Supreme Court of Canada
The Queen v. Starrs (1889) 17 SCR
118
Date: 1889-12-14
Her Majesty The Queens (Defendant)
Appellant
And
Michael Starrs, John Herbert and John
Lawrence Power O'Hanly (Claimants)
Respondents
1889: May 23; 1889: Dec. 14.
Present: Sir W. J. Ritchie C.J. and
Fournier, Taschereau, Gwynne and Patterson JJ.
APPEAL FROM THE EXCHEQUER COURT OF CANADA.
Contract—Claim against
Government—Certificate of engineer—Condition precedent—Arbitration—31 V. c. 12.
S. et al. made a contract with Her Majesty the Queen, represented by the
Minister of Public Works, for the construction of a bridge for a lump sum.
After the completion of the bridge a final estimate was given by the chief
engineer, and payment thereof made, but S. et al. preferred a claim for
the value of work, not included in such final estimate, alleged to have been
done in the construction of the bridge, and caused by changes and alterations
ordered by the chief engineer of so radical a nature as to create, according to
the contention of the claimants, a new contract between the parties.
Held,
reversing the judgment of Henry J. in the Exchequer, Fournier J. dissenting,
that the engineer could not make a new contract binding on the crown; that the
claim came within the original contract and the provisions thereof which made
the certificate of the chief engineer a condition precedent to recovery, and
such certificate not having been obtained, the claim must be dismissed. The
Crown having referred the claim to arbitration instead of insisting throughout
on its strict legal rights, no costs were allowed.
Appeal from a judgment of the Exchequer Court
of Canada (Henry J.),
setting aside the award of the
official arbitrators, and allowing the respondents (claimants) the sum of $11,393.71,
The claim in this case arose out of a
contract for constructing a bridge across the Ottawa River at Des Joachims, for the lump sum of $25,300. The
bridge
[Page 119]
was completed by the
respondents in the summer of 1885, and in the month of August of that year, the
chief engineer of the Department of Public Works made out and certified, under
contract, the final estimate of the contractors in respect to the work on the
bridge at $41,896.50, and the balance due upon that certificate was paid to the
respondents in October of the said year of 1885.
The respondents after the completion of the
bridge presented a claim to the Department of Public Works, claiming the sum of
$81,100.17 as the value of the work done by them, alleging that the chief
engineer had made such radical changes in the plan of the work that the
original contract was virtually superseded and they requested the department to
recommend to the Government of Canada the payment of this sum, after deducting
the amount of the said final certificate of $41,896.50, and they asked that in
the event of their claim not being so entertained and paid it should be
referred to the board of official arbitrators for their award, and on or about
the 29th day of December, 1885, the said claim was duly referred by the said Department
of Public Works to the board of official arbitrators for investigation and
award.
The claim was heard by the said arbitrators
in the month of November, 1886, when evidence both on the part of the claimants
and the crown was submitted, and on the 8th day of December following the
arbitrators made and published their award in the matter.
The award as made by the arbitrators was for
the sum of $44,279.
The contractors not being satisfied with the
award as made appealed therefrom to the Exchequer Court of Canada, and by their
notice of appeal they in effect asked the court to declare that the sum awarded
by the official arbitrators, was a balance due them by the crown in respect to
the said bridge works, after deducting all previous payments made to them, and
they
[Page 120]
asked to have the
award amended in such manner as to carry into effect their request that the
amount awarded should be declared a balance due to the contractors over and
above all payments already made.
A cross-appeal was taken on behalf of the
crown by which it was contended that the claimants were not entitled to be paid
any sum upon their claim, and that it was clear that the amount awarded was
intended to be, and was in fact, in full payment and satisfaction of all the
work performed on the bridge, and that from the said sum so awarded should be
deducted all payments previously made to the contractors, which would leave the
amount the arbitrators intended to award to be the sum of $2,382.50, and in support
of the latter contention the arbitrators filed affidavits, stating in effect
that their intention was that the award was in full of all work done by the
contractors on the bridge works, from which was to be deducted the amount of
the chief engineer's certificate, leaving the balance only to be paid to the
respondents.
The appeal and cross-appeal came on for
hearing in the Exchequer Court before His Lordship Mr. Justice Henry, when His
Lordship stated that he would in the first place hear argument upon the
question of the validity of the award which was then proceeded with, and on a
subsequent day His Lordship gave his judgment setting aside the award, and he
then announced that the case being open he would hear arguments on the whole
case and dispose of it on the evidence in the same manner, and as if no award
had ever been made, and such argument having taken place judgment was reserved,
and on the 10th day of October, 1887, His Lordship rendered his judgment, by
which he ordered and adjudged that Her Majesty should pay to the respondents
the sum of $11,393.71 in full of all claims against the crown.
