Supreme Court of Canada
Burrard Drydock v. Canadian Union
Line, [1954] S.C.R. 307
Date: 1954-06-21
Burrard
Drydock Company Limited (Third Party) Appellant;
and
Canadian
Union Line Limited and Union Steamship Company of New Zealand Limited (Defendants)
Respondents;
and
Australian
Newsprint Mills Limited (Plaintiff).
1954: March 4, 5, 8; 1954:
June 21.
Present: Rinfret C.J. and
Kerwin, Rand, Estey and Cartwright JJ.
ON APPEAL FROM THE COURT OF
APPEAL FOR BRITISH COLUMBIA
Damages—Negligence—Third
Party proceedings—Water carrier—Carrier held liable for damages to cargo—Relief
over against negligent ship's repairer—Proximate cause of the damage—Contributory
negligence—Estoppel—Water Carriage of Goods Act, 1936, c. 49—Contributory
Negligence Act, R.S.B.C.1948, c. 68.
In a judgment from which no
appeal was taken, the cargo owner recovered damages from the respondents, the
ship owner and the charterer, for a cargo damaged during its carriage in the
respondents' ship, on the ground that due diligence had not been exercised to
make the ship seaworthy. The trial judge found that the damage had been caused,
by the imperfect tightening of the covering of a storm valve which had allowed
water to seep through to the cargo.
Immediately prior to loading
the cargo, the appellant, a ship repairing: company, had overhauled and
repaired the ship, including this storm valve. An officer of the ship had
inspected the work generally, but in spite of his apprehension that the valve
might not have been screwed tight, no final inspection of it was made. A
certificate that the repairs had been done to their satisfaction was signed by
the officers of the ship.
In the third party proceedings
taken by the carriers against the appellant and tried subsequently, judgment
for relief over was given at trial and this was affirmed in the Court of
Appeal.
In this Court the appellant
contended that the failure to fulfil the contract had not been the proximate
cause of the damage, that the respondents were estopped from denying that the
work had been properly done, and that, in any event, there had been
contributory negligence.
Held: The appeal should be dismissed.
Per Rinfret C.J., Kerwin and Estey JJ.: The damage to
the cargo was a natural and probable consequence that was, or ought to have
been, in the appellant's contemplation when it breached its contract. Assuming
[Page 308]
that the phrase novus actus
interveniens may apply to a case of contract, that breach was the proximate
cause of the damage and not the action of the ship's officers. The repairer's
negligence continued even though the ship's officers failed to intervene.
Furthermore, there was no duty owing by the respondents or their agents to the
appellant to inspect. The taking of the ship to sea was the very thing
contemplated as well by the appellant as by the respondents.
As the repairs to the valve
itself had in fact been properly done, the signing of the certificate did not
create an estoppel.
Although the evidence of the
appellant's workmen that the bolts had been tightened securely was not believed
by the trial judge, it must be taken that they would have reported to their
foreman who would thereupon have given the same information to the respondents
and, therefore, there was no negligence on the part of the respondents which
caused or contributed to the damage.
Per Rand and Cartwright JJ.: The damages sought were
such as would be contemplated or anticipated and came well within the scope of
those for which redress is given.
The ground on which the
default of the intermediate actor, the ship, was not be treated as a novus
actus was that the respondents were entitled to rely upon their contract
for the completeness of the work to be done. So far as the respondents
inspected the work, they did so in their own interest and not because of any
obligation toward the repairer. There was an absolute obligation to finish the
work with care and skill. Nor is the burden of guarding against such an
oversight to be thrown on the ship as a matter of policy in limiting damages.
For those reasons also, it could not be said that, as between these parties,
there were concurrent causes of damages.
The certificate of
satisfaction did not imply an acceptance of all particulars regardless of
latent flaws and could not be intended to conclude against the ship such a
delinquency as was present here.
APPEAL from the judgment of
the Court of Appeal for British Columbia,
affirming, Sloan C.J.A. dissenting in part, the judgment at trial in a third
party proceeding for relief over against a ship's repairer for damage to the
cargo of a ship.
