Supreme Court of Canada
City of
Edmonton et al. v. Northwestern Utilities Ltd., [1961] S.C.R. 392
Date:
1961-04-25
City of Edmonton, Town of Jasper Place, City of Red
Deer and Town of Vegreville (Respondents) Appellants;
and
Northwestern Utilities Limited (Applicant) Respondent.
1961: January 31; February 1; 1961: April 25.
Present: Kerwin C.J. and
Locke, Cartwright, Abbott and Judson JJ.
ON APPEAL FROM THE SUPREME COURT OF ALBERTA, APPELLATE
DIVISION.
Public
utilities—Jurisdiction of Board in fixing rates to allow for transitional
losses between date of application and date of decision—Meaning of statutory
phrase "undue delay"—Jurisdiction to approve of purchased gas
adjustment clause—The Public Utilities Act, R.S.A. 1955, c. 267, as amended by
1959 (Alta.), c. 73.
In June 1958 the
respondent utility company applied to the Public Utilities Board to fix a new
schedule of rates. The hearing of the application commenced in the following
December and continued intermittently until February 26, 1959. The Provincial
Legislature amended The Public Utilities Act on April 7, 1959, to
provide by s. 67(8) as follows: "It is hereby declared that, in fixing
just and reasonable rates, the Board may give effect to such part of any excess
revenues received or losses incurred by a proprietor after an application has
been made to the Board for fixing of rates as the Board may determine has been
due to undue delay in the hearing and determining of the application".
Effect was given to this
amendment in an order of August 28, 1959, by which the Board approved an
increase in the utility's rates as of September 1, 1959. An application was
then made on behalf of the appellants under s. 49 of the Act for leave to
appeal from the Board's order on the grounds that (i) the Board erred in law
and had no jurisdiction to fix rates enabling the respondent to collect through
its rates an additional amount for transitional losses during 1959, and that
[Page 393]
(ii) the Board erred in law and had no jurisdiction to approve
the principle of a purchased gas adjustment clause. Another question raised was
as to whether there had been "undue delay" within the meaning of the
amendment to s. 67. Leave to appeal was granted and the Appellate Division, by
a majority decision, dismissed the appeal on the first ground. The appeal on
the second ground was allowed unanimously. The appellants appealed to this
Court on the first question and the respondents cross-appealed on the second.
Held: The appeal should be dismissed. The cross-appeal
should be allowed, and in lieu of the answer made by the Appellate Division to
the second question, judgment should be entered declaring that the Public
Utilities Board did not err in law and had jurisdiction to approve the
principle of a purchased gas adjustment clause.
Per Kerwin C.J. and Cartwright J.: It was not
necessary to express an opinion on the contention of the respondent that the
question whether there had been undue delay in the hearing and determination of
the application to the Board was not open to the appellants. On the assumption
that the question was open the Board had decided it correctly.
Per Locke, Abbott and Judson JJ.: The language of
subs. 8 of s. 67 of the Act, which gave the Board power to provide for
transitional losses, made it clear that the amendment was intended to be
retroactive. Sussex Peerage case (1844), 11 Cl. & Fin. 85 and Vacher
v. London Society of Compositors, [1913] A.C. 107, referred to. It is only,
however, such losses as have been due to undue delay in the hearing and
determining of the application which may be permitted to be recovered. In the
decision to authorize the utility to collect an additional amount for 1959 it
was implicit that the Board held that the delay after December 31, 1958, was
undue within the meaning of that expression in the subsection. It was clear
that the Board attributed to the expression the meaning "more than was
reasonable in the circumstances", and it was correct in doing so. As to
whether the delay after December 31 was more than was reasonable, this was a
question of fact as to which there could be no appeal under the statute.
