Supreme Court of Canada
Ross v. The Queen (1895) 25 SCR
564
Date: 1895-12-09
John T. Ross and others (Supplants)
Appellants
and
Her Majesty The Queen (Respondent)
Respondent
1895: Oct. 1; 1895: Dec. 9.
Present:—Sir Henry Strong C.J., and
Taschereau, Gwynne Sedgewick and King JJ.
ON APPEAL FROM THE EXCHEQUER COURT OF
CANADA.
Contract—Public work—Final certificate of
engineer—Previous decision—Necessity to follow.
The Intercolonial Railway Act provides that
no contractor for construction of any part of the road should be paid except on
the certificate of the engineer, approved by the commissioners, that the work
was completed to his satisfaction. Before the suppliants’ work in this case was
completed the engineer resigned, and another was appointed to investigate and
report on the unsettled claims. His report recommended that a certain sum
should be paid to the contractors.
Held, per
Taschereau, Sedgewick and King JJ., that as the court in McGreevy v. The
Queen (18 Can. S.C.R. 371) had, under precisely the same state of facts,
held that the contractor could not recover that decision should be followed,
and the judgment of the Exchequer Court dismissing the petition of right
affirmed.
Held, per
Gwynne J. that independently of McGreevy v. The Queen the contractor
could not recover for want of the final certificate.
Held, per
Strong C. J., that as in McGreevy v. The Queen a majority of the
judges were not in accord on any proposition of law on. which the decision
depended, it was not an authority binding on the court, and on the merits the
contractors were entitled to judgment.
Appeal from
a decision of the Exchequer Court of Canada
dismissing the suppliant’s petition of right.
The circumstances of this case were precisely
the same as those in McGreevy v. The Queen. The
suppliants were contractors for construction of a portion of the Intercolonial
Railway, and before the work
[Page 565]
was Completed the
engineer, Mr. Sandford Fleming, resigned the position. Some time after Mr.
Shanly, C.E., was appointed by the Crown to investigate unsettled claims in
connection with the railway and report to the Government. He reported on the
claim of the suppliants, recommending payment to them of a certain sum, but
payment was refused, and in answer to a petition of right filed the Crown
contended that there was no final certificate of the engineer, approved by the
railway commissioners, as required by the Intercolonial Railway Act. The
Exchequer Court judge dismissed the petition, holding that he was bound by the
decision in McGreevy’s case. The suppliants appealed.
Stuart Q.C.
and Ferguson Q.C. for the
appellants. In McGreevy v. The Queen
the judges were not in accord on matters of law, and the decision does not bind
the court. See Stanstead Election Case;
Ridsdale v. Clifton.
The merits were fully discussed in the former
case, and we rely on the judgment of Strong J.
therein.
Hogg Q.C. for
the respondent, contended that the court could not but follow McGreevy v.
The Queen (1), and on the merits cited Cutter v. Powell; Munro
v. Butt.
THE CHIEF JUSTICE.—For the reasons stated in
my judgment in the case of The Queen v. McGreevy (1), a case
which involved precisely the same questions as those which are presented by the
appeal now before the court, I am of opinion that this appeal should be allowed
and judgment should be entered in the Exchequer Court for the suppliants.
[Page 566]
The case of The Queen v. McGreevy I do not
consider a binding authority for the reason that a majority of the judges
composing the court were not of accord on any proposition of law on which the
decision of the appeal depended. The late Chief Justice and Mr. Justice Gwynne
were of opinion that the certificate of Mr. Shanly was not the final
certificate of the chief engineer. My brother Taschereau, my late brother
Patterson and myself, in accord with the Exchequer judge, Mr. Justice Fournier,
were of opinion that the certificate of Mr. Shanly was the final and closing
certificate required by the contract. Mr. Justice Patterson, however, differing
from the members of the court who in other respects agreed with him, thought
that was not sufficient to entitle the suppliants to recover. Upon this latter
point there was no concordance of a majority of the court. Under these
conditions it is apparent that there was no agreement of a majority of the
court on any distinct proposition of law. Upon authority, therefore, I consider
the judgment in The Queen v. McGreevy (1) not to be a decision
binding upon me, inasmuch as the judgment of the majority of the court
proceeded upon no settled principle but upon different grounds.
I am, therefore, of opinion that the appeal
should be allowed and judgment entered in the Exchequer Court in favour of the
suppliants.