J. W. de B. Farris Q.C.
and J. D. Taggart for the appellant.
C. K. Guild Q.C. and V. R.
Hill for the respondents.
The judgment of Rinfret C.J.,
Kerwin and Estey JJ. was delivered by:—
KERWIN J.:—Australian Newsprint
Mills Limited brought action in the Supreme Court of British Columbia against
Canadian Union Line Limited, the owner of the S.S. "Waitomo", and
Union Steamship Company of New Zealand Limited, the charterer by demise of the
ship, for
[Page 309]
damages to a quantity of unbleached
sulphite wood pulp shipped by the plaintiff in the Waitomo from Powell River,
British Columbia, to Tasmania. Third party proceedings were taken by the
defendants for indemnity from Burrard Dry Dock Company Limited against any
liability that might be imposed upon them in the main action. Counsel for all
parties took part in the trial of the action and on November 24, 1951, judgment
was given by Mr. Justice Coady for the plaintiff against the defendants for
$21,384 and costs. From that judgment no appeal was taken.
Subsequently Mr. Justice Coady
presided at the trial of the issues in the third party proceedings in which, by
agreement, the evidence in the main action, so far as it had any application,
was taken as if it had been repeated. Also by agreement both parties to the
issues put in further evidence. Judgment was given for the plaintiffs in the
third party proceedings against the Dry Dock Company for $21,384 and interest
at five per cent per annum from November 24, 1951; for $1,653.25, being the taxed
costs of the plaintiff in the main action; for the costs of the defendants in
that action, and the latter's costs as plaintiffs in the third party
proceedings. Subsequently, pursuant to an order made by the trial judge, the
plaintiffs in the third party proceedings amended their claim by asking, in the
alternative, for relief over against the Dry Dock Company in respect of any and
all damages and costs found against them in the main action. Special leave was
given to postdate the judgment in the third party proceedings from March 26,
1952, to October 6, 1952.
An appeal to the Court of Appeal
was dismissed although the Chief Justice of British Columbia would have given
judgment for only one-half of the damages and costs as he was of opinion that
there was active, concurrent, continuing negligence of the ship's officers, as
well as of the Dry Dock Company, and that the case came within the British
Columbia Contributory Negligence Act, R.S.B.C. 1948, c. 68. That point
was raised for the first time in the Court of Appeal by the Chief Justice and
hence there is no reference to it in the reasons for judgment of the trial
judge.
[Page 310]
The Dry Dock Company now appeals.
Some of the arguments advanced in the Courts below need not now be considered
as counsel for the appellant realized that there were concurrent findings of
fact. However, judging from the form and scope of the reasons for judgment, the
main questions have been presented to us in a somewhat different manner and, in
view of the argument, a new approach to the problem must be made.
In the main action Mr. Justice
Coady held that the respondents had not exercised due diligence to make the
Waitomo seaworthy as required by paragraph 1(a) of article 3 of the
Rules relating to Bills of Lading scheduled to The Water Carriage of Goods
Act, 1936 (Canada), c. 49. He found:— "The cause of the damage to the
Plaintiff's goods was occasioned by a storm valve the covering of which had not
been screwed down tightly thereby allowing sea water in 'tween decks and when
this water had there accumulated in sufficient quantity it flowed over the
hatch combing and down into the No. 3 hold where the goods in question were
stowed." Part of what the trial judge says later is relied on by the
appellant and it is therefore transcribed:—
The defendants here probably
did rely on and expect the Third Party to do the work entrusted to it in a
proper and workmanlike manner but I am not now dealing with any claim or
liability arising as between them with respect to that. In the discharge of the
defendants' statutory duty to the Plaintiff however it is clear the defendants
did rely to some extent at least on Captain Beaton to check the work of the
Drydock Company in respect to any matter of repair which could affect the
seaworthiness of the ship. Captain Beaton admits that his duty went that far.
