Supreme Court of Canada
Travelers Indemnity Company v. Foley Brothers (Canada)
Limited et al., [1969] S.C.R. 56
Date: 1969-10-07
The Travelers
Indemnity Company (Defendant) Appellant;
and
Foley Brothers
(Canada) Limited and C.A. Pitts General Contractors Ltd. (Plaintiffs) Respondents;
and
Stormont General
Contractors Limited Mise-en-cause.
1969: May 26, 27, 28, 29; 1969: October 7.
Present: Fauteux, Abbott, Judson, Spence and
Pigeon JJ.
ON APPEAL FROM THE COURT OF QUEEN’S BENCH,
APPEAL SIDE, PROVINCE OF QUEBEC
Insurance—Performance bond—Sub-contract for
clearing and grubbing of railway right of way—Operations suspended and finally
abandoned—Action claiming amount of bond—Sub‑contractor in
default—Liability on the performance bond—Quantum of damages.
The plaintiffs, F and P, entered into a
contract to build a railroad and awarded a sub‑contract to S for the
clearing and grubbing of the right of way. S provided a performance bond issued
by the defendant T in the amount of $896,723. S began operations in September
1958 and suspended them in February, alleging that it was unable to continue
because of severe snow conditions. After negotiations with F and P, S resumed
work but eventually abandoned all work, alleging breach of contract. F and P
instituted the present action against T as S’s surety claiming the full amount
of the performance bond. The trial judge and the Court of Appeal found that S
was in default and was liable for the damages, and also that T was liable under
its performance bond. The trial judge awarded an amount of $820,332.10, but
this was reduced by the Court of Appeal to $606,873.80. The defendant T
appealed to this Court and the plaintiffs F and P cross appealed.
[Page 57]
Held: The appeal should be dismissed and the
cross-appeal allowed.
There was ample evidence to support the
findings of the two Courts as to liability, and they should not be disturbed.
T’s contention that the claim of F and P for
overhead, calculated at 30.62 per cent of direct costs, was excessive, must be
rejected. There was evidence upon which the trial judge and the majority in the
Court of Appeal could make the finding which they did as to the basis upon
which overhead was calculated.
There are concurrent findings that S was not
entitled to an additional credit for grubbing done outside areas designated by
the owner.
The obligations undertaken by F and P in a
subsequent agreement to increase the unit price for clearing were conditional
obligations within the meaning of art. 1079 of the Civil Code and
never took effect. It follows that the subcontract was not amended.
APPEAL and CROSS-APPEAL from a judgment of the Court of
Queen’s Bench, Appeal Side, province of Quebec,
allowing an appeal from a judgment of Robinson J. Appeal dismissed and
cross-appeal allowed.
Walter C. Leggat, Q.C., and Joseph Nuss,
for the defendant, appellant.
Ruston B. Lamb, Q.C., and Pierre
Sébastien, for the plaintiffs, respondents.
The judgment of the Court was delivered by
ABBOTT J.—This appeal is from a majority
judgment of the Court of Queen’s Bench (Appeal Side)1, rendered on
July 26, 1968, allowing the appellant’s appeal in part, and reducing the amount
of the judgment at trial to $606,873.80. The judgment of the Superior Court
rendered on June 25, 1965, had condemned the appellant to pay respondents
$820,332.10 with interest and costs. The respondents cross-appealed and asked
that the trial judgment be restored.
For convenience, I shall refer to the appellant
as The Travelers, to the respondents
[Page 58]
as Pitts-Foley, and to the mise-en-cause as
Stormont.
The facts are fully reviewed in the judgments
below. Shortly stated they are as follows: On September 8, 1958, Pitts-Foley
entered into a contract with Quebec Cartier Mining Company, to build a railroad
from Shelter Bay on the north shore of the St. Lawrence River to a mining
property located at Lac Jeannine. Pitts-Foley in turn entered into a number of
subcontracts, including one with Stormont dated October 21, 1958, for the
clearing and grubbing of the right of way. It was a condition of this contract
that Stormont would provide a performance bond and this bond was issued by The
Travelers on September 16, 1958, in an amount of $896,723.
Stormont began operations in September 1958,
prior to the signing of the subcontract, and continued the work until February
27, 1959, when it suspended operations, alleging that it was unable to continue
because of severe snow conditions. After negotiations with Pitts‑Foley,
Stormont resumed work on April 17 and continued, after a fashion, until early
in July 1959, when it abandoned all work alleging breach of contract by
Pitts-Foley.
