The City of Calgary (Defendant) Appellant;
and
The Dominion Radiator Company (Plaintiff) Respondent
1917: October 18; 1917: November 28.
Present:—Sir Charles Fitzpatrick C.J. and Davies, Idington
Duff and Anglin JJ.
ON APPEAL FROM THE APPELLATE DIVISION OF THE SUPREME COURT OF
ALBERTA.
Mechanic's lien—Notice in writing—Verbal notice—Registration—
"Alberta Mechanics' Lien Act," s. 32, as amended in 1908.
[Page 141]
Held, Fitzpatrick C.J. and Idington J. dissenting,
that, to enforce the mechanics' or the material man's lien, under the
"Alberta Mechanics' Lien Act," a "notice in writing of such lien
and of the amount thereof" must be given to "the owner or person
having superintendence of the work on behalf of the owner," according to
section 32 of the Act, as amended in 1908.
Per Fitzpatrick C.J. dissenting.—Such notice in writing
is not intended to affect the validity of the lien, but merely to determine the
extent of the owner's liability.
APPEAL from the judgment of the Appellate Division of the
Supreme Court of Alberta,
reversing the judgment of Harvey C.J. at the trial, and maintaining the
plaintiff's action.
The respondent's action was brought against the appellant to
enforce a lien under the "Mechanics' Lien Act" of Alberta, recorded
against property owned by the appellant on which a building known as the
"Children's Shelter" had been constructed. The respondent had
supplied for this building the steam boiler and radiators necessary for a
heating system and a pumping equipment.
[Page 142]
The principal issue submitted by the appellant is that
respondent's claim was barred by failure to give written notice as required by
section 32 (as amended in 1908), of the "Mechanics' Lien Act" of
Alberta. The respondent contends that section 32 is merely a provision made to
protect an innocent owner from having to pay money a second time; that the lien
given by sec. 4 of the Act has its commencement as soon as the material is
furnished, and that, when fyled, such lien is an encumbrance upon the land.
The trial judge held against the respondent, and dismissed the
action; but, on appeal, the Supreme Court of Alberta unanimously reversed this
decision.
F. E. Meredith K.C. and C. F. Adams for the
appellant.
R. S. Robertson for the respondent.
THE CHIEF JUSTICE (dissenting).—Under the terms of
the "Mechanics' Lien Act," as I
read it, the material men and labourers acquire, from the moment that
the material is furnished or the labour performed (section 4), an interest in
the contract price limited to the sum actually owing to the person entitled to
the lien (section 8), which interest cannot be for any greater sum than the
owner has agreed to pay by his contract (section 19). The lien to secure that
interest becomes effective upon registration under section 2 (g) and (k)
and section 41 of the "Land Titles Act."
But the appellants contend: 1st, that the claim of lien was filed
too late: and 2nd, that the claim was barred by reason of the failure to give
written notice. Section 32, as amended.
Dealing with the first point. I find that section 13 of the Act,
fixing the time within which the material
[Page 143]
man's lien must be filed, provides that
the lien shall cease to exist on the expiration of 35 days after the claimant
has ceased from any cause to place or furnish the material. In other words, the
date from which the delay runs is not that from which the purchase price
becomes due and exigible but from the date at which the material man has ceased
to place or furnish the material, and that, of course, depends on the facts of
each case.
There can be no dispute about the facts here. When the city
authorities gave the order to supply the heating system for the Children's
Shelter in July, 1914, they had then in contemplation the installation of a
pumping system to supply the water without which the heating system could not
be operated. A well was then dug, and the subject of a pumping system was
discussed with the company before they supplied the radiator for the heating.
As a matter of fact, the pump was actually ordered about the 14th of November
(1914), at which date the radiator and boiler were being installed. The one
system was necessarily complementary of the other: the heating system could not
be operated without the pumping system. As one witness observes, it is
difficult to use radiators and boilers without water.
Although the material required was ordered at different times,
the parties had in contemplation from the outset the purchase and supply of a
complete set of pumps, boilers and radiators to heat the building by hot water.
This explains why a price for the pump was obtained from the respondent at the
outset. It is difficult to read the evidence without coming to the conclusion
that, as found below, there was what Chancellor Boyd calls in Morris v. Tharle:
[Page 144]
one entire prevenient governing
contract of which the respective deliveries are merely the execution.