With respect to the valve coverings, he knew that these had been removed—he
knew that the inspections had been made by the surveyors when the valve
coverings were removed—he knew that they had not been replaced when the
surveyors were there—he knew that the failure to replace properly would affect
the seaworthiness of the ship. With this knowledge and in pursuance of what he
considered his duty, he asked an employee of the Drydock Company to be advised
when the valve coverings had been replaced so that he could check them, and he
says that he would have checked them to see that these valve coverings had been
replaced and properly screwed down if he had been so advised. He states however
that he was not advised when or if these valve coverings had been properly
replaced and he consequently did not check. That certainly was not the exercise
of due diligence—that was not carrying out what he admits was his duty. He
apparently assumed, not having been advised, that the valve coverings had been
replaced and securely fastened. Before he had any opportunity to check, the
valves had been boxed in. But it would not even then have been a difficult
matter for him to check as he ought
[Page 311]
to have done. It is
difficult to understand his conception of duty when he says he would have
checked had he been advised and did not apparently consider it necessary to
check when not advised.
The only conclusion I can
arrive at upon the evidence here is that there was a lack of due diligence on
the part of the defendants under the circumstances.
The appellant is a dry dock
company having its works at North
Vancouver. Prior to the voyage of the
Waitomo to Tasmania, the appellant had contracted with the respondents
to overhaul and repair the ship in order that it might pass Lloyd's four year
survey. This contract included specifically the work on and in connection with
the storm valves as the following requisition shows:—
All storm valves to be put
into working order. At present ineffective.
The account ultimately rendered
by the appellant to the respondents for its services totals approximately
$126,000 and includes this item:—
Order No. 5645
Storm Valves
Opening up all storm valves
throughout vessel and cleaning for examination. Supplying and fitting new flap
leathers as necessary, freeing up valves, rejointing and closing up in good
order. Removing sparred protection boxes in way of valves in Nos. 3 & 4 ‘tween
decks for access and refitting in good order.
Then follow the charges for work
and labour.
About one hundred employees of
the appellant had been engaged in the work. For the respondents, the Chief
Officer of the ship (Beaton) was on duty from 8 a.m. to 5 p.m. each working
day but it is made clear in the evidence that he could not possibly oversee
everything. The appellant removed the old sparring and covering which protect
the valves, and repaired and reseated the valves. Confining ourselves to the
valve in question, the evidence shows that it was examined by Beaton and one of
the appellant's workmen. They removed the plate, worked the flap back and
forth, found the valve "in effective condition", and replaced the
plate. The bolts were put on and tightened by hand but, as it was necessary
that they should also be tightened by a spanner, Beaton told the workman to let
him know later through the appellant's foreman when the spanner had been used.
He heard nothing further about the matter from anyone. The ship proceeded from
the dry dock to Powell River and Ocean
Falls and thence to New Westminster where Beaton noticed that "the valves
[Page 312]
had been completely boxed
in" i.e., with new sparring and covering. In the course of Beaton's cross-examination
by counsel for the plaintiff in the main action this appears:—
Q. Now, before your ship
commences a voyage, is it not one of your normal duties to see that all inlet
and outlet valves are closed?
(After an objection, which was
overruled, the question was read by the reporter).
A. No, not if the ship is
just making a normal voyage and hasn't gone into dry dock, or hasn't had those
valves open, we don't go around and inspect them.
Q. Assuming it has been in
dry dock for repairs to be opened, is it part of your duty to see that it is
closed?—A. To the company.
Q. It is your duty to your
company, is that right?—A. Yes.
Q. And your company owes
that duty to its shippers, doesn't it?—
A. I should say so, yes.
Q. And I think that you have
already given evidence to the effect that the only reason you didn't in this
case was because you were waiting for some further word from the Burrard Dry
Dock Company's foreman?
—A. That is more or less
true, yes.
The interjection by the Court at
this stage is of particular significance:—
The COURT: That is only part
of the reason. He has already stated that he saw that they were all boxed in,
and he assumed that the work had been done by the Burrard Dry Dock that they
were supposed to do.
On October 1, 1948, a "shop
order" was prepared by the appellant reading as follows:—
5645. Storm Valves
All storm valves to be put
into working order. At present ineffective.
5646 Port Deep Tank
Ladder Rung
Rung to be inserted in steel
ladder to port deep tank (to replace missing rung).
