Supreme Court of Canada
Alkok v. Grymek et al., [1968] S.C.R. 452
Date: 1968-04-01
Arnold Alkok (Plaintiff) Appellant;
and
Issie Grymek and
Yetta Grymek (Defendants) Respondents.
1967: December 15, 18; 1968: April 1.
Present: Judson, Ritchie, Hall, Spence and
Pigeon JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
ONTARIO.
Contract—Building contract providing for
payment by instalments upon architect’s certificate—Breach of term requiring
builder to satisfy architect that subcontracts had been paid—Contract terminated
by owners—Builder not in breach of term going to root of
contract—Damages—Quantum meruit.
The plaintiff, a building contractor, entered
into a contract in writing with the defendants to build a house for $57,500. It
was provided that the defendants were to “make payment on account thereof upon
the architect’s certificate (when the architect is satisfied that the payments
due to subcontractors have been made)” according to a schedule set out in the
contract. The plaintiff proceeded with the contract and the defendants paid the
first two instalments and one-half of the third, which amounts totalled
$22,000, without requiring that the plaintiff satisfy
[Page 453]
the architect that the payments to the
subcontractors had been made. Later when the plaintiff pressed for payment of
the balance of the third instalment, the defendants required the plaintiff to
comply with the provisions of the contract and to so satisfy the architect.
After several conferences, the plaintiff failed to so satisfy the architect and
in addition there were complaints from the defendants and the architect that
there were defects in the construction and that the construction was delayed.
Although the plaintiff was willing and anxious to continue the work, the
defendants terminated the contract and engaged others to complete the building.
In an action brought by the plaintiff under
the provisions of The Mechanics Lien Act, the Master dismissed the
plaintiff’s claim and allowed a counterclaim by the defendants in the amount of
$6,075. On appeal, the Court of Appeal allowed the plaintiff’s appeal in part,
finding that the plaintiff was entitled to a lien and personal judgment against
the defendants in the amount of $1,125 and dismissing the counterclaim of the
defendants. The plaintiff further appealed to this Court and the defendants
cross-appealed.
Held: The
appeal should be allowed and the cross-appeal dismissed.
The Court agreed with the Court below that
the defendants had not shown sufficient grounds to support their termination of
the contract. The plaintiff was not in breach of a term going to the root of
the contract. While it was true that he was in breach of the term requiring him
to satisfy the defendants’ architect that the subcontracts had been paid this
was a mere ancillary term which could be enforced perfectly by the defendants
simply refusing to make payments until they were satisfied, as indeed the
defendants were refusing. As to the additional alleged breaches, i.e., defective
work and delay, the Master had found that these defects were minor, easily
rectified and certainly not such as to go to the root of the contract, and that
despite any delay the contract could have been completed substantially at the
time completion was required by its provisions. These findings were accepted by
the Court of Appeal.
On the matter of damages, the contractor’s
right to recover was what he could prove on a quantum meruit basis.
Accepting that the plaintiff was entitled to the balance of the third draw and
the whole of the fourth draw, less certain deductions, the Court found that the
quantum meruit claim proved was $11,042.50. Adding thereto $2,495 for
repair of storm damage and $950 for extras supplied at the request of the
defendants, but deducting therefrom liens in the amount of $2,320 paid by the
defendants, the total amount due to the plaintiff was $12,167.50. The
defendants, however, were entitled to claim a reduction for the cost of
correcting the defects in the work done by the plaintiff, such amount to be
determined upon a reference to the Master.
Northern Lumber Mills Ltd. v. Rice (1917), 41 O.L.R. 201, referred to.
APPEAL by plaintiff and CROSS-APPEAL by
defendants from a judgment of the Court of Appeal for Ontario,
varying a report of D.W. Rose, Q.C., Master, in a mechanics’ lien action.
Appeal allowed and cross-appeal dismissed.
[Page 454]
C.E. Woollcombe, for the plaintiff,
appellant.
D.I. Bristow, for the defendants,
respondents.