Once that conclusion was reached by the Appellate Division, then,
I think, there can be no doubt that, as found, the claim was filed within the
delay (en temps utile). The pump was delivered in December, 1914 but
when tested it was found to be defective; and in February the shaft and wheel
were returned to the manufacturer. In a letter written in February, 1915, by
the contractor, he says:
It (the pump) was running about five minutes, when the
pinion became jammed and when they stopped the machine it was all chewed up the
way it was mailed to you.
It was not until March, 1915, that a
complete pump was furnished and the lien was filed on April 1st, 1915, well
within the statutory delay. Idington J. in the case of Day v. The
Crown Grain Co.,
says:
The test question here is whether or not the appellant could
in law have sued on the 20th April and recovered from Cleveland as for a
complete contract. I am of opinion he could not. Trifling as the parts
unfinished were, the party paying, in such a case, was entitled to insist on
the utmost fulfilment of the contract and to have these parts so supplied that
the machine would do its work.
Now, dealing with the second objection to the effect that the
claim is barred by reason of failure on the part of the material man to give
notice in writing. By supplying the material, an interest or lien on the money
in the hands of the owner is acquired by the furnisher, and by registration
that lien becomes, under the "Land Titles Act," an incumbrance on the
owner's title to the land so that under the provisions of the two statutes the
furnisher of material acquires, by registration in the Land Titles: Office, an
incumbrance on the owner's land for the price of his material.
[Page 145]
Anglin J. said in Travis v. Brakenbridge (unreported)
:
Registration may be deemed notice to the owner.
In this case the material man not only registered his claim but
also gave actual notice to the owners through Sylvester, their representative
on the work, that he looked directly to the fund for the payment of his claim.
There is nothing in the statute that requires him to do more than to register
his lien to acquire this incumbrance; and, as Mr. Robertson argued here, there
is nothing in the statute which states that the interest in the fund so secured
by an incumbrance on the land ceases to exist or that the incumbrance on the
land is discharged, if a notice in writing is not given under section 32. That
section, as it formerly stood, read as follows:
No lien * * * shall attach so as to make the owner liable
for a greater sum than the sum owing and payable by the owner to the contractor
As amended it now reads:
No lien * * * shall attach so as to make the owner liable
for a greater sum than the sum owing; by the owner to the contractor at the
time of the receipt by the owner or person having the superintendence of the
work on behalf of the owner of notice in writing of such lien and of the amount
thereof or which may become owing by the owner to the contractor at any time
subsequent thereto while such lien is in effect.
The section was amended in 1908 I strongly suspect because of the
judgment of the Alberta appeal court in Travis v. Brackenbridge, which condemned the owner to pay
twice over.
Those amendments, especially in view of the conditions in the
various sub-sections were intended not to effect the lien but to determine the
amount for which the owner would be liable. His liability is limited to the
amount due at the moment the notice
[Page 146]
was served; taken literally, that is all
the language means. The Act does not say when the notice should be served to be
effective. It does not in terms make the validity of the lien depend upon the
service of a notice in writing upon the owner, nor does it say that failure to
give notice discharges the encumbrance on the land. The Act says merely (sec.
32):
No lien * * * shall attach so as to make the owner liable
for a greater sum than the sum owing by the owner to the contractor.
The notice is not intended to affect the validity of the lien,
but merely to determine the extent of the owner's liability, and for his
interest only.
Whatever may have been the purpose of the legislature in enacting
the amendments to clause 32 as it originally stood, it seems to me obvious that
the notice in writing was not intended to protect the contractor or his
assignee. The construction contended for by the bank would, in the
circumstances of this case, give to a general contractor a preference over the
material man who had a lien under the statute for the price of his material,
and of which lien the owner had particular notice, as is evidenced from the
terms in which the receipt taken from the bank is drawn.
The appeal should be dismissed with costs.
DAVIES J.—I concur in the opinion stated by Mr Justice
Anglin.
IDINGTON J. (dissenting):—This is an appeal from a
judgment maintaining a claim of respondent to enforce a lien for material,
under the "Alberta Mechanics' Lien Act."
The only serious difficulty I
find in the case turns upon the question of whether or not a transaction
between appellant and the Bank of British North America (which, as assignee of
the contractors with
[Page 147]
the city, admittedly stands in the same
position as the contractor), represented by an instrument which reads as
follows,
EXHIBIT 13.
