McNair,
J.:—This
is
an
appeal
from
the
Minister's
disallowance
of
sums
deducted
by
the
plaintiff
as
accounts
payable
in
its
taxation
year
ending
February
28,
1983.
The
issue
is
whether
the
Minister
acted
correctly
in
characterizing
these
sums
as
"holdback
payables”,
whose
deductibility
was
prohib-
ited
under
paragraphs
18(1)(a)
and
18(1)(e)
of
the
Income
Tax
Act,
R.S.C.
1970-71-72,
c.
63,
as
amended.
While
the
amounts
actually
disallowed
totalled
$349
581.20,
counsel
for
the
Crown
conceded
at
the
commencement
of
trial
that
the
correct
figure
for
the
amounts
in
dispute
was
$347,276.08.
The
Facts
The
plaintiff
company
carries
on
the
business
of
mechanical
engineering
and
contracting
in
the
Province
of
Alberta.
In
the
taxation
year
in
question,
the
plaintiff
was
involved,
inter
alia,
in
three
major
construction
projects
and
one
minor
one,
designated
as
jobs
370,
379,
382
and
391
respectively.
The
plaintiff's
president,
Lloyd
E.
Wilson,
appeared
as
a
witness
on
its
behalf.
He
explained
that
his
company,
as
one
of
a
number
of
subcontractors
engaged
in
these
projects,
was
responsible
for
the
installation
of
plumbing,
heating,
sprinklers
and
controls,
and
other
mechanical
systems.
For
each
of
the
projects
in
issue,
the
plaintiff
entered
into
a
contract
with
a
different
general
contractor.
The
general
contractors,
in
turn,
concluded
“prime
contracts"
with
the
different
projects'
owners.
The
plaintiff,
as
subcontractor,
engaged
a
number
of
sub-subcontractors
to
supply
and,
in
all
but
one
case,
also
install
equipment.
Mr.
Wilson
testified
that
while
his
company
might
sometimes
use
formal
contracts
in
its
dealings
with
sub-subcontractors,
the
sub-subcontractors
involved
in
the
projects
in
question
were
retained
under
purchase
orders.
These
purchase
orders,
copies
of
which
were
exhibited
in
the
book
of
documents
jointly
proffered
by
counsel
for
both
parties,
typically
provided
that
the
different
sub-subcontractors
were
to
"supply
and
install"
various
materials
"as
per
plans,
specifications,
and
addenda"
to
the
satisfaction
or
approval
of
the
engineer
or
engineers.
The
subsubcontractors
thus
hired
regularly
submitted
progress
invoices
for
amounts
reflecting
the
estimated
work
completed
as
of
a
certain
date
each
month.
Notations
on
these
invoices
reveal
the
plaintiff
generally
paid
its
subsubcontractors
within
several
months
of
receipt
of
their
invoices.
However,
the
plaintiff
retained
from
these
payments
certain
amounts
referred
to
as
"H/Bs"
or
holdbacks.
In
its
income
tax
return
for
the
taxation
year
ending
February
28,
1983,
the
plaintiff
characterized
the
total
amount
of
these
holdbacks
in
the
sum
of
$788,966
as
accounts
payable
deductible
as
outlays
or
expenses
made
or
incurred
by
it
for
the
purpose
of
gaining
or
producing
income
from
its
business
within
the
meaning
of
paragraph
18(1
)(a)
of
the
Act.
As
mentioned,
the
defendant
disallowed
the
deduction
of
$347,276.08
as
holdback
payables.
Paragraph
18(1)(a)
The
first
statutory
provision
on
which
the
Minister
relied
is
paragraph
18(1)(a)
of
the
Income
Tax
Act,
which
in
1983
read
as
follows:
18.
(1)
In
computing
the
income
of
a
taxpayer
from
a
business
or
property
no
deduction
shall
be
made
in
respect
of
(a)
an
outlay
or
expense
except
to
the
extent
that
it
was
made
or
incurred
by
the
taxpayer
for
the
purpose
of
gaining
or
producing
income
from
the
business
or
property;
At
issue
is
whether
the
amounts
deducted
represented
expenses
incurred
by
the
plaintiff
in
the
taxation
year.
The
plaintiff
could
properly
deduct
the
sums
in
question
only
if
it
was
in
fact
under
an
obligation
to
pay
them:
The
Queen
v.
Burnco
Industries
Ltd.
et
al.,
[1984]
C.T.C.
337;
84
D.T.C.
6348.
Put
another
way,
the
question
is
whether
the
holdbacks
were
payable
within
the
taxation
year.