TASCHEREAU
J.—Whatever may have been the reasons given by each of the judges who
concurred in dismissing the suppliants’ claim in The Queen v. McGreevy
(1), the decision in that case is that upon a certificate such as the one
upon which the suppliants here rely, the Crown is not liable. By that decision
we are bound, and the appeal must be dismissed. It would
[Page 567]
be a blot on the
administration of justice in this country if the present appellants succeeded
upon a case precisely similar to that in which McGreevy failed.
GWYNNE J—Upon
the 26th day of October, 1869, two persons doing business together as
contractors in partnership under the name, style and firm of J. B. Bertrand and
Company, entered into a contract by deed with Her Majesty represented by the
Intercolonial Railway Commissioners appointed under the Dominion statute 31
Vic. ch. 13, for the construction of a portion of the Intercolonial Railway,
known as section nine of that railway, according to certain plans and
specifications annexed to and made part of the said contract.
Upon the 15th day of June, 1870, the same
contractors in like manner entered into a similar contract with Her Majesty for
the construction of another portion of the said railway known as section
fifteen thereof. By the said respective contracts the said contractors
covenanted with Her Majesty that the said section number nine should be finally
and entirely completed in every particular to the satisfaction of the said
commissioners and their engineer on or before the first day of July, 1871, at
and for the price or sum of $354,897 to be paid as in the contract for that
section was provided, being at the rate of $16,899.86 per mile of that section,
and that the said section number fifteen should in like manner be finally and
entirely completed to the satisfaction of the said commissioners and their
engineer on or before the first day of July, 1872, for the price or sum of
$363,520.59, to be paid as in the contract for that section was provided, being
at the rate of $30,000 per mile on that section. The said contractors by the
said respective contracts further covenanted with Her Majesty—
[Page 568]
That all the works should be executed and
materials supplied in strict accordance with the plans and specifications, and
to the entire satisfaction of the commissioners and their engineer, and that
the commissioners should be the sole judges of the work and material, and that
their decision on all questions in dispute with regard to the works or
materials, or as to the meaning or interpretation of the specifications or
plans, or upon points not provided for, or not sufficiently explained in the
plans or specifications, should be final and binding upon all parties. By
paragraph no. 3 of said respective contracts, it was covenanted that the times before
mentioned for the final completion of the works embraced in the respective
contracts should be of the essence of the said respective contracts, and that
in default of such completion on the respective days for that purpose limited
by the contracts the said contractors should forfeit all right and claim to the
sum or percentage by the said respective contracts agreed to be retained by the
commissioners, and also to any moneys whatever which at the time of such
failure of completion as aforesaid might be due or owing to the contractors;
and that the contractors should also pay to Her Majesty as liquidated damages
and not by way of fine or penalty the sum of two thousand dollars for each and
every week, and the proportionate fractional part of such sum for every part of
a week, during which the works embraced in the said respective contracts, or
any portion thereof, should remain incomplete, or for which the certificate of
the engineer approved by the commissioners should be withheld, and the
commissioners might deduct and retain in their hands such sums as might become
due for liquidated damages from any sum of money then due or payable, or to
become due and payable
[Page 569]
thereafter to the
contractors. By paragraph numbered 4 in the said respective contracts it was
provided that: The engineer should be at liberty at any time before the
commencement or during the construction of any portion of the work to make any
changes or alterations which he might deem expedient in the grades, the line of
location of the railway, the width of cuttings or fillings, the dimensions or
character of structures, or in any other thing connected with the works whether
or not such changes increased or diminished the work to be done, or the expense
of doing the same, and that the contractors should not be entitled to any
allowance by reason of such changes, unless such changes consisted in
alterations in the grades or the line of location, in which case the
contractors should be subject to such deductions for any diminution of work, or
entitled to such allowance for increased work, as the case may be, as the
commissioners might deem reasonable, their decision being final in the matter.
