Supreme Court of Canada
Dryden Construction Co. Ltd. v. Hydro-Electric Power
Commission of Ontario, [1960] S.C.R. 694
Date: 1960-06-24
Dryden Construction
Company Limited (Plaintiff) Appellant;
and
The Hydro-Electric
Power Commission of Ontario (Defendant) Respondent.
1960: March 18, 21, 22; 1960: June 24.
ON APPEAL FROM THE COURT OF APPEAL FOR
ONTARIO.
Contracts—Road construction—Time of the
essence—Contractor unable to complete work in time—Work completed by principal—Claim
for deficiencies in payments—Claim for compensation—Quantum meruit.
[Page 695]
The plaintiff company undertook to construct
a road for the defendant. Time was stated to be of the essence. Slow progress
was made by the plaintiff with the work, and in order to complete the work on
time, the road was shortened and also built to grades lower than originally
agreed upon. Eventually, the plaintiff ceased all work under the contract, and
contending that the defendant was in default under the contract in refusing to
entertain a claim for substantial deficiencies in payments due, treated the
contract as terminated by the defendant. The plaintiff claimed the deficiencies
and the defendant claimed compensation for breach of the contract. The trial
judge maintained the action, but this judgment was reversed by the Court of
Appeal.
Held: The
appeal should be dismissed.
The terms of the written contract applied
throughout to the work performed by the plaintiff. Conclusive evidence proved
that the plaintiff had not completed the work to the satisfaction of the
engineer by the time it abandoned the work, nor was it shown that it had been
released of its obligation to complete the whole length of the road. The
alleged breach of contract by the defendant was not established. The plaintiff
was not entitled to quantum meruit but only to contract unit prices; and
the defendant was entitled to damages for breach of contract by virtue of the
plaintiff’s refusal to complete the work.
APPEAL from a judgment of the Court of Appeal
for Ontario, reversing a
judgment of Wells J. Appeal dismissed.
A.L. Flemming, Q.C., and Meredith
Flemming, Q.C., for the plaintiff, appellant.
R.F. Wilson, Q.C., R.L. McDonald, Q.C., and
C.E. Woollcombe, for the defendant, respondent.
The judgment of the Court was delivered by
LOCKE J.:—This is an appeal from a judgment of
the Court of Appeal of Ontario by which the appeal
of the present respondent from the judgment of Wells J. was allowed, the
judgment at the trial set aside and the cross-appeal of the present appellant
dismissed.
On April 9, 1954, the appellant, therein
described as the contractor, and the respondent entered into an agreement for
the construction of approximately 8½ miles of a road from a designated point on
Provincial Highway no. 105 westerly to Station 450 of the said road. The
respondent was at the time in the course of constructing an electric generating
station at Manitou Falls on the English
River, and the proposed road was to provide access to this undertaking.
[Page 696]
Prior to the making of the contract the appellant
had been invited to tender for the work and had been furnished with a form of
the contract which would be made if the tender made was accepted, the general
specifications which would be applicable, drawings which indicated the location
and a profile of the proposed road, and further detailed information as to the
proposed work.
In view of the contention of the contractor that
the nature of the location for the proposed road had been misrepresented to it,
certain of the terms of the tender that was made dated February 13, 1954, and
which was accepted are to be considered.
The tender recited that the appellant had
visited the location of the road, examined the documents above referred to, and
was fully informed as to the nature of the work and the conditions relating to
its performance and understood that the quantities tendered for were
approximate only and subject to either increase or decrease.
The instructions to the tenderers which were in
the appellant’s possession before the tenders were made contained the
information that tenderers were required to examine the condition’s at the site
before submitting their tender and that the road was urgently required and the
completion date should be September 1, 1954.
The documents described as instructions to tenderers,
information for tenderers, which contained the above mentioned statements, the
general specifications with accompanying drawings and the standard
specifications of the respondent as enumerated in the agreement, were by their
terms to be read with and form part of the contract.
By para. 6 of the contract the contractor agreed
to construct the road on or before September 1, 1954, in strict accordance
with the contract and to the approval of the engineer, and to do all work under
the direction of the engineer whose directions as to the construction and
meaning of the exhibits were declared to be final.
