Supreme Court of Canada
Scotia Construction Co. Ltd. v. The City of Halifax,
[1935] S.C.R. 124
Date: 1934-12-12
Scotia Construction
Company, Limited (Plaintiff) Appellant;
and
The City Of Halifax
(Defendant) Respondent.
1934: October 22; 1934: December 12.
Present: Duff C. J. and Cannon, Crocket,
Hughes and Maclean (ad hoc) JJ.
ON APPEAL FROM THE SUPREME COURT OF NOVA
SCOTIA IN BANCO
Courts—Judgments—Jurisdiction—Res judicata —
Arbitration — Appeal—Action for balance due under contract—Dismissal of application
to set aside default judgment and give leave to defend—Appeal dismissed from
refusal to set aside judgment, but reference made under terms of
contract—Reference, and report of findings—Objection to
jurisdiction—Confirmation of report—Appeal therefrom.
Plaintiff (appellant) recovered judgment by
default against respondent City for $14,432.11, the balance due on a
construction contract, which the City had held back as protection against
workmen’s claims threatened
[Page 125]
under a wage clause in the contract. An
application by the City to open up the judgment was dismissed and the City
appealed. The Supreme Court of Nova Scotia in banco dismissed its appeal
but, the contract having, by agreement, been laid before it, and its attention
called to the fact that certain workmen had begun an action against the City on
the basis of the said wage clause, it ordered a stay of execution as to $5,000,
discontinuance of the workmen’s action, and arbitration of the workmen’s claims
before the City Engineer (as referee named in the contract). Before the
Engineer, plaintiff objected to his jurisdiction to proceed, on the ground, inter
alia, that the contract was merged in the judgment. Before proceeding, the
Engineer prepared a stated case for directions, but the Court, on application
to fix a date for hearing it, directed him to proceed without delay to hear
evidence. He found that $2,879.43 was due by plaintiff to workmen to comply
with the contract terms. Plaintiff, treating the report as an award made under
the terms of the contract, moved the Court to set it aside on the said
jurisdictional ground and on the ground that it purported to set up a new
contract between plaintiff and its workmen. The Court referred the matter back
to the Engineer for definite findings on a point as to rate of wages. The
Engineer filed a supplementary report. The City then moved for an order
confirming both reports and to make them a rule of court, and plaintiff moved
to set aside the award. The Court, by a majority, granted the City’s motion and
dismissed plaintiff’s motion. From that judgment plaintiff brought the present
appeal.
Held: The
appeal should be dismissed. The jurisdiction of the Engineer to investigate and
report depended entirely upon the jurisdiction of the Court in banco to
make the order of reference; and this order, not having been appealed from at
the proper time, could not now be reviewed; plaintiff, therefore, could not how
impeach the award on the ground that the rights of the parties to the contract
had become merged in the default judgment (which ground was the basis of
objection to the jurisdiction of the Court in banco to make the order
and of the Engineer to proceed under it); and there was no uncertainty or
manifest error of law on the face of the award.
As to the order of reference of the Court in
banco:
Per Duff C.J.:
The Court in banco had discretionary authority to set aside the default
judgment, and had jurisdiction to grant the stay, and to impose, as a term of
its refusal to set aside the judgment, that the amount, if any, found due by
the contemplated award should be treated as payment pro tanto on account
of the judgment; which was in substance the effect of its decision. It is
gravely questionable whether this Court had jurisdiction to hear an appeal from
that judgment; and whether, if jurisdiction existed, the judgment dismissing the
appeal having been acted upon, any appeal would not have been barred exceptione
personali. But whether appealable or not, it was a judgment of a Court of
general jurisdiction, possessing (with some reservations not here material)
authority to pronounce conclusively, subject to appeal if the law gave an
appeal, upon any question of its own jurisdiction; and, disregarding any
question of personal estoppel by acceptance of the judgment, the Court in the
subsequent proceedings was bound by its own judgment (Samejima v. The
King, [1932] Can. S.C.R. 640, at 647).
Per curiam:
Had the City defended the action it would have been entitled under the contract
to withhold moneys due by it to plaintiff to make
[Page 126]
good to workmen any deficiency in the wages
found to be payable to them under the wage clause; and the result of the
proceedings taken under the order of reference was precisely the same as that
which would have followed had the Court set aside the default judgment and
allowed the City to defend; and was one which seemed to meet the justice of the
case as it was brought before the Court with concurrence of both parties to the
contract.