The proposed order, with
respect to the purchased gas adjustment clause, would be made in an attempt to
ensure that the utility should from year to year be enabled to realize, as
nearly as may be, the fair return mentioned in s. 67(2) and to comply with the
Board's duty to fix just and reasonable rates to permit this to be done. How
this should be accomplished, when the prospective outlay for gas purchases was
impossible to determine in advance with reasonable certainty, was an
administrative matter for the Board to determine.
APPEAL and
cross-appeal from a judgment of the Supreme Court of Alberta, Appellate
Division,
reversing in part a decision of the Alberta Board of Public Utility
Commissioners. Appeal dismissed and cross-appeal allowed.
A. F. Macdonald, Q.C., and W. R. Sinclair, for the City of
Edmonton.
G. J. Bryan,
Q.C., for the Town of Jasper
Place.
[Page 394]
J. W. Beames, for the City of Red Deer.
W. H.
Hurlburt, for the Town of
Vegreville.
George H.
Steer, Q.C., and B. V. Massie, Q.C., for the applicant, respondent.
The
Chief Justice:—Subject to the same
reservation expressed in the reasons of Mr. Justice Cartwright and on the same
assumption that he makes, I agree with the reasons of Mr. Justice Locke.
The judgment of Locke,
Abbott and Judson JJ. was delivered by
Locke
J.:—The respondent is the owner and
operator of a natural gas transmission and distribution system serving large
numbers of domestic, commercial and industrial consumers in the City of
Edmonton, the Town of Jasper Place, the City of Red Deer and the Town of
Vegreville and some 55 other municipalities or places in the Province of
Alberta. The respondent is a public utility within the meaning of The Public
Utilities Act, R.S.A. 1955, c. 267, as amended.
On June 13, 1958, the respondent
applied to the Public Utilities Board, constituted under the said Act, for an
order:
fixing and approving as
of the return date of this motion, or such other date as the Board may deem
proper, such new rates as are necessary to meet the applicant's costs,
including its return.
The hearing of the said
application commenced on December 9, 1958, and continued intermittently until
February 26, 1959.
On June 29, 1959, the
Board rendered its decision fixing a rate of depreciation, working capital
allowance and estimated expenses of operation, and held the respondent entitled
to a rate of return of 7.5 per cent upon its property used or required to be used
in its service to the public within Alberta as determined and that the
respondent was entitled to an increase in its revenue of $2,817,929 for the
year 1959 and $3,019,792 for 1960, and directed that the respondent file
schedules of rates for the approval of the Board, indicating how it suggested
such amounts should be obtained.
[Page 395]
The value of the properties of the respondent upon which it
was permitted the annual return above stated was fixed for the year 1959 at
$48,568,892 and for the year 1960 at $51,412,702. The respondent has large
natural gas reserves of its own but, in addition, purchases large quantities,
for use in the operation, from the owners of other gas wells and operators of
oil wells. The Board's estimate of its expense for this purchased gas for the
year 1959 was $3,825,690 and for the year 1960 $3,722,300.
Section 67(a) of
the Act reads:
The Board, either upon
its own initiative or upon complaint in writing, may by order in writing, which
shall be made after giving notice to and hearing the parties interested,
(a) fix just and reasonable individual rates, joint rates, tolls
or charges or schedules thereof, as well as commutation, mileage and other
special rates, which shall be imposed, observed and followed thereafter by any
proprietor.
During the lengthy
proceedings before the Board it was contended on behalf of the respondent that
the Board had power to make provision for the loss sustained by the respondent
between June 13, 1958, the return date of its motion, and the date of the
coming into effect of new rates. This loss referred to in the proceedings as
"transitional loss" was the difference in the revenue of the
respondent under the old rates, which remained applicable throughout the time
consumed by the hearings and until the new rates became effective, and the
amount which would have been received had the new rates to be authorized been
in effect throughout this period. It was contended by the present appellants
that the Board was without jurisdiction to make any such order, a contention
which was upheld by the Board. As to this, the decision made in March 4, 1959,
read in part:
The board has no doubt
that the application of the principle of transitional loss is in effect fixing
rates retroactively. The principle results in rates which are determined being
dated back to the time of the application. The board can find no authority for
it to do this either in The Public Utilities Act or elsewhere. The language
used in The Public Utilities Act is prospective rather than retrospective. The
authority of the board in this regard is limited to fixing rates for the
future. The board accordingly has come to the conclusion that it cannot give
effect to the principle of transitional loss.