In August 1960, Stormont sued Pitts-Foley for
$657,142.24 as damages for breach of contract and alternatively claimed
$494,000 as the value of the work done. In September 1960, Pitts‑Foley
countered with an action against Stormont for $1,212,648.77 as damages for
breach of contract. At the same time, Pitts-Foley instituted the present action
against The Travelers as Stormont’s surety claiming $896,723, the full amount
of the performance bond. After issues were joined, Pitts-Foley moved to join
all three actions for trial at the same time. The two actions between
Pitts-Foley and Stormont were ordered to be joined for trial, but for some
reason which I cannot understand the application was refused with respect to
the action against The Travelers.
[Page 59]
The Stormont and Pitts-Foley actions were tried
before Mr. Justice André Demers who, after a long trial, rendered two
judgments on July 28, 1964, maintaining Pitts-Foley’s action and dismissing
Stormont’s action. The amount of the damages assessed against Stormont,
$843,122.48, was not an assessment by the trial judge, but resulted from a
consent entered into by the parties before judgment. The Travelers, which was
intervenant in Stormont’s action against Pitts-Foley, did not sign this consent
and it is a common ground that it is not bound by it.
Appeals were entered by Stormont from these two
judgments and are still pending, awaiting the result of the appeal in this
action.
After judgment in the Stormont actions,
Pitts-Foley moved to bring the present case on for trial, which took place
before Mr. Justice Robinson, during a period extending from January to
May, 1965; the parties agreed that all the depositions taken and all the exhibits
filed in the Stormont cases would serve as evidence in this case with the right
reserved to each party to call additional evidence. Both parties called
additional evidence and filed additional exhibits.
Judgment was rendered on June 25, 1965,
condemning The Travelers to pay $820,332.10, the amount claimed by Pitts-Foley
in its action, together with interest from the institution of the action, and
costs. From this judgment, The Travelers appealed to the Court of Appeal and,
as I have said, judgment was rendered on July 26, 1968, allowing the appeal to
the extent of $213,458.30, and reducing the judgment of the Superior Court to
$606,873.80.
The learned trial judge and all the judges in
the Court below were unanimous in finding (1) that Stormont was in default
to perform its obligations under its subcontract with Pitts‑Foley and (2)
was liable for the damages sustained by the latter—a view shared by Demers J.
in the Stormont cases. The learned trial judge and all the judges in the Court
of Queen’s Bench also held that The Travelers was liable under its Performance
Bond.
[Page 60]
There was ample evidence to support those
findings and I would not disturb them. There remains therefore only the
question as to the quantum of damages.
On the question of quantum, the principal issues
raised by The Travelers before the Court of Appeal and before this Court were
(1) Pitts-Foley’s claim for overhead, calculated at 30.62 per cent of direct
costs, which The Travelers contended was excessive (2) an additional credit for
clearing on the basis that such credit should be calculated at the rate of
$202.70 per acre, and not $157.60 per acre as provided in the subcontract, and
(3) an additional credit for grubbing done outside areas designated by the
owner. The additional credit claimed under this last head was $225,684.
As I have stated, the Court below was unanimous
as to The Travelers’ liability. The majority (Tremblay C.J. and Montgomery J.)
held that The Travelers was entitled to an additional credit for clearing, of
$213,458.30, and reduced the damages awarded at trial by that amount.
Montgomery J., dissenting in part, would have allowed a further credit by
disallowing in part Pitts-Foley’s claim for overhead. Rivard J., dissenting,
would have confirmed the trial judgment and dismissed the appeal.
From this summary, it will be seen that there
are concurrent findings that Stormont was not entitled to the additional credit
for grubbing. This question is fully discussed in the reasons of Rivard J.,
which on this point were concurred in by Tremblay C.J. and Montgomery J. I am
in agreement with those reasons and there is nothing I could usefully add.
As to the basis upon which overhead was
calculated, there was evidence upon which the trial judge and the majority in
the Court of Appeal could make the finding which they did. I agree with that
finding.
As I have stated, Pitts-Foley cross-appealed
from the majority decision in the court below which reduced the damages awarded
at trial from $820,332.70 to $606,873.80. That finding was
[Page 61]
based upon the interpretation and effect of an
agreement dated April 13, 1959, under the terms of which, subject to certain
conditions, the unit price to be paid to Stormont for clearing the right of way
might be increased from $157.60 per acre to $202.70.
