The
Assistant
Chairman:—This
is
the
appeal
of
Dominion
Construction
Company
(Niagara)
Limited
from
an
income
tax
assessment
in
respect
of
its
1970
taxation
year.
On
April
25,
1969
the
appellant
entered
into
a
contract
with
the
Welland
County
Board
of
Education
for
the
construction
of
an
addition
to
Fort
Erie
High
School.
The
plans
and
specifications
were
drafted
and
supervision
of
the
project
was
carried
out
by
Donald
N
Chapman,
Architect.
Mr
Gordon
Goulty,
who
worked
for
Mr
Chapman,
was
looking
after
the
work
involved.
The
original
contract
in
the
amount
of
$602,490
called
for
specific
work
to
be
completed
on
December
31,
1969,
and
the
contract
included
such
work
as
paving,
grading,
painting
exterior
entrances,
cleaning
windows
and
general
site
cleaning
(Exhibit
A-1).
Because
of
weather
conditions,
and
because
of
the
existence
of
two
buildings
on
the
school
site
which
had
to
be
removed
before
the
grading
and
paving
could
be
completed,
it
was
decided,
at
the
suggestion
of
Mr
Goulty,
to
terminate
the
original
contract
on
March
16,
1970
(Exhibits
A-2
and
A-15),
and
to
engage
in
another
contract
for
the
remaining
work
which
was
required
to
be
done.
On
March
20,
1970
a
supplementary
contract
in
the
amount
of
$3,500
which
was
to
be
completed
on
June
15,
1970
was
let
in
order
to
permit
the
appellant
company
to
execute
the
paving,
grading
and
exterior
painting
which
formed
part
of
the
original
contract
but
which
was
delayed
owing
to
the
circumstances
described
above
(Exhibit
A-7).
The
amount
of
the
original
contract
was
reduced
by
$3,500
(Exhibit
A-3).
On
March
18,
1970
the
original
contract
having
been
reduced
by
$3,500
amounted
to
$598,990
and
the
15%
holdback
provided
for
in
the
contract
and
calculated
thereon
was
in
the
amount
of
$89,530
(Exhibits
A-4—A-16).
On
March
20,
1970
the
architect
issued
a
certificate
which
certified
that
the
addition
to
the
Fort
Erie
Secondary
School
was
completed
and
that
the
commencement
of
the
lien
period
was
established
as
March
17,
1970
(Exhibit
A-17).
On
April
20,
1970,
as
requested,
the
appellant
company
forwarded
to
the
architect
the
subcontractors’
waiver
of
liens
A-4-A-16).
On
April
24,
1970
the
appellant
submitted
his
account
claiming
the
holdback
of
$89,530
(Exhibit
A-10).
On
April
27,
1970
the
architect
issued
certificate
No
11
entitled
“Release
of
Holdback”
(Exhibit
A-19).
Although
it
is
not
clear
on
what
date
the
amount
of
$89,530
was
actually
received,
it
is
on
record
that
the
holdback
was
deposited
at
the
Bank
of
Montreal
in
Niagara
Falls
on
April
29,
1970
(Exhibit
A-11).
It
was
established
that
the
appellant
company’s
fiscal
year
ended
March
31,
1970,
and
uncontradicted
evidence
would
indicate
that
since
1958
it
has
been
the
company’s
policy
to
calculate
its
profits
only
when
a
contract
has
been
completely
terminated.
The
main
issues
to
be
determined
in
this
appeal
are—first,
whether
the
holdback
on
the
original
contract
amounting
to
$89,530
was
received
by
the
company
in
its
1970
fiscal
year
and
whether
that
amount
was
properly
included
in
computing
the
company’s
income
for
that
year;
secondly,
whether,
upon
the
issuance
of
the
architect’s
certificate,
the
$89,530
holdback
constituted
an
amount
receivable
by
the
appellant
in
its
1970
fiscal
year
and
whether
such
a
receivable
was
properly
included
in
calculating
the
appellant’s
1970
income;
thirdly,
whether
the
$89,530
constituted
part
of
progress
payments
received
by
the
appellant
in
its
1970
taxation
year.
