Supreme Court of Canada
Fairbanks Soap Co. Ltd. v. Sheppard, 1953 1 S.C.R. 314
Date: 1953-03-02
Fairbanks Soap
Company Limited (Plaintiff) Appellant;
and
Mel Sheppard (Defendant)
Respondent.
1952: October 22, 23, 24; 1953: March 2.
ON APPEAL FROM THE COURT OF APPEAL FOR
ONTARIO.
Contract—Agreement to construct machine—Work
not completed—Abandonment of Contract—Right to recover.
The defendant, a mechanical engineer,
contracted with the plaintiff, a manufacturer of soap, to construct in the
plaintiff’s plant a machine for making and drying soap chips for a price of
$9,800, payable $4,000 in cash on completion and the balance to be secured by
promissory notes. When the work was nearly completed the defendant, who had
been paid $1,000 on account, refused to do anything more until paid a further
$3,000.
[Page 315]
Held: On the
view of the evidence most favourable to the defendant, he deliberately
abandoned the contract at a stage when the machine would not perform the work
for which it had been ordered and when what remained to be done required the
exercise of engineering skill and knowledge. Under such circumstances it could
not be said that he had substantially completed his contract. Appelby v.
Myers L.R. 2 C.P. 651; Sumpter v. Hedges [1898] 1 Q.B. 673 at
674; Dakin v. Lee [1916] 1 K.B. 566, applied.
Decision of the Court of Appeal for Ontario
[1951] O.R. 860, reversed.
APPEAL from the judgment of the Court of
Appeal for Ontario,
affirming the judgment of Genest J. at the trial dismissing the plaintiff’s
action and awarding judgment to the defendant on his counterclaim.
W.B. Williston for the appellant.
J.D. Arnup, Q.C. and J.S. Boeckh for the
respondent.
The judgment of the Court was delivered by
CARTWRIGHT J.:—The appellant is a manufacturer
of soap and the respondent is a mechanical engineer. This action arises out of
an agreement between the parties for the construction by the respondent in the
plant of the appellant of a machine for making and drying soap chips. There is
also a claim made by the respondent for $1,000 for the “installation” of the
machine in question and of certain pulleys, hangers and shafting to be supplied
by the appellant which requires consideration but it will be convenient first
to dispose of the questions relating to the contract for the construction of
the machine itself. It was a term of the contract that the type of design of
the machine and the products produced by it should be “of the standard
generally used and produced by all the large soap producers on this continent.”
It is now common ground that this was an entire contract to construct the
machine for a price of $9,800 payable $4,000 in cash on completion and the
balance to be secured by promissory notes. For the reasons given by Roach J.A.
I agree with his conclusion, which was also that of the learned trial judge,
that the contract was not one for the sale of goods but for work to be done and
materials supplied.
The contract was made in September 1945. No date
for completion was fixed. For reasons with which we are not now concerned there
were numerous and lengthy delays
[Page 316]
in building the machine. By March 1, 1949,
according to the evidence of the respondent, the work had progressed to a point
where the supplying of a small number of parts and the performance of a few days
work would have resulted in the completion of the machine. At this point the
respondent took the position that he would do nothing more unless and until he
was paid $3,000, which, added to $1,000 which had been paid to him in November
1946, would make up the payment of $4,000 which was due on completion. The
explanation of this given by the respondent at the trial was that he was afraid
that if he completed the machine so that the appellant no longer required his
services in connection with it he would not be paid. The appellant offered to
deposit the sum mentioned in escrow to be paid to the respondent on completion
of the machine but the respondent refused to proceed unless payment was made to
him. By letter dated March 25, 1949 the appellant required the respondent to
complete his contract by April 30, 1949 stating in part that unless he did so:—
… we shall cancel the contract and require
you to remove this machine from our premises, and request you to return the
$1,000 paid to you, and further reimburse us for the time our employees worked
on this machine with your employees, at your request, and for materials
supplied at your request.
The letter concluded with the following
paragraph:—
If for any reason the time limit fixed by
us for completion of the machine is unreasonable or insufficient, we would ask
you to kindly advise us at once, otherwise we shall presume that we have given
you reasonable time for so doing, and will act accordingly.
Counsel for the respondent does not suggest that
the date fixed by this letter for completion was unreasonable. His submission
is that the contract was already substantially completed. The respondent did
nothing further and on May 11, 1949 the appellant commenced this action. The
Statement of Claim recites the contract, alleges that the machine had never
been constructed or completed and claims:—
(a) A declaration of this court that
the contract between the parties hereto and dated the 21st of September, 1945,
has been cancelled,
(b) The sum of $1,000 paid to the
defendant.
(c) The sum of $700, value of floor
space in the plaintiff’s factory, used by the defendant.