The respondent agreed to determine the contract
price for the work on the basis of the schedule of unit prices, which were
those proposed by the appellant in its tender, applied to the quantities of the
several works items actually performed, as computed by the engineer, in
accordance with the drawings and specifications.
[Page 697]
In dealing with the main claim of the appellant,
the prices which apply are those for earth excavation (including borrow) of .50
cts. per cubic yard and rock excavation of $1.75 per cubic yard.
Para. 8 of the contract
stated that the contractor agreed that it was fully informed regarding all of
the conditions affecting work to be done and labour and materials to be
furnished for the completion of the work, that this information was secured by
personal investigation and research and not from the commission or its
estimates, and that it will make no claim against the commission based on any
estimate or representation of the commission or the engineer, or any
representative of either.
Para. 11 reads:
The Commission, without invalidating the
Contract, may make changes by altering, adding to or deducting from the work
subject to adjustments for compensation or extension of time as may be agreed
between the parties hereto.
Para. 13 obligated the
contractor to prosecute the work with all skill and diligence so as to complete
the same in accordance with the contract and declared that if the contractor
did not, in the opinion of the engineer, carry on the work with sufficient
diligence and speed to ensure completion in accordance with the contract, the
commission might terminate the agreement and at its option complete the work in
such manner as it should think fit, the contractor to be liable for any loss
sustained by the commission by reason of the contractor’s failure to complete
the work.
Para. 16 provided that any loss or damage
arising out of the nature of the work, or from any unforeseen circumstances in
the prosecution of the work or any unusual obstructions or difficulties, should
be sustained and borne by the contractor at his own cost.
Para. 21 provided that
the decision of the engineer should control as to the interpretation of the
drawings and specifications during the execution of the work and that he should
be the sole judge of the work, material and plant, both as to quality and
quantity, and that his decision on all questions of dispute relating to any of
these matters should be final.
[Page 698]
The general specifications forming part of the
contract provided that payment for compaction should be included in the
tendered unit price for earth excavation.
The standard specifications for general grading
operations made applicable to the contract provided by para. 18 that “earth
excavation shall include the removal of all material that does not come under
the classification of rock.” Para. 21 provided, inter alia, that
back-fill material, if specified, should be paid for at the contract unit price
for the material used. Para. 28
provided that all rock excavated should be used for rock embankment
construction and material from earth cuts or earth borrow should be used for
earth embankment, if approved by the engineer. Para. 43 provided in part:
Payment for earth and rock embankment
construction shall be included in the contract unit prices per cubic yard for
excavation… In addition, payment will be made for:
(c) Borrow material at the contract
unit price per cubic yard for earth or rock excavation for the material
actually used in embankments.
The cross section of the proposed road shown
upon the plan submitted to the contractor showed that it was to be constructed
of what may properly be described as three courses, the lower course being
described in the cross section as being of earth or rock-fill. Above this,
there was to be placed 12 inches of selected granular base B material and,
above that, 6 inches of 5/8 inch crushed gravel. The top course was to be
given what was described as Bituminous Surface Treatment, in accordance with
designated specifications. The granular base course was defined in the standard
specification as being selected from deposits of pit‑run gravel, sand or
other granular materials which have a physical structure not affected by water
and elements, and the Class B mentioned, it was said, might be used directly
from the pit without processing if the material conformed with the
specification requirements which were then stated in para. 7.
Included in the information supplied to the
tenderers was a statement that an extensive body of material suitable for road
construction had been located by the commission near the junction of the
proposed access road and the
[Page 699]
provincial highway and that no other areas in
the vicinity of this section of the road had been investigated up to the time
the information was furnished.
The appellant’s tender was made during the
winter, at a time when the area in which the proposed road was to be
constructed was covered with snow. While the profile plan which was exhibited
to the appellant indicated the nature of the ground at various places along the
course of the proposed road, this was information which the commission had
obtained by enquiry and was not, by the terms of the tender and the contract,
guaranteed to be accurate. In the result, not long after the appellant
commenced its work, it was found that this information was in many respects
quite inaccurate. There was, however, close to the point of the commencement of
the road, the large deposite of suitable granular material referred to, from
which the great majority of the material of this nature used in the
construction of the road throughout its course was obtained. The evidence
appears to me to justify the conclusion that, in the main, the material from
this source was suitable for the selected granular base course required by the
contract and the specification.