The Bank of British North America hereby acknowledges to
have received from the City of Calgary $1,457.98,
the balance due as certified by the city engineer on the contract
between Grant Brothers, Limited, and the city for plumbing, heating and water
supply in connection with the Children's Shelter; and the bank hereby
undertakes and agrees with the City of Calgary that if any claim shall be made
and established against the city under the "Mechanics' Lien Act"
under said contract not exceeding the said sum of $1,457.98, the same shall be paid by the said bank, and if any
action is brought against the city to establish any such lien the bank will
either pay the amount claimed, or, at its own costs and charges, contest said
claim and indemnify the city against the same and any costs occasioned thereby
not exceeding the amount hereinbefore mentioned—the city on receipt of said
claim, or on being served with any proceedings in Court, to notify the bank
thereof.
Dated the fifth day of May, A.D. 1915,
is clear evidence of payment absolving
appellant from all liability under the Act.
There is no evidence, unless it be the admitted fact that the
said sum of money was paid to the bank, of how or why the appellant should be
held to have so paid, in face of the clearest evidence that both the appellant
and the bank knew, at the time of said payment that the respondent had duly
registered the lien, under the Act, now sought to be enforced.
There were two fairly arguable points of law which may have been
present to the minds of those concerned relative to the right of the respondent
to maintain the lien so registered as to any part, or at all events as to the
larger item, of the claim.
It has been stoutly contended throughout, first, that the lien
was registered too late to be effective, and secondly, in any event, that the
first item of the account had been delivered and for a short time in use, two
months or so before registration of the lien.
[Page 148]
I agree for the reasons assigned in the judgment of Mr. Justice
Beck in the court below, that the account was, under the circumstances in
question, of that continuous nature and in relation to the same work as to
render the lien under section 4 of the Act valid if registered within
thirty-five days from the completion of the entire work and that by reason of
the inefficiency of the machine which constituted the second item thereby
needing a substitution of one of its parts, that the time for registration only
began to run from a date clearly within thirty-five days preceding
registration.
Were these the only questions which confronted the appellant and
the bank and were present to the minds of those concerned in framing the above
mentioned instrument? If so, then there is an end of the appeal.
But in the absence of any evidence, we are left to conjecture or
to draw such inferences as we may relative to the intention and meaning of the
transaction.
However that may be, it is now claimed that under section 32
which reads thus:
Sec. 32:—No lien, except for not more than six weeks' wages
in favour of labourers, shall attach so as to make the owner liable for a
greater sum than the sum owing by the owner or the contractor at the time of
the receipt by the owner or person having superintendence of the work on behalf
of the owner, of notice in writing of such lien and of the amount thereof; or which
may become owing by the owner to the contractor at any time subsequent thereto
while such lien is in effect,
inasmuch as there was no written notice
to the appellant, the lien never attached.
That has been answered by holding the statement of claim was a
written notice and so it would be literally within the language of the Act.
That is answered again by saying that no lien attaches so as to
[Page 149]
make the owner liable for a greater
sum than the sum owing by the owner or the contractor at the time of the
receipt by the owner or person having superintendence of the work * * * of
notice in writing of the lien, etc.
What does this mean? Clearly the contractor owed, and still owes,
the entire sum. And just as clearly under the statute, a lien did attach unless
we are to hold that in the case of a contractor paid in advance by the owner,
no lien is intended by the statute to attach under section 4 by virtue of the
respondent's furnishing the material.
It is not the registration that makes it attach. That is only a
requirement for its continuation beyond thirty-five days after completion.
It may be said this is hypercritical, and that the intention of
the statute must be looked to in order to make it workable. I incline to agree
therewith, but I submit that those relying upon such a doubtfully worded
instrument as that now in question ought, in the same spirit, to have made
plain what they intended.
It can, in every word of it, be made operative by referring the
questions of what it, negatively as it were, provided should nullify the
operation of the lien, to the obvious questions I have referred to, as all the
document had in contemplation under the circumstances.
To insist upon more renders it necessary to impute to the
appellant, having full knowledge of the fact that the lien existed, the most
unworthy motive of resorting to a trick for the purpose of unjustly depriving
respondent of its money.
For my part, I will not put that construction (which will wear
the appearance of an intent akin to fraud) upon the document, and short of
that, in my view, the appeal fails.
