Supreme Court of Canada
Boone v. The King, [1934] S.C.R. 457
Date: 1934-04-24.
Frank L. Boone (Suppliant)
Appellant;
and
His Majesty The
King Respondent.
1933: October 18, 19; 1934: April 24.
Present: Rinfret, Lamont, Smith, Crocket and
Hughes jj.
ON APPEAL FROM THE EXCHEQUER COURT OF CANADA
Contract—Construction of ice pier for
Crown—Alleged delay of contractor—Work and contractor’s plant, etc., taken over
by Crown for completion of work—Claim by contractor for damages—Proposed change
in plan of work—Lack of instructions in writing—Alleged conduct of Crown’s
engineers as excuse for contractor’s delay—Petition of
Right—Parties—Non-joinder of co-contractor.
Appellant and one V. (who was not a party to
the action) contracted with the Crown to build an ice pier, and did some of the
work. In the foundation work, the contract required excavating the bottom to
bed rock by dredging. Dredges chartered by appellant abandoned the work because
of difficulties encountered, and appellant complained to the Crown’s District
Engineer that the dredging was impossible of performance. The District Engineer
changed the plan of the work so as to eliminate the dredging and secure the
foundation by other means, and directed appellant to proceed on the plan as
changed. The District Engineer and appellant differed in their estimates of the
nature of the change made and of the extra cost involved, and appellant asked
for written instructions, which were not given. A
[Page 458]
deadlock ensued and the time within, which,
under the contract, the work was to be completed, expired. The Crown’s Chief
Engineer gave notice to the contractors, in pursuance of a clause in the
contract, to put an end to their
“default and delay” and that, if within a certain time satisfactory progress
was not made, the Crown would take the work out of their hands and complete it;
and, the work not being proceeded with, the Crown, on further notice, and
purporting to act under said clause, took over the work and appellant’s
materials and plant and proceeded to complete the work according to the plan as
changed. Appellant sued (on petition of right) for damages.
Held, reversing
judgment of Maclean J., President of the Exchequer Court, [1933] Ex. C.R. 33, Lamont and Hughes JJ. dissenting, that,
upon all the facts and circumstances and the proper construction of the
contract, the appellant was entitled to succeed.
Per curiam: The
nature of the change made in the plan was such as required, under the contract,
written instructions from the Chief Engineer; also, in the absence thereof, the
Chief Engineer’s said notice requiring satisfactory progress to be made, must
be taken to mean to proceed under the original plan. Per Rinfret and
Crocket JJ.: Previous to the change of plan there was no delay of which the
Crown could now complain; and the delay after the change of plan was directly
attributable to the Crown itself, because, while its District Engineer (a
recognized departmental representative and the real controlling spirit in all
that pertained to the contract and its execution throughout) had directed to
proceed on the new plan, it failed to give written instructions, in accordance
with the contract, to do so; therefore the taking over by the Crown of the work
and materials and plant was not justified (Roberts v. Bury Improvement
Commissioners, 39 L.J.C.P. 129, Lodder v. Slowey, 73 L.J. P.C. 82, cited). Further, the Crown did
not bring itself within the clause under which it purported to act, as that
clause, fairly construed, contemplated that the contractors should be made
aware of the specific default or delay with which the engineer was
dissatisfied, and, to justify under it, the Crown must show that the
contractors were guilty of some default or delay in diligently executing some
part of the contract work to the engineer’s satisfaction (the intention being
that the engineer in the exercise of his judgment should act justly and
reasonably); and the facts failed to discharge that onus and, further,
absolutely negatived justification of the Crown’s act. The case should be sent
back to the Exchequer Court for assessment of damages, with right to appellant
to join V. in the petition (though quaere whether this was necessary, in
view of the terms of the partnership agreement between appellant and V. Atkinson
v. Laing, 171 E.R. 901,
referred to).
Per Smith J.:
There was actually little delay on the contractors’ part that counted, except
what was caused by the miscalculation that it was practicable to do the
dredging in the manner attempted. This was a miscalculation of the engineers
that was relied on by the contractors, though they were not warranted in doing
so by the terms of the contract. But, when the District Engineer directed the
change of plan, the contractors were justified in insisting upon approval
thereof by the Chief Engineer in writing before proceeding further. Although
the notice by the Chief Engineer to proceed could mean only, in the absence of
written instructions to the contrary, to proceed on
[Page 459]
the original plan, yet, as the Crown
subsequently proceeded on the changed plan, the latter was the one clearly
contemplated, and there was never any intention of resorting to the original
plan. The contractors were never in default as to the changes, and appellant
should ‘ succeed on his claim. The case should be sent back for assessment of
damages in the manner directed by Rinfret and Crocket JJ.
Per Lamont J.
(dissenting): There was unreasonable delay by the contractors in engaging
dredges. It was not established that the dredging was impossible of
performance; on the evidence, it could have been done, though probably at
considerable expense. Moreover, in view of provisions of the contract,
appellant was not entitled to recover from the Crown his expense in connection
with the attempt to operate the dredges on the footing of impossibility of
performance. The contractors, with the contract before them, must be held to
have known of the lack of authority to make the proposed change in the plan of
the work in the absence of written instructions from the Chief Engineer. The
trouble arose by reason of their failure to examine the bottom, though a
certificate in their tender indicated they had done so. They should have known
beforehand whether dredges such as were employed were sufficient for the work.
The Crown could not be mulcted in damages for alterations made by an official
who had no authority to make them. The judgment of the Exchequer Court should
be affirmed, with the variation suggested by Hughes J.
Per Hughes J.
(dissenting): The District Engineer had no power to make the proposed
alteration in the work, and, in the absence of written instructions from the
Chief Engineer, the contract, plan, and specifications remained as they were
originally. The contractors must have been aware of said lack of power in the District
Engineer. The contractors were in default on the date limit set by the contract
for completion; and the difficulty in dredging was not a valid excuse for such
default (Thorn v. The Mayor and Commonalty of London, 1 App. Cas. 120, at 132; Connolly v. City
of Saint John, 35 Can. SCR. 186, referred to). Under the terms of the
contract the Crown was entitled to take over and use appellant’s materials and
plant to complete the work, even with changes in plan. The appeal should be
dismissed, but the judgment should be without prejudice to any proceedings in
proper form which appellant might, if so advised, subsequently take against the
Crown for the return of, or damages in respect of, any materials or plant not
used up by the Crown in accordance with the contract and improperly withheld.
APPEAL by the suppliant from the judgment of
Maclean J., President of the Exchequer Court of Canada, holding that he was not entitled to the
relief sought by his Petition of Right herein, in which he claimed damages from
the Crown in respect of a contract for the construction of an ice pier at Barrington Passage, Nova Scotia, the Crown
having, by reason of alleged default and delay in the work, taken the work out
of the contractons’ hands and taken possession of appellant’s materials and
plant
[Page 460]
for purposes of completion of the work. The
material facts of the case are sufficiently stated in the judgments now
reported. The appeal was allowed with costs and the judgment of the Exchequer
Court was set aside and the case sent back to that court for the assessment of
damages, with a reservation of the right of the suppliant, if deemed advisable,
to join in the Petition one Voye, who had, with the suppliant, been a party to
the said contract. Costs in the Exchequer Court were left in the discretion of
that court. Lamont and Hughes JJ. dissented.
P. J. Hughes K.C. for the appellant.
A. N. Carter for
the respondent.
The judgment of Rinfret and Crocket JJ. was
delivered by
Crocket J.—I find it impossible upon the evidence to avoid the conclusion
that the real reason for the action of the Department of Public Works in
terminating this contract and confiscating the contractors’ material, plant and
equipment was the impossible situation in which the contractors were placed by
the failure of Locke, the supervising resident engineer, or the Chief Engineer
himself to provide the necessary written confirmation of the radical change
which the former had ordered in August, 1929, in the contract plans and
specifications regarding the construction of the foundation for the pier, and
not any default or delay on the part of the contractors before that time, as
the Department is now contending.
Locke admitted that on August 13, 1929, after
the powerful dredge Leconsfield had tried unsuccessfully to do the
required dredging for the foundation of the pier, following the failure of the
dredge J. A. Gregory, he told Boone that it was not feasible to excavate
by a dredge to the rock, as required by the contract specification, and that he
would make a change in the plans. He admitted that he did make a change in the
original plan, for another foundation than that specified in the contract,
which it was not denied affected not only the foundation itself but
necessitated the reduction in the height of the crib, which the contractor at
that time had built on the shore, all ready to float and place in position on
the site as soon as the foundation was
[Page 461]
prepared. He admitted that he delivered a copy
of the changed plan to the contractor and another to Mr. McKay, the inspector,
and that he notified Mr. Allison, an engineer also employed in his office and
to whom much of the supervision of this contract work was entrusted. On August
28 he telegraphed Boone to start the bag concrete foundation on the changed
plan. Boone wrote Locke the following day acknowledging this telegram and
requesting, as he had previously personally done, to have the instructions
concerning the proposed changes made in writing before commencing the new work.