Dealing
with
the
last
question
first—If
I
understood
counsel
for
the
respondent
correctly,
he
contended
that
what
had
been
referred
to
as
a
supplementary
contract
was
in
fact
not
an
addition
to,
but
was
part
of,
the
original
contract
which
terminated
on
August
31,
1970,
and
the
amount
of
$89,530
paid
to
the
appellant
on
or
about
March
27,
1970
was
a
progress
payment
and
not
the
payment
of
a
holdback
since
the
holdback
would
not
have
become
a
receivable
until
August
31,
1970.
This
contention
is
not,
in
my
view,
supported
by
the
facts
of
this
appeal.
The
Niagara
South
Board
of
Education’s
letter
of
March
13,
1970
reads
(Exhibit
A-15):
R
A
McLeod—Director
of
Education
|
250
Thorold
Rd
|
|
West,
Welland,
|
|
Ontario
|
|
March
13,
1970
|
Donald
N
Chapman,
Architect,
|
|
2385
Colborne
Street,
|
|
Niagara
Falls,
Ontario
|
|
Re:
Fort
Erie
Secondary
School
|
|
Attention:
Mr
G
Goulty
|
|
Dear
Sir:
|
|
This
will
confirm
our
meeting
of
March
12,
1970
where
the
following
items
were
discussed
and
agreed
upon
with
the
contractor:
Item
1
The
contract
for
the
work
which
has
been
completed
and
inspected
will
be
terminated
effective
as
of
March
16th.
Item
2
A
new
contract
for
the
items
that
could
not
be
completed
due
to
the
weather
conditions
will
be
drawn
up.
The
items
of
this
pertain
to
the
remaining
paving
to
be
done,
the
remaining
grading
to
be
done,
the
remaining
painting
of
exterior
entrances,
both
sides,
etc,
exterior
window
cleaning
(excluding
greenhouse),
general
site
cleaning
and
exterior
cleaning
and
touch
up
of
the
building.
The
amount
of
the
contract
is
$3,500
for
the
remaining
work
and
all
work
is
to
be
completed
by
June
15th.
The
specifications
and
drawing
of
the
first
contract
will
apply
to
the
new
contract.
Item
3
The
contractor
will
furnish
waiver
of
liens
from
the
sub-contractors
along
with
the
other
certificates
and
documents
required
at
the
termination
of
the
contract.
Also
we
would
like
a
copy
of
the
letters
from
the
General
Contractor
to
his
subs
notifying
them
of
the
commencement
of
the
lien
period.
Yours
very
truly,
NIAGARA
SOUTH
BOARD
OF
EDUCATION
Signed
.
.
.
On
March
16,
1970
Mr
Goulty,
Architect,
forwarded
to
the
appellant
the
following
letter
(Exhibit
A-2):
DONALD
N
CHAPMAN
2385
Colborne
Street
ARCHITECT
Niagara
Falls,
Ontario
D
N
Chapman,
B
Arch,
MRAIC
March
16th,
1970
Dominion
Construction
Co
Ltd,
Box
31,
Niagara
Falls,
Ontario
Attention:
Mr
Iseppon
Re:
Fort
Erie
Secondary
School
Dear
Mr
Iseppon:
Further
to
the
meeting
in
our
office
on
Friday
last,
we
attach
a
photo
copy
of
a
letter
from
the
Board
received
today.
From
this
letter
you
will
note
that
the
amount
contract
is
terminated
with
effect
from
today,
March
16th,
and
that
the
work
covered
by
the
supplementary
contract
must
be
completed
by
June
15th,
1970.
In
order
for
us
to
issue
a
certificate
terminating
the
amount
contract
we
must
attach
copies
of
letters,
from
you
to
your
subs
informing
them
of
the
commencement
of
the
lien
period.