Counsel
for
the
plaintiff
argued
that
because
the
terms
of
the
formal
contract
between
the
plaintiff
and
the
various
general
contractors
contained
no
reference
to
the
sub-subcontractors,
the
only
contractual
documents
rele-
vant
to
the
appeal
were
the
purchase
orders
and
the
corresponding
invoices.
While
the
plaintiff
withheld
in
all
cases
a
percentage
of
the
amounts
invoiced,
counsel
submitted
that
there
was
nothing
in
the
terms
of
the
purchase
orders
or
any
other
contractual
document
which
permitted
it
to
do
so.
In
his
submission,
the
sub-subcontractors
were
legally
entitled
to
the
full
amount
of
the
progress
estimates
at
the
time
they
submitted
their
invoices
therefor.
Anticipating
the
argument
of
opposing
counsel,
he
contended
that
there
was
neither
a
verbal
agreement
nor
a
practice
or
custom
of
the
trade
in
respect
of
holdbacks
at
this
level
of
the
construction
industry
in
Alberta.
Counsel
for
the
defendant
submitted,
on
the
other
hand,
that
the
evidence
supported
the
Crown's
proposition
that
by
virtue
of
a
custom
or
practice
respecting
the
retention
of
holdbacks
by
subcontractors
from
subsubcontractors,
the
relationship
between
the
plaintiff
and
its
subsubcontractors
could
be
said
to
be
governed
by
implied
terms
providing
for
such
withholdings
in
the
present
case.
Relying,
inter
alia,
on
the
decision
of
Noël,
A.C.J.
in
J.L.
Guay
Ltée
v.
M.N.R.,
[1971]
F.C.
237;
[1971]
C.T.C.
686;
71
D.T.C.
5423
(F.C.T.D.);
affd
[1972]
F.C.
1441;
[1973]
C.T.C.
506;
73
D.T.C.
5373
(F.C.A.);
affd
without
reasons
[1975]
C.T.C.
97;
75
D.T.C.
5094
(S.C.C.),
and
on
that
of
the
Federal
Court
of
Appeal
in
Newfoundland
Light
&
Power
Co.
v.
Canada,
[1990]
1
C.T.C.
229;
90
D.T.C.
6166;
affg
in
part
[1986]
2
C.T.C.
235;
86
D.T.C.
6373
(F.C.T.D.),
she
raised
two
further
arguments:
firstly,
because
the
purchase
orders
stipulated
the
performance
of
the
sub-subcontractors’
work
to
engineers’
approval
or
satisfaction,
it
followed
that
the
plaintiff's
liability
to
disburse
the
amounts
withheld
was
merely
contingent;
and,
secondly,
holdbacks
were
not
deductible
in
that,
by
virtue
of
possible
chargebacks,
set-offs
and
other
price
reductions,
the
exact
amounts
ultimately
released
by
the
plaintiff
were
uncertain
in
the
taxation
year.
Purchase
Orders
and
Invoices
A
review
of
the
purchase
orders
and
invoices
relating
to
the
projects
in
issue
reveals
those
documents
indeed
contain
no
express
provisions
relating
to
holdbacks
between
the
plaintiff
company
and
its
sub-subcontractors.
Furthermore,
there
is
nothing
in
the
terms
of
the
plaintiff's
contracts
with
the
various
general
contractors
which
could
be
said
to
import
any
such
terms
into
the
relationship
at
the
lower
level.
The
subcontracts,
all
completed
on
Alberta
Standard
Sub-contract
Forms
("A.C.A.
Form
A”),
incorporate
by
reference
many
of
the
terms
of
the
prime
contract
between
the
general
contractors
and
the
owners
of
the
respective
projects.
Article
Il
of
A.C.A.
Form
A,
entitled
“Payment”,
specifically
provides
in
part
as
follows:
A.
The
Sub-contractor
shall
submit
proper
progress
estimates
in
writing
on
the
day
of
each
month
to
the
Contractor
for
approval
and
due
processing
covering
the
value
of
the
materials
delivered
for
the
Project
and
the
work
performed
by
the
Sub-contractor
up
to
such
date,
whereupon
payment
to
the
Sub-contractor
by
the
above
submission
date
of
the
proper
estimate
by
the
Sub-contractor
or
seven
(7)
days
after
certification
of
the
proper
estimate
by
the
Architect/Engineer,
whichever
is
the
later.
Contractor
in
the
amount
of
|
%
shall
become
due
and
payable
|
days
after
the
|
B.
and
the
whole
of
the
balance
of
the
amount
payable
by
the
Contractor
to
the
Sub-contractor
shall
be
paid
one
day
after
the
Builders’
Lien
rights
expire
or
ten
days
after
receipt
of
such
amount
by
the
Contractor
from
the
Owner.
