Supreme Court of Canada
Bourk v. Canada Products Ltd., [1928] S.C.R. 573
Date: 1928-04-30
Robert H. Bourk (Defendant)
Appellant;
and
Canada Products
Limited (Plaintiff) Respondent.
1928: April 30.
Present: Anglin C.J.C. and Mignault,
Rinfret, Lamont and Smith JJ.
ON APPEAL FROM THE COURT OF APPEAL FOR
SASKATCHEWAN
Pleadings—Refusal of amendment at trial—New
trial ordered—Costs—Claim for breach of logging contract.
On the question, whether plaintiff or
defendant was responsible for termination of a logging contract between them,
the trial judge, on his construction of defendant’s counterclaim, held that
defendant was not entitled to rely on what took place prior to November 14,
1924, and refused to allow amendment. The Court of Appeal, Sask. (27 Sask. L.R.
29, allowing plaintiff’s appeal, and dismissing defendant’s cross-appeal, from
the judgment at trial) took the same view on the pleadings, and also refused
amendment. On defendant’s appeal to this Court, a new trial was directed, as
the Court, while not holding that the construction given below to the pleading
was erroneous (though such construction seemed to this Court rather narrow), or
that the trial judge had wrongly exercised his discretion as to amendment, was
of opinion that, under the circumstances, the trial was unsatisfactory, and
that justice could only be done by a new trial. Costs down to the asking of
amendment at trial were to be borne by defendant, costs subsequent thereto to
be in the discretion of the judge presiding at the new trial.
APPEAL by the defendant from the judgment of
the Court of Appeal for Saskatchewan
allowing the plaintiff’s appeal and dismissing the defendant’s cross-appeal
from the judgment of Maclean J. at the trial.
The parties entered into a contract whereby
the defendant was to cut, log and deliver timber at the plaintiff’s mill. The
contract came to an end, the responsibility for which was a matter in dispute.
The plaintiff sued for moneys alleged to have been paid by it, after the
termination of the contract, to release liens placed upon their logs for wages
due to the defendant’s workmen. The defendant disputed the claim, and, alleging
that the plaintiff had wrongfully repudiated and terminated the logging
contract, counter-claimed for damages.
Maclean J. held that the plaintiff was
responsible for the termination of the contract, and that, as its claim arose
[Page 573]
under the contract, it could not recover, and
dismissed the action; but he also held that, under the circumstances to be
considered in fixing the basis and quantum of damages, and taking into account,
for the purpose of estimating the damages, the moneys paid by the plaintiff to
discharge the workmen’s liens, the defendant had suffered no actual damage, and
he dismissed the defendant’s counterclaim. The plaintiff appealed, and the
defendant cross-appealed, to the Court of Appeal for Saskatchewan. That Court held that the defendant must be held
responsible for the termination of the contract; that the plaintiff’s claim
should have been allowed, and the defendant’s counterclaim dismissed; and,
accordingly, allowed the plaintiff’s appeal and dismissed the defendant’s
cross-appeal.
On the question of the responsibility for the
termination of the contract, the judgments at trial and in the Court of Appeal
proceeded upon what took place between the parties on and after November 14,
1924. Late in the course of the trial the judge interrupted defendant’s
counsel, while examining a witness, to remind him that the defendant was not
complaining in his pleadings of having been delayed by the plaintiff before
November 14. Counsel for defendant asked that, if necessary, he be allowed to
amend, but this was refused. The Court of Appeal
took the same view as the trial judge as to the limited interpretation and
effect of the defendant’s pleading in charging the plaintiff for breach of
contract, and also refused to allow an amendment. In the course of his argument
before the Supreme Court of Canada, counsel for the defendant contended that a
too narrow and strict interpretation had been taken of the defendant’s
pleadings in his counterclaim, and that, on such pleadings, he was entitled to
rely on events prior to November 14, 1924.
After hearing argument by counsel for both
parties, the members of the Court retired, and on their returning to the Bench,
the judgment of the Court was orally delivered by
Anglin C.J.C.—While we are not prepared to hold that the view taken by the
trial judge and affirmed by the Court of Appeal as to the proper construction
of the pleading is erroneous, we think it rather narrow. We also think that
[Page 575]
justice was much more likely to be done if
the amendment asked for had been granted. Without reviewing the judgments
below, and while not saying that the learned trial judge wrongly exercised his
discretion, we are all of the opinion that the trial was unsatisfactory, and
that justice between the parties can only be done by a new trial. A new trial
is accordingly directed. The costs down to the time when Mr. Gregory asked for
the amendment at the trial (Case, p. 111), will be borne (and are to be paid
forthwith) by the defendant. The costs subsequent to that time are to be in the
discretion of the judge who presides at the new trial, including the costs of
this appeal.
New trial ordered.
C. E. Gregory K.C. for the appellant.
C. C. Robinson K.C. for the respondent.