APPEAL by the plaintiff from the judgment of
the Supreme Court of Nova Scotia in banco.
The plaintiff company recovered judgment, in
default, of defence, against the defendant city for $14,432.11, the balance
payable under a contract between it and the city for construction by it for the
city of sidewalks, etc.
Certain workmen had claimed that they had
been paid by the plaintiff wages below that required by clause 12 of the
contract, and they brought action against the city and the plaintiff in regard
to the same.
The contract provided (inter alia) as
follows:
12. The rate of wages to be paid by the
Contractor for labour and truckage shall not be less than the rate paid by the
City for similar classes of labour and truckage. The rate of wages for other
workmen or mechanics shall be that current for workmen or mechanics engaged in
the respective trades in the City of Halifax.
15. Any dispute or difference between the
parties hereto—
(a) in respect to the proper amount
payable under this agreement or the proper amount of any certificate of the
Engineer for any work done, or the final settling of accounts, or
(b) arising out of or relating to this
memorandum of agreement, including the plans, drawings, specifications and
details of the work to be done and material supplied, or the construction and
meaning thereof, or
(c) In any other way arising out of or
concerning this agreement or the work to be done thereunder shall be referred
to the Engineer, whose sole written decision thereon shall be absolutely final,
binding and conclusive between the parties hereto, and all persons concerned
and every such reference and decision, may be made a rule of court as a
submission or as an award respectively, and no action or other proceedings
shall be instituted or prosecuted in reference to any matter so in dispute or
difference until the said matter is so referred to the Engineer and he has
given his written decision thereon, and then only for the purpose of enforcing
such decision.
17. (1) If the Contractor fails to pay for
any labour or materials after payment is due, the City may appropriate any
amount due the Contractor under this contract, or any amount held by the City
by way of deposit as security for this contract, and apply the same or any part
thereof towards the payment of such liabilities and the amount of any such payment
shall be considered payment out of the amount due to the Contractor, or out of
the value of the work performed or materials provided.
(2) If the Contractor and any labourer, or
any person who has provided material, cannot agree as to the amount due, the
Engineer shall
[Page 127]
immediately after notice to the parties
concerned, hear and determine any question as to such amount, and the amount so
found to be due by the Engineer shall be final and conclusive between the
parties.
(3) The City shall not in any way be liable
for any such wages or materials or for any payment or appropriation made under
this section, nor shall the City be bound to act under this section or to make
any such appropriation.
“Engineer” (defined in the contract) meant
the city engineer of the said city.
The city applied for leave to reopen the
judgment entered against it by the plaintiff and to defend the action. Hall J.
dismissed the application.
The city appealed to the Supreme Court of Nova Scotia in banco. That
court
dismissed the appeal, but, the contract having been laid before it by agreement
of counsel and its attention called to the fact of the workmen’s action, it
ordered a stay of execution as to $5,000 for 30 days, with leave to apply for a
further extension; it also ordered that the workmen’s action be discontinued
and that proceedings to arbitrate the workmen’s claims be proceeded with
without delay before the city engineer.
On objection by counsel for the plaintiff as
to the engineer’s jurisdiction to proceed, on the ground, inter alia, that
the contract was merged in the judgment, the engineer, before proceeding with
evidence, prepared a stated case to the Supreme Court for directions, but the
court, on application to fix a date for hearing, directed him to proceed without
delay to hear evidence. He did so and made a report. The plaintiff moved to set
it aside. The court referred the matter back to the engineer to make definite
findings upon a certain point, and the engineer accordingly filed a
supplementary report. The above proceedings are set out with some further
particularity in the judgment of Crocket J. now reported. The city moved for an
order confirming both reports and to make them a rule of court so that they
might be enforced as upon a judgment; and the plaintiff moved to vacate and set
aside the award. The court granted the city’s motion and dismissed the
plaintiff’s motion (Hall and Doull JJ. dissenting). It was from this judgment
that the plaintiff’s present appeal was brought.
[Page 128]
R. McInnes K.C., for
the appellant.
C. P. Bethune for
the respondent.