[Page 396]
On April 7, 1959, the Legislature amended section 67 of the
Act by, inter alia, adding thereto the following:
(8) It is hereby
declared that, in fixing just and reasonable rates, the Board may give effect
to such part of any excess revenues received or losses incurred by a proprietor
after an application has been made to the Board for the fixing of rates as the
Board may determine has been due to undue delay in the hearing and determining
of the application.
The amendment and the
matter of the delays which had occurred between the filing of the application
and the date of the Board's decision were dealt with in the following terms in
the decision of June 29, 1959:
Counsel for the
consumers have asked that the decision upon transitional loss given by this
board respecting the application of Canadian Western Natural Gas Company
Limited be applied to this case. In the Canadian Western case this board came
to the conclusion that it could not give effect to the principle of
transitional loss as it could find no authority for it to do so either in The Public
Utilities Act or elsewhere. Since that decision The Public Utilities Act has
been amended and Section 67(8) now provides:—(reciting the above amendment).
In this case, as has
been pointed out above, the company's motion was returnable June 13, 1958. The
hearing commenced December 9, 1958. There were unavoidable adjournments from
December 19, 1958 to January 15, 1959, and from January 24, 1959, to February
24, 1959, and the hearing finally concluded February 26, 1959. There has been
an inevitable delay from that date to the date of this decision and it appears
that it will not be possible to have the new rates effective until August 1 at
the earliest. It is apparent that the losses due to undue delay in the hearing
and determining of the application have been considerable. The Board considers
that it is only fair, in the circumstances, to reserve this question until the
hearing of the second phase of this application.
It was impossible in the
circumstances disclosed by the evidence for the respondent to determine with
certainty in advance the amounts it would expend for purchased gas from year to
year, and the figures above mentioned were, of necessity, estimates only. The
respondent, accordingly, asked that the order to be made by the Board should
contain what was called a purchased gas adjustment clause, a provision which,
it was said, was approved by public utility boards in various states of the
Union. The practical effect of such a clause would be that, assuming by way of
illustration that the estimate of the cost of purchased gas for the year 1959
should prove to be $800,000 less than the actual expenditure for that purpose,
this amount would be recouped by the company by an increase in the price of gas
to consumers for the year 1960.
[Page 397]
Should, however, the estimated figure for this cost, used in
approving the rates for the year 1959, be greater than the actual expenditure,
the rates fixed for the year following would be reduced to give to the
purchasers of gas the benefit of the saving. The details of the manner in which
this would, in practice, be worked out was given by the witness Wilson, the
executive vice-president of the respondent, and was explained in Exhibit 3
filed before the Board. It is unnecessary for the disposition of this aspect of
the matter to examine these details in any more particularity.
In its decision of June
29, 1959, the Board said:
The evidence disclosed
that the company faces a serious problem in estimating, with any degree of
accuracy, the volumes of oil field gas which it will be required to purchase in
any particular year. Added to this is the problem resulting from the fact that
contracts between producers and exporters contain escalation and favoured
nations clauses which affect future prices. In view of these problems the
company led evidence as to a possible purchased gas adjustment clause which
might be inserted in the board's order. Counsel for the company point out in
argument that the company's proposal at no time involved, and does not now
involve, rate changes without board approval.
After pointing out
that a further amendment had been made to the Act as s. 42(a) which
might affect the matter, the Board reserved judgment until further
representations might be made to it.