The form of tender supplied by the commission
for use by proposed tenderers also contained estimates of, inter alia, the
quantities of the various kinds of material to be excavated, the estimated
extent of the muskeg excavation being 8,000 cubic yards. These estimates, which
were described as such, turned out to be quite inaccurate and a very much
greater quantity of material was excavated from muskegs than the estimate
indicated.
By the terms of the contract the appellant
agreed to construct the road westerly to Station 450 of the said road. Its
course was shown upon a drawing which was made part of the contract. The
profile plan referred to in the tender showed the proposed levels of the road
and the location of these stations, they being 100 feet apart. Whether their
location was marked on the ground along the proposed right-of-way is not
stated.
Donald Murphy, the president of the appellant
company, was in active charge and direction of the work from the outset. For
the respondent, P.G. Campbell, the resident engineer for the construction work
at Manitou Falls, was
[Page 700]
appointed the project manager in connection with
the construction of the road. W.G. Baggs, a professional engineer employed by
the respondent, was appointed as the divisional engineer in charge of the
construction and was in constant touch with the work throughout.
According to Murphy, when the work had
progressed to a point between Stations 25 and 35, it was necessary to excavate
and back-fill a considerable area of muskeg and, upon the direction of Baggs,
granular material brought from the borrow pit above mentioned was used for this
purpose. It was Murphy’s contention, advanced at this time and never abandoned
by him, that under the terms of the contract the appellant was entitled to be
paid for granular material used, either as back-fill, embankment or otherwise,
in connection with the work, at the price stipulated in the agreement for the
selected granular base course which was .68 cts. per ton, or approximately
$1.02 per cubic yard. Baggs, on the other hand, said that the only material
that would be paid for at this rate was that used for the course 12 inches in
depth described as selected granular course in the plan and the agreement, and
that all other granular material used would be paid for only as earth
excavation for which the price of .50 cts. per cubic yard was payable.
The claim advanced by Murphy on behalf of the
appellant was based upon a term of para. 21 of the standard specification which
said:
Back-fill material if specified will be
paid for at the contract unit price for the material used.
Since the engineer directed that granular
material should be used, it was contended that the price for that material
agreed upon for the selected granular base course was applicable. This
contention was made on behalf of the appellant at the trial and in the Court of
Appeal and, in both Courts, it was found that as there was no contract unit for
granular material or gravel as such, apart from the 12 inches of selected
granular base course, when used elsewhere it must be deemed to come under the
heading of earth excavation, payment for which was provided for in para. 7 of
the contract. By the terms of para. 43 of the specification above mentioned
this payment included placing the material as part of the road construction.
[Page 701]
By a tender in writing dated June 7, 1954, the
appellant offered to supply 14,000 tons of 5/8 inch crushed gravel to be
delivered to a 4.8 mile stretch of the road, and 4,000 tons to be stock-piled
at the gravel pit area “G” which was close to the point where the road
commenced, at prices which were stated. This offer was accepted in writing by
the respondent on July 20, 1954, and this material which was required for the
top course of the road was laid by the appellant up to Station 95.
Slow progress was made by the contractor with
the work. This was undoubtedly due in part to the fact that the terrain
encountered was less favourable for road construction than Murphy had
anticipated and to bad weather. By July 21st, when they were working at about
Station 95, less than 2 miles from the point of commencement, Campbell wrote to
Murphy pointing out that the agreement required the work to be completed by
September 1, 1954, that he had repeatedly drawn to the contractor’s attention
that it was behind schedule and that when asked how it was proposed to improve
the speed of the work no satisfactory answer had been given. The letter stated
that the project manager had recommended to his superiors that the commission
itself take over the completion of the last 1½ miles of the road and carry out
the work by its construction department. Apparently, Murphy raised no objection
to this.
