Tremblay,
T.C.J.
[Translation]:—This
appeal
was
heard
on
December
5,
1985
at
Québec,
Quebec.
1.
The
Point
at
Issue
According
to
the
pleadings,
the
issue
is
whether
the
appellant,
a
corporation
whose
principal
activity
is
the
provision
of
installation
services
for
industrial
machinery,
is
correct
in
claiming
the
deduction
for
Canadian
manufacturing
and
processing
profits
as
defined
in
paragraphs
125.1
(3)(a)
and
(b)
of
the
Income
Tax
Act
(the
“Act")
in
computing
its
income
for
the
1976,
1977
and
1978
taxation
years.
The
appellant
argues
that
it
operates
a
company
that
manufactures
various
pieces
of
equipment
used,
inter
alia,
by
sawmills
and
pulp
and
paper
mills
in
their
production.
The
respondent
disallowed
the
deduction
of
such
profits,
chiefly
on
the
grounds
that
the
machinery
installed
did
not
belong
to
the
appellant
and,
moreover,
had
not
been
manufactured
by
it.
He
also
contends
that
the
appellant’s
activities
really
relate
to
construction
and,
therefore,
paragraph
125.1(3)(a)
does
not
apply.
2.
The
Burden
of
Proof
2.01
The
burden
is
on
the
appellant
to
show
that
the
respondent's
assessment
is
incorrect.
This
burden
of
proof
results
particulary
from
several
judicial
decisions,
including
the
judgement
delivered
by
the
Supreme
Court
of
Canada
in
Johnston
v.
M.N.R.,
[1948]
S.C.R.
486;
[1948]
C.T.C.
195;
3
D.T.C.
1182.
The
appellant
initially
disputed
this
burden,
but
later
agreed
to
it.
2.02
The
facts
relied
on
by
the
respondent
are
set
out
in
subparas
(a),
(b),
(c)
(d)
and
(e)
of
paragraph
6
of
the
respondent's
reply
to
the
notice
of
appeal.
This
paragraph
reads
as
follows:
6.
In
reassessing
[sic]
the
appellant
for
the
1976,
1977,
and
1978
taxation
years,
the
respondent
relied,
inter
alia,
on
the
following
presumed
facts:
(a)
During
the
taxation
years
in
question,
the
appellant’s
principal
activity
was
the
provision
of
installation
and
erection
services
for
industrial
machinery
as
indicated
in
its
income
tax
return
for
the
1978
taxation
year;
(b)
The
machinery
installed
by
the
appellant
did
not
belong
to
it
and
was
not
manufactured
by
it;
(c)
The
appellant’s
activities
were
in
fact
related
to
construction;
(d)
For
the
purposes
of
the
excise
tax,
the
appellant
did
not
qualify
as
a
manufacturer;
(e)
During
the
taxation
years
in
question,
the
appellant’s
manufacturing
and
processing
activities
represented
less
than
10
per
cent
of
its
gross
income.
3.
Discontinuance
and
Admissions
During
the
investigation,
counsel
for
the
appellant
discontinued
the
appeal
in
respect
of
the
1976
taxation
year.
With
regard
to
the
1977
and
1978
taxation
years,
the
reassessments
were
based
on
50
contracts
according
to
Exhibit
A-1,
a
handwritten
worksheet
used
by
the
respondent's
auditors,
Mr.
Guy
Portelance
and
Mr.
Jacques
Dubé.
Exhibit
A-2
is
a
typewritten
summary
of
Exhibit
A-1
and
lists
the
1977
contracts,
numbered
from
1
to
9
and
the
1978
contracts
from
10
to
48
(no.
45
includes
two
contracts,
and
no.
48,
three
contracts.
There
is
no
contract
no.
47).
The
1977
contracts
total
$306,748.79
and
the
1978
contracts,
$662,079.73.
According
to
the
reassessments,
only
five
of
these
contracts
(nos.
1,
10,
11,
22,
46)
are
eligible
for
the
manufacturing
and
processing
deduction
of
$18,000
in
1977
(contract
no.
1)
and
$43,813
in
1978.
These
were
accordingly
allowed
by
the
respondent
and
treated
as
such
in
the
reassessments.
It
should
be
noted
that
the
$43,813
figure,
which
includes
$17,818
for
contract
no.
11
(Exhibit
A-2)
and
which
was
admitted
by
the
respondent
during
the
investigation
(Exhibit
A-1)
as
being
in
relation
to
the
processing
of
goods
for
sale,
is
thus
allowed
as
“Canadian
manufacturing
and
processing
profits".
Twenty-nine
of
the
other
46
contracts
were
not
entered
in
evidence
by
the
appellant,
2
in
1977
(nos.
2
and
8)
totalling
$128,845.29
and
27
in
1978
(nos.
12
to
18,
20,
24
to
29,
30,
36,
39
to
45
(2)
and
48(3))
totalling
approximately
$301,326.
The
appellant
has
therefore
admitted
that
these
contracts
do
not
meet
the
requirements
for
the
"manufacturing
and
processing
profits"
deduction.
In
addition,
16
contracts
were
put
in
evidence
by
the
appellant
and
the
Court
must
reach
a
decision
as
to
their
status.
The
following
six
contracts
(nos.
3,
4,
5,
6,
7
and
9)
relating
to
1977
are
worth
over
$170,000
or
57
per
cent
of
$310,019,
which
is
the
turnover
for
1977
according
to
the
financial
statements.
As
for
1978,
the
other
ten
contracts
(nos.
19,
21,
23,
30,
32,
33,
34,
35
37
and
38)
total
more
than
$350,000.
This
is
approximately
53
per
cent
of
$720,995,
the
turnover
for
1978
according
to
the
financial
statements.
4.
The
Facts
A.
General
4.01
Two
witnesses
testified:
Mr.
Gilles
Bouchard,
president
and
director
general
of
the
appellant,
and
Mr.