As to the transitional
losses, the company was, as above stated, given permission to file rate
schedules for the approval of the Board, calculated to produce an increase in
its revenue for the calendar year 1959 of $2,817,929. In preparing these
schedules the respondent company proceeded on the basis that the Board had
decided that the delay in disposing of the application from January 1st onward
had been undue delay within the meaning of s. 67(8), since the figure of
$2,817,929 included, according to the respondent's computation, $1,845,000 as
the transitional loss from January 1st to August 31, 1959. The schedule of
rates filed proposed that this amount should be recouped from the rates to be
imposed during the four and one-third years immediately succeeding September
1st, 1959. After further hearings for the purpose of hearing objections to the
rates proposed, the Board rendered its decision on August 26th.
[Page 398]
In dealing with the question of transitional loss, the Board
quoted that portion of its decision of June 29th, above referred to, and said:
The board in its
decision of June 29 last quoted above, after citing the many adjournments and
delays held that there had been undue delays and is still of the same opinion.
After saying that
the amendment to s. 67 permitted it to allow for losses sustained before the
amendment was passed, the decision read in part:
In its decision of June
29th the Board held:
Subject to the above the
board finds that the additional revenue to meet the deficiency as set out in
detail in Schedule "B" amounts to $2,817,929.00 for 1959 and
$3,019,792.00 for 1960. The company may now file schedules of rates for the
approval of the board indicating how it suggests such amounts should be
obtained.
It will be noted that
there is no mention of transitional loss in Schedule "B" which gives
the details of the computation of the deficiency. It is considered clear that
the board by this finding authorized the company to collect an additional
$2,817,929.00 for the year 1959. The manner of collecting that amount was not
broken down by months, the intention, which appears obvious, being that an
additional amount of $2,817,929.00 would be collected for the entire year.
Since new rates cannot be made effective until September 1 at the earliest it
is apparent that to recover such an amount in the four remaining months of the
year would result in very high rates for those months. The company accordingly
designed its rates to recover the amount over a period of several years and
this commends itself to the board.
Dealing with the
proposed purchased gas adjustment clause and the objections raised to the
application of any-such principle, the Board said in part:
The board undoubtedly
has jurisdiction to fix just and reasonable individual rates, joint rates,
tolls or charges or schedules thereof as well as other special rates which
shall be imposed, observed and followed thereafter by any proprietor. It
appears to the board that it has jurisdiction to say that the rate would be a
certain amount per MCF. or per therm plus the cost of purchased gas or a
certain rate plus or minus an adjustment for any variation in the cost of
purchased gas which is in effect what is done by the adoption of a purchased
gas adjustment clause.
After pointing out that
the cost of purchased gas was one of the main items of expense of the company
and that it was obvious that it is entitled to recover this expense through the
rates charged, the Board said:
After reviewing very
carefully all the evidence in this respect and giving consideration to what was
said in argument this board is convinced that a provision for purchased gas
adjustment is in the best interests of the consumer and is essential to the
company if its financial integrity is to
[Page 399]
be maintained, which of course is also in the best interests
of the consumer. The detailed provisions of the necessary order need not be
discussed in this decision as these can be worked out between representatives
of the consumers and the company subject to the approval of the board. The
right is reserved to the company to file revised estimates of its purchased gas
expense if for any reason it is found to be impossible to make such order
effective.
By a formal order dated
August 28, 1959, the Board approved the proposed rates as interim rates, to
become effective on and after September 1, 1959, and dealt with the proposed
purchased gas adjustment clause in the following terms:
The principle of a
purchased gas adjustment clause as proposed by the Applicant is approved and
the form of Order submitted in evidence by the Applicant is referred to the
Applicant and the Respondents to consider whether agreement can be reached
among them as to the wording of such a clause to be submitted to the Board for
its approval. Failing such agreement the Applicant on ten (10) days' notice to
the communities or persons who appeared on the said hearings may submit for the
approval of the Board a form of Order providing that the rates as shown in
Schedule "A" may be increased or decreased by Order of the Board to
reflect changes in the average cost to the Applicant of gas and to reflect
surpluses or deficiencies in revenue which have accrued to the Applicant due to
the over or under provisions in the said rates for such average cost of gas.