By paragraph 9 of the said respective
contracts it was declared that—
9. It was distinctly understood, intended and
agreed that the said prices or consideration of $354,897 in the one case and of
$363,520.50 in the other shall be and shall be held to be full compensation for
all the works embraced in or contemplated by the said respective contracts or
which might be required in virtue of any of the provisions of the same, or by
law, and that the contractors should not upon any pretext whatever be entitled
by reason of any change or addition made in or to such works, or in the said
plans and specifications, or by reason of the exercise of any of the powers
vested in the Governor in Council by the Act intituled, “An Act respecting the
construction of the Intercolonial Railway,” or in the commissioners or engineer
by the said respective contracts, or by law, to claim or demand any further
[Page 570]
or additional sum for
extra work or as damages or otherwise the contractors by the said respective
contracts expressly waiving and abandoning all such claims or pretensions to
all intents and purposes whatsoever except as provided in the fourth paragraph
or section of the said respective contracts.
By the eleventh paragraph or section of the
said respective contracts it was further mutually agreed upon by the parties
thereto—
11. That cash payments equal to 85 per cent
of the value of the work done approximately made up from the returns of
progress estimates should be made monthly, on the certificate of the engineer
that the work for or on account of which the sum should be certified had been
duly executed, and upon approval of such certificate by the commissioners; that
on the completion of the whole work to the satisfaction of the engineer a
certificate to that effect should be given but that the final and closing
certificate, including the 15 per cent retained should not be granted for a
period of two months thereafter; and that the progress certificates should not
in any respect be taken as an acceptance of the works or release of the
contractors from their responsibility in respect thereof, but that they, upon
the conclusion of the works, would deliver over the same in good order,
according to the true intent and meaning of the contract and of the
specifications annexed to and made part of the said contract.
The contractors proceeded with the
construction of the works under these contracts, and from time to time received
progress certificates from Mr. Fleming, the engineer of the commissioners, and
payment thereof, but they wholly failed to complete the respective works on the
days limited by the contracts for the completion thereof, namely, the section 9
on the 1st
[Page 571]
day of July, 1871,
and the section 15 on the 1st day of July, 1872, and in the spring of 1873, by
reason of such default continuing, the commissioners were obliged to take the
completion of the said works into their own hands, and did complete the same
under the terms of the contract at the cost of the Government.
The statement in the suppliants’ petition of
right in relation to this matter is thus stated by the suppliants in 23rd,
24th, 25th and 26th paragraphs of the petition of right.
23. The said J. B. Bertrand & Co., under
the aforesaid contract for section 9, had undertaken to finish and complete the
same on or about the first day of July, one thousand eight hundred and
seventy-one, and they did virtually complete the same on or about the month of
May, 1873, and if any delay occurred in the completion of the same it is
altogether attributable to the acts of the commissioners and engineers under
their directions, to the alterations made in the grades and line of location,
to changes in the works and to large quantities of extra and surplus work
imposed upon the said J. B. Bertrand & Co. and for which they cannot be
held responsible.
24. The said J. B. Bertrand & Co. under the aforesaid contract for
section 15, had undertaken to finish and complete the same on or about the 1st
day of July, 1872, and they did virtually complete the same on or about the
month of May, 1873, and if any delay occurred in the completion of the same it
is attributable to the acts of the commissioners and the engineers under their
direction—to the alterations made in the grades and line of location—to changes
in the works and to the large quantity of extra and surplus work imposed upon
the said J. B. Bertrand & Co., and for which they cannot he held
responsible.
25. That the said commissioners in the spring
of the year 1873, under misapprehensions and without any reasonable cause, and
at a time when a large amount of money was due to the said J. B. Bertrand &
Co. for work done, assumed control of the said works upon the said sections,
and without giving J. B. Bertrand & Co. any notice of their intention of so
doing in writing or otherwise as required by contract, paid out money so
belonging to the said J. B. Bertrand & Co. to some of the workmen on the
said works, which position the said J. B. Bertrand & Co. were forcibly
constrained to accept.
26. That in consequence of this action of the
commissioners the said J. B. Bertrand & Co. suffered great loss from the
fact that the said
[Page 572]
commissioners, after assuming control of the
works, expended unnecessarily large sums of money which would not have been
expended, and which the said J. B. Bertrand were not bound to expend, and which
were for works not contemplated nor included in the contracts, and it is
submitted that no portion of the same can be charged in deduction of the lump
sum mentioned in the contracts for sections 9 and 15.
The allegations in these paragraphs of the
petition are thus answered in paragraph no. 24 of the statement of defence
filed by Her Majesty’s Attorney General.