Roland
Gauthier,
C.A.,
the
appellant’s
financial
adviser
and
auditor.
4.02
Mr.
Bouchard
testified
that:
(a)
the
appellant,
incorporated
in
May
1975,
specialized
in
the
installation
of
industrial
machinery
generally
in
sawmills
and
paper
mills;
a
significant
amount
of
machinery
was
also
installed
at
the
Alcan
factory;
(b)
the
appellant
leased
two
buildings,
approximately
4,000
square
feet
in
size,
both
located
on
rue
Vimy
in
Chicoutime-Nord,
Quebec;
these
buildings
were
used
as
factory
space.
In
addition,
the
appellant
also
had
a
5,000
to
6,000
square
foot
warehouse;
material
such
as
steel
beams
and
so
forth
was
also
stored
on
the
property;
(c)
at
the
time
of
the
hearing
the
appellant’s
annual
turnover
in
1984
and
1985
was
$7
million;
(d)
installation
of
machinery
in
a
sawmill
takes
place
after
construction
of
the
building
has
been
completed,
with
the
exception
of
large
machines
which
are
installed
prior
to
the
completion
of
construction,
since
it
would
be
impossible
to
install
such
machinery
once
construction
was
completed;
(e)
some
machines
(such
as
debarkers,
edgers,
planing
machines,
motors
and
so
on)
were
bought
by
the
customer
(the
sawmill
owner)
and
some
or
all
of
the
base
plates
for
this
machinery
were
manufactured
at
the
appellant’s
factory
and
then
transported
to
the
client's
factory
and
affixed
to
the
floor;
the
said
machines
were
then
attached
to
the
bases
under
the
supervision
of
representatives
(engineers
or
others)
of
the
vendors
of
the
said
machinery.
In
comparison
to
the
project
as
a
whole,
such
installations
represented
a
very
small
part;
(f)
in
addition
to
the
bases,
the
appellant
also
manufactured
slabs,
sheet
steel
tanks,
belt
guards
linking
motors,
ladders,
walkways,
railings;
(g)
twenty
per
cent
of
the
work
related
to
the
manufacture
of
the
base
plates,
slabs,
tanks
and
belt
guards
was
done
at
the
appellant's
factory
and
80
percent
on
the
customer's
premises;
the
large
preportion
of
on-site
manufacture
is
attributed
to
the
numerous
adjustments
required
to
adapt
the
plates
to
site
characteristics;
(h)
in
1977
and
1978,
the
appellant
had
between
16
and
100
employees;
(i)
contracts
were
usually
obtained
by
tenders,
but
occasionally
at
the
customer's
invitation.
In
the
Province
of
Quebec
there
were
only
five
or
six
other
outfits
in
the
business
of
mechanical
installation;
(j)
according
to
the
contracts,
material
and
labour
were
allocated
as
follows:
25
to
33
per
cent
for
materials
and
6624
per
cent
for
labour.
4.03
Mr.
Roland
Gauthier,
the
appellant’s
auditor,
testified
that
an
agreement
had
been
reached
with
the
provincial
tax
department
and
Revenue
Canada
respecting
sales
tax
in
accordance
with
their
respective
jurisdictions.
When
the
customer
issued
a
purchase
order
and
marked
it
"exempt"
(see,
for
example,
Alcan,
Exhibits
A-3,
A-4,
A-5,
A-6),
the
appellant
first
paid
the
sales
tax
on
the
cost
of
material
and
then
claimed
the
reimbursement.
Because
of
that
agreement,
the
appellant
said,
it
never
had
to
apply
for
registration
as
a
manufacturer
for
purposes
of
the
excise
tax.
4.04
It
is
important
to
note
that
Exhibit
A-1,
the
auditor's
work
sheet
on
which
the
reassessment
was
based,
contains
a
breakdown
showing
the
percentage
of
manufacturing
and
processing
activities
engaged
in
by
the
appellant
compared
to
gross
income
for
the
two
years
in
question:
1977
—
$18,000
as
against
$306,748.79
or
six
per
cent
1978
—
$43,813
as
against
$662,079.73,
or
seven
per
cent
The
ten
per
cent
minimum
required
by
subparagraph
125.1
(3)(b)(x)
of
the
Act,
para.
5.01,
infra,
has
not
therefore
been
met.
Evidence
concerning
the
contracts
in
dispute
is
therefore
of
significant
importance.
B.
The
Disputed
Contracts
4.05
The
first
disputed
contract
(no.
3,
Exhibit
A-2)
for
$11,705
($4,785
for
materials
and
$6,920
for
labour)
relates
to
a
purchase
order
dated
January
13,
1977
from
Alcan.
Among
other
things
it
required
that
work
commence
on
January
10,
1977
(Exhibit
A-3).
The
work
was
therefore
already
underway
when
the
order
was
issued.
The
work
to
be
performed
was
as
follows:
repair
"the
hopper
—
building
310
in
accordance
with
the
sketch
attached
hereto
and
Mr.
R.
Lennox's
verbal
instructions".
Mr.
Lennox
is
probably
the
Alcan
engineer.
The
hopper
was
a
tank
(with
a
bevelled
base)
that
collected
the
material
from
the
electrolytic
cell.
Steel
sheets
or
plates
furnished
by
the
appellant
were
used
to
make
the
repair.
4.06
The
second
disputed
contract
(no.
4,
also
with
Alcan)
amounted
to
$5,644.20.
It
was
also
dated
January
13,
1977
and
was
entered
as
part
of
Exhibit
A-3.
It
was
actually
an
addition
to
contract
no.
2.
It
provided
for
installing
guiding
slabs
on
the
conveyor
to
prevent
the
materials
from
overturning.
4.07
The
third
disputed
contract
(no.
5,
Exhibit
A-2)
amounted
to
$97,535.
This
purchase
order
from
Alcan
was
dated
December
16,1976
(Exhibit
A-4).
This
contract
resulted
from
the
strike
in
1976
that
left
137
cells
full
of
hardened
or
congealed
material.
