Supreme Court of Canada
Rocky Mountain v. Atlas Lumber Co., [1954] S.C.R.
589
Date: 1954-10-05
Board of Trustees of Rooky Mountain School Division
No. 15 (Defendant) Appellant;
and
Atlas Lumber Company Limited (Plaintiff) Respondent.
1954: May 6; 1954: October 5.
Present: Kerwin C.J.; Rand, Estey Locke and Cartwright JJ.
ON APPEAL FROM THE APPELLATE DIVISION OF THE SUPREME COURT OF
ALBERTA.
Mechanics' Liens—Materialman's—Whether materials
furnished under one continuous contract when contract abandoned and work
completed by owner—The Mechanics' Lien Act, R.S.A. 1952, c. 236.
Where materials are furnished a contractor for the erection of
a school but, due to the contractor's death', the contract with the school
board is abandoned by his estate, and further materials are supplied on the
owner's (the school board's) order and charged to it, the two contracts cannot
be tacked together to enlarge the time specified in The Mechanics' Lien Act,
R.S.A. 1952, c. 236, s. 24, for registering a lien for materials furnished
under the first contract.
Held: (Reversing the judgment of the Appellate Division
of the Supreme Court of Alberta, (1953) 8 W.W.R. (N.S.) 513) that the materials
furnished after the contractor's death were not supplied under the contract
entered into by him with the appellant Board of Trustees.
Per: Locke and Cartwright JJ.: Union Lumber Co. v.
Porter (1908) 8 W.L.R. 423 not followed; Whitlock v. Loney (1917) 3
W.W.R. 971, 10 Sask. L.R. 377 and Fulton Hardware Co. v. Mitchell (1923)
54 O.L.R. 472, approved.
APPEAL from the judgment of the Appellate Division of the
Supreme Court of Alberta
by which the judgment of the trial judge, McLaurin J. (now Chief Justice of the
Trial Division) which dismissed the respondent's claim to a lien under The
Mechanics' Lien Act upon a school building erected for the appellant was
set aside.
C. W. Clement, Q.C. and D. C. Bury for
the appellant.
S. J. Helman, Q.C. for the respondent.
The judgment of the Chief Justice and of Estey J. was
delivered by:—
The Chief Justice:—The
Appellate Division of the Supreme Court of Alberta unanimously reversed the
judgment at the trial and; as I find myself in disagreement with that result, I
propose, as shortly as may be, to state my reasons for this conclusion.
[Page 590]
In my opinion, the main point to be determined is one of
fact. Much was made by the respondent of the" difference between the
evidence of Whaley at the first sittings and when the trial was re-opened.
While on both occasions he was positive that the delivery of most of the lumber
sold on November 22, 1949, was to the old school (part having been taken by him
from the respondent's yard), he had stated at the first trial that all the
materials had been used for toilet doors, catwalk and coat racks in the latter,
while on the second occasion he admitted that in the old school the lumber was
therein made into bookcases and cabinets which were then taken to the new
school where they were installed. It also appeared that when Whaley's own claim
for lien was filed a mistake was made as to the dates upon which he had worked
for Matatall. The trial judge, having heard both stories, believed that Whaley
had been honestly mistaken at the first trial as to what had happened to the
lumber and that the error in his claim for lien was due to carelessness. The
trial judge preferred the evidence of Whaley where it was in conflict with that
of others, and I can find no ground for disagreeing with him.
I also agree that Matatall's contract with the appellant had
been abandoned by his executrix prior to November 22, 1949. Moreover, there is
no doubt that the order for lumber on that date was given by Whaley, nor that
he was then employed by the appellant Board and not by Matatall's executrix.
