Supreme Court of Canada
McCarron v. McGreevy, (1886) 13 SCR 378
Date: 1886-05-06
CHARLES MCCARRON et al (PLAINTIFFS)
Appellants;
And
THOMAS MCGREEVY (DEFENDANT)
Respondent.
1886: March 19; 1886: May 6
Present Sir W.
J. Ritchie C.J. and Strong, Fournier, Henry and Taschereau JJ.
ON APPEAL FROM THE COURT OF QUEEN'S BENCH FOR LOWER CANADA
(APPEAL SIDE).
Railway contract — Certificate of engineer-Necessity for
Laches.
McC et al. appellants entered into a contract with
McG., (respondent) the contractor for the construction of the North Shore
Railway between Montreal and Quebec to do and perform certain works of
construction on a portion of the road and by a clause in his contract agreed
" to keep open at certain times and hours at his own cost and expense the
mainline for the passage of traffic or express trains run by McG. without any
charge to the latter:" but there was a proviso that, "any time
occupied on the road over and above what may be required by the hours
hereinbefore mentioned, or any expense caused thereby, shall be paid by the
contractor (McG.) on a certificate to that effect signed by the superintendent
of the contractor,"
[Page 379]
On an action brought by appellants against respondent for
damages caused by the interruption of the work on said road by the passing of
respondent's trains ;
Held, affirming the judgment of the court below, that
it was the duty of the appellants to get the superintendent's certificate
within a reasonable time, and not having taken any steps to obtain it until six
years after the superintendent had left the respondents' employment, the
failure to produce such certificate was sufficient ground for dismissing the
appellants action.
APPEAL from a
judgment of the Court of Queen's Bench for Lower Canada (appeal side) () reversing the
judgment of the Superior Court in favor of the present appellants.
The respondent
was the contractor for the construction of the North Shore Railway between
Quebec and Montreal under a contract with the Provincial Government, and on the
30th March, 1877, by notarial instrument entered into before Samuel J.
Glackmeyer, notary public, between the appellants' and the respondent, the
appellants undertook, in consideration of the payments and covenants stipulated
in the said notaries instrument, to finish the track laying and ballasting for
the respondent on the said North Shore Railway from Quebec to Portneuf, and as
far beyond as " Patton's
Contract shall begin, " and also to do and performing all the works, more
particularly detailed in the schedule annexed to the said agreement, for the
prices therein detailed.
Prior to the
bringing of their present action the appellants had sued the respondent for the
sum of $37,000, alleged excess of work done by them and damages they claimed to
have suffered.
In that suit
judgment was rendered against the respondent for $15,423, reserving to
appellants their recourse, if any, for an item of $5,290 on the ground that
they had not produced the certificate of the respondent's superintendent, as
required by the contract.
The present
action was brought in the Superior
[Page 380]
Court at
Quebec, by the present appellants against the respondent, to recover the sum of
$7,970, $5,890 for the amount reserved, and $2,680 for alleged damages caused
to the appellants by the interruption of the work upon their section by the
passing in excessive numbers and at irregular intervals of appellants' trains.
The declaration alleged that since the contract was completed the plaintiffs
had demanded a certificate from one D D. MacDonald, the superintendent
mentioned in the contract, but that the tatter, at the instigation of
respondent, had unjustly and fraudulently refused to deliver said certificate.
The other
material facts and pleadings fully appear in the report of the case in 12 Q. L R.
p. 373.
The ninth
paragraph of the contract is the only one upon which any controversy between
the parties arose, and is as follows :—
Ninth. The said
parties of the first part agree and bind themselves to furnish at their own
costs and charges all labor and material to work the locomotive and cars; such
as water, wood, oil, tools and implements of all kinds, except as otherwise
stipulated, •but that they will not have or exercise any control over the
movements of trains except of those in use for track-laying and ballasting; on
the contrary, will in all such movements be subject to the orders of the party
of the second part. They shall also keep open at their own costs and charges
the main line for the passage of traffic or express trains run by the said
party of the second part, and all turnouts, sidings and switches, as well as
the road bed, shall be kept in project order for said traffic, and they will
see that their trains are kept off the main line at the hours appointed by the
timetable at the respective places, without any charge to the said party of the
second part.