[Page 150]
It comes to this that despite all the growing tendency of public
corporations, like the appellant, to promote honesty and fair dealing with
those serving the city, as we had illustrated in the contract we had before us
in the recent case of Union Bank of Canada v. Ritchie Contracting
& Supply Co., which specifically provided (and we upheld its doing so)
that such claims must be paid, there is room to argue that material men may be
beaten out of their rights under the "Mechanics' Lien Act" if the
contractor can induce such corporation to aid them.
Leaving aside the broad question of whether or not it is possible
to so contract that the lien may be prevented by an agreement providing for advance
payments to the contractor, suppose we found such an attempt to take the form
of this document being incorporated into and made part of the agreement for any
public work, how should a court look at it?
Suppose a bank at the back of a contractor in such a case at the
very outset willing to indemnify upon receiving the money, would such a
transaction fall within the meaning of section 32 and be held payment?
This question I put to counsel and am yet without an answer.
I cannot assent to such a repeal of the Act.
I agree with Mr. Justice Walsh that such a transaction of
suspensive holding of money, as evidenced by this receipt, is not a payment
within the meaning of the Act.
I think the appeal should be dismissed with costs.
DUFF J.—The appeal should be allowed, and the action
dismissed with costs.
[Page 151]
ANGLIN J.—Reversing the judgment of Harvey C J., who had
dismissed the action, the Appellate Division of the Supreme Court of Alberta
held the plaintiffs, the Dominion Radiator Co., entitled to a mechanics' lien
in respect of the price of a hot water heating system ($1,019.27) and a water
pumping system ($438.71) furnished by them as sub-contractors for Grant Bros.
Limited to the defendants, the City of Calgary, for a children's shelter. From
that judgment the city appeals on three distinct grounds:—
(a). That the lien in respect of the whole claim had
expired before it was registered;
(b). That the contract for the heating system was entirely
distinct and separate from that for the water system and that the lien in
respect of the former, at all events, had expired;
(c). That when the city first received a "notice in
writing" of the plaintiffs' lien no sum was owing by it to the
contractors.
In view of my opinion on the third ground of appeal, I have found
it unnecessary to pass upon the other two grounds.
Sec. 32, s.s. 1, of the "Alberta Mechanics' Lien Act"
is as follows:—
Sec. 32.—No lien, except for not more than six weeks' wages
in favour of labourers, shall attach so as to make the owner liable for a
greater sum than the sum owing by the owner to the contractor (at the time of
the receipt by the owner or person having superintendence of the work on behalf
of the owner, of notice in writing of such Hen and of the amount thereof; or
which may become owing by the owner to the contractor at any time subsequent
thereto while such Hen is in effect).
The words in brackets were added by an amendment of 1908.
The lien is created by section 4 of the Act, and is thereby
declared to be
limited in amount as hereinafter
mentioned.
[Page 152]
By section 8, it is
limited in amount to the sum
actually owing to the person entitled to the lien.
By section 19 it is provided that
the owner complying with the
provisions of the Act shall not be liable for any greater sum than he had
agreed to pay by contract.
By section 32, above quoted, a further limitation is imposed,
with the result that the lien attaches only to the extent of any moneys owing
to the contractor by the owner when the latter receives notice in writing of
the lien, or which may subsequently become owing to the contractor.
Admittedly the first notice in writing of the appellant's lien
received by the city was the statement of claim in this action delivered on the
fourth of November, 1915. At that time the city had in hand no moneys owing to
the contractor, Grant Bros. Limited. It had paid the last of such moneys in its
hands ($1,457.98), to the Bank of British North America on the 19th of May,
1915, upon a claim made by the bank under an assignment from Grant Bros., of
which it had received formal notice on the 25th Feb., 1915. The appellants'
lien was registered on the first of April, 1915, and there is evidence of
verbal notice of their claim having been given to the city's building
superintendent shortly before its registration and again shortly afterwards. On
making the payment to the bank the city took from it the following receipt:
The Bank of British North America hereby acknowledges to
have received from the City of Calgary $1,457.98, the balance due as certified
by the city engineer on the contract between Grant Bros. Limited and the city
for plumbing, heating and water supply in connection with the Children's
Shelter; and the bank hereby undertakes and agrees with the City of Calgary
that if any claim shall be made and established against the city under the "Mechanics'
Lien Act" under said contract not exceeding the sum of $1,457.98, the same
shall be paid by the said
[Page 153]
bank, and if any action is brought
against the city to establish any such lien the bank will either pay the amount
claimed, or, at its own costs and charges, contest said claim and indemnify the
city against the same and any costs occasioned thereby not exceeding the amount
hereinbefore mentioned—the city, on receipt of said claim, or on being served
with any proceedings in court, to notify the bank thereof.