The judgment of the Court was delivered by
SPENCE J.:—This is an appeal from the judgment
of the Court of Appeal for Ontario
pronounced on February 21, 1966.
The Master of the Supreme Court of Ontario had
tried this mechanics’ lien action pursuant to a judgment of reference made by
Morand J. on October 4, 1963.
By his report made on June 24, 1964, the learned Master had dismissed the
plaintiff’s claim for lien and had allowed a counterclaim by the defendants in
the amount of $6,075.
By the judgment of the Court of Appeal for Ontario this was varied to allow the
plaintiff (there appellant) a lien on the premises owned by the defendants in
the sum of $1,125 together with the costs of the action and dismissing the
counterclaim of the defendants-respondents.
The plaintiff as appellant in the Court of
Appeal further appealed to this Court and the defendants cross-appealed.
The appellant is a contractor in the City of Toronto. He entered into a contract with
the respondents dated May 14, 1956, whereby he agreed to
(a) provide all the materials and perform
all the work shown on the drawings and described in the specifications entitled
“proposed residence for Mr. I. Grymek” which have been signed in duplicate
by both the parties and which was prepared by Edward I. Richmond, M.R.A.I.C.,
acting as and hereinafter entitled “the architect” and
(b) do and fulfill everything indicated by
this Agreement, the Specifications, and the Drawings.
The contract provided that the owner would pay
to the contractor $57,500 and
(b) Make payment on account thereof upon
the Architect’s certificate (when the Architect is satisfied that payments due
to Sub-Contractors have been made), as follows:
i) Upon completion of the sub-floor
$6,000.00;
ii) Upon completion of the roof $12,000.00;
iii) Upon completion of the brown coat of
plaster $8,000.00;
iv) Upon completion of the white coat of plaster,
including all plumbing and electrical work $12,000.00;
v) Upon completion of trim $8,000.00;
vi) the sum of ELEVEN THOUSAND, FIVE
HUNDRED DOLLARS ($11,500.00) . . .
[Page 455]
The appellant commenced work of erecting the
house in accordance with the said contract and from time to time the
respondents required the addition of certain extras which the appellant added
and which the Court of Appeal for Ontario found were of the value of $950. The
respondents paid to the appellant the whole of the first two instalments of
$6,000 and $12,000 respectively, and one-half of the third instalment, i.e.,
$4,000, and did so without requiring that the appellant comply with the
provisions of para, (b) aforesaid by satisfying the architect that the payments
due to the subcontractors had been made.
Later when the appellant pressed for the payment
of the balance of the third instalment, the respondents required the appellant
to comply with the provisions of the contract and to so satisfy the architect.
After several conferences, the appellant failed to so satisfy the architect and
in addition there were complaints from the respondents and from their architect
Mr. Richmond that there were defects in the construction and that the
construction was delayed. The solicitor for the respondents who had drafted the
original contract and who had been present at the various conferences when an
attempt was made to satisfy the architect that the subcontractors had been
paid, wrote to the appellant on November 10, 1956, complaining of the progress
of the work and of certain defects expressing the fear that mechanics’ liens
would be registered against the property and concluded with this paragraph:
Unless all of the building infractions,
which are your responsibility, have been remedied, and the work carried on at a
proper pace, my clients shall have no alternative than to employ their own
specific trades to complete your portion of the uncompleted work, and any
moneys or expenses incurred by my clients in employing tradesmen for either work
done or materials supplied shall be deducted from the contract price herein.
Six days later, on November 16, 1956, the said
solicitor wrote again to the appellants in which he said:
Further to the above matter, in confirming
my conversation with you yesterday, I hereby advise you on behalf of my clients
Issie Grymek and Yetta Grymek that they are terminating their contract with you
as of todays date.
They intend to complete the lands and
premises in the manner in which they believe the work should be done.
In accordance with that letter the appellant
ceased work on the contract though Mr. Richmond, the architect for
[Page 456]
the respondents, has testified that the
appellant was willing and anxious to continue it. The respondents proceeded to
complete the building themselves through the intervention of other contractors
and material men.