At a meeting at Dryden, held on or about July
22nd, Campbell informed Murphy that he proposed to reduce the grade of the road
and gave him a written memorandum as to the changes to be made between Stations
103 and 145. The purpose of this, according to Campbell, was to reduce the
quantities of materials to be moved so that the work might be completed on
time. Apparently, an extension of time for completing the work was discussed at
this meeting as on the same date Murphy wrote to Campbell confirming a
discussion of the subject and saying that it was expected to have the road
completed by September 15 to the full width but not to the profile grade.
Murphy did not object to the commission taking over the part of road indicated
and the work continued.
According to Murphy, he was instructed by Baggs
not to put any more of the 5/8 inch crushed material on the road past Station
95. He was indefinite as to the date when this
[Page 702]
occurred, saying that it was either in the first
or second week of August. Campbell denied that any such instructions were given. Baggs was not asked
as to this but a letter written by him to D. Ganton, the superintendent of the
appellant company, on August 9, 1954, in which he drew the superintendent’s
attention to various matters connected with the work which he considered
required attention, was put in evidence and included the following statement:
Before placing 5/8 inch crushed gravel
between Sta. 95 plus 00 and Sta. 145 plus 00 the road surface is to be brought
to final grade as indicated on my Memo to you re “List of grades to be adhered
to and considered as profile grade”.
The list of grades referred to were those shown
in the memorandum which had been given to Murphy on July 22nd. Murphy
acknowledged having seen this letter at the time and the instructions appear to
be completely inconsistent with his statement that work of laying this material
had been stopped.
As the progress made with the work continued to
be unsatisfactory and as Murphy contended that the work already done had not
been paid for in accordance with the agreement, a meeting was arranged between
him and some of the senior officials of the commission and one of its
solicitors in Toronto early in
August. Murphy was represented by a solicitor at these meetings but there is a
conflict of evidence as to what was actually agreed upon. It is, however,
common ground that the parties agreed that the commission should take over the
1½ miles of the road above mentioned and the appellant be released of any
obligation as to that portion of the work and that the time of completion be
extended to September 15th.
The work which had commenced in April had then
been in the main completed to Station 185, though the top course of 5/8 inch
crushed gravel had not been laid past Station 95, and an equal distance of the
road remained to be completed. In view of the urgency of having a usable road
for hauling freight by September 15th, further changes in the work were then
directed by Campbell. On August
17, he wrote to Murphy in the following terms:
In view of the importance of having a road
through to the powersite by September 15th, we have requested you to
concentrate on placing fill, only to a depth required to carry your haulage
equipment; thus providing us with a road bed of reasonable grades, over which
we can haul freight.
[Page 703]
Since this material will be placed as
common fill and will in most cases be of sufficient depth to meet our
requirements for a finished road bed, some method of paying you for the top 12
inches of this fill, as selected granular base course, will have to be agreed
upon.
We are prepared to pay you for a volume of
selected granular base course 12 inches thick and 29 1/2 feet wide over the
total length of the road from Sta. 0 plus 00 to 370 plus 00. This volume to be
converted to a weight basis by applying a factor of 3,600 pounds per cubic yard
of material compacted in the road bed.
Please study this proposal and advise if
you are in agreement with this method of determining the quantity of material
to be paid for as selected granular base course.
Further instructions as to this work were given
by Baggs in a letter to the superintendent of the appellant which read in part:
It is requested that your company concentrate
on placing fill only to a depth required to carry your haulage equipment. From
Sta. 193 plus 00 to 370 plus 00, except for several muskeg and rock
excavations, the road is strictly a fill proposition, and grades should be kept
to at least sub-grade, and where possible, lower. In order to do this, it will
be necessary that the road bed, before fill is placed, be well drained, and in
a reasonably dry condition. This can only be made possible by paying particular
attention to lateral and offtake ditches.
This letter was dated August 20, 1954.
No written reply was made to either of these
letters. The appellant, however, proceeded with the work, using granular
material where fill was required for the lower course and, the appellant
contends, placed the 12 inch granular base course to Station 370. This road
which was referred to by the parties as a “skin” road from Station 185 was
lower than the grade shown upon the profile, this being accomplished by
lowering the lower course required by the original contract. This portion of
the road as constructed was apparently sufficient to carry the trucks which
brought the material for the construction.
