money. That action was
consolidated with the other one. The nature of this claim is described in the
following extract from the reasons of Davey J.A. and I agree with the reasons
which he gives for holding that that claim fails:
The plaintiff commenced a second action to
recover the holdback money. That action was consolidated with the first one.
General condition 7-02 provides that the defendant shall pay the balance of the
contract price to the plaintiff 40 days after presentation of the engineer’s
certificate that he has accepted the work, and upon delivery by the plaintiff
of, inter alia, releases of all its claims and demands under the
contract or in connection with its subject matter. The delivery of such a
release and payment of the holdback money are thus to be concurrent acts. The
plaintiff delivered only a qualified release, which reserved all its claims in
respect of the specific matters that have been litigated. The defendant refused
to accept it. The learned trial Judge held that since the disputes had not been
adjudged until after the second writ had issued and the plaintiff had not delivered
or tendered an unqualified release, the cause of action for the holdback money
was not complete when the second writ was issued. He dismissed that action,
without prejudice to the plaintiff’s bringing a new one when its cause of
action was complete. The plaintiff appeals. I agree with the reasoning of the
learned trial Judge. The intention of the provision seems to be that if the
plaintiff does not release all outstanding claims, and wants to litigate some
of them, it cannot get the holdback money until it has done so. So, if the
defendant is harassed by expensive litigation, it will have security through
the holdback money for its taxed costs if successful. That provision may seem
harsh—I do not say it is—or unnecessary with respect to this plaintiff, but
that is no ground upon which to relieve the plaintiff from the plain meaning of
an otherwise lawful provision by which it has bound itself: Roberts v. Bury
Commissioners, (1870) L.R. 5 C.P. 310 at pp. 325 and 326. I would dismiss
this part of the appeal.
In my opinion the appeal should be dismissed
with costs.
Appeal dismissed with costs.
Solicitors for the plaintiff, appellant:
Clark, Wilson, White, Clark & Maguire, Vancouver.
Solicitors for the defendant,
respondent: Russell & DuMoulin, Vancouver.