Supreme Court of Canada
Oshawa (City) v. Brennan Paving Co., [1955] S.C.R. 76
Date: 1954-12-09
The Corporation of
the City of Oshawa (Defendant) Appellant;
and
Brennan Paving
Company Limited (Plaintiff) Respondent.
1954: June 1, 2, 3; 1954: December 9.
ON APPEAL FROM THE COURT OF APPEAL FOR
ONTARIO.
Contract—Construction of street—Payment for
materials to be by weight and engineer’s certificate condition precedent to
payment—Effect of engineer’s failure to comply with prescribed conditions.
A contract entered into by the appellant
municipality with the respondent provided that as to the gravel and asphalt to
be supplied by the latter, payment should be by weight, and that possession of
an estimate or certificate signed by the appellant’s engineer should be a
condition precedent to the right of payment. The respondent complied with the
provisions of the contract but the appellant’s engineer refused to certify for
the materials by weight and arrived at the amounts to be paid for each by his
own methods of calculation.
Held: That
when the engineer refused to certify, as called for by the contract, he
abdicated his proper function thereunder and the appellant, having concurred in
the position he took, brought itself within the principle of Panamena v.
Leyland [1947] A.C. 428. The respondent was thus absolved from the
requirement with respect to the final certificate and the construction of the
contract became in the circumstances entirely a matter for the court.
Appeal dismissed and judgment of the Court of
Appeal for Ontario [1953], O.R. 578, affirmed but varied by deducting
$1,305.02, the value of 160.125 tons of asphalt, supplied in excess of the
estimate.
[Page 77]
APPEAL by defendant from the judgment of the
Court of Appeal for Ontario
affirming the judgment of the trial judge, McRuer C.J.H.C., in favour of the plaintiff.
J.J. Robinette, Q.C. and G.K. Drynan for
the appellant.
P.B.C. Pepper for the respondent.
The judgment of the court was delivered by:
KELLOCK J.:—With respect to the claim for
gravel, Mr. Robinette relies only on the absence of a final certificate
from the engineer. As to the asphalt, his position is twofold: (1) that the
claim for any amount over the 3000 tons mentioned in the specifications is
irrecoverable for lack of an “order from the engineer in writing” as required
by clause M of the General Conditions of Contract; and (2) that as
to the remainder, it is in the same position as the gravel, namely,
irrecoverable for lack of the engineer’s certificate.
With respect to the gravel, it is provided by
the specifications that the “basis of payment for this material shall be per
ton, all material being weighed on the city weigh-scales by the city
weigh-master and checked on the job by the inspector designated by the
engineer.” The engineer, in his final certificate, however, entirely
disregarded this provision. What he did is thus described in the judgment of
Roach J.A., who delivered the judgment of himself, Hogg and Gibson JJ.A.:
He took the total surface area and
multiplied it by 6 inches (the depth of gravel called for) and determined the
total number of cubic yards. Then by adopting what someone told him was the
weight of a cubic yard of gravel, he determined the quantity by weight of the
total cubic yards. To that amount he added something as an allowance for
gravel used in filling the voids in the rubble that was used to fill soft
spots. How he could determine the quantity of gravel that was used in these
soft spots I am totally unable to understand. He did not know the depth or area
of the soft spots or the size of the voids.
This, of course, was not in accordance with the
contract, and its construction is, in the circumstances, entirely a matter for
the court. Clause F of the General Conditions upon which some reliance is put
by the appellant has no bearing. It reads as follows:
Work mentioned on the plans or
specifications shall be performed as though shown on both. In the event of
dispute, the decision of the engineer as to the meaning or intent of the plans
and specifications shall be final.
[Page 78]
While the gravel was being furnished to the job
and worked into it, there was no dispute whatever as to what was called for.
The gravel was supplied to the job as directed by the inspector who was the
representative of the engineer. Accordingly when the engineer refused to
certify for the gravel by weight as called for by the contract, but adopted a
method of his own, he abdicated his proper function under the contract. His
refusal to certify in accordance with the contract was completely arbitrary and
illegal. The appellant has concurred in the position taken by the engineer and
has maintained this position down to the present, thus bringing itself within
the principle of the decision in Panamena v. Leyland. In that case, when the surveyor insisted
on matters outside the quality and quantity of the work, which alone he was by
the terms of the contract authorized to take into consideration, and this was
concurred in by the appellant, the respondent was absolved from the requirement
with respect to a final certificate. The same applies in the case at bar.
