Supreme Court of Canada
J.D. Sterling Co. Ltd. v. A. Janin Co. Ltd., [1967]
S.C.R. 685
Date: 1967-02-13
J.D. Sterling
Company Limited (Plaintiff) Appellant;
and
A. Janin Company
Limited (Defendant) Respondent.
1966: December 14, 15; 1967: February 13.
PRESENT: Taschereau C.J. and Cartwright,
Fauteux, Abbott and Spence JJ.
ON APPEAL FROM THE COURT OF QUEEN’S BENCH,
APPEAL SIDE, PROVINCE OF QUEBEC
Damages—Construction of sewer—Two
contractors having separate contracts from city—Works of one contractor flooded
by installations of the other—Liability—Quantum of damages—Civil Code, arts.
1053, 1054.
The two parties to this appeal were engaged
in performing contracts with the city of Montreal to build an underground covered collector sewer running parallel to
a stream. By erecting certain culverts in the stream, the defendant caused the
flooding of the works being executed by the plaintiff, thereby causing damages
to the works and also the immobilization for some days of the heavy equipment
being used by the plaintiff. The trial judge found for the plaintiff and
awarded damages in the sum of $52,000. The Court of Appeal, by a majority
judgment, reduced the damages to the sum of $31,916. The plaintiff appealed to
this Court and the defendant cross-appealed. The question of liability was not
in issue in this Court, where only two questions were raised: (1) the quantum
of damages and (2) whether the right of action belonged to a company known as
Miron Co. Ltd. and not to the plaintiff. This second submission was rejected
unanimously in the Courts below and, at the hearing, this Court expressed the
opinion that it had rightly been rejected.
Held: The
appeal should be allowed and the cross-appeal dismissed.
The amount of damages awarded by the trial
judge and upheld by the reasons of the minority in the Court of Appeal was
supported by the evidence and should not have been disturbed.
Dommages—Construction d’un égout—Deux
entrepreneurs ayant contracté séparément avec la cité—Travaux d’un des
entrepreneurs inondés par les installations faites par
l’autre—Responsabilité—Quantum des dommages—Code Civil, arts. 1053, 1054.
Les deux parties dans cet appel étaient à
construire pour la cité de Montréal un égout collecteur souterrain le long
d’une petite rivière. Certaines installations faites par la défenderesse ont eu
pour résultat d’inonder les travaux exécutés par la demanderesse, causant ainsi
des dommages à ces travaux et en plus l’immobilisation pendant quelques jours
de l’équipement lourd employé par la demanderesse. Le juge au procès se
prononça en faveur de la demanderesse et lui accorda des dommages au montant de
$52,000. La Cour d’Appel, par un jugement majoritaire a réduit les dommages à
la somme de $31,916. La
[Page 686]
demanderesse en appela devant cette Cour et
la défenderesse a produit un contre‑appel. La question de responsabilité
n’était pas en jeu devant cette Cour, où deux questions seulement ont été
soulevées: (1) le quantum des dommages et (2) la question de savoir si le droit
d’action appartenait à une compagnie connue sous le nom de Miron Co. Ltd. et
non pas à la demanderesse. Cette seconde prétention a été rejetée unanimement
par les Cours inférieures et, lors de l’audition, cette Cour s’est déclarée
d’accord avec le juge de première instance qui l’avait rejetée.
Arrêt: L’appel
doit être maintenu et le contre-appel rejeté.
Le montant des dommages accordé par le juge
au procès et confirmé par les juges formant la minorité dans la Cour d’Appel
était supporté par la preuve et n’aurait pas dû être changé.
APPEL et CONTRE-APPEL d’un jugement
majoritaire de la Cour du banc de la reine, province de Québec,
réduisant les dommages accordés par le Juge Batshaw. Appel
maintenu et contre-appel rejeté.
APPEAL and CROSS-APPEAL from a majority
judgment of the Court of Queen’s Bench, Appeal Side, province of Quebec1, reducing the amount of damages awarded by Batshaw J.
Appeal allowed and cross-appeal dismissed.
Jacques Leduc, Q.C., for the plaintiff,
appellant.
Walter C. Leggat, Q.C., for the
defendant, respondent.
The judgment of the Court was delivered by
CARTWRIGHT J.:—This is an appeal from a judgment
of the Court of Queen’s Bench (Appeal Side)1 which, by a majority,
allowed an appeal from a judgment of Batshaw J. to the extent of reducing the
amount of damages awarded to the appellant from $52,000 to $31,916. Choquette
and Badeaux JJ. dissenting would have dismissed the appeal.
In this Court, the appellant asks that the
judgment at trial be restored; the respondent asks that the appeal be dismissed
and by way of cross-appeal asks that the action be dismissed with costs or,
alternatively, that a new trial be ordered to assess the damages, if any, to
which the appellant is entitled.
The action arose from the fact that while the
parties were engaged in performing contracts with the City of Montreal to build an underground covered
collector sewer
[Page 687]
running parallel to a stream known as the
“Little Rivière St. Pierre” the respondent, by the erection of certain
culverts in the stream, caused the flooding of the works being executed by the
appellant damaging the works and causing the immobilization for some days of
the heavy equipment being used by the appellant.
At the trial the respondent denied liability,
but in this Court only two points were raised, first, the quantum of damages
and, second, the submission made by the respondent that if damages had been
caused for which the respondent was responsible the right of action for those
damages was that of a company known as Miron Company Limited and not of the
appellant. This second submission was rejected unanimously in the Courts below
and at the conclusion of the argument of counsel for the appellant in this
Court, counsel for the respondent was informed that we were all of opinion that
it was rightly rejected for the reasons given by Batshaw J. and that he need
not deal with it.