Would
you
please
forward
these
letters
without
delay
in
order
that
we
can
issue
the
certificate
of
termination.
Yours
very
truly,
Gordon
Goulty
(Signed
for
D
N
Chapman,
Architect).
The
original
contract,
by
consent
of
the
interested
parties,
was
formally
terminated
on
March
16,
1970
in
keeping
with
the
provisions
of
section
A-3(b)(1)
of
the
original
contract
dated
April
25,
1969,
which
reads
(Exhibit
A-1):
A-3(b)(1)
Notwithstanding
the
provisions
contained
in
subsection
(2)
above—
(1)
if
on
account
of
climatic
or
other
conditions
reasonably
beyond
the
Contractor’s
control
there
are
items
of
work
that
cannot
readily
be
completed,
the
payment
in
full
for
the
work
which
has
been
completed
shall
not
be
delayed
on
account
thereof,
but
the
Owner
may
withhold
a
sufficient
and
reasonable
sum,
as
determined
by
the
Architect,
until
the
uncompleted
work
is
finished
and
such
sum
as
will
adequately
protect
the
Owner
against
liens;
I
am
satisfied
from
the
record
that
the
main
contract
was
terminated
on
March
16,
1970.
A
new
and
supplementary
contract
was
entered
into
by
the
parties
for
the
work
remaining
to
be
done
(Exhibit
A-7).
The
payment
of
$89,530
calculated
on
the
reduced
amount
of
the
original
contract,
viz
$598.990
(Exhibit
A-10),
was
not
a
progress
payment
on
the
original
contract
of
$602,490
but
was
the
payment
of
the
85%
holdback
provided
for
in
section
A-3(a)(2)
on
the
reduced
original
contract
that
was
terminated
on
March
16,
1970.
Even
if
one
were
to
assume
that
the
amount
of
$89,530
was
a
progress
payment,
the
record
shows
that
in
any
event
the
payment
was
received
between
April
24,
1970
and
the
date
of
its
deposit
in
the
bank
which
was
April
29,
1970.
It
was
also
established
to
the
satisfaction
of
the
Board
that
the
appellant
company’s
fiscal
year
ended
March
31,
1970,
so
that
in
keeping
with
the
decision
in
John
Coif
ord
Contracting
Company
Limited
v
MNR,
[1962]
CTC
546;
62
DTC
1338,
cited
by
counsel
for
the
appellant,
“progress
payments
must
be
taken
into
account
in
the
year
in
which
they
are
received”.
It
cannot
be
held
that
a
progress
payment
of
$89,530,
even
if
it
were
a
progress
payment,
was
received
by
the
appellant
in
its
fiscal
year
ending
March
31,
1970,
and
for
that
reason
it
cannot
be
properly
included
in
the
appellant’s
1970
taxation
year.
The
two
remaining
issues
to
be
determined
are
somewhat
related.
The
first
is
whether
or
not
a
holdback
of
$89,530
was
received
in
the
appellant’s
1970
fiscal
year.
The
second
is
whether
the
amount
of
the
holdback
became
a
receivable
in
the
appellant’s
1970
fiscal
year.
From
the
above
stated
facts
and
the
reasons
already
given,
the
amount
of
$89,530
having
been
received
after
the
end
of
the
appellant’s
1970
fiscal
year,
the
holdback
cannot
in
my
view
properly
be
included
in
calculating
the
appellant’s
income
in
that
year.
As
to
the
contention
that
the
amount
of
$89,530
became
a
receivable
in
the
appellant’s
1970
fiscal
year,
counsel
for
the
respondent
relied
largely
on
the
certificate
of
the
architect
dated
March
20,
1970
(Exhibit
A-17)
which
certifies
that
the
proposed
addition
to
the
Fort
Erie
Secondary
School
project
was
terminated
and
that
the
37-day
lien
period
was
established
as
at
March
17,
1970.