The
evidence
indicates
the
subcontracts
typically
provided
for
a
withholding
of
15
per
cent
of
payments.
Mr.
Wilson
testified
his
company's
normal
procedure
was
to
gather
its
sub-subcontractors'
invoices
at
the
end
of
each
month
and,
partly
on
the
basis
thereof
to
submit
a
progress
estimate
to
the
general
contractors.
The
latter,
in
turn
assembling
the
progress
estimates
of
their
various
subcontractors,
would
thereupon
submit
their
own
progress
estimates
to
the
owner.
Subject
to
the
approval
of
the
engineers
and/or
architects,
the
general
contractors
would
then
receive
the
stipulated
percentage
of
payment
from
the
owner,
and,
after
withholding
the
percentage
agreed
to
in
A.C.A.
Form
A,
pass
payment
down
to
their
subcontractors.
While
the
plaintiff
customarily
withheld
moneys
from
its
subsubcontractors
engaged
on
the
projects
in
the
usual
range
of
15
per
cent
of
the
sums
invoiced,
there
was
nothing
in
its
own
contracts
with
the
various
general
contractors
which
permitted
it
to
do
so.
A.C.A.
Form
A
used
in
Alberta,
unlike
the
national
subcontract
form
C.C.A.L.
(1)
apparently
used
elsewhere,
contains
no
reference
whatever
to
sub-subcontractors.
Nor
was
there
any
mention
of
the
plaintiff's
entitlement
to
holdbacks
in
the
documents
governing
the
relationship
at
the
lower
level.
The
wording
of
the
purchase
orders
pursuant
to
which
the
plaintiff
retained
its
sub-subcontractors,
as
counsel
for
the
plaintiff
pointed
out,
was
very
terse.
Neither
the
formal
terms
and
conditions
of
the
orders
nor
the
descriptions
therein
of
the
various
projects
mentioned
holdbacks.
As
for
the
invoices
submitted
by
the
plaintiff's
sub-subcontractors,
the
only
terms
stipulated
therein
typically
read:
"Terms:
Net
30
days.
_°/o
per
month
service
charge
on
overdue
accounts".
Thus,
I
am
satisfied
that
the
contractual
documents
governing
the
plaintiff's
relationships,
both
with
its
general
contractors
at
the
next
level
above
and
its
sub-subcontractors
below,
did
not
expressly
authorize
withholdings
from
payments
made
to
subsubcontractors.
Implied
Terms
Counsel
for
the
defendant
argued
that
the
express
terms
of
the
purchase
orders
and
invoices
were
not
the
only
things
determinative
of
the
plaintiff's
dealings
with
its
sub-subcontractors.
In
her
submission,
there
was
evidence
of
a
practice
or
custom
for
the
imposition
of
holdbacks
by
subcontractors
on
subsubcontractors
in
the
Alberta
construction
industry
whereby
terms
providing
for
imposition
were
incorporated
by
implication
into
the
contracts
between
the
plaintiff
and
its
sub-subcontractors
in
the
present
case.
I
am
unable
to
find
on
the
evidence
as
a
whole
that
such
a
custom
or
practice
did,
in
fact,
exist.
Mr.
Smith,
president
of
a
sub-subcontracting
company,
testifying
as
an
expert
witness
on
behalf
of
the
plaintiff,
indicated
on
cross-examination
that
it
might
be
common
in
the
industry
to
have
withholdings
in
cases
of
subsubcontractors
supplying
and
installing
equipment
under
a
purchase
order.
However,
on
re-examination
he
intimated
that
there
was
no
set
custom
or
practice
to
that
effect.
The
plaintiff's
second
expert
witness,
Mr.
Gove,
president
of
a
general
contracting
company,
was
also
cross-examined
about
payments
to
suppliers
and
installers
working
under
purchase
orders.
He
stated
that
holdbacks
would
probably
be
normal
on
larger
projects,
but
reaffirmed
the
opinion
proffered
in
his
expert's
affidavit
that
there
was
no
practice
or
custom
respecting
subcontractors'
withholdings
from
progress
payments:
"It
might
vary
from
job
to
job,
depending
on
what
the
work
is,
the
flexity
of
it,
payment
terms.
There
is
a
lot
of
things
that
are
built
into
it.
It’s
not
a
thing
that
you
do
all
the
time."
Given
Mr.
Smith's
confusion
on
the
stand,
both
counsel
were
in
agreement
that
little
weight
should
be
attached
to
his
testimony,
and
I
agree.