This letter Locke did not acknowledge and in his testimony, under questioning
by the respondent’s counsel, admitted that he deliberately waited until the
expiration of the contract and then reported to the Chief Engineer of the
Department at Ottawa and that the Chief Engineer then notified the appellant’s
firm of the expiry of the contract.
The Chief Engineer’s notice appears under date
of September 11, 1929, and recites the making of the contract on September 22,
1928, and that by the terms thereof the work should have been satisfactorily
executed and completed within twelve months from the date of notification of
the acceptance of the firm’s tender, viz., on or before September 1, 1929, and
then proceeds:
And Whereas, you have made default and
delay in diligently continuing to advance or execute the said works to the
satisfaction of the undersigned;
Therefore, the undersigned, in pursuance of
Clause 19 of said contract, hereby requires you to put an end to said default
and delay, and if within six days from the service hereof on you, satisfactory
progress is not made with the said works, His Majesty the King, represented by
the Minister of Public Works, intends to avail Himself of the provisions of
said Clause and take the said works out of your hands and complete them.
To this notice the appellant’s firm replied on
September 18, giving, as my brother Smith states in his judgment, an accurate
account of the situation which had developed in connection with the dredging,
calling the Chief Engineer’s attention to the fact that he had asked for
written instructions covering the changes which had been made by the resident
engineer in the plan and stating that as soon as the Department gave them these
instructions they were prepared to deal with the work just as expeditiously as
they reasonably could and asking that the written instructions
[Page 462]
be given them without delay. This letter, it
seems, was not acknowledged either. On September 25, after receiving a long telegram from Locke, which shews that the
Chief Engineer had forwarded to him the contractors’ letter of the 18th, and
which telegram advised that the Department was fully justified in completing
the work itself, the Chief Engineer on September 25 again wrote the appellant’s
firm that,
as no satisfactory progress has been made
since my notice has been served upon you it has been decided to take the work
out of your hands, in pursuance of Clause 19 of [the contract],
and that “the materials, tools, equipment, etc.,
become the property of the Department.” This letter stated that “the required
instructions have been given Mr. District Engineer Thomas J. Locke,” to whom
the firm was referred for any further information.
The Department afterwards proceeded with the
work itself under Mr. Locke’s supervision and upon the changed plan which the
latter had made, using the appellant’s materials and equipment therefor.
The Chief Engineer’s notice of September 11,
1929, was the first complaint made to the contractors by that official of any
default or delay in diligently executing any part of the work to his
satisfaction after the signing of the contract by the Deputy Minister on
September 22, 1928. There is not a written line of any such complaint by any
officer or representative of the Department in the whole record from the date of
the signing of the contract until that notice was served. The only exhibit
containing even so much as a suggestion that there had been any delay of any
kind on the part of the contractors is Locke’s letter of May 8, 1929. This is
the letter in which Locke confirmed his conversation of the previous day
regarding the creosoting of the timber for the crib after six weeks’ seasoning
instead of four months’ seasoning which the creosoting plant usually insisted
upon. “This concession,” Locke stated in that letter, “was made you in order to
expedite commencement of this work at the earliest possible date,” and he
added:
I wish to emphasize the importance of your
not neglecting any opportunity of procuring a suitable dredge quickly for the
purpose of having the foundation excavated and work commenced June 1, 1929.
It is true that on the trial he said, in answer
to questions by the respondent’s counsel, that he was not satisfied
[Page 463]
with the progress the contractors had made up to
May 7, and that he felt that they should have made arrangements the first part
of September when they heard they had the contract—that was before the contract
was signed—and it was the first of May when they were trying to procure
dredges. In cross-examination, however, he admitted that he approved of the
creosoted timber; that he did not expect any actual work to be commenced before
spring; and that the earliest time he would expect the contractors to undertake
the dredging would be between the middle of May and June 1. His letter of May 8
itself, it will be noted, made no complaint of any delay that had occurred in
connection with the dredging, but merely impressed upon the contractors the
importance of procuring a suitable dredge quickly in order that work might be
commenced on June 1, 1929. As a matter of fact, the contractors had tried to
secure a dredge some time before that from the Saint John Dredging Company,
which was unwilling on account of the small quantity of material to be dredged
to undertake the job, and Boone on the very day of the conversation mentioned,
May 7, according to Locke’s own testimony, negotiated with the manager of the
Beacon Dredging Co. of Halifax to do the dredging, and informed him that the
latter had agreed to do the work. It was May 27, however, before the formal
charter was signed, whereby the Dredging Company agreed to send its dredge J.
A. Gregory from Parrsboro, where it was, to the site within a week of that
date with a tug boat and scows with three days’ allowance to make the trip. On
account of repairs which had to be made, this dredge did not arrive at the site
until late in June and it did not make its unsuccessful attempt to do the
dredging until July 2. No complaints were made by Locke or by the Chief
Engineer or anybody else of the delay caused by the dredging company, and after
its failure Locke himself made arrangements for the contractors with the
manager of the Saint John Dry Dock Co. to send the Leconsfield into the
site while on its way to Liverpool, N.S. McKay, the resident engineer’s inspector,
admitted that at the time Locke made the changes in the plan all that could
reasonably be done on the crib had been done by the contractors, and it is
obvious that no progress could be made with the
[Page 464]
actual erection of the crib and pier until the
foundation was prepared.
So far, therefore, as the Chief Engineer’s
notice of September 11 is concerned, although it recites the fact that the time
for performance of the contract had then expired, it conclusively shews that
this was not the reason for the contemplated action. The notice on its face
carries with it an extension of time and commits the Department to the second
preamble as its justification, viz., that the contractors had “made default and
delay in diligently continuing to advance or execute the said works to the
satisfaction of the undersigned.” If this preamble refers to any default or
delay in the execution of the work before the resident engineer changed the
foundation plans, it is clear from what has already been stated that there is
no evidence whatever that there was any default or delay of any kind on the
part of the contractors before that time in diligently continuing to advance or
execute the work to the satisfaction either of the Chief Engineer himself or of
the resident engineer or of any other officer or representative of the
Department. It must accordingly be taken as referring to the delay which took
place afterwards. If there had been any delay of any kind previously it could
only have been in relation to the contractors not having arranged immediately
after being notified of the acceptance of their tender for the procuring of the
timber for the crib and for the hiring of a dredge, notwithstanding that the
dredging for the foundation was not expected by the resident engineer or the
Department itself to be commenced before June 1. These were the only pretended
grounds of previous delay suggested on the trial. If they were real or in any
light fell within the terms of the contract they were clearly condoned, as
clause 55 of the contract shews that any breach or default might be condoned,
though providing that no such condonation shall operate as a waiver of any term
of the contract if it is a breach or default “similar to that for which any
action is taken or power exercised or forfeiture is claimed or enforced against
the Contractor.”
What then are the true facts as to the delay for
which it must be taken, as already intimated, that the Department’s
[Page 465]
action was taken and
the forfeiture of the contractors’ materials, plant and equipment claimed?
The resident engineer finds the original
foundation plans unfeasible, informs the contractors to that effect and that he
is going to change them and substitute a new foundation, furnishes the
contractors and his own inspector with copies of the changed plan, admits that
the substituted plan involved the abandonment of ten feet of the crib the
contractors already had constructed, new work in the rock talus and many other
important items for which no provision was made in the original contract,
telegraphs the contractors on August 28 to start work on the new plans,
notifies his assistant supervising engineer, ignores the contractors’ request
for written confirmation covering the changes in accordance with the terms of
the contract, deliberately waits until the date for completion expires, and
then advises the Chief Engineer to take the work out of their hands. The Chief
Engineer consequently directs the necessary notice to the contractors. The
resident engineer’s report which brought this notice to the contractors was not
produced on the trial for some reason, but the notice to the contractors
brought a letter from them to the Chief Engineer, which advised him of the true
facts and that the contractors were awaiting the written confirmation to which
they were entitled from him before proceeding to construct the new foundation
which Locke had ordered them to do. The Chief Engineer, without acknowledging
this letter or either confirming or repudiating Locke’s order to the contractors
to proceed on the changed plans, sends a copy of it to Locke. The latter
replies on September 23 with a telegram of over 500 words. In his telegram he
states that he instructed the contractors on August 13 to immediately proceed
with the foundation work on the changed plan; that their complaint as to
non-receipt of written confirmation did not bear on subject as his instructions
were given in the presence of three witnesses and that the change was not a
sufficient radical departure to justify their complaint, and then he proceeds
to formulate complaints of previous delays on the part of the contractors in
connection with the procuring of the dredge, alleging, quite contrary to the
evidence adduced on the trial, that the contractors made no move to procure
[Page 466]
a dredge until practically compelled by him to
do so, and that their entire conduct had been unsatisfactory and unprogressive. Not content with this he went on
to bolster up a case against the contractors by stating that he had learned
from outside sources that Mr. Boone did not intend to move “until he received a
letter from me promising much larger prices than he was getting”—a statement
for which no justification whatever is to be found in the record, and concludes
with the statement that he considers the Department fully justified in
completing the work itself and “not trusting contractor who pursues such
dilatory methods with the evident intention of forcing our hand if possible to
receive a larger remuneration for work which he should have completed long ere
this date” and an urgent recommendation “for early action” to this end. Then
follows the final notice of September 25, from the Chief Engineer, taking the
work out of the contractors’ hands without any acknowledgment having been made
of their letter of September 18, though a later note of September 20, referring
to a claim received from the Beacon Dredging Co. for its futile attempt to do
the dredging, was acknowledged on September 24 with the mere statement: “the
contents of which have been noted.”