[Page 121]
From this judgment Her Majesty appealed to
this court, and contended that the said judgment was not warranted by the
evidence in the case or the law respecting it.
The respondents filed notice of cross-appeal.
The principal clauses of the contract are the
following:—
4. That the several parts of the contract
shall be taken together, to explain each other, and to make the whole
consistent; and if it be found that anything has been omitted or mis-stated
which is necessary for the proper performance and completion of any part of the
work contemplated, either in the drawings hereinbefore referred to or the
specification hereunto annexed, the explanation and interpretation given by the
Chief Engineer shall be received and shall be final, binding and conclusive
upon the contractors, and the contractors will, at their own expense, execute
the same as though it had been properly described, and the correction of any
such error or omission shall not be deemed to be an addition to or deviation
from the works hereby contracted for.
5. The engineer shall be at liberty at any
time either before the commencement or during the construction of the works or
any portion thereof, to order any extra work to be done and to make any changes
which he may deem expedient in the dimensions, character, nature, location or
position of the works or any part or parts thereof, or in any other thing
connected with the works whether or not such changes increase or diminish the
work to be done or the cost of doing the same, and the contractors shall
immediately comply with all the written requisitions of the engineer in that
behalf, but the contractors shall not make any change in or addition to, or
omission or deviation from the works, and shall not be entitled to any payment
for any change, addition, omission, deviation or any extra work, unless such
change, addition, omission, deviation, or any extra work shall have been first
directed in writing by the engineer, and notified to the contractors in
writing, nor unless the price to be paid for any addition or extra work shall
have been previously fixed by the engineer in writing, and approved of by the
Minister of Public Works for the time being, and the decision of the engineer
as to whether any such change or deviation increases or diminishes the cost of
the work, and as to the amount to be paid or deducted, as the case may be, in
respect thereof, shall be final, and the obtaining of his decision in writing
as to such amount shall be a condition precedent to the right of the
contractors to be paid therefor. If any such change or alteration constitutes,
in the opinion
[Page 122]
of the said engineer, a deduction from the
works, his decision as to the amount to be deducted on account thereof shall be
final and binding.
6. That all the clauses of this contract
shall apply to any changes, additions deviations or extra work, in like manner,
and to the same extent as to the works contracted for, and no changes,
additions, deviations or extra work shall annul or invalidate this contract.
7. That if any change or deviation in or
omission from the works be made by which the amount of work to be done shall be
decreased, no compensation shall be claimable by the contractors for any loss
of anticipated profits in respect thereof.
8. That the engineer shall be the sole judge
of work and material in respect of both quantity and quality, and his decision
on all questions in dispute with regard to work or material, or as to the
meaning or intention of this contract and the plans, specifications and
drawings shall be final, and no works or extra or additional works and changes
shall be deemed to have been executed, nor shall the contractors be entitled to
payment for the same unless the same shall have been executed to the
satisfaction of the engineer, as evidenced by his certificate in writing, which
certificate shall be a condition precedent to the right of the contractors to
be paid therefor.
25. Cash payments equal to about ninety per
cent. of the value of the work done, approximately made up from returns of
progress measurements and computed at the prices agreed upon or determined
under the provisions of this contract, will be made to the contractors monthly
if practicable, on the written certificate of the Engineer that the work for,
or on account of which the certificate is granted, has been duly executed to
his satisfaction, and stating the value of such work computed as above
mentioned, and upon approval of such certificate by the Minister of Public
Works for the time being for the Dominion of Canada, and the said certificate
and such approval thereof shall be a condition precedent to the right of the
contractors to be paid the said ninety per cent. or any part thereof. The
remaining ten per cent. shall be retained till the final completion of the
whole work to the satisfaction of the chief engineer for the time being, having
control over the work, and within two months after such completion the remaining
ten per cent. will be paid. And it is hereby declared that the written
certificate of the said Engineer certifying to the final completion of said
works to his satisfaction shall be a condition precedent to the right of the
contractors to receive or be paid the said remaining ten per cent., or any part
thereof.
26. It is intended that every allowance to
which the contractors are fairly entitled will be embraced in the Engineer's
monthly certificates; but should the contractors at any time have claims of any
description
[Page 123]
which they consider are not included in the
progress certificates, it will be necessary for them to make and repeat such
claims in writing to the engineer within fourteen days after the date of each
and every certificate in which they allege such claims to have been omitted.
27. The contractors in presenting claims of
the kind referred to in the last clause, must accompany them with satisfactory
evidence of their accuracy, and the reason why they think they should be
allowed. Unless such claims are thus made during the progress of the work,
within fourteen days, as in the preceding clause, and repeated in writing every
month, until finally adjusted or rejected, it must be clearly understood that
they shall be forever shut out, and the contractors shall have no claim on Her
Majesty in respect thereof.