As
for
Mr.
Gove,
his
area
of
expertise
was
at
the
general
contractor
level,
and
his
experience
with
sub-subcontractors
was
limited
to
his
dealings
with
them
on
a
daily
work
basis.
Accordingly,
I
am
unable
to
attach
much
weight
to
this
witness’
evidence.
Finally,
while
the
plaintiff's
president
did
indicate
in
his
examination
for
discovery
that
sub-subcontractors
repeatedly
engaged
by
the
plaintiff
would
probably
assume
part
of
their
billed
invoices
would
be
withheld
because
"they
must
feel
that
that
is
the
custom”,
he
repeatedly
pointed
out
that
he
had
no
knowledge
of
the
payment
procedures
followed
by
his
competitors
in
the
industry
and
restricted
his
testimony
at
trial
to
his
own
company's
dealings
with
its
sub-subcontractors.
In
Georgia
Construction
Co.
v.
Pacific
Great
Eastern
Ry.
Co.,
[1929]
S.C.R.
630;
[1929]
4
D.L.R.
161,
Duff,
J.
stated
at
page
633:
.
.
.
Usage,
of
course,
where
it
is
established,
may
annex
an
unexpressed
incident
to
a
written
contract;
but
it
must
be
reasonably
certain
and
so
notorious
and
so
generally
acquiesced
in
that
it
may
be
presumed
to
form
an
ingredient
of
the
contract,
Juggomohun
Ghose
v.
Manickchund,
[7
Moore's
Indian
Appeals
263,
at
p.
282].
In
the
present
case,
the
evidence
falls
far
short
of
establishing
that
there
was
a
practice
in
the
Alberta
construction
industry
by
which
subcontractors
withheld
moneys
from
progress
payments
to
their
sub-subcontractors
which
was
so
certain
and
notorious
that
I
could
find
it
to
be
a
term
of
the
purchase
orders
between
these
parties.
Nor
can
I
accept
the
argument
of
counsel
for
the
defendant
that
terms
may
be
implied
in
the
plaintiff's
contracts
with
its
subsubcontractors
by
reason
of
the
parties’
previous
dealings.
It
is
true
that
the
various
sub-subcontractors
generally
accepted
the
plaintiff's
imposition
of
holdbacks
without
complaint
and
charged
no
interest
on
their
invoices.
It
is
also
a
fact
that
Wide-Lite
Ltd.,
the
only
sub-subcontractor
which
did
question
the
plaintiff's
accounting,
was
apparently
satisfied
by
a
letter
of
explanation.
These
facts
alone,
in
my
opinion,
do
not
permit
me
to
infer
that
the
parties
always
intended
to
contract
on
that
basis,
especially
when
the
terms
of
the
purchase
orders
and
invoices
were,
as
here,
clear
and
unequivocal.
Finally,
there
was
no
evidence
of
a
verbal
agreement
applying
to
the
Alberta
construction
industry
generally
in
respect
of
holdbacks,
and
on
that
basis
alone
the
present
case
is
distinguishable
from
the
situation
in
Ellis
Construction
Ltd.
v.
M.N.R.,
[1982]
C.T.C.
2604;
82
D.T.C.
1625
(T.R.B.).
Engineers'
Approval
As
noted
previously,
each
of
the
plaintiff's
purchase
orders
for
the
projects
in
question
referred,
under
the
heading
“description”,
to
a
requirement
that
the
particular
sub-subcontractor
perform
his
work
as
per
the
plans
and
specifications
to
the
approval
or
satisfaction
of
the
engineers
and,
in
one
case,
the
architect.
If
I
apprehend
the
matter
correctly,
defendant's
counsel
argues
that
the
effect
of
these
approval
stipulations
is
to
make
uncertain
the
plaintiff's
liability
to
pay
its
sub-subcontractors
the
amounts
due
to
them,
thus
precluding
the
plaintiff
from
asserting
that
the
holdbacks
were
in
fact
payable
during
the
taxation
year
and
deductible
under
paragraph
18(1)(a)
of
the
Act.
In
support
of
this
proposition,
counsel
referred
to
the
decisions
in
Guay,
supra,
and
Newfoundland
Light
&
Power,
supra.
In
Guay,
Noël,
A.C.J.
had
to
decide
whether
the
appellant
general
building
contractor
was
entitled
to
deduct
holdbacks
which,
pursuant
to
the
terms
of
its
contracts
with
subcontractors,
it
was
not
obliged
to
pay
to
the
latter
until
35
days
after
final
approval
of
the
work
by
the
architect.