Duff C.J.—I entirely concur with my brother Crocket. The substantial
question involved is whether or not there was manifest error of law on the face
of the award.
The issue as to jurisdiction disappears when the
true nature of the order of the full court of the 18th of February, 1933, is understood. It is explained in the reasons of Mellish, J.:
“Proceedings on the judgment to the exent of
$5,000 were,” he says, “stayed to enable the city to proceed under said clause
15 of the contract, and have the question in dispute as to whether clause 12 of
the contract had been complied with by the contractors determined” and the
further amount due to the labourers by the contractors under the terms of the
contract ascertained. “Subject to this the appeal was dismissed with
liberty to apply for further directions.”
There can be no doubt that the Full Court had
discretionary authority to set aside the judgment by default, or that it had
jurisdiction to grant the stay, and to impose as a term of its refusal to set
aside the judgment, that the amount, if any, found due by the contemplated
award should be treated as payment pro tanto on account of the judgment.
That, as Mellish J. points out, is, in substance, the effect of the Full Court’s decision of February.
It is gravely questionable whether this court
had jurisdiction to hear an appeal from this judgment; and whether, if
jurisdiction existed, the judgment dismissing the appeal having been acted
upon, any appeal would not have been barred exceptione personali. In any
case, no appeal was attempted, and whether appealable or not, it was a judgment
of a court of general jurisdiction, possessing (with some reservations not here
material) authority to pronounce conclusively, subject to appeal if the law
gave an appeal, upon any question of its own jurisdiction; and, disregarding
any question of personal estoppel by acceptance of the judgment, the court in
the subsequent proceedings was bound by its own judgment (Samejima v. The
King).
[Page 129]
In view of this qualification introduced into
the order of Hall J., the appellants, obviously, were precluded from impeaching
the award on the ground that the rights of the parties to the contract had
become merged in the default judgment; and I agree that there is no manifest
error of law on the face of the award, and that the award is not void for
uncertainty.
An award can be set aside, (1) when it has been
improperly procured, and (2) on the ground of misconduct of the arbitrator. “Misconduct”
is in this relation a term of very comprehensive denotation, and includes
ambiguity and uncertainty in the award, as well as manifest error of law on the
face of the award. The appellants have not established the existence of any of
these grounds.
The appeal should be dismissed with costs.
The judgment of Cannon, Crocket, Hughes and
Maclean (ad hoc) JJ. was delivered by
Crocket J.—This case has already been before the Supreme Court of Nova
Scotia en banc three times.
The first appeal to that Court was against a
judgment of Mr. Justice Hall dismissing an application of the City to reopen a
judgment by default which had been entered against it at the suit of the
appellant for $14,432.11 and costs. This amount was a balance due on a contract
for the construction of sidewalks, curbs, etc, which the City had held back to
protect itself against claims which were being threatened against it by certain
workmen, under a fair wages clause contained in the contract, requiring the contractor
to pay them not less than the rate paid by the City itself for similar classes
of labour. The Supreme Court dismissed this appeal but, the contract having
been laid before it by agreement of counsel and its attention called to the
fact that an action had been begun by certain of the workmen against the City
for wages on the basis of the fair wages clause, it ordered a stay of execution
as to $5,000 for thirty days with leave to apply for a further extension. It
ordered at the same time that the workmen’s action be discontinued and
proceedings to arbitrate the workmen’s claims before the City Engineer be
proceeded with without delay. When the hearing came on before the
[Page 130]
City Engineer counsel for the contractor
objected to his jurisdiction to proceed with the reference on the ground, inter
alia, that the contract was merged in the judgment. The Engineer before
proceeding with any evidence prepared a stated case to the Supreme Court for
directions, but the Court, on an application by him to fix a date for hearing
the proposed case, directed him to proceed without delay to hear evidence. In
the end he found that the minimum rate of wages contemplated by the contract
was 40 cents per hour, and that the sum of $2,879.43 was due by the contractor
to some 159 workmen if the terms of the contract were complied with. The men
had been paid at the rate of 35 cents per hour.