Nothing herein
contained shall compel the party of the first part to take any precautions or
means provided for passage of trains, . except a train leaving Pont Rouge at or
before seven o'clock in the morning, and Quebec at or after five o'clock and
forty-five minutes in the afternoon; all special or trains required at
different hours will be arranged for with the party of the first part and with
their consent; any time occupied on the road over and above what may be
required by the hours herein before mentioned and stipulated, or any expense
caused thereby, shall be paid by party of the second part, on a certificate to
that effect signed by the superintendent of
[Page 381]
the party of the
second part.”
Larue Q.C. for appellants.
The appellants
were entitled, under their contract to charge for every train that went beyond
Pont Rouge, even the regular train, and they had also a right to charge for
every train between Quebec and Pont Rouge, except a train leaving Pont Rouge at
or before seven o'clock in the morning, and Quebec at or after five o'clock and
forty-five minutes in the afternoon.
The passage of
all these trains imposed upon the appellants a very large increase of wx)rk not
included in their contract.
On behalf of
the respondent it is contended that the appellants cannot claim from the
respondent without a certificate of the superintendent, and that they could not
demand nor obtain said certificate after the works were finished, or after the
superintendent had left McGreevy's employ. We did all we could to obtain it,
and we cannot be held responsible for the neglect of duty of respondent's
employee.
Such an excuse
cannot be held sufficient to enable the respondent to get rid of a legitimate
debt.
Redfield Amer.
Rly. Gas. ();
Scott v. Liverpool ().
Irvine Q.C. for respondent.
It cannot be
held that this is any such demand on the superintendent, Macdonald, for a
certificate as would excuse the appellants from making the proof which the
contract required of them. Macdonald could not be expected after that lapse of
time, and whilst engaged in other work at a great distance from the place
referred to in the contract, to certify to work of which he could then have had
only a very imperfect recollection. No demand had ever been previously made
upon him for such certificate, although an action had been brought and had been
pending for a number of years covering these same items. The requirement of
this certificate is peremptory, and no action can be maintained without
[Page 382]
it and indeed
it would not be possible for the respondent otherwise to obtain reliable
information as to claims of this nature.
The greater
part of the appellant’s claim is in the year 1878. Their contract binds them to
complete the works in 1877. There is nothing in the record to show on what
terms the time was extended, or whether it was extended at all otherwise than
by tacit consent. The right of the respondent to use the railway for the
running of his trains without compensation to the appellants, could not be
taken away without some express agreement.
Lastly:—The
respondent refers the court with confidence to the evidence, and asserts that
there is no proof whatever to justify the appellant's demand. There is no evidence
of any particular detention causing any particular damage. The majority of the
special trains of which complaint is made were run on Sundays, when presumably
the appellants were not at work. Others were run at night, and generally there
is no particular case shown causing damage to the appellants. This absence of
proof without any attempt within any reasonable period to obtain the
certificate of the superintendent should be sufficient to dismiss the
appellants' action
SIR W. J. RITCHIE C.J. —There is a very small
question in this case. To enable the plaintiff to recover he was bound to
produce the certificate of the engineer as 9th the correctness of his accounts.
He never obtained these certificates nor did he attempt to obtain them until
years afterwards when the party had left the employment and then he did not
take, even at that time what I should consider the necessary steps to enable
him to get the certificate
Therefore I
think the plaintiff in the suit cannot recover, and in looking at the evidence
even if I thought he could recover, I should be greatly puzzled
[Page 383]
to determine,
if any amount, how much. I think the appeal should be dismissed.
STRONG J.—Concurred.
FOURNIER J. I
think the appeal should be dismissed. I agree with the judgment of the Court of
Queen's Bench. The evidence shows that during all the time the work was going
on the plaintiff never made any effort to obtain the certificate of the
engineer and six years afterwards they ask him for it when they are told that
it cannot be supplied. I certainly think they have not complied with the
condition and they have, therefore, no claim against the defendant.
HENRY J.—The
parties appellant in this case cannot, I think, succeed on their appeal. When a
party is to receive compensation consequent on the certificate of a certain
engineer, it is to be assumed that the certificate will be obtain l within a
reasonable time that is when the party is employed and when the work is going
on, and that a person should not wait five or six years when the memory of the
engineer cannot be expected to serve him. Here were men making a claim for
damages they claim to be entitled to several veers before any claim was made by
them. If their right to recover depends upon a certificate they cannot sustain
the claim by other evidence without production of that certificate. I think the
court below was perfectly right and this appeal should be dismissed.
TASCHEREAU J.—I
am of the same opinion, and I also think that this is a frivolous appeal.
Appeal dismissed with costs.
Solicitors
for appellant: Larue, Angers and Casgrain.
Solicitor
for respondent: George Irvine.