The
Minister
had
refused
to
allow
their
deduction
under
statutory
provisions
equivalent
to
the
present
paragraphs
18(1)(a)
and
18(1)(e)
of
the
Act.
Noël,
A.C.J.
said
at
page
5427:
As
a
general
rule,
if
an
expenditure
is
made
which
is
deductible
from
income,
it
must
be
deducted
by
computing
the
profits
for
the
period
in
which
it
was
made,
and
not
some
other
period.
The
procedure
adopted
by
appellant,
of
deducting
from
its
income
amounts
withheld
by
it,
which
it
may
one
day
be
required
to
pay
its
sub-contractor,
but
which
the
latter
may
not
claim
until
35
days
after
the
work
is
approved
by
the
architect,
is,
as
we
have
just
seen,
contrary
to
the
rule
that
an
expenditure
may
only
be
deducted
from
income
for
the
period
in
which
it
was
made,
and
this
would
suffice
to
dispose
of
the
present
appeal.
However,
as
we
have
seen
above,
there
is
an
additional
reason
for
dismissing
the
appeal:
this
is
that
we
are
dealing
with
amounts
withheld
which
are
not
only
uncertain
as
to
quantum
if
partial
damages
result
from
badly
done
work,
but
which
will
no
longer
even
be
due
or
payable
if
damages
exceed
the
amounts
withheld.
How
can
it
he
claimed
in
such
circumstances
that
a
certain
and
current
expense
is
involved,
and
that
the
amounts
withheld,
which
appellant
has
full
enjoyment
of
until
it
pays
the
amounts
owing
to
the
sub-contractor,
or
until
compensation
becomes
due,
may
be
deducted
by
appellant
as
it
receives
them
from
the
owner.
The
appellant
in
Newfoundland
Light
&
Power
was
a
Newfoundland
company
engaged
in
the
business
of
generating,
transmitting
and
distributing
electrical
energy
to
the
public
which,
under
the
terms
and
conditions
of
its
contracts
with
general
contractors,
was
entitled
to
withhold
ten
per
cent
of
amounts
otherwise
payable
to
the
latter,
pending
approval
or
certification
of
the
works
by
its
engineers.
In
the
taxation
year
in
question,
the
appellant
withheld
both
“capital
holdbacks",
on
which
it
claimed
capital
cost
allowance,
as
well
as
"service
holdbacks"
relating
to
maintenance
work.
At
the
trial
level,
Martin,
J.
accepted
expert
evidence
that
generally
accepted
accounting
principles
allowed
the
amounts
in
issue
to
be
treated
as
actual
rather
than
contingent
liabilities,
but
nevertheless
disallowed
the
taxpayer's
deductions
under
paragraph
18(1
)(e).
In
the
Court
of
Appeal,
Desjardins,
J.A.
found
that
paragraph
18(1)(e)
was
inapplicable
to
the
facts
of
the
case,
and
Pratte
and
Hugessen,
JJ.A.,
each
writing
concurring
reasons
for
judgment,
agreed
that
the
trial
judge
had
erred
in
relying
on
that
paragraph
of
the
Act.
In
the
view
of
the
appeal
judges,
the
result
of
the
case
was
dictated
by
the
decisions
in
M.N.R.
v.
Colford
Contracting
Co.,
[1960]
Ex.
C.R.
433;
[1960]
C.T.C.
178;
60
D.T.C.
1131
(Ex.
Ct.);
affd
without
reasons
[1962]
S.C.R.
viii;
[1962]
C.T.C.
546;
62
D.T.C.
1338
(S.C.C.),
and
Guay,
supra.
As
Hugessen,
J.A.
stated
at
page
240
(D.T.C.
6174):
That
said,
however,
the
appellant
faces
the
insuperable
obstacle
of
the
decisions
in
Colford
and
Guay.
Each
of
those
decisions
was
approved,
albeit
without
extensive
reasons,
by
the
Supreme
Court.
In
my
view,
they
stand
for
the
proposition
that,
as
a
matter
of
law,
uncertified
construction
holdbacks
are
to
be
regarded
as
contingent
both
from
the
point
of
view
of
the
payor
and
from
that
of
the
payee.
That
being
so,
the
appellant
cannot
treat
such
uncertified
holdbacks
as
"an
outlay
or
expense"
under
paragraph
18(1
)(a)
(the
"service"
holdbacks)
or
as
“part
of
the
capital
cost
.
.
.
of
property"
under
paragraph
20(1
)(a)
(the
“capital”
holdbacks).
During
his
examination
for
discovery,
Mr.
