Supreme Court of Canada
Scharfenberg
v. Kortes, [1956] S.C.R. 273
Date:
1956-01-24
Hugo O. Scharfenberg (Plaintiff) Appellant;
and
Edith Kortes (Defendant) Respondent.
1955: November 1, 2; 1956: January 24.
Present: Rand, Kellock, Estey, Locke and Abbott JJ. Estey J.
died before the delivery of the judgment.
ON APPEAL FROM THE SUPREME COURT OF ALBERTA; APPELLATE DIVISION
Contract—Agreement to build
house—Interpretation—Evidence—Rectification—Substantial performance.
The appellant, who had some twenty years experience as a
building contractor, signed a contract to build a house for the respondent.
During the negotiations, prior to the signing, he had been supplied with a set
of plans, which were later attached to the contract, supplying the data for
finishing both the main floor and the basement of a one-storey building. The
appellant testified that he quoted a price of $30,000 for the completion of the
ground floor and basement and a price of $18,000 for the completion of the
ground floor but only structural parts of the basement, and that the latter
figure was agreed upon. The respondent denied that any other figure than
$18,000 was ever mentioned.
The appellant claimed for a balance owing upon the contract
and for a lien upon the land under the Mechanic's Lien Act. A claim for
rectification of the contract was later made by the appellant. The defence was
that the appellant had not completed the building as required by the agreement
since, as admitted, the basement had not been finished. The trial judge
rejected the claim for rectification, found that the contract had not been
substantially performed and dismissed the action. This judgment was affirmed by
the Court of Appeal.
Held (Locke J. dissenting) : The appeal should be
allowed and a new . trial directed.
Per Rand, Kellock and Abbott JJ.: The evidence, which
the appellant attempted to make at the trial to support the case that it would
have been absurd for an experienced contractor to have agreed to
"finish" the entire building at the price of $18,000, that
ambiguities and uncertainties in the plan demonstrated that the actual contract
was for the finish of the ground floor and rough structural completion of the
basement only, and which would also have shown the amount of money required to
finish the basement, should not have been rejected by the trial judge. That
rejection was not material nor warranted. The evidence might have had a
decisive influence on the mind of the trial judge in coming to an opinion on
the veracity of the appellant, particularly in view of the fact that the
reasons for judgment give no indication that the anomalies and inconsistencies
in the plan and the evidence were given serious consideration. There is no
doubt that its rejection operated to the serious detriment of the case for the,
appellant.
Per Locke J. (dissenting): As the evidence of the
respondent and the witness Hoffman had been accepted by the trial judge and the
Appellate Division, the claim for rectification failed.
[Page 274]
The proposed evidence which, it was claimed, had been rejected
was not properly tendered (Perm v. Bibby (1866) L.R. 2 Ch. 137).
As the appellant had deliberately refrained from arguing the question as to the
rejection of the evidence raised by his notice of appeal in the Appellate
Division and the matter had accordingly not been considered in that Court, the
point should be treated as abandoned or waived (Hamelin v. Bannerman
(1901) 31 S.C.R. 534; Attorney General of Canada v. Ritchie Contracting
Co. (1915) 52 S.C.R. at 92).
APPEAL from the judgment of the Supreme Court of Alberta,
Appellate Division, affirming the dismissal of the action by the trial judge.
M. J. A. Lambert for
the appellant.
J. W. K. Shortreed for the respondent.
The judgment of Rand, Kellock and Abbott JJ. was delivered
by:—
Rand J.:—This
appeal concerns a contract by which the appellant as contractor agreed to build
a house for the respondent, the owner. Following preliminary discussions plans
were prepared for the owner by a third person and the contractor was called in
for a general examination of them with the owner and her stepson Hoffman who
lived with her. Certain changes of a minor nature were made after which the
contractor was furnished with a set on which to give a price. On their face
they supply data for finishing both the main floor and the basement of a
one-storey dwelling. The basement layout included bedrooms, bathroom, den,
rumpus room, etc.
Later, in submitting a price to the owner, the contractor
says he mentioned two figures : one for the final completion of both ground
floor and basement and the other for the completion of the ground floor but
only structural parts— a rough finish—of the basement. The former is said to
have been $30,000 and the latter $18,000. In the result it was agreed that the
latter amount should be the contract price, and the dispute is whether the
house was to be completed in its entirety or to the modified extent mentioned.