That the Chief Engineer’s notice of September 11
was, directed to the contractors at the instance of the resident engineer
cannot, in my opinion, be doubted. That the contractors had previously been
advised by the resident engineer of material alterations he had made in the
original plans and definitely ordered by him to proceed with their work under
the altered plans and at the time they received the Chief Engineer’s notice
were awaiting the written confirmation of the resident engineer’s directions,
which they had requested of the latter, is alsо beyond question. That the Chief Engineer’s notice can only be
interpreted as a notice to proceed with the work under the original plans is
self-evident. The learned President of the Exchequer Court so construed it, and
held that, at the time the Chief Engineer gave notice, the original plans and
specifications remained unaltered because of the failure of that official to
approve the changes and instructions, made and given to the contractors by the
resident engineer.
[Page 467]
The result of the whole situation is that we
have the Department terminating the contract and declaring a forfeiture of the
contractor’s materials, plant and equipment because of the Department’s own
failure to approve the resident engineer’s orders in accordance with the terms
of the contract, and refusing to do so upon the representations and advice of
the resident engineer himself, and then immediately proceeding to do the work
itself, not upon the original contract plans and specifications, but upon the
very plans, as altered by the resident engineer, which it had refused to
confirm in writing for the contractors.
This seems to me, not only to constitute harsh
treatment of the contractors and to have placed them in a most awkward position,
as stated by my brother Smith, but to constitute on the part of the Department
itself conduct which cannot be defended or justified under any of the very
onerous and oppressive terms of the contract which the contractors were
required to sign before entering upon their work. It surely ought not to be
permitted to justify its harsh and arbitrary action by putting forward as a
default or delay of the contractors “in diligently continuing to advance or
execute the said works,” a default or delay which is directly attributable to
the Department itself. That the law precludes the Department from doing so is
clearly shewn by Roberts v. Bury Improvement Commissioners, and Lodder v. Slowey. In the
former case Blackburn, J., enunciated this principle in the following words at
p. 136:—
for it is a principle very well established
at common law that no person can take advantage of the non-fulfilment of a
condition the performance of which has been hindered by himself.
Kelly, C.B., in delivering the judgment of
himself and Channell, В., in
the same ease, said:—
In this case we should have been content to
have simply adopted the judgment of my brother Blackburn, in which we in
substance concur, and observing that, inasmuch as it is admitted on the record
that the alleged failure by the plaintiff to use such diligence and to make
such progress as to enable him to complete the work by the day specified, was
caused by the failure of the defendants and their architect to supply plans and
set out the land necessary to enable the plaintiff to commence the work, the
rule of law applies, which exonerates one of two contracting parties from the
performance of a contract when the performance of it is prevented and rendered
impossible by the wrongful act of the other contracting party.
[Page 468]
And again:
Now, in considering this question, we agree
that we are not to assume a jurisdiction which we do not possess, to mitigate
the hardship upon contractors of clauses, however oppressive, which are
sometimes, and indeed most commonly introduced into agreements of this nature;
but we must take care also not to add to their severity, and to the injustice
which they are often the means of inflicting upon a contractor, by imagining
stipulations which are not to be found in the contract, and which the parties
have never entered into or contemplated.
In Lodder v. Slowey, in
delivering the judgment of the Judicial Committee of the Privy Council, Lord
Davey pointed out that the jury had found that the corporation, meaning the
borough council acting by their engineer, prior to the seizure of the works
improperly prevented the respondent from proceeding with the works in the
manner authorized by his contract and also prevented him from proceeding with
the works with sufficient expedition, and said:—
Their Lordships hold that a party to a
contract for execution of works cannot justify the exercise of a power of
re-entry and seizure of the-works in progress when the alleged default or delay
of the contractor has been brought about by the acts or default of the party
himself or his agent
—citing Roberts v. Bury Improvement
Commissioners.
In this case the Chief Engineer and the resident
engineer between them just as effectually held up the contractors as if they
had directed them to suspend all work. One was ordering them to proceed with
the foundation work on a new plan, while refusing to obtain for them the
written confirmation which they demanded and to which they were entitled, and
the other, knowing this fact, was notifying them to proceed on the original
plan, while ignoring their specific request to him for written confirmation of
the resident engineer’s orders to such an extent that he would neither signify
to them his approval or disapproval thereof.
Apart, however, from this feature of the case, I
go further and hold that the Department did not bring itself within the terms
of clause 19 of the contract, under which it pretended to act. I have already
pointed out that the Chief Engineer’s notice committed the Department to the
second preamble as the justification for its action, and did not claim to
exercise the power of re-entry and confiscating the contractors’ property
because of their failure to complete within the contract time, but in point of
fact notified
[Page 469]
them to proceed with the work after the time
fixed for completion had expired. The Department, therefore, was bound to
justify under the following words of that clause:
In case the Contractor shall make default
or delay in commencing, or in diligently executing any of the works or portions
thereof to be performed, or that may be ordered under this contract, to the
satisfaction of the Engineer, the Engineer may give a general notice to the
Contractor requiring him to put an end to such default or delay, and should
such default or delay continue for six days after such notice shall have been
given by the Engineer to the Contractor * * * the Minister * * * may take all
the work out of the Contractor’s hands * * *
On a fair construction of this language it must,
I think, be taken to pre-suppose the existence of some specific, definite
default or delay on the part of the contractors in diligently executing any of
the works or portions thereof to the satisfaction of the Engineer, of which
complaint has been made to them; otherwise what effect can be given to the
words of the notice “to put an end to such default or delay”? If by “the
Engineer” is meant, as is contended, the Chief Engineer, he certainly had never
apprized the contractors of any dissatisfaction on his part with the progress
of the work in any manner or form, and there is no evidence of any complaint
having been made by the resident engineer or any of his representatives other
than that already pointed out of any default or delay prior to the time when
the resident engineer recognized the un-feasibility of the provision in the
original specifications requiring that the footing for the pier be excavated to
the rock by means of a dredge. The words of clause 19, under which the
Department purported to act, clearly contemplate that the contractor shall be
made aware of the default or delay with which the Engineer is dissatisfied.
Otherwise how could the contractor reasonably be expected to put an end to such
default or delay within six days? The clause is a confiscatory clause and as
such should be strictly construed against the party seeking to enforce its
provisions. It was incumbent on the Department, in order to justify under it,
to prove by a preponderance of testimony that the contractors were guilty of
some default or delay in diligently executing some part of the contract work to
the satisfaction of the Engineer, the intention of the clause, of course, being
that the Engineer in the exercise of his judgment should act justly and
reasonably. The undisputed and indisputable facts al-
[Page 470]
ready pointed out not only fail, in my opinion,
to discharge that onus, but absolutely negative the claim that the Department
was justified in taking the contract work out of the contractors’ hands and
confiscating their material, plant and equipment.
Notwithstanding the one-sided character of the
contract and the limitation prescribed in clause 37 of the specifications as to
the power of the Department’s supervising District Engineer in respect of it, I
can find nothing in that clause or in any other clause of the contract or the
specifications from beginning to end, by which it is provided that the action
of the District Engineer or any other representative of the Chief Engineer or
of the Department may not be relied upon by the contractors as an excuse for
any default or delay which may be charged against them in the execution of the
contract work, even though such action may not be approved in writing by the
Chief Engineer. The question to be decided here is not whether the contractors
are to receive compensation for work ordered by the District Engineer, without
the written authority of the Chief Engineer, but whether they are to be
debarred from claiming for the work which they performed under the original
contract and specifications because they declined to proceed with their work on
the foundation on the orders of the District Engineer under plans delivered to
them which constituted a radical departure from their contract without the
changed plans and the resident engineer’s order to execute these changes first
being approved in writing by the Chief Engineer in accordance with the terms of
the contract. That the Department entrusted the whole supervision of the work
to the District Engineer cannot be disputed, and I am not at all sure that,
apart from the limitation prescribed in clause 37 of the specifications, the
words “the Engineer” used in many other clauses of the contract should not be
construed as the District Engineer. The definition of the term “Engineer”
provides that it “shall extend to and include any of the officers or employees
of the Department of Public Works acting under the instructions of the Chief
Engineer or Chief Architect,” while the introductory words of the interpretation clause provide that it is
only where the context does not otherwise require,
[Page 471]
that the definitions stated shall apply. It is a
matter of common knowledge that the Chief Engineer himself does not personally
witness the progress of any of these works, and that he necessarily relies
entirely on the reports of the supervising district engineers throughout the
country, and moreover, that these District Engineers are permanent and highly
responsible representatives and agents of the Department in the supervision and
direction of the execution of all such works. Indeed in the case at bar the
evidence indicates that Locke’s was really the controlling mind from the very
inception to the termination of this contract. The original plan of August 7,
1928, bears his signature as having been checked by him as Supervising Resident
Engineer. It was he who notified the contractors by telegram on September 1,
1928, that he had been advised directly by the Minister of the passage of the
order in council accepting their tender, and of his anxiety to have the work
commenced at the earliest possible date, as the Minister wished to make
“important announcement in address Clarks Harbour his constituency Monday
matter urgent.” It is true that he denied on the trial that this message was
dictated by his desire for political reasons to get something which could be
seen on the ground, even before the contract was signed, but the message none
the less shews to what an extent the Department relied upon him as its
representative in the district, and the facts as above outlined as to what
occurred in connection with the creosoting of the timber, the dredging, the
changing of the plans, the giving of the notice terminating the contract, the
appropriation by the Department of the contractors’ materials, plant and equipment,
its immediate approval after the termination of the contract of his change in
the plan, and the prosecution of the work by the Department under the changed
plan and under his supervision and direction, are, in my opinion, conclusive as
to his being, not only a recognized representative and agent of the Department,
but, as I have already said, the real controlling spirit in all that pertained
to this contract and its execution from beginning to end.
