Supreme
Court of Canada
Samuel
v. Black Lake Asbestos and Chrome Co., (1921) 62 S.C.R. 472
Date:
1921-10-11
Frank
Samuel and Others (Plaintiffs) Appellants;
and
Black Lake
Asbestos and Chrome Company (Defendant) Respondent.
1921: June 10, 13; 1921:
October 11.
Present: Idington, Duff,
Anglin, Brodeur and Mignault JJ.
ON APPEAL FROM THE
APPELLATE DIVISION OF THE SUPREME COURT OF ONTARIO.
Contract—Purchase of goods—Time for delivery—Extension—Breach—Measure of damages—Substituted contract.
By a contract entered into
in April, 1917, S. agreed to purchase a specified quantity of chrome ore from
the Black Lake Co., delivery to be completed on Nov. 1st. The ore was not
delivered on that date though S. had been urging expedition and had offered to
extend the time and in October the company wrote S. that material shipments
could not be made for some months and suggesting that the contract be
cancelled, which S. refused to do. There was no formal extension. In November
conversations took place between S. or his representative and the manager of
the mines which ended in the latter undertaking to deliver the ore as fast as
it could be got out. The delays continued with S. still urging expedition until
June, 1918, when the company wrote that no further deliveries would be made. In
an action by S. for damages the breach of contract was admitted the only
question being its date and the consequent measure of damages.
Held, reversing the judgment of
the Appellate Division (48 Ont. L.R. 561) that there was no breach of the
contract before June, 1918; that there was no new contract entered into as a
result of the conversations that took place in November, 1917, but the parties
acted throughout on the basis of the original agreement made in April; and that
the measure of damages was the difference between the contract price and the
value of the ore in June, 1918.
[Page 473]
APPEAL from a decision of
the Appellate Division of the Supreme Court of Ontario, reversing the judgment at
the trial as to the measure of damages.
The
material facts are stated in the above head-note.
Anglin
K.C. and R.C.H. Cassels for the appellants. The respondents were in fault and the
appellants exercised forbearance up to June 21st, 1918. The breach occurred on
that date and the measure of damages should be the difference between the
contract price and the value of the ore then as there was no market. See Ogle
v. Earl Vane; Hickman v. Haynes.
H.J.
Scott K.C. and R.S. Cassels K.C. for the respondents referred to British
Westinghouse Electric Co. v. Underground Electric Railways Co.
IDINGTON
J.—The respondent, in the end
of April and beginning of May, 1917, entered into two written contracts with
the appellants to sell and deliver to them Canadian Lump Chrome ore.
The following is a copy of the first
of these contracts:
Philadelphia, April 25th, 1917.
Messrs.
Black Lake Asbestos & Chrome Co., Ltd.,
Black Lake, P.Q., Canada.
Dear
Sirs:—We have to-day bought for
our account from you a lot of Canadian Lump Chrome Ore on the following
conditions, viz.:
Quantity
1,500 gross tons of 2,240 lbs. each.
Brand
or make.
Quality
good, well prepared chrome ore.
Price:
Ore analyzing 32 to 35% chromic oxide, $23.50; for ore analyzing over 35% to
38%, $25.75; for ore analyzing over 38% up to 39%, $27.50, with a scale of
$1.00 for each full unit over 39% and up to 42%. All per gross ton.
[Page 474]
Terms
of payment to be made in U.S. gold coin or equivalent. Cash in full to be paid
in Black Lake, less 25c. per ton as heretofore.
Place
of delivery f.o.b. cars, Quebec Central Railroad Company’s tracks, between
Robertsonville and D’Isrœli, P.Q.
Time
of shipment: As fast as possible. The entire quantity to be shipped not later
than first of November. This purchase is subject to the Canadian Government
granting permission to ship to the United States.
Shipping
directions: Will be given as fast as the ore is loaded.
Remarks:
Sampling and analyzing to be done by us, at our expense. Where our
determinations are not satisfactory to seller, he is to have the privilege of
disposing of such carloads which are to be replaced.
Note:
Each delivery to constitute a separate and independent contract unless
otherwise stated.
All
agreements contingent upon strikes, accidents, delays of carriers, or other
unforeseen circumstances beyond the reasonable control of the sellers, wars of
this or other nations, as well as interruptions of navigation through strikes
or other causes, in which case deliveries against this contract may be
suspended.
Sellers
are not compelled to replace shipments lost at sea.
Accept.
May 29, 1917.
Black
Lake Asbestos & Chrome Co., Limited.