In
my
view
there
are
in
a
construction
project
such
as
the
one
before
us
several
certificates
of
the
architect
issued
for
different
purposes,
and
the
purport
of
each
certificate
has
to
be
taken
into
account.
I
find
it
difficult
to
interpret
the
March
20,
1970
certificate
as
saying
anything
more
than
that
the
project
was
completed
and
accepted
by
the
architect,
and
determines
the
date
when
the
lien
period
was
to
commence.
Pursuant
to
subsection
11(1)
of
The
Mechanics’
Lien
Act
of
Ontario,
the
amount
of
$89,530
was
held
back
for
a
period
of
37
days
after
the
completion
of
the
addition
to
the
Fort
Erie
High
School
in
order
to
ensure
the
Niagara
South
Board
of
Education
that
the
completed
project
was
free
of
structural
defects
and
that
the
appellant
had
honoured
all
its
financial
commitments
in
respect
of
that
project.
The
required
waiver
of
liens
and
other
pertinent
documents
were
forwarded
to
the
architect
on
April
20,
1970
(Exhibit
A-9).
Subsequently,
on
April
27,
1970,
the
architect
issued
another
certificate,
No
11,
entitled
“Release
of
Holdback”
in
which
the
architect
confirms
that
the
contractor
was
entitled
to
the
release
of
the
holdback
of
$89,530
(Exhibit
A-19).
The
actual
amount
of
holdback
payable
to
the
contractor
could
finally
be
determined,
not
only
after
the
project
was
completed
by
the
contractor
and
accepted
by
the
architect,
but
the
amount
of
holdback
also
depended
on
whether
or
not
moneys
were
still
owing
to
the
subcontractors
on
the
project
by
the
contractor.
The
appellant,
in
my
view,
would
have
a
clear
legal
right
to
the
holdback
only
when
both
these
conditions
had
been
met.
The
holdback
therefore
was
finally
determined
only
after
the
architect
had
assured
himself
that
the
contractor
had
no
outstanding
debts
relative
to
the
formally
accepted
project
and
that
he
confirmed
this
fact
by
issuing
the
“Release
of
Holdback”
certificate.
In
my
opinion
the
$89,530
became
a
receivable
on
the
issue
of
the
‘‘Release
of
Holdback”
certificate.
Since
this
certificate
was
issued
on
April
27,
1970,
after
the
expiry
of
the
appellant’s
1970
fiscal
year,
the
appellant
had
no
clear
legal
right
to
the
amount
of
$89,530
and
it
was
not
a
receivable
in
that
year.
Therefore
it
should
not
have
been
included
in
calculating
the
appellant’s
income
for
the
1970
taxation
year.
Paragraph
85B(1)(b)
of
the
Income
Tax
Act
does
not
apply
to
the
facts
of
this
appeal.
The
$89,530
holdback
was
not,
in
my
opinion,
a
receivable
in
the
appellant’s
1970
taxation
year.
Furthermore;
the
section
does
not
apply
because
the
evidence
was
that
the
appellant
company
computed
its
income
only
on
the
completion
of
its
contracts.
This
method
of
computing
the
appellant’s
income
was
not
contested
by
the
respondent,
and
the
Board
must
assume
that
it
was
accepted
by
the
Minister
.The
appellant
therefore
comes
within
the
exception
provided
in
paragraph
85B(1)(b)
of
the
Income
Tax
Act
and
would
not
have
had
to
include
the
holdback
in
its
1970
taxation
year
even
though
the
$89,530
holdback
had
been
considered
a
receivable
in
the
appellant’s
1970
fiscal
year.
I
conclude
that
the
holdback
in
the
amount
of
$89,530
was
not
received,
nor
did
it
constitute
a
receivable
for
the
appellant
in
its
1970
taxation
year
and
was
therefore
improperly
included
in
calculating
the
appellant’s
income
for
that
year.
For
these
reasons
the
appeal
is
allowed.
Appeal
allowed.