5647 Mainmast Head Light
Screen
Horizontal screen to
mainmast head range light to be readjusted to requirements. At present screen
ineffective and light illuminates bridge.
The above work has been
carried out to our satisfaction.
This was signed by Ritchie, the
Master of the ship, and Beaton.
Upon these facts the contentions
advanced on behalf of the appellant are:— (1) the appellant's failure to fulfil
its contract to overhaul and repair the ship was not the proximate cause of the
damage giving rise to the judgment in the main action against the respondents:
(2) by reason of the signatures of their officers to the shop order of October
1, 1948 the respondents are estopped from denying that the
[Page 313]
work was properly done: (3) in
any event, the respondents are entitled to judgment only as proposed by the
Chief Justice of British Columbia.
As to the first point, it being
established that the appellant breached its contract, the damage to the wood
pulp was a natural and probable consequence that was, or ought to have been, in
its contemplation. But it is said it was not the appellant's breach of contract
but the action of Beaton, amounting to a novus actus interveniens, that
was the proximate cause of the damage. Assuming that the phrase may apply to a
case of contract, the real position is that the appellant's negligence continued
even though Beaton failed to intervene. Beaton did not do anything which
permits it to be said that that original negligence ceased to operate.
Furthermore, there was no duty owing by the respondents or its agents to the
appellant to inspect: Mowbray v. Merryweather,
a decision of the Court of Appeal which was followed in Vogan v. Oulton,
and which was also followed by a trial judge in Scott v. Foley.
There is nothing in Nance v. British Columbia Electric Railway
Company Ld.,
inconsistent with this. Buckner v. Ashby and Horner Limited,
was relied on by the appellant but, there, the Court of Appeal merely affirmed
the decision of Atkinson J. on the facts, and that was a case of a plaintiff
who was injured failing to recover against contractors who had agreed with the
Corporation of the City of London to erect a roof above the ground in a private
passage as a protection against "blast" and "shrapnel" to
the satisfaction of the Corporation. Similarly, in my opinion none of the other
decisions referred to on behalf of the appellant has any bearing upon the
question. Connected with this first point of the appellant is the argument that
the damage was really caused by the respondents taking out the ship in an
unseaworthy condition. As to this it is sufficient to say that the action of
the respondents in taking the ship to sea was the very thing contemplated as
well by the appellant as by the respondents.
On the point of estoppel, I agree
with Mr. Justice Sidney Smith that the repairs to the valve itself had in fact
been properly done and that the fault was in the appellant's
[Page 314]
workmen not securely bolting the
plate. I also agree with him that, as stated by the trial judge, the shop order
of October 1, 1948, must be construed reasonably. "It cannot",
Mr. Justice Sidney Smith says, "be read as meaning that every item
incidental to repair must be inspected by the ship's people—otherwise they
would have to follow the workmen all day long and every day. The ship was in
Burrard hands for three weeks and the repairs were extensive, costing
$126,000." What the trial judge had stated with reference to this matter
in his reasons for judgment in the trial of the third party proceedings is as
follows:—
It would be going a long way
to hold that the defendant's officers had by signing the memorandum in question
released the Third Party from any liability with respect to work negligently
done in the repair and overhaul of this ship which was, as I stated, a rather
major job. To hold that, would be to hold that the defendants have assumed a
duty to check every nut and bolt handled by the Third Party's workmen to see
that these workmen were not negligent. In other words, it would be necessary to
have someone representing the defendants continuously with the workmen of the
Third Party inspecting their work as they proceeded to see that nothing was
left undone which they ought to have done. This was never in the contemplation
of the parties. The defendants owed no duty to the Third Party to check the
work done by the workmen engaged by the Third Party and the Third Party cannot
take refuge now behind the memorandum to which I have referred and claim to be
relieved from liability for the negligent acts of its workmen.
The third point raised by the
appellant before us is that, in any event, it should be held liable for only
one-half of the damages and costs by virtue of the Contributory Negligence
Act. In his reasons for judgment in the third party proceedings the trial
judge found that the plate on the valve had not been properly replaced and that
it had not been properly screwed down, and that owing to the negligence of the
workmen employed by the appellant. He then continued:—
The evidence permits of no
other reasonable conclusion despite the evidence of the workmen who contended
that this valve covering was properly screwed down. Their evidence as to that,
while given in good faith no doubt, I cannot accept.