(Sgd.) J.E. Murphy, Jr.
Yours truly,
(Signed)
Frank Samuel.
The second is identical in its terms save being for 2,000
gross tons instead of as in the first for 1,500 tons and the dates of the
making being 2nd May, and acceptance the 29th of May and in the use of the word
“analyzing” for “containing.” A printed form was used in
each case and I surmise one used by appellants.
The
respondent not only failed to complete delivery by the 1st November, 1917,
named in each of the respective contracts for limit of time therefor, but
continually held out to appellants hopes of doing so and accepted their
forbearance from time to time until June, 1918, when the respondents’ many broken promises had
apparently become unbearable to appellants and led them to write respondents
the following letter:—
[Page 475]
Philadelphia, Pa., June 11th, 1918.
Messrs.
Black Lake Asbestos & Chrome Co.:
Dear
Sirs:—Referring to our two
contracts with you for chrome ore on April 25th and May 3rd, 1917, we are
advised by our representative at Black Lake that your Black Lake office is
shipping chrome ore to other parties without giving us the opportunity to
sample and analyze this ore and apply against our contracts with you. We
consider this a repudiation on your part of our contracts, and therefore, will
have to take legal action and hold you for non-delivery of this ore.
We
telegraphed you to this effect to-day and must have an immediate answer in
reference to same. We are sending a copy of this letter to your Black Lake
office.
Yours very truly,
(Sgd.)
Frank Samuel.
The
substance of this letter was also sent by telegraph on the 11th of June, but no
reply came to either until the following:—
No 20 Victoria Street,
Toronto, Ontario, June 21st, 1918.
Frank
Samuel, Esq.,
Harrison Building,
Philadelphia, Pa., U.S.A.
Dear
Sir:—Delay in answering your
telegram and communication of the 11th inst. has been due to the writer’s absence from the city.
The
contracts to which you refer bear on their face a ground for termination, viz.,
the pinching out of ore, which unfortunately took place on our properties.
We
regret to say, also that the sampling and analysis which has been done by your
representative in the past has been most unsatisfactory.
In
addition, practically our entire output at the present time is being used for
home consumption, and we regret that we cannot make any further shipments to
you.
Yours very truly,
Black Lake Asbestos & Chrome
Company, Limited,
(Sgd.)
Robert F. Massie,
Managing Director.
[Page 476]
Hence
this action for damages in which respondents set up many defences all of which
were decided by the learned trial judge to be unfounded.
He
assessed (expressly relying upon Ogle v. Vane, hereinafter referred to)
the damages on the basis of the difference in market price for such goods on
the date of respondents’ last letter, quoted above,
and the price named in each of said contracts.
On
appeal therefrom to the first Appellate Division of the Supreme Court for
Ontario, that court maintained said judgment in all respects save in the taking
of said date as basis for the assessment of damages.
It
instead thereof directed a reference to the Master in Ordinary to inquire and
state the damages.
Instead
of taking any fixed date as the basis for applying the relevant law to the
existent facts it directs said master
to
ascertain and state what quantity of Canadian lump chrome ore within the grades
contracted for was diverted from delivery to the plaintiffs by the defendants
other than for unsatisfactory analysis of the ore, and sold to other persons
between May 1st, 1917, and June 22nd, 1918, and whether any and if so what
quantity of similar ore was purchased by the plaintiffs between the said dates
to replace the ore so diverted and sold to other persons, and is to allow to
the plaintiffs, as damages, in respect to the ore, so diverted and replaced,
the excess, if any, between the price paid by the plaintiffs in each case and
the contract price for the same grade of ore. And as to the residue of the
2,660 tons undelivered by the defendant the said Master shall allow as damages
the sum of $30.26 per ton, being the difference per ton between $23.50 the
contract price and $53.76, the market price on June 21st, 1918, of ore of the
lowest grade contracted for, but the defendant shall be entitled to shew before
the said Master in mitigation of the said last mentioned damages: (1) that the
plaintiffs bought at a lower price than $53.76 per ton by reason of the
situation caused by the defendants default in delivery, and (2) that the
plaintiffs bought in in the market at a lower price than $53.76 per ton in
excess of the amount required to fill their forward contracts, and in either of
the said events the damages on the ore so bought shall be calculated on the
basis of the said lower price instead of at the sum of $30.26 per ton.