It was the view of the learned Master that the
respondents were entitled to terminate the contract at the time and in the
fashion aforesaid.
The Court of Appeal for Ontario, however, came to the conclusion that sufficient grounds for the
termination of the contract had not been established. McGillivray J.A., in his
reasons for judgment, quoted Anson’s Law of Contract, 21st ed., at p. 424, as
follows:
The question to be answered in all these
cases of incomplete performance is one of fact; the answer must depend on the
terms of the contract and the circumstances of each case. The question assumes
one of two forms—Does the failure of performance amount in effect to a renunciation
on his part who makes default? Does it go so far to the root of the contract as
to entitle the other to say, “I have lost all that I cared to obtain under this
contract; further performance cannot make good the prior default”?
That proposition needs no support by citation
from judgments and I accept it as expressing the proper test which the Court
must apply here. As pointed out by McGillivray J.A., in his reasons, the
contract as between the parties was for the contractor to build a house and for
the defendants to pay for it. The contractor had proceeded with the building
although not in accordance with the pace which the owners believed he should be
proceeding and had been guilty of what the Court of Appeal for Ontario has found were certain minor defects
in construction. The owners having paid two instalments and part of the third
were refusing to pay the balance of the third instalment or those which would
become due thereafter, and in so doing were relying upon the provision of the
contract which required the appellant as contractor to satisfy the respondents’
architect that the payments to the subcontractors had been made. They were
entitled to require that the appellant continue his work upon the contract and
to refuse to pay him until he did satisfy that provision. If the appellant had
refused to proceed on that basis then, of course, he would have been in breach
of the provision of the contract going to the root thereof and the respondents
would have been entitled to terminate the contract. The
[Page 457]
appellant did not indicate by word or conduct an
intention to so act or not to be bound in every way by the contract. The
appellant, therefore, did not give to the respondents the opportunity to
terminate the contract on the ground that the appellant had been in breach of a
term going to the root of it. It was true that he was in breach of the term
requiring him to satisfy the respondents’ architect that the subcontracts had
been paid, but, with respect, I agree with McGillivray J.A.’s view that this
was a mere ancillary term which could be enforced perfectly by the respondents
simply refusing to make payments until they were satisfied, as indeed the
respondents were refusing. I am, therefore, in accord with the view of
McGillivray J.A., that the respondents have not shown sufficient grounds to
support their termination of the contract.
I should point out that while I have referred
only to the alleged breach by the appellant in his failure to satisfy the
architect as to payment of subcontractors, there were two additional breaches
alleged: firstly, defective work, and secondly, delay. The learned Master found
that the defects were minor, easily rectified and certainly not such as to go
to the root of the contract, and that despite any delay the contract could have
been completed substantially at the time completion was required by its
provisions. The Court of Appeal for Ontario accepted these findings and they seem to be based on the evidence
of Mr. Richmond, the architect called as a witness by the respondents, who
testified as follows:
Q. Are you saying that what you saw in
November could not have been finished on the inside by the middle of February
of the following year?
A. It would be pretty close to it, if the
builder would, say, have 3 or 4 groups on the job, and carried his work along
at a reasonable pace. I would say about the latter part of February and he
could have gotten out of there.
The contract between the parties provided in
para. 4:
Interior to be completed no later than February 15, 1957, so that owner can take
possession thereof.
Once it is determined that the respondents’
action in terminating the contract had not been justified, one must turn, to
the question of what, if any, damages the appellant is entitled to recover.
[Page 458]
It was said in Macklem & Bristow on
Mechanics’ Liens in Canada, at p. 47:
If the owner ceases to make payments under
the contract, cancels it or, through some act of his own and without cause,
makes it impossible for the contractor to complete then the contractor is
justified in abandoning the work and is entitled at that time to enforce his
claim for lien to the extent of the actual value of the work performed and
materials supplied up until that time.