The claim for damages was itemized in the
Declaration and totalled $110,600. This was slightly amended at the trial and,
as amended was as follows:
|
(1) Travaux d’assèchement, de pompage et
de protection de l’équipement et de la machinerie se trouvant sur les
chantiers
|
$30,254.00
|
|
(2) Installation et enlèvement de
barrages temporaries
|
4,104.00
|
|
(3) Construction d’un talus étanche et
nettoyage et assèchement des tranchées d’excavation
|
6,208.00
|
|
(4) Pour immobilisation d’équipement et
retards dans l’exécution des travaux
|
52,634.00
|
|
(5) Déboursés divers pour travaux
spéciaux requis
|
5,676.00
|
|
(6) Augmentation de frais généraux et
perte de benefices
|
11,800.00
|
|
|
$110,676.00
|
After setting out the itemized claim as above
the learned trial judge continued:
The interruption of the Plaintiff’s work
caused by the flood lasted for a period which it was difficult to determine
precisely since resumption of the operations could only be effected on a
gradual basis. The estimates varied from 7 to 15 days; R.F. Bird, the Executive Vice-President for Sterling, who was its principal witness as
to the damages, affirmed that it lasted for about 8 days. To be conservative
however, the Plaintiff based its claim on a period of 5.2 days which
seems to the Court not to be unwarranted.
This finding was not challenged.
[Page 688]
The learned trial judge disallowed item 6 and in
this Court no argument was advanced against his having done so.
The learned trial judge then pointed out that of
the remaining amount of $98,876 a sum of $84,812 represented the daily rental
value of the equipment claimed on the basis of the calculation explained by the
appellant’s witness Bird, and the balance of $14,064 represented the total of
items 1, 2, 3 and 5 excluding therefrom the portions of those items made up of
rental value of equipment. That this is so appears clearly from Exhibit P-14.
The amount of damages to be assessed for the claims totalling this $14,064 was
fixed by the learned trial judge at $12,000 and no ground has been shewn from
disturbing this figure.
There remains the item of $84,812 for which the
learned trial judge allowed $40,000. As to this item the evidence of the
witness Bird supported the claim of $84,812 while that of the respondent’s
witness Rousseau was to the effect that the amount should be $19,916. The
learned trial judge did not accept either of these figures and gave reasons for
his refusal to do so. His reasons for not accepting Rousseau’s figure were
concurred in by Badeaux J. with whom, as already mentioned, Choquette J.
agreed.
With respect, I am unable to discern any
sufficient reason for reversing the conclusion of the learned trial judge that
he should not accept Rousseau’s evidence in toto, nor am I able to say from a perusal
of the record that his estimate of $40,000 for this item was erroneous. While
always hesitant to differ from the judgment of a majority in the Court of
Appeal in fixing damages the amount of which is not susceptible of precise
arithmetical calculation, it does appear that in the reasons of the majority
there was a misapprehension of the basis on which the learned trial judge had
proceeded.
As already pointed out, the award of the learned
trial judge was made up of two items: (i) $12,000 allowed in respect of a claim
of $14,064 (being the total of items 1, 2, 3 and 5 excluding the sum of $32,178
charged in those items for the rental value of equipment) and (ii) $40,000
allowed in respect of a claim of $84,812 (being the total of item 4 and the
above sum of $32,178). That this is so is
[Page 689]
made clear in the reasons of the learned trial
judge when, after dealing with the claim for $84,812 and giving his reasons for
allowing $40,000 in respect thereof, he says:
Having dealt with the $84,812.00, part of
Plaintiff’s claim of $98,876.00 referred to above, there remains the difference
of $14,064.00 which represents miscellaneous items of damages other than for
rental value of equipment contained in paragraph 29 sub-paragraphs 1, 2, 3 and
5 of the declaration. It was conceded that this figure could not be ascertained
with mathematical accuracy and represented a rough estimate of the damages
involved. In the opinion of the Court this part of the claim could reasonably
be assessed at $12,000.00.
Casey J., however, says at the opening of his
reasons:
This claim was for $110,600.00 divided into
six items. The trial judge disallowed No. 6 ($11,800.00) and allowed $40,000.00
for No. 4 ($56,400.00 claimed) and $12,000.00 for nos. 1, 2, 3 and 5 ($42,400
claimed).
No doubt Rousseau’s figure of $19,916 was
intended by that witness to represent the amount which in his opinion should
have been allowed in respect of the total of $84,812 claimed for rental value
of equipment; but I think it probable that Casey J. might not have adopted that
figure if he had realized that the appellant’s claim in regard to this item,
supported as it was by Bird’s evidence, was not for $56,400 but for the much
larger sum of $84,812. Be that as it may, I have reached the conclusion that the
figure arrived at by the learned trial judge and upheld by the reasons of the
minority in the Court of Queen’s Bench was supported by the evidence and should
not have been disturbed.
I would allow the appeal with costs in this
Court and in the Court of Queen’s Bench (Appeal Side) and restore the judgment
of the learned trial judge. I would dismiss the cross-appeal with costs.
Appeal allowed with costs; cross-appeal dismissed with
costs.
Attorneys for the plaintiff, appellant:
Birtz & Leduc, Montreal.
Attorneys for the defendant, respondent:
Foster, Watt, Leggat & Colby, Montreal.