34. It is hereby agreed that all matters of
difference arising between the parties hereto, upon any matter connected with,
or arising out of this contract, the decision whereof is not hereby specially
given to the Engineer, shall be referred to the award and arbitration of the
Chief Engineer for the time being having control over the works, and the award
of such engineer shall be final and conclusive; and it is hereby declared that such
award shall be a condition precedent to the right of the contractors to receive
or be paid any sum or sums on account or by reason of such matters in
difference.
35. It is distinctly declared that no implied
contract of any kind whatsoever, by or on behalf of Her Majesty, shall arise or
be implied from anything in this contract contained, or from any position or
situation of the parties at any time, being clearly understood and agreed that
the express contracts, covenants and agreements herein contained and made by
Her Majesty, are and shall be the only contracts, covenants and agreements upon
which any rights against her are to be founded.
Hogg Q. C.,
for appellant.—The only contract that could be made binding on Her Majesty for
such a work as the construction of this bridge, is a contract made in pursuance
of the 7th section of the Public Works Act, 31 Vic. ch. 12, which must be "signed and sealed by "the Minister of
Public Works or his deputy and "countersigned by the secretary," and
the contract of the 8th September, 1882, was so executed, so that the contract
which the suppliants say superseded the contract of the 8th day of September,
1882, could not, if it
[Page 124]
ever had any
existence, be binding upon Her Majesty. Wood v. The Queen; O'Brien
v. The Queen.
Under the provisions of the contract, the
court would have no power to order payment of any sum beyond what the engineer
had certified. Emden on building contracts,;
Jones v. The Queen.
By the 35th clause of the contract, no implied contract can in any way arise
between the respondents and the crown in respect to the work. It is therefore
quite plain, that the only contract binding on either party, is the contract of
the 8th September, 1882. See O'Brien v. The Queen; Sharpe
v. San Paulo Ry Co..
However, the evidence shows that the
respondents have been liberally paid for all the work done by them upon the
bridge, both as regards the work alleged to have been contracted for, and the
extra or additional work caused by changes and alterations in the designs and
works as finished.
O'Gara Q. C.
for respondents.—The plans and the evidence show there was a radical difference
between the bridge contracted for by the contract made in 1882, and the one
actually built, and the fact of the department accepting the work and, when the
respondents put in their claim, agreeing to refer the matter to arbitration, is
evidence that the written contract was set aside.
But it is now urged that the respondents
should get nothing. 1st. Because there was no contract in writing between the
respondents and the Minister authorizing the work or changes. 2nd. There is no
certificate of the Government engineers allowing the amount.
By the Public Works Act, 31 Vic. ch. 12, secs. 10 and 15, Parliament has entrusted to the Minister of Public
[Page 125]
Works the absolute
control of the erection of bridges, &c. 35 Vic. ch. 24, sec. 1, again repeats this.
42 Vic. ch. 7, sec. 4, divides the Public Works Department into two
departments—Railways and Canals and Public Works—and sec. 5 defines their
duties, and to the latter department is again given the absolute jurisdiction
to erect bridges, &c.
Sec. 10 defines the duties of the chief
engineer, &c.
The Minister of Public Works having by these
acts the absolute authority to undertake the work, the provisions in the
subsequent sections of these acts are only for the guidance and direction of
the Minister himself. They cannot take away the power conferred by the previous
clauses.
As regulations for the working of the
department they do not affect the outside public, and even if they did, they
could be waived, as they were in this case: 1° by the conduct of the
department, the chief engineer and the Minister, in making payments on account
of the work from time to time.
2nd. By the Minister and chief engineer
advising an arbitration.
3rd. By the order in council referring to
arbitration.
4th. By the letter of the department
enclosing the account to the arbitrators.
See Park Gate Co. v. Coates, which
shows that negative words in a statute do not take away a power conferred by a
prior clause, and that the provisions contained in these negative clauses are
only directory and may be waived.
Sec. 20 of ch. 12, 31 Vic. provides that tenders are to be always invited unless
there is a pressing emergency.
Sec. 6 defines the duty of the chief
engineer.
[Page 126]
Sec. 34 provides for the reference of
disputed claims to arbitration.
Sec. 36. No arbitration is allowed where it
is the duty of the Minister or of the engineer to determine the matter themselves.
The statutes do not declare that there is to
be no claim for work done unless there is a writing executed by the Minister.
Sec. 7. No deeds, contracts, documents, or
writing shall be deemed to be binding, &c., unless executed in a certain
way. The word "contract" in that section means, from the context in
which the word is found, a writing of some kind on which it might be sought to
enforce some claim as for the breach of an executory contract.
That clause does not apply here, as this
claim is not brought for a breach of an executory contract.
The claim being for work done and accepted
the Government is liable, because:
1st. The certificate of the engineer is not
necessary. The work is not done under the old contract, and the new agreement
made did not require a certificate.