As to the objection which was raised on the
trial regarding the non-joinder of Voye as a suppliant, I am
[Page 472]
inclined to think, having regard to the terms of
the partnership agreement between Boone and Voye whereby Boone was to supply
without charge all plant, tools and equipment which he owned as well as all
necessary funds for the completion of this and the two other contracts to which
the partnership agreement was confined and that all moneys received by the
partnership in respect of the three contracts were to be deposited in the name
of Boone and that Voye’s interest in the partnership was limited to his right
to share only in the profits of the three contracts after payment of all moneys
properly payable by the partnership, that Boone had a right to bring his
petition in his own name. See Atkinson v. Laing.
Whether I am justified in this view or not, it is clear that the mere failure
to join Voye in the petition could have made no difference in the attitude of
the Attorney General in granting his fiat and that the respondent was in no way
prejudiced by such non-joinder on the trial of the cause. If, therefore, there
should be any doubt upon this question of non-joinder, I have no doubt as to
the right of the Exchequer Court to allow an amendment joining Voye in order
that the petition should not be defeated upon that ground. The learned
President of the Exchequer Court in his judgment expressed the same view,
though, as he stated, not without some doubt, and granted leave to add Voye as
a suppliant upon the condition that Boone indemnify Voye, if the latter so
required, against any costs to which he might be subjected thereby. Apparently
this suggestion was not accepted on the trial.
In my opinion this appeal should be allowed, the
judgment of the Exchequer Court should be set aside and the case sent back to
the said Court for the assessment of damages, with the reservation of the right
of the suppliant, if deemed advisable, to join Voye in the petition.
I would therefore allow the appeal with costs
and remit the case to the Exchequer Court for the purpose and with the
reservation stated.
[Page 473]
Smith J.—The appellant, having been the successful
tenderer for the contract of Ice Pier No. 5 at Barrington
Passage, Shelburne County, Nova Scotia, entered into a
contract for its construction with the Department of Public Works.
The plan and specifications of the work, upon
which the appellant tendered, required that the pier should be founded upon bed
rock, necessitating the removal of an accumulated mass of what was called
“sand, gravel and boulders,” amounting to 975 cubic yards. The specification
provides that the footing for the crib must be excavated by means of a dredge
to the rock, and cleared off by a diver. A crib of the size of the proposed
pier was to be built of 10˝ by 10˝ square creosoted timber, to be
placed on the prepared foundation.
The contract was signed on 22nd September, 1928,
and provided that the work was to be completed by 1st September, 1929.
The first question that arose was as to the
timber. The appellant says that this timber could not be procured anywhere in a
seasoned condition, and had to be cut from the woods, that the creosoting plant
selected by the Department Engineer, pursuant to the terms of the contract,
required that the timber should be seasoned for four months, and that this
seasoning does not take place in winter, but commences about the 1st of April,
so that the creosoting could not be commenced until the 1st of August, 1929.
The appellant knew, or ought to have known, all about this at the time of
entering into the contract.
The Resident Engineer, Mr. Locke, says that in
his opinion seasoned timber could have been had, but at greater expense. This
difficulty, however, has little bearing on the question, because it was
surmounted by Mr. Locke persuading the creosoting plant that the seasoning
referred to was not necessary, and the timber was on the site in time.
The real difficulty was in connection with the
dredging. Mr. Locke says that the time he would expect Mr. Boone to do the
dredging in this case would be from the middle of May to the first of June, and
that he would not dredge any considerable time before being in a position to
put the crib down. The reason for this, as I gather from the
[Page 474]
evidence, is that if the dredging were done much
in advance of the time the crib could be placed, drift material would be lodged
by the rapid current; and that it was therefore desirable to have the bottom
cleared off and the foundation laid immediately after the completion of the
dredging.
Mr. Locke had, after the appellant’s tender was
accepted, pointed out to him the need of having the work completed within the
stipulated time. On the 7th May, 1929, the appellant was in Mr. Locke’s office
when the question of the creosoting was brought up, and finally disposed of in
the manner I have already
indicated. Mr. Locke made some complaints about delay, and reminded the
appellant that he should make arrangements for a suitable dredge. Mr. Dunfield,
of the Beacon Dredging Company, was present, and negotiations at once took place
for a contract with his company; and he and Mr. Boone, as Mr. Locke says, went
out with the intention of making a contract. A contract was entered into, dated
27th May, for doing the work with the dredge Gregory, which arrived at
the site on the 2nd July, and utterly failed to do any work, owing to the
dangerous current. Arrangements were then made, with the help of Mr. Locke, to
get the dredge Leconsfield to do the work. This was the most powerful
dredge available in the Maritime Provinces. This dredge attempted to do the
work on 2nd August, and also found it impossible, owing to the nature of the
material to be removed.
In the meantime, during the month of July, the
crib had been built up to ten tiers, ready for floating, and all necessary
material was on the ground.
Mr. Locke was notified of the failure of the Leconsfield,
and decided to change the plans by having the material that he had intended
to dredge remain, and by having the foundation built on this material after it
had been properly cleared off.
The appellant went to Mr. Locke’s office on the
13th August, when the latter told the appellant he did not think it feasible to
have the dredging done, because to do this it would be necessary to bring a
drill for the purpose of boring and blasting, and that he was substituting a
change in the plan, and handed to the appellant a plan
[Page 475]
on which the proposed change was indicated. A
discussion took place as to what this change involved in the way of extra
expense, Mr. Locke contending that it would increase the cost by $600, and the
appellant contending that the increase would be $10,000. The latter asked for
written instructions to proceed on the changed plan, which were not given, and
on 28th August Locke telegraphed the appellant as follows:
Kindly start bag concrete foundation for
pier Barrington Passage Allison
advises by wire to notify your representative at Barrington
to this effect.
On the 29th August the appellant replied to this
telegram, stating that in his opinion this change called for work quite outside
the terms of the contract, that it was an entire change and a modification of
the contract as to price and as to time for completion, and asking to have
instructions concerning the proposed changes made in writing before commencing the
work.
No further instructions were given, and Mr.
Locke says he waited for the 1st September, when the time for completion of the
work under the contract elapsed, and then recommended to the Chief Engineer
that the work should be taken over by the Department, pursuant to the terms of
the contract, owing to the delay. This recommendation does not appear to be
printed in the records, but in pursuance of it the Chief Engineer of the
Department wrote to the appellant reciting in part the terms of the contract,
and stating that there was default and delay in diligently continuing to
advance or execute the said works, and finally notifying the appellant that if
within six days satisfactory progress was not made, the Minister intended to
avail himself of the provisions of clause 19 of the contract and take the works
out of the appellant’s hands and complete them.
This brought a reply from the appellant, dated
18th September, in which he refers to the failure of the dredges, the change of
plan made by Mr. Locke, his request for written instructions for such change,
as required by the contract, and the failure to receive same; and promising,
upon receipt of such instructions, to proceed with the work as expeditiously as
possible.
On the 23rd September Mr. Locke sent a long
telegram to the Chief Engineer, in which he stated that the appellant
[Page 476]
was instructed on August 13 to proceed with
leveling the present foundation, as the material could not be moved by either
dredge. He complains of the delay in obtaining the dredges, and says he was
told from outside sources that the appellant did not intend to move until he
received a letter promising larger prices; complains of delays and
unsatisfactory actions of Boone in connection with the work; and concludes by
saying that he considers the Department fully justified in completing the work
itself rather than trust to the contractor, who pursues dilatory methods, with
the evident intention of obtaining a larger remuneration for the work.