In spite of this change which very materially
reduced the amount of work to be done by the contractor, Station 370 was not
reached until about September 22nd.
Murphy then took the attitude for the first time
that the work to be performed by the appellant had been completed. On September
28, 1954, the appellant wrote to Campbell saying that since the base road was completed the appellant would
no longer require the services of a machine which it had rented from the
commission.
[Page 704]
The reasons assigned by the appellant for
declining to carry out the terms of the written agreement must be carefully
considered. On September 11, 1954, Murphy had written to the general manager of
the respondent stating that the monthly estimates made on the instruction of
the respondent’s engineer upon which payments were made differed so materially
from the work actually done that the appellant found its credit jeopardized and
unless the matter was remedied the appellant would be unable to continue. There
was enclosed with this letter a statement purporting to show the difference
between the various materials actually placed in the road according to the
appellant’s figures, and those allowed by the engineer for the months May to
August inclusive. According to this statement, while payment had been made by
the respondent for 16,180 tons of granular material in June, the appellant had
placed 52,430 tons on the road and in the other months very large discrepancies
were shown. As to the granular material, it is admittedly the fact that in
preparing these figures all granular material placed upon the road, whether or
not it formed part of the granular base course, was treated as material for
which the appellant was entitled under the contract to payment at the rate of
$1.02 per ton instead of .50cts., as contended by the engineers. This
contention was based upon an interpretation of the contract which the learned
trial judge and the Court of Appeal have held to be erroneous.
On October 1, 1954, Murphy wrote to J.R.
Montague, the director of engineering of the respondent at Toronto, in response to a request that he
state what were the appellant’s claims. In this letter it was stated that the
appellant’s contension was that all quantities of granular material used as
backfill sections over critical material (meaning material unsuitable for use
as fill), all through cuts of critical material, all back-fill of muskeg
excavation and all fill through wet sections must be classified as granular
base course and paid for at the contract unit price for such material.
On October 7, 1954, J.H. Amys, Q.C., who had
attended the meeting with the Hydro Commission above mentioned as solicitor for
the appellant, wrote to the respondent saying that Campbell had declined to have the quantities of
[Page 705]
selected granular base course material
calculated in accordance with an agreement that he had made with Murphy and
that the appellant took the attitude that the commission had defaulted in its
obligations under the contract and that such default justified it in treating
the contract as terminated by the Hydro-Electric Power Commission of Ontario.
The reference to the agreement said to have been made between Campbell and
Murphy as to the measurements of granular material was one which they had
agreed upon early in the work but which Campbell had thereafter decided was
unsuitable as a means of accurately determining the quantities and declined to
carry into effect.
On the day following, a letter was sent to the
respondent in the name of the appellant company saying that, as the commission
had refused to entertain its claim for substantial discrepancies due under the
contract which, it was said, amounted as of September 30th to approximately
$100,000, the appellant treated the contract as terminated by the commission
and that such termination justified the appellant in ceasing further work under
the contract. The contract referred to at the end of this letter was described
as being Manitou Falls Generating Station Access Road Construction Contract.
The only contract that answered that description was that of April 9, 1954.
The cause of action set up in the statement of
claim was that in the course of attempting to carry out the contract of April
9, 1954, the parties had found that the drawings did not describe the road
required by the defendant for the purposes of its enterprise, that the
plaintiff had been verbally requested by the defendant to construct a shorter
road at the general location indicated in the written contract, but in
conformity with the actual conditions found on the terrain rather than with
those shown on the drawings, and that payments were to be made as the work
progressed and that it was an implied term that the plaintiff would be paid a
reasonable price for its materials and labour. It was further alleged that:
The plaintiff proceeded with the said work
which the defendant accepted but the defendant did not carry out its
undertaking to make payments as the work progressed and as a result the
plaintiff was obliged to stop work on the road.
[Page 706]
In respect of the cause of action thus pleaded
the defendant claimed the sum of $457,245.14 for breach “of contract on
building the road”, or alternatively on a quantum meruit basis.