24. Her Majesty’s Attorney General in answer
to paragraphs 23,24, 25 and 26 of the said petition says that the contractors
having made default in the prosecution of the work required to be done under
the said contracts, the said commissioners in strict accordance with the
provisions of the said contracts and with the contractors’ assent, finding the
men employed by the contractors on the said sections of the said railway
unpaid, notwithstanding that up to that time the contractors had been paid more
than they were entitled to under the contracts, and finding the work upon the
said sections stopped, took the work into their own hands and proceeded to
complete the same in accordance with the terms of the said contracts; and the
said Attorney General denies that the default of the contractors in not
proceeding with their work upon the said sections was in any wise attributable
to the said commissioners or the engineer of the Government.
Now after the
completion of the work by the commissioners, and upon the first day of June,
1874, the said commissioners by force of an Act of the Dominion Parliament, 37
Vic. ch. 15, became fundi officio, and’ thereupon all the powers and
duties which had been vested in them became by the said Act transferred to and
vested in the Minister of Public Works, and by the Act it was enacted and
declared that all contracts entered into with the commissioners as such should
enure to the use of Her Majesty and should be enforced and carried out under
the authority of the Minister of Public Works as if they had been entered into
under the authority of an Act passed in the 33rd year of Her
[Page 573]
Majesty’s reign
entituled an Act respecting the Public Works of Canada.
Although the commissioners by this Act ceased
to have control over the contracts entered into with them for the construction
of the works contracted for by the above named contractors, their engineer, Mr.
Fleming, continued for several years to be the engineer in charge of the
Intercolonial Railway under the Minister of Public Works; and he could have
given to the contractors the certificate in the above 11th paragraph of their
contracts mentioned if they had by fulfilment of their contracts to his satisfaction
became entitled to such certificates; but he never did give to them and indeed
never could have given to them any such certificates within the terms of the
contracts in that behalf for, by the default of the contractors to complete the
works within the times in that behalf provided by the contracts, and the
commissioners having been obliged because of such default to take the works
from the contractors and to complete them themselves, the contractors by the
express terms of the above third paragraph of the contracts had absolutely
forfeited all claim to all sums which then remained due to them under their
contracts, and all claim to have a certificate given to them by the engineer to
the effect that they had completed the works in the contracts specified to his
satisfaction.
In the month of
September, 1875, all the rights, title, interest and demand of the said J. B.
Bertrand & Co. against the Government of the Dominion of Canada, arising
out of and connected with the construction of the said sections 9 and 15, were
duly transferred to a Mr. John Ross, since deceased, whose representatives the
present suppliants are. In the month of June, 1880, a Mr. Frank Shanly, C.E.,
was by an order in council dated the 21st June, 1880,
[Page 574]
appointed chief engineer
of the Intercolonial Railway “for the purpose (as stated in the order in
council) of investigating and reporting upon all unsettled claims in connection
with the construction of the line.” In the month of July, 1881, Mr. Shanly made
a report to the government in relation to a claim of J. B. Bertrand & Co.
in respect of their contracts for the said sections 9 and 15, and it is upon
this report that the claim of the suppliants is wholly rested, their contention
being that it constitutes the final and closing certificate of the engineer
given under the provisions of, and within the meaning of, the above quoted 11th
section of the contracts with the said J. B. Bertrand & Co., and that under
it the suppliants as representing J. B. Bertrand & Co. are entitled to
recover the amount mentioned therein as an amount due to J. B. Bertrand &
Co. under their contracts. Now without saying that in 1880, when Mr. Shanly was
so appointed chief engineer of the Intercolonial Railway, there may not have
been contracts in existence for work upon that railway in such a position that
Mr. Shanly could have given certificates as contemplated by, and provided for
in, the contracts for such work, it is in my judgment quite impossible to say
that his appointment “for the purpose of investigating and reporting upon all
unsettled claims in connection with the construction of the line” gave him, or
that any order in council could give him, authority to accept as completed, and
to certify as completed, by the contractors to his satisfaction works which,
like those on sections 9 and 15, had seven years previously been taken from the
contractors for default in fulfilment of their contracts, and had been
completed by the government through the said commissioners under the direction
of their engineer, Mr. Shanly’s predecessor, who alone was the person who could
have certified that the
[Page 575]
contractors had
completed the works contracted for, if they had completed them, to his
satisfaction as provided by the contracts. The language, of the order in
council appointing Mr. Shanly plainly, in my opinion, indicates that in a case
like the present Mr. Shanly could do no more than investigate and report to the
Government any circumstances attending the default of Messrs. J. B. Bertrand
& Co. in fulfilment of their contracts, which might appear to warrant the
Government, notwithstanding the forfeiture by the contractors of all right to
any payment under their contracts, in entertaining favourably and ex gratia any
claim preferred on behalf of the contractors, altogether apart from the
contracts, and this, in my opinion, is precisely what Mr. Shanly’s report in
relation to J. B. Bertrand & Co.’s contracts does, and nothing more
He reports, first,
that in May, 1873, neither of the sections was completed, and that the
commissioners then took the works into their own hands and finished them. He
then proceeds to say that he could find nothing to warrant, in a strict legal
point of view, a departure from the terms of the contracts, which provide for all
contingencies arising out of the increase or decrease of quantities shown in
the bill of works and schedule of prices upon which the contracts were based;
that it did not appear that the quantities were increased in the aggregate, but
on the contrary they were decreased.