No agreement was reached
as to the wording of such a clause and the record does not indicate that the
Board made any further order thereafter dealing with the question.
Section 49 of The
Public Utilities Act provides that leave to appeal to the Appellate
Division of the Supreme Court of Alberta upon a question of jurisdiction or
upon a question of law may be obtained from a judge of the Court of Appeal upon
application within a defined time. Such an application was made to Johnson J.A.
who, by order dated October 20, 1959, gave leave to appeal upon the following
grounds:
(a) That the said Board erred in law and had no jurisdiction under
the provisions of The Public Utilities Act or otherwise to fix rates enabling
the Respondent to collect through its rates an additional $2,817,929 for the
year 1959, as provided in the said decision;
(b) That the Board erred in law and had no jurisdiction to approve
the principle of a purchased gas adjustment clause as referred to in the said
decision and order.
The questions upon which
leave to appeal was granted are, according to the reasons delivered by the
learned judge, those proposed on behalf of the City of Edmonton. Another
question raised on the argument before him was as to
[Page 400]
whether there had been "undue delay" within the
meaning of the amendment. This would appear to be a question which would arise
in considering the first question upon which leave was granted. Whether the
applicants proposed that a separate question should be submitted as to this is
' not clear. Johnson J.A. said that the question was not a question of law but,
at the highest, a mixed question of fact and law. I mention the matter because
it was contended by the respondent that the question of whether there had been
undue delay within the meaning of that expression in the amendment was not open
to the appellants, a contention with which I do not agree.
The Appellate Division,
by a decision of the majority of the court, dismissed the appeal on the first
ground, Porter J.A., with whom Milvain J. agreed, dissenting. The appeal upon
the second ground was allowed by a unanimous judgment of the court.
The appellants have
appealed to this Court from the judgment on the first question and the
respondent has cross-appealed from the judgment dealing with question (b).
A public utility, such
as the respondent, in Alberta may not change a rate theretofore fixed by the
Public Utility Board without its approval (s. 83(1)). The rates, we are
informed, had last been fixed several years earlier. The Board was empowered at
the time of the application to require the utility to furnish safe, adequate
and proper service and to keep and maintain its property and equipment in such
condition as to enable it to do so (s. 67(d) (ii)) and to make
extensions to its facilities when, in the judgment of the Board, to do so was
reasonable and practicable (s. 67(d) (iii)). These powers were continued
in the 1959 amendments to ss. 66 and 67. The utility was further under the
obligation to supply and deliver gas at such rates and upon such terms as the
Board might direct (s. 67(d) (viii); s. 67(1) (e) as
amended). The rates thus to be fixed from time to time were such as the Board
considered to be just and reasonable.
Unlike the British
Columbia Act, considered by this Court in B.C. Electric Railway Company v.
Public Utilities Commission,
the expression "unjust and unreasonable rates" is not defined.
Section 66(b), however, as it read prior
[Page 401]
to the 1959 amendment, empowered the Board to value the
property of the public utility, and the purpose of these powers was explained
and they were amplified in the amendment of 1959. This required the Board, in
fixing just and reasonable rates, to determine a rate base for the property of the
proprietor that is used or required to be used in his service to the public
within Alberta and to fix a fair return thereon.
There is no explanation
in the record of the delay in considering the respondent's application between
June 13, 1958, and December 9, 1958. While the respondent might have applied
for an interim order increasing the rates under s. 41(2), this was not done,
presumably because in a matter involving so many varied interests this was
deemed impractical. A further delay occurred between the conclusion of the main
hearings on February 26 and the rendering of the decisions of June 29 and
August 26 and, as shown, the new rates did not come into effect until September
1, 1959.