2nd. The Government engineer, by his
certificate of the 5th January, 1885, had certified the value of the work to
the department to be $39,000, and having thus, previously to all the work being
done, bound himself to a particular sum, with the knowledge and at the request
of the department, he has become unfit to act as an unbiassed judge. Kimberley
v. Dick,
Kemp v Rose.
3rd. Even if the old contract applied, it was
waived by the department by the reference to arbitration. See Parke Gate Co.
v. Coates.
4th. As by section 36 of ch. 12, aforesaid, no arbitration
[Page 127]
can be allowed where it is the duty of the Engineer or Minister to
settle the matter, the allowance of the arbitration by the Minister and
Government shows conclusively that the Government and the Minister and his
agents did not consider that any certificate was required, or that it was the
duty of the Minister to give a final certificate, otherwise they would, by
permitting an arbitration, be violating the statute itself, which must not be
supposed or should not be urged on their behalf.
5th. The chief engineer, moreover, shows in
his evidence that he made out his prices without ever seeing the work, making
any inquiries as to the value of materials there, the difficulties of the
place, &c., all which showed such gross carelessness and disregard of the
rights of the respondents as to amount to fraud, and such misconduct renders
him unfit to be an umpire.
6th. The chief engineer, in giving his
estimate, disregarded the contract, calculating the price of the works at a
scale of prices fixed by himself according to measurements, and not the
contract price.
The respondents then should be allowed to
recover, and the amount they are entitled to is a matter of detail, and a final
certificate is not required.
When the case was before Mr. Justice Henry in
the Exchequer Court that learned judge only allowed the respondents for their
expenditure and $3,000 for loss of time.
On the cross-appeal, I submit that the
claimants should be allowed for their work the prices established, namely:
$61,905.85 for the bridge as it stands, and $18,195.22 for their other claims,
which they incurred by reason of the changes and the instructions from time to
time given to them by the officers of the Department of Public Works.
[Page 128]
Hogg Q.C., in
reply, referred to sec. 41 of the Public Works Act, 31 Vic. ch. 12, which provides, that "in
"awarding upon any claim arising out of any contract "in writing, the
arbitrators shall decide in accordance "with the stipulations in such
contract, and not award "compensation to any claimant on the ground that
he "expended a larger sum of money in the performance "of his
contract than the amount stipulated therein;" and pointed out that while
the amount stipulated in this contract was the sum of $25,300, that sum was
increased by reason of extra work caused by changes and alterations in the
character of the structure, to the sum of $41,896.50, which latter sum must be
taken under the provisions of this section to be the amount stipulated in the
contract.
Sir W. J. RITCHIE C.J., after stating the
facts as hereinbefore set out, proceeded as follows:—
The claimants in
this case claim that the position of the bridge contracted for was changed and
that radical changes were made in the plan of the bridge. There is no doubt
that the position of the bridge was changed and that great changes and
alterations took place in the character and nature of the works, but it was in
consequence of these changes and alterations that the chief engineer made out
under the requirements of the contract a final certificate and allowed the
contractors $41,896.50 instead of $25,300.
It has been
contended that the engineer and contractors had altered the original contract,
in fact, had put it aside and that there was a new contract. But neither the
engineer nor contractor could put an end to the contract and make a fresh
verbal contract binding upon the crown. The work clearly was done under the
contract and it must be governed by the provisions of the contract.
[Page 129]
As to the contention
that there was an implied contract, there is an express provision declaring
that there could be no implied contract. The contract that binds the parties is
that of the 8th September, 1882, and under that contract the engineer's
certificate is indispensable. These clauses 4, 5, 6, 7, 8, 25, 26, 27, 34 and
35 cannot be got over, and the final estimate and certificate having been paid,
the contractors can have no further claim.
The only objection
the crown appears to have raised in the first instance to the award was that
the amount of the certificate, $41,896.50, should be deducted from the amount
awarded by the arbitrators $44,279.32, leaving a balance of $2,382.82. The
contractors claimed that the award was in addition to the certificate and the
crown claimed that the payment of the certificate should be deducted, leaving
the above amount $2,382.82. Had this been acquiesced in by the contractors, in
all probability the controversy would have been at an end. Had the crown
intended to rely on its strict legal rights, as it has done throughout this
case, this matter should never have been sent to the arbitrators, for in such a
case there was nothing for the arbitrators to adjudicate on, and this reference
caused all the subsequent litigation. If the circumstances could have permitted
me to come to the relief of the respondents, I should have been disposed to
allow the contractors the balance of $2,482.82, but the crown insisting on its
strict legal rights I am bound to give them. While conceding to these rights
which we are bound to do, we can only mark our disapproval of this reference,
in consequence of which these claimants have been put to the enormous expenses
of this litigation, by depriving the crown of costs in any of the courts.
