Supreme Court of Canada
Miller v. Advanced Farming Systems Ltd., [1969] S.C.R.
845
Date: 1969-05-16
Stanley Miller (Defendant) Appellant;
and
Advanced Farming
Systems Limited (Plaintiff) Respondent.
1969: March 21, 24; 1969: May 16.
Present: Cartwright C.J. and Martland,
Judson, Hall and Spence JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
ONTARIO.
Mechanics’ liens—Enforcement action—Contract
for erection of dairy barn complex—Substantial deficiencies—Measure of
damages—Amount to which lienor entitled—The Mechanics’ Lien Act, R.S.O. 1960,
c. 233.
In a mechanics’ lien action in which the
plaintiff’s claim was for the sum of $25,984.60, being the cost of services and
materials supplied in building certain farm buildings for the defendant under a
written agreement between the parties, the trial judge gave judgment for the
plaintiff in the sum of $22,654.60 together with interest and costs. On appeal,
the Court of Appeal affirmed the trial judgment and the defendant then appealed
to this Court.
Having held that the concrete work generally
was substandard, the trial judge concluded that although the work had not been
done as called for in the contract that there had been substantial performance
and that the plaintiff was entitled to be paid under the contract the amount
provided for therein, giving credit for any deficiencies that he found to exist
in the work. He thereupon proceeded to make what he called reasonable
allowances for a number of so-called deficiencies which were, in fact, very
serious defects in the whole of the concrete work and in other areas.
Held: The
appeal should be allowed and the judgment at trial varied.
The correct measure of the defendant’s
damages was the cost of making good the defects and omissions in the work the
plaintiff contracted to do. Applying this principle, the Court found that the
total of the amounts which the defendant was entitled to was $13,423. Deducting
this amount from the plaintiff’s net claim of $25,984.60 left a balance of
$12,561.60 that the plaintiff was entitled to recover under its lien.
Hoenig v. Isaacs, [1952] 2 All E.R. 176; H. Dakin & Co., Ltd., [1916] 1
K.B. 566, applied.
APPEAL from a judgment of the Court of Appeal
for Ontario, affirming a
judgment of Robinson D.C.J., sitting as Local Judge, in an action for enforcement
of a mechanics’ lien. Appeal allowed; judgment at trial varied.
Joseph A. Mahon, Q.C., for the defendant,
appellant.
G.W. Cameron, for the plaintiff,
respondent.
The judgment of the Court was delivered by
HALL J.:—This is an appeal in an action for
enforcement of a mechanics’ lien filed on the appellant Miller’s farm
[Page 846]
property in the District of Temiskaming. The
action was tried by His Honour J.B. Robinson, sitting as Local Judge of the
Supreme Court, who declared that the respondent was entitled to a lien under The
Mechanics’ Lien Act, R.S.O. 1960, c. 233, on the lands of the appellant for
the sum of $22,654.60 and interest at 7 per cent from February 8, 1966,
together with costs to be taxed on the Supreme Court scale. The appellant
Miller appealed to the Court of Appeal for Ontario, and that Court, on January 19, 1968, affirmed, without written
reasons, the judgment of His Honour Judge Robinson. The appellant now appeals
to this Court.
The validity of the mechanics’ lien was disputed
at the trial, but the respondent’s right to a lien was upheld by his Honour
Judge Robinson. This issue was not argued before us, and I will deal with the
matter on the basis that the lien was properly filed.
The parties entered into a contract in writing
dated October 5, 1965, whereby
the respondent agreed to erect for the appellant a dairy barn complex on the
appellant’s farm. The contract contained specific plans and specifications for
the buildings and equipment to be installed therein. The contract called for
four buildings as follows:
(a) Cattle Feeding Building,
50′ x 40′ x 19′ eave height called the feed barn;
(b) Free Stall Barn, 75′ x 50′ x
9′ eave height (the loafing area);
(c) Milking Parlour, 40′ x 15′ x
9′ eave height;
(d) Milkhouse, 20′ x 20′ x 9′
eave height.
