Date: 19991223
Docket: 1999-959-IT-I
BETWEEN:
CHARLES ARTHUR WRIGHT,
Appellant,
and
HER MAJESTY THE QUEEN,
Respondent.
Reasons for Judgment
Mogan J.T.C.C.
[1] The Appellant is a businessman who lives in Saskatoon.
Over a period of more than 20 years, he has controlled and
operated a number of corporations engaged in business. The issue
in this appeal is whether the Appellant, as a director of one of
his corporations, is liable under section 227.1 of the Income
Tax Act because the corporation failed to remit a certain
amount to Revenue Canada. In the assessment under appeal, the
Appellant is required to pay the following amounts resulting from
failure to remit in the period January 1 to December 31,
1992:
Federal Tax $ 5,267.73
Provincial Tax 3,580.01
Penalty and Interest 5,005.71
Total $13,853.45
The Appellant has elected the informal procedure.
[2] The circumstances in this appeal arise out of a project
which had been developed in Prince Albert in the period 1991 and
1992. The Appellant was the only witness to testify and he
described the construction of what he called a SuperStore in
Prince Albert. The general contractor was The Dominion Company
Inc. ("Dominion"), a corporation which apparently was
not connected or affiliated in any way with the Appellant or any
of his companies. I drew the inference from the Appellant’s
evidence that the Appellant and his companies were totally at
arm's length with Dominion. One of the Appellant’s
corporations was identified as Renex Enterprises Ltd.
("Renex") engaged in the batching and delivering of
redi-mix concrete. Jim Marshall was the comptroller of the
Appellant’s companies and either the Appellant or Mr.
Marshall was authorized to sign cheques for the operating
companies.
[3] At the start of the SuperStore project in Prince Albert,
Renex was one of the original subcontractors providing redi-mix
concrete to Dominion. After the project commenced, Renex was
forced into bankruptcy and was unable to continue to supply the
concrete. According to the Appellant, Dominion attempted to
obtain concrete from other sources but, being in the middle of a
project and turning to other sources, Dominion was being
overcharged for regular concrete. I drew the inference, although
the Appellant did not say this, that the redi-mix concrete
suppliers in the Prince Albert area were holding Dominion to
ransom more or less because it was in the middle of a project and
they had not signed on as the original concrete subcontractors.
There is no evidence to that effect, but that was an inference I
drew from the Appellant’s description of events.
[4] When Dominion concluded that it was being overcharged, it
turned to the Appellant and asked him if there was some kind of
arrangement which could be worked out to provide concrete to
Dominion at a more favourable price. According to the Appellant,
the workers who had been employed by Renex were still available
because they had been put out of work when Renex went into
bankruptcy and they were known to the Appellant or his manager.
He suggested to Dominion that the workers who used to batch and
deliver the concrete were available and unemployed, but of course
the Appellant’s company, Renex, could not engage in any
business because it was bankrupt.
[5] An arrangement was worked out between the Appellant and
Dominion whereby the Appellant would either provide the names of
the former workers of Renex or contact them himself; and they
would become employed by Dominion or Dominion would at least pay
them and obtain the raw materials for concrete, (i.e. cement,
sand and gravel). One of the Appellant’s other companies,
Arlo Investments ("Arlo"), happened to own a property
in Prince Albert with a concrete batching plant which was idle at
the time. It seemed a natural fit then that if the concrete plant
on the Arlo property could be put into operation and if Dominion
could find people who knew how to mix, batch and deliver
concrete, an arrangement with Dominion could be worked out. The
arrangement was actually put into place and confirmed by a letter
dated February 17, 1992 from Dominion to Renex and Arlo (Exhibit
A-1). It appears that Arlo is a holding company which owns all
the shares of Renex and the Appellant is a principal shareholder
in Arlo. Also, the Appellant was the sole director of Renex at
all relevant times.
[6] Exhibit A-1 is interesting because it is a letter
addressed to both Renex and Arlo to the attention of Mr. Art
Wright and it sets out the arrangements entered into between
Dominion and the Appellant's two companies, Renex and Arlo.
The letter states in part:
RE: SUPERSTORE, P.A.
CONCRETE SUPPLY
This letter will confirm our discussion with regards to supply
of redi-mix concrete to the subject project, to the following
terms and conditions.
1. That Arlo Investments will provide a lease for the property
and a full and operative redi-mix concrete plant capable of
supplying The Dominion Company Inc. (hereinafter known as
Dominion) required concrete quantities, to Renex Enterprises
Ltd., which will in turn supply the required concrete quantities
as discussed (approx. 2000 m3, 20 mm,
25 mpa).
2. The quantity price per m3, as per Northern
Concrete's quote dated Oct. 7, 1991, and our previous
purchase order #510577 with Northern Concrete, will be $73.13 for
concrete, $5.00 for heating, $21.00 for delivery, and $5.47 for
pst. GST will be 7%.
