RAND
J.:—This
is
an
information
brought
to
recover
sales
taxes
claimed
in
respect
of
a
contract
of
sale
between
the
respondent
as
seller
and
the
Lake
Sulphite
Pulp
Co.
Ltd.
as
purchaser
of
an
apparatus
known
as
a
pulp
drying
machine.
The
machine
was
to
be
built
according
to
plans
and
specifications,
and
delivery
was
to
be
made
on
or
about
March
5,
1938,
f.o.b.
ears
at
Lachine,
Quebec,
with
freight
prepaid
to
the
plant
of
the
purchaser
at
Nipigon,
Ontario.
The
erection
of
the
machine
was
to
be
done
by
the
purchaser.
The
proposal
was
under
date
of
June
5,
1937,
and
the
acceptance
by
the
purchaser
made
on
August
3,
1937.
The
price
was
$488,335
payable
in
nine
monthly
progress
instalments
of
$48,800
each
commencing
July
5,
1937,
and
the
balance
of
$49,135
when
the
machine
was
in
operation
but
in
no
event
later
than
six
months
from
the
date
of
final
shipment
or
offer
of
shipment
from
the
respondent’s
works
at
Lachine.
Title
was
to
pass
on
payment
in
full
of
the
price.
Although
the
acceptance
was
not
made
until
August
3rd,
work
was
actually
commenced
on
June
15th
and
at
the
outset
consisted
of
the
preparation
of
plans,
ordering
of
materials
and
parts,
making
of
moulds,
castings,
machinery,
etc.
The
instalments
due
on
July
5th
and
August
5th
were
paid
on
August
27th,
that
for
September
5th
on
the
30th
of
that
month,
for
October
on
the
7th
and
for
November
on
the
13th.
Some
time
in
December
it
was
made
known
that
the
purchasers
were
under
the
necessity
of
raising
funds
to
carry
on
the.
completion
of
their
plant
by
an
issue
of
treasury
notes.
A
subscription
of
$50,000
by
the
respondent
was
made
on
terms
that
the
instalment
due
on
December
5th
should
be
paid
out
of
the
funds
realized,
and
that
instalment
was
paid
on
January
11,
1938.
On
February
5,
1938,
a
petition
in
bankruptcy
was
filed
against
the
Sulphite
Company
and
on
February
11th
all
work
on
the
machine
was
stopped.
On
February
22nd
an
order
was
made
for
winding-up
under
the
Dominion
Winding-up
Act,
R.S.C.
1927,
ce.
213
and
a
liquidator
was
appointed.
On
February
11th
the
purchaser
had
paid
on
account
the
sum
of
$292,800.
There
remained
of
the
price
a
balance
of
$195,535.
On
April
6,
1938,
the
respondent
by
letter
communicated
to
the
liquidator
the
details
of
the
contract
adding
certain
extras,
sales
tax
and
freight
amounting
to
$1,662.80
and
stating
that
the
"‘work
under
the
contract’’
was
approximately
75%
completed.
With
that
was
submitted
a
statutory
proof
of
claim
for
the
sum
of
$202,820.76.
The
difference
of
$5,622.96
was
for
three
small
additional
contracts.
There
is
no
evidence
of
what,
if
anything,
took
place
thereafter
between
the
liquidator
and
the
respondent.
The
information
was
filed
on
April
25,
1940.
The
tax
is
claimed
under
s.
86
of
the
Special
War
Revenue
Act,
R.S.C.
1927,
c.
179
as
amended.
Subsection
(1)
is
as
follows.
^86(1)
There
shall
be
imposed,
levied
and
collected
a
consumption
or
sales
tax
of
eight
per
cent
on
the
sale
price
of
all
goods,
—
"‘(a)
produced
or
manufactured
in
Canada,
payable
by
the
producer
or
manufacturer
at
the
time
of
the
delivery
of
such
goods
to
the
purchaser
thereof.