The right of the
consumers to require the respondent to supply them with gas, conferred by the
statute, would, in my opinion, even in the absence of any statutory provision,
impose upon them an obligation at common law to pay for the service on the
basis of a quantum meruit. In such circumstances, I consider that the
position of the utility would be similar to that of a common carrier upon whom
is imposed, as a matter of law, the duty of transporting goods tendered to him
for carriage at fair and reasonable rates (Great Western Railway v. Sutton). Here the duty of
determining what rates are fair and reasonable is imposed upon the Board. In
the result, in the present matter the consumers paid less than a fair price for
a period of something more than a year.
As shown by the decision
of March 4, 1959, while on various earlier occasions the Board had made
provision for the recovery of transitional losses in fixing rates, this had
apparently been done by consent of the parties. When its power to do so was
questioned in the present matter, the Board came to the conclusion that its
powers were limited to fixing rates to apply in the future. While the reasons
given do not explain the grounds upon which the Board proceeded, it may, I
think, be fairly assumed that it was
[Page 402]
based upon the language of s. 67(a) which speaks of
rates which shall be imposed, observed and followed thereafter by any
proprietor. The amendment adding subs. (8) to s. 67 was passed in the following
month and the Board acted upon the powers which it considered were given to it.
There has been much
discussion in argument before the Appellate Division and in this Court as to
whether the amendment was retroactive, or whether it was simply declaratory of
the law as it stood before its enactment. In my opinion, it is unnecessary to
determine this question since, in agreement with the majority of the learned
judges of the Appellate Division, I consider that the language of the amendment
is perfectly clear.
Under the decision
approving the new rate schedule made on August 26, 1959, authority was given to
add to the rates over a term of years the amount by which the revenue of the
company fell short of what it would have been, had the new rates been in effect
throughout the year 1959. No doubt, the vast majority of the consumers who
purchased gas from the utility during the first eight months of the year 1959
continued as customers thereafter. Those persons had paid the rates approved by
the Board during this period and, while they were less than what was fair and reasonable,
it is clear that in the absence of an order of the Board the utility had no
enforceable claim against them for any difference. The new rates while
prospective created a new obligation in respect of transactions already past in
the case of these consumers and, in that respect, were retroactive (Craies on
Statute Law, 5th ed. 357).
This, however, is
exactly what the amendment authorized since it empowered the Board to give
effect to such part of any excess revenues received or losses incurred by a
proprietor after an application has been made to the Board for the fixing of
rates, to the extent that the Board may determine these to have been due to
undue delay in the hearing and determining of the application. The amendment
applies to both losses and gains and, if during the prescribed interval it were
shown that the proprietor had earned amounts in excess of what were determined
to be fair and reasonable, the continuing consumers might be given the benefit
in the rates to be fixed. Since in the interval between the return date of the
application and
[Page 403]
the going into effect of the new rates the customers would
be required to pay the existing rate on the former date, of necessity an order
made under the subsection would be retroactive in its effect, whether the
proprietor had suffered losses or realized excess revenues in the sense that
these expressions are used.
In the Sussex Peerage
case,
Tindal C.J. said that:
the only rule for the
construction of Acts of Parliament is that they should be construed according
to the intent of the Parliament which passed the Act. If the words of the
statutes are in themselves precise and unambiguous, then no more can be
necessary than to expound those words in their natural and ordinary sense.
In Vacher v. London
Society of Compositors,
where the question was as to the interpretation of a section of the Trade
Disputes Act, of 1906, Haidane
L.C. said (p. 113) that he proposed:
to exclude consideration of everything excepting the state
of the law as it was when the statute was passed, and the light to be got by
reading it as a whole, before attempting to construe any particular section.
Subject to this consideration, I think that the only safe course is to read the
language of the statute in what seems to be its natural sense.
Section 9 of The Interpretation Act of Alberta, R.S.A.