The contractor, treating the report as an award
made under the terms of the contract, moved the Supreme Court to set it aside
on the jurisdictional ground already mentioned, as well as upon the ground that
it purported to set up a new contract between the company and its workmen. On
this motion there was a marked difference of opinion among the members of the
Court as to whether the Engineer had made any finding which could safely be
acted upon as to what the rate was which the City was paying for similar
classes of labour during the currency of the contract, but a majority of the
Court decided that the matter be referred back to the Engineer to make a
definite finding upon this point. Mellish and Carroll, JJ., thought the finding
already reported was sufficient.
The Engineer accordingly filed a supplementary
report, whereupon the City moved for an order confirming both reports as awards
made by the Engineer, “sitting as arbitrator in the matter of an arbitration
between the Scotia Construction Co. Ltd. and certain workmen” and to make them
a rule of court so that they might be enforced as upon a judgment. The majority
of the Court granted this motion, Hall and Doull, JJ., dissenting, and the case
now comes before us on appeal from the last named judgment.
The judgment on appeal concerns only the
confirmation of the two awards or findings of the Engineer. No appeal was taken
from the judgment of the Court en banc staying execution and referring
the matter in controversy to the Engineer for investigation and report.
Although that
[Page 131]
judgment was in a sense an interlocutory
proceeding it was nevertheless, to quote the language of Duff, J., in
delivering the judgment of this Court in Diamond v. The Western
Realty Co.,
“a final decision in the sense that in the absence of appeal it became binding
upon all parties to it.” The jurisdiction of the Engineer to investigate and
report depended entirely upon the jurisdiction of the Court to make the order
of reference, and, this order not having been appealed from at the proper time,
we are of opinion that we cannot now review it. In the words of Lord Macnaghten
in delivering the judgment of the Judicial Committee of the Privy Council in Badar
Bee v. Habib Merican Noordin,
quoted by Duff, J., in Diamond v. The Western Realty Co., “if the decision was wrong,
it ought to have been appealed from in due time.” So far, therefore, as that
question is concerned, it must be taken to have been already settled.
All the objections which are now urged against
the validity of the Engineer’s awards or findings, save one, are in reality
grounded on the alleged extinction of the contract with all its fair wages and
arbitration provisions by reason of its merger in the default judgment. This
was the whole basis of the objection to the jurisdiction of the Court en
banc to make the order of reference and of the Engineer to proceed under
it. Though these questions are not now open for the reason already stated, it
may not be inappropriate to observe that, notwithstanding the contract was dead
as between the City and the Company, it was expressly agreed by counsel for
both parties that it should be laid before the Court for consideration on the
first appeal from Mr. Justice Hall’s judgment, and that it was thus that the
dispute regarding the alleged breach of the fair wages clause and the claims of
the workmen upon it were brought to the Court’s attention, and, moreover, that,
had the City defended the original action instead of deliberately allowing
judgment to pass against it by default, it would have been entitled under
clause 17 to withhold any amount due by it to the Company to make good to the
[Page 132]
workmen any deficiency in the wages found by the
Engineer to be payable to these workmen under the fair wages clause. The result
of the proceedings which have been taken by the order of the Court, therefore,
is precisely the same as that which would have followed had it set aside the
judgment by default and allowed the City in to defend, and is one which seems
to meet the justice of the case as it was brought before the Court with the
concurrence of both parties to the contract.
Apart from the jurisdictional grounds the single
ground put forward against the validity of the judgment now on appeal is that
the awards or findings were bad for manifest error of law because of their
uncertainty and indefiniteness. While one perhaps might have expected the
Engineer to be more explicit in his supplementary finding in view of the reason
given by the Court for sending the case to him a second time, I agree with the
majority of the Judges that it cannot well be taken to be other than a finding
that the rate which the City paid for similar work performed by itself during
the currency of the contract was 40 cents an hour, and that the contractor had
not, therefore, fully paid these workmen the wages they were entitled to
receive under the fair wages clause. In my opinion this objection cannot be
sustained. The awards being good on their face, we cannot go behind them in the
absence of any fraud or misconduct on the part of the Engineer in the
performance of the duty which the Court committed to him, of which there has
been no suggestion. We must assume that he has rightly and regularly performed
that duty.
The appeal should be dismissed with costs.
Appeal dismissed with costs.
Solicitor for the appellant: Russell McInnes.
Solicitor for the respondent: C. P. Bethune.