"‘Provided
that
in
the
case
of
any
contract
for
the
sale
of
goods
wherein
it
is
provided
that
the
sale
price
shall
be
paid
to
the
manufacturer
or
producer
by
instalments
as
the
work
progresses,
or
under
any
form
of
conditional’
sales
agreement,
contract
of
hire-purchase
or
any
form
of
contract
whereby
the
property
in
the
goods
sold
does
not
pass
to
the
purchaser
thereof
until
a
future
date,
notwithstanding
partial
payment
by
instalments,
the
said
tax
shall
be
payable
pro
tanto
at
the
time
each
of
such
instalments
falls
due
and
becomes
payable
in
accordance
with
the
terms
of
the
contract,
and
all
such
transactions
shall
for
the
purposes
of
this
section,
be
regarded
as
sales
and
deliveries.
"‘Provided
further
that
in
any
case
where
there
is
no
physical
delivery
of
the
goods
by
the
manufacturer
or
producer,
the
said
tax
shall
be
payable
when
the
property
in
the
said
goods
passes
to
the
purchaser
thereof.’’
It
is
contended
by
the
Crown
that
the
case
is
within
the
first
proviso
and
that,
as
the
agreement
formally
provided
for
instalments
on
the
5th
day
of
January,
February
and
March,
1938,
when
these
times
arrived
the
tax
eo
instanti
became
an
absolute
obligation
to
the
Crown
divorced
wholly
from
the
contract.
It
was
conceded
that,
as
the
remaining
balance
was
payable
only
after
delivery
or
its
equivalent,
it
could
not
be
said
to
be
due
and
payable
and
the
tax
had
not
arisen.
The
transaction
is
undoubtedly
within
the
first
part
of
the
proviso.
It
is
a
contract
for
the
sale
of
goods
‘‘wherein
it
is
provided
that
the
sale
price
shall
be
paid
to
the
manufacturer
or
producer
by
instalments
as
the
work
progresses.’’
It
contemplates
the
machine
to
be
built
or
assembled
by
the
respondent
and
the
monthly
payments
are
distributed
evenly
over
the
time
allowed
for
construction.
But
there
is
nothing
in
the
contract
to
indicate
that
the
course
of
the
work,
whether
as
to
plans
or
material
or
the
production
or
assembly
of
parts,
should
follow
any
particular
order
or
schedule
or
observe
any
uniformity
of
progress.
That
lay
quite
within
the
main
obligation
of
the
seller
to
furnish
the
apparatus
at
the
time
fixed.
By
the
proviso,
"‘the
.
.
.
.
tax
shall
be
payable
pro
tanto
at
the
time
each
of
such
instalments
falls
due
and
becomes
payable
in
accordance
with
the
terms
of
the
contract,
and
all
such
transactions
shall
for
the
purposes
of
this
section,
be
regarded
as
sales
and
deliveries.”
The
words
"‘such
transactions”
refer
either
to
the
contracts
themselves
or
to
the
successive
liabilities
for
instalments.
But
in
either
sense
the
expression
"‘becomes
payable”
is
not
to
be
limited
solely
to
the
event
of
the
day
named
for
the
payment
of
the
instalment.
What
is
contemplated
is
an
obligation
to
pay
arising
from
the
legal
effectiveness
of
the
contract.
The
language
of
the
proviso,
appropriate
to
a
contract
performed
according
to
its
original
terms,
presents
difficulties
in
its
application
to
one
which
has
been
modified
or
disrupted.
If,
for
instance,
after
the
first
two
instalments
and
the
related
taxes
had
been
paid,
the
parties
had
altered
the
agreement
by
either
increasing
or
reducing
the
price,
there
can
be
no
doubt
that
the
incidence
of
the
tax
would
thereafter
have
varied
accordingly.
But
what
is
the
effect
on
unpaid
taxes
of
a
subsequent
disturbance
of
the
contract
which
affects
the
instalment
obligations
from
which
the
taxes
arose?
Although
the
section
declares
the
"‘transaction’’
to
be
a
constructive
sale
and
delivery,
the
fundamental
support
of
the
tax
is
an
executory
contract
leading
to
the
transfer
of
title
and
possession.
That
contract
is
conceived
as
a
potential
sale
to
which
in
turn
is
related
a
potential
total
tax
:
‘‘the
tax
shall
be
payable.”