[Page 477]
I, with
great respect, cannot find in my view of the contract above set forth and the
relevant facts anything to warrant the court below in finding as the reasons
for its judgment shew, that
as
each car was diverted from the respondent (now appellant) and shipped elsewhere
that was a repudiation pro tanto and was known to be so by the
respondent (now appellant) through his agent Wooler.
The
contract was not for the entire output of the mines of respondent regardless of
its obligations to others either express or implied. The only words in the
contract giving any colour for such an interpretation are, I submit, the words “fast as possible” which, seeing it had till
the 1st November—a period of seven months—to get out and load about
three thousand tons of the desired ore, must be interpreted reasonably.
Let us
imagine a buyer under such like contract, on discovery that other customers of
the vendors were getting shipments from him of the like goods, immediately
going into the open market and buying at a lower price than named in his
contract and trying then to evade the acceptance of delivery tendered him
within the ultimate time named for delivery and setting up such a defence.
I
submit such a proceeding could not be countenanced and that such a defence
would not be listened to for a moment. Nor can the counterpart thereof as
presented herein be maintainable. Contracts for delivery by instalments at
stated times have been presented in some cases to courts and damages assessed
on that basis as evidently what was within the contemplation of the parties
concerned therein. But that is not the nature of this contract. Nor do the
words therein “note: each delivery to
constitute a separate and independent contract unless otherwise
[Page 478]
stated,” which seem to be relied on
by the reasons assigned below, make it so. They are words which form part of a
printed form used in making the contract and the only operative effect they can
have herein would be in the event of a contest as to the quality of goods that
had been so delivered, or something akin thereto, arising out of such delivery
or in relation to such goods as had been delivered.
There
is no dispute herein arising out of past deliveries.
The
only thing here in question is what arises out of non-delivery to which the
said note is entirety inapplicable.
I
submit, therefore, the first part of the above quoted direction to the master
is not maintainable.
Thus, I
conceive, is also eliminated from our consideration, all that transpired up to
the time limit of 1st November for the complete fulfilment of the contract,
save in so far as the correspondence between the parties hereto prior to that
date may, and I think, must, be looked at to help in the due appreciation of
what followed up to the 21st of June, 1918.
It is
upon the correct appreciation of the said correspondence so had, that
maintenance of the remaining parts of the order of reference should depend.
The
difference between the market price of such goods as in question, on the 1st
November, 1917, and the price agreed for under the contract, would be the true
measure of damages for the breach then, of the contract, unless otherwise
provided, or determined by the conduct of the parties.
On the
17th October, 1917, in reply to a complaint as to the tardy nature of
deliveries under the contract, on the part of appellants, the respondent wrote
Samuel (the writer of said complaint) as follows:—
[Page 479]
Dear
Sir:—We have your favour of the
11th inst. and in reply beg to advise, that we do not expect to be in a position
to make larger shipments of chrome ore on your contract before next summer, so
if you wish to cancel your contract on the first of next month we will do so.
We regret very much that we are unable to make larger shipments on your
contract at present, but it is a cause beyond our control. Kindly let us have
your reply to this offer at an early date.
Yours truly,
Black Lake Asbestos & Chrome Co.,
Ltd.,
Per J.E. Murphy, Jr.
Reply
thereto (dated 23rd October) was as follows:—
Dear
Sirs:—We are in receipt of your
favour of October 17th, and in reply would state that we cannot cancel our
contract with you for chrome ore, as our people are willing and anxious to
receive this ore at the present time, and we must ask you to get shipments off
as rapidly as possible.
Very truly yours,
(Sgd.) Frank Samuel.
It
seems quite clear that respondent by offering cancellation meant literally what
it said and did not intend to be held for damages in case of assent on the part
of appellants to the proposition presented
On the
20th November the correspondence is resumed and it continued until June
following of such a character as clearly to demonstrate that the respondent was
claiming it was doing the best it could to live up to the contract and was
asking and accepting appellants’ forbearance and promising
future deliveries and that the appellants were exercising due forbearance and
perhaps more than the respondent deserved.
Indeed
it would have been improper under such relations as said correspondence discloses
to have brought chrome ore of kind and quality named in the contract for the
sole purpose of asserting an action for damages and thereby establishing the
measure of such damages as appellant had suffered.
[Page 480]
The
respondent’s factum points to a letter
of appellant of 18th March, 1918, pointing out to the former the measure in
which it had failed to live up to its promises and to threats it had made of a
discontinuance of the forbearance that had hitherto been shewn respondent
unless it shewed a better appreciation thereof.