By the terms of the contract the respondents
covenated to
Do the whole of the works herein mentioned
with due expedition and in a thoroughly workmanlike manner, in strict
accordance with the provisions of this Agreement, and the said Plans,
Specifications and General Conditions therein referred to…
The appellant on its part covenanted with the
respondents:
That if the said work including all extras
in connection therewith, shall be duly and properly executed as aforesaid, and
if the said Contractors shall observe and keep all the provisos, terms and
conditions of this Contract, they, the said City, will pay the said Contractors
therefor the sum of $112,282.32 (more or less) according to the schedule of
unit prices in the Form of Tender, upon Estimates or Certificates signed by the
Engineer.
Provided that no money shall become due or
be payable under this Contract unless and until an Estimate or Certificate
therefor shall have been signed by the Engineer as herein provided the
possession of which is hereby made a condition precedent to the Contractors’
right to be paid or to maintain any action for such money or for any part
thereof.
Provided also that the said City shall not
be liable to pay for work rejected or condemned by the said Engineer, or to pay
any money upon any Estimate or Certificate until the work so rejected or
condemned has been replaced by new material and workmanship to the written
satisfaction of the said Engineer…
[Page 79]
It cannot, in my opinion, be doubted that the
“Estimate or Certificate”, the possession of which is made a condition
precedent to payment, is one covering the work as to quality and quantity at
the appropriate rate called for according to the prices stipulated in the
contract. In departing from the area thus marked out the engineer rendered his
certificate no more essential to the respondent’s right of action than it would
have been in Panamena’s case had the surveyor in that case, issued his
certificate for a reduced amount by reason of his view of the economical manner
in which performance of the work had been carried out, a matter entirely
outside the scope of his authority to consider.
The lack of an order in writing for the quantity
of gravel in excess of the estimate of 2600 tons is not an obstacle in the way
of the respondent, and, as already pointed out, Mr. Robinette does not rely
upon this point. That estimate was for the 6” gravel course only and did not
include the gravel used in filling the soft spots. It has not been shown what
the respective amounts required for the gravel course and the soft spots
respectively, were, and therefore it is not shown that the 2600 tons for the
gravel course was exceeded. It was, no doubt, for this reason that Mr. Robinette
took the position he did on this point.
With respect to the asphalt, the relevant
provisions of the original contract, as amended by the later contract, as well
as the specifications, are as follows. The original “Information to Bidders”,
after providing for the removal of the existing pavement and sub-structure,
went on to state:
It is then proposed to fill the space
formerly occupied by the ties with compacted asphaltic concrete base course,
and also to build up the shoulders of the present concrete base with the same
material, after which it is proposed to spread the consolidated asphaltic
concrete wearing surface, varying the thickness from 1” to 2”. In making
this consolidation of the asphaltic concrete wearing surface, it is proposed
that the engineer should set grades at intervals not exceeding 50 feet, which
will effect a parabolic cross sectional contour on the finished pavement.
Attention is drawn to the fact that this contour
must be carefully followed, in order to strengthen the bearing value of the
pavement, and in order to partially eliminate the excessive crown which
is apparent on the existing street.
[Page 80]
Item 327 of the original specification has the
following:
The surface course shall consist of coarse
aggregate sand and mineral filler uniformly mixed with asphalt cement and shall
be laid upon the previously prepared pavement base to a minimum thickness of
one inch and a maximum finished depth of two inches, as directed by the
Engineer.
Clause G. of the General Conditions provides
that no work shall be done without lines, levels, and instructions having been
given by the engineer, “or without the supervision of an inspector.” It is
provided by the specification, under the heading “Method of Payment”, that:
All hot-mix, hot-laid asphalt mixtures
supplied and incorporated into the work will be paid for at the price tendered
per ton.
The Owner will provide and place a man at
the Contractor’s weigh scale for the purpose of weighing the mixtures
incorporated into the work, and the net weights so determined will be the only
basis for payment.