A written contract in simple form was drawn up which,
generally, provided for the construction according to the plans, that the work
should be prosecuted with diligence,
[Page 275]
and that payment would be made in three instalments of
$4,000 each and a final instalment of $6,000 "on completion of the building".
Clause 3 reads:—
The contractor covenants that he will well and sufficiently
execute and perform in a thorough and. workmanlike manner the erection and
completion of the said building, and will purchase, use and obtain the best of
materials and labour that may be available to him as may be necessary in
connection with the construction of the said building, and in particular but
without restricting the generality of the foregoing, the Contractor agrees to
use Number One materials throughout and to install standard double plumbing.
"and to furnish & install the items listed in Schedule 'A'
hereto."
Schedule "A" was as
follows:—
1. Forced air furnace worth
approximately $1,000.
2. One-half inch oak floor throughout
except in the kitchen and bathroom'.
3. Rubber tile on floor of
bathroom and kitchen. Plastic tile 4½ feet in kitchen and bathroom walls.
4. Colored toilet, bath and wash
basin in bathroom and kitchen.
5. Thermopane windows
in living room, dining room, front bedroom.
6. Asphalt red shingles on roof.
7. Fireplace in living room.
8. Mercury light switches
throughout.
9. Single garage.
The contract was signed on May 15, 1953 and the work was
begun about that time. On November 23 the contractor presented a bill for the
final instalment plus certain extras which are not disputed; on some excuse, he
was told to return in a few days. Three days later he was informed that the
work had not been completed according to the contract although he contends that
no mention then was made of the omission to finish the basement. A mechanics'
lien was thereupon filed and in January, 1954, these proceedings were brought.
In the course of the trial the plaintiff offered the
evidence of an architect to support the case that it would have been utterly
absurd for an experienced contractor such as the appellant to have agreed to
"finish" in the manner indicated the entire dwelling at the price of
$18,000 and that ambiguities and uncertainties in the plan, including items in
Schedule "A", demonstrated the actual bargain between the parties to
have been not for the finish of the two floors but the finish of the ground
floor and rough structural completion of the basement. That evidence would have
led not only to the comparison of any reasonable range of price for the one degree
of completion as contrasted with the other,
[Page 276]
but also the amount of money which it would have taken to
finish the basement. On the objection of counsel for the respondent the
evidence was rejected, and the question which meets us at the outset is whether
that rejection was, in the circumstances, material and warranted.
In considering that question, there are certain indisputable
and significant facts which should be mentioned. It will be seen that section 3
provides that the contractor will install "standard double plumbing".
That may or may not be intended to include fixtures but light is thrown on this
by Schedule "A". In item 2 we find that a one-half inch oak floor is
to be laid throughout except in the kitchen and bathroom. Item 3 speaks
of the floor of "bathroom and kitchen" and "kitchen and bathroom
walls". Item 4 specifies the type of "bath and wash
basin in bathroom and kitchen". The bathroom fixtures were
chosen by the respondent and only one set selected. In these circumstances it
is obviously striking that the singular "bathroom" is used through
the Schedule and that only one set of fixtures was selected. Its effect seems,
in fact, to define "standard double plumbing" as meaning what the
contractor contends: the installation of the pipe system exclusive of fixtures.
Then, on the plan a four-inch concrete floor in the basement
is specified. That, on its face, seems to me to exclude oak flooring which is
claimed under the word in item 2 "throughout"; and no light is thrown
on the method or practicality of placing oak over a concrete basement floor. In
this aspect the word "throughout" in Schedule "A" is
confined to the ground floor, as its ordinary signification in the context
seems to indicate.