One of the workmen referred to,
Murdo Maclean, testified in chief as follows:—
Mr. TAGGART: Q. After the
chief officer and yourself had inspected that particular valve, what action did
you take with regard to that valve?
—A. Tightened the holding—down
nuts.
Q. You positively recall
that?—A. Yes.
Mr. GUILD: That, again, is a
leading question.
[Page 315]
Mr. TAGGART: Q. After you
had tightened down the holding down nuts, what action did you then take?—A. I
informed my foreman that the job was completed.
Q. And that was the end of
the job?—A. That was the end of the job.
The other workman, Stuart Grant,
testified in chief:—
Mr. TAGGART: Q. Can you add
anything, now to that answer? The question was: Do you wish to add anything to
the last answer?—A. After the officer told Maclean to put the cover plate on,
on the last one that was left open, we went back and closed it up, bolted it
securely. I was the last one to test it with a spanner to see if it was tight.
Q. Do you remember how many
valves you worked on?—A. It is hard to say, but I think we put the cover plates
on three storm valves on the starboard side and two on forward port and one on
after port.
Mr. TAGGART: That is to say,
two on the forward port side, and one on the after port side, my lord.
Q. In what condition were
these valves when you finally finished the work?—A. In good shape.
This is the evidence referred to
by the trial judge and which he did not accept, and his finding in that respect
is one that was approved by the Court of Appeal and upon which no attack has
been made. However, in view of this evidence, it must be taken that the foreman
would have reported to Beaton that the bolts had been tightened with a spanner
and, therefore, there was no negligence on the part of the respondents which
caused or contributed to the damage.
The appeal should be dismissed
with costs.
The judgment of Rand and
Cartwright JJ. was delivered by:—
RAND J.:—The question raised on
this appeal is one of damages. The appellant undertook certain large scale
repairs to a vessel owned by the respondent, placed in drydock for the purposes
of undergoing a four-year Lloyd's survey, included in which was that of putting
a galley drain storm valve in proper condition. This valve, about 2 1/2 inches
in diameter, was affixed to the side of the vessel in a 'tween deck hold about
three feet above the water line. A flap prevented sea water from entering but
permitted the discharge of the drainage. A box with a removable cover was set
on the horizontal portion of the valve about a foot or so from the vessel's
side and by removing the cover the operation of the flap could be observed. The
cover fitted over four threaded stud bolts and was held in position by
[Page 316]
nuts screwed on the studs. The
flap had been working sluggishly, admitting water, and after the repair had
been done an inspection for the purposes of certification was made for which the
cover had to be removed. After replacing it, the nuts were to some extent
screwed on by hand to be later tightened with a wrench.
An officer of the vessel
inspected the work generally as it was being done, including that of the valve,
and in fact assisted a workman in replacing the cover and giving a turn to two
of the nuts. At that time there was no wrench available and the officer asked
to be notified when the nuts were made tight and he would make a further
examination, but no notice was given and no further inspection made.
In the course of the next voyage,
entered upon immediately after the repairs, water entered the hold and damaged
cargo. It was found that the nuts had not been tightened and that there was a
play in the cover of about threeeighths of an inch at one end through which the
water had entered. The claim of the cargo owners was allowed for
unseaworthiness and a failure of due diligence on the part of the vessel. From
this judgment no appeal was taken.
Third party procedure was invoked
by the vessel against the contractor, the appellant company, which being found
responsible for the failure to tighten the nuts was held liable to the vessel
in the amount of judgment and costs of the main action. This second judgment
was affirmed on appeal and
from that ruling the appellant has brought the case here.