He thus reports to
the government that the commissioners were justified in taking the works off
the contractors’ hands and in completing them themselves. Now, in this state of
facts, the contracts provided in the above third paragraph thereof, that the
contractors should forfeit all moneys whatsoever which at the time of their
failure of completion of the works as provided in the contracts should be due
or owing to them.
[Page 576]
The facts as above
reported also showed that nothing was claimed by or on behalf of the
contractors under the 4th paragraph of the contracts, and that being so, the
9th paragraph of the contracts expressly provided that upon no pretext
whatsoever should the contractors be entitled to claim or demand any sum in excess
of the respective above mentioned contract lump sums, for extra work or as
damages or otherwise howsoever,
the contractors hereby expressly waiving and
abandoning all such claims or pretensions to all intents and purposes
whatsoever except as provided in the fourth section of the contracts.
Having thus reported
and shown that the contractors had no claim under the terms of their contracts,
Mr. Shanly in his report proceeded to recommend an allowance in excess of the
lump sums agreed upon in the contracts to be made, namely, of $104,587 on
section 9, and of $127,600 on section 15. Of the lump sum or contract price
agreed upon for section 9, namely, $354,897, he reported that the contractors,
when the work was taken off their hands in May, 1873, had been paid $346,658,
leaving only a balance of $8,239 of the contract price for completion of that
work, and as to section 15 he reported that the contractors had been paid the
sum of $372,130, or the sum of $8,610 in excess of the contract price agreed
upon for that section, and adding the $8,239 to the $104,587, making $112,816,
he recommended that this sum should be allowed by the government on section 9,
and deducting the above $8,610 from the $127,° 600 recommended in excess of the
contract price of section 15, making the sum of $118,990, he recommended should
be allowed on section 15. These sums he recommended should be allowed, not as
being due under the contracts for his report clearly shows they were not, but
because the evidence furnished to him disclosed great difficulties and cost
incurred by the contractors in carrying out the heaviest portions of the
[Page 577]
work, and he closes
his report by saying that he thought the increased amounts he recommended would
be equitable to the contractors and to the Government; that he thought that if
the Government should adopt his recommendations the contractors would have a,
reasonable profit and that the Government would have full value for its money.
I confess that I am
utterly unable to understand how these sums so recommended can be claimed to be
sums recoverable under the terms of the contracts or how Mr. Shanly’s report
can be claimed to be a certificate within the meaning of the 11th paragraph of
the contracts.
The appeal must in
my opinion be dismissed with costs.
As it was argued
that in a case of McGreevy v. The Queen where a
similar question arose there was not a concurrence of a majority of the court
in the reasons upon which the judgment in that case was founded and that it
therefore should be considered an open question I have thought it best, without
entering into any question as to the correctness of that argument, to state
anew my views in this case irrespective of the judgment in that case, the court
being now differently constitute
SEDGEWICK J.—I am of opinion that in this case it
is our duty to follow the decision* of this court in McGreevy v. The
Queen (1). I am also of opinion that although Mr. Shanly was an engineer
capable of giving the certificate required by the statute yet the documents
relied on as such certificate did not come up to the requirements of the Act.
It was. not, nor was it intended to be such a certificate.
[Page 518]
KING J.—I am of opinion that in this case we
should follow the decision of the court in McGreevy v. The Queen.
Appeal dismissed with costs.*
Solicitors for the appellants: Pentland & Stuart.
Solicitors for the respondent: O’Connor & Hogg.