Pro
tanto
portions
of
the
tax
are
related
to
instalments
of
price
and,
when
the
latter
become
payable
as
parts
of
a
whole,
the
right
to
the
tax
takes
on
the
same
character:
but
throughout,
the
tax
depends
for
its
efficacy
upon
the
maturing
contract.
For
the
total
tax
there
is
only
an
inchoate
liability
created
by
the
making
of
the
agreement:
and
to
sustain
the
right
to
the
tax,
the
instalment
become
payable
must
remain
an
obligation
of
an
executory
contract.
The
legal
liability
at
any
time
for
any
portion
of
the
tax
in
no
degree
restricts
the
parties
in
good
faith
from
modifying
the
contract
as
they
see
fit,
and
a
fortiori
it
does
not
prevent
a
modification
by
operation
of
law.
If
in
the
legal
result,
the
actual
transaction
ceases
to
be
one
of
sale,
then
the
necessary
support
for
the
tax
disappears.
That
result,
at
least
where
the
termination
of
the
contract
does
not
effect
a
total
rescission,
will
not
affect
the
right
to
taxes
on
any
portion
of
the
price
paid
to
the
seller
nor
does
it
touch
those
that
have
been
collected
or
reduced
to
judgment
by
the
Crown.
It
is
contended
that,
on
the
dates
mentioned,
the
work
was
so
far
behind
any
schedule
as
to
constitute
a
breach
sufficient
to
give
rise
to
a
suspensive
defence
by
the
purchaser.
To
prove
that
state
of
things
a
graph
was
introduced
showing
lines
of
normal
progress
and
actual
progress
in
the
shop
work,
and
indicating
that
completion
by
March
5th
was
impossible.
It
may
be
that
on
December
31,
1937,
the
work
was
at
such
a
stage
that,
even
with
the
capacity
available
to
the
respondent,
the
machine
could
not
have
been
finished
on
time.
The
evidence
does
not
clearly
indicate
that.
It
is
admitted
that
there
was
a
quick
as
well
as
an
average
schedule
for
the
work
at
the
Lachine
plant,
the
former
of
six
months
and
the
latter
of
nine.
But
assuming
such
a
defence
to
be
available
under
the
Civil
Code
and
on
the
footing
that
the
contract
was
six
weeks
behind
in
its
progress
at
the
end
of
1937,
on
January
11,
1938,
the
instalment
due
on
December
5,
1937,
was
paid
and
the
delay
up
to
that
time
waived.
It
is
not
suggested
that
from
then
on
until
the
insolvency
appeared,
a
satisfactorily
high
rate
of
performance
was
not
maintained.
But
whether
under
the
Act
such
a
defence
could
have
been
interposed
against
the
claim
for
the
taxes,
it
is
not
necessary
to
decide.
The
fact
of
bankruptcy
intervening
is,
in
my
opinion,
a
circumstance
fatal
to
the
right
of
the
Crown
to
maintain
this
information.
When,
on
February
22nd,
the
liquidation
order
was
made,
the
instalments
for
the
balance
of
purchaseprice
ceased
to
be
‘‘due
and
payable”
within
the
meaning
of
the
statute.
What
remained
to
the
respondent
was
to
prove
for
unliquidated
damages
subject
to
the
right
of
the
liquidator
to
elect
to
complete
the
contract.
It
is
not
suggested
there
was
any
such
election
prior
to
the
commencement
of
this
proceeding.
But
the
respondent
could
not
have
enforced
payment
of
the
remaining
instalments
and
the
essential
condition
of
the
tax
that
they
should
continue
as
effective
obligations
of
a
contract
of
sale
was
not
existing
when
the
information
was
issued.
A
right
of
election
by
the
liquidator
even
then
continuing
could
not
affect
the
present
proceeding.
This
interpretation
of
the
Act
does
not
mean
that
either
price
or
instalment
of
price
in
such
a
contract
must
be
received
before
the
tax
is
exigible
but
it
does
mean
that
where
the
obliga-
tion
of
such
an
executory
contract
is
by
operation
of
law
destroyed,
then
unpaid
taxes
related
to
its
terms,
themselves
suffer
a
corresponding
effect.