The appellant who had limited experience as a dairy
farmer relied on the respondent to build him a barn complex of good quality and
in accordance with the regulations of The Milk Industry Act of Ontario,
R.S.O. 1960, c. 239. The specifications provided that all the concrete work was
to be 3,000 p.s.i. The respondent did not do the work itself but employed a
subcontractor. On the completion of the work, the appellant took the position
that the contract had not been fulfilled and that the work had not been done in
accordance with the plans and specifications, and, in particular, the concrete
work was very deficient and that the whole job had been done in a negligent
manner.
[Page 847]
The learned trial judge, after a relatively long
trial and having heard evidence on behalf of the appellant and the respondent,
held as follows:
A careful review of the evidence has
impelled me to the conclusion that the concrete work generally was substandard
in that the psi rating was below specifications, the porosity of the floors was
too high as indicated by the absorption factor and the finish upon the floors
in the milk parlour and milk house was inadequate.
It appears that these defects were
contributed to by the use of pit run gravel to begin with, by the failure to
increase the strength by compensating for this by using more cement (e.g. three
to one instead of four to one), by inconsistent batching and lack of control
over the concrete mix, by failure to remove large stones from the gravel and by
pouring the cement in cold frosty weather with inadequate precautions to keep
it from freezing.
Indeed of four holes drilled for cores in
the two outside slabs only one hole permitted the recovery of a core and that
one was not suitable for a compression test.
The tests indicated that the concrete in
the outside slabs were very weak ranging from below 1,000 psi for three holes,
to below 1,590 psi for one hole.
The natural inference from the evidence as
to the outside concrete slabs was that they had been poured upon frozen ground
and that the frost had affected the curing of the cement.
Having so held, he concluded that although the
work had not been done as called for in the contract that there had been
substantial performance and that the respondent was entitled to be paid under
the contract the amount provided for therein, giving credit for any
deficiencies that he found to exist in the work. He thereupon proceeded to make
what he called reasonable allowances for a number of so-called deficiencies
which were, in fact, very serious defects in the whole of the concrete work and
in other areas. In my view this is a case in which the learned trial judge
might well have found that the contract had not been substantially performed,
but he did not do so, and, as stated, found that he could apply the doctrine of
substantial performance. That position was accepted by the appellant in this
Court and the case remains to be determined on the basis that the finding of
substantial performance is valid. However, having found that there were
substantial deficiencies, the learned trial judge proceeded to allow deductions
from the contract price therefor on a completely erroneous principle. Having
found that the concrete work was wholly unsatisfactory, he went on to say that
in lieu of having it replaced that it would be made serviceable by the application
of
[Page 848]
some surface treatments by patching up and
coating over and that that was all that the circumstances required.
The correct measure of damage in a case such as
the present one was stated by Lord Denning in Hoenig v. Isaacs, where from the principles laid down
in H. Dakin & Co., Ltd. v. Lee
he stated:
The measure is the amount which the work is
worth less by reason of the defects and omissions, and is usually calculated by
the cost of making them good.
or as Pickford L.J. said in Dakin v. Lee, at
p. 582:
…the case must go back… in order that it
may be ascertained what is the expenditure necessary, first, to put this
underpinning right and make it accord with the contract both in regard to
quality and quantity, and, secondly, to do the work which ought to have been
done…Supreme Court of Canada
Further, Ridley J., quoting Parke J. said in the
same case at p. 571:
“What the plaintiff is entitled to recover
is the price agreed upon in the specification, subject to a deduction; and the
measure of that deduction is the sum which it would take to alter the work, so
as to make it correspond with the specification.”
In my view the measure of the appellant’s damage
is the cost of making good the defects and omissions in the work which the
respondent contracted to do.
The learned trial judge found that the area of
concrete which was in the milk parlour, platform, free stall area, outside
slabs, curbs and gutters was 5,300 square feet. The evidence of Helmer
Pedersen, a masonry contractor of 18 years’ experience, was that it would cost
50¢ per square foot to remove the deficient concrete and $1 per square foot to
put in new concrete. The appellant is accordingly entitled to an award of
$7,950 under this heading in lieu of the $2,285 allowed him by the learned
trial judge.