3. Dominion will purchase the following for Renex Enterprises
Ltd.'s use in the supply of redi-mix concrete to the subject
project.
- purchase of cement from Ideal Cement Ltd., including all
applicable taxes.
- purchase of sand from the trustee for Tru-Mix Ltd. at a
normal industry cost of $8.00 per yd3, plus
all applicable taxes.
DOMINION CONSTRUCTION
- payment of the normal utilities of natural gas, electrical,
& water to operate the concrete plant for this project.
4. Renex Enterprises Ltd. will supply all necessary labour for
operation & delivery of the redi-mix concrete, to the subject
project and Dominion agrees to pay on approved labour statements
from Renex Enterprises Ltd., with payment made directly to the
individual employees on a 2 week pay period sequence.
5. The following "payment schedule example"
will be used to pay Renex Enterprises Ltd.
The letter required testimony from the Appellant to make it
understandable because there are terms in the letter which
indicate that the author and the Appellant, as the recipient,
understood certain circumstances which were taken for granted
within the knowledge of both Dominion and Mr. Wright. In
paragraph one, there is a statement that Arlo will provide a
lease for the property and a full and operative redi-mix concrete
plant capable of supplying Dominion. That of course was necessary
because, on the Appellant's evidence, Arlo owned the concrete
plant in Prince Albert. Paragraph two deals with the price per
cubic yard of concrete to be delivered to the site with extra
charges for heating, delivery and provincial sales tax. The third
paragraph provides that Dominion will purchase the following for
Renex's use in the supply of redi-mix concrete; and then it
lists the purchase of cement and the purchase of sand and the
payment of normal utilities. One can see that it is really the
financial resources of Dominion which are bankrolling the
operation because it is buying the supplies that will be
necessary to produce the concrete.
[7] The fourth paragraph is most important because it states
that Renex will supply all necessary labour for the operation and
delivery of redi-mix concrete to the project and Dominion agrees
to pay, on approved labour statements from Renex, with payment
made directly to the individual employees on a two-week pay
period sequence. That paragraph, according to the Appellant,
meant what it said. The Appellant recruited the former workers of
Renex; gave the list to Dominion; the batcher at Arlo's
concrete plant in Prince Albert provided the time sheets to
Dominion showing who had worked on certain days and what hours
they had worked and what their pay would be; and Dominion paid
those workers in accordance with paragraph four. That was the
arrangement and the way the matter proceeded for a period of
time. I am not sure how long but, at some point, that arrangement
was changed and, while the project was still continuing, the
workers whom Dominion had agreed to pay on approved labour
statements from Renex were transferred from what I would call the
payroll of Dominion to the payroll of Renex. I use the word
"payroll" as my own. It was not used by the
Appellant.
[8] The Appellant also entered Exhibit A-2 which is a fax
dated March 4, 1992, approximately 15 days after the letter
agreement of February 17, 1992. The fax was sent by Dominion to
the Appellant and it states: "I assume from these rates we
deduct UIC, CPP, etc., and no other benefits are payable other
than the normal amounts. Please confirm." The Appellant
confirmed that the fax was in agreement with his understanding of
the letter agreement of February 17 (Exhibit A-1).
Therefore, when the arrangement began, Dominion paid the workers
and withheld the normal source deductions for unemployment
insurance premiums, Canada Pension Plan contributions and income
tax. There was some suggestion from the Appellant that the
workers were transferred from Dominion to Renex at the insistence
of Revenue Canada and counsel for the Appellant made that point
in argument. I will come back to that later because I have doubts
about the accuracy and relevancy of that statement.
[9] In any event, it is not disputed that at some time after
March 1992, the workers came on the payroll of Renex and, for
whatever reason, Renex paid the workers; withheld the source
deductions; and certain of those source deductions were not
remitted to Revenue Canada. That is the cornerstone of the
assessment against the Appellant as the sole director of Renex.
Under section 227.1 of the Income Tax Act, there are
certain conditions which have to be satisfied before a director
can be held liable and those conditions are primarily set out in
subsection 227.1(2). The Appellant does not argue that any
of those conditions was not satisfied. The only issue before the
Court is whether the Appellant had satisfied the due diligence
test in subsection 227.1(3). The Appellant is satisfied that he
had done what any diligent director would do. Subsection 227.1(3)
states:
(3) A director is not liable for a failure under subsection
(1) where he exercised the degree of care, diligence and skill to
prevent the failure that a reasonably prudent person would have
exercised in comparable circumstances.
[10] There is a great volume of jurisprudence on the question
of a director's liability. Many cases have come to this Court
and it is a daunting task to synthesize them because they fall
into different categories. The decision of the Federal Court of
Appeal in Soper v. The Queen, 97 DTC 5407 offers useful
guidance on certain areas of directors' liability. It is a
unanimous decision and I rely on the following statement of
Robertson, J.A. at page 5416:
... The standard of care laid down in subsection 227.1(3)
of the Act is inherently flexible. Rather than treating
directors as a homogeneous group of professionals whose conduct
is governed by a single, unchanging standard, that provision
embraces a subjective element which takes into account the
personal knowledge and background of the director, as well as his
or her corporate circumstances in the form of, inter alia,
the company's organization, resources, customs and conduct.