That is made clear not only by Whaley, but also by James Heron, the
respondent's retail manager at Rocky Mountain House. The yard slip was made out
in the name of the appellant and the items were charged to it in the
respondent's books and payment therefor was made by the appellant to the
respondent. At least part of the respondent's account against Red Deer
Construction Co. (under which name Matatall had carried on business), which
included the item of November 22nd, was compiled after the commencement of the
proceedings, since there is an entry under date of December 1, 1949, of $5
filing fee. That is the date of the claim for lien filed by the respondent, in
which document it is stated that all materials were furnished "on or
before the 2nd day of November A.D. 1949. The claimant ceased to furnish materials
on the 2nd day of November, 1949."; and, while an attempt was made to
explain this, I
[Page 591]
agree with the trial judge that the explanation is not
satisfactory, particularly when it is borne in mind that the amount of the
claim, $7,402.48, did not include the item of November 22, 1949. The account
sent by the respondent to the appellant shows an item of $26.55, represented by
the yard slip of November 22, 1949, which includes $21.20 for the lumber in
question and the balance for lumber for two different schools of the appellant.
Under these circumstances the transaction of November 22nd
does not support the respondent's claim for a lien. While section 6(1) of The
Mechanics' Lien Act, R.S.A. 1942, c. 236, gives a lien for materials
furnished for any owner, contractor, or sub-contractor, the enactment does not
mean, as contended by counsel for the respondent, that the materials may in any
case be furnished to any one of these three without regard to the contract
under which they were so furnished. Nor can there be any presumption under s.
6(2) of the Act:—
Materials shall be considered to be furnished to be used
within the meaning of this Act when they are delivered either upon the land
upon which they are to be used or upon some land in the vicinity thereof,
designated by the owner.
because, while the appellant was, on November 22, 1949,
the owner of the new school and the respondent might have a lien thereon if it
was not paid, there was no agreement between the respondent and Matatall, or
his executrix, for the delivery of this lumber so as to keep in force any lien
it might have by virtue of the original contract. S. 22(1) was also relied
upon, which section is in these terms:—
A lien in favour of a contractor or sub-contractor in cases
not otherwise provided for, may be registered before or during the performance
of the contract or sub-contract, or within thirty-five days (or in the case of
oil or gas wells or oil or gas pipe lines within one hundred and twenty days)
after the completion or abandonment of the contract or subcontract, as the case
may be.
As applied to the present appeal, the respondent's
subcontract with Matatall was not abandoned, as it was merely a contract for
the supply of materials as ordered by him from time to time. The section has no
application to the abandonment by the executrix of Matatall of the contract
between the latter and the appellant.
[Page 592]
It is unnecessary to consider the cases cited as, in my
view, they have no relation to the facts of the case. The appeal should be
allowed, the judgment of the Appellate Division set aside, and that of the
trial judge restored with costs throughout.
Rand J.:—I
think it the clear intention of the statute that the liens created shall be
related to the mediate or immediate contracts under which the particular work
is done or the particular materials furnished. S. 14(3) is explicit on this:—
(3) The lien shall be a charge upon the amount directed by
this section to be retained in favour of lienholders whose liens are derived
under persons to whom such moneys so required to be retained are respectively
payable.
Although the date shown on the claim of lien as that of the
last delivery of materials is November 2nd, evidence accepted by the trial
judge puts that date as October 26th and establishes the fact that the
materials delivered thereafter were ordered by and charged to the School
Division. Assuming that they were used for the purposes within the construction
contract, there would be no statutory holdback because the district was the
purchaser and the work was done by its own employees. So far as the respondent
Lumber Company was entitled to a lien, it would rank with those under the main
contract.
In ordering the materials, the School Division was not
acting under any contractual power to engage the credit of the main contractor;
it was acting either independently of the contract, by way of making an
addition to the building, or as an owner to complete work which the contractor
had abandoned or in relation to which he had committed a breach of his
obligation. In either view, the capacity of the company was not that in which
the goods were supplied to the 'contractor and their delivery cannot be
incorporated with those to the latter.
It is then argued that by sending a copy of the invoices to
the School Division as the materials were delivered there was given a notice,
in writing of the lien within the meaning of s. 14(4) of the statute. But s. 6
provides for a lien "unless he (the contractor) signs an express agreement
to the
[Page 593]
contrary". The delivery of goods does not, then,
necessarily raise a lien nor does the fact that the goods are furnished on
credit constitute notice that a lien is claimed.