1955, c. 160, declares that every Act shall be deemed remedial and shall
accordingly receive such fair, large and liberal construction and
interpretation as will best ensure the attainment of the object of the Act
according to its true intent, meaning and spirit.
In my opinion, the language of the subsection makes its
meaning perfectly clear and it is unnecessary to resort to any outside aid to
interpretation. If, however, it were otherwise, as the evidence shows, the
state of the law as of March 5, 1958, was considered by the Public Utility
Board to be that it was without power to provide for transitional losses, a
state of affairs which the amendment passed so soon thereafter was clearly and
obviously designed to remedy.
It is only, however, such losses as have been due to undue
delay in the hearing and determining of the application which may be remedied.
As to this, it must be said that the finding of the Board might have been
expressed
[Page 404]
with greater clarity. The passage from,
the decision of June 29, 1959, above quoted recites the various delays,
referring particularly to the adjournments after December 19, 1958, and the
delay in giving the decision following the conclusion of the hearings on
February 26. As has been shown, however, at the same time the Board held that
there would be a deficiency of revenue for the years 1959 and 1960 and
authorized the company to file rates for the approval of the Board, suggesting
how such amounts should be obtained. In referring to this in its final decision
the Board said that it was clear that it had by this finding authorized the
company to collect an additional amount of $2,817,929 for the year 1959. In my
opinion, it is implicit in this decision that the Board held that the delay
after December 31, 1958, was undue within the meaning of that expression in the
subsection. I think it is clear that the Board attributed to the expression the
meaning "more than was reasonable in the circumstances" and, in my
opinion, it did not err in doing so. As to whether the delay after December 31
was more than was reasonable, that is a question of fact as to which there can
be no appeal under the statute.
Porter J.A. has
criticized the manner in which effect was given to the Board's order permitting
the recovery of the transitional loss for the year 1959, in various respects.
The schedule approved by the Board appears to have capitalized the actual net
deficiency of revenue after income tax, and added the income tax which would
have been paid by the company if the new rates had been applicable for the year
1959. I think there is much to be said for these views but the questions are
not those in respect of which leave to appeal was granted, and it is, no doubt,
for that reason that they were not raised before the Appellate Division. The
question is whether the Board erred in law and was without jurisdiction to fix
rates enabling the respondent to collect the transitional loss for the year
1959, and not as to whether, granted the Board had power to do this, the method
approved to carry the decision into effect was authorized by the statute. In
these circumstances, I express no opinion upon these matters.
[Page 405]
The respondent cross-appeals from the judgment of the
Appellate Division by which the decision of the Board upon the purchased gas
adjustment clause was set aside, on the ground that there was no jurisdiction
to make such an order.
As I have pointed out,
no formal order was made by the Board, the order of August 29 simply approving
the principle of such a clause as proposed by the utility but referring the
settlement of the form of the order to the parties in the hope that they could
agree. Failing such agreement, permission was given on ten days' notice to
submit an order for the approval of the Board. The respondent contends that
since no formal order was made there was no right of appeal to the Appellate
Division. Section 49(2) reads that leave to appeal may be obtained from a judge
of the Court of Appeal within one month after the making of the order,
decision, rule or regulation sought to be appealed from. I agree with the
learned judges of the Appellate Division that there was such a decision from
which the appeal was properly taken.
In approving rates which
will yield a fair return to the utility upon its rate base, it is, of course,
essential for the Board to estimate the expenses which will necessarily be
incurred thereafter in rendering the service. The fair return permitted is,
after deducting from the gross revenue these necessary estimated expenditures
and such necessary outgoings as taxes, including income taxes. The Board can
only come to a conclusion as to what rates should be approved by determining as
closely as may be done in advance the probable amount of these expenditures.