Alcan
made
the
necessary
repairs
to
the
cells
to
get
them
back
into
production.
The
order
gave
a
rather
terse
description
of
the
work
to
be
done:
TO
COVER
YOUR
SERVICES
AND
THE
MATERIALS
REQUIRED
FOR:
ON
137
SODERBERG
ANODE
CELLS
IN
ONE
OR
TWO
CELL
ROOMS
SOLDER,
FLEXIBLE,
ANODE
BUS
BARS,
HANGERS,
ANGLE
BARS
AND
SEAL-BOX
IN
ACCORDANCE
WITH
OUR
CONTRACT
NO.
20-36-76,
dated
December
16,
1976.
In
short,
the
work
consisted
of
installing
hangers
to
facilitate
connection
of
the
anode
bus
bars
between
adjoining
cells.
A
cell
is
20
feet
long
by
10
feet
wide
by
16
feet
high.
The
anode
bus
bars
were
electrical
conductors
that
had
jumped
following
the
strike.
The
bus
bar
was
an
integral
part
of
the
cell.
Bases
had
to
be
made
which
involved
installing
the
base
on
the
floor,
cutting
the
angle-iron
flush
with
the
steel
plates
and
soldering.
Even
when
Alcan
provided
some
of
the
angle
bars
that
it
had
in
stock,
they
had
to
be
"worked"
on
and
adapted.
In
connection
with
this
work,
the
respondent's
auditor
wrote
in
Exhibit
A-1:
"137
cells,
construction,
because
it
involves
work
on
components
affixed
to
the
building".
4.08
The
fourth
disputed
contract
(no.
6,
Exhibit
A-2)
totalling
$19,500
($3,500
for
materials
and
$16,000
for
labour)
was
an
addition
to
the
preceding,
contract
no.
5.
It
was
also
dated
December
16,
1977
and
was
part
of
Exhibit
A-4.
It
referred
to
the
purchase
order
for
contract
no.
5.
The
work
to
be
performed
was
described
as
follows:
TO
COVER
INSTALLATION
AND
SOLDERING
OF
STEEL
AND
ALUMINUM
ANGLES
AND
ALUMINUM
SQUARE
RODS
ON
THE
BUS
BARS
AND
CELLS
TO
SUPPORT
THE
INSULATORS
WHICH
WILL
SEAL
CELL
ENDS.
ALL
MATERIAL
AND
LABOUR
IS
(sic)
PROVIDED
BY
THE
CONTRACTOR
FOR
BEFORE
FRIDAY,
MARCH
11,
1977
AT
4
O'CLOCK.
The
auditor’s
note
for
Exhibit
A-1
was
“of
the
same
kind
as
5”,
i.e.
construction,
since
affixed
to
the
building.
4.09
The
fifth
disputed
contract
(no.
7,
Exhibit
A-2)
for
$13,956
was
dated
February
4,1977
(Exhibit
A-5).
The
work
began
on
February
1.
This
contract
was
also
with
Alcan.
The
work
to
be
performed
was
described
as
follows:
TO
COVER
MATERIALS
AND
LABOUR
FOR
THE
INSTALLATION
OF
NEW
VALVES
FOR
UNLOADING
BAUXITE
ON
BELTS
BC-5
AND
BC-12,
ACCORDING
TO
THE
SKETCH
ATTACHED
HERETO
AND
PLANS
A-62210-AC,
A-622011-AC
and
A-62212-AC
AND
YOUR
LETTER
OF
JANUARY
31,
1988
[sic].
THE
WORK
COVERED
BY
THIS
CONTRACT
ORDER
SHOULD
COMMENCE
ON
FEBRUARY
1,
1977
AND
BE
COMPLETED
BY
MARCH
17,
1977.
According
to
the
witness,
the
train
unloaded
alumina
(washed
bauxite)
onto
a
filter
above
the
conveyer.
The
new
valves
made
of
sheet
steel
were
supposed
to
do
a
better
job
of
guiding
the
alumina
along
the
belts
and
to
close
if
necessary.
There
was
a
glider
system
to
allow
the
valve
to
open
and
close.
The
gliders
were
made
by
the
appellant
and
affixed
to
the
ceiling
and
floor.
The
new
mechanism
allowed
the
loading
of
the
conveyer
to
be
stopped
by
closing
the
valve.
On
this
subject,
the
comment
of
the
respondent's
auditor
(Exhibit
A-1)
was:
“affixed
to
the
building”’.
4.10
The
sixth
disputed
contract
(no.
9,
Exhibit
A-2),
dated
March
25,
1977,
amounted
to
$11,563
(Exhibit
A-6).
The
job
was
to
commence
on
March
28
and
to
end
on
April
25.
This
contract
was
also
with
Alcan.
The
job
was
described
as
follows:
FOR
THE
CONSTRUCTION
OF
A
FUME
EVACUATION
SYSTEM
ACCORDING
TO
OUR
DESIGN
A-62959-AC
AND
INSTRUCTIONS
DATED
MARCH
10,
1977.
On
the
letter
of
March
10,
1977,
entered
as
part
of
Exhibit
A-6,
the
Court
read:
“The
contractor
will
have
to
do
the
excavation
for
a
fume
evacuation
system
as
shown
on
drawing
B-62960-AC".
According
to
the
witness,
the
purpose
of
the
ventilation
system
was
to
remove
fumes
from
the
cells.
The
fumes
were
caused
by
the
smelting
of
alumina
in
the
cells.
The
ventilation
system
was
provided
by
Alcan,
but
the
work
consisted
of
placing
the
said
system
on
a
steel
base
manufactured
by
the
appellant
and
in
joining
the
whole
thing
to
the
chimney
by
a
system
of
piping
manufactured
by
the
appellant.
On
this
subject,
the
auditor’s
comment
for
the
respondent
(Exhibit
A-1)
was:
“affixed
to
the
building
for
ventilation".