The contractor’s right to recover therefore
would seem to be what he could prove on a quantum meruit basis. In the
present case, the Court of Appeal for Ontario was of the opinion that the
plaintiff had quite failed to prove any quantum meruit basis. The
plaintiff had attempted this by two alternative methods: firstly, the plaintiff
proved the total amount due under the contract, i.e., $57,500, and
agreed to the deduction therefrom of the amounts already paid on account, i.e.,
$22,000; the amounts which the respondents were required to pay in
satisfying certain mechanics’ liens registered against the property, and also
the amount which he, the plaintiff, testified would have been required to
complete the building, i.e., $18,195.
As I have said, the defendants (here
respondents) did proceed to complete the building at a cost of $48,231.21.
Deducting therefrom the sum of $1,400 for an air conditioning unit which the
Master found was not included in the original cost, the defendants’ costs of
completion, therefore, were $46,882.31. The learned Master found on the evidence
of Mr. Richmond that those costs had represented about 15 per cent more
than would have been required by an efficient builder and therefore, found that
the proper cost of completion was $39,850.31. There is such a gross discrepancy
between the plaintiff’s estimated cost of completion and the defendants’ actual
cost of completion that neither the learned Master nor the Court of Appeal
could place any reliance upon that method of proof. It should be noted in
addition that this method fails to adduce the evidence necessary to establish a
quantum meruit claim. The use in the calculation of the final contract
price must include an element for a contractor’s profit and what the plaintiff
would be entitled to upon a quantum meruit proof in a mechanics’ lien action
is a payment for the work and materials provided up to the time of the
termination not
[Page 459]
such a profit as he might have contemplated
making had the contract been completed: The Mechanics’ Lien Act, R.S.O.
1960, c. 233, s. 5.
The plaintiff’s second method of calculation was
this. The plaintiff alleged that at the time the contract had been terminated
he had completed all the work which entitled him to the third draw, of which he
had been paid only one-half, and substantially all the work which would have
entitled him to the fourth draw. It was his submission that these draws were
calculated to keep pace with the construction and that therefore the completion
of the work which would entitle the plaintiff to demand the payment of the
instalment would automatically demonstrate the proportion of the work which had
been completed, and would, therefore, prove the amount of the quantum meruit
to which, subject to adjustments, the plaintiff would be entitled. On this
basis, the appellant submitted to the Court of Appeal and to this Court that it
should be entitled to the balance of the third draw of $4,000, the whole of the
fourth draw of $12,000 less deductions to which he agreed to submit in the
following amounts:
|
Balance of
plumbing........................................
|
$2,262.50
|
|
Balance of
electrical work...............................
|
800.00
|
|
Repairs to
plaster.............................................
|
910.00
|
In Northern Lumber Mills Ltd. v. Rice, an action was brought under the
provisions of The Mechanics’ Lien Act as here to enforce a lien for the
material supplied for the erection of a house. The price of those materials was
to be paid for in three payments. Before the action, the first two had become
payable but the third had not. Meredith C.J.C.P. said at p. 202:
A cause of action arose upon default in
payment of each of these instalments; and so, apart from the provisions of the
enactment, the action would have been properly brought as to the first two, but
improperly as to the third…
The Court held that the action under the
provisions of The Mechanics’ Lien Act was not premature as to any of the
three instalments.
At the trial, there was produced in
cross-examination of Mr. Richmond, called as witness for the defendants, a
[Page 460]
statement which he had drawn up in preparation
of an answer to the evidence of the plaintiff (here appellant) as to the costs
of completion, and the appellant is submitting to the deductions in the amounts
set out by Mr. Richmond in his statement items 16, 17 and 18, i.e.,
|
16—Plumbing...................................................
|
$2,262.50
|
|
17—Plastering.................................................
|
910.00
|
|
18—Electrical...................................................
|
800.00
|
Mr. Richmond was cross-examined on these
various items as well as all the others in the said statement. It is true that
also to be completed before the plaintiff was entitled to the fourth draw were,
of course, roofs, and Mr. Richmond had deducted that $228 for repair of
roofs. He admitted, however, that if the roofs were in need of repair then, of
course, the roofing contractor who had supplied the roofs only a short time
before under guarantee should have been approached and required to make good
his guarantee and that he had not done so.