(d) The sum of $137.11 the
value of materials supplied by the plaintiff to the defendant at his request.
[Page 317]
(e) The sum of $355.77 being value
of materials purchased by the plaintiff as aforesaid less their salvage values
and wasted by reason of the failure of the defendant to complete such machine.
At the opening of the trial the following claim
was added by amendment, (e) (1) the sum of $1,191.80 the cost of labour
referred to in paragraph 9 of the Statement of Claim. The relevant sentence in
paragraph 9 is as follows:
The plaintiff further supplied labour at
the request of the defendant in the construction of such machine, such labour
costing the plaintiff the sum of $1,191.80.
There was an alternative claim for $15,000
damages, presumably to cover the contingency of its being held that the
appellant had to accept and pay for the machine.
Paragraph 5 of the Statement of Defence reads as
follows:—
The defendant says and the fact is that he
has manufactured upon the premises of the plaintiff a machine as specified in
the said agreement referred to in paragraph 3 of the statement of claim and
that the plaintiff is now obliged to accept and pay for the same.
The respondent asked that the action be
dismissed and counterclaimed (a) $9,584 being the contract price of
$9,800 plus $784 sales tax less $1,000 paid on account, (b) $1,000 for
“installation” as mentioned above and (c) $500 paid by the respondent
for labour which he claimed should have been supplied by the appellant.
The learned trial judge held that “there was a
substantial compliance with the contract” by the respondent, that there was no
abandonment of the work by him, and no total failure of consideration, and that
the respondent was entitled to be paid the contract price “less the cost of
completing the machine, etc. and putting it in working order,” which last
mentioned cost he fixed at $600. He allowed the respondent’s claim on the
separate contract at $1,000 and on his claim of $500 he allowed him $200.
Judgment was accordingly given for the respondent on his counterclaim for these
amounts totalling $10,184, with costs, and the action was dismissed with costs.
This judgment was affirmed by the Court of Appeal and the plaintiff now appeals
to this Court.
I did not understand counsel to differ as to the
present state of the law in Ontario but rather as to its application to the
facts of the case at bar. In Appleby v. Myers,
[Page 318]
a decision of the Exchequer Chamber in which the
unanimous judgment of the Court, Martin B., Blackburn J., Bramwell B.,
Shee and Lush JJ., was delivered by Blackburn J., that learned judge stated the
general rule at page 661, as follows:—
... the plaintiffs, having contracted to do
an entire work for a specific sum, can recover nothing unless the work be done,
or it can be shown that it was the defendant’s fault that the work was
incomplete, or that there is something to justify the conclusion that the
parties have entered into a fresh contract.
The judgment in Appleby v. Myers was
approved and acted upon by the Judicial Committee in Forman & Co.
Proprietary Ltd. v. The Ship “Liddesdale”,
particularly at page 202. In Sumpter v. Hedges, A.L. Smith L.J. said:—
The law is that, where there is a contract
to do work for a lump sum, until the work is completed the price of it cannot
be recovered.
This rule was recognized by the Court of Appeal
in H. Dakin and Co. Ltd. v. Lee, but it
was pointed out that the word “completed” as used in the rule is, in certain
circumstances, equivalent to “substantially completed”. The judgments in Dakin
v. Lee have been repeatedly approved and followed in Ontario, vide e.g.
Taylor Hardware Co. v. Hunt, and in
my respectful opinion they correctly state the law.
The real question on this appeal is whether the
respondent substantially completed his contract to construct the machine. With
the greatest respect for the contrary view held by the learned trial judge and
the Court of Appeal, I have reached the conclusion that he did not. From a
perusal of the written record I would have inclined to the view that the
evidence of the appellant’s expert witness Mitchell, who was of opinion that
the machine when completed would not be capable of producing soap chips of
commercial quality should be preferred to that of the experts called by the
respondent not only because of his admittedly high qualifications but because
he appeared to have based his opinion on a much more thorough examination of
the machine than was made by the other witnesses; but I do not rest my judgment
on this view. In my opinion
[Page 319]
on the evidence of the respondent himself and of
the witnesses called on his behalf there was no substantial completion of the
contract. At the time when the respondent definitely refused to proceed further
with the construction of the machine it was incomplete in the following
respects: the “knife” and “flange” were missing, baffles were required for the
canvas apron screening of the dryer, further work was required on the fans and
the speed of the machine had to be changed, being about six times as fast as
was proper. It is urged on behalf of the respondent that these are
comparatively unimportant details and that the allowance of $600 for the completion
of the machine made by the learned trial judge is a generous one. But it
appears from the evidence of the respondent and his witnesses that what
remained to be done required engineering skill and knowledge. The record is
silent as to whether the services of an engineer other than the respondent
possessing the necessary skills were available to the appellant. The situation
was, I think, accurately summed up in the following answer made in
re-examination by the expert witness Stokes called for the respondent:—
I think I know what both you gentlemen are
trying to get at, and let me put it this way, it may not be legal or it may not
be orthodox, but I am going to say this, if Fairbanks and Sheppard do not get
together that machine will never run, it has to depend on the co‑operation
of two individuals just the same as ours at Guelph. If we had sat on the
sidelines looking at it, it would never run. We had to co-operate with Sheppard
and he had to co-operate with us. Everyone has to co-operate to operate the machine.