4.11
The
seventh
disputed
contract
(no.
19,
Exhibit
A-2)
amounted
to
$6,780
and
was
dated
October
24,
1977
(Exhibit
A-11).
The
purchase
order
from
Alcan
described
the
work
to
be
performed
as
follows:
TO
COVER
LABOUR,
SUPERVISION,
EQUIPMENT
AND
MATERIALS
REQUIRED
FOR
THE
INSTALLATION
OF
A
STEEL
PLATE
ON
THE
NORTH
WALL
OF
CASTING
SECTION
32
AS
PER
DRAWING
A0-93595-R—00.
THE
WORK
COVERED
BY
THIS
ORDER
CONTRACT
(sic)
SHALL
COMMENCE
ON
NOVEMBER
26,
1977
AND
SHALL
BE
COMPLETED
BY
DECEMBER
1977.
SCHEDULE
“A”
ATTACHED
HERETO
FORMS
PART
OF
THIS
CONTRACT
ORDER.
According
to
the
witness,
the
purpose
of
installing
the
said
plate
was
to
protect
the
north
wall
because
it
was
near
where
the
molten
aluminum
was
poured
to
manufacture
rolls
or
plates.
Moreover,
the
appellant
had
placed
two
poles
joined
by
pipes,
manufactured
by
the
appellant,
to
“prevent
the
fork
lifts
from
knocking
against
each
other
and
the
material”.
(Transcript,
p.
50).
4.12
The
eighth
disputed
contract
(no.
21,
Exhibit
A-2)
issued
by
Alcan
was
an
addition
to
the
preceding
contract
(Exhibit
A-11
).
The
purchase
order
for
$1,521
was
also
dated
October
24,1977
and
was
the
Schedule
A
mentioned
in
the
preceding
contract
(supra
para.
4.11).
In
this
case,
it
involved
“a
modification
to
the
east
wall
of
casting
pit
C-32
as
per
our
discussion
..
.”
According
to
the
witness,
the
job
involved
placing
steel
plates
inside
the
elevator
shaft
“.
.
.
it’s
not
an
elevator
that's
being
put
in
there
.
.
.
It’s
at
the
bottom
of
the
hole,
there
is
a
kind
of
“jack”
that
takes
the
big
pieces
of
aluminum
and
gently
lifts
them
up.
It
comes
in
and
it
raises
it
at
the
same
time
that
it
“fits",
it
raises
it.
It’s
called
an
elevator,
but
it’s
...
a
jack”
(Transcript,
p.
51).
The
steel
plates
were
cut
and
installed
on
the
walls
inside
the
hole;
the
said
plates
were
bolted
on.
4.13
The
ninth
disputed
contract
(no.
23,
Exhibit
A-2)
was
with
the
Price
Company
(as
were
all
contracts
nos.
22
to
36,
incidentally).
The
amount
involved
was
$5,790.
It
was
set
out
in
purchase
order
no.
KKA—114804,
dated
August
22,1977
with
four
other
pieces
relating
to
contracts
nos.
33,
34
and
35.
It
is
part
of
Exhibit
A-10.
The
description
on
the
purchase
order
reads
as
follows:
TO
EFFECT
THE
FINAL
CONNECTIONS
BETWEEN
THE
NEW
LINES
AND
EXISTING
LINES
ON
THE
BY-PASS
CLARIFIER
PROJECT
AND
ON
THE
SEWER
CLEANER
PROJECT,
AS
PER
YOUR
TENDER
178-77-KK1-161
OF
AUGUST
12,
1977
AND
THE
ANNUAL
CONTRACT
SIGNED
ON
JULY
27,
1977.
According
to
the
witness,
the
work
of
making
the
final
connection
between
the
by-pass
tank
and
the
sewer
tank
consisted
chiefly
of
labour
and
hardly
involved
any
materials.
This
contract
(no.
23)
which
was
carried
out
toward
the
end
of
August
1977
would
have
been
performed
at
the
same
time
as
the
three
others
(33,
34,
35),
if
the
factory
had
not
been
in
operation
when
the
appellant
finished
the
sewer
system.
4.14
Given
that
contracts
nos.
33,
34
and
35
belong
together
with
contract
no.
23
(para.
4.13),
all
filed
as
Exhibit
A-10,
it
is
appropriate
to
consider
them
here.
4.14.1
Contract
no.
33,
the
tenth
disputed
contract,
was
provided
for
under
purchase
order
no.
112339
dated
June
23,
1977
and
the
tender
letter
of
the
appellant
to
the
Price
Company
dated
May
16,
1977.
These
documents
show
that
basically
the
work
consisted
of
installing
piping
and
pumps
for
the
sewer
cleaner
at
a
cost
of
$32,240
($25,700
for
labour
and
$6,540
for
materials).
According
to
the
witness
“.
.
.
it
was
pipes
.
.
.
that
were
brought
in,
that
were
cut,
that
were
fit,
that
joints
were
made
in
so
it
would
fit,
that
sort
of
thing"
(Transcript,
p.
46).
After
soldering,
the
pipes
were
suspended
from
the
ceiling
by
the
support
beams.
As
in
a
paper
mill,
the
witness
explained,
there
are
many
open
drains
in
the
floor
to
collect
“all
the
liquid
from
everywhere"
and
channel
it
into
a
holding
tank
(Transcript,
p.
47).
The
pipes
installed
under
contract
no.
33
took
the
waste
liquid
from
the
holding
tank
to
a
cleaner
to
be
clarified.
This
clarified
liquid
was
then
moved
along
to
another
tank
and
when
it
came
out
was
“white
water”.
This
tank
was
linked
to
another
system
which
used
the
white
water
in
the
paper
manufacturing
process.
4.14.2
Contract
no.
34,
the
eleventh
disputed
contract,
(order
of
July
27,
1977,
no.
KKA-112339)
was
an
addition
to
contract
no.
33.
The
order
reads
as
follows:
“To
cover
pipe
work,
an
extra
on
the
original
contract.