The Act undoubtedly is to be interpreted to further its
purposes which are to provide security for those who contribute work or
materials to the construction of an improvement. But the legislature has made
it clear that that security may, in the absence of a notice, be limited to the
amount of the contract price unpaid and that the lien must be registered within
a specified time. To declare that it shall "absolutely cease to exist on
the expiration of the time hereinbefore limited for the registration
thereof" (s. 24(1)) leaves no room for judicial indulgence. The lien can
be registered before or during the supplying of material or within thirty-five
days after the last material has been furnished; and the notice of the claim of
lien to the owner affecting his payments to the contractor may be given at any
time after the lien arises. With this ample time within which a supplier may
act, it would be a distortion of the statute to stretch the interpretation of
its provisions to the extent argued by Mr. Helman.
For these reasons the appeal must be allowed and the
judgment at the trial of the issue restored with costs throughout.
The judgment of Locke and Cartwright JJ. was delivered by:-
Locke J.:—This
is an appeal by the Board of Trustees of Rocky Mountain House School Division
No. 15 from a judgment of the Appellate Division of Alberta by which the
judgment rendered at the trial by McLaurin J. (now Chief Justice of the Trial
Division) which dismissed the respondent's claim to a lien under The
Mechanics' Lien Act upon a school building erected for the appellant at
Rocky Mountain House was set aside.
On January 6, 1949, the School Division entered into a
contract with Hugh Matatall, a contractor carrying on business under the name
of Red Deer Construction Company, for the erection of a school-house on a
portion of its property at Rocky Mountain House. By the contract, Matatall
agreed to provide all the materials and perform all the work shown on the
drawings and described in the specifications
[Page 594]
prepared by Mr. Campbell-Hope, an architect, for the sum of
$54,900. Payments were to be made upon the architect's certificate on or before
the 10th day of each month for eighty per cent of the value, proportionate to
the amount of the contract, of labour and materials incorporated in the work or
delivered at the site up to the first day of that month as estimated by the
contractor and approved by the architect, less the aggregate of previous
payments.
The general conditions forming part of the contract
provided, inter alia, that the work should be done under the general
supervision and direction of the architect, that the owner might require the
contractor to furnish a bond covering the faithful performance of the contract
in such form as the architect might prescribe, that the owner or the architect
might make changes by altering or adding to the work the contract sum to be
adjusted accordingly, but, except in case of emergencies, no change should be
made unless in pursuance of a written order from the architect and no claim to
an addition to or deduction from the contract price should be valid unless so
ordered. It was further provided that if the contractor should neglect to
prosecute the work properly, the owner, after three days' written notice, might
make good such deficiencies and deduct the cost from the moneys due or to
become due under the contract, provided that the architect approved such action
and the amount charged to the contractor. There was further reserved to the
owner the right to terminate the contract upon written notice in certain
enumerated circumstances and the right to let other contracts in connection
with the undertaking of which the work described in the contract should be a
part.
Matatall, who apparently had done business with the
respondent company for some years in connection with other of his construction
operations, arranged with Carl Paulsen, then the respondent's manager at Rocky
Mountain House, for the supply of lumber and certain other materials for the,
work. There was no arrangement made binding either upon the respondent to
supply or Matatall to purchase all the materials required, but the evidence is
sufficient, in my opinion, to show that both parties contemplated that all the
required material of the kind handled by the respondent should be purchased from
it.
[Page 595]
Deliveries of material were made on the site commencing on
April 5, 1949. While payments had been made to Matatall on account of the
contract price prior to June 7, 1949, he had not made any payment to the
respondent and on that date, at the request of the latter, he gave a written
order, directed to the secretary of the School division, directing it to pay
all accounts as submitted by the lumber company and to charge the same to his
account. On July 5, 1949, Matatall gave a further order in writing, directed to
the School Division, authorizing it to pay to the respondent a sum of
$8,936.50, stated to be the amount due for the materials supplied by that
company for the new school and saying that further deliveries made were to be
paid according to statements rendered to the School Division by the lumber
company after being approved by Matatall. Pursuant to these orders, payments
totalling $8,846.64 were made prior to the date of Matatall's death.