The result was that on the 25th September the
Chief Engineer notified the appellant that it had been decided to take the
works out of his hands pursuant to clause 19 of the contract, and that
therefore the materials, tools, equipment, etc., had become the property of the
Department.
The work was accordingly taken out of the hands
of the appellant, and the Department proceeded to do the work by day labour,
and has spent so far, apparently, $27,000, the original estimate by the
Department being $17,000, and the contract price $18,190. The work was
apparently still incomplete at the commencement of these proceedings in 1932.
It appears to me that the appellant has been
somewhat harshly treated. In the first place, the Departmental engineers had
come to the conclusion that the sand and boulders to be removed in order to
place the foundation of the pier on solid rock could be removed by dredges
without drilling and blasting. It was not contemplated that any drilling outfit
would be required, as Mr. Locke himself helped to arrange for the two dredges
that attempted to do the work. On the failure of these dredges, he told the
appellant that the dredging was not feasible, and it is therefore quite idle to
talk of the possibility of doing this work by drilling and blasting.
The specifications provided that the excavation
was to be done by means of a dredge, and there is no suggestion of blasting the
material. There was, no doubt, some delay on the part of the appellant in
getting the first dredge on the scene, but this was by reason of the appellant
[Page 477]
having been informed by the creosoting company
that they would require the timber to be seasoned for four months, so that the
crib, according to this, could not be ready to place on the foundation before
1st August. It is admitted that the dredging should be done so that this could
be followed up at once by laying the foundation and placing the crib.
The creosoting difficulty being surmounted, by
the intervention of Mr. Locke, as already stated, the dredging was arranged
for, and would have been completed in June in time for the placing of the crib,
had it not turned out that the dredge was unable to do the work, by reason of
the unexpected nature of the material to be removed. This unforeseen occurrence
involved the delay that occurred in getting the other dredge, and it was quite
unexpected that that powerful dredge would also fail. From these failures, Mr.
Locke decided that it was not feasible to do the dredging at all, and altered
the plan.
Under the terms of the contract, the appellant
was perfectly right in requiring written instructions before proceeding upon
this altered plan, and, while he received instructions from Mr. Locke by
telegram to proceed, these instructions were altogether insufficient because,
as admitted, Mr. Locke had no authority to give the required instructions, and
he absolutely refused to give them. He never advised the Chief Engineer of the
change of plan that he proposed. Instead of doing this, he deliberately, as he
says, waited for the expiration of the time limit, and then advised the Chief
Engineer to take over the work.
The appellant, on being shown the changed plan,
took the attitude already referred to as to extra cost and the effect on prices
and time limitation. Mr Locke, no doubt because of this attitude, considered it
necessary to be careful not to give any written instructions that would involve
such a result. He was quite right in not giving any such instructions in
writing himself, as he had no authority. He no doubt went beyond his authority
in changing the plan and telegraphing to the contractor to proceed upon that
changed plan, because the Chief Engineer alone had authority to do all this.
The result was that the contractor was placed in a most awkward position. He
was asked by
[Page 478]
the Resident Engineer to proceed with the work
on the changed plan, and at the same time was refused the necessary written
instructions that would enable him to do so with safety under the terms of the
contract.
The Chief Engineer, without any notice of this
situation, was recommended to take possession of the work because of delay,
and, acting upon this recommendation, notified the contractor to proceed with
the work within six days, without informing him upon which plan he was to
proceed.
The first intimation that the Chief Engineer
seems to have received as to the actual circumstances was from the letter of
the appellant of the 18th September, which was in fact an accurate
representation of the real circumstances, but which was counteracted largely by
the telegram of Mr. Locke of the 23rd September, in which he tells of the
delays and insincerity and lack of real effort upon the part of the contractor,
founded in large part upon what he had been told from outside sources as to the
appellant’s intentions in order to secure larger remuneration.
When Mr. Locke found, on the 2nd August, by the
failure of the large dredge that dredging was impracticable, and resolved to
change the plan, his proper course was so to inform the Chief Engineer and
request his approval and written instructions to the contractor to proceed on
the changed plan. This he knew to be a necessity under the terms of the
contract. Instead, he altered the plan and asked the appellant to proceed on
his own authority, and thus wasted the precious time from 2nd August until 1st
September. If he had followed the proper course that I have pointed out, the
work would probably have been completed, not on 1st September, but probably
later that fall.
There was actually little delay that counted on
the part of the appellant except what was caused by the miscalculation that it
was practicable to do the dredging in the manner attempted. This was a
miscalculation of the engineers that was relied on by the contractor, though he
was not warranted in doing so by the terms of the contract.
If, immediately after the 2nd August, the Chief
Engineer had received from Mr. Locke the information and request mentioned
above, it is very improbable that he
[Page 479]
would have failed to act accordingly. The time
for completion was allowed to expire, and then Mr. Locke recommended that the
work be taken out of the appellant’s hands, but on what precise representations
does not appear. The result was, the letter from the Chief Engineer to proceed
with the work within six days, which, by the lack of written instructions to
the contrary, could mean only a request to proceed on the original plan, which
the engineers had determined to abandon as impracticable, and which they did in
fact abandon when they took over the work. The appellant was then in the
position of having been furnished a changed plan, with a telegram from the
Resident Engineer to proceed on that plan, and then a formal notification from
the Chief Engineer to proceed, without any intimation as to the plan that he
was to proceed with.
I think that it is quite clear that the Chief
Engineer had decided to change the plan as Mr. Locke intended. The contractor
was quite right in insisting upon the approval of the Chief Engineer in writing
before proceeding further. The Chief Engineer does not say in his notice
anything about it, but he clearly contemplated a change of plan because, after
the notice, he proceeded on the changed plan and carried on the work according
to it.
No doubt the contractor made some complaint
about the change, but all that was provided for in the contract; and the final
claim that he made was that he had a right to have the changes made by the
Chief Engineer in writing. He never got these changes approved in writing by
the Chief Engineer, and he was never in default as to these changes, and there
was never any intention on the part of Mr. Locke or the Chief Engineer of
resorting to the original plan.
I would allow the appeal
with costs, and would send the case back to the Exchequer Court for the
assessment of damages in the manner set out by Mr. Justice Crocket.
Lamont J. (dissenting).—The material facts in this appeal and the relevant
clauses of the contract entered into between the appellant (hereinafter called
the “ Contractor”), and His Majesty the King, represented by the Minister of
Public Works, are set out in the judgment of my brother Hughes.
[Page 480]
The contract, which was dated September 22,
1928, was for the construction of Ice Pier No. 5 at Barrington
Passage, Shelburne County, N.S., according to the plans
and specifications attached to the contract. The work was to be completed by
September 1, 1929, and time was made of the essence of the contract.
The contract called for a crib built pier of a
certain size and shape placed upon a level foundation. This foundation was to
be secured by excavating the bottom to bed rock, a distance of some ten feet,
by means of a dredge, clearing it off by a diver and then levelling it up with
bags of cement. Clause 56 of the contract provided that it was made and entered
into on the distinct understanding that the Contractor had, before execution,
investigated and satisfied himself of everything and of every condition
affecting the work to be executed, and the labour and material to be provided
and that
the execution of this contract by the
Contractor is founded and based upon his own examination, knowledge,
information and judgment, and not upon any statement, representation, or
information * * * derived from any * * * tests, specifications, plans * * *
furnished by His Majesty or any of His officers, employees or agents.
The tender of the Contractor contained the
following:—
(We) hereby certify that (we) have visited
and examined the site of the proposed work, or have caused it to be visited and
examined by a competent person on (our) behalf.
This certificate was not true. The Contractor,
Boone, some years before, had gone through Barrington Passage in a boat, but the water where the pier was to be
constructed was twenty-five feet deep, and he admits that he could not see the
bottom. The bottom, according to a plan attached to the specifications, was
shewn to consist of large and small boulders, gravel and sand, with the
boulders covering the entire surface of the bottom. The contract further
provided that if the Contractor should make default or delay in commencing or
in diligently prosecuting the work, the Minister of Public Works, act for His
Majesty, might take the work out of the Contractor’s hands and complete it
himself.
On September 1, 1929, when the pier should have been
completed, little work had been done beyond the building on shore of the frame
work of the crib, the accumulation of materials for the construction of the
pier, the blasting of a number of boulders on the bottom by a diver so that
[Page 481]
the dredge would be able to operate, and the
dredging of one hundred and twelve of the estimated nine hundred and
seventy-five cubic yards. This one hundred and twelve cubic yards was dredged
out on August 3, and was the only dredging which was done. In September the
Minister took the work out of the Contractor’s hands, and took over the
materials he had on hand, and used his plant, equipment and tools for
completing the work. After the work was taken out of his hands, the Contractor
brought this action against His Majesty, claiming some $13,000 damages for
being deprived, by the Minister, without just cause, of an opportunity to
complete the contract. He alleged that if the work was delayed, the delay was
due to a change in the plans made by the District Engineer, one Locke, and his
refusal or neglect to give instructions to proceed with the work, according to
the substituted plan, to which instructions he claimed to be entitled under the
contract.