In response to a demand for particulars the
plaintiff said that the request to construct a shorter road had been made by Campbell on or about July 21, 1954. As to
the allegation that the defendant had accepted the road, the plaintiff said
that the defendant had taken over and used the work done by the plaintiff in
the Fall of 1954, thereby accepting it.
The defence denied that the plaintiff had been
requested to construct a shorter road and set up the terms of the contract and
the documents incorporated in it as an answer to the claim. It was further
denied that the defendant had accepted the road and alleged that as the
plaintiff had failed to carry out the work required the defendant had been
compelled to complete such work at an expense of $17,925.07. This amount, while
claimed originally as a counterclaim, was later added to the statement of
defence by way of set off.
The learned trial judge found, as has been
stated, that for the granular material used in the construction of the road
other than for the granular base course 12 inches in depth, the appellant was
entitled to be paid .50 cts. per cubic yard, being the price specified in the
contract for earth excavation. The claim pleaded that a new contract had been
substituted for that of April 9, 1954, was rejected and the plaintiff was found entitled to recover for
the work performed up to Station 186 in accordance with the prices fixed by the
written contract. Wells J. however, considered that the situation was
different in respect to the work done from Station 186 to Station 370.
Referring to the letter of August 17, 1954, above quoted, the learned judge
found that the directions there given did not amount to an abandonment of the
contract but that the effect of it was to take away from the contractor for the
remaining portion of the road what were referred to as the two most valuable
items of the contract, namely, the laying of the ⅝ inch crushed gravel
and the laying of the selected granular base course from Station 186. Pointing
out that while paragraph 11 of the contract permitted the respondent to make
changes by altering, adding to or deducting from the work,
[Page 707]
the right was “subject to adjustments for
compensation or extension of time as may be agreed between the parties hereto”,
and it was said that this implied that proper compensation should be made and
that no such adjustments were ever made. The reasons continue:
The failure to make such compensation was,
in my view, a serious breach of the contract by the defendant Commission, and,
in view of such breach and failure, the plaintiff was, in my view, entitled to
stop work as he did. He would have, I think, been entitled to do it earlier.
In these circumstances the learned judge
considered that the amount of the compensation should be calculated and that
this could be done only by requiring the defendant to pay for what had been
done as on a quantum meruit. It was further held that there was not any
“clear understanding with Mr. Murphy, and I accept his evidence and that of his
witnesses that so far as they understood their work was through when the skin
road was put through and the road finally trimmed and cleaned up.” It was,
accordingly, not necessary to consider the claim of the present respondent to
set off against any moneys owing to the appellant its costs of completing the
road in accordance with the written contract.
The trial judge further allowed the plaintiff
company to amend by claiming a number of sums as extras to which I will make
reference later.
The unanimous judgment of the Court of Appeal
was given by Laidlaw J.A. It was found that the terms of payment prescribed by
the written contract applied throughout and directed that the judgment at the
trial be set aside. Upon the vital question as to the basis upon which the
appellant was entitled to payment for granular material used other than for the
12 inch granular base course, in agreement with the trial judge, it was held
that the price applicable was .50 cts. per cubic yard under the terms of the
contract and that the changes made, first at Station 95 and thereafter at
Station 186, did not make the work of construction radically different from
that which was undertaken by the appellant under the contract. After pointing
out that the reduction in grade was made by reducing the dept of the earth and
rock-fill only and that the necessity for this reduction was occasioned by the
urgent need of the
[Page 708]
respondent to have the whole length of the road
in a usable state by September 15th as agreed, the learned judge said that the
reductions thus made were an accommodation to and for the advantage of the
appellant since, in the event of non-completion of the road on or before
September 15th, the respondent might have exercised its contractual right to
declare the contract forfeited and have proceeded to hold the appellant liable
in damages for breach of contract. Upon the evidence the learned judge
concluded that the appellant knew that, after placing the earth and rock-fill
and building the base course overlying it from Station 186 to Station 370, the
respondent expected that at a later date the surface course of ⅝ inch
crushed stone would be laid by the appellant in accordance with the contract
and that both parties fully understood that the contract continued in force and
effect notwithstanding the reduction in the grade.