This
work
is
due
either
to
certain
modifications
made
in
the
plans
or
to
errors
on
these
plans
or
to
changes
to
the
equipment
already
installed?"
The
price
was
$7,371,
or
409.5
hours
at
$18
an
hour.
There
was
no
provision
for
materials
in
this
contract.
Furthermore,
on
this
order,
the
Court
read:
ORIGINAL
CONTRACT
AMOUNT
|
$32,240.00
|
TOTAL
ADDITIONAL
WORK
|
$7,371.00
|
4.14.3
Contract
no.
35,
the
twelfth
disputed
contract,
for
$2,450
($1,800
for
labour
and
$650
for
materials)
involved
manufacturing
and
installing
a
walkway
"to
reach
the
recently
installed
valves
on
the
sewer
cleaner
project"".
This
was
all
provided
for
under
purchase
order
KKA-113827
dated
August
1,
1977.
All
this
work
(contracts
nos.
23,
33,
34
and
35)
was
done
at
the
Kénogami
factory.
4.15
The
thirteenth
disputed
contract
(no.
30,
Exhibit
A-2)
involved
$4,151
($900
for
materials
and
$3,251
for
labour).
According
to
purchase
order
KKA
113915
dated
August
3,
1977
(Exhibit
A-12)
the
job
involved
"the
installation
of
a
screw
conveyor
and
replacing
the
chute
in
the
chip
cyclone
chute
digester
service"".
According
to
the
witness,
the
job
basically
involved
making
bases
to
set
the
conveyor
on.
There
was
$900
for
materials
and
$3,251
for
labour.
4.16
The
fourteenth
disputed
contract
(no.
32,
Exhibit
A-2)
was
also
with
the
Price
Company.
It
involved
$75,200,
as
per
purchase
order
KKA
114929,
dated
August
25,
1977
(Exhibit
A-9).
The
work
to
be
performed
was
described
as
follows:
"To
perform
all
mechanical
work
required
to
install
the
foundation
for
the
new
Jagenberg
cutter
.
.
.""
According
to
the
witness,
it
meant
installing
a
German-made
board-cutting
machine
on
a
base
constructed
by
the
appellant.
To
do
this,
the
appellant’s
employees
had
to
break
open
the
cement
floor,
set
beams
and
repour
the
cement.
To
make
the
base
required,
he
said,
50
per
cent
material
and
50
per
cent
labour.
The
cost
was
approximately
$50,000.
It
had
cost
$25,000
just
to
install
the
cutter
once
the
base
was
completed.
It
was
complicated.
4.17
The
fifteenth
disputed
contract
was
awarded
by
Donohue
St-Félicien
Inc.
for
the
sawmill
at
Millage
54,
Chibougamau
Division.
In
contract
no.
37
(Exhibit
A-2),
the
amount
involved
was
$42,924.87.
The
purchase
order
of
March
30,
1978
(Part
of
Exhibit
A-7)
showed,
however,
$116,000.
It
appears
that
only
$42,924.87
was
included
in
income
for
1978.
The
reason
is
that
the
job
had
continued
during
the
1979
taxation
year,
and
the
balance
of
the
income
from
it
was
included
in
that
year.
The
work
to
be
performed
was
described
as
follows:
"To
provide
all
labour
required
to
perform
mechanical
installation
work
and
all
equipment
required
for
this
pursuant
to
our
call
for
tenders
4160793-3.7.2
and
your
bid
dated
March
14,
1978
.
.
.”.
According
to
the
witness,
the
job
involved
installing
all
the
machinery
that
would
be
needed
in
a
sawmill:
planers,
edgers,
canters,
saws,
and
so
on
and
all
the
conveyor
belts
for
moving
the
wood.
These
conveyors
took
up
60
per
cent
of
the
factory
area
(Transcript
p.
29).
The
appellant
did
not
manufacture
or
purchase
all
these
machines.
It
only
did
the
installation
and
the
bases
and
shortened
or
lenghtened
the
feet
of
the
machines
as
re-
quired.
Seventy-five
per
cent
of
the
total
cost
of
the
job
went
to
supplying
and
manufacturing
the
bases
and
25
per
cent
to
installing
the
machinery
on
the
bases
(Transcript,
p.
31).
4.18
The
sixteenth
disputed
contract,
for
$175,712.51,
was
also
awarded
by
Donohue
St-Félicien
Inc.
for
the
Girardville
mill
(no.
38,
Exhibit
A-2).
The
work
was
of
the
same
nature
as
in
the
case
of
the
sawmill
at
Millage
54,
Chibougamau
Division
(para.
4.17).
The
work
of
mechanical
installation
included
such
sawmill
equipment
as
conveyors,
planing
machines,
eight
debarkers
and
so
on.
According
to
Mr.
Bouchard,
the
appellant
"manufactured
what
it
needed”
for
the
machines
purchased
by
Donohue
to
make
a
sawmill,
namely
bases,
ladders,
ramps,
walkways,
and
so
on.
A
series
of
13
photographs
numbered
from
A-8.1
to
A-.8.13
shows
the
bases
of
the
conveyors,
the
debarkers,
the
beams
used
as
foundations
for
the
walkways
and
so
on.
The
contract
was
introduced
in
evidence
as
part
of
Exhibit
A-7.
The
difference
between
$98,500
and
$175,712
is
attributed
to
additional
work
arising
out
of
the
installation,
Incidentally,
the
quantum
is
not
in
dispute.
Seventy-five
per
cent
of
$175,712
was
for
manufacturing
and
installing
the
bases
(Transcript,
p.
35).
5.
Act
—
Case
Law
—
Analysis
5.01
Act
The
provisions
chiefly
involved
in
this
case
are
paragraphs
125.1
(3)(a)
and
(b)
of
the
Income
Tax
Act
and
section
5200
of
the
Income
Tax
Regulations.
These
provisions
read
as
follows:
125.1(3)
Definitions.