A further item is of importance. The third instalment of
$4,000 was to be paid "when the building has been plastered". A
request for this payment was made shortly before or after the 1st of August but
was refused on the ground that some of the work done was defective. This
refusal was followed by a letter dated August 5 from solicitors of the
contractor to the respondent which pointed out that by the terms of the
contract she was "to pay $4,000 when the building has been plastered";
that Mr. Scharfenberg had informed them that "the plastering was
completed several weeks ago"; and that "We are writing to remind
you
[Page 277]
of the terms of the contract into which you entered …";
and it asked; for immediate payment. Evidently the respondent then had some
communication with the solicitors and on August 11 a further letter was written
to the effect that the contractor was unwilling to consent to any variation of
those terms. It was again pointed out that according to the agreement the
$4,000 was to be paid "when the building had been plastered"
and it reiterated the completion of the plastering. The stepson Hoffman in his
evidence said that sometime in July or "even in June" he had spoken
to; the contractor about the plastering and was told, "don't you worry, I
am. building the house". In spite of all of this!, the payment was made
shortly after the receipt of the letter of August 11.
Another such circumstance is that the wires running through
the concrete walls of the basement which held the construction forms together
were only in part clipped off and the remaining four or five inches left as
they were. The significance of this is that according to the contractor cutting
was discontinued when Hoffman indicated that he would like to have them left to
be used later in finishing the walls of the basement. If that request was made,
it would tell strongly against the contention that the contractor was to
plaster the basement walls. Mr. Lambert urged that it would be quite
unreasonable to assume that when the contractor had finished plastering the
walls on the ground floor he would discontinue that work, complete the ground
floor 'and then weeks later return to finish plastering in the basement. At
least this item of plastering shows beyond question that from the early part of
July the understanding of the contractor in this respect was clearly indicated
to the owner.
There were also on the plans two descriptions that remain
yet to be explained if the contract is as urged by the respondent. One corner
of the basement is on the plan described as "future rumpus room". To
give the adjective "future" any meaning at all it is that the
finishing was not intended at that time. This is supported by the absence of
any mention of the room on Schedule "A". Then an area is marked
"proposed bath". How that description can be reconciled with complete
finishing, including fixtures, remains to be shown.
[Page 278]
The appellant, although, he has been a contractor in
Edmonton for about thirty years, has not, as his evidence indicates, such an
acquaintance with the English language as gives him facility in its use; on the
other hand, both the respondent and her stepson appear to be quite at home with
it. Since the plan and Schedule "A" furnished the data not only for a
final completion of both floors but also for that of the ground floor and the
partial construction of the basement, it does not require much imagination to
appreciate how the contractor could have fitted his understanding of what had
been agreed to be done into the inclusion of the plan in the contract. If
evidence had been admitted to show the extreme unlikelihood of a bargain to
build for $18,000 a finished house such as claimed, then obviously it might
have had a decisive influence on the mind of the trial judge in coming to an
opinion on the veracity of the contractor, particularly in view of the fact
that the reasons give no indication that the anomalies and inconsistencies
which I have, in part, mentioned, were given serious consideration. The evidence
tendered should, in my opinion, have been admitted and that its rejection might
have operated to the serious detriment of the case for the contractor I have no
doubt.
I would, therefore, allow the appeal and direct a new trial.
The appellant will be entitled to his disbursements of the appeal in this Court
but otherwise there will be no costs in this Court or in the Court of Appeal.
The costs of the first trial will be in the discretion of the judge presiding
at the rehearing
Locke J.
(dissenting):—The appellant, by the Statement of Claim, alleged that the
defendant was indebted to him for a balance owing upon a contract dated May 15,
1953, for the erection of a house in the City of Edmonton, and claimed a lien
upon the land for such amount under the provisions of the Mechanics' Lien
Act of Alberta.
By the Statement of Defence the respondent pleaded that the
plaintiff had not completed the building, as required by the agreement, and, in
addition, claimed that there had been various defects in certain of the work
which had been done. Particulars of the work called for by the contract which
had not been done and of the alleged defective work were furnished by the respondent
on demand. The
[Page 279]
unfinished work related almost entirely to the; basement of
the dwelling. Upon this defence the appellant joined issue. :
At the opening of the trial before Macdonald J. the
appellant obtained leave to amend the Statement of Claim by the addition of the
following:—
3. (a) The Plaintiff says that the said contract to
which were attached a certain set of plans inadvertently and by mistake
incorporated certain plans for a finished basement whereas the Plaintiff says
that the parties hereto had agreed verbally prior to the execution of the said
contract that the basement would not be finished as shown in the said plans and
would contain the bearing partitions only and roughed in double Plumbing and
the Plaintiff asks that the said contract be rectified to correct the said
mutual mistake.