Mr. Farris, in a thorough and
lucid argument, put his case thus. The third party claim is for damages and
damages only, and there is no case for indemnity; it is then a matter solely of
the extent to which damages are allowable. The issue is whether the judgment
recovered against the vessel by reason of a breach of warranty of seaworthiness
can be taken to be the measure of damages resulting from the breach of the
contract to repair. The chain of consequences in damages is broken by the
intervention of the act of a new conscious volition, and there was such an
intervening act here in putting the vessel to sea with the cover loose, in the
knowledge that it had not been given a final inspection. That inspection was a
duty of the ship
[Page 317]
toward the cargo, its failure was
culpable, and combined with the act of setting upon the voyage was the sole
cause of the loss. Being a duty toward cargo, it is to be taken as something
contemplated and expected by both parties to the repair contract. He criticizes
the references in the judgments below to there being no "duty" on the
part of the ship toward the contractor as confusing negligence with damages.
Incidentally, he raises the question of collateral liability in tort for
negligence in the defective work done and its significance to the recovery of
damages by both cargo and ship. He relies on a written acknowledgement by
representatives of the vessel that the work of repairs had been done to their
satisfaction. His final submission is that in any event there was concurrent
default on the part of the vessel which jointly with that of the contractor
brought about the damage.
Notwithstanding the force of this
argument, I am unable to agree with it. It is unnecessary to cite authority for
the general proposition that damages for breach of contract reach at least to
consequences which, if the parties to the contract had thought about the
question at all, would have come within the range of foreseeable likely, probable
or reasonably possible happenings. The language used to express this idea has
taken various forms; they are "natural consequences", consequences
within "the contemplation of the parties" or what, as reasonable men,
they would "anticipate". These I take to mean the same thing; they
are intended to convey the notion of proximate events following the culpable
act in the not exceptional course of things, not necessarily proximate in time
or space but in consequential relation.
In the circumstances here there
can be no doubt of what those events would have been. The valve was one of the
few means by which sea water could enter the holds, and in the latter would
soon be stowed goods which would be damaged by sea water. It was a vital
feature of repair the importance of which everybody appreciated. It was equally
evident that the goods, if not owned by the respondent, would be carried under
the ordinary and uniform terms— prescribed in fact by statute—and that the
seaworthiness of the ship would be one of the obligations of the vessel. That
the cargo would in all probability be damaged if the
[Page 318]
top of the box was not tightly
fastened would be patent to every person familiar with the workings of a
vessel. On principle, then, the damages sought are such as would be
contemplated or anticipated and come well within the scope of those for which
redress is given. Whether any such distinction between a contractor for the
general repair of the vessel for survey purposes and one engaged for, say, the
repair of a valve only, can, as suggested by Smith J.A., be made, does not call
for consideration.
We are not lacking in express
authority on such a situation. In Mowbray v. Merryweather,
the defendant agreed to supply a chain along with other equipment to be used in
discharging a cargo from a ship. The chain was defective and broke while being
so used. An employee of the purchaser was injured and recovered judgment
against his employer on the ground that the latter could have discovered the
defect by reasonable inspection. The employer then brought action against the
seller on the warranty that the chain was suitable for the purpose intended.
The Court of Appeal held the employer's liability to the workman to be the
natural consequence of the breach of warranty reasonably presumed to have been
within the contemplation of the parties when entering into the contract.
To the application of this case
two objections are made: first, that there was no conscious act on the part of
the dockman who was carrying on the work, but rather a mere failure to inspect;
and secondly, that a claim by the workman against the person furnishing the
chain could there, but not here, have been maintained. The
"consciousness" in the present case is the knowledge that the
tightness of the screws had not been tested; but equally so was the knowledge
of the dockman that he had not examined the chain before using it. Then,
whether a direct liability in negligence toward the injured person by the
original wrongdoer in any case exists depends upon its circumstances; but that
question is not involved here. The basis of a wrong under the general law and
that arising under a contract have no necessary relation, and how far the
former can be affected, if at all, by the circumstances of the latter offers a
bait to speculation that must be refused: what must be kept in mind is the
fundamental distinction between their
[Page 319]
origins. The appellant is liable
on its contract to put the valves "in working order" and the
respondent on its warranty to furnish a seaworthy vessel. The third person, in
this case the cargo owner, has no claim arising out of that contract for
repairs; but no rule has ever been laid down that a contractual claim in
damages reaching to injury done to a third person is conditioned upon a
collateral tortious liability in the original wrongdoer to the third person. A
duty under the general law may or may not have arisen between the contractor
and either or both the vessel and the cargo owner, and a like duty between the
vessel and the cargo; but these collateral possibilities are irrelevant to the
issue before us.