For the reasons given in the judgment at the
trial and in the Courth of Appeal, I agree that under the terms of the contract
the granular material used, other than for the base granular course, was to be
paid for at the rate fixed for earth excavation, including “borrow”, that is
.50 cts. per cubic yard. The pit run gravel that was used was borrow material.
I also agree with the learned judges of the Court of Appeal that the terms of
the written contract applied throughout to the work performed by the appellant.
The contract made between the parties dated
April 9, 1954, was executed under their respective corporate seals. The
contractor, as I have pointed out, agreed to construct a road in accordance
with the specifications and that all phases of the work should be performed to
the satisfaction of the engineer on or before September 1, 1954. Time was
declared to be material and of the essence of the contract.
In order to succeed it was necessary for the
appellant to establish that in some manner it had been released of its
obligation to complete the road throughout its length, including the
construction of the lower course and the granular base course from Station 186
to Station 370, and the laying of the top course and the application of the
bituminous surface treatment from Station 95 to the end of the road, to the
satisfaction of the engineer. That the appellant had not completed this work to
the satisfaction of the engineer on October 8, 1954, when it abandoned the
work, is conclusively proven by the evidence.
[Page 709]
With great respect I disagree with the finding
at the trial that the respondent was then in default under the contract and
that the appellant was entitled to elect to treat such contract as repudiated
by the respondent.
I find nothing in the evidence to support a
contention that the appellant was released of its said obligation under this
contract. The letters referred to directing the work to be done forthwith
between Stations 186 and 370 did not say that the contractor was relieved of
its obligation to lay the top course upon the road from Station 95 to Station
370 and to apply the bituminous surface treatment, or that the work was not to
be carried out to the satisfaction of the engineer. The reason for the orders
then given by the engineer are made apparent by the evidence. The road was
urgently needed by September 15th for transporting freight to the large
construction works being carried on at Manitou Falls and less than one month of
the new time stipulated for completion remained and half of the road remained
to be constructed. At that time the appellant had spent four months upon the
first half of the road and even that work was not completed.
The learned trial judge, after considering the
evidence, found that when these instructions were given to Murphy it was not
made clear to him that he was to do anything more than comply with the
directions then given. I would not so interpret the evidence but, even if this
were correct, it does not assist the position of the appellant. The written
contract still remained in force, the grade between Stations 186 and 370 had
not been completed to the satisfaction of the engineer and the top course had
not been laid past Station 95. It was not necessary for the engineer to point
out to the appellant or its officers its obligations under the contract.
This covenant of the appellant remaining
unfulfilled, the respondent was entitled to insist upon its performance unless
in some manner it was estopped by the actions of the engineer from doing so. As
to this there is no plea of estoppel in the appellant’s pleadings and estoppel
must be pleaded. I may add that if there were such a plea, any such contention,
in my opinion, is untenable upon this evidence.
[Page 710]
I have carefully examined the evidence of the
witnesses Murphy, Campbell and Baggs and the correspondence affecting the
matter and, having done so, I share the view expressed by Laidlaw J.A. that
both parties understood that the written contract continued in force throughout
and that Murphy knew that, after completing what has been referred to as the
skin road, the engineer expected that the remainder of the work would be
completed forthwith. There is evidence in the record of a discussion in the
cookhouse of the appellant company on September 21, 1954, between Murphy and
C.T. Enright, the roads supervisor of the respondent commission, at which time
Enright says that Murphy stated that he would keep his entire crew working full
time until he had got the skin road through to Station 370, at which time he
would give his men a holiday of four days and then he would come back and
finish up the road, but that one of the conditions for coming back was that he
would get “a revision of prices on certain materials.” Baggs was present and
heard this statement by Murphy and gave evidence to the same effect. The
latter, when asked about it, admitted that he had been there and talked to
Enright but said that he did not remember saying that they would not do any
further work unless they were paid. The judgment at the trial, dealing with
this conversation, says that Murphy denied this but this, with respect, was
inaccurate since he merely said that he did not remember making the statement.