On November 11, 1949, Matatall was killed in an automobile
accident. His widow, in her capacity as executrix of his last will, employed a
solicitor, Mr. W. J. C. Kirby, to advise her as to what should be done in
relation to the construction contract with the School Division, and on November
17th, Mr. Kirby went to Rocky Mountain House and, after discussing the
situation with Mr. Stronach, the secretary-treasurer of the School Division,
informed the latter that he did not think the estate would be in a position to
complete the contract. On the following day, Mr. Kirby wrote to Stronach
informing him that he had been instructed by the executrix to say that the
estate was not in a position at that time to finance the completion of the
school.
The claim of lien filed by the respondent in the Land Titles
Office for the North Alberta Land Registration District on December 3, 1949,
claimed a lien upon the estate of the Red Deer Construction Co. and the
appellant in the land in question in respect of materials which:—
were furnished (or which materials are to be furnished) for
RED DEER CONSTRUCTION CO. and the BOARD OF TRUSTEES OF THE ROCKY MOUNTAIN HOUSE
SCHOOL DIST. No. 2590 (sic) on or before the 2nd day of November A.D. 1949. The
claimant ceased to furnish materials on the 2nd day of November 1949.
[Page 596]
It is the contention of the appellant that the last delivery
of materials pursuant to the arrangement made between Matatall and the
respondent was on October 26, 1949, and that as this was more than 'thirty-five
days prior to the date upon which the claim of lien was registered, the lien
had ceased to exist prior to the registration of the claim in accordance with
the terms of s. 24 of The Mechanics' Lien Act (R.S.A. 1942, c. 236).
In the statement of claim delivered in this issue, the
respondent claimed that the last material was furnished to the School Division
and the Red Deer Construction Company on or about November 22, 1949. Nothing
was said in the pleading as to the date which was given as the date of the last
delivery in the lien filed having been made by mistake. The justification for
the claim that the last delivery was on November 22nd is to be found, if at
all, in a delivery of materials made after Matatall's death under the following
circumstances: Prior to Matatall's death, he had employed a carpenter named
Whaley on this work. On an adjoining property to that upon which the new school
was in course of completion, there was an old school building and on November
11th Whaley was doing certain carpenter work there, the exact nature of which became
the subject matter of dispute at the trial. When Mr. Kirby had been at Rocky
Mountain House, on November 17th, he said that he had asked Whaley for a
statement of his wage claim against the estate and he obtained this made up to
November 11th. Thereafter, Whaley said that he was employed by the School
Division in doing certain carpenter work and on the instructions of the
principal and the secretary-treasurer, he ordered material from the respondent
amounting to $22.10 for the purpose of doing certain work on 'their
instructions in the old school. Whaley said that from November 12th on he was
working for and was thereafter paid by the School Division. As it had been
shown that the last previous delivery of material was on October 26, 1949, the
learned trial judge, at the conclusion of the argument, dismissed the action on
the ground that the claim of lien had been filed too late, as the transaction
of November 22nd was an isolated transaction relating to the old school
building and had no connection with the contract between the School Division
and the Red Deer Construction Company.
[Page 597]
Some time later, but before judgment had been
entered, upon the application of the present respondent, the hearing was
reopened and additional evidence given in an endeavour to show that Whaley had
been mistaken in saying that the work he had done after November 11th, for
which the material had been delivered on November 22nd, was required, was done
in the old school. Both parties were permitted to give further evidence. When
recalled, Whaley said that he had been mistaken in saying that the material was
required for work done upon the old school, but it had been used for making
certain cabinets and also some shelves to go over the radiators. He said that
he had done this work on the orders of the Principal of the school and
Stronach, the secretary-treasurer and that it had nothing to do with Matatall
nor was it part of the Matatall contract. While the evidence of this witness,
as to the exact nature of the work in question, is not entirely clear and there
is no description of the nature of the cabinets referred to, it is undoubted
that it was done on the instructions of the officials of the School Division
referred to and the necessary material, on their instructions, purchased on the
credit of the School Division. There is no suggestion that this work was either
directed to be done or authorized by the architect or that he had anything to
do with the matter.