[Page 130]
FOURNIER J.—En 1882, les intimés ont contracté à forfait avec le département des Travaux
Publics pour la construction d'un pont sur l'Ottawa au-dessus de Pembroke, aux rapides des Joachims, pour le prix de $25,300.
Le pont devait être en bois,
construit dans un endroit spécifié, avec deux culées, six piliers et sept
arches (spans), suivant certains plans et spécifications.
Dans l'hiver suivant,
les intimés se procurèrent à grand frais les matériaux nécessaires. Ils se
préparaient à commencer l'ouvrage dans le mois d'avril suivant, lorsque le
département, à la demande des intimés, envoya sur les lieux un ingénieur pour
localiser l'endroit des piliers et des culées du pont. Cet ingénieur constata
que l'endroit choisi par l'ingénieur Austin employé à cet effet
par le département ne convenait aucunement et que les plans et spécification
qu'il avait faits ne pouvaient nullement servir à cette construction, et il en
fit rapport à l'ingénieur-en-chef, qui, avec l'appropation du département, les
changea tellement qu'il fallut faire une construction tout à fait différente de
celle originairement projetée et beaucoup plus coûteuse.
De nouveaux plans et
spécification furent donnés aux intimés par Perley, l'ingénieur-en-chef, avec
instruction de s'y conformer dans la construction du nouvel ouvrage—les prix
des ouvrages devant être déterminés plus tard. En conséquence de ce nouvel
arrangement, les con tracteurs se mirent à l'œuvre et
s'acquittèrent avec diligence de la tâche qu'ils avaient ainsi acceptée.
Plusieurs témoins,
ainsi que l'ingénieur Perley, prouvent que tel a été l'arrangement pour la
construction du pont après que le contrat originaire et les premiers plans et
spécification eurent été mis de côté. Si les intimés eussent insisté sur
l'exécution des ouvrages du premier contrat, comme ils en avaient le
[Page 131]
droit, le gouvernement ne pouvait les faire exécuter
à cause de l'imperfection des plans et spécification, et aurait eu, dans ce
cas, des dommages à leur payer.
C'est alors que sur les
représentations des officiers du département, ils renoncèrent à ce premier
contrat et s'engagèrent, à la demande de l'ingénieur-en-chef, à construire un
pont d'après des nouveaux plans et spécification qui devaient leur être
fournis. L'ouvrage a été fait conformément à ces nouveaux plans et
spécification, et leur présente demande a pour objet d'être payés de la balance
qu'ils réclament comme leur étant due sur la valeur de ces ouvrages.
La construction qu'ils
ont eu à faire est essentiellement différente de celle mentionnée au premier
contrat. Hamel, l'ingénieur qui a fait les nouveaux plans, ceux qui ont été
exécutés, dit à ce sujet:—
There was evidently an error in the original plans. In September, 1883, I got orders to change
the site of the piers. I found original plan would not do.
Perley dit:
In August, 1883, difficulty as to finding
centre line, I got Austin to go and pick up centre line and the work proceeded.
When we found that Austin's soundings, were wrong we took fresh soundings and
revised the bridge and readjusted the spans to suit the altered circumstances.
I never saw the work, but I was in the locality before the work was begun. The
contractors were paid the progress estimates as the work went on. I never had
such radical changes as there was in this contract. Before making out my final
estimate, I asked the contracture for a detailed statement of their claim, but
I did not get it before making final estimate.
O'Hanly, l'un des intimés qui est lui-même
un ingénieur civil, dit en parlant de ces
changements:
The whole thing was changed. There was a new location of the piers and abutments,
the lengths of the spans and the number of the spans. The result was to put the
piers in a much greater depth of water than the original.
Being asked to specify the depth, he answers:
Where there was five feet of water shown on
the plan, there was 20
[Page 132]
feet. Of course the bottom was very irregular
at the time. I have soundings of the whole to show.
Il est inutile d'entrer dans le détail des différences entre les deux plans de
construction de ce pont, les différences sont bien établies par la preuve et
mentionnées en détail dans l'exhibit du dossier. Elles sont tellement
considérables qu'après les avoir indiquées spécialement, l'ingénieur Bell,
employé du département dit:
They bear a certain resemblance to each other. They are both made of wood, but they are
different structures.
Q. You could not, in other words, take out of
the second plan the first one, say so much is extra and so much is according to
the original plan.
Oh, no.
La difference dans le coût des deux plans est également
donnée et elle est beaucoup plus élevée dans le deuxième (celui qui a été
exécuté) que dans le premier.
En conséquence de ces
changements, il était absolument impossible d'exécuter le premier plan
conformément au contrat. Le délai pour son exécution était même expiré et le
contrat avait cessé d'exister lorsque les nouveaux plans et spécification pour
l'ouvrage exécuté, ont été fournis aux intimés.