In
this
section,
(a)
“Canadian
manufacturing
and
processing
profits”
of
a
corporation
for
a
taxation
year
means
such
portion
of
the
aggregate
of
all
amounts
each
of
which
is
the
income
of
the
corporation
for
the
year
from
an
active
business
carried
on
in
Canada
as
is
determined
under
rules
prescribed
for
that
purpose
by
regulation
made
on
the
recommendation
of
the
Minister
of
Finance
to
be
applicable
to
the
manufacturing
or
processing
in
Canada
of
goods
for
sale
or
lease
and
(b)
“manufacturing
or
processing”
does
not
include
(i)
farming
or
fishing,
(ii)
logging,
(iii)
Construction,
(iv)
operating
an
oil
or
gas
well,
(v)
extracting
minerals
from
a
mineral
resource,
(vi)
processing
to
the
prime
metal
stage
or
its
equivalent,
ore
from
a
mineral
resource,
(vii)
producing
industrial
minerals
other
than
sulphur
produced
by
processing
natural
gas,
(viii)
producing
or
processing
electrical
energy
or
steam,
for
sale,
(ix)
processing
gas,
if
such
gas
is
processed
as
part
of
the
business
of
selling
or
distributing
gas
in
the
course
of
operating
a
pubic
utility,
or
(x)
any
manufacturing
or
processing
of
goods
for
sale
or
lease
if,
for
any
taxation
year
of
a
corporation
in
respect
of
which
the
expression
is
being
applied,
less
than
10%
of
its
gross
revenue
from
all
active
businesses
carried
on
in
Canada
was
from
(A)
the
selling
or
leasing
of
goods
manufactured
or
processed
in
Canada
by
it,
and
(B)
the
manufacturing
or
processing
in
Canada
of
goods
for
sale
or
lease,
other
than
goods
for
sale
or
lease
by
it.
5200.
Subject
to
section
5201,
for
the
purposes
of
paragraph
125.1
(3)(a)
of
the
Act,
“Canadian
manufacturing
and
processing
profits”
of
a
corporation
for
a
taxation
year
are
hereby
prescribed
to
be
that
proportion
of
the
corporation’s
adjusted
business
income
for
the
year
that
(a)
the
aggregate
of
its
cost
of
manufacturing
and
processing
capital
for
the
year
and
its
cost
of
manufacturing
and
processing
labour
for
the
year,
is
of
(b)
the
aggregate
of
its
cost
of
capital
for
the
year
and
its
cost
of
labour
for
the
year.
5.02
Case
law
and
doctrine
The
parties
referred
the
Court
to
the
following
case
law
and
doctrine:
1.
Les
Ateliers
Benoit
Allard
Inc.
v.
M.N.R.,
[1984]
C.T.C.
2189;
84
D.T.C.
1131
(T.C.C.);
2.
Le
Soleil
Limitée
v.
M.N.R.,
[1973]
F.C.
97;
[1973]
C.T.C.
91;
73
D.T.C.
5093
(F.C.A.);
3.
Halliburton
Services
Ltd.
v.
The
Queen,
[1985]
2
C.T.C.
52;
85
D.T.C.
5336
(F.C.T.D.);
4.
Federal
Farms
Limited
v.
M.N.R.,
[1966]
S.C.R.
410;
[1966]
C.T.C.
62;
66
D.T.C.
5068;
5.
The
Queen
v.
York
Marble,
Tile
and
Terrazzo
Limited,
[1968]
S.C.R.
140;
[1968]
C.T.C.
44;
68
D.T.C.
5001;
6.
Frankel
Steel
Construction
Limited
v.
M.N.R.,
68
D.T.C.
144;
7.
Admiral
Steel
Products
Limited
v.
M.N.R.,
40
Tax
A.B.C.
322;
66
D.T.C.
174;
8.
Gruen
Watch
Company
of
Canada
Limited
et
al.
v.
Attorney-General
of
Canada,
[1950]
C.T.C.
440;
50
D.T.C.
784;
9.
Nowegijick
v.
The
Queen,
[1983]
1
S.C.R.
29;
[1983]
C.T.C.
20;
10.
Interpretation
Bulletins
IT-145R
of
June
19,
1981
and
IT-411
of
March
23,
1978.
5.03
Analysis
5.03.1
In
view
of
the
appellant’s
discontinuance
of
its
appeal
in
respect
of
the
1976
contracts
from
April
1,
1975
to
March
31,
1976
and
in
view
of
the
admissions
that
were
made,
the
task
before
the
Court
is
to
analyze
the
16
contracts
placed
in
evidence,
six
for
1977,
from
April
1,
1976
to
March
31,
1977,
and
ten
for
1978,
from
April
1,
1977
to
March
31,
1978
(para.
3.01).
The
first
question
is
whether
manufacturing
and
processing
were
involved
in
the
first
16
contracts.
5.03.2
With
the
exception
of
contract
no.
23,
Exhibit
A-2
(the
ninth
disputed
contract,
see
para.
4.13),
which
the
appellant’s
witness
admitted
involved
only
labour
and
no
materials,
the
evidence
showed
that
manufacturing
and
processing
was
involved
in
the
other
15
contracts.
Contract
no.
23
is
also
analyzed
in
para.
4.03.6
infra.
5.03.3
According
to
the
respondent,
the
fact
that
a
contract
did
involve
manufacturing
and
processing
does
not
mean
that
the
whole
contract
relates
only
to
manufacturing
and
processing.
In
the
case
of
the
installation
of
a
large
machine,
for
example,
making
a
base
or
angle
irons
for
it
may
be
manufacturing,
while,
on
the
other
hand,
the
actual
installation
of
the
machine
with
the
help
of
a
crane
can
hardly
be
considered
manufacturing,
according
to
the
respondent,
and
the
appellant
would
not
have
met
the
burden
of
proof.