Wilson
was
questioned
about
the
effect
of
the
references
on
each
purchase
order
to
work
being
done
as
per
plans
and
specifications
to
the
engineers'
or
architect's
approval.
He
was
asked
specifically
whether
the
plaintiff
would
have
considered
the
various
contracts
to
be
completed
prior
to
such
approval
being
given,
and
he
repeatedly
answered
in
the
negative.
Under
rigorous
cross-examination,
he
qualified
his
earlier
discovery
answers
by
suggesting
that
he
might
have
taken
the
reference
to
"contract"
to
mean
those
subsisting
between
his
company
and
the
general
contractors,
rather
than
the
ones
at
the
lower
level
between
his
company
and
the
various
sub-subcontractors.
He
went
on
to
explain
that
while
the
plaintiff's
payments
from
the
general
contractors
were
dependent
upon
final
engineers'
or
architect's
approval
in
the
form
of
a
substantial
completion
certificate
pursuant
to
the
specific
terms
of
A.C.A.
Form
A,
no
such
contingency
obtained,
in
his
opinion,
in
the
case
of
purchase
orders.
The
witness
further
testified
that
on
large
projects
the
engineers
would
frequently
visit
the
job
site
and
regularly
issue
inspection
reports
outlining
any
perceived
deficiencies
which
needed
to
be
corrected
by
the
various
sub-trades
as
the
work
progressed.
According
to
Mr.
Wilson,
it
was
the
engineers'
approval
of
these
deficiencies,
rather
than
the
issuance
of
a
substantial
completion
certificate,
which
usually
signalled
the
plaintiff
to
release
holdbacks
to
the
subsubcontractors,
as
the
following
excerpt
from
his
cross-examination
illustrates:
Q.
And
would
Wil
Mechanical
have
considered
this
work
completed
prior
to
the
engineer's
approval?
A.
I
have
to
answer
it
the
same
way,
and
I
probably
could
qualify
a
little
bit
of
my
reasoning
for
that,
is
that
in
all
these
it
says
engineer's
approval,
but
it
doesn't
refer
to
the
substantial
completion
date,
it
doesn't
refer
to
the
time
that
is
allotted
for
payment
after
the
substantial
completion
date.
All
these
items
that
are
specific
to
the
Alberta
contract
form
or
the
form
that
I
enter
into
with
the
general
contractor
are
not
in
this,
so
in
reference
to
the
engineer's
approval,
it
is
the
engineer
expecting
that
his
job
inspection
reports
have
been
rectified
to
his
satisfaction,
and
as
it
goes
along
the
final
accountability
for
all
of
this
is
the
substantial
completion.
I
accept
the
witness'
clarification
of
the
answers
given
on
discovery
for
two
reasons.
Firstly,
the
evidence
shows
that
the
plaintiff
did
not
always
await
the
issuance
of
the
substantial
completion
certificate
before
releasing
holdbacks
to
its
sub-subcontractors.
For
instance,
the
completion
certificate
for
Job
379
was
issued
in
August
of
1983.
While
the
plaintiff
did
not
release
holdbacks
to
its
sub-subcontractor,
Green
Thumb
Irrigation
Ltd.,
until
that
date,
nevertheless
it
made
payments
totalling
$45,666.30
to
another
sub-subcontractor
involved
in
the
same
project,
Wide
Lite
Ltd.,
on
March
21
and
May
13,
1983.
To
take
another
example,
Job
370
was
not
substantially
completed
until
November
1983.
According
to
the
records,
the
plaintiff,
however,
had
by
then
paid
in
full
all
holdbacks
owing
to
four
different
sub-subcontractors
engaged
on
the
same
project.
Counsel
for
the
defendant
endeavoured
to
show
during
cross-
examination
that
the
timing
for
the
release
of
holdbacks
to
the
subsubcontractors
was
directly
related
to
the
receipt
by
the
plaintiff
of
holdbacks
retained
at
the
subcontract
level.
I
am
unable
to
find
on
the
evidence
that
any
such
correlation
existed.
In
any
event,
I
would
be
inclined
to
question
its
relevance.
The
fact
is
that
the
plaintiff,
more
frequently
than
not,
paid
its
subsubcontractors
in
full
prior
to
the
dates
when
the
substantial
completion
certificates
were
issued,
and
this
alone
suffices
to
convince
me
that
Mr.
Wilson
was
right
in
stating
that
those
certificates
were
not
the
ones
referred
to
in
the
various
purchase
orders.
There
is
another
reason
for
accepting
Mr.
Wilson's
evidence.