It is
to be observed that said letter went no further than pointing out the course
which the appellant might be driven to adopt and hence they remained liable to
fulfil their part of the contract until they had gone further or the respondent
had as it did later repudiate in clear and explicit terms.
The
answer to the respondent’s attempt to use this
letter as evidence that the contract had ended is not confined to that alone
for the effect of it was to produce a delivery of it and acceptance by
appellants of two more car loads of chrome ore in the month of April.
Thus by
the concurrence of both parties the contract had not ended and the final breach
thereof taken place.
The
decision in the case of Ogle v. Earl Vane, seems to me to exactly
fit the facts in the case as I find them by a perusal of the entire
correspondence. In that case Blackburn J. wrote the leading judgment. In the
Exchequer Chamber, in appeal therefrom, the court was unanimous and it may not
be amiss to remark that Willes J. was one of those writing to express the
opinion of the court. Shortly thereafter in 1875, in the case of Hickman v.
Haynes, a strong court in appeal,
Lindley J. writing the judgment, accepted that decision as a guide and applied
the principle involved.
[Page 481]
In 1899
the late Chief Justice Lord Russell of Killowen in the Commercial Court applied
the identical principle thus involved to the decision of the case of Ashmore
& Son v. C.S. Cox & Co., and at the close of his
judgment page 443 furnished an apt illustration of what should be borne in mind
in dealing with the facts presented herein.
Unfortunately
respondent seemed to have been inclined herein throughout to get away from the
actual facts as I view them both in its dealing with the appellants and the
case presented to the court, or to read them backwards.
In my
view of the facts the case is simple and the appeal should be allowed and the
judgment of the learned trial judge be restored with costs here and in the
first Appellate Division of the Supreme Court of Ontario,
DUFF J.—The appellants, I think,
are entitled to succeed on the principal ground on which they based their
appeal, namely that there was no substituted contract but that the time for
delivery was extended from time to time in forbearance and by way of indulgence
at the request of the defendants. That is, I think, a substantially just
interpretation of what occurred between the parties, and it is also, I think,
what the trial judge intended to find although his findings, perhaps, are not
very precisely expressed.
No
question arises here such as that which, but for the arrangement between the
parties, might have arisen in Tyres v. Rosedale Iron Co., where the
[Page 482]
plaintiffs
insisted upon putting an end at once to the indulgence and required immediate
delivery of all the overdue instalments. No such question arises here, because
the immediate cause of the indulgence being terminated was the repudiation by
the defendants of their obligations under their contract.
ANGLIN
J.—At the conclusion of the
argument I had a strong impression that the disposition made of this case by
the learned trial judge had been entirely satisfactory and should not have been
interfered with. Further consideration has confirmed that view. The issues as
to the breach of the contract by the defendants, the date when such breach
occurred, alleged purchases by the plaintiffs to replace ore which the
defendants had failed to supply and the quantum of the plaintiff’s damages were presented
for trial and were tried out. The evidence supports the finding of a wilful
breach of contract by the defendants deliberately made in order to take
advantage of an increased market price. Forbearance by the plaintiffs at the
instance of the defendants prevented an actionable breach before the 21st of
June, 1918, when such a breach undoubtedly occurred. The assessment of damages
as of that date was therefore warranted. The measure of damages adopted by the
trial judge—the difference between the
sale price and the value at the date of breach—was that prescribed by the law under
such circumstances as the evidence disclosed no market in which the goods were
procurable at the date of the breach. The quantum allowed has not been
successfully challenged. Prior to the 21st of June, 1918, the plaintiffs were
under no obligation to look elsewhere for ore in order to mitigate their
damages. Indeed they could not safely purchase ore to
[Page 483]
replace
what the defendants were bound to furnish as the contract being still open they
might be compelled to take the latter. After the 21st of June, so far as the
evidence shews, no ore was available—certainly
none at any price less than that which the learned trial judge fixed as the
value at that date of the ore in the delivery of which the defendants made
default.
There
is in my opinion nothing to justify further investigation. The appellants had
their day in court. They took their chances on the evidence submitted at the
trial. If they failed to take every advantage of the opportunity they then had
they must suffer the consequences. With respect, the judgment of the trial
judge was in my opinion entirely right; it should not have been disturbed and
should now be restored.
BRODEUR
J.—I concur in the result.
MIGNAULT
J.—The only question here is
as to the quantum of the damages to which the appellants are entitled for the
admitted default of the respondent to make deliveries in accordance with the
requirements of the two contracts which it had made with the appellants to sell
them the total quantity of 3,500 gross tons of Canadian lump chrome ore. The
quantity undelivered was 2,660 tons, and by the terms of the contracts the
whole of the ore should have been delivered not later than the first of
November, 1917.