As to item 16, Mr. Richmond testified that
when the plaintiff left the job the rough plumbing was all done and that it
represented about 50 per cent of the plumbing contract.
As to electrical work, about 65 per cent had
been done at the time the plaintiff left the job.
As to plastering, all the white plaster had been
completed but it was necessary to repair some. As I have pointed out, the
appellant has accepted Mr. Richmond’s amounts of these three items. The
appellant, however, has not agreed to any deduction for heating. Heating, of
course, would have had to have been installed before the white plaster was put
on and that white plaster was required by the terms of the contract to have
been completed before the fourth instalment was due.
Mr. Richmond in his statement gave a figure
of $2,385 as being the amount necessary to complete the heating, but he agreed
in his evidence that of that amount $1,400 was paid for an air conditioning
unit not part of the original contract and he agreed also with the suggestion
of counsel for the plaintiff at the trial that “a little less than $1,000 was
charged in respect of heating”. Deducting the $1,400 from $2,385 one finds a
balance of $985 and I am of the
[Page 461]
opinion that the appellant must also submit to a
deduction of that sum. Therefore, I am of the opinion that the appellant has
proved a quantum meruit as follows:
|
Balance of third
draw.............................
|
|
$ 4,000.00
|
|
Fourth draw.............................................
|
|
12,000.00
|
|
|
|
|
|
|
|
|
|
Deduct:
|
|
|
|
Heating...............................................
|
$ 985.00
|
|
|
Balance
plumbing..............................
|
2,262.50
|
|
|
“plaster................................
|
910.00
|
|
|
“electrical............................
|
800.00
|
|
|
|
|
|
|
|
|
$ 11,042.50
|
Therefore, the quantum meruit claim
proved was $11,042.50. In addition, the appellant is entitled to two amounts:
Firstly, the amount of $2,495 for repair of storm damage, and secondly, $950
for extras supplied at the request of the respondents. The Court of Appeal
found in favour of the appellant in both of these items and such a finding
would seem to be in accordance with the evidence. The appellant admits that the
respondents have paid mechanics’ liens in the amount of $2,320 which sum must
be deducted from any recovery of the appellant. Therefore, allowing to the
appellant his quantum meruit proof of $11,042.50 and adding thereto the
storm damage of $2,495 and the extras of $950 but deducting therefrom the liens
paid by the respondents one reaches a total amount due to the appellant of
$12,167.50.
This would appear to dispose of the issues in
this appeal with one exception. As I have pointed out, the learned Master found
that the defects in the work done by the appellant were minor and easily
rectified, and McGillivray J.A., in the Court of Appeal adopted this finding.
The respondents are, however, entitled to claim a reduction for the cost of
correcting such defects. Therefore, I would allow the appeal and direct that
the report of the Master be amended by the deletion of the sum of $1,125
appearing in the first paragraph of the report and replacing that sum with the
sum of $12,167.50 unless within thirty days of the delivery of this judgment
the respondents proceed with a reference before the Master of the Supreme Court
of
[Page 462]
Ontario to determine the
costs of the correction of the said minor defects. In that event the sum to be
inserted should be the said $12,167.50 less the cost of correcting the defects
found by the Master upon such reference. The cost of the reference should be
determined by the Master in his report.
The appellant is entitled to the costs granted
to him by the order of the Court of Appeal for Ontario and to his costs in this Court. The cross-appeal is dismissed
without costs.
Appeal allowed with costs;
cross-appeal dismissed without costs.
Solicitors for the plaintiff, appellant:
Day, Wilson, Campbell &
Martin, Toronto.
Solicitors for the defendants, respondents:
Timmins & Bristow, Toronto.