Further evidence given on behalf of the respondent on the
continued hearing was given by Mr. Ellenwood who had been the manager of the
respondent's yard at Red Deer at the time and who had gone with Mr. Kirby to
Rocky Mountain House on November 17, 1949, who said that when they were in the
new school building on that day Whaley was working there and had been
instructed by Mr. Kirby and Mr. Stronach "to get this lab completed so
they could get into it."
Mr. Kirby who had been called for the first time on the
continued hearing was not asked as to whether he had given these instructions.
Whether the work of completing the laboratory included the making of the
cabinets and the shelving to go above the radiators is not shown nor indeed
where these articles were to be placed. Whaley, however, had said that the work
which he had done after Matatall's death was on the instructions of the
officials of the School Division as above stated, a statement which is borne
out
[Page 598]
by the fact that he was paid for this work by the Division
and that when he went to the dumber yard to order the material on November
22nd, he directed that it be charged to it. The learned trial judge has said
that he considered Whaley to be an honest man and accepted his testimony where
it was in conflict with that of other witnesses, and I can see no ground for
differing from this finding.
The evidence given on behalf of the respondent as to the
manner in which the transaction of November 22nd was treated by it requires
close examination. Mr. W. S. Heron was the manager of the yard of the
respondent at Rocky Mountain House from some time in April, 1949, and it was
upon his evidence that the respondent relied to prove its account. Heron, in
addition to his other duties, apparently kept the books and, in giving evidence
at the first hearing, he said that the respondent's account with the Red Deer
Construction Company ran until October 26, 1949. In giving evidence in chief,
he produced a number of documents called "yard slips" and these
included one made out on November 22, 1949, for material the price of which
amounted to $26.55, the slip reading that the material was -"sold to R.
Mt. House School Div.", and being signed by Whaley who, Heron said, was
working for the School Division. This account included materials amounting to
$4.45 to be delivered to two other schools and which were not ordered by
Whaley, the amounts being entered on the slip after he had signed it. The
balance was for the material delivered that day to the school in question.
There were also produced and put in evidence at the same time certain ledger
sheets showing the Red Deer Construction Company's account with the respondent
running back to the year 1946 and the account of the School Division, and it
was in the latter account that the material ordered by Whaley and the two
amounts delivered to other schools were charged. Heron was unable to explain
how it was that in the claim of lien filed, the statement was made that the
materials were furnished on or before the second day of November, other than to
suggest that it was a mistake made at the head office of the respondent in
Calgary where the yard slips and journal pages had been sent for the purpose of
making up the claim of lien. He was not recalled when the hearing was continued
and further evidence taken. It is common ground that there were no deliveries
[Page 599]
on November 2nd, and in the examination for discovery of Mr.
J. P. Glaum, an officer of the respondent, it had been admitted that the last
delivery prior to that date was October 26th. It is of importance to note that
the amount of the lien claimed by the respondent was $7,402.48 and that this
amount did not include the sum of $22.10 for the material delivered on November
22nd. It was also stated by the counsel for the respondent at the trial that
the School Division had paid for the material delivered on November 22nd.
The learned trial judge, after hearing the further evidence
adduced by the parties, delivered written reasons for his judgment dismissing
the claim in which the relevant portions of the evidence of Heron to which I
have referred are quoted. In the course of these reasons, it was said that the
School Division and not Matatall were billed for the material delivered on
November 22nd. In delivering the judgment of the Appellate Division, Mr.