The
finding of fact of the learned trial judge with regard to the question whether
the time for delivery had been extended beyond November 1st, 1917, is as
follows:—
[Page 484]
From
the beginning defendants were dilatory in making delivery, so that long before
November 1st—the date fixed for the
completion of the deliveries—it became apparent that
full delivery would not be made within that time. Plaintiffs did not then stand
on their strict right to enforce performance at that time, but while
continually pressing for more prompt and larger deliveries than they were
getting, the facts warrant the inference that the effect of what happened
between them was an extension from time to time of the time for making
deliveries until hope for further deliveries was ended by a notice of
June 21st, 1918, by the defendants declining to make further shipments to plaintiffs.
Not only is this so but Mr. Tomlinson makes the statement that plaintiffs
had extended the time for delivery down to the time defendants repudiated the
contracts, which statement has not been contradicted.
It is
true that the learned judge arrives at this finding by means of an inference
from the facts proved, but there was certainly no refusal of the respondent to
make any deliveries after November 1st, and subsequently to that date the
appellants pressed for the carrying out of the contracts, and the respondent
made certain deliveries thereunder, so that until the final refusal to make
further deliveries in June, 1918, both parties were acting under the original
contracts of sale. The inference of the learned trial judge is therefore fully
justified by the evidence.
I
cannot accept the contention of the respondent that after the 1st of November,
1917, a substituted contract was entered into to sell ore to the appellants as
fast as it could be mined, which contract not being in writing could not be
enforced, but, according to my reading of the correspondence, until the final
repudiation in June, 1918, the original contracts were considered in force and
acted upon by both of these parties.
If
therefore there was not a substituted contract, but a mere forbearance as to
deliveries under the original contracts, the time of repudiation or of refusal
to make further deliveries is the time at which the
[Page 485]
damages
for breach of contract should be assessed. Unfortunately for the respondent the
price of chrome ore had very notably increased from November 1st, 1917, to June
21st, 1918, when the letter of repudiation was written, so that its position is
worse than if it had declined to make further deliveries after November 1st.
But it is impossible to accept the latter date as the one at which the damages
should be assessed, for both parties acted under the contract for several
months afterwards, and really the respondent, by its letter of repudiation, has
determined the time for ascertaining the damages to which its repudiation
entitles the appellants.
The
only point remaining is whether the variation made by the Appellate Division in
the judgment of the learned trial judge should be sustained. This involves the
question whether an opportunity should be given to the respondent to shew, if
it can, whether or not the appellants, under their obligation to minimize the
damages, bought chrome ore to replace that undelivered by the respondent, the
damages then being the difference between the contract price and the price at
which such ore was purchased. After due consideration, I have come to the
conclusion that up to the time of repudiation the appellants were not entitled
to purchase chrome ore to replace that yet undelivered by the respondent, and
that if they had made such a purchase they could nevertheless have been forced
by the respondent to take the full quantity mentioned in the contracts. The
reference ordered by the Appellate Division would therefore be without any
possible use, for, if the appellants could not buy as against their contract,
it is immaterial to inquire at what price they did in fact purchase ore. The
appellants were dealers in ore and as there was a great
[Page 486]
demand
for the commodity they naturally bought all they could. It is true that the
contract states that each delivery should constitute a separate and independent
contract, but that certainly does not mean that as to the quantity undelivered
there should be as many contracts of sale as there were tons or carloads to be
delivered. And even were there such a multitude of contracts to be fulfilled
not later than November 1st, unquestionably the time for delivery could be
extended by forbearance beyond that date, and then the damages for the final
breach of contract would have to be determined as of the time of the breach.
In my
opinion, therefore, the judgment of the learned trial judge should not have
been disturbed, and the appeal should be allowed and this judgment restored.
The cross-appeal of the respondent should be dismissed with costs.
I may
add that inasmuch as the contracts in question were made in the Province of
Quebec where also the breach occurred, the liability of the respondent should
have been determined according to the Quebec law. The parties however assumed
otherwise and they appealed to the law of the forum which was applied by the
courts below. I am not to be taken as dealing with the matter under any other
basis.
Appeal allowed with costs.
Solicitors for the
appellants: Blake, Lash, Anglin & Cassels.
Solicitors for the
respondent: Cassels, Brock & Kelley.
[1868]
L.R. 2 Q.B. 275; 3 Q.B. 272.