That there was an unreasonable delay on the part
of the Contractor in engaging dredges to excavate the foundation is, I think,
established beyond question. The evidence shews that to complete the pier would
require in the neighbourhood of four months’ work after the dredging had been
done. Although the attention of the Contractor had been called by Locke during
the fall of 1928 to the necessity of arranging for the dredge to start work
early in May, 1929, the Contractor did not get his first dredge on the job
until July 2. This dredge—the Gregory —did not attempt to do any excavating.
When it arrived it found the current so strong that the crew were afraid to
operate, so it turned and went away. No further attempt at dredging was made
until August 2, when the Leconsfield, a large bucket dredge, was
procured and commenced dredging. It took out one hundred and twelve yards when
it quit. The reason for quiting, so far as the evidence discloses, was that the
surface of the bottom was covered with large boulders which, owing to their
weight and size, were doing damage to the buckets. No further attempt was made
to secure a suitable dredge, but the Contractor reported to Locke, through one
Allison, who was an engineer in Locke’s office, that the dredging part of the
contract was impossible of performance. Locke,
[Page 482]
being anxious to get on with the pier, said he
would see if he could make a change by which something else could be
substituted for the dredging. On August 13 the Contractor came to Locke’s
office and Locke shewed him a plan of the work with changes on it marked in red
ink. The suggested changes were that the dredging should be eliminated and that
a level foundation upon which the pier could rest should be secured by
levelling the bottom with bags of concrete, to the top of the boulders, and
placing around this a talus, constructed also of bags of concrete. The
Contractor and Locke had some discussion as to the cost of the suggested
changes. Locke thought that the work, according to the plan as he had altered
it, would cost about $600 more than the original work; the Contractor thought
it would cost about $10,000 more, and that he should be given written
instructions to proceed with the suggested alterations, as it entirely changed
the contract, and he asked for written instructions. Locke told him to go down
and start the work and he would get his instructions. The Contractor went away
but he did not start the work. On August 24, Allison, who was making a tour of
inspection, called at Barrington Passage and reported to Locke in these words:—
Mr. Boone on the work and states he is
waiting final instructions under a new scheme of foundation.
On August 28, Locke telegraphed the Contractor
as follows:—
Kindly start bag concrete foundation for
pier Barrington Passage Allison
advises by wire to notify your representative at Barrington
to this effect.
On the following day the Contractor wrote to
Locke as follows:—
I received your wire yesterday re proposed
changes in foundation. While I am willing and most anxious to do the work just
as you wish it done, I wish to point out that in my opinion this change calls
for work quite outside the provisions of the contract.
By the terms of the contract it is provided
that the footing of the crib must be excavated by means of a dredge to the
rock. We had the largest and most powerful dredge available undertake to do
this excavation, and it was found impossible to excavate because the material
was such that a dredge could not remove it.
The change now proposed is to meet the
situation arising from the impossibility of using a dredge. I claim that this
makes an entire change and a modification of the contract as to price and as to
time for completion of the work should be made with us as a result.
We have also been put to large expense in
connection with the attempt made to operate the dredge which under the
circumstances ought to be paid by the Department.
[Page 483]
As already requested I would like to have the instructions concerning the proposed
changes made in writing before commencing the work.
On September 11, the Chief Engineer, as required
by the contract, gave the Contractor six days’ notice to put an end to his
default and delay and to make satisfactory progress, within that time,
otherwise the work would be taken out of his hands. Nothing was done, so the
Minister took the work away from the Contractor.
The position taken by the Contractor was that
the alterations made an entire change in the character of the work to be done,
and that the alterations should all be considered as work outside of the
contract. The object of this is, I think, apparent: The Contractor, in his
letter of August 29, said that he had been put to a large expense in connection
with the attempt to operate the dredges for which he desired the Department to
pay. He would only be entitled to this if the necessity for the alterations
could be attributed to the fault of the Department. This he attempted to prove
by claiming that the work as called for in the specifications was impossible of
performance. In my opinion the Contractor is not entitled to succeed on that footing:
first, because the Department has sufficiently protected His Majesty from an
action of this nature by clause 56, above referred to, and clause 45, which
negatives all implied covenants or agreements; and, secondly, because it is not
established that the dredging was impossible of performance. The Leconsfield
was able to take out one hundred and twelve cubic yards because a diver had
been sent down to blast out a number of boulders so that the dredge could take
hold. From the evidence I am satisfied that the rest of the surface could have
been dealt with in the same way. No doubt blasting the surface with dynamite
would have been expensive, but the Contractor had agreed to do the dredging.
Furthermore there is evidence that this dredging could have been done by means
of a dipper dredge.
The position taken by the Contractor raises the
very important question of Locke’s authority to alter the nature of the work to
be done. Locke, as I gather from his evidence and communications, held the view
that, as all the work was being paid for at unit prices, the alterations
suggested were matters of detail and came within what
[Page 484]
was described as “small things necessary to
secure good work,” which he had authority to make without referring the matter
to the Chief Engineer, and did not come within the clause requiring written
instructions to be given. The trial judge, however, held that the alterations
made by Locke were decided variations in the plans and not something of a mere
trifling nature, and with that view I agree.
The contract provides that the Engineer may, in
writing, order any additional work not covered by the contract to be performed
by the Contractor, but it also provides that, as a condition precedent to being
paid for such extra work, the Contractor must obtain and produce the order of
the Engineer in writing and shew that the work ordered had been done.
In the contract “Engineer” is defined as meaning
the “Chief Engineer” for the time being having control over the work, and
extends to and includes any of the officers or employees of the Department of
Public Works acting under the instructions of the Chief Engineer, but all
instructions, or directions, or certificates given, or decisions made by anyone
acting for the Chief Engineer, shall be subject to the approval of the Chief
Engineer. In the specifications which were made a part of the contract, clause
37, in part, reads:—
37. Power
of the District Engineer.—The District Engineer will have no power to
order extra work or changes which will entail an increase or decrease in cost
without referring the matter to the Chief Engineer, and being authorized by him
to order such changes. The Contractor will have no claims for compensation if
such changes, though ordered by the District Engineer, have not been
authorized, in writing, by the Chief Engineer. * * *
Under those provisions the onus, in my opinion,
was upon the Contractor to establish that, notwithstanding clause 37, Locke had
express instructions to make the alterations which he in fact did make, or that
the Chief Engineer had approved of the same. This onus the Contractor did not
discharge. So far as the evidence discloses, the Chief Engineer had no
knowledge that any alterations had been made or suggested until after the date
on which the contract was to be completed, nor did he authorize the same. The
Contractor, whose duty it was to obtain and produce an order, in writing, from
the Chief Engineer, did not communicate with him at all in respect of the same,
until after he received the Engineer’s
[Page 485]
notice, which lends some plausibility to the
opinion expressed by Locke, in his testimony, that the Contractor found himself
with a disadvantageous contract on his hands and was looking for a way to get
rid of it. Locke, in my opinion, went beyond his authority when he so
materially altered the character of the work to be done, and the Contractor,
with his contract before him, must be held to have known of his want of
authority to make the alterations, or to give written instructions, without which
the Contractor would not proceed. The trouble in this case arises by reason of
the failure of the Contractor to examine the bottom for himself, as he
certified he had done. He should have known, before he put in his tender,
whether or not the current was too strong for the small dredge he first
employed, and he also should have known whether a bucket dredge was sufficient
to remove the boulders which were indicated as being on the surface of the bed.
As I see it, the real question in
this appeal is, whether His Majesty can be mulcted in damages for alterations
made by an official who had no authority to make them? The answer to this
question must be in the negative.
The appeal should be dismissed with costs, and
the judgment of the Exchequer Court affirmed, but with the variation suggested
by my brother Hughes.
Hughes J. (dissenting).—This is an appeal by the suppliant from a judgment of
the learned President of the Exchequer Court of Canada dated the 6th day of
December, 1932, whereby it was held that the suppliant was not entitled to the
relief sought in a Petition of Right, in which the suppliant claimed damages
from the Crown in respect of a contract for the construction of an ice pier at Barrington Passage, Nova Scotia. The
contract provided for the completion of the work on or before September 1,
1929. On September 25, 1929, the Crown notified the contractor that it had been
decided to take over the work in pursuance of clause 19 of the contract, and
this was done.
The following contentions were presented to this
Court by the appellant:—
1. That there was no default on the part of the
contractors.
[Page 486]
2. That there was no order of the Minister of
Public Works declaring the forfeiture.
3. That there was no justification for the
forfeiture of the appellant’s contract, goods and deposit.
4. That the respondent did not apply the
appellant’s goods and use the appellant’s plant to complete the works mentioned
in the contract, but for a new work substituted for the work called for under
the contract and for other purposes.
The contract was between the appellant and one
Alexander R. Voye, of the first part, and His Majesty the King, represented by
the Minister of Public Works, of the second part, and was dated the 22nd day of
September, 1928. Attached to the contract and made a part of it were
specifications and a plan.