Justice Frank Ford has said that this was incorrect and that what had happened
was that the original delivery slip was made out on that date to the School
Division and that:—
Although set. up in the appellant's books as a debit to the
School Division another statement bearing the same date was made out to
"Red Deer Construction in account with Atlas Lumber Company Ltd".
Thus it appears that the item was "billed" to both.
With great respect, I do not think that the evidence
supports the latter statement. Heron's uncontradicted evidence makes it quite
clear that the material sold on November 22nd on Whaley's order was supplied on
the credit of the School Division and the amount was charged to it and not to
Matatall. Whaley's evidence makes it equally clear than he was instructed by the
officials of the School District to purchase the material and did so, directing
Heron to charge the amount to them. Matatall had then been dead for eleven days
and Whaley had no authority to order material on his credit even if he had
assumed to do so. There appear, however, among the exhibits in this case copies
of a number of accounts of the respondent company charged to "Red Deer
Construction" commencing on September 4th and continuing to November 22nd,
which were put in, during the course of Heron's evidence in chief. In answer to
a question asked by counsel for the respondent at the trial whether the
documents included in
[Page 600]
this exhibit, which was marked Exhibit 13, had been sent to
the School Division, he said that this was right. Included in Exhibit 13 was a
statement dated November 22, 1949, for the items making up the amount of $22.10
made out against "Red Deer Construction". A further account made out
against "Red Deer Construction" bearing the dates September 24, 1949,
November 22, 1949, shows that an entry on November 22nd of $22.10 was included.
No explanation was given by Heron or by anyone else as to how this document
came to be made up. It was apparently made, however, not at the time the
material was purchased but on or after December 3, 1949, since under that date
at the foot of the statement there appears an entry "fee filing lien
$5.00." A further matter to be noted is that the balance shown as owing by
the Red Deer Construction Company on this statement is $7,424.58, while, as pointed
out, the claim of lien was for $22.10 less. There is no proof to be found in
this record that these accounts were ever rendered to the Red Deer Construction
Company or to Mrs. Matatall as executrix of her husband's estate, and, on the
contrary, . Heron's evidence proves conclusively that no charge had been made
against anyone but the School Division for the amount in question at the time
the material was supplied.
The learned trial judge further found upon the evidence that
by November 22nd, the contract between Matatall and the School Division had
been abandoned. The learned judges of the Appellate Division have disagreed
with this finding, holding that the evidence does not show any such
abandonment. In the view that I take of the matter and in the circumstances of
the present case, I think the point is immaterial. It should, however, be noted
that when Mr. Kirby wrote the letter of November 18, 1949, to the School
Division, which would no doubt be received before November 22nd, the latter
apparently proceeded to treat the contract as being at an end. As to this the
evidence of Mr. Stronach, the secretary-treasurer, is clear.
From the date of the receipt of Mr. Kirby's letter, the
School Division apparently took charge of the completion of the school. The
provision of the agreement which gave the owner the right to terminate the
contract upon written notice, was apparently not complied with, the letter from
[Page 601]
the solicitor apparently being treated as a refusal to
complete and the Division electing to rescind. There is no evidence that the
matter of the performance of the further work, either that done by Whaley after
November 11th or by other workmen, was authorized in writing by the architect,
as provided by the agreement. The only question of law to be determined in the
case is as to whether, under these circumstances, the respondent's claim of
lien was filed in time.
By The Mechanics' Lien Act, a person who furnishes
any materials to be used in the construction of any improvement for any owner
or contractor has, by virtue thereof, a lien for so much of the price as
remains due to him upon the estate or interest of the owner in the improvement,
subject in the case of material supplied at the instance of a contractor rather
than directly to the owner, to certain limitations. By s. 14 of the Act, the
person primarily liable upon a contract by virtue of which a lien may arise, is
required to retain for the statutory period 15 per cent of the value of the
work actually done where the contract price, as in the present case, exceeds
$15,000. The lien is declared to be a charge upon the amount directed by this
section to be retained in favour of lienholders whose liens are derived, under
persons to whom the moneys so required to be retained are respectively payable.