While referring to the fact that Baggs had given evidence to this effect, no
mention was made of the fact that Enright also had sworn to it. The statement
in the letter of October 8, 1954, above referred to, that the appellant was
justified in “ceasing further work under the contract”, is completely
inconsistent with the idea that at that time Murphy considered the work to be
done had been completed.
It will be seen that the reason assigned by the
appellant for treating the contract as repudiated by the respondent and itself
discharged from doing further work was not the reason upon which that action
was justified in the judgment at the trial. The letter of September 11, 1954 complained that the monthly
payments that were being made were not in accordance with the contract, the
complaint being based upon the respondent’s refusal to pay for the granular
[Page 711]
material in accordance with Murphy’s
construction of the agreement. The letter of October 1st from Murphy to the
director of engineering of the respondent made it perfectly clear that this was
the complaint and the letters of October 7th and 8th based the appellant’s
refusal to do further work on the alleged fact that approximately $100,000 was
owing to the appellant for the work already done, this referring to the same
matter.
These letters contain no complaint that the
effect of the instructions given by the engineers in August was to deprive the
contractor of the profitable work of laying the granular base course and the top
course of the road. There was good reason for this since this work had not been
taken away from the appellant, though the time for completing it was deferred.
As the evidence discloses, the appellant repudiated the contract upon grounds
which have been held to be and are untenable and the usual consequences must
follow.
Apart from the claims made in respect of the
construction of the road, the appellant claimed an amount for supplying certain
5/8 inch crushed gravel under the terms of the contract of July 20, 1954. That
contract fixed a price for 14,000 tons of this material to be delivered to a
4.8 mile stretch of the road at $1.78 per ton, and 4,000 tons to be stock piled
at a specified gravel pit for which the price was .97 cts. per ton.
In addition, the appellant claimed to recover
under a further contract dated July 31, 1954 for 2,938 tons of crushed gravel concrete aggregate and 8,582 tons
of concrete sand which it claimed to have delivered. The statement of defence
denies that the appellant had delivered any of the 5/8 inch crushed gravel
under the contract of July 20, but admitted that the plaintiff had delivered
material under the contract of July 31 to a total slightly in excess of that
claimed, in respect of which it was admitted that the appellant was entitled to
a credit of $9,247.39.
The price provided for the 5/8 inch crushed
gravel, other than that which was to be stock piled, included the delivery of
this material on to the road and this had not been done, the appellant
contending that it had been stopped from doing so. This fact was found against
it in the judgment at the trial.
[Page 712]
In dealing with this claim, Wells J. directed
that there be a reference to the Master to determine the amount payable in
respect of the 5/8 inch crushed gravel less a fair and reasonable amount to be
deducted from the contract price for the haulage of such part of the said
material as should have been delivered by the plaintiff. In respect of the
claim for the material produced under the contract of July 31st, the Master was
directed to give credit to the plaintiff in the amount of $9,192.04, a sum less
than the amount admitted as payable in the statement of defence.
The judgment of the Court of Appeal, as entered,
directed the Master to enquire as to the amount of the credit to be allowed for
the 5/8 inch crushed gravel referred to, being the cost to the plaintiff of
producing such material, plus a reasonable percentage of such cost as profit.
No mention was made of the credit to be allowed in respect of the material
covered by the contract of July 31.
No objection was made to the form of this
reference to the Master and, as the amount of the credit to which the appellant
is admittedly entitled on the pleadings is not in question and will be taken
into account by the Master, I think it unnecessary to amend the judgment of the
Court of Appeal in this respect.
In addition to these claims, the appellant was
permitted by the judgment at the trial to claim various amounts as extras and
the pleadings were amended to claim certain sums should it be held that the
appellant was not entitled to be paid as on the basis of a quantum meruit for
its entire claim.
As to all of these claims I agree with the
reasons for judgment of Mr. Justice Laidlaw and am of the opinion that they are
properly dealt with in the judgment of the Court of Appeal.
I would dismiss this appeal with costs.
Appeal dismissed with costs.
Solicitors for the plaintiff, appellant:
Flemming, Smoke & Burgess, Toronto.
Solicitors for the defendant, respondent:
Day, Wilson, Kelly, Martin
& Campbell, Toronto.