Borings, at and about the site of the pier
proposed in the contract, had been made by the Department of Public Works in
the year 1923. The plan attached to the contract was not lacking in information
as to borings or the condition of the bottom, as it shewed a section on the
line of the proposed ice piers, details of borings and materials above the
surface of the rock, including information that large and small boulders
covered the bottom. The contractors had examined the plan before tendering and
had seen the references to the borings and to the condition of the bottom. They
had also examined the specifications. The contractors, in their tender of
August 25, 1928, certified that they had seen and examined the site of the
proposed work or had caused it to be visited and examined by a competent person
on their behalf, although, as a fact, they had not examined it or had it
examined. The appellant had merely seen the site some time previously.
The contractors tendered for the total price of
$18,190 as per the following unit prices:—
Dredging,
975 c.у. at $3 . . . . . . .
. . . . . . . . . . . . $ 2,925
Bag
concrete, 66 c.у. at $24 . .
. . . . . . . . . . . . . . 1,584
Crib
work, 14,500 cf. at 65 . . . . . .
. . . . . . . . . . . 9,425
Concrete top, 133 c.у. at $32. . . . . . . . . . . . . . . 4,256
$18,190
[Page 487]
On August 30, 1928, an Order in Council was
passed accepting the above tender but the contract was not signed until
September 22, 1928.
The crib was to be constructed of creosoted
hardwood timber. Even before the contract was signed the District Engineer at
Halifax, Thomas J. Locke, was asking the appellant about the timber and told
the appellant that he, Thomas J. Locke, would like to get it to Barrington Passage that fall. The appellant
told the District Engineer that it was impossible to get the timber to the
creosoting plant for treatment that fall. The District Engineer thought the
timber could be procured, and, as the appellant put it, was harping to get the
timber down. The appellant testified, however, that he could not get the timber
that fall, although he tried to do so. The contractors finally procured the
timber and framed it and sent it to the creosoting plant about April 1, 1929.
The appellant testified that there it had to be piled and stacked for seasoning
purposes for at least four months before creosoting could be properly done. It
must, therefore, have been fairly clear to the appellant before the contract
was signed that the contractors could scarcely complete the work on or before
September 1, 1929. On May 7, 1929, the District Engineer and the appellant had
a conference and, on May 8, 1929, the District Engineer wrote the appellant
that he would have the timber creosoted at the earliest possible moment, and
emphasized the importance of procuring a suitable dredge for the purpose of
having the foundation excavated and work commenced by June 1, 1929. As a result
the timber had six weeks’ treatment and was then delivered to Barrington Passage. The contractors then
began to build the crib and ran it up ten courses, which was as high as it
could usefully be built on land.
On May 27, 1929, the contractors entered into an
agreement in writing whereby they hired the dredge J. A. Gregory, two
dump scows and a steam tug to do the dredging. This dredge was a 1½ yards, orange peel, bucket dredge. It proceeded to Barrington Passage and pulled over the site
on July 3, 1929, but could do nothing because of the swift running of the tides
and gave up. The contractors then procured the dredge Leconsfield which
arrived at Barrington Passage
on July 27, 1929. The Leconsfield
[Page 488]
was a powerful dredge but it also was a bucket
dredge, which, according to the appellant, was the only kind procurable. This
dredge took out 68 yards of material and then the superintendent gave up as the
buckets were being torn to pieces.
The appellant, on August 3, 1929, went to
Halifax and saw the District Engineer. The appellant testified that they looked
over the plans and the District Engineer said that he would make changes.
It is important at this stage to mention some of
the provisions of the specifications and contract.
“Engineer” is defined in the specifications as
the Chief Engineer of the Department of Public Works of Canada.
Clauses 14 and 15 of the General Conditions are
as follows:—
14. Alterations.—The
Engineer shall have the power and right to make from time to time and at any
time, additions to or deductions from the dimensions shown on the drawings or
specified herein and ta add to, omit, change, modify, cancel or alter the works
and materials herein specified, or shown on the drawings, without rendering
void or in any way vitiating the contract. The value or cost of such additions,
deductions, omissions, modifications, or alterations, shall be determined in
accordance with the rates or prices stated in the tender which prices are
assumed, and will be taken to cover the cost of materials and workmanship
measured in the works, or as specified herein, and to include the cost and
expense of all plant, labour, machinery, tools, temporary works, cartages,
freight, patterns, moulds, superintendence and profit; but the Contractor is
not to make any change or alteration in the works or in the dimensions and
character of the materials to be used without the consent and permission, in
writing, of the Engineer. In case such permission is not obtained, unless the
Contractor can show good and sufficient reason for his action, payment for such
works will be refused.
15.
Meaning of Terms, Etc.—Alterations, deductions,
omissions, modifications or deviation are to be understood as applying to
decided variations in the plans or designs, such as a decrease in width, an
increase in depth, the substitution of one class of material for another, the
addition of works neither shown nor described, etc., and for these or similar
matters alone, will ‘ any sum be allowed to the Contractor or deducted from the
contract, and then only upon the written orders of the Engineer. All other
alterations, etc., consequent upon a better disposal of materials an improved
mode of construction adopted, repairs required, and such like, as long as the
costliness of the materials, workmanship, etc., are of a trifling nature, which
shall be, judged of by the Engineer, shall be deemed to be included in the
contract, and for such no extra sum or amount will, under any consideration be
allowed to the Contractor.
Clause 32 of the General Conditions is as
follows:—
32. Claims.—No claims for extras will be entertained by the Department on
account of unforeseen difficulties in the carrying out of the works herein
specified.
[Page 489]
Clause 37 of the General Conditions is as
follows:—
37. Power
of the District Engineer.—The District Engineer will have no power to
order extra work or changes which will entail an increase or decrease in cost
without referring the matter to the Chief Engineer, and being authorized by him
to order such changes. The Contractor will have no claims for compensation if
such changes, though ordered by the District Engineer, have not been
authorized, in writing, by the Chief Engineer. The District Engineer will see
that the work is carried out exactly in accordance with the plans and
specification, and in matters of detail, or small changes necessary to secure
good work, where the question of extra cost cannot come into consideration, he
must use his best judgment in the interpretation of the specification, and must
conduct the work and carry out the plans with the idea that the best results
are to be obtained and the Contractor must abide by the decision.
He shall give clear and detailed
instructions in writing to all Inspectors, who will have no power to allow or
make any changes in the work.
It will not be his duty to take the
responsibility of advising the Contractor as to the way or best method of
conducting his operations, and the Contractor must have his own Engineer in
this connection. However, if in his opinion, the methods employed by the
Contractor are such that the progress of the work is not satisfactory, or that
they may lead to bad results, it will be his duty to warn the Contractor to
change these methods, and force him to take such steps as will ensure the
completion of the works in strict accordance with the plans and specification.
The provision of the contract defining “Engineer”
and his duties is as follows:—
“Engineer” shall mean the Chief Engineer or
Chief Architect, as the case may be, of the Department of Public Works of
Canada, for the time being having control over the work, and shall extend to
and include any of the officers or employees of the Department of Public Works,
acting under the instructions of the Chief Engineer or Chief Architect, and all
instructions or directions, or certificates given, or decisions made by any one
acting for the Chief Engineer or Chief Architect, shall be subject to the
approval of the Chief Engineer, or the Chief Architect, tand
may be cancelled, altered, modified and changed as to
the Chief Engineer or Chief Architect may see fit: Provided always and it is
hereby understood and agreed that any act on the part of the Chief Engineer or
the Chief Architect in connection with and in virtue of the present contract,
and any instructions or directions or certificates given, or decisions made by
the said Chief Engineer or the Chief Architect, or by any one acting for such
Chief Engineer or the Chief Architect shall be subject to the approval of or
modification or cancellation by the Minister of Public Works of Canada.
Clause 7 of the contract is as follows:—
7. The Engineer may, in writing, at any
time before the final acceptance of the works, order any additional work, or
materials or things, not covered by the contract, to be done or provided, or
the whole or any portion of the works to be dispensed with, or any changes to
be made which he may deem expedient, in, or in respect of the works hereby
contracted for, or the plans, dimensions, character, quantity, quality,
description, location or position of the works, or any portion or portions
thereof, or in any materials or things connected therewith, or used or intended
[Page 490]
to be used therein, or in any other thing
connected therewith, or used or intended to be used therein, or in any other
thing connected with the works, whether or not the effect of such orders is to
increase or diminish the work to be done or the materials or things to be
provided or the cost of doing or providing the same; and the Engineer may, in
such order, or from time to time as he may see fit, specify the time or times
within which each order shall, in whole or in part, be complied with. The
Contractor shall comply with every such order of the Engineer. The decision of
the Engineer as to whether the compliance with such order increases or
diminishes the work to be done or the materials or things to be provided, or
the cost of doing or providing the same, and as to the amount to be paid or
deducted, as the case may be, in respect thereof, shall be final. As a
condition precedent to the right of the Contractor to payment in respect of any
such order of the Engineer, the Contractor shall obtain and produce the order,
in writing, of the Engineer, and a certificate, in writing, of the Engineer,
showing compliance with such order and fixing the amount to be paid or deducted
in respect thereof.