(a.a.) An Order of this Honourable Court directing that the
certain contract dated the 15th day of May, 1953, be rectified to delete any plans
for a finished basement as shown in the plans attached to the said contract. ,
The Statement of Defence contained a general denial of the
allegations of fact in the Statement of Claim and upon these issues the action
was tried.
The appellant has had twenty years' experience as a building
contractor in the Edmonton District. Shortly prior to May 15, 1953, the parties
entered into negotiations for the erection of a house upon the respondent's
property. During most of the negotiations the respondent was represented by her
adopted son, Hubert Hoffman. The learned trial judge accepted the evidence of
the respondent and Hoffman, in preference to that of the appellant, and,
accordingly, it is their version of what took place that is to be considered.
After some preliminary discussions, the appellant introduced
Hoffman to a Mr. MacDonald, an employee of the City of Edmonton, who, the
appellant had suggested, was a suitable person to prepare a plan. Upon the
information given to him by Hoffman, MacDonald prepared plans for a one storey
house, with a basement, the latter to contain two bedrooms, a den or study, a
bathroom, what was called a rumpus room, a utilities room where the furnace was
to be placed, and at least two other rooms which bore no designation. Upon
receiving this, the parties and Hoffman met at the respondent's home, went over
the plans in detail, and, upon one of the blue prints
taken from them, marked in the appellant's presence certain changes which, it
was agreed,
[Page 280]
were to be made. The appellant said that he would consider
the plans and give an estimate of the price for which he would construct the
building and, two days afterwards, Hoffman says that he came and quoted the
figure of $18,000. . The appellant suggested that they have an agreement drawn
by a solicitor he knew. The respondent and Hoffman were strangers in Edmonton
and did not know any solicitor and agreed to this. The appellant went alone to
Mr. J. H. Jamieson, a member of a well known Edmonton firm, taking with him a
copy of the blue prints upon which the agreed changes were marked, and
instructed him to draw the agreement.
According to Hoffman, it was on May 11 that he and the
respondent went to Mr. Jamieson's office and read the draft agreement which had
been prepared. The agreement, as drawn, required the appellant as contractor, inter
alia, to:—
provide all materials and perform all the work mentioned in
the specifications and shown in the drawings and details supplied by the owner.
the contract price to be the sum of $18,000 and the
building to be completed by October 1, 1953. No specification had been
prepared. There were certain discussions between the parties in the solicitor's
presence but the matter was not then concluded and the respondent and Hoffman
left taking the draft agreement home to-be studied. Some two days after,
Hoffman says he went with the respondent to Mr. Jamieson's office and there met
again Scharfenberg and a discussion took place in regard to certain changes
which the respondent wished to have made. Hoffman had made a list of these and
the details were taken down by Mr. Jamieson after they had been agreed to by
the appellant. The respondent returned alone to the solicitor's office on May
15. A change had been written into clause 3 of the draft in pen and ink,
requiring the contractor to furnish and install the items listed on a page
described as Schedule A, which was attached. These included a forced air
furnace worth approximately $1,000 and eight other changes or additions to the
plans. In the presence of Mr. Jamieson, the parties then signed the agreement
upon which the action was brought and the blue prints, being the
"drawings" referred to in it.
The appellant gave evidence that when he received the plans
he gave an estimate of $30,000 to build the house, this
[Page 281]
including the entire work indicated. According to him, the
respondent and Hoffman said this was too much. He then claims to have said to
them that the property was in a one family zone and that he could not
"build a suite" (referring to the basement rooms) and that it was
then agreed that he would build only the first floor shown on the plans and
"roughed in double plumbing" in the basement. The respondent and
Hoffman both flatly denied this and said that no figure other than $18,000 was
ever mentioned during the negotiations. According to both the respondent and
Hoffman, their only discussion with the appellant during the negotiations was
for a price for all of the work indicated by the plans, evidence which the
learned trial judge, after hearing the witnesses, has accepted, a finding that
has been affirmed on appeal. While, in view of this, it is unnecessary in my
opinion, to consider further the evidence bearing upon these questions of fact,
it may be noted that the appellant can read, and that he himself gave
instructions to Mr. Jamieson for the drawing of the agreement, in the absence
of the respondent, that Hoffman and the respondent were in the solicitor's
office twice discussing the matter with the appellant in his presence, and the
respondent alone, on the day that the agreement was signed, again in the
presence of the appellant, and that Mr. Jamieson was not called as a witness by
the appellant to support the contention that there had been some mistake. It
may be added that the statement that there was any difficulty in getting a
building permit from the City for the house as shown on the plans, if ever
made, was shown to be untrue.