The section further provides that all payments up to 85 per cent in a case such
as this, made in good faith by the owner to a contractor before notice in
writing of the lien is given by the person claiming the 'lien to the owner, shall
operate as a 'discharge pro tanto of the lien.
By the terms of the contract in this matter, it was
provided, however, that 20 per cent of the value of the work should be held
back and the evidence of Mr. Stronach on behalf of the School Division shows that
this was done. The lien which the respondent was entitled to assert in respect
of the material supplied by it on the orders of Matatall up to October 26,
1949, differed materially from that which is was entitled to assert against the
School Division in respect of material delivered from November 22, 1949 onward,
in that the former claim was subject to the limitations of s. 14, while the
latter claim was not.
[Page 602]
The respondent's contention to which effect has been given
in the judgment of the Appellate Division is that the delivery of November 22nd
was not made under a separate contract but, as stated in the reasons:—
was a delivery under the contract between the owner and the
contractor
and accordingly preserved the right of lien. The only
authority to which we have been referred in support of this finding is a
judgment of Harvey J., as he then was, in Union Lumber Co. v. Porter . In that case, the contractor,
after proceeding part way with the contract, abandoned the work and the
building was completed by the owner. Prior to the abandonment, material had
been supplied to the contractor and afterwards further material was delivered
on the directions of the architect. None of the material delivered at the
instance of the contractor was furnished within thirty-one days of the time of
the filing of the lien, being the statutory period in Alberta at that time. As
to this Mr. Justice Harvey said:—
I think the continuing to supply material keeps the lien
alive under the terms of the statute in respect of all material supplied
before. If it were otherwise, all a person who wished to get rid of a lien
would need to do would be to pay for the last 31 days' work or material, and so
cut out the claim for all that was done or supplied before.
Dealing first with the statement made in the second
sentence, it could hardly be contended that the lien of a material man
supplying material for an improvement at the request of the contractor engaged
in performing the work, could be disposed of in this manner. With great
respect, however, for the opinion of the late learned Chief Justice of Alberta,
I am unable to perceive how this statement bears upon the proposition stated in
the first sentence. While the question does not directly arise in the present
case, it was decided in Morris v. Tharle , that where there is a general
arrangement, even though it be not binding, between a contractor and a supplier
of building material for the supply of all the material required for a
particular building contract, the entire transaction, although it may extend
over some months, is linked together by the preliminary understanding on both
Slides and a lien for all material so supplied is in time, if filed within
thirty days of the furnishing of the last item. The reasoning of the Divisional
Court in that case was adopted by Killam
[Page 603]
C.J., in Robock v. Peters . In the view of the law as it was
stated by Chancellor Boyd in Morris v. Tharle and adopted by
Killam C.J., the lien would not be affected if there were a greater period than
the time within which the lien must be registered after the delivery of the
last material between deliveries made from time to time as the work progressed.
In my opinion, this statement of the law applies to liens arising under The
Mechanics' Lien Act of Alberta, but as a period of thirty-eight days
elapsed from the time the respondent ceased to furnish material under the
arrangement made between Matatall and Paulsen, the question does not arise.