He
testified
that
on
occasion,
although
apparently
not
on
the
projects
in
issue,
the
plaintiff
would
release
holdbacks
to
sub-subcontractors
upon
determining
their
work
to
be
completed
to
its
satisfaction.
However,
the
plaintiff
would
still
bear
ultimate
responsibility
for
any
remaining
deficiencies
discovered
at
the
time
the
final
completion
certificate
was
issued.
In
my
view,
this
evidence
supports
the
witness'
contention
that
the
release
of
holdbacks
was
dependent
not
upon
the
issuance
of
the
certificates,
but
rather
upon
the
plaintiff's
satisfaction
with
the
work
of
its
sub-subcontractors.
This
subjective
criterion
could
well
be
influenced
by
the
engineers'
on-site
inspection
reports.
Not
surprisingly,
the
plaintiff's
own
cash
flow
situation
appears
to
have
been
a
factor
determining
the
timing
of
holdback
releases.
I
note
in
this
regard
Mr.
Wilson's
testimony
that
cash
management
concerns
prompted
his
company's
imposition
of
holdbacks
in
the
first
place.
In
my
opinion,
the
present
case
is
distinguishable
from
Guay
and
Newfoundland
Light
&
Power,
supra.
The
terms
of
the
contracts
in
those
cases
specifically
provided
for
the
retention
of
holdbacks
until
"final
approval
of
the
work
by
the
architect"
(D.T.C.
5425)
and
“until
the
contract
has
been
substantially
completed
to
the
satisfaction
of
the
Engineer"
(C.T.C.
236;
D.T.C.
6167)
respectively.
I
am
also
of
the
opinion
that
the
principle
enunciated
by
Hugessen,
J.A.
in
Newfoundland
Light
&
Power
(C.T.C.
240;
D.T.C.
6174),
namely,
that
”.
.
.
as
a
matter
of
law,
uncertified
construction
holdbacks
are
to
be
regarded
as
contingent
both
from
the
point
of
view
of
the
payor
and
from
that
of
the
payee"
has
no
application
to
the
circumstances
of
this
case.
Moreover,
I
accept
the
submission
of
plaintiff's
counsel
that
Guay
and
Newfoundland
Light
&
Power
are
distinguishable
on
another
ground.
In
Guay,
the
subject
contracts
were
between
a
general
contractor
and
its
subcontractors.
In
Newfoundland
Light
&
Power,
the
relevant
contracts
were
concluded
at
yet
a
higher
level,
that
is,
between
the
owner
and
the
general
contractor.
Furthermore,
each
of
the
contracts
in
those
cases
specifically
provided
for
the
withholding
of
a
specified
percentage
of
monthly
progress
estimates.
Consequently,
I
cannot
see
that
the
principles
enunciated
by
those
cases
apply
in
the
present
situation.
Chargebacks
and
Set-offs
The
submission
of
defendant's
counsel
on
this
point
is
simply
that
the
actual
amounts
sought
to
be
deducted
by
the
plaintiff
in
respect
of
the
subject
projects
were
not
certain
as
of
February
28,
1983,
having
regard
to
the
plaintiff's
evidence
that
these
could
involve
chargebacks
against
the
sub-subcontractors
and
deficiencies
which
the
plaintiff
would
eventually
have
to
correct.
Because
of
the
uncertainty
as
to
liability
and
quantum,
it
therefore
follows,
in
counsel's
submission,
that
the
holdbacks
in
the
present
case
are
analogous
to
those
in
the
cases
of
Guay
and
Newfoundland
Light
&
Power
because
of
the
similar
uncertainty
as
to
liability
and
quantum.
In
my
view,
those
cases
are
again
distinguishable.
It
seems
to
me
that
the
principles
stated
therein
are
predicated
on
the
existence
of
stipulations
regarding
the
issuance
of
final
certificates
by
architects
or
engineers
in
the
particular
contracts
involved
which,
as
I
have
found,
are
dissimilar
to
the
ones
in
the
case
at
bar.
In
Guay,
Noël,
A.C.J.
observed
at
page
5426:
It
seems
to
me,
therefore,
that
it
is
far
from
certain
that
the
amounts
so
withheld
will
be
paid
in
full
to
the
sub-contractor.
In
fact,
the
payment
of
these
amounts
to
the
sub-contractor
is
perhaps
to
be
regarded,
if
damages
are
incurred,
as
contingent.
It
is
true
that,
once
fixed,
such
damages
may
be
offset
by
the
amounts
withheld,
and
that
the
general
contractor
will
not
benefit
therefrom,
but
the
damages
have
not
yet
been
liquidated
for
1965,
and
compensation
cannot
be
paid
until
they
are.