If
that
were
not
so,
sellers
with
unsold
property
on
their
hands
would
be
liable
for
taxes
in
respect
of
purchase-price
not
only
unpaid
but
the
legal
right
to
which
had
been
annulled:
and
on
the
other
hand
a
resale
of
the
same
property
would
attach
to
itself
a
new
tax
unrelated
in
any
sense
to
that
attributed
to
the
first
sale.
What
is
created
is
a
tax
liability
running
parallel
to
executory
commercial
transactions
which,
before
their
completion,
is
exposed
to
the
effect
of
contractual
changes
or
fundamental
legal
infirmities
to
which
they
may
become
subjected.
For
these
reasons
I
would
dismiss
the
appeal
with
costs.
Hudson
J.:—This
appeal
concerns
a
claim
on
behalf
of
the
Crown
against
the
respondent
in
the
sum
of
$10,844.46
as
sales
tax,
and
for
a
penalty
for
non-payment
thereof.
The
claim
arises
out
of
a
contract
in
writing
concluded
on
August
3,
1937,
whereby
the
respondent
company
agreed
to
manufacture
and
deliver
to
the
Lake
Sulphite
Pulp
Co.
Ltd.
a
pulp
drying
machine
with
accessories
and
spare
parts
for
a
price
of
$488,335,
this
amount
to
be
paid
in
nine
monthly
progress
payments
of
$48,800
each,
commencing
on
July
5,
1937,
and
continuing
until
a
total
of
$439,800
should
have
been
paid,
and
the
balance
of
$49,135
when
the
machine
was
placed
in
operation,
but
in
no
event
later
than
six
months
from
the
date
of
final
shipment
or
offer
of
shipment.
It
was
further
stipulated
that
the
property
in
the
goods
should
remain
the
personal
property
of
the
respondent
until
the
price
had
been
fully
paid
for
in
cash.
The
machine
to
be
constructed
was
very
large
and
complicated.
It
requires
much
planning
and
a
great
variety
of
materials
and
skilled
workmanship
in
construction
over
a
considerable
period
of
time.
The
work
of
construction
had
actually
been
commenced
prior
to
the
conclusion
of
the
written
contract,
and
thereafter
was
carried
on
but
not
at
the
rate
expected
by
the
parties,
owing
to
various
causes
which
need
not
be
considered.
However,
five
progress
payments
totalling
$244,000
had
been
paid
by
the
Lake
Sulphite
Co.
by
November
13,
1937.
Thereafter
another
instalment
of
$48,800
was
made
in
January,
1938,
in
respect
of
the
sum
falling
due
in
December,
1937,
but
no
instalments
1938,
paid
in
the
months
of
January,
February
and
March
of
1938,
and
it
is
for
the
amount
of
these
three
payments
that
the
present
proceedings
are
taken.
It
appears
that
the
Lake
Sulphite
Co.
found
difficulty
in
pay
ing
its
obligations
about
the
end
of
1937
and
eventually
a
winding-up
order
was
made
against
it
on
February
22,
1938.
The
respondent’s
manager
learning
of
the
Lake
Sulphite
Co.’s
financial
difficulties
ceased
work
on
the
machinery
entirely
on
February
11,
before
the
formal
assignment.
The
respondents
paid
sales
tax
to
the
Crown
in
respect
of
the
payments
actually
made
and
the
claim
of
the
Crown
is
in
brief
that
under
s.
86(1)
(a)
of
the
Special
War
Revenue
Act
the
respondents
are
liable
for
the
tax
in
respect
of
the
three
payments
above
mentioned
because
these
payments
"‘fell
due
and
became
payable
in
accordance
with
the
terms
of
the
contract
during
the
months
of
January,
February
and
March”.
There
is
no
dispute
as
to
any
material
facts
and
the
whole
question
is
as
to
the
interpretation
of
the
section
in
relation
to
the
facts.
It
must
be
kept
in
mind
that
the
machinery.
was
being
sold
as
a
unit,
that
it
was
never
completely
manufactured,
and
that
physical
delivery
had
not
been
made
of
any,
except
a
small
part
of
the
value
of
$1,200
and
that
the
property
in
such
part
of
the
machine
as
had
been
manufactured
did
not
pass
to
the
purchaser.