The respondent in his own evidence makes it
clear that he decided to desist from further construction at a time when the
machine was not capable of producing soap chips and to refuse to bring it to
the state where it would produce them unless and until he was paid moneys to
which under the contract he was not then entitled. He says in effect that he
had intentionally put in sprockets of the wrong size so that the appellant
could not use the machine to produce chips. After stating that one reason for
putting in a small sprocket was to “run the machine in” he added that he had
another reason. He was questioned as to this by the learned trial judge as
follows:—
His Lordship: You asked him what reason and
he is not finished his answer. A. Will I give the other reason?
Q. Yes.
[Page 320]
A. Because of the fact if I had gone and
put the proper speeds on that dryer and I had put the knife on the dryer and
operated that dryer producing chips, from my previous experience about the loan
on the machine, with my dealings with Mr. Fairbanks with the machine, I
had come to the firm conclusion I would have been locked out of the plant the
same as Arneil, I would have been locked out and I would have had to sue him
for my money. He could have fooled around for years and been making soap chips
at my expense. I have $6,000 tied up in the machine and I think I have a right
to get something out of it before I operate it and he could go on and operate
it for years.
I can find nothing in Dakin v. Lee (supra) or
in the numerous other authorities referred to by counsel to indicate that under
all these circumstances it could be said that the respondent had substantially
completed his contract. The contract was to construct a machine to produce soap
chips of a certain standard. The respondent refused to do anything further at a
time when on his own evidence the partially constructed machine would not
produce soap chips at all. In my opinion on the view of the evidence most
favourable to the respondent he abandoned the work and left it unfinished. The
difference between the facts of the case at bar and those in Dakin v. Lee
(supra) are apparent on reading all the judgments in the last mentioned
case, and it will be sufficient to refer to the following passage from the
judgment of Lord Cozens-Hardy M.R. at pages 578 and 579:—
In these circumstances it has been argued
before us that, in a contract of this kind to do work for a lump sum, the
defect in some of the items in the specification, or the failure to do every
item contained in the specification, puts an end to the whole contract, and
prevents the builders from making any claim upon it; and therefore, where there
is no ground for presuming any fresh contract, he cannot obtain any payment.
The matter has been treated in the argument as though the omission to do every
item perfectly was an abandonment of the contract. That seems to me, with great
respect, to be absolutely and entirely wrong. An illustration of the
abandonment of a contract which was given from one of the authorities was that
of a builder who, when he had half finished his work, said to the employer “I
cannot finish it, because I have no money,” and left the job undone at that
stage. That is an abandonment of the contract, and prevents the builder,
therefore, from making any claim, unless there be some other circumstances
leading to a different conclusion. But to say that a builder cannot recover
from a building owner merely because some item of the work has been done
negligently or inefficiently or improperly is a proposition which I should not
listen to unless compelled by a decision of the House of Lords. Take a contract
for a lump sum to decorate a house; the contract provides that there shall be
three coats of oil paint, but in one of the rooms only two coats of paint are
put on. Can anybody seriously say that under these circumstances the building
owner could go and occupy the house and take the benefit of all the decorations
which had been done in the other
[Page 321]
rooms without paying a penny for all the
work done by the builder, just because only two coats of paint had been put on
in one room where there ought to have been three?
I regard the present case as one of
negligence and bad workmanship, and not as a case where there has been an
omission of any one of the items in the specification. The builders thought
apparently, or so they have sworn, that they had done all that was intended to
be done in reference to the contract; and I suppose the defects are due to
carelessness on the part of some of the workmen or of the foreman: but the
existence of these defects does not amount to a refusal by them to perform part
of the contract; it simply shows negligence in the way in which they have done
the work.
In the case at bar when the respondent knew the
machine was not capable of producing soap chips he said to the appellant: “I
will not finish it unless you pay me $3,000.” In my opinion the conduct of the
respondent falls within the illustration of an abandonment of a contract given
by the Master of the Rolls in the above quoted passage.