Dated the fifth day of May, A.D. 1915.
Upon the foregoing facts, the respondent urges that the payment
by the city to the bank after registration and verbal notice of the lien was a
fraudulent attempt to defeat it, and should therefore be held void as against
the lien holder, and that the terms of the receipt taken by the city confirm
this view and also shew that the payment to the bank was not intended to be a
genuine and absolute payment, and should therefore be disregarded in
considering whether there was any sum owing by the city to the contractors when
it received notice in writing of the lien—that it was in fact merely a
conditional payment of money to be returned to the extent to which the city
might be held liable to meet the plaintiffs' lien.
There is no evidence of any collusion or of fraudulent intent on
the part of either the city or the bank. No indirect or improper motive has
been suggested for the city or its officials preferring the bank's claim under
its assignment to that of the plaintiffs. For aught that appears the civic
authorities may have acted in the bond fide belief that the plaintiffs'
lien had expired before its registration, and that the city was bound to make
payment under the assignment of which it had received notice on the 25th of
February. Fraud is not to be presumed in this case more than in any other.
The effect of section 32 as it now stands, is, in my opinion, to
make the giving of notice in writing to the owner a condition of the mechanic's
or the mat-
[Page 154]
erial man's lien attaching so as to make
the owner liable, just as other sections of the Act make registration and the
institution of an action within defined periods conditions of its preservation.
There can be no more justification for holding verbal notice to be a sufficient
ground for dispensing with the fulfilment of one condition than for treating it
as a valid excuse for non-compliance with the others. To hold that the extent
of the owner's liability is fixed either by actual verbal notice or by
registration would be contrary to the explicit terms of section 32 and would
involve either reading out of that section the words "in writing" or
inserting a declaration that registration shall be deemed "notice in
writing." Such an alteration of the statute the legislature alone is
competent to make.
There is nothing inherently unfair or extraordinary in a
provision imposing the giving of notice in writing to the owner as a condition
of the existence of such a special privilege as the right to a lien conferred
on vendors of labour and material for work upon lands. It may be that in
endeavouring to protect the owner from the difficulties of a situation that
might arise from the absence of some such provision (illustrated in the cases
of Breckenridge & Lund v. Short
and Travis v. The Breckenridge-Lund Company
the legislature went farther in 1908 than was necessary or desirable. But, if
so, the responsibility is with it and the remedy in its hands.
Much was made in argument for the respondent of the provision of
the "Land Titles Act" which declares a mechanics' lien when
registered to be an encumbrance on the lands. But the existence of the
[Page 155]
lien itself and its extent depend upon
the provisions of the "Mechanic's Lien Act." The two statutes must be
read together, and registration under the "Land Titles Act" cannot be
taken to create an encumbrance where there is no valid lien under the
"Mechanics' Lien Act" or to neutralize or modify the limitation upon
its extent which the "Mechanics' Lien Act" explicitly imposes.
As to the receipt taken by the city it does not establish that
the payment to the bank was conditional. It merely shews that, having some
knowledge of a claim of lien which they may have deemed quite unfounded, the
civic officials, ex majori cautela, sought and obtained from the bank an
indemnity against the possibility of that claim turning out to be enforceable.
Failure to have done so in reliance upon their own belief, however firm, that
no lien in fact existed, or that the assignment to the bank, operating from the
date when the city had notice of it, gave its claim priority over that of the
plaintiffs, of which it received verbal notice only subsequently, might have
been deemed culpable remissness by those to whom the officials were
accountable. However mistaken that belief may have been, after the city had
paid over to the bank all the moneys in its hands owing to the contractor,
there was, in my opinion, no "sum owing by the owner to the
contractor" within the meaning of section 32.
With great respect for the learned judges who take the contrary
view, I am of the opinion that the judgment a quo involves a repeal of
the amendment of 1908 to section 32 which the legislature alone can effect. On
this branch of the case I agree with the learned Chief Justice of Alberta,
whose judgment,
[Page 156]
I think,
should be restored. The appellant should have its costs here and in the
Appellate Division.
Appeal allowed with costs.