In addition to the deficient concrete work, the
learned trial judge found that the walls of the milk house did not meet
contract specifications in that they were not impervious to liquids up to three
feet from the floor. The area to be altered in this respect was 133 square
feet. He allowed $1.20 per square foot as a reasonable estimate to remedy the
defect for a total of $160 and that amount should stand.
The learned trial judge also found that the
contract had not been performed as to the exterior door, the screen door
[Page 849]
and the ceiling of the milk house and he allowed
$75 for these items. However, Lorne M. Jelly, a local carpenter and contractor,
whose evidence would appear to be credible, estimated it would cost $620 to alter
the building and put in five windows and a proper door in accordance with the
plans. I think that this is the amount which should be allowed which, with the
$160 to make the walls of the milk house impervious to liquid, comes to $780.
The taking out of the concrete flooring in the
milk parlour will necessitate the replacement of the floor heating coil at a
cost of $358, according to the evidence of John A. Brown, the electrician who
installed the electric cable originally. A claim for loss of heat and additional
cost of electrical energy would be eliminated by placing the floor heating coil
where it was intended to be placed by the specifications, and the appellant
would, therefore, suffer no loss of heat or incur any additional expense for
electrical energy. He is, however, entitled to the cost of replacing the floor
heating coil at the figure of $358.
Replacing the concrete also involves removing,
storing and reinstalling the stalls and equipment in the milk room and milk
parlour. The witness Albert Cooper, a dairy farm equipment dealer, testified
that it would cost $2,645 to dismantle and store the equipment, to set up the
stalls, to reinstall the milking equipment, and to take out and put back the
auto-feed system as well as the electrical controls.
The learned trial judge made certain minor
allowances as follows which should not be disturbed:
|
(a)
|
Reinstalling
the stalls in the free stall area..........................................................
|
$ 65.00
|
|
(b)
|
Deficiency in
insulation in the ceiling of the free stall barn.................................
|
35.00
|
|
(c)
|
Defects in
the construction of the feed barn and manger being short posts and other
minor matters................................................................................................
|
75.00
|
|
(d)
|
For a
defective beam and rafters in the feed barn..............................................
|
15.00
|
The learned trial judge also found that the
gutters in which the barn cleaner operated were of such poor quality that the
barn cleaner was constantly breaking down and could not run properly. He
allowed $160 under this heading. The witness, Jean Trudel, a farm machinery and
equipment dealer who supplied the barn cleaner, testified that the chain which
should have lasted 15 years was almost worn out at the end of two years and
required replacing.
[Page 850]
The cost of the chain was $1,232 and with
installation would come to $1,500. This amount should be allowed in lieu of the
$160 fixed by the learned trial judge.
If is manifest that when all of the work has
been redone, the appellant will not have the kind of modern dairy barn complex
that he contracted for, but there was no evidence as to whether there was any
actual loss in this regard or how it could be estimated, and I do not find it
possible in the circumstances to make an award under this heading.
The total of the amounts which I find the
appellant is entitled to is $13,423 and he is entitled to have this amount
deducted from the respondent’s net claim of $25,984.60 as found by the learned
trial judge which leaves a balance of $12,561.60 that the respondent is
entitled to recover under its lien. The judgment of the learned trial judge
should be varied by substituting the sum of $12,561.60 for the sum of $22,654.60
where this figure appears in the formal judgment of the Court. The respondent
will also be entitled to interest on the sum of $12,561.60 at the rate of 5 per
cent per annum from the date of the judgment, namely, March 1, 1967.
As success at the trial was divided, I would
direct that there be no costs to either party at the trial. The appellant is
entitled to his costs in the Court of Appeal and in this Court, the amount
thereof to be set off against the amount which the respondent is entitled to recover.
Appeal allowed; trial judgment varied.
Solicitor for the defendant, appellant:
Joseph A. Mahon, Toronto.
Solicitors for the plaintiff, respondent:
Clement, Eastman, Dreger, Martin & Meunier, Kitchener.