Counsel for the respondent did not seek to base
any claim in regard to this contract on a quantum meruit and I think it
clear that, if, as I have held to be the case, there was no substantial
completion of the contract, there was no evidence from which any new contract
to accept and pay for the work done could be inferred. From the evidence it
seems probable that the machine in its present state has become part of the
realty which belongs to the appellant. Assuming this to be so it is clear from
the reasons in Sumpter v. Hedges that
the mere fact of the appellant remaining in possession of his land is no
evidence upon which an inference of a new contract can be founded. At page 676
Collins L.J. puts the matter as follows:—
There are cases in which, though the
plaintiff has abandoned the performance of a contract, it is possible for him
to raise the inference of a new contract to pay for the work done on a quantum
meruit from the defendant’s having taken the benefit of that work, but, in
order that that may be done, the circumstances must be such as to give an
option to the defendant to take or not to take the benefit of the work done. It
is only where the circumstances are such as to give that option that there is
any evidence on which to ground the inference of a new contract.
In the case at bar the appellant has never
elected to take any benefit available to him from the unfinished work and
Mr. Williston stated that he was willing that, in the event of his appeal
succeeding, a term should be inserted in the judgment permitting the respondent
to remove the machine within a reasonable time.
[Page 322]
For the above reasons I am of opinion that the
respondent’s claim based on the contract to construct the machine fails and
that the appellant is entitled to a declaration that the contract was cancelled
and to the return of the $1,000 paid to the respondent in November 1946.
It is next necessary to consider the appellant’s
claim for damages. The amount to which the appellant should be held entitled
was not argued before us and the best course might be to direct a reference but
in the hope of bringing the litigation to an end I have examined the evidence
and have concluded that substantial justice would be done by awarding the
appellant the total of items (d), (e) and (e)
(1) claimed in the Statement of Claim amounting to $1,684.68, but as this
branch of the matter was not fully argued before us, either party dissatisfied
with this amount may have a reference at his own risk as to costs to the Master
at Toronto to determine the amount.
It remains to consider the item of $1,000,
claimed by the respondent for “installation”, referred to in the opening
paragraph of these reasons. This item is claimed in paragraph 2 of the
counterclaim which reads as follows:—
The defendant further says that the
installation of the said machine and accessories thereto was on the basis of a
separate order from the plaintiff to the defendant for which the defendant was
to be separately paid and in respect of which the defendant is entitled to the
sum of $1,000. The plaintiff further agreed to supply labour to assist the
defendant in the installation of the said machine and failed to do so, as a
result whereof the defendant had to hire extra labour and incurred expenditures
in the sum of approximately $500.
In so far as these claims are for the
installation of the machine they must fail. Having refused to complete the
construction of the machine I can find no basis for a claim to be paid for the
installation of an incomplete machine which must now be removed. There was
however a separate agreement to be found in the letters marked as Exhibits 27,
28, 29, 30, 31 and 32 to install a motor and certain pulleys and hangers to be
used on the ceiling counter shafts for driving the dryer. Exhibit 32, a letter
from the respondent to the appellant, reads as follows:—
We acknowledge your letter of September
26th, authorizing us to proceed with the erection of pulleys, hangers and motor
for the driving members to the various sections of the dryer.
We as arranged are to supply the labour and
engineering in connection with the same but not materials, and for the sake of
record and invoicing wish to point out that this is a separate order from the
dryer proper and will be billed to you on that basis.
[Page 323]
There is no evidence of any bill having been
rendered by the respondent shewing what part of the $1,000 claimed in paragraph
2 of the counterclaim is attributable to the installation of these items and I
am unable to find much assistance in the evidence. It does appear however that
the work was done and the exhibits referred to indicate the amount of material
installed. While I feel it is little better than a guess, I would, once more in
the hope of bringing the litigation to an end, assess the amount to which the
respondent is entitled for installing the equipment in question at $200 with a
similar right to either party, if dissatisfied with this figure, to have a
reference to the Master at Toronto.
In the result the appeal should be allowed and
judgment should be entered (a) declaring that the contract between the
parties dated the 21st of September 1945 has been cancelled, (b) providing
that the appellant recover from the respondent the sum of $2,684.68, (c)
providing that the respondent shall have the right to remove the incomplete
machine from the premises of the appellant within sixty days from the date of
the delivery of this judgment, (d) providing that the respondent recover
from the appellant on his counterclaim the sum of $200; provided however that
if either party so elects within fifteen days of the date of the delivery of
this judgment in respect of either or both of items (b) and (d) above,
instead of judgment being entered for the amount above set out it shall be
referred to the Master at Toronto to determine the amount of damages in respect
of the item or items as to which such election is made.
As the appellant has succeeded substantially
both on the claim and counterclaim it should have its costs of the action and
counterclaim and of the appeals to the Court of Appeal and to this Court.
Appeal allowed.