In Mowbray, supra, Kay
L.J. referred to a direct remedy and Rigby L.J. mentioned its admission by the
defendant as concluding the question of damages: but there was no reference to
it by Lord Esher M.R. nor was there any suggestion that it was a condition of
the recovery which was allowed. The question was incidentally mentioned in Boston
Woven Hose v. Kendall. In that case a boiler had been warranted to stand a
pressure of 100 pounds. It was defective and the defect was patent to any real
inspection. Subjected to a pressure much below 100 pounds, the boiler weakened
to allow naphtha to escape which exploded and injured employees of the
purchaser. The latter admitted liability to the employees, paid the damages
suffered and was allowed to recover them from the seller. In giving the
judgment of the court, Holmes C.J., in speaking of Mowbray, supra, said:—
It is intimated in that case
that the workman himself could have recovered in the first place against the
defendant. Whether that is a necessary condition of a recovery over we need not
consider… There are many cases in our own and other reports which offer as
strong or stronger applications of the principle of liability over.
The ground on which the default
of the intermediate actor, here the vessel, is not to be treated as a novus
actus is that the respondent was entitled to rely upon its contract with
the Drydock Company for the completeness of the work to be done, and it is that
persisting contractual right which differentiates the case from one of
negligence. So far as the respondent inspected the work, it did so in its own
[Page 320]
interests and not because of any
obligation toward the contractor. The default was in relation to an item of
detail which it would be absurd to say the parties contemplated or anticipated
would be the matter of a specific inspection by the vessel as a check for the
benefit of the contractor. That would require the ship owner to see that every
nail was properly driven and every screw tightened in the entire course of the
work. Here was an absolute obligation to finish the work with care and skill.
So long and so far as the respondent is entitled to rely on that contract, it
cannot be said that any act of his in the ordinary run of things is novus
actus, and that reliance, as it is here, may be of the essence of the
agreement. If he is not so entitled, then a new situation is presented.
Circumstances may indicate a common understanding or assumption that, for
example, a machine repaired will not be put in use without a fresh inspection
or test of the part repaired, an inspection, say, required by law: but that is
another way of saying that there is no right to rely on the contractor's
obligation.
Nor is the burden of guarding
against such an oversight to be thrown on the vessel as a matter of policy in
limiting damages. The object of such a policy should be to minimize losses, but
how can that be done by exempting the guilty person from responsibility for its
consequences? Except in special circumstances, and as between the parties,
reliance upon undertakings is essential to modern business and in fact to our
daily affairs generally; occasionally there will be failures, but that
possibility cannot justify such a transfer of the burden, which in practical
terms would mean the shifting of the obligation of insurance from the culpable
to the innocent.
These considerations furnish the
answer also to the last contention that, as between these parties, there were
concurrent causes: the original failure was in a setting which contemplated
reliance on the contractor, a fact which the evidence puts beyond dispute; and
so long as that reliance was justified, there can be no intervening cause.
The certificate of satisfaction
related, obviously, to the general performance of the different items of the
work including that of the valve; it did not imply an acceptance of all
particulars regardless of latent flaws; that would have been equivalent to a
release which the persons furnishing
[Page 321]
the certificate had no authority
to give. Nor is this avoided by treating it as an estoppel. If the certificate
had been refused or had expressly excepted defects in the work, what would the
Dockyard Company have done? Certainly not entered upon a minute re-inspection
of the whole work. As Smith J.A. intimates, the purpose of the certificate is
primarily to authorize payment; it is not intended to conclude against the
vessel such a delinquency as was present here.
I would therefore dismiss the
appeal with costs.
Appeal dismissed with
costs.
Solicitors for the
appellant: Farris, Stultz, Bull & Farris.
Solicitors for the
respondents: Macrae, Montgomery & Macrae.