At
first
blush,
the
Court
is
of
the
opinion
that
everything
depends
upon
the
proportion
of
the
work
which
is
neither
manufacturing
nor
processing
compared
to
the
work
which
constitutes
manufacturing
and
processing,
in
accordance
with
the
Halliburton
Services
Ltd.
case
studied
below.
Before
I
get
into
that,
I
should
say
that
in
Les
Ateliers
Benoît
Allard
Inc.
(para.
5.2.1.),
there
was
uncontradicted
evidence
that
the
labour
used
for
the
installation
of
machinery
such
as
debarkers,
edgers
and
so
on,
belonging
to
the
appellant's
customers
and
purchased
from
someone
other
than
the
client,
was
only
five
per
cent
of
the
appellant’s
total
labour
cost
(D.T.C.,
p.
1147,
para.
4.03.4).
In
this
appeal,
the
manufacturing
and
processing
work
in
respect
of
which
evidence
was
led
was
performed
in
the
course
of
rendering
a
service,
the
installation
of
machinery.
In
Halliburton
Services
Ltd.,
supra,
an
argument
similar
to
the
respondent's
was
made.
The
Department
of
National
Revenue
argued
that
drilling
oil
wells
was
a
service
and
that
this
work
consisted
almost
entirely
of
labour.
The
Department
also
argued
that
the
processing
activity
was
only
incidental
to
the
service
rendered.
Accordingly,
the
Department
argued
that
it
was
not
manufacturing
and
processing
of
merchandise
for
sale
(see
subparagraph
125.1
(3)(b)(x)
of
the
Act,
supra,
para.
5.01).
The
Court
rejected
that
contention
and
held
that
subparagraph
125.1(3)-
(b)of
the
Act
did
not
necessarily
relate
to
the
sale
of
goods,
but
rather
to
the
profit
from
the
manufacture
or
processing
of
goods
for
sale.
There
is
no
reason
to
distinguish
between
goods
sold
under
a
contract
for
the
sale
of
goods
and
those
sold
under
a
contract
of
service
for
labour
and
materials.
More
specifically,
the
Court
says
in
Halliburton
Services
Ltd.
at
55
(D.T.C.
5338):
There
is
no
doubt
that
the
products
in
question
are
sold
to
the
plaintiff’s
customers
in
the
sense
that
the
invoices
list
the
cost
of
the
various
components
which
go
into
each
product
and
the
blending
and
processing
charges
are
specifically
detailed
in
the
invoice.
Secondly,
I
do
not
find
any
requirement
that
the
contract
which
gives
rise
to
the
taxpayer’s
profit
must
be
of
a
particular
nature,
e.g.:
one
for
the
sale
of
goods
and
not
one
of
a
more
extensive
nature
involving
work
and
labour
as
well
as
the
goods
or
material
supplied.
In
my
view
it
is
the
source
of
the
profit,
(arising
out
of
processing)
that
is
important
for
the
purposes
of
paragraph
125.1(3)(b),
not
the
nature
of
the
taxpayer’s
contract
with
its
customers.
In
the
third
place,
to
adopt
the
distinction
for
which
the
defendant
argues
would
be
to
create
an
illogical
result.
As
counsel
for
the
plaintiff
pointed
out,
under
such
a
regime,
a
manufacturer
or
processor
of
a
product
(e.g.:
a
chemical
fertilizer)
who
also
provided
a
service
in
connection
therewith
(e.g.:
spreading
the
fertilizer
for
his
customers)
would
be
denied
the
processing
tax
deduction.
If
he
merely
sold
the
produce
to
his
customers
he
would
be
allowed
the
deduction.
5.03.4
A
simple
reading
of
Bouchard’s
evidence
relating
to
the
disputed
1977
contracts
(i.e.,
all
the
contracts
with
Alcan,
see
para.
4.05,
4.06,
4.07,
4.08,
4.09,
4.10)
makes
it
clear
that
the
manufacture
of
bases
for
the
gliders
and
so
on
was
the
main
subject
of
the
contracts.
The
auditor
viewed
much
of
this
as
construction
work
because
it
was
affixed
to
the
building.
It
is
obvious,
as
Bouchard
testified,
that
all
this
material
"could
not
be
held
up
by
thin
air".
The
Court
already
touched
on
that
aspect
in
Les
Ateliers
Benoît
Allard
Inc.
(supra),
and
it
also
made
reference
to
Interpretation
Bulletin
IT-411
in
para.
4.03.7,
at
p.
1147.
This
reads
as
follows:
4.03.7
Furthermore,
even
if
the
equipment
sold
by
the
appellant
which
was
installed
and
affixed
with
solder
and
nails
thereafter
constituted
immovables
by
destination
within
the
meaning
of
the
Civil
Code,
so
far
as
the
customer
was
concerned,
it
nonetheless
remained
a
sale
for
the
appellant
and
to
that
extent
it
was
not
a
construction
activity.
Both
counsel
admitted
as
valid
the
description
of
a
construction
activity
given
in
paragraph
3
of
Interpretation
Bulletin
IT-411.
Even
though
the
Court
is
not
bound
by
these
bulletins,
it
feels
that
in
the
case
at
bar
at
least
the
description
is
accurate:
3.
As
a
general
rule,
the
on-site
fabrication,
installation
and
erection
of
machinery
and
equipment,
regardless
of
size,
is
not
considered
to
be
construction,
unless
it
constitutes
a
component
part
of
a
building
or
structure
(e.g.
—
heating
system,
air-conditioning
equipment,
sprinkler
system,
plumbing,
wiring,
etc).
Machinery
or
equipment
which
will
form
an
integral
part
of
a
manufacturing
or
processing
activity
carried
on
inside
a
building
is
not
regarded
as
a
component
part
of
the
building,
even
though
it
may
be
firmly
attached
to
it
because
of
vibrations,
weight,
size,
etc.
In
some
cases,
where
the
installation
of
machinery
and
equipment
coincides
with
the
construction
and
erection
of
a
building
or
other
structure,
there
may
be
practical
difficulties
in
determining
what
activities
are
construction.