The appellant saw the District Engineer on
August 13, 1929, and received from the latter a copy of the plan with proposed
amendments shewn in red ink. By these amendments it was proposed to eliminate
the dredging, to take ten feet off the height of the timber portion of the
crib, to level off the bottom with concrete and to build a talus of concrete.
The appellant said that he asked for instructions in writing and for an
extension in time, and he testified at the trial that the District Engineer
said the instructions would follow. At the trial before the learned President
the District Engineer, Thomas J. Locke, testified that on August 13, 1929, he
did tell the appellant that he was substituting a change in the plan, which
would involve a number of extras. He estimated a net difference of $600 in
favour of the contractors, made up of the excess of extras over deductions.
The contractors, however, claimed that there was
an entire change, and asked for a modification of the contract as to price and
time for completion. On August 28, 1929, the District Engineer sent to the
appellant a telegram reading as follows:—
Kindly start bag concrete foundation for
pier Barrington Passage.
Allison advises by wire to notify your representative at Barrington to this effect.
T. J. LOCKE.
Written instructions, however, were not
forthcoming from the Chief Engineer and thus the date for completion came and
went with matters in a deadlock. This was most unfortunate for the contractors.
[Page 491]
I agree with the finding of the learned
President that the District Engineer could not alter the contract and that, in
the absence of written instructions from the Chief Engineer, the contract remained to be executed
according to the original contract, plan and specifications; that the
alterations proposed were such as could be authorized only by the Chief
Engineer, and, as he did not authorize them in writing, they were as
ineffective as if they had never been proposed at all, and, as a consequence,
the contract, plan and specifications remained as they were.
It must have been clear to the contractors that
the power of the District Engineer was restricted by General Condition 37 and
that the District Engineer had no power to order extra work or changes which
would entail an increase or decrease in cost without authorization in writing
by the Chief Engineer. Nor was the difficulty in dredging any answer to the
contention of the respondent that there was default on September 1, 1929. The
appellant was not misled in any way by the respondent before he undertook the
work. Clause 32 of the General Conditions was clear. Even if the dredging was
difficult or impossible without blasting, the contractors would not be excused.
In Thorn v. The Mayor and Commonalty
of London, Lord
Chelmsford said:—
[The builder] before he made his tender,
ought to have informed himself of all the particulars connected with the work,
and especially as to the practicability of executing every part of the work
contained in the specification.
See also Connolly v. The City of Saint
John. It
must be held, therefore, that there was default on September 1, 1929, and that
the first contention of the appellant fails.
It is convenient now to set out clauses 19 and
20 of the contract:—
19. In case the Contractor shall make
default or delay in commencing, or in diligently executing any of the works or
portions thereof to be performed, or that may be ordered under this contract,
to the satisfaction of the Engineer, the Engineer may give a general notice to
the Contractor requiring him to put an end to such default or delay, and should
such default or delay continue for six days after such notice shall have been
given by the Engineer to the Contractor, or should the Contractor make default
in the completion of the works, or any portion thereof, within the time limited
with respect thereto in or under this contract, or should the Contractor become
insolvent, or abandon the work, or
[Page 492]
make an assignment of this contract without
the consent required, or otherwise fail to observe and perform any of the
provisions of this contract, then and in any of such cases, the Minister, for
and on behalf of His Majesty, and without any further authorization, may take
all the work out of the Contractor’s hands and may employ such means as he, on
His Majesty’s behalf, may see fit to complete the works, and in such case the Contractor
shall have no claim for any further payment in respect of work performed, but
shall be chargeable with, and shall remain liable for all loss and damage which
may be suffered by His Majesty by reason of such default or delay, or the
non-completion by the Contractor of the works, and no objection or claim shall
be raised or made by the Contractor by reason, or on account of the ultimate
cost of the works so taken over, for any reason proving greater than, in the
opinion of the Contractor, it should have been; and all materials, articles and
things whatsoever, and all horses, machinery, tools, plant and equipment, and
all rights, proprietary or otherwise, licences, powers, and privileges, whether
relating to or affecting real estate or personal property, acquired, possessed
or provided by the Contractor for the purposes of the work, or by the Engineer
under the provisions of this contract shall remain and be the property of His
Majesty for all purposes incidental to the completion of the works, and may be
used, exercised and enjoyed by His Majesty as fully to all intents and purposes
connected with the works as they might therefor have been used, exercised and
enjoyed by the Contractor; and the Minister may also, at his option, on behalf
of His Majesty, sell or otherwise dispose of, at forced sale prices, or at
public auction or private sale, or otherwise, the whole or any portion or
number of such materials, articles, things, horses, machinery, tools, plant and
equipment at such price or prices as he may see fit, and detain the proceeds of
any such sale or disposition and all other amounts then or thereafter due by
His Majesty to the Contractor on account of, or in part satisfaction of any
loss or damage which His Majesty may sustain or have sustained by reason
aforesaid.
20. Whenever in this contract power or
authority is given to His Majesty, the Minister, the Engineer or any person on
behalf of His Majesty, to take any action consequent upon the insolvency of the
Contractor or upon the acts, defaults, neglects, delays, breaches,
non-observance or non-performance by the Contractor in respect of the works or
any portion or details thereof, such powers or authorities may be exercised
from time to time, and not only in the event of the happening of such contingencies
before the time limited in this contract for the completion of the works, but
also in the event of the same happening after the time so limited in the case
of the Contractor being permitted to further proceed with the execution of the
works.
Provided always that after the expiration
of the time limited for the completion of the works the Minister shall be sole
judge as to what additional time, if any, may be allowed to the Contractor for
such completion, and is decision as to the reasonableness or sufficiency
thereof for the purpose of completion shall be final and binding upon the
Contractor.
On September 11, 1929, the Engineer notified the
Contractor in writing that if within six days satisfactory progress was not
made, the work would be taken over and completed in pursuance of clause 19 of
the contract.
[Page 493]
On September 25, 1929, as apparently the
Contractors had not complied with that notice, the Engineer wrote them and
advised them that it had been decided to take over the work, and that the
materials, tools and equipment would thenceforth be the property of the
Department of Public Works.
At this time Alexander R. Voye wrote the
appellant an informal letter of withdrawal from their partnership.
The respondent then went ahead and constructed a
pier at a cost very considerably in excess of the contract price above
mentioned.
As the Minister was empowered by clause 19, for
and on behalf of His Majesty, to take the works out of the Contractor’s hands
with the consequent forfeiture provided in that clause, it must be assumed that
the forfeiture was the act of the Minister. Moreover the Minister resisted the
claim of the suppliant in the Exchequer Court of Canada and in this Court. It
must, therefore, be held that the second contention of the appellant fails.
The forfeiture of the contract and goods have
just been discussed in connection with clause 19. As there was default on the
part of the Contractors, it must be held that the deposit was forfeited under
clause 54 of the contract, and the third contention of the appellant,
therefore, fails.
The appellant lastly contended that the
respondent did not apply the appellant’s goods, and use the appellant’s plant
to complete the works mentioned in the contract, but for a new work substituted
for the work called for under the contract, and for other purposes.
It may be true that the respondent did not
complete the pier strictly in accordance with the original contract, plan and
specifications. But the respondent did build a pier at the place designated on
the plan, and the General Conditions and contract provided for very wide
latitude in changing the original plan and specifications. See clauses 14 and
15 of the General Conditions, and clauses 7, 8 and 9 of the contract. Clause 8
of the contract is particularly in point. It reads as follows:
All the clauses of this contract shall
apply to any changes, additions, deviations, or additional work, so ordered by
the Engineer, in like manner, and to the same extent as to the works contracted
for.
[Page 494]
J. K. McKay,
a civil engineer, testified before the learned President that the respondent
took over the crib which the appellant had worked upon and launched it upon the
proposed site, and built upon it. There is, moreover, no evidence in the record
that the respondent refused to return to the appellant, before the Petition of
Right was launched, any of the appellant’s goods or any of the appellant’s
plant not used up by the respondent, in accordance with the provisions of the
contract. Clayton v. Le Roy. Moreover, the appellant has not before this Court his partner, or
former partner, Alexander R. Voye. The learned President gave leave to the
appellant to join Alexander R. Voye, if possible, but the appellant has not
taken advantage of that leave. Under the circumstances, however, this judgment
will be without prejudice to any proceedings in proper form which the appellant
may, if so advised, subsequently take against the respondent for the return of,
or damages in respect of, any goods, tools or plant not used up by the
respondent in accordance with the contract and improperly withheld.
With this variation the appeal should be
dismissed with costs.
Appeal allowed with costs.
Solicitor for the appellant: P. J. Hughes.
Solicitor for the respondent: H. A. Carr.