Until
then,
and
even
after,
until
the
architect
has
issued
his
certificate
and
35
days
have
elapsed,
the
general
contractor
is
under
no
obligation
to
pay
this
amount,
and
it
is
not
claimable
by
the
sub-contractor.
In
fact,
compensation
takes
place
by
the
sole
operation
of
law
only
between
debts
which
are
equally
liquidated
and
exigible,
and
have
each
for
object
a
sum
of
money
or
a
certain
quantity
of
indeterminate
things
of
the
same
kind
and
quality
(cf.
Articles
1187
and
1188
C.C.).
[Emphasis
added.]
In
Newfoundland
Light
&
Power,
Desjardins,
J.A.
concluded
that
payment
of
the
holdback
amounts
in
that
case
was
similarly
contingent
for
the
following
reasons,
stated
at
page
238
(D.T.C.
6172):
I
agree
that
when
the
work
is
completed,
a
liability
exists.
Until
the
certificate
is
issued,
the
taxpayer
however
does
not
know
for
sure
the
full
cost
of
the
work.
On
December
31,
1977,
the
appellant
could
not
ascertain
the
exact
cost
of
the
assets
acquired
by
him
since
the
certificate
as
to
quality
had
not
been
issued.
The
costs
to
the
taxpayer
were
known
for
an
added
amount
of
$201,783.04
only
in
1978;
and
for
another
added
amount
of
$5,276.86
only
in
1979.
More
eloquently,
an
amount
of
$959.10
was
never
disbursed.
The
taxpayer
would
be
acting
under
a
wrong
assumption
had
he
been
able
to
claim
those
amounts,
particularly
the
$959.10,
as
a
cost
to
him
in
1977.
Based
on
the
evidence
in
its
entirety,
I
find
that
the
plaintiff
has
demonstrated
on
balance
of
probability
that
the
holdbacks
in
issue
were
expenses
or
outlays
made
or
incurred
by
the
plaintiff
for
the
purpose
of
earning
income
from
its
business
within
the
meaning
of
paragraph
18(1)(a)
of
the
Income
Tax
Act,
and
that
the
Minister’s
factual
assumption
to
the
contrary
was
erroneous
in
the
circumstances.
Paragraph
18(1)(e)
The
other
ground
on
which
the
Minister
disallowed
the
plaintiff's
deduction
from
income
of
holdback
payables
was
based
on
his
assumption
that
the
total
of
these
holdbacks
represented
an
amount
transferred
or
credited
to
a
reserve
or
contingent
account,
the
deduction
of
which
was
prohibited
by
paragraph
18(1)(e)
of
the
Income
Tax
Act.
Counsel
for
the
defendant
cited
several
authorities,
but
otherwise
did
not
press
the
point
of
the
paragraph
18(1)(e)
argument.
In
my
opinion,
the
evidence
supports
the
submission
of
plaintiff's
counsel
that
the
present
case
falls
more
readily
within
the
provisions
of
paragraph
18(1)(a)
of
the
Act
than
the
"contingent
account"
provisions
of
paragraph
18(1)(e).
See
in
this
regard:
Time
Motors
Ltd.
v.
M.N.R.,
[1969]
C.T.C.
190;
69
D.T.C.
5149
(S.C.C.),
per
Pigeon,
J.
at
pages
192-93
(D.T.C.
5151-520).
Consequently,
I
am
compelled
to
conclude
that
the
Minister
was
incorrect
in
assuming
as
an
alternative
basis
of
assessment
that
the
total
holdbacks
of
$347,276.08
represented
an
amount
transferred
or
credited
to
a
reserve
or
contingent
account,
the
deduction
of
which
was
prohibited
by
paragraph
18(1)(e)
of
the
Act.
Having
found
that
the
plaintiff's
obligation
in
respect
of
moneys
withheld
from
its
sub-subcontractors
was
not
contingent,
the
cases
of
Cummings
v.
The
Queen,
[1981]
C.T.C.
285;
81
D.T.C.
5207
(F.C.A.),
and
Harlequin
Enterprises
Ltd.
v.
The
Queen,
[1977]
C.T.C.
208;
77
D.T.C.
5164
(F.C.A.),
cited
by
counsel
for
the
defendant
are,
in
my
view,
irrelevant.
Disposition
In
the
result,
the
plaintiff's
appeal
is
allowed
with
costs,
and
the
subject
assessment
is
referred
back
to
the
Minister
for
reconsideration
and
reassessment
in
accordance
with
these
reasons
for
judgment.
Appeal
allowed.