In
these
cases,
the
following
criteria
apply:
(a)
The
installation
and
erection
of
the
foundation,
walls,
floors,
roof
and
infrastructure
for
the
machinery
or
equipment
(i.e.
—
pilings
footings,
piers,
pillars,
pits,
etc.)
is
regarded
as
construction.
(b)
The
fabrication,
installation
and
erection
of
the
machinery
and
equipment
inside
the
structure
(including
related
wiring,
plumbing,
ductwork,
etc.)
that
is
primarily
for
the
purpose
of
a
manufacturing
or
processing
activity
which
will
be
carried
on
inside
the
structure
is
not
regarded
as
construction.
5.03.5
The
disputed
1978
contracts
(paras.
4.1
to
4.18)
principally
relate
to
work
performed
in
lumber
mills,
with
the
exception
of
contracts
nos.
19
and
21
of
Exhibit
A-2
(paras.
4.11
and
4.12)
which
consisted
of
work
for
Alcan.
The
two
Alcan
contracts
required
steel
plates
to
be
installed
on
the
north
wall
in
the
casing
section
and
on
the
east
wall
of
the
casting
pit
or
elevator
shaft.
The
respondent
argued
that
the
contracts
did
not
involve
manufacturing
or
processing
but
rather
construction.
According
to
the
evidence,
this
casting
pit,
if
the
Court
correctly
understood
the
technical
details,
is
crucial
to
the
processing
of
molten
aluminum
in
rolls
and
plates.
A
jack
lifts
large
pieces
of
aluminum
in
this
pit.
It
appears
to
the
Court
that
the
plates
installed
in
the
pit,
just
like
the
poles
that
were
joined
by
pipes
to
prevent
the
forks
of
the
jack
(or
of
the
elevator)
from
knocking
against
the
walls,
form
an
integral
part
of
the
whole
system
that
manufactures
aluminum
plates
and
rolls
from
molten
aluminum.
Accordingly,
the
Court
is
of
the
opinion
that
the
installation
of
the
plates,
poles
and
pipes
is
not
part
of
the
construction
of
the
building
but
rather
part
of
manufacturing
and
processing
within
the
meaning
of
the
Act.
5.03.6
The
other
disputed
contracts
for
1978
involve
work
performed
in
lumber
mills.
Contract
no.
23
of
Exhibit
A-2
(para.
4.13)
for
$5,790
involves
labour
only
and
does
not
at
first
appear
to
be
manufacturing.
The
Court
must
consider,
however,
that
it
represents
the
final
stage
completing
a
group
of
three
other
contracts,
nos.
33,
34
and
35
of
Exhibit
A-2.
The
three
contracts
involved
the
construction
of
a
piping
system
for
moving
waste
water
into
a
tank
to
be
clarified
or
purified
for
re-use
in
the
paper
manufacturing
process.
This,
in
my
opinion,
is
not
construction
but
involves
an
entire
component
required
directly
in
the
production
of
paper,
namely
manufacturing.
Contract
no.
23
was
the
final
phase.
It
involved
connecting
already
existing
lines
of
pipe
to
the
pipelines
that
had
just
been
built
under
contracts
nos.
33,
34
and
35.
This
contract
required
labour
only.
In
response
to
the
question
as
to
whether
the
new
system
could
function
independently
of
the
old
one,
the
Court
decided
that
because
of
the
nautre
of
the
work
it
could
not.
Connecting
the
two
systems
required
only
labour
and
was
absolutely
vital
to
the
operation
of
the
new
system.
Also,
when
the
sewer
system
(contracts
nos.
33,
34
and
35)
was
completed,
it
would
have
been
connected
up
immediately,
(contract
no.
23),
but
for
the
fact
that
the
paper
mill
was
in
operation;
this
work
could
not
be
done
unless
the
paper
mill
were
shut
down.
Because
the
existing
system
was
needed
to
make
the
new
one
operate,
contract
no.
23
cannot
be
considered
separately
from
the
three
others.
I
am
of
the
opinion
that
the
decision
handed
down
in
Halliburton
Services
Ltd.,
supra,
applies
to
this
case.
5.03.7
Evidence
concerning
the
installation
of
a
Jagenberg
cutter
(no.
32,
Exhibit
A-2)
in
para.
4.16
shows
that
the
placement
alone
of
the
said
machinery
cost
$25,000
out
of
a
$75,000
contract.
It
would
seem,
therefore,
at
first
glance
that
the
$25,000
should
be
excluded
from
the
manufacturing
amount.
However,
on
the
basis
of
Hallibuton
Services
Ltd.,
supra,
I
am
of
the
opinion
that
this
amount
should
be
treated
as
manufacturing,
because
it
is
part
of
the
entire
$75,000,
the
profit
from
which
is
the
basis
of
the
deduction
claimed.
5.03.8
The
evidence
relating
to
the
installation
of
a
screw
conveyor
(no.
30,
Exhibit
A-2),
supra,
para.
4.15,
makes
it
clear
that
manufacturing
was
involved.
5.03.9
The
same
conclusion
applies
to
the
contract
for
the
installation
of
machinery
for
a
sawmill
at
Millage
54,
Chibougamau
Division
that
was
awarded
by
Donohue
St-Félicien
Inc.
(no.
37,
Exhibit
A-2).
The
facts
here
are
substantially
similar
to
those
in
Les
Ateliers
Benoit
Allard
Inc.,
supra.
5.03.10
The
evidence
relative
to
similar
work
awarded
by
Donohue
St-
Félicien
Inc.
for
the
installation
of
the
Girardville
sawmill
also
leads
to
the
same
conclusions.
6.
Conclusion
The
appeal
is
dismissed
in
respect
of
the
1976
taxation
year.
It
is
admitted
in
part
with
costs
for
the
1977
and
1978
taxation
years
in
accordance
with
the
grounds
set
out
above.
Appeal
allowed
in
part.