It may further be noted that both the respondent and Hoffman
were in touch with the work as the building progressed and both questioned the
appellant as to when he was going to do the work called for in the basement.
Hoffman asked him as to this several times from June onward, but the only
answer made to him was that he was not to worry as the appellant was building
the house. Mrs. Kortes says that she also asked him specifically when he was
going to finish the basement, to which he replied:—"I will see",
[Page 282]
or some such phrase, and she says that at no time did he
tell her that he was not going to do the work called for by the plan. All this
is completely inconsistent with the appellant's story. To this evidence there
was no answer as the appellant did not give evidence in rebuttal.
That there was a material part of the work called for by the
plans which had not been completed at the time the action was commenced
and which the appellant declined to complete is admitted. Of the work
required to be done in the basement, only what the appellant referred to as the
bearing partitions were erected. In addition, there was what he referred to as
"roughed in double plumbing." Asked as to what was meant by standard
double plumbing, the term employed in the contract, he said that it included a
bath, toilet and a basin. The walls of the various rooms, the closets in the
bedrooms and the den or study and the doors were not built and none of the
lathing and plastering, which the appellant admitted were indicated by the
plans was done.
The learned trial judge found that the claim for the
rectification of the agreement failed, that the appellant had not substantially
performed the contract, and dismissed the action. Upon the later point, he
applied, properly in my opinion, the principle referred to in the judgment of
our brother Cartwright in Fairbanks Soap Company v. Sheppard . In a short judgment delivered by
Johnson J.A. for the Appellate Division, agreeing, after consideration of the
evidence, with the findings of the learned trial judge, the appeal was
dismissed.
As to the claim for the rectification of the agreement, the
matter does not appear to me to admit of argument when, as here, the evidence
of the respondent and Hoffman as to what took place during the negotiations
which led up to the signing of the agreement has been accepted. The learned
trial judge, in considering the evidence necessary to support such a claim,
referred to a passage from the
[Page 283]
judgment of Duff J., as he then was, in The Ship M. F. Whalen v. Point Anne Quarries Ltd. , where the following language,
taken from the judgment of Sir W. M. James in MacKenzie v. Coulson
, was adopted, reading:—
that it is always necessary for the plaintiff to show that
there was an actual concluded contract antecedent to the instrument which is
sought to be rectified … It is impossible for this court to rescind or alter a
contract with reference to the terms of the negotiation which preceded it.
There was no such proof in the present matter, in the
opinion of the learned trial judge and of the learned judges of the Appellate
Division.
A point which arose during the argument of this appeal
remains to be considered, touching what was then said to be a wrongful
rejection of evidence tendered by the appellant. Upon this ground a new trial
is sought. The appellant called an architect, James B. Bell, who had examined
the plans and the building as constructed. Counsel for the plaintiff at the
trial said that he wished to show by the witness the cost of the house as it
stood and "that the house is a house without a completed basement."
Later, he said that:—
my question now would be limited to that particular phase of
the cost of this house and the cost of building the house according to the
letter of those plans as corroboration of the position taken by the plaintiff.
Both of these statements appear to me to be lacking in
clarity. When the learned trial judge said at once that he did not see that the
suggested evidence would be relevant, counsel for the plaintiff made no attempt
to explain the ground upon which he contended that it was and dropped the
matter. Some explanation of the nature of the proposed evidence and of its
suggested relevancy may perhaps be found in the Notice of Appeal given by the
plaintiff in appealing to the Appellate Division. Of the seven grounds of
appeal given, the fifth alone complains of the wrongful rejection of evidence
and reads:—
That the learned trial judge erred in failing to accept
evidence as to the interpretation of the contract.