Dans cette situation
d'affaire, l'intimé O'Hanly s'adressa à M. Perley, l'ingénieur-en-chef, pour
connaître d'après quel arrangement se ferait l'ouvrage du deuxième plan. Voici
comment il rapporte ses entretiens à ce sujet avec Perley:
Q. What did you say to
him?
A. I said to Mr. Perley, everything being
radically changed there was not a shred left of the original design: and I
asked him now as we had neither plans nor anything to guide us whether we would
have a written order for everything we did.
Q. What did Mr. Perley say?
A. Mr. Perley said that the whole design
having been entirely recast and radically changed altogether, that now, to go
on and do whatever we were ordered verbally or otherwise.
[Page 133]
Q. And leave the prices to be settled
afterward?
A. There was nothing said about prices; but I
wanted to know how we stood, and this is the answer I got.
By Mr. Cowan.
Q. Repeat it.
A. That work having been entirely changed,
and everything in connection with it re-cast, and the designs being set aside,
and no designs being yet ready, we were to do whatever we were ordered by the
inspector or the engineer in charge.
By Mr. O'Gara.
Q. There is no difficulty between you and Mr.
Perley as to that?
A. I think not; I am not aware of any.
Q. Will you look at the paper, Mr. Perley's
report of the 25th January, 1885, when he was asked to state why the money paid
exceeded the original contract?
A. I have read it.
Q. That admits the fact that things were
changed, and that the original plans were all wrong and had to be recast?
A. Yes, it admits it; as a necessity they had
to do it.
Q. And that before he had to do the best he
could to provide additional money to complete the structure.
A. Yes. (Report filed as exhibit
"I.")
Q. When did you get any plans upon that?
A. We got no detailed plans at all of any
pier from beginning to end. We got a plan of the first span in January 1884;
and we got a plan of the remaining spans in the end of March 1884. We never got
any plan of the sub-structure at all.
Q. You have those plans?
A. Yes.
Q. Have you got them here?
A. No.
Q. When were you made aware of the sizes of
the piers and changes in the abutment?
A. Just as the work went on. Wherever they
located it they told us to build there.
Q. And gave you the description and sizes
&c.?
A. Yes, and sometimes they got no sizes to
work on, as the inspector told us. The inspector was changing every day.
Q. What effect had those changes upon the
first material that you got out?
A. The timber and iron, a great deal of it,
was valueless in consequence of the changes, worthless to us.
Q. And where did you get the material for the
new design?
[Page 134]
A. We had to hunt round everywhere we could,
and from the lumbermen principally we got what we required for the design for
the new piers.
Q. You had to pick it up wherever you could?
A. Yes, from the lumbermen.
Q. Had you any time to get it cut in the
woods?
A. No, there was no chance of getting it out
that season. It was impossible.
A. You were getting orders gradually, and you
had to give the orders gradually for the timber?
A. Yes.
Q. Is there any difference in the expense to
yourself of timber so acquired and of timber got out regularly by contract in
the woods?
A. There is a great difference, oftentimes
double the price besides the loss of time and trouble the expense in hunting
round for it, getting a little here and a little there.
Q. What was the result in this particular
case?
A. It nearly doubled the price.
Q. What was the effect of it upon your iron?
A. A great deal of the iron was worthless. We
could not use it at all. When the spans were changed, bolts for the one would
not do for the other.
Q. You said that after these changes were
ordered and the new piers were to be put in that you saw Mr. Perley and told
him about the changes and difficulties that were going to take place?
A. I do not know if I said difficulties or
not.
Q. You said there was a new class of work
which would be more difficult to do, etc., and that he told you to go on and
what you were ordered?
A. Yes, that is the answer he made. He said
that the whole work was changed and that we were to carry out the instructions
of the inspector and engineer in charge.
Q. Did he say that you were to carry out the
instructions of the engineer and inspector because the work was changed?
A. Yes; because the work was radically
changed, he said.
Q. Did you infer from that that you were to
carry out the orders of the inspector and engineer whether the work was changed
or not—under your contract originally?
A. No, of course we knew that under the
contract and specification we had to carry out the instructions of the
engineer, but that was another thing altogether.
Q. I want to get the exact words that Mr.
Perley said, that because the work was changed radically you must go and carry
out the work under the instructions of the engineer and inspector.
[Page 135]
A. I went to Mr. Perley specially to ask him
whether, as everything had been changed, the whole character of the work
changed, would it be necessary for us to have a written order for everything
that was to be done. He said, no, in consequence of this entire change, you
will have to carry out every instruction that you will get either from the
engineer in charge or the inspector. "All right," I said.
C'est d'après l'arrangement mentionné dans ce
témoignage que l'ouvrage en question a été fait. Plusieurs autres témoins font
preuve que c'est sous la direction immédiate du département et sans aucun
contrat en forme, comme il en avait été fait un pour l'exécution du premier
projet, que le deuxième plan a été exécuté.