Upon the application in
the present matter, the expense which would be incurred for purchased gas in
the year 1959 was estimated by the applicant as an amount which, as of August
1959, appeared to be approximately $800,000 less for that year than the amount
which would necessarily be expended. For the year 1960, in respect of which an
estimate had been given for the use of the Board in considering the
application, the amount that would be expended for this purpose had been
underestimated, in the opinion of the executive vice-president of the
applicant, by $1,300,000. The reason for these inaccurate estimates was
explained at length in the evidence of this witness.
[Page 406]
That, in determining what was a fair return and deciding
what rates should be authorized to earn such a return, the expenses of
operation must be estimated as accurately as is reasonably possible is not
questioned by anyone. The Board was apparently satisfied that, in the
circumstances, it was not possible to estimate for years in advance the cost to
which the respondent would be put for purchased gas from year to year, and
concluded that such a provision as was proposed was in the best interests of
the consumers and essential to the company if its financial integrity was to be
maintained.
What was proposed was
that the utility should submit to the Board, and to such other interested
parties as the Board might direct should be notified, not later than November
1st in each year, the figures as to its cost for purchased gas during the first
nine months of the year and its estimate of the amounts required for such
purpose during the months of October, November and December. Dependent upon
whether these costs were in excess of or less than the amount estimated, in
approving the rates the Board would be asked to make such adjustments in the
rates for the following year to carry out the purpose above explained.
Macdonald J.A., with whom the Chief Justice and Johnson J.A.
agreed, was of the opinion that in adopting the proposed clause the Board
intended to fix gas rates without compliance with s. 67(2) of the 1959
amendment which reads:
In fixing just and reasonable rates, tolls or charges, or
schedules thereof, to be imposed, observed and followed thereafter by a
proprietor, the Board shall determine a rate base for the property of the
proprietor that is used or required to be used in his service to the public
within Alberta and fix a fair return thereon.
With great respect, however, the proposed order would
be made in an attempt to ensure that the utility should from year to year be
enabled to realize, as nearly as may be, the fair return mentioned in that
subsection and to comply with the Board's duty to permit this to be done. How
this should be accomplished, when the prospective outlay for gas purchases was
impossible to determine in advance with reasonable certainty, was an
administrative matter for the Board to determine, in my opinion. This, it would
appear, it proposed to do in a practical manner which would, in its judgment,
be fair alike to the utility and the consumer.
[Page 407]
As pointed out by Porter J.A., s. 67(5) does not touch the
matter and this the respondent concedes, but the Board has not assumed to act
under that subsection. Rather did it propose to make the order under the powers
given to it and the duty imposed upon it by the sections to which I have
referred to fix just and reasonable rates which would yield the fair return
mentioned in s. 67(2).
I would dismiss the appeal with costs. I would allow the
cross-appeal with costs and direct that, in lieu of the answer made by the
Appellate Division to the second question, judgment be entered declaring that
the Public Utility Board did not err in law and had jurisdiction to approve the
principle of a Purchased Gas Adjustment Clause, as referred to in the said
decision and order.
Cartwright J.:—I
agree with the reasons of my brother Locke subject only to one reservation. I
do not find it necessary to express an opinion on the contention of the
respondent that the question whether there had been undue delay in the hearing
and determination of the application to the Board was not open to the
appellants and I wish to reserve my opinion on that contention.
On the assumption that the question was open I would agree,
for the reasons given by my brother Locke, that the Board decided it rightly.
I would dispose of the appeal and the cross-appeal as
proposed by my brother Locke.
Appeal dismissed with costs, cross-appeal
allowed with costs.
Solicitor for the City of Edmonton: A. F.
Macdonald, Edmonton.
Solicitors for the Town of Jasper Place: Bryan,
Foote, Andrekson & Wilson, Edmonton.
Solicitors for the City of Red Deer: Kirby,
Murphy, Armstrong & Beames, Red Deer.
Solicitors for the Town of Vegreville: Kane,
Hurlburt and Kane, Edmonton.
Solicitors for the applicant, respondent: Milner,
Steer, Dyde, Massie, Layton, Cregan & Macdonnell, Edmonton.