The specification under the amending contract
under the heading “Scope of Work” provides:
Remove existing concrete base.
Excavate the material thereunder to a depth
to provide a 6” crushed gravel base course and new concrete sub-base 8” thick
and a minimum of 3” binder and asphaltic top.
Provide 6” crushed gravel base course and
8” concrete base and minimum of 2” of asphaltic binder and 1” of asphaltic top.
The engineer interpreted, for purposes of his
final certificate, the later specification as to the wearing surface, as
providing for a thickness of 1 inch only. In his view, “minimum” in the second
paragraph of the amending specification under the heading “Scope of Work”
above, was confined to the 2 inches of asphaltic binder and did not apply to
the 1 inch of asphaltic top. He therefore entirely disregarded the actual
quantity of asphalt delivered and arrived at a theoretical figure by taking the
superficial area on the footing of 1 inch in depth and ascertaining the weight
by that means.
It has been expressly found in the courts below,
that in executing the work after the amending contract was entered into, the
respondent continued the practice it had previously followed and laid a minimum
thickness of 1 inch and a maximum thickness of 2 inches, under the specific
instructions of the inspector on the job. Both the respondent and the inspector
considered that in so doing they were
[Page 81]
carrying out the terms of paragraph G. of the
General Conditions of Contract. No one suggested that there was any ambiguity
in the terms of the contract in this respect until the completion of the work
when the engineer, Meadows, did so, as above mentioned. When the question of a
final certificate came up Meadows had himself up to that time, issued progress
certificates for asphalt on the basis of tonnage actually delivered, and the
respondent had received payment.
The appellant again places reliance upon clause
F. of the General Conditions already quoted above and contends that Meadow’s
decision as embodied in his final certificate, governs.
In the language of Roach J.A. the answer is:
That during the progress of the work there
was no dispute between the plaintiff and Meadows as to the thickness of the
asphaltic wearing-surface called for by the plans and specifications. The
plaintiff’s interpretation of the plans and specifications as they related to
that item differed from the interpretation Meadows now says he intended they
should bear, but the parties were not disputing about it. The plaintiff did not
know that there was any difference between their respective interpretations.
Roach J.A. also says:
Meadows saw the plaintiff proceeding with
the work in compliance with the understanding of its superintendent, but never
communicated any objection to the plaintiff. At the trial Meadows stated that
on one occasion he objected and in substance warned the superintendent against
laying down a greater thickness than 1 inch of asphaltic wearing-surface. The
superintendent in his evidence denied any such discussion and the trial judge
accepted the superintendent’s evidence.
Meadows must have known that the plaintiff,
in laying down a thickness of asphaltic top in excess of 1 inch, was doing so
because its superintendent interpreted the plans and specifications as
permitting it and requiring it where to do so was necessary for proper
drainage. If he felt—and he now says he did—that the plaintiff was thereby
exceeding the thickness authorized, he should have interfered at the time. To stand
by and do nothing about it was to acquiesce. Even more important than the
foregoing is the fact that Courtlee specifically instructed the superintendent
to proceed as he did. To my mind it is idle to say that Courtlee thereby
exceeded his jurisdiction. He was on the job to see that the work, as it
progressed, had that standard of excellence agreed upon between the parties. He
gave those instructions, not for the purpose of varying the plans and
specifications, but for the purpose of requiring the contractor to live up to
them.
In my opinion the engineer has in this instance
also, abdicated his function under the contract. The asphalt, like the gravel,
was to be paid for by weight. This was the
[Page 82]
“only basis of payment” provided for by the
contract. The same principle, therefore, applies as in the case of the gravel
save as to the excess over the estimate of 3000 tons as to which the lack of an
order in writing is, in my opinion, fatal.
Accordingly the appeal should be dismissed with
costs but the judgment should be varied by deducting $1,305.02, the value of
160.125 tons of asphalt which is the amount in excess of the estimate. In the
circumstances, this variation should not affect the costs.
Appeal dismissed with costs and
judgment of the Court of Appeal affirmed subject to a variation.
Solicitors for the appellant: Creighton,
Fraser, Drynan & Murdoch.
Solicitors for the respondent: McMillan,
Binch, Wilkinson, Stuart, Berry
& Dunn.