Dans un cas semblable,
quelle est la responsabilité du département des Travaux Publics vis-à-vis des
intimés? Est-il vrai qu'en l'absence d'un contrat par écrit
entre le ministre des Travaux Publics et les intimés, ceux-ci n'ont droit de
rien réclamer pour la valeur de leur ouvrage et des matériaux fournis? Est-il
nécessaire, dans le cas actuel, qu'ils produisent comme condition préalable à
l'exercice de leur action, un certificat de l'ingénieur-en-chef des travaux en question?
A cette dernière
question, je répondrai de suite qu'on ne peut exiger dans ce cas la production
d'un tel certificat, parce qu'il n'y a eu aucune condition à ce sujet dans
l'arrangement en vertu duquel les travaux ont été faits. Il est vrai qu'il en
existait une dans le premier contrat, mais ce contrat a été complètement
abandonné et remplacé par une entreprise toute différente, dont les travaux
ont été exécutés sous la direction immédiate du département et sans contrat par
écrit.
En outre, il n'est pas
inutile de faire remarquer que l'ingénieur-en-chef déclare dans son témoignage
qu'il n'a eu aucune connaissance personnelle des ouvrages.; qu'il n'est allé
sur les lieux qu'une seule fois, et ce avant le commencement des travaux. Quel
certificat pouvait-il donner? Heureusement pour les intimés
[Page 136]
que ce certificat n'est
pas nécessaire dans le cas actuel et qu'on ne peut leur opposer les décisions
rendues en d'autres cas, où il existait une condition à ce sujet.
L'autre question semble
au premier abord beaucoup plus difficile à résoudre, en conséquence de
certaines dispositions des actes concernant les travaux publics. Elle s'est
toutefois déjà présentée devant la cour d'Echiquier, dans la cause de Wood v. La
Reine,
dans laquelle Sir William Richards ex-juge en chef de cette cour se fait deux
questions tendant à définir la responsabilité du département des Travaux
Publics.
Elles étaient posées
comme suit:—
Can the crown in this Dominion be made
responsible under a petition of right, on an executory contract entered into by
the Department of Public Works, for the performance of certain works placed by
law under the control of that department, when the agreement therefor was not
in writing, nor signed or sealed by the Minister of Public Works or his Deputy,
or countersigned by the secretary?
If work had been done for and at the request
of the Department, will a petition of right lie for the value of such, which
causes an expenditure not previously sanctioned by Parliament?
La loi alors en force, la 31
Vict. ch. 12, est encore la même, avec certaines modifications faites par la 42 Vict. ch. Y, qui a
divisé en deux le département des Travaux Publics pour en faire le départment des canaux et chemins de fer et celui des Travaux
Publics.
La section 11 de ce dernier acte déclare bien qu'aucun contrat, document, ou écrit ne
sera obligatoire pour l'un ou l'autre de ces deux départements, ou ne sera
considéré l'acte de tel département à moins d'être signé et scellé par lui ou
son député, et contresigné par le secrétaire ou autre personne autorisée à cet
effet. Cette disposition qui est à peu près la même que la 31 Vict. ch. 12, est conçue en ces termes:—
Sec. 7. No deeds,
contracts, documents or writings
shall be deemed to be binding upon the Department, or shall be held to be the
acts of the
[Page 137]
said Minister, unless signed and sealed by
him or his deputy, and countersigned by the Secretary.
La comparaison des deux
textes fait clairement voir que la loi n'a pas été changée en ce qui concerne
la responsabilité du département.
L'honorable juge après
avoir décidé que le contrat allégué par Wood n'était
pas obligatoire pour le département, et que le pétitionnaire n'avait pas droit
à des dommages pour avoir été empêché de l'exécuter, s'exprime comme suit sur la
deuxième question qui est la même que celle soulevée en cette cause.
I do not think, however, that the 7th section
would prevent the suppliant recovering for the actual value of the work done by
him and accepted by the department. I see no reason why the law may not imply a
contract to pay for the work done in good faith, and which the department has
received the benefit of. Suppose, instead of work done the contract had been to
furnish a quantity of lumber, the lumber had been supplied and worked up by the
workmen of the department in finishing one of the the public buildings; suppose
for some reason the department repudiated the verbal contract and refused to be
bound by it, could it be said that the property of the suppliant could be
retained and used for the purposes of the department, and he not be paid for
it, because the statute said the contract on which it was furnished was not
deemed binding on the department. I should say not. The contract which is
binding is that which arises from the nature of the transaction; having
received the benefit of the contractor's property he ought to be paid for
it—under the new contract which the law implies. For the same reason, for the
value of all services actually rendered by the suppliant, before he was notified
not to do any further work, he ought to be paid. If only the 7th section were
considered, I should, as at present advised, say the suppliant is entitled to
recover what the services rendered by him were worth under the implied
contract. It may be, that on further consideration my views as to the
suppliant's right on this point would be less favorable.
L'honorable juge, par ces dernières expressions,
fait allusion à
la 15ème section, défendant au ministre des travaux publics
d'autoriser des dépenses qui n'ont pas
[Page 138]
été préalablement
sanctionnées par le Parlement. La
clause est en ces termes:
The minister shall direct
the construction, maintenance and repairs of all canals, harbors, roads, or parts of roads, bridges, slides or
other public works, or building in progress, or constructed or maintained, at
the expense of Canada, and which by this Act are, or shall hereafter be, placed
under his management and control; but nothing in this Act shall give authority
to the minister to cause expenditure not previously sanctioned by Parliament,
except for such repairs and alterations as the necessities of the public
service may demand.
L'honorable juge, après
avoir examiné les précédents et la pratique suivie en
Angleterre à ce sujet, en vient à la conclusion qu'en vertu de cette section,
si le Parlement n'a pas autorisé la dépense, il n'y a pas lieu à la pétition de
droit pour ouvrage fait à la réquisition du département des Travaux Publics, à
moins que ce ne soit pour des ouvrages de réparations, et de
changements rendus nécessaires par les exigences du service public:
Unless it be for work done
in connection with repairs and alterations which the
necessities of the public service demanded.
That in this case, if Parliament has made
appropriations for these works and so sanctioned the expenditure, and if the
work done was of the kind that might properly be executed by the officers and
servants of the department, under section 20 of said Act, then no written
contract would be necessary to bind the department, and suppliant could recover
for work so done.
Le principe ainsi posé
par l'honorable juge est d'une application parfaite aux faits de la présente
cause On a vu que la preuve établit positivement que, en août 1883, même après l'expiration du délai pour l'exécution du
premier contrat, on s'est aperçu que les plans et specifications de cet ouvrage ne convenaient aucunement pour l'endroit où il fallait
construire. En conséquence, de nouveaux plans et de nouvelles spécifications
devinrent nécessaires et furent ordonnés et préparés. La saison étant alors
avancée, l'ouvrage à faire étant d'une haute importance pour le public, la
nécessité des communications à établir entre les deux
[Page 139]
rives de l'Ottawa,
urgente, et comme il n'y avait plus le temps nécessaire pour demander de
nouvelles soumissions pour l'exécution des nouveaux plans et spécifications,—il fut alors décidé, comme on l'a vu plus haut, de faire faire les
ouvrages en question sous la direction du département des travaux publics.
Les circonstances
justifiaient cette action en même temps qu'elles dispensaient de la nécessité
de nouvelles annonces.
Dans la cause de Wood où il n'y avait comme dans celle-ci ni contrat par écrit ni annonces, Sir
William Richards s'exprime ainsi sur le droit de recouvrer du département en
pareil cas.
On the broad question whether the suppliant
can recover, and in the view I take of the 15th section
the suppliant can only recover if the work and services rendered come under the
exception referred to in that section, and in which necessity would also
justify the omitting to advertize for tenders under the 28th section.
L'honorable juge
termine ses notes par l'observation suivante au sujet de l'autorisation de la
dépense par le parlement:
It was contended on the agreement, that Parliament has made appropriations for those
work and so sanctioned the expenditure. If that be so, and the work done was of
that kind, that might properly be executed by the officers and servants of the
department, then I apprehend no contract would be necessary to bind the
department for work done, and so suppliant should recover for work so done; and
in every view also for the work actually done, if the expenditure was
previously sanctioned by Parliament.
Dans cette cause, l'autorisation du parlement n'est pas mise en
question; non-seulement les deniers pour la construction du pont
des Joachims ont été votés, mais ils ont été, en grande
partie, payés par le département;
ce qui reste à payer n'est que
pour la différence entre l'exécution des travaux des derniers plans et ceux des
premiers. Les circonstances ont imposé aux officiers du département la
nécessité de se charger de la direction
[Page 140]
des travaux et les ont
justifiés de ne pas demander de nouvelles annonces. Je considère que sous tous
les rapports cette cause est analogue à celle de Wood et La Reine, et que
l'on doit y faire l'application des principes posés par Sir William Richards
dans le jugement dont j'ai donné de si copieux extraits.
Par tous ces motifs, je
suis d'opinion que les requérants ont droit à la confirmation du jugement rendu
en leur faveur par feu l'honorable juge Henry.
Taschereau, Gwynne and Patterson JJ. concurred
with Sir W. J. Ritchie C. J..
Appeal allowed without costs.
Cross-appeal dismissed without costs.
Solicitors for appellant—O'Connor and Hogg.
Solicitors for respondent—O'Gara and Remon.