The opinion expressed in the first sentence of the quotation
raises an entirely different and, in my view, unrelated question. For the
conclusion of the learned judge no authority was given. While the arrangement
made between Matatall and Paulsen was rather indefinite and the former did not
obligate himself to purchase all the required material from the respondent nor
agree upon the prices to be paid, I think that, as I have said, the evidence is
sufficient to show that both parties contemplated that, as in the case of other
earlier contracts, Matatall would order and the respondent company would supply
such lumber and other building material of the kind sold by it as was necessary
for carrying out the contemplated1 work. In this respect the
position of the respondent is supported by the authorities to which I have
above referred. The agreement to be inferred from the conduct of the parties,
however, was solely between Matatall and the respondent: there was no privity
of contract between the respondent and the School Division and there could
accordingly be no claim upon a money count for material supplied under the
arrangement with Matatall, the only remedy as against the owner being that
provided by The Mechanics' Lien Act, if the terms of that statute were
complied with. Upon the respondent's own showing, the last delivery made by it
under the agreement with Matatall was on October 26, 1949, and within a few
days after his death on November 11th it was made clear to the parties that his
estate did not propose to continue with the work or complete the contract with
the School Division. This fact was recognized by the respondent in supplying
[Page 604]
all the required material thereafter at the request and on
the credit of the School Division without any reference to Matatall's personal
representative. The right to a mechanics' lien which accrued to the respondent
by virtue of the delivery of the material on November 22nd and thereafter,
arose by virtue of the arrangement it made following Matatall's death with the
School Division, and in respect of that right a separate lien must have been
filed to preserve the respondent's position, in my opinion, had the claim not
been extinguished as it was by payment.
I am unable, with respect, to agree with the statement
contained in the judgment of the Appellate Division that the delivery of
November 22nd was not made under a separate contract but was a delivery under
the contract between the owner and the contractor. The evidence, in my opinion,
clearly demonstrates the contrary. While it was by virtue of the fact that the
School Division had entered into the contract for the erection of the school
building with Matatall that the respondent might, by furnishing material at
Matatall's request, acquire the statutory right of lien upon the property of
the School Division, that fact does not mean that deliveries made under the
arrangement made between the respondent and Matatall were deliveries under the
contract between the School Division and the latter. To that contract the
respondent was a complete stranger. To the agreement made between the School
Division and the respondent for the supply of material after Matatall's death,
the estate of Matatall was equally -a stranger. That the right to a lien which
arose by virtue of the supply of material after Maitatall's death under these
circumstances is distinct from that which was vested in. the estate of Matatall
appears to me to be clear from a consideration of ss. 6, 13 and 14 of The
Mechanics' Lien Act.
Further support for the view which I have expressed is to be
found in the statement of the law adopted by Lamont J. in Whitlock v. honey
, to which reference is made in
the reasons for judgment of the Appellate Division. In that case Lamont J.
adopted the following statement taken from 27 Cyc. 114:—
Where labour or materials are furnished under separate
contracts, even though such contracts are between the same persons and relate
to the same building or improvement, the contracts cannot be tacked together
[Page 605]
so as to enlarge the time for filing a lien for what was
done or furnished under either, but a lien must be filed for what was done or
furnished under each contract within the statutory period after its compliance.
Where, however, all the work is done or all the materials are furnished under
one entire continuing contract, although at different times, a lien claim or
statement filed within the statutory period after the last item was done or
finished is sufficient as to all the items; and in order that the contract may
be a continuing one within this rule it is not necessary that all the work or
materials should be ordered at one time, that the amount of work or materials
should be determined at the time of the first order, or that the prices should
be then agreed upon, or the time of payment fixed; but a mere general
arrangement to furnish labour or materials for a particular building or
improvement is sufficient, if complied with, even though the original
arrangement was not legally binding.
In effect, what has been attempted in the present case is to
tack the right of lien acquired by the respondent under its arrangement with
Matatall to that which subsequently arose under its arrangements with the
School Division. It may be noted that this statement of the law was adopted by
the Appellate Division of Ontario in Fulton Hardware Co. v. Mitchell .
While this is decisive of the matter, in my opinion, it may
further be noted that the material delivered on November 22nd was not for the
purpose of carrying out work to be done under the contract between the owner
and the contractor. According to Whaley, none of this work was specified by the
contract. The School Division, apparently electing to treat the contract with
Matatall as rescinded and at an end, did not act under its terms and ask the
authority of the architect for this work outside the terms of the contract, but
clearly undertook the work on its own account. Thus the materials were not
supplied nor the work done under the contract.
I would allow this appeal with costs throughout and dismiss
the action.
Appeal allowed with costs.
Solicitors for the appellant: Smith, Clement,
Parlee & Whittaker.
Solicitors for the respondent: Helman &
Barron.