Stormont in breach of its subcontract had
abandoned work at the end of February 1959 giving as its reason severe weather
conditions. It seems clear, however, that the real purpose of the suspension
was to force price concessions from Pitts-Foley. Be that as it may, the latter
made every effort to get Stormont back on the job and a series of proposals and
counter-proposals culminated in an agreement evidenced by a letter dated April
13, 1959.
That letter reads:
Stormont General Contractors Limited,
2345 Viau Street,
Montreal, P.Q.
Attention: Mr. J.G. Joncas,
President.
Gentlemen:
This will confirm the arrangements made
between us concerning the clearing to be done by you in connection with the
construction of the railway facilities from Shelter Bay, Quebec to Lac Jeannine
under the contract between ourselves dated October 21, 1958. Subject to
compliance by you with all the conditions stipulated in this letter and in the
event of your actual cost for such clearing exceeding the contract price at the
specified rate of $157.60 per acre, we shall, in lieu of such contract price,
pay you your actual cost for such clearing not exceeding $202.70 per acre as
determined and certified by our auditors.
Future payments for clearing shall be made
as follows:
I. We shall make progress payments under
Article IV of the contract on the basis of the unit price of $157.60 per
acre;
II. When all acres to be cleared under the
contract have been felled and stacked we shall within 30 days of acceptance of
such acres by the owners pay such additional sum as may be required to adjust
the unit per acre to your actual cost for clearing, to the extent above
provided, as determined and certified
[Page 62]
by our auditors, less all amounts withheld
by the Owners to cover burning not completed;
III. When all burning has been completed
and accepted by the Owners we shall pay any balance then due to you for
burning.
The conditions stipulated are that:
(a) You shall recommence on or
before the 20th day of April, 1959, continue without interruption and complete
all your work under the contract in accordance with work schedules to be
submitted by you and approved by us as conforming with the requirements of
provision 16 of Appendix “A” to the contract;
(b) You shall supply evidence
acceptable to us on or before the 20th day of April 1959 that the principal
amount of the Performance Bond with The Travelers Insurance Company, provided
by you under the contract, covers complete performance of the work and payment
therefor as provided above;
(c) You shall give our auditors
access to your books and records at any time during business hours for the
purpose of determining your actual costs of clearing.
Also subject to your compliance with the
above conditions, we undertake to deduct from the total clearing to be
performed by you under the contract the total of the acres cleared by us for
you during the suspension of your operations since March 2, 1959. We shall
assume the entire cost of such clearing done by us and retain all payments
received by us from the Owners in respect thereof.
This letter, when accepted by you, will
constitute a binding agreement between us and except as expressly modified
hereby our contract of October 21, 1958 shall remain in full force and effect.
If this letter is acceptable to you, kindly
sign the enclosed copy and return it to us.
Very truly
yours,
PITTS-FOLEY
mc:
L.G. Lofholm,
Vice-President.
ACCEPTED
this day
of 1959.
STORMONT GENERAL
CONTRACTORS LIMITED
per: J. Gerard
Joncas
[Page 63]
The Travelers Indemnity Company hereby
consents to the modification outlined in this letter.
Oscar
H. Gaudet
OSCAR
H. GAUDET
Attorney-in-fact
The obligations undertaken by Pitts-Foley in
that letter, in my opinion, were conditional obligations within the meaning of
art. 1079 of the Civil Code and never took effect. Rivard J. stated
the position accurately and concisely when he said:
[TRANSLATION] Work started again on April
13, 1959, but was abandoned for good on July 6, 1959. Grubbing was resumed only
on May 23 and was obviously stopped also on July 6. The conditions laid down by
Pitts-Foley in the April 13 agreement were not complied with by Stormont, and
Pitts-Foley cannot be considered in default by paying to Stormont only the
prices stipulated in the original contract.
It follows that the subcontract between Stormont
and Pitts-Foley was not amended and, in establishing its claim for damages,
Pitts-Foley was not obliged to pay or to credit Stormont with any unit price
for clearing other than that provided for in the subcontract dated
October 21, 1958.
For the foregoing reasons and for those of
Rivard J., with which I am in agreement, I would dismiss the appeal and allow
the cross-appeal in both cases with costs.
Appeal dismissed with costs; cross-appeal allowed with
costs.
Solicitors for the defendant, appellant:
Foster, Watt, Leggat, Colby, Rioux & Malcolm, Montreal.
Solicitors for the plaintiffs, respondents: Lafleur &
Brown, Montreal.