Section
86
is
as
follows:
^86(1)
There
shall
be
imposed,
levied
and
collected
a
consumption
or
sales
tax
of
eight
per
cent
on
the
sale
price
of
all
goods,—
“(a)
produced
or
manufactured
in
Canada,
payable
by
the
producer
or
manufacturer
at
the
time
of
the
delivery
of
such
goods
to
the
purchaser
thereof.
Provided
that
in
the
case
of
any
contract
for
the
sale
of
goods
wherein
it
is
provided
that
the
sale
price
shall
be
paid
to
the
manufacturer
or
producer
by
instalments
as
the
work
progresses,
or
under
any
form
of
conditional
sales
agreement,
contract
of
hire-purchase
or
any
form
of
contract
whereby
the
property
in
the
goods
sold
does
not
pass
to
the
purchaser
thereof
until
a
future
date,
notwithstanding
partial
payment
by
instalments,
the
said
tax
shall
be
payable
pro
tanto
at
the
time
each
of
such
instalments
falls
due
and
becomes
payable
in
accordance
with
the
terms
of
the
contract,
and
all
such
transactions
shall
for
the
purposes
of
this
section,
be
regarded
as
sales
and
deliveries.
"'Provided
further
that
in
any
case
where
there
is
no
physical
delivery
of
the
goods
by
the
manufacturer
or
producer,
the
said
tax
shall
be
payable
when
the
property
in
the
said
goods
passes
to
the
purchaser
thereof.’’
This
section
requires
careful
analysis.
Under
s-s.
(a)
the
tax
is
payable
on
delivery
of
the
goods.
In
the
first
proviso,
provision
is
made
for
earlier
payments
in
cases
where
the
contract
calls
for
payment
by
instalments.
In
most
of
the
cases
falling
with
this
proviso
there
would
be
an
actual
physical
delivery
of
the
goods
agreed
to
be
sold.
For
example,
in
cases
of
conditional
sales
and
hire-purchase.
this
is
almost
invariably
the
case.
In
some,
however,
there
would
not
be
physical
delivery
and
for
such
it
is
provided
that
a
constructive
or
notional
delivery
should
be
assumed.
The
second
proviso
does
not
apply
to
cases
where
there
is
an
actual
physical
delivery,
but
in
any
other
cases
makes
the
tax
payable
when
the
property
in
the
goods
passes
to
the
purchaser.
The
facts
in
the
present
case
may
bring
it
within
the
language
of
the
first
proviso.
By
the
contract
the
sales
price
was
to
be
paid
in
instalments
in
the
nature
of
progress
payments
although
there
was
no
provision
that
these
instalments
should
be
made
in
accordance
with
any
particular
rate
of
progress.
I
think,
however,
that
it
must
be
assumed
that
it
was
the
intention
of
the
parties
that
the
payments
should
not
become
payable
until
the
respondents
were
making
fair
progress
in
their
work.
This
was
the
interpretation
of
the
Lake
Sulphite
Co.
officials
because
it
appears
from
the
evidence
that
that
Company’s
manager
protested
against
the
delays
of
the
respondents,
and
in
fact
held
up
the
December
payment
for
some
time
on
that
account.
It
is
a
question
whether
or
not
the
instalments
in
respect
of
which
the
Crown
claims
ever
fell
due
and
became
payable
but,
even
if
this
were
so,
I
am
of
the
opinion
that
the
second
proviso
must
prevail.
The
language
is
unqualified
and
it
is
clear
that
the
property
in
the
goods
never
passed
to
the
purchaser.
The
second
proviso
does
not
destroy
altogether
the
first
but
applies
only
to
cases
where
there
is
no
physical
delivery.
I
think
for
that
reason
that
the
rule
of
construction
approved
of
in
Forbes
v.
Git
(1921),
61
D.L.R.
353,
[1922]
1
A.C.
256
is
applicable.
The
machinery
was
never
completed
and
thus
was
never
capable
of
physical
delivery
in
fulfilment
of
the
contract.
I
would
dismiss
the
appeal
with
costs.