This is not what was suggested to the learned trial
judge at the time and he, accordingly, had not ruled as to whether it was
admissible for this purpose. We are informed that
[Page 284]
no question as to the improper rejection of evidence
was argued before the Appellate Division. There is no reference to any such
question in the reasons for judgment delivered by Mr. Justice Johnson to that,
apparently, the matter was not considered. Had the question been argued and the
suggested evidence found to be admissible, no doubt the court would have
considered the application of Rule 604 of the Supreme Court of Alberta which
provides, inter alia, that a new trial shall not be granted on the
ground of the improper rejection of evidence unless, in the opinion of the
court, some substantial wrong or miscarriage has been thereby occasioned.
The argument advanced on behalf of the appellant before us,
if I correctly appreciate it, is that the evidence proposed to be given was to
show that the cost of completing the entire work shown on the plans was so much
in excess of the contract price of $18,000 that no experienced contractor would
have agreed to do so for that amount, and not, as suggested in the Notice of
Appeal, as an aid to the interpretation of the blue prints. If this was what
was intended at the time, it does not appear to have been made clear to the
presiding judge. Had it been admitted on the suggested basis, I think it is
most probable that the defendant would have called evidence on the point.
On the argument before us, counsel for the appellant was
asked if it was his opinion that the evidence that was rejected would have had
any effect upon the judgment of the trial judge as to the veracity of the
witnesses. He candidly stated that, in his opinion, it would not. Had the
question, which was clearly considered to be not worth arguing before the
Appellate Division, been raised there and had such a question been asked of
counsel, no doubt the same answer would have been given, with the result that
the Appellate Division, I would expect, would have applied Rule 604.
In Penn v. Bibby , where the defendant had not been
permitted at the trial to cross-examine some of the plaintiff's witnesses upon
matters which, it was contended, were relevant, Chelmsford L.C. said in part:—
In order to ground this objection, however, the question
proposed to be put should have been formally tendered to the Judge, and
rejected by him as inadmissible. Now, it appears that his Honour was never distinotly
[Page 285]
requested to admit any specific question, but from some
cursory remarks it is assumed that he would not have permitted a particular
line of cross-examination.
This, however, is not sufficient. The Judge should have an
opportunity of deciding upon some distinct question, and have refused to allow
it, before there can be a motion made for a new trial on account of the
rejection of evidence.
In my opinion, this principle is applicable in the
present matter. I do not think that the nature of the proposed evidence was
adequately explained to the learned trial judge to enable him to rule upon its
admissibility. Nor was any distinct question put to the witness upon which he
was asked to rule.
I am further of the opinion that where litigants
deliberately refrain from arguing questions such as this before the Appellate
Court of the Province, it should not be open to them to raise the question in
this Court. The failure to argue the question as to the rejection of evidence
raised by the fifth ground of the Notice of Appeal to the Appellate Division
was obviously deliberate. Had the matter been argued, we would have had the
advantage of having the opinion of the Appellate Division as to whether, in
their judgment, the matter was one for the application of Rule 604. The course
followed in this case has deprived us of that advantage. In Hamelin v. Bannerman
, where an appellant sought to
raise for the first time in this Court an objection that arbitration and award
were conditions precedent to the right to bring an action for damages,
Taschereau J.; whose judgment was concurred in by Sir Henry Strong C.J.,
Sedgwick and Davies JJ., said that, as the matter had not been mentioned in the
factums filed in either court, the point must be considered as abandoned. The
improper rejection of evidence is not one of the errors alleged in Part 4 of the
appellant's factum in this Court, though the matter is briefly mentioned in the
following written argument. In my opinion, this is a case for the application
of| the same principle and the point should be
[Page 286]
considered as abandoned or waived. See also Attorney
General for Canada v. Ritchie Contracting Company [(1915) 52 S.C.R.
at 92)], Fitzpatrick C.J.
I would dismiss this appeal with costs.
Appeal allowed; new trial directed.
Solicitors for the appellant: Lindsay, Emery, Ford,
Massie, Jamieson & Lambert.
Solicitors for the respondent: Shortreed &
Shortreed.