Thus, for example, more is expected of individuals with superior
qualifications (e.g. experienced business-persons).
The standard of care set out in subsection 227.1(3) of the Act
is, therefore, not purely objective. Nor is it purely subjective.
It is not enough for a director to say he or she did his or her
best, for that is an invocation of the purely subjective
standard. Equally clear is that honesty is not enough. However,
the standard is not a professional one. Nor is it the negligence
law standard that governs these cases. Rather, the Act contains
both objective elements -- embodied in the reasonable person
language – and subjective elements -- inherent in
individual considerations like “skill” and the idea
of “comparable circumstances.” Accordingly, the
standard can be properly described as “objective
subjective.
[11] The important words in subsection 227.1(3) are
"care, diligence and skill", "a reasonably prudent
person", and "comparable circumstances" because
those words permitted Robertson J.A. to establish both an
objective standard and a subjective standard. Those two standards
lead me to find against the Appellant in this appeal. There are a
number of cases which deal with inside and outside directors, and
I am satisfied that the Appellant was an inside director because
he was the only director and he had signing authority at the
bank. He is an experienced businessman which identifies him as an
individual with superior qualifications because he has owned a
number of operating companies. Also, he employed a trusted
person, Jim Marshall, as the comptroller of his companies. Either
the Appellant or Jim Marshall could sign the cheques of the
companies but the Appellant was the only director. Therefore, of
necessity, I would say he was an inside director. Robertson J.A.
stated at page 5417:
... I intend to focus on the category of cases respecting
the distinction between inside and outside directors since that
line of authority is the most pertinent to this appeal.
At the outset, I wish to emphasize that in adopting this
analytical approach I am not suggesting that liability is
dependent simply upon whether a person is classified as an inside
as opposed to an outside director. Rather, that characterization
is simply the starting point of my analysis. At the same time,
however, it is difficult to deny that inside directors, meaning
those involved in the day-to-day management of the company and
who influence the conduct of its business affairs, will have the
most difficulty in establishing the due diligence defence. For
such individuals, it will be a challenge to argue convincingly
that, despite their daily role in corporate management, they
lacked business acumen to the extent that that factor should
overtake the assumption that they did know, or ought to have
known, of both remittance requirements and any problem in this
regard. In short, inside directors will face a significant hurdle
when arguing that the subjective element of the standard of care
should predominate over its objective aspect.
[12] Relying on the above, I find that the Appellant failed to
discharge the burden of showing that he had exercised due
diligence. In fact, on the evidence before me, I find that the
Appellant failed to demonstrate that he exercised any diligence
at all. There was simply no evidence as to what happened when the
workers were taken on by Renex as a liability to pay their wages.
There was no evidence as to what happened to the source
deductions or why they were not set aside and remitted to Revenue
Canada. There was just a bland statement by the Appellant that he
had been duly diligent. Much more is required of a man with his
business acumen, a man who really made the deal with Dominion and
who must have known, or ought to have known, that at some later
time the workers were transferred from what I would call the
payroll of Dominion to the payroll of Renex.
[13] In closing, I come back to a statement made by the
Appellant that Revenue Canada was at fault for forcing the
transfer of the workers from Dominion to Renex. The Appellant
said that when he finally went to the offices of Revenue Canada
(either after he was assessed as a director or after he received
a letter indicating he was going to be assessed) somebody at
Revenue Canada reviewed some documents or correspondence from
which the Appellant drew the conclusion that Revenue Canada had
forced the transfer of the workers from being paid by Dominion to
being paid by Renex.
[14] Revenue Canada no doubt has a lot of clout in the
assessment and collection of tax but, in terms of forcing one
corporation to transfer the payment of workers to a totally
arm's length corporation, I do not know how Revenue Canada
could bring about that business result. I am not impressed with
the rather vague statements of the Appellant that he drew that
conclusion by watching some documents called up on a computer
screen in a Revenue Canada office sometime long after the failure
to remit the source deductions. Even if Revenue Canada could, by
some means or other, persuade Dominion to transfer the workers to
Renex (and there is no evidence that it did), I do not know how
it would have any bearing on or any relevance to the obligations
of Renex as a corporation making payments of salary and wages. I
do not know how it could absolve Renex of the obligation to
withhold and remit source deductions under section 153 of the
Income Tax Act. I place no weight on this argument
concerning Revenue Canada. For these reasons, the appeal is
dismissed.
Signed at Ottawa, Canada, this 23rd day of December 